Foundation Design

November 27, 2017 | Author: Hafiz Kamal | Category: Screw, Building Materials, Mechanical Engineering, Building Engineering, Industries
Share Embed Donate


Short Description

Foundation Design...

Description

1 (8)

1

FOUNDATION

1.1 Foundation design The factors affecting the foundation design are: • Height of the mast • Quantity of lights / mast (in lattice masts 1-5 pcs) • Wind load (including jet blast loads caused by the aircraft engines in the proximity of the threshold) • Soil quality The following tables describe some typical examples of mast foundations. The calculations have been made for tubular masts carrying single luminaires and lattice masts carrying barrettes of four luminaires. The maximum wind speed used in the calculations is 40 m/s. Dimensioning of the foundations has been done according to DIN V 4017-100. Two types of foundations have been calculated, slab foundation and drum foundation.

Illustration 1:

Slab foundation and drum foundation

2 (8)

Slab foundation Mast Type height Meters H = 16 Lattice H = 20 Lattice H = 25 Lattice Table 1:

Drum foundation Mast Type height Meters H = 16 Lattice H = 20 Lattice H = 25 Lattice Table 2:

SOIL TYPE 1

SOIL TYPE 2

SOIL TYPE 3

L=W

H

Mass

L=W

H

Mass

L

H

Mass

mm 2300 2600 3000

mm 800 900 1000

kg 10400 14900 22000

mm 2200 2500 2900

mm 800 900 1000

kg 9500 13800 20600

mm 2600 3100 3600

mm 900 900 1000

kg 14900 21200 31700

Dimensioning of the concrete slab foundation for mast heights from 16 to 25 m.

SOIL TYPE 1

SOIL TYPE 2

SOIL TYPE 3

D

H

Mass

D

H

Mass

D

H

Mass

mm 1200 1200 1200

mm 2600 3100 3600

kg 7200 8600 10000

mm 1200 1200 1200

mm 2000 2400 2800

kg 5600 6700 7800

mm

mm

kg

Dimensioning of the concrete drum foundation for mast heights from 16 to 25 m.

Soil type 1:

Sand, sandy soil angle of friction weight by volume cohesion

δ = 25° γ = 17 kN/m³ c = 0 kN/m²

Soil type 2:

Compacted coarse sand and moraine angle of friction δ = 40° weight by volume γ = 21 kN/m³ cohesion c = 0 kN/m²

Soil type 3:

Hard clay (drum foundation should not be used!) angle of friction δ = 0° weight by volume γ = 19 kN/m³ cohesion c = 20 kN/m²

Concrete:

> K30

3 (8)

• •

In a groundwater area the foundation shall be deeper. In a soil frost area, the foundation shall reach below the soil frost penetration depth.



All design values mentioned in this instruction are purely indicative. Exel Oyj shall not take responsibility for their applicability to the area in question. It is highly recommended to always consult a local civil engineer about the dimensioning of the foundation. Exel Oyj will provide the necessary load calculations (shear force and bending moment), when requested.

• • • •

Positioning of masts has been dimensioned in the layout-drawing. The heights of the top of foundation have been listed separately for each position in the mast list, if this information has originally been provided to Exel Oyj.

1.2 Preparation of foundation 1.2.1 Hinged post or permanently fitted post Part of foundation bolt remaining visible Allowed deviation of the position of the jig/base frame from the approach light centre line. Allowed deviation of the position of the jig/base frame from the horizontal level. Table 3:

125 ±5mm ± 0,5° =8,7mm/1000mm ± 1° =17mm/1000mm

Essential information necessary for preparation of foundation.



Plywood jigs (option) are available to facilitate concrete casting.



Hot dip galvanised foundation bolts shall in no case be welded to the steel reinforcement of the foundation. Fasten the foundation bolts with wire. Protect the thread of the foundation bolts during the casting for example with tape. See: ”Preparation of foundation for the erection of the mast”. See: ”Installation of wiring”. See Appendix 4: ”Assembly drawings”. See Appendix 5: ”Foundation lay-out drawings”.

• • • • •

4 (8)

1.2.2 Accessories needed for preparation of foundation Measure -

Instrument Foundation bolt, 8–24pcs

Fastening of foundation bolts to the jig -:-:Positioning of foundation bolts

Nut, 16–48 pcs

Size HPM30/L-500 / HPM30/P-1420 M 30

Washers, 16–48 pcs Wrench Casting jig 642218 642208 642209A 642210 Masking tape Wire

Ø32 S=46mm For 8 bolts For 12 bolts For 20 bolts For 24 bolts -

Equipment used in casting of concrete including moulds and steel reinforcements. A stiff ruler

-

Water level

-

Protection of screw thread Fastening of screws to steel reinforcement Casting of foundation Verification of straightness / angle of the jig -:Table 4:

L > 1000 mm

Accessories needed for preparation of foundation.

1.2.3 Work instruction for casting of foundation • • • • • •

• • •

Make a cast mould with its steel reinforcements in accordance with the design of a local civil engineer. Draw the cable duct (IR 65) under the ground from the transformer housing to the foundation and fasten the cable duct to the steel reinforcement so that its’ end comes through the foundation cast at the centre of the foundation. Fasten the foundation bolts to the cast jig according to the illustration above. Protect the threads in the anchor bolts by using for example tape. Place the casting jig with bolts to the correct position. Fasten the bolts to the steel reinforcement with wire if necessary. The foundation bolts shall remain for the length of 125 mm above the concrete surface Make sure that the base frame is in straight angle towards the approach light centre line. The allowed deviation of the position of the jig/base frame from the approach light centre line is ± 0,5°, which corresponds to 8,7 mm/1000 mm. Correct if necessary. Cast concrete in the foundation mould. Make sure that the cast jig is in a horizontal position. Correct the position before the concrete hardens. When the concrete is hard, remove the casting jig.

5 (8)

Locate the foundation bolts with a casting jig to fit the bolts exactly at their correct places in the concrete casting (see the illustrations below). Nut Washer

125±5 [5.0"±0.2"]

Base plate of steel post

Washer Nut Reinforcing mesh Ø8#150 [dia. 5/16"x6"]

min. 10xd

Foundation bolt Concrete foundation

Ød

Reinforcing mesh Ø8#150 [dia. 5/16"x6"]

min.115 min.[4.5"]

240.0 [9.45"]

240.0 [9.45"]

480.0 [18.90"]

480.0 [18.90"]

HPM30/L KZN, L=500 mm (19.7")

6 [26 78.8 .73 "]

240.0 [9.45"]

240.0 [9.45"]

ALTERNATIVE FOUNDATION BOLTS

HPM30/P KZN, L=1420 mm (55.9")

8xM30 bolts

Illustration 1: Principal draft of foundation, casting jig for 8 bolts and foundation bolts of the mast.

6 (8)

Nut Washer

125±5 [5.0"±0.2"]

Base plate of steel post

Washer Nut Reinforcing mesh Ø8#150 [dia. 5/16"x6"] Foundation bolt Concrete foundation

min.10xd

70.0 [2.76"]

Ød min.115 min.[4.5"]

195.0 195.0 [7.68"] [7.68"]

Reinforcing mesh Ø8#150 [dia. 5/16"x6"]

70.0 [2.76"]

530.0 [20.87"]

HPM30/L KZN, L=500 mm (19.7")

6 [25 50.5 .61 "]

195.0 195.0 [7.68"] [7.68"]

ALTERNATIVE FOUNDATION BOLTS

530.0 [20.87"]

12xM30 bolts

HPM30/P KZN, L=1420 mm (55.9")

Illustration 2: Principal draft of foundation, casting jig for 12 bolts and foundation bolts of the mast.

7 (8)

Nut Washer

125±5 [5.0"±0.2"]

Base plate of steel post

Washer Nut Reinforcing mesh Ø8#150 [dia. 5/16"x6"] Foundation bolt Concrete foundation

Ød min.10xd

85.0 [3.35"]

Reinforcing mesh Ø8#150 [dia. 5/16"x6"]

min.115 min.[4.5"]

4x115.0 [4x4.528"]

85.0 [3.35"]

ALTERNATIVE FOUNDATION BOLTS

630.0 [24.80"]

4x115.0 [4x4.528"]

HPM30/L KZN, L=500 mm (19.7")

630.0 [24.80"]

HPM30/P KZN, L=1420 mm (55.9")

20xM30 bolts

Illustration 3: Principal draft of foundation, casting jig for 20 bolts and foundation bolts of the mast.

8 (8)

Nut Washer

125±5 [5.0"±0.2"]

Base plate of steel post Washer Nut Reinforcing mesh Ø8#150 [dia. 5/16"x6"]

min.10xd

Ød min.115 min.[4.5"]

Foundation bolt Concrete foundation Reinforcing mesh Ø8#150 [dia. 5/16"x6"]

Ø900.0 [35.43"]dia.

Ø770.0 [Ø30.31"] ALTERNATIVE FOUNDATION BOLTS HPM30/L KZN, L=500 mm (19.7")

24x15° HPM30/P KZN, L=1420 mm (55.9")

24xM30 bolts Illustration 4: Principal draft of foundation, casting jig for 24 bolts and foundation bolts of the mast.

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF