Final Feasibility NH-235
Short Description
Download Final Feasibility NH-235...
Description
Scott Wilson India Pvt Ltd
Consultancy Services for Preparation of Detailed Project Report for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)]
MEERUT TO BULANDSHAHR SECTION (NH-235)
Final Feasibility Report Volume – I (Main Report)
January 2011
Prepared For:
NATIONAL HIGHWAYS AUTHORITY OF INDIA
Table of Contents
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
Final Feasibility Report Table of Contents
TABLE OF CONTENTS CHAPTER NO.
TITLE
PAGE NO.
0.0
EXECUTIVE SUMMARY
0-1
0.1 0.2
Background Investigations & Evaluations
0-1 0-1
Project Development Descriptions General District and Nodal Towns on the Project Road Carriageway and Roadway Width Right of Way Traffic Volume Proposed Developmental Plan/ Construction Features Proposed Bypass Section Pavement Composition Junction Improvement Proposal of Bridges, Culverts and other Structures Toll Plaza Total Cost of the Project
0-1 0-1 0-2 0-2 0-2 0-3 0-4 0-5 0-6 0-7 0-10 0-14 0-14
1.0
OVERVIEW OF NHAI
1-1
1.1
NHAI Establishment
1-1
NHAI Mandate NHAI Organization National Highway Development Program (NHDP) Government Policy Initiatives
1-1 1-1 1-1 1-3
2.0
PROJECT ROAD DESCRIPTIONS
2-1
2.1
General
2-1
2.2
Project Background
2-1
Study of Project Corridor Terrain and Land use Climatic Conditions Existing Carriageway Width Existing Right of Way Cross Drainage Structures Highway Geometrics Pavement Condition Major Developments along project road Cross Roads and Junctions Drainage Condition Railway Crossings Flyover Utility Lines
2-1 2-3 2-3 2-6 2-6 2-6 2-7 2-7 2-7 2-7 2-7 2-8 2-8 2-8
0.3 0.3.1 0.3.2 0.3.3 0.3.4 0.3.5 0.3.6 0.3.7 0.3.8 0.3.9 0.3.10 0.3.11 0.3.12
1.2 1.2.1 1.2.2 1.2.3
2.3 2.3.1 2.3.2 2.3.3 2.3.4 2.3.5 2.3.6 2.3.7 2.3.8 2.3.9 2.3.10 2.3.11 2.3.12 2.3.12
Scott Wilson
i
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
CHAPTER NO.
TITLE
Final Feasibility Report Table of Contents
PAGE NO.
3.0
METHODOLOGY FOR FEASIBILITY STUDY
3-1
3.1
General
3-1
Traffic Surveys Classified Traffic Volume Count Origin- Destination and Commodity Movements Survey Turning Movements Survey Axle Load Surveys Speed Delay Surveys Pedestrian/Animal Cross traffic /Truck terminal Surveys Survey Programme
3-1 3-1 3-1 3-2 3-2 3-2 3-2 3-2
Traffic Forecast
3-3
3.4 3.4.1 3.4.2 3.4.3 3.4.4
Engineering Surveys and Investigations Reconnaissance and Alignment Topographic Surveys Road and Pavement Investigations Subgrade Characteristics and Strength
3-3 3-3 3-3 3-4 3-5
3.5 3.5.1 3.5.2
Environmental and Social Screening Environmental screening Social Screening
3-5 3-5 3-6
3.6 3.6.1 3.6.2 3.6.3 3.6.4 3.6.5
Scheme Development and Assessment Widening and Strengthening scheme Bypasses Homogeneous Section Pavement Design Bridges and Culverts
3-7 3-7 3-7 3-7 3-7 3-8
3.7 3.8 3.9 3.10
Preliminary Cost Estimates Economic Viability Financial Study Feasibility Report
3-8 3-8 3-8 3-9
4.0
SOCIO-ECONOMIC PROFILE
4-1
4.1 4.1.1 4.1.2 4.1.3 4.1.4 4.1.5
Introduction Background Project Influence Area Methodology Data sources Project Corridor
4-1 4-1 4-1 4-1 4-1 4-2
4.2 4.2.1 4.2.2 4.2.3
Demographic Profile Population Growth Density and Urbanization Likely Population Growth Rate
4-2 4-2 4-2 4-3
3.2 3.2.1 3.2.2 3.2.3 3.2.4 3.2.5 3.2.6 3.2.7 3.3
Scott Wilson
ii
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
CHAPTER NO.
Final Feasibility Report Table of Contents
TITLE
PAGE NO.
4.3 4.3.1 4.3.2 4.3.3 4.3.4 4.3.5 4.3.6 4.3.7 4.3.8
Economic Profile State Income and its dynamics Growth Trend Per capita Income growth Industrial growth Agricultural Sector Performance Mineral Exploration Energy Tourism Potential
4-4 4-4 4-4 4-5 4-6 4-9 4-11 4-12 4-12
4.4 4.4.1 4.4.2 4.4.3 4.4.4
Transport Network Background Road Network Development Road Transport Non Road Transport
4-13 4-13 4-14 4-14 4-15
4.5 4.5.1 4.5.2
Economic Growth Prospects State income growth perspective Population Growth Scenario
4-16 4-16 4-18
5.0
TRAFFIC SURVEYS, ANALYSIS AND FORECAST
5-1
5.1 5.2 5.3
Introduction Identification of Homogeneous Road Sections Primary Surveys – Schedule
5-1 5-1 5-1
5.4 5.4.1 5.4.2 5.4.3 5.4.4 5.4.5
Survey Methodology Classified Traffic Volume Counts Origin-Destination Survey Turning Movement Survey Axle Load Survey Speed and Delay Survey
5-4 5-4 5-4 5-5 5-5 5-5
5.5 5.5.1 5.5.2 5.5.3 5.5.4 5.5.5 5.5.6 5.5.7
Data Analysis Analysis of Traffic Volume Count Average Daily Traffic (ADT) Annual Average Daily Traffic (AADT) Daily Traffic Variation Hourly Variation and Peak Hour Share of Traffic Directional Distribution Traffic Composition
5-5 5-5 5-6 5-7 5-11 5-11 5-13 5-13
5.6 5.6.1 5.6.2 5.6.3 5.6.4 5.6.5 5.6.6 5.6.7 5.6.8
Analysis of O-D Survey Data Data Checking Zoning System Commodity Groups Expansion Factors and Development of Origin-Destination Matrices Commodity Analysis Travel Pattern Lead Load Analysis Trip Frequency Distribution
5-14 5-14 5-15 5-16 5-17 5-17 5-18 5-26 5-28
Scott Wilson
iii
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
CHAPTER NO.
TITLE
Final Feasibility Report Table of Contents
PAGE NO.
5.7 5.7.1 5.7.2
Analysis of Turning Movement Survey Data Peak Hour Traffic Analysis and Improvement Proposal
5-28 5-28 5-29
5.8 5.8.1 5.8.2 5.8.3 5.8.4 5.8.5
Analysis of Axle Load Survey Data General Location Vehicle Damaging Factor Load Equivalence Factors Axle Load Spectrum Analysis
5-30 5-30 5-30 5-30 5-31 5-32
Analysis of Speed and Delay Survey Data
5-36
Traffic Forecast Transport Demand Elasticity Economic Perspective Projected Traffic Growth Rates
5-36 5-36 5-39 5-41
Total Forecasted Traffic
5-41
5.12 5.12.1 5.12.2
Capacity Analysis Capacity and Design Service Volume Guidelines Capacity Analysis
5-42 5-42 5-42
5.13 5.13.1 5.13.2 5.13.3
Toll Plaza Existing Toll locations Proposed Toll Plaza Locations Number of Lanes at Toll Plaza
5-45 5-45 5-45 5-45
ENGINEERING SURVEYS AND INVESTIGATIONS
6-1
6.1 6.1.1 6.1.2 6.1.3 6.1.4 6.1.5 6.1.6 6.1.7 6.1.8 6.1.9 6.1.10 6.1.11 6.1.12
Road Inventory and Road Condition Terrain Land use Carriageway and Roadway width Surfacing Type Shoulder Embankment Height Right of Way Villages and Towns Side Drain Horizontal Curves Road Junctions Road Signs
6-1 6-1 6-1 6-1 6-2 6-2 6-2 6-2 6-3 6-3 6-3 6-3 6-4
6.2 6.2.1 6.2.2 6.2.3
Pavement Condition Survey Pavement Condition Shoulder Condition Drainage Condition
6-4 6-4 6-5 6-5
5.9 5.10 5.10.1 5.10.2 5.10.3 5.11
6.0
Scott Wilson
iv
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
CHAPTER NO. 6.3
TITLE
Final Feasibility Report Table of Contents
PAGE NO.
Benkelman Beam Deflection Technique
6-5
6.4 6.4.1 6.4.2 6.4.3 6.4.4
Trial Pits Pavement Composition Insitu-density and moisture content Field CBR using DCP Characterisation of Subgrade
6-8 6-8 6-9 6-10 6-11
6.5 6.5.1 6.5.2
Material Investigations Borrow Area Soil Sand Quarry
6-13 6-13 6-13
Inventory and Condition Surveys of Culverts
6-13
Bridges Investigations Bridge Inventory Condition Survey of Bridges
6-13 6-14 6-14
6.8
Railway Level Crossing/ROB/RUB/VUP & Other Structures
6-14
7.0
DESIGN STANDARDS
7-1
7.1 7.2 7.3 7.4
Introduction Guiding Principles Terrain Classification Design Speed
7-1 7-1 7-1 7-2
Cross Sectional Elements Road Land Width/ Right-of-Way (ROW) Cross-Sectional Requirement in Rural Sections Cross-Sectional Requirement in Urban/Built up Sections
7-2 7-2 7-2 7-3
Camber or Crossfall
7-3
Horizontal Alignment Radii of Horizontal Curves Super elevation Transition Curves
7-4 7-4 7-4 7-5
Site Distance
7-5
7.9 7.9.1
Vertical Alignment Vertical Curves
7-5 7-6
7.10
Embankment
7-6
Pavement Design Subgrade Type of Pavement Design Traffic Design Procedures
7-6 7-6 7-7 7-7 7-7
6.6 6.7 6.7.1 6.7.2
7.5 7.5.1 7.5.2 7.5.3 7.6 7.7 7.7.1 7.7.2 7.7.3 7.8
7.11 7.11.1 7.11.2 7.11.3 7.11.4
Scott Wilson
v
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
CHAPTER NO.
7.12 7.13 7.14
Final Feasibility Report Table of Contents
TITLE
PAGE NO.
Service Roads Geometric Design Requirements of additional features Geometric Design Control
7-7 7-7 7-8
7.15 7.15.1
Roadway Width at Cross-Drainage Structures Culverts
7-8 7-8
7.16 7.16.1 7.16.2 7.16.3 7.16.4 7.16.5 7.16.6 7.16.7 7.16.8
Design Standards for Structures General Hydraulic and Hydrological Investigations Cross-sectional Elements Type of Super Structure Specification for Material Loads and Forces to be considered in Design Design Methodology Quality Assurance
7-8 7-8 7-9 7-9 7-10 7-10 7-11 7-14 7-17
7.17 7.18 7.19
Standards for Interchanges Standards for At-Grade Intersections Traffic signs and Road Markings
7-17 7-18 7-19
8.0
DEVELOPMENT PROPOSALS
8-1
8.1 8.2
General Alignment and Geometry
8-1 8-1
Cross Sectional Details Lane Width Paved Shoulders Earthen Shoulders Median Service Road Footpath Utility Corridor Side Slopes Crossfall Proposed ROW Cross Section
8-1 8-1 8-1 8-1 8-2 8-2 8-2 8-2 8-2 8-2 8-2 8-2
Widening Scheme
8-14
8.5 8.5.1 8.5.2 8.5.3 8.5.4
Proposals for Bypasses Phaphunda Bypass Kharkhauda Bypass Hapur Bypass Gulaothi Bypass
8-20 8-20 8-21 8-21 8-22
8.6 8.6.1 8.6.2
Homogeneous Sections Analysis of Unit Delineation by Cumulative Differences Homogeneous section for pavement design of widening of existing
8-27 8-27 8-27
8.3 8.3.1 8.3.2 8.3.3 8.3.4 8.3.5 8.3.6 8.3.7 8.3.8 8.3.9 8.3.10 8.3.11 8.4
Scott Wilson
vi
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
CHAPTER NO.
8.6.3 8.6.4 8.7 8.7.1
Final Feasibility Report Table of Contents
TITLE
PAGE NO.
lane Homogeneous section for overlay and reconstruction of existing lane Homogeneous section for pavement design of new construction
8-29 8-31
Pavement Options IRC: 37-2001 Method of Flexible Pavement Design – Widening and for New Construction IRC: 81-1997 Method of Flexible Overlay – For Strengthening of Existing Pavement IRC: 58-2002 Method of Rigid Pavement Design – For Toll Plaza locations
8-33 8-33
8.8 8.8.1 8.8.2
Junctions Design General Criterion for improvement proposal at junctions Details of Junctions improvement proposal
8-40 8-40 8-41
8.9 8.9.1 8.9.2 8.9.3 8.9.4
Design of Bridges Existing Bridges Proposal of New Bridges Improvement Proposal of Railway Level crossings Proposal for VUP and PUP
8-44 8-44 8-44 8-48 8-50
8.10
Design of Culverts
8-51
8.11 8.11.1 8.11.2 8.11.3 8.11.4 8.11.5 8.11.6 8.11.7 8.11.8 8.11.9 8.11.10 8.11.11
Road Furnitures and Other features Introduction Bus Bays and Bus Shelters Truck Lay byes Road Markings Cautionary, Mandatory and Informatory Signs Kilometre Stone Details 200m Stones and Boundary Stones Delineators and Object Markers Guard Post Crash Barrier Road Humps and Rumble Strips
8-58 8-58 8-58 8-59 8-59 8-59 8-59 8-59 8-60 8-60 8-60 8-60
8.12 8.12.1 8.12.2
Design of Toll Plaza Number of Lanes at Toll Plaza Toll Plaza Design
8-61 8-61 8-61
8.13
Road Safety Audit
8-62
9.0
ENVIRONMENTAL SCREENING ENVIRONMENTAL EVALUATION
9.1 9.2 9.3 9.4 9.5
Background Project Description Description of the Environment Potential Environmental Impacts and Mitigation Measures Environmental Monitoring Plan
8.7.2 8.7.3
Scott Wilson
vii
AND
INITIAL
8-37 8-37
9-1
9-1 9-1 9-1 9-5 9-10
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
CHAPTER NO.
Final Feasibility Report Table of Contents
TITLE
PAGE NO.
9.6 9.7
Environmental Management Plan Environmental Budget for Mitigation Measures & Environmental Management Plan
9-10 9-10
10.0
INITIAL SOCIAL ASSESSMENT AND PRELIMINARY LAND ACQUISITION/ RESETTLEMENT PLAN
10-1
10.1 10.2
Description of the Project Road Objectives of the Resettlement Action Plan
10-1 10-1
Land Acquisition and Project Impact Location and Area Right of Way/Land Requirement Measures to Minimize Impacts Acquisition of Land and Structures Project Affected Persons (PAPs)
10-1 10-1 10-2 10-2 10-2 10-3
10.4 10.5 10.6 10.7 10.8
Resettlement Principles Consultation and Disclosures Institutional Mechanism & Grievance Redressal RAP Implementation Budget Monitoring & Evaluation
10-3 10-3 10-4 10-5 10-5
11.0
COST ESTIMATE
11-1
11.1
General
11-1
Rate Analysis Material Labour Machineries
11-1 11-1 11-2 11-2
11.3 11.4
Estimation of Quantities and Cost Preliminary Project Cost
11-2 11-3
Scott Wilson
viii
10.3 10.3.1 10.3.2 10.3.3 10.3.4 10.3.5
11.2 11.2.1 11.2.2 11.2.3
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
Final Feasibility Report Table of Contents
LIST OF TABLES PAGE NO.
TABLE NO.
TITLE
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 0.10 0.11 0.12 0.13 0.14 0.15 0.16 0.17 0.18
Project Length Lane Configuration along the Project Stretch Proposed Right of Way along the project stretch Annual Average Daily Traffic (AADT) Widening Scheme Length Proposed Bypass Locations Flexible Pavement Thickness for Pavement widening portion Flexible Pavement Thickness for New Pavement and Reconstruction stretch Proposed Overlay Thicknesses for existing lane Rigid Pavement Composition at Toll Plaza Junction Improvement proposal Summary of Development of Bridges Summary of Development of Culverts List of Railway Crossing on the Project Road Section Existing and Proposed VUP Existing and Proposed PUP /CUP Details Toll Plaza Abstract Project Cost (Design length = 62.521 km)
0-7 0-7 0-7 0-11 0-12 0-12 0-13 0-13 0-14 0-14
2.1
Summarised Details of Cross Drainage Structures
2-6
4.1 4.2 4.3 4.4
4-2 4-2 4-3 4-4
4.19
Population growth of PIA and India Demographic profiles of study district and state, 2001 Census Population projection by RGI (1996-2016) Adopted population growth rate of the study region (Average Annual Compound Growth Rate) Periodical growth rate of State Income, in real terms at current price (Average Annual Compound Growth Rate in %) Summary growth rates of Per Capita Income of U.P. (2000-2001 to 2006-07 at 1999-00 constant prices) Summary of Growth Rates of Manufacturing Sector of UP Economy Major exports from UP in 1997-98 Details of land use in UP Productivity of major crops in UP in 2004-2005 Major mineral production by U.P Number of Tourist coming to Uttar Pradesh PWD Road Length in Uttar Pradesh (Km) Vehicles Plying on road in U P Vehicles Registered in a year in U.P. Economic growth scenarios in Uttar Pradesh in 2001-2010 Annual NSDP economic growth estimated by major sector 2001-2010 Annual growth estimated by economic sector and Region 2001-2010 (Medium Growth Scenario) Future population growth of UP (AACGR in %)
5.1 5.2 5.3
Homogeneous Traffic Sections Schedule of Traffic Surveys on the Project road (Meerut - Bulandshahr) Vehicle Classification System
4.5 4.6 4.7 4.8 4.9 4.10 4.11 4.12 4.13 4.14 4.15 4.16 4.17 4.18
Scott Wilson
ix
0-2 0-2 0-3 0-4 0-4 0-5 0-6 0-6
4-5 4-5 4-6 4-8 4-10 4-11 4-11 4-13 4-14 4-15 4-15 4-17 4-17 4-17 4-18 5-1 5-2 5-4
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
Final Feasibility Report Table of Contents
PAGE NO.
TABLE NO.
TITLE
5.4 5.5 5.6 5.7 5.8 5.9 5.10 5.11 5.12 5.13 5.14 5.15 5.16 5.17 5.18 5.19 5.20 5.21 5.22 5.23 5.24 5.25 5.26 5.27 5.28 5.29 5.30 5.31 5.32 5.33 5.34 5.35 5.36 5.37 5.38 5.39 5.40 5.41 5.42
5-5 5-6 5-7 5-7 5-9 5-10 5-13 5-13 5-15 5-15 5-16 5-17 5-19 5-26 5-26 5-27 5-27 5-28 5-28 5-28 5-29 5-29 5-30 5-31 5-32 5-33 5-33 5-34 5-34 5-35 5-35 5-36 5-37 5-38 5-38 5-39 5-39 5-40 5-41
5.43 5.44 5.45 5.46 5.47 5.48 5.49 5.50
PCU Factors Adopted for the study Average Daily Traffic Adopted Seasonal Correction Factor Annual Average Daily Traffic Summary of Classified Traffic Volume Count at Km 18+000 Summary of Classified Traffic Volume Count at Km 39+000 Peak Hour Traffic Directional Distribution Share Sample Size of O-D Survey Adopted Zoning System for the Study Classification of Commodities Commodity Wise Goods Movement Pattern (%) Share of Travel Pattern (%) Lead Distribution of Passengers Vehicles (%) Lead Distribution of Freight Vehicles (%) Average Trip Length Load Distribution of Freight Vehicles (%) Average Load Average Trip Frequency Distribution (%) Peak Hour Traffic at Intersections Projected Average Daily Traffic of Cross Roads at Junctions Projected Peak Hour Traffic at Junctions Junction wise Improvement Load Equivalency Factors Vehicle Damage Factors Meerut-Bulandshahr Section on NH-235 Sample Size of Axle Load Survey at location Km 18+000 (Kharkhauda) Sample size of axle load survey at location Km 39+000 (Padau) Meerut to Bulandshahr – Km 18+000 (Kharkhauda) Bulandshahr to Meerut – Km 18+000 (Kharkhauda) Meerut to Bulandshahr – Km 39+000 (Padau) Bulandshahr to Meerut – Km 39+000 (Padau) Observed Speed along Project Road Mode wise PIA Percentage Share Transport Demand Elasticity using Vehicle Registration Data of PIA Weighted Transport Demand Elasticity Projected Transport Demand Elasticities Average Annual Growth Rates from Time Trend Growth Rate in Economy Projected Traffic Growth Rates using Econometric Model (Figures in Percentage) Adopted Projected Traffic Growth Rates (Figures in Percentage) Mode-wise Forecasted Traffic Design Service Volume of Four-lane Highway in PCUs per day Design Service Volumes at Different Level of Services Projected Sectional Tollable Traffic in Vehicles Projected Sectional Total Traffic in PCUs with LOS Projected Sectional Tollable Traffic in PCUs with LOS Required Toll Lanes
6.1 6.2
Lane configuration along the project stretch Shoulder details along the project stretch
6-2 6-2
Scott Wilson
x
5-41 5-42 5-42 5-42 5-43 5-43 5-44 5-46
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
TABLE NO.
Final Feasibility Report Table of Contents
TITLE
PAGE NO.
6.3 6.4 6.5 6.6 6.7 6.8 6.9 6.10 6.11 6.12 6.13 6.14 6.15 6.16 6.17
Location of villages and towns Locations for needing geometric improvement Location of major road junctions Criteria for classification of pavement sections Characteristic Deflection along the Project Road Pavement Composition of the Existing Road Field dry density Field CBR value obtained from DCP Test Different Tests carried out on Subgrade Soil Test Results of Existing Subgrade Soil Lists of Source of Materials Details of Culverts and Condition Major and Minor Bridges along the Project Road List of Railway Crossing on the Project Road Section. List of VUP on the Project Road Section
6-3 6-3 6-4 6-4 6-6 6-9 6-9 6-11 6-11 6-12 6-13 6-13 6-14 6-14 6-14
8.1 8.2 8.3 8.4
8-15 8-20 8-21 8-27
8-37 8-38 8-38
8.17 8.18 8.19 8.20 8.21 8.22 8.23 8.24 8.25 8.26 8.27 8.28 8.29 8-30
Tentative Widening Scheme Summary of Widening Scheme Salient Features of proposed Hapur Bypass Homogeneous Sections for Pavement Design of Widening of Existing Lane Homogeneous Sections for Overlay & reconstruction of existing lane Homogeneous Sections for New Pavement Pavement Design Methods Annual Average Daily Traffic in Base year (2010) Vehicle Damage Factors adopted for the design Design Traffic in Million Standard Axles Materials Specification and Characterisation Flexible Pavement Thickness for Widening of Existing Lane Flexible Pavement Thickness for New pavement and Reconstruction Stretches Proposed Overlay Thicknesses on existing lane Recommended Temperature Differentials for Concrete Approximate k-value corresponding to CBR Values for Homogeneous Soil Subgrade k-Values over Granular and Cement Treated Sub-bases k-Values over Dry Lean Concrete Sub-base Proposed Rigid Pavement thickness at Toll Plaza Location, km 35+215 Junction Improvement proposal Development scheme of Existing and New Bridges Development Proposal for Railway Level Crossings Existing and Proposed VUP Summary of development of culverts Development Proposals for Existing Culverts Locations of Bus bays with Bus Shelter Locations of Bus Shelters Locations of truck lay byes Location and Section of Toll Plaza Required Toll Lanes
11.1
Abstract Project Cost
11-4
8.5 8.6 8.7 8.8 8.9 8.10 8.11 8.12 8.13 8.14 8.15 8.16
Scott Wilson
xi
8-29 8-31 8-33 8-34 8-34 8-35 8-35 8-36 8-37
8-38 8-39 8-40 8-41 8-47 8-49 8-50 8-51 8-52 8-58 8-58 8-59 8-61 8-62
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
Final Feasibility Report Table of Contents
LIST OF FIGURES FIGURE NO.
TITLE
PAGE NO.
1.1 1.2
Organisation Chart of NHAI National Highways Development Project Phase-I, II & III
1-4 1-5
2.1 2.2 2.3
Project Location Map Mean Temperature of the state of Uttar Pradesh Annual Rainfall of the state of Uttar Pradesh
2-2 2-4 2-5
4.1 4.2 4.3 4.4 4.5
Growth of State Income of UP Sectoral contribution to NSDP, 2004-09 Annual growth in industrial performance of UP Average Yield of Major Crops in U.P. Growth in Tourism Sector
4-4 4-6 4-8 4-11 4-13
5.1 5.2 5.3 5.4 5.5 5.6
Traffic Survey Location Map Daily Traffic Variation Hourly Variation of Traffic Composition of Traffic Desire Line Diagram for OD Goods Vehicles for both locations Desire Line Diagram for OD Passenger Vehicles for both locations Desire Line Diagram for OD Goods Vehicles at Km 18+000 (Kharkhauda) Desire Line Diagram for OD Goods Vehicles at Km 39+000 (Padau) Desire Line Diagram for OD Passenger Vehicles at Km 18+000 (Kharkhauda) Desire Line Diagram for OD Passenger Vehicles at Km 39+000 (Padau)
5-3 5-11 5-12 5-14 5-20 5-21
5.7 5.8 5.9 5.10 6.1 6.2 6.3 8.1 8.1A 8.2 8.3 8.4 8.5 8.6 8.7 8.8 8.9 8.10A 8.10B 8.10C 8.10D 8.11 8.12 8.13
Scott Wilson
Characteristic Deflection (mm) along the Project road from Meerut – Bulandshahr (NH-235) Field dry density in (gm/cc) Field Moisture content (%) Typical Cross Sections – I Typical Cross Sections – IA Typical Cross Sections – II Typical Cross Sections – III Typical Cross Sections – IV Typical Cross Sections – V Typical Cross Sections – VI Typical Cross Sections – VII Typical Cross Sections – VIII Typical Cross Sections – IX Proposed Alignment for Phaphunda Bypass Proposed Alignment for Kharkhauda Bypass Proposed Alignment for Hapur Bypass Proposed Alignment for Gulaothi Bypass Homogeneous Sections for Pavement Design for Widening of Existing lane Homogeneous Sections for Pavement design for Overlay of Existing Lane Homogeneous Sections for New Pavement design
xii
5-22 5-23 5-24 5-25 6-7 6-10 6-10 8-4 8-5 8-6 8-7 8-8 8-9 8-10 8-11 8-12 8-13 8-23 8-24 8-25 8-26 8-28 8-30 8-32
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
Final Feasibility Report Table of Contents
FIGURE NO.
TITLE
PAGE NO.
8.14
Cross Section of Bridge at Deck Level- with Footpath for 4-Lane Divided Highway (Both sides new Bridges for 4-Lane Standards)
8-45
8.15
Cross Section of Bridge at Deck Level- with Footpath for 4-Lane Divided Highway (Both sides new Bridges for 6-Lane Standards)
8-45
8.16
8.17
Cross Section of Bridge at Deck Level- with Footpath for 4-Lane Divided Highway (One side New 2-Lane Bridge and other sides Existing 2-Lane Bridge) Cross Section of Bridge at Deck Level- without Footpath for 4-Lane Divided Highway (One side New 2-Lane Bridge and other sides Existing 2-
8-46
8-46
Lane Bridge)
8.18
Scott Wilson
Cross Section of Culvert for 4-Lane Divided Highway at Road Level
xiii
8-51
January 2011
Chapter – 0 Executive Summary
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
Final Feasibility Report Executive Summary
0.0
EXECUTIVE SUMMARY
0.1
Background
0.1.1
The work for consultancy services for Preparation of Detailed Project report for rehabilitation and upgradation of National Highway stretches under NHDP – IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh has been awarded to M/s. Scott Wilson India Private Limited, vide National Highways Authority of India (NHAI) letter no. NHAI/Coord./4/2009/10467 dated on 12th March 2010.
0.1.2
Scott Wilson India Private Limited has been commissioned by NHAI to provide consulting services in the preparation of Detailed Project Report (DPR) for rehabilitation and upgrading of the stretch to 2-lane with paved shoulder configuration with provision of capacity augmentation.
0.2
Investigations & Evaluations
0.2.1
Feasibility Study was carried out by Scott Wilson India Private Limited and the report evaluates Financial Viability in terms of Financial Internal Rate of Return (FIRR) and economic viability in terms of Economic Internal Rate of Return (EIRR) of the homogeneous road sections for optimum upgrading. The above evaluation has been based on various surveys and investigations carried out during the course of the study and these include traffic, topography, pavement condition, inventory and condition of road/structures and material investigations. Special attention has been given to maximize the use of existing pavement and available land and use of local resources. Beside, due care is also taken to ensure use of modern construction technology to achieve the desired quality and performance requirements and attain the intended level of service for the next 15 years.
0.3
Project Development Descriptions
0.3.1
General The project road NH-235, starts from Meerut Town (Km. 0+000) and ends at Bulandshahr town (Km. 66+482). Project road section traverses through three districts of the Uttar Pradesh, viz. Meerut, Ghaziabad and Bulandshahr. The nodal towns on the stretches are Meerut, Hapur, Gulathi and Bulandshahr. The project was initially conceived and awarded to prepare detailed project report for upgradation and rehabilitation of Meerut – Bulandshahr section of NH-235 to 2-lane with paved shoulder configuration. However, traffic survey and analysis reveals that currently between Meerut to Hapur the total traffic volume is 23713 PCU while between Hapur to Bulandshahr total traffic volume is 24171 PCU, which as per Clause 2.16 of IRC: SP: 73-2007 exceeds the capacity of 2lane+Paved Shoulder configuration and is due for 4laning with level of service “B” as per Clause 2.17 of IRC: SP: 84-2009. Both MORT&H and NHAI officials were made aware of this scenario in the meeting held at MORT&H on 10th September 2010 and the officials agreed in principle to prepare the Draft and Final Feasibility Report based on proposed development of the highway on 4-lane configuration. The same was further corroborated by NHAI in the meeting held at NHAI on 14th September 2010. On receipt of the comment on the Draft Feasibility Report dated 9th October and subsequent meeting held with the Project Director, Meerut, all the suggestion was addressed and accordingly Final Feasibility Report was submitted on 25th October 2010. From km 0+000 to km 7+469 the existing project road has four-lane with divided carriageway configuration inside the Meerut town and hence, the development proposal for the Meerut-
Scott Wilson
0-1
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
Final Feasibility Report Executive Summary
Bulandshahr section of NH-235 is framed with the concept of 4-lane configuration highway from km 7+469 onwards. A summary of the project corridor is given in Table 0.1 Table 0.1: Project Length Sl. No.
Existing Chainage (km) From To
Existing Design Chainage (km) Design Length Length (km) (km) From To
Remark
Out of project scope, inside Meerut town Length for improvement 62.521 km & 3.522 km of 2 7+469 66+482 59.013 7+469 73+512 66.043 existing Hapur Bypass (NH-24) followed Maintenance of existing 2-lane road proposed proposed approximate length is junction of new junction of new 2.000 73+512 Bulandshahr 2.000 2.0 km includes 140m 2 66+482 Bulandshahr long existing twin Bypass (NHBypass (NHbridge on Upper 91) 91) Ganga Canal) 1
0.3.2
0+000
7+469
7.469
-
-
-
District and Nodal Towns on the Project Road Project road section traverses through three districts of the Uttar Pradesh, namely Meerut, Ghaziabad and Bulandsahar. The nodal towns / villages on the stretches are Meerut, Phaphunda, Kharkauda, Kaili, Hapur, Gulaothi and Bulandshahr.
0.3.3
Existing Carriageway and Roadway Width The project road section is having carriageway width configuration of 7m to 14m, while the formation width varies from 10m to 15m. At few locations formation width is around 25 to 30 metre. The summary of the lane configuration for the entire stretch is given in Table 0.2. Table 0.2: Lane configuration along the project stretch Chainage (Km) From To 0+000 7+469 7+469 25+500 25+500
Length (Km)
CW Width (m)
Lane Configuration
7+469 18.031
14.0 10.0
2x2 Lane with 1m median 2 Lane with PS
40.892
7.0
2 Lane
66+482
Length of 4- lane section Length of 2- lane with PS section Length of 2- lane section 0.3.4
: : :
7.469km 18.031km 40.982km
Right of way (ROW) There is no road boundary pillar along the road. As per the record from the department, average existing Road Way width is around 35 meter. The proposed ROW for the project is as per
Scott Wilson
0-2
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
Final Feasibility Report Executive Summary
Table 0.3 below. Table 0.3: Proposed Right of Way along the project stretch Sl. No. 1 2 3
Design Chainage From To 7+469 9+500 9+500 12+100
Proposed Length (m)
Proposed ROW (m)
2031.0 2600.0
60 45
Alipur Phaphunda Bypass
12+100
14+800
2700.0
60
4 5
14+800
17+700
2900.0
60
17+700
20+900
3200.0
60
6 7 8 9
20+900 23+400 27+100
23+400 27+100 35+400
2500.0 3700.0 8300.0
60 60 60
35+400
38+930
3530.0
-
38+930
39+299
369.0
60
11 12 13 14 15
39+299 39+966 43+200 44+150
39+966 43+200 44+150 47+600
667.0 3234.0 950.0 3450.0
45 60 45 60
47+600
48+200
600.0
180
Toll Plaza location
16 17 18 19 20 21 22
48+200 49+800 53+100 57+250 58+130 68+000 68+400
49+800 53+100 57+250 58+130 68+000 68+400 73+512
1600.0 3300.0 4150.0 880.0 9870.0 400.0 5112.0
60 60 60 45 60 45 60
Jindal Factory
10
0.3.5
Remarks
Kharkhauda Bypass Hapur Bypass Hapur Bypass Existing Hapur Bypass on NH-24 Slip Road on Ex. Hapur Bypass on NH-24 Sadikpur Padao
Jainpur
Traffic Volume The summary of the average annual daily traffic for the project stretch is given in Table 0.4.
Scott Wilson
0-3
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
Final Feasibility Report Executive Summary
Table 0.4: Annual Average Daily Traffic (AADT) Vehicle Type
Location Kharkhauda Padau (km 18+000) (km 39/000) Passenger Cars 4857 4494 Utility Vehicle (Jeep, Van) 236 87 Two Wheeler 6042 4398 Three Wheelers 400 152 Other Passenger Vehicles 0 0 Minibus 61 47 Standard Buses 691 658 Tempo/ LCV 1058 1344 2-Axle Truck 1119 1706 3-Axle Truck 1522 1659 Multi Axle Vehicles 164 180 Tractors 231 217 HEM / EMV 18 13 Bycycles 820 417 Cycle Rickshaw 174 88 Hand/ Animal Cart 149 140 Ambulance/ Police/ Military/ VIP 4 5 Total Exempted Police/ Military Buses 0 0 Police/ Military Trucks 2 2 Motorised Traffic 16405 14963 Total Vehicles Non Motorised Traffic 1143 646 17549 15609 Total Motorised Traffic 22060 22945 Total PCUs Non Motorised Traffic 1654 1227 23713 24172 Total 9726 10189 Tollable Traffic Vehicles 17589 19607 PCUs 7822 5420 Non Tollable Traffic Vehicles 6124 4565 PCUs
0.3.6
Proposed Developmental Plan/Construction features are summarised below:a) 4 lane divided carriageway with 3.5m wide lane width, 1.5m wide paved shoulder and 2.0m earthen shoulder. In each direction 2-lane carriageway is divided by 4.5 m wide median, thereby totalling the roadway width to 26.0m. At selected urban stretches the median width is reduced to 1.5m to maximize the utilisation of available land. To facilitate local traffic and pedestrian movements the paved shoulder is increased to 2.0m and 1.5m wide footpath provided on both sides at theses stretches b) Widening scheme can be summarised as given in Table 0.5. Table 0.5: Widening Scheme Length Description 4-lane Eccentric Widening in rural stretches 4-lane Eccentric Widening in rural stretches with 8m wide
Scott Wilson
0-4
Design Length ( in m) 23283 7250
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
Final Feasibility Report Executive Summary
Design Length ( in m)
Description median 4-lane Eccentric Widening in Built-up stretches 4-lane Concentric Widening in restricted ROW stretches 4-lane Concentric Widening in built-up stretches having restricted ROW 4-lane Concentric Widening with functional overlay over existing pavement 4-lane Bypass / Realignment
395 840 450 4400 25903 62521
Total Length of existing Hapur Bypass to be used as a part of this project, which has been kept out of the scope of development proposal of this project Total Project Length 0.3.7
3522 66043
Proposed Bypass Sections The existing section of NH-235 from Meerut to Bulandshahr passes through number of town and villages. In general, bypasses are proposed where section of the road passes through heavily built-up area on both side, with insufficient land width, where improvement of the existing road catering to desired standards will involve considerable resettlement and rehabilitation measures. Based on the reconnaissance carried out by consultant and subsequent site visit with NHAI officials bypass is recommended for the Hapur town. Gulaothi town also the available width between the building lines is not sufficient to accommodate a four lane highway with service road. Therefore, a bypass for Gulaothi town is also proposed. Summary of bypass locations and length of each bypass is given in Table 0.6. Table 0.6: Proposed of Bypass Locations Existing Chainage (km) Sl. No.
Bypass Location
From
To
Length (Km)
Design Chainage (km) From
To
Length (Km)
1
Phapunda 12+100 14+350 Bypass
2.25
12+100 14+800
2.70
2
Kharkhuda 17+250 20+250 Bypass
3.00
17+700 20+900
3.20
23+400 34+600 3
Hapur Bypass
22+750 34+171
11.42
15.95 34+600 35+456 38+978 39+350
4
Scott Wilson
Gulaothi Bypass
44+650 50+500
5.9
49+800 57+375
0-5
Remarks Survey Length may vary after the topographic Survey
12.428 km Proposed Bypass 3.522 km Existing Hapur Bypass of NH-24 to be used as a part of this project Widening of 1.228km of existing slip road of flyover & VUP on Hapur Bypass of NH-24
7.575
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
0.3.8
Final Feasibility Report Executive Summary
Pavement Composition Pavement composition thicknesses were designed for widening, reconstruction and new construction section as per IRC: 37-2001. For strengthening of existing flexible road pavement, overlay thickness were established as per IRC: 81-1997. At Toll plaza locations provision of rigid pavement is given and pavement composition were established as per IRC: 58-2000. a) Widening and strengthening of NH-235 between existing km 7+469 to km 25+500 has been taken up by PWD, NH Division, Bulandshahr and completed by month of April 2011. Therefore, no improvement to the existing pavement in this stretch is proposed in the eccentric widening sections. However a functional overlay of 50mm thick BC layer is proposed on the existing pavement before opening to traffic. b) Pavement composition for flexible road pavement for Widening and New construction sections is given in Table 0.7 and Table 0.8.
CBR of Subgrade (%)
Table 0.7: Flexible Pavement Thickness for Pavement widening portion Pavement Thickness (mm) Design Design Traffic Designed for Designed Chainage (km) for 15 years 10 years Total Remarks 10 Sub- (mm) 15 Wearing Binder Base base Course Course From To Year Year (mm) (mm) (mm) (mm) (MSA) (MSA) Existing 135 250 260 685 39+150 62+040 63 108 6 40 (BC) ground to be (DBM) checked for suitability and loosened, 130 250 230 620 recomputed 62+040 73+512 63 108 7 40 (BC) (DBM) to desire MDD Table 0.8: Flexible Pavement Thickness for New Pavement and Reconstruction stretch Design Chainage (km) Design Traffic CBR of Pavement Thickness (mm) Subgrade Designed for 10 Designed for years 15 years Total From To 10 15 (%) Wearing Binder Base Sub(mm) Year Year Course Course (mm) base (MSA) (MSA) (mm) (mm) (mm) 7+469 35+456 52 89 7 40 125 250 230 645 35+456 38+978 No Improvement is proposed for existing Hapur Bypass of NH-24 38+978 73+512 63 108 7 40 130 250 230 650 c) Pavement composition thickness for strengthening of flexible road pavement for overlay sections is given in Table 0.9.
Scott Wilson
0-6
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
Final Feasibility Report Executive Summary
Table 0.9: Proposed Overlay Thicknesses for existing lane Design Length Average Design Thickness Thickness in Chainage (km) (m) Characteristic Traffic for in BM term of Deflection (mm) 10years (mm) BC/DBM (MSA) (mm) From To 39+350 49+800 10450 0.818 63 68 48 49+800 58+215 8415 0.902 63 88 62 58+215 73+512 15297 0.853 63 76 54
Overlay Portion (mm) BC DBM 40 50 40 50 40 50
d) Pavement composition thickness for rigid pavements at Toll plaza locations is given in Table 0.10.
Table 0.10: Rigid Pavement Composition at Toll Plaza Material Type Thickness (mm) Pavement Quality Concrete (M-40) 300 Dry Lean Concrete (M-10) 150 Granular Sub-base 150 Subgrade 500 0.3.9
Junction Improvement There are existing 6 major, 68 minor junctions and 10 new major junctions will be evolved due to the proposal of bypasses. Cross roads with paved carriageway are only considered for development of the junction. The major junctions forming with National Highways, State highways and District roads are listed in Table 0.11.
Scott Wilson
Table 0.11: Junction Improvement proposal Design Cross Road Type Chainage Side Leading to (km)
Sl. No
Existing Chainage (km)
1
7+469
7+469
2*
12+200
3*
Remark
LHS
City Road
RHS
Existing Meerut bypass road
12+200
LHS
Phaphunda
At start of proposed Phaphunda Bypass
14+250
14+700
LHS
Phaphunda
At end of Proposed Phaphunda Bypass
4*
17+350
17+800
LHS
Kharkhauda
At start of proposed Kharkhauda bypass
5*
20+145
20+800
LHS
Kharkhauda
At end of Proposed Kharkhauda Bypass
Straight
To Hapur
6*
22+900
23+500 Left
Hapur bypass
0-7
Start Point of Project
New Junction at start of proposed Hapur bypass
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
Design
Sl. No
Existing Chainage (km)
Chainage (km)
7*
---
34+600
8
44+800
9
49+200
10
66+482
Final Feasibility Report Executive Summary
Cross Road Type
Remark Side
Leading to
LHS
Moradabad
RHS
Delhi
49+900
RHS
Gulaothi
At the start of Proposed Gulaothi Bypass
57+000
RHS
Gulaothi
At the end of Proposed Gulaothi Bypass
LHS
NH-235 /Bulandshahr
73+512
NH-24 bypass
End of Project Road RHS
NH-91/Delhi
Minor Intersections
Scott Wilson
7+469 7+970 8+524 9+328 9+465 9+600 10+325 12+180 12+880 14+050 14+620 16+810 17+780 18+270
Junction Type (Cross(X)/T or Y type X T T T T T T T X X T T T X
LHS &RHS RHS RHS LHS RHS LHS LHS LHS LHS &RHS LHS &RHS LHS RHS LHS LHS &RHS
15
18+500
X
LHS &RHS
16 17 18 19 20 21 22 23
20+790 21+055 21+180 21+500 21+770 22+290 23+580 23+810
X T X X T T T X
LHS &RHS LHS LHS &RHS LHS &RHS LHS RHS LHS LHS &RHS
Sl. No.
Design Chainage
1 2 3 4 5 6 7 8 9 10 11 12 13 14
0-8
Side
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
Scott Wilson
Sl. No.
Design Chainage
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
39+300 39+940 40+660 40+865 40+885 41+000 41+150 41+270 41+770 42+000 42+400 42+995 43+600 44+030 45+180 46+150 46+425 48+295 48+635 48+865 49+340 49+360 58+000 58+100 58+360 59+470 59+575 61+450 63+495 63+620 64+400 64+700 65+140 66+475 67+000 68+155 68+460 69+070 69+350 69+410
Final Feasibility Report Executive Summary
Junction Type (Cross(X)/T or Y type X T T T T T T T T T T T T T T T T X T T T T X T T T T X T T T T T T T X T X T T
0-9
Side LHS &RHS LHS LHS RHS LHS RHS LHS RHS RHS RHS LHS LHS LHS RHS RHS LHS RHS LHS &RHS LHS LHS LHS RHS LHS &RHS LHS RHS RHS LHS LHS &RHS LHS RHS RHS RHS RHS RHS LHS LHS &RHS LHS LHS &RHS RHS LHS
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
Final Feasibility Report Executive Summary
Junction Type (Cross(X)/T or Side Y type 64 70+840 T RHS 65 72+000 T RHS 66 72+650 T RHS 67 73+165 T LHS 68 73+437 X LHS &RHS Above junctions to be developed as per the IRC / Ministry Design Standards Sl. No.
Design Chainage
0.3.10 Proposal of Bridges, Culverts and other Structures a)
Major & Minor Bridges There are total 7 bridges on this route. Out of these, one is a Major Bridge and the remaining six are minor bridges. The requirement / possibility of widening and reconstruction of the existing bridges has been checked based on the following criteria If the width of additional widening is 1.0m (0.5 m on each side) or less, the widening of the structure may be dispensed with and traffic shall be guided with the help of crash barriers in a transition of 1 in 20 on either side approaches. All existing bridges which are structurally distressed shall be reconstructed as new bridge All existing brick arch bridge shall be dismantled and replaced by a new bridge The development proposal for all the bridges is tabulated in Table 0.12.
Scott Wilson
0 - 10
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
Final Feasibility Report Executive Summary
Table 0.12: Summary of Development of Bridges Design Sl. Existing No. Chainage Chainage (km) (Km.)
Type of Structure
Span (m) Carriagewa Total No of Span x Width y Width Effective Span (m) (m) L
1
36 + 570
41+615
Minor Bridge
4 x 8.5
6.40
8.40
2
40 + 545
45+665
Major Bridge
3 x 25.0
7.60
10.5
3
41 + 590
46+630
Minor Bridge
3 x 10.0
7.20
9.20
4
-
52+215
1 x 15.0 (SK)
11.0
2x12.0
5
-
53+478
Minor Bridge Minor Bridge
1 x 20.0 (SK)
11.0
2x12.0
6
-
56+788
1 x 20.0 (SK)
11.0
2x12.0
7
58 + 610
65+602
Minor Bridge
4 x 2.50
9.80
11.80
8
58 + 640
65+632
Minor Bridge
1 x 20.0
7.40
10.40
9
60 + 915
67+912
Minor Bridge
3 x 2.8
8.40
9.40
10
62 + 460
69+432
Minor Bridge
3 x 3.0
7.80
9.40
Scott Wilson
Minor Bridge
Type of Bridge
Remark
Proposal for Bridges
Existing Bridge will be abandoned and a new Condition of bridge is 2x12m wide bridge parallel to existing one with 2 x 17m is proposed (RCC T-beam). very poor Existing Bridge will be retained and a new Minor RCC Girder repair is 12m wide bridge parallel to existing one with and Slab span configuration of 3 x 25.0m. required Existing Bridge will be abandoned and a new Condition Brick Arch of bridge is 2x12m wide bridge parallel to existing one with very poor span configuration of 2 x 17.0m (RCC T-beam). RCC T-Beam New PSC/RCC TNew Bridge across Canal on Gulaothi Bypass New beam (2x12m wide) PSC/RCC TNew beam Minor Existing Bridge will be retained and a new 12m RCC Slab repair is wide bridge parallel to existing one with span required configuration of 2 x 5m (Box cell). Minor Existing Bridge will be retained and a new 12m RCC Girder repair is wide bridge parallel to existing one with span and Slab required configuration of 1 x 25.0m. Existing bridge will be replaced by a new 12m wide bridge at the same location with span Condition Brick Arch of bridge is configuration of 2x 5.0m. and another new 12m wide bridge near the existing one with span very poor configuration of 2x5.0m (Box cell). Skew ( 51°) Existing Bridge will be retained and a new 12m Minor wide bridge with 1 x 7.0m (Box cell) after RCC Slab repair is realignment of the existing canal which currently required has a skew angle 81°. Brick Arch
0 - 11
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
Final Feasibility Report Executive Summary
b) Culverts There are total 67 existing culverts in the proposed road corridor. A summary of the proposal is given in Table 0.13. Table 0.13: Summary of Development of Culverts Number of Culverts and Condition Type of Culvert
Reconstruction
Widening
New Construction
Hume Pipe
15
1
24
RCC Slab
12
Brick Arch
4 by RCC slab
Total
19
13
24
35 number of culvert on the existing road is not considered for any development proposal, as these culvert locations are bypassed, Realigned or in the section of out of project scope. c) ROB at Railway line crossing The project road crosses railway tracks at 2 locations inside the Hapur town and construction of ROB is under progress for these two railway crossings. As Hapur town has been bypassed, therefore no improvement proposal has been made inside the Hapur town. However, the proposed Hapur bypass crosses the Railway line at one location at 31+600 (Design Chainage). The crossing has been grade separated by a ROB. The improvement proposal for the railway crossings is presented in Table 0.14 Table 0.14: List of Railway Crossing on the Project Road Section Number Span Existing Design Over Sl. of Development Bridge arrangement Chainage Chainage Remark all No. Tracks/ Proposal (Nos x Type (km) (km) Width Type length), m Existing ROBs One/ Section Hapur 1 29 + 900 Broad ROB under construction Bypassed No Bypass Gauge improvement Two/ Section Hapur 2 30 + 400 Broad ROB under construction Bypassed No Bypass Gauge improvement Proposed ROBs PSC Two/ Girder or On Proposed 2x 1 -31+600 Broad New ROB Composite 2 x 36.0 (SK) Hapur 12.0m Gauge Steel bypass Girder
Scott Wilson
0 - 12
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
Final Feasibility Report Executive Summary
d) Proposal for VUP and PUP
Structural details of the proposed Vehicle Underpass (VUP) and Pedestrian Underpass (PUP) / Cattle Underpass (CUP) structures are given in Table 0.15 and Table 0.16. Table 0.15: Existing and Proposed VUP a) Details of Proposed New Vehicular Underpasses Existing Sl Chainage No. (Km)
b)
Name of Design Chainage Intersecting (Km) Roads
1
Bypass
28+148
State Highway to Modinagar
2
Bypass
51+644
MDR to Dhaluna
3
Bypass
54+778
Road to Sikandrabad
Proposed structural configuration Double span Box type structure Double span Box type structure Double span Box type structure
Structure Over Proposed Dimension all Structure (m) width type No.xLxH in m RCC Box Type
2x12x5.5
27.5
RCC Box Type
2x12x5.5
27.5
RCC Box Type
2x12x5.5
27.5
Details of Existing Vehicular Underpasses
Sl No.
1
Existing Chainage (Km)
Design Chainage (Km)
34+171
39+150
Structure Dimension (m) No.x Lx H 2x10.5x5.5
Name of Intersecting Roads
Remark
NH-24
Existing VUP Retained/ Improvement of slip road
Table 0.16: Existing and Proposed PUP /CUP Sl. No.
Existing Chainage (Km)
Design Chainage (Km)
1
Hapur Bypass
26+682
2
Hapur Bypass
30+540
3
Gulaothi Bypass
52+795
4
Gulaothi Bypass
53+582
Scott Wilson
Proposed Overall Name of Proposed Proposed Span Width Intersecting structural Structure arrangement Roads configuration type No. x Lx H Single span RCC Box VR Box type 1 x 7 x 3.5 27.5 Type structure Single span RCC Box VR Box type 1 x 7 x 3.5 27.5 Type structure Single span RCC Box VR Box type 1 x 7 x 3.5 27.5 Type structure Single span RCC Box 1 x 7 x 3.5 27.5 VR Box type Type structure
0 - 13
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
Final Feasibility Report Executive Summary
0.3.11 Toll Plaza Location of toll plazas has been proposed based on the traffic dispersal pattern at the respective homogenous sections, road geometry and vertical profile of the road and the surrounding area. The location and details of the toll plaza is given in Table 0.17. Table 0.17: Details Toll Plaza Toll Plaza Location Sl. No
Existing Chainage (km)
Design Chainage (km)
42+876
47+900
1
Remark One section from Project Start to Project End
0.3.12 Total Cost of the Project as assessed at this stage is given in Table 0.18 Meerut (at Km 7.469) to Bulandshahr (at km 66.482) Section of NH-235 in the state of Uttar Pradesh to 4-lane configuration (Project length = 66.043 km) Length of existing Hapur Bypass to be used as a part of this project, which has been kept out of the scope of development proposal of this project (Length 3.522km) Table 0.18: Abstract Project Cost (Design length = 62.521 km) Sl. No.
Description
A
Civil Works
Amount in Rs.
Amount in Crores
62.521
62.521
11,642,094
1.16
1
Site Clearance & Dismantling
2
Earth work
574,000,636
57.40
3
Base & Sub-base courses
920,928,178
92.09
4
Bituminous works
1,275,628,236
127.56
5
Culverts
74,590,384
7.46
6
Structures i.e. Bridges, ROB,VUPs and PUP
628,312,441
62.83
7
Drainage & Protection works
72,170,621
7.22
8
Traffic Signs and Road Appurtenances
113,814,738
11.38
9
Truck lay-bye & Bus bay with shelters
22,183,406
2.22
10
Toll Plaza & Junctions
165,178,653
16.52
11
Repair & Maintenance work
44,176,442
4.42
12
Miscellaneous items
76,110,480
7.61
3,978,736,311
397.87
Total Civil Works (based on SOR 2009-10)
Scott Wilson
0 - 14
January 2011
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of UP: Meerut –Bulandshahr Section ( NH-235)
Sl. No.
Description
Amount in Rs.
Updated cost of civil works at level 2010-11 with 5% escalation Per km Civil works cost 14
Contingencies @ 3% on civil work
15
Charges for Independent Engineer @ 1% of (14+15) Total Cost
B
Amount in Crores
4,177,673,126
417.77
66,820,318
6.68
125,330,194
12.53
43,030,033
4.30
4,346,033,353
434.60
76489000
7.65
707020000 52,080,000
70.70
835,589,000
83.56
5,181,622,353
518.16
82,878,111
8.29
Non-Civil Works
16
Budget for EMP
17
Resettlement and Land Acquisition cost
18
Utility Relocation Total Non Civil Works Total Cost (A+B) Cost Per Km
Scott Wilson
Final Feasibility Report Executive Summary
0 - 15
5.21
January 2011
Chapter – 1 Overview of NHAI
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
1.0
OVERVIEW OF NHAI
1.1
NHAI Establishment
Final Feasibility Report Overview of NHAI
The National Highways Authority of India was constituted by an act of Parliament, “the National Highways Authority of India, 1988”. It is responsible for the development, maintenance and management of National Highways entrusted to it and for matters connected or incidental thereto. The Authority was operationalized in February 1995 with the appointment of full time Chairman and other Members. 1.2
NHAI Mandate 1. Primary mandate is time and cost bound implementation of National Highways Development Project (NHDP) through host of funding options including from external multilateral agencies like World Bank, Asian Development Bank, JBIC etc. Work mainly comprises of strengthening and 4/6 laning of high-density corridors around 13,146 kms. The components are:
Golden Quadrilateral – 5,846 kms connecting Delhi-Kolkata-Chennai-Mumbai. North-South-East-West Corridor – 7,300 kms connecting Kashmir to Kanyakumari and Silchar to Porbandhar.
2. Providing Road connectivity to major ports. 3. Involving the private sector in financing the construction, maintenance and operation of National Highways and wayside amenities. 4. Improvement, maintenance and augmentation of the existing National Highways network. 5. Implementation of road safety measures and environmental management. 6. Introducing Information Technology in Construction, maintenance and all operation of NHAI. 1.2.1
NHAI Organization A full time Chairman heads NHAI. Member Finance, Member Administration, Member Technical head their respective departments and report to the Chairman. A detailed organization chart of NHAI is given in Figure 1.1.
1.2.2
National Highway Development Program (NHDP) The National Highways have a total length of 66,590 km to serve as the arterial network of the country. The development of National Highways is the responsibility of the Government of India. The Government of India has launched major initiatives to upgrade and strengthen National Highways through various phases of National Highways Development Project (NHDP) presented in Figure 1.2. National Highway Development Program is envisaged to plan, design and construct a network of world class highways to support the economic growth of the country. Infrastructure in India has been found to be a bottleneck/speed breaker for the trade and business, poverty alleviation and economic growth of the country. Advantages of providing well developed network of highways are as follows:
Scott Wilson
1-1
October 2010
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
Final Feasibility Report Overview of NHAI
Savings in vehicles operating costs by reduced fuel consumption and maintenance costs Travel time savings by faster and comfortable journeys Safer travel Benefits to trade especially in movement of perishable goods. Reduce demographic shift to urban areas Poverty alleviation and all round development of areas
NHDP’s focus is on developing International standard roads with facilities for uninterrupted flow of traffic with:
Enhanced safety features Better Riding Surface Better Traffic Management and Noticeable Signage Divided carriageways and service roads Grade separators Over bridges and Underpasses Bypasses Wayside amenities
National Highways Development Project is being implemented in 6 phases, which are briefly as under: NHDP Phase I : NHDP Phase I was approved by Cabinet Committee on Economic Affairs (CCEA) in December 2000 at an estimated cost of Rs. 30,000 crores comprises mostly of GQ (5,846 km) and NS-EW Corridor (981 km), port connectivity (356 km) and others (315 km). NHDP Phase II : NHDP Phase II was approved by CCEA in December 2003 at an estimated cost of Rs. 34,339 crores (2002 prices) comprises mostly NS-EW Corridor (6,161 km) and other National Highways of 486 km length, the total length being 6,647 km. The total length of Phase II is 6,647 km. NHDP Phase III : Government approved on 5.3.2005 upgradation and 4 laning of 4,035 km of National Highways on BOT basis at an estimated cost of Rs. 22,207 crores (2004 prices). Government approved in April 2007 upgradation and 4 laning at 8074 km at an estimated cost of Rs. 54,339 crores. NHDP Phase IV : With a view to providing balanced and equitable distribution of the improved/widened highways network throughout the country, NHDP-IV envisages upgradation of 20,000 kms of such highways into two-lane highways, at an indicative cost of Rs.27,800 crore. This will ensure that their capacity, speed and safety match minimum benchmarks for national highways. NHDP Phase V : CCEA has approved on 5.10.2006 six laning of 6,500 km of existing 4 lane highways under NHDP Phase V (on DBFO basis). Six laning of 6,500 km includes 5,700 km of GQ and other stretches. NHDP Phase VI : CCEA has approved on November 2006 for 1000 km of expressways at an estimated cost of Rs. 16680 crores. Finance Mechanisms: NHAI proposes to finance its projects by a host of financing mechanisms. Some of them are as follows:
Scott Wilson
1-2
October 2010
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
Final Feasibility Report Overview of NHAI
1. The Government of India – Budgetary Allocation In a historic decision, the Government of India introduced a Cess on both Petrol and Diesel. This amount at that time (at 1999 prices) came to a total of approximately Rs. 2,000 crores per annum. Further, Parliament decreed that the fund so collected were to be put aside in a Central Road Fund (CEF) for exclusive utilization for the development of a modern road network. The developmental work that it could be tapped to fund, and the agencies to whom it was available were clearly defined as:
Construction and Maintenance of State Highways by State Governments Development of Rural Roads by State Governments Construction of Rail Over Bridges by Indian Railways. Construction and Maintenance of National Highways by NHDP and Ministry of Road Transport & Highways.
Today, the Cess contributes between Rs. 5 to 6 Thousand crores per annum towards NHDP. 2. Loan Assistance from International Funding Agencies Loan assistance is available from multilateral development agencies like Asian Development Bank and World Bank or Other overseas lending agencies like Japanese Bank of International Co-operation. 3. Market Borrowing NHAI proposes to tap the market by securities cess receipts. 4. Private Sector Participation Major policy initiatives have been taken by the Government to attract foreign as well as domestic private investments. To promote involvement of the private sector in construction and maintenance of National Highways, Projects are offered on Build, Operate and Transfer (BOT) basis to private agencies. After the concession period, which can range up to 30 years, this road is transferred back to NHAI by the Concessionaires. NHAI funds are also leveraged by the setting up of Special Purpose Vehicles (SPVs). The SPVs borrow funds and repay these through toll revenues in the future. Some more models have emerged for better leveraging of funds available with NHAI such as Annuity, which is a variant of BOT model. 1.2.3
Government Policy Initiatives Policy Initiatives for Attracting Private Investment
Scott Wilson
Government will carry out all preparatory work including land acquisition and utility removal. Right of Way (ROW) to be made available to concessionaires free from all encumbrances. NHAI / GOI to provide capital grant up to 40% of project cost to enhance viability on a case to case basis. 100% tax exemption for 5 years and 30% relief for next 5 years, which may be availed of in 20 years. Concession period allowed up to 30 years. Arbitration and Conciliation Act 1996 based on UNICITRAL provisions In BOT projects entrepreneur are allowed to collect and retain tolls Duty free import of specified modern high capacity equipment for highway construction
1-3
October 2010
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
Final Feasibility Report Overview of NHAI
Figure 1.1: Organisation Chart of NHAI
Scott Wilson
1-4
October 2010
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
Final Feasibility Report Overview of NHAI
Figure 1.2 : National Highways Development Project Phase-I, II & III
Scott Wilson
1-5
October 2010
Chapter – 2 Project Road Descriptions
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
2.0
PROJECT ROAD DESCRIPTIONS
2.1
General
Final Feasibility Report Project Road Descriptions
The project road NH-235, starts from Meerut Town (Km. 0+000) and ends at Bulandshahr town (Km. 66+482). Project road section traverses through three districts of the Uttar Pradesh, namely Meerut, Ghaziabad and Bulandshahr. The nodal towns on the stretches are Meerut, Hapur, Gulaothi and Bulandshahr. The Project Location Map is shown in Figure 2.1. 2.2
Project Background With a view to providing balanced and equitable distribution of the improved/widened highways network throughout the country, NHDP-IV envisages upgradation of 20,000 kms of such highways into two-lane highways, at an indicative cost of Rs.27,800 crore. This will ensure that their capacity, speed and safety match minimum benchmarks for national highways. The work for consultancy services for Preparation of Detailed Project report for rehabilitation and upgradation of National Highway stretches under NHDP – IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh has been awarded to M/s. Scott Wilson India Private Limited, vide National Highways Authority of India (NHAI) letter no. NHAI/Coord./4/2009/10467 dated on 12th March 2010. In line with Terms of references (TOR) the Final Feasibility Report is being submitted. The main objective of this Consultancy Service is to establish the technical and economical viability of the project and prepare feasibility cum detailed project reports for rehabilitation and upgradation of the existing Meerut to Bulandshahr Section of NH-235 in the state of Uttar Pradesh to 4-lane with paved shoulders configuration with provision of capacity augmentation.
2.3
Study of Project Corridor The consultant's team during their several site visits have collected field data to understand the project and its constraints which has been subsequently used to formulate the project improvement/ development proposals. The salient existing features of the project are discussed in the subsequent paragraphs to give an overview of the project corridor. The proper understanding of the existing project features and constraints form the basis of the design proposals to follow. The project features discussed are as follows:
Scott Wilson
Terrain and Land use Climatic Conditions Physiographic Features Geological Features Existing Roadway Right of Way Cross-Drainage Structures Highway Geometrics Pavement Condition Major Developments Cross-road and Junctions Drainage Condition Railway Crossings Utility Lines Environmental and Social Status Alternate Routes
2-1
October 2010
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
Final Feasibility Report Project Road Descriptions
Figure 2.1: Project Location Map
Scott Wilson
2-2
October 2010
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
2.3.1
Final Feasibility Report Project Road Descriptions
Terrain and Land use The project road traverses fully through plain terrain. While classifying a terrain, short isolated stretches of varying terrain is not taken into consideration. The predominant length of the project road passes through agricultural areas with predominance of rural settlements alongside of the road. The percentage distribution of land use is 10%, 43% & 47% for Semi Built-up, Built-up, and agricultural respectively.
2.3.2
Climatic Conditions ANNUAL TEMPERATURE: The spatial distribution of annual mean temperature in Uttar Pradesh shows a gradual decrease in the mean value from south to north because of the increasing distance from the tropic of Cancer which passes through Madhya Pradesh touching the southern tip of Uttar Pradesh. All isopleths are latitudinal following the boundaries of relief regions of the state. Temperature gradient is low in the plain but increase towards the north with the rise of elevation. A major part of the state comes under the temperature zone of 250 C and above whereas the northern portions of Uttar Pradesh remains below 250 C. From March to May there is sharp rise in the mean temperature (Lucknow: mean monthly temperature in March shows 24.60 C and in May 33.90C) while the central and western Uttar Pradesh (including Bundelkhand) experience spells of heat waves. But with the burst of summer monsoon in June, the mean temperature declines sharply. In the month of September there is a slight rise in temperature which again shows a downward trend from October to January, the coldest month of the year. Uttar Pradesh enjoys a tropical monsoon climate. January is the coldest month for the state as a whole. Isotherm lines are almost parallel. May is the hottest month of the state as a whole but July is the typical month of south-western monsoon. During the cold season, particularly in January, the cold waves sweep over the whole Ganga plain. They generally accompany the winter depression. ANNUAL RAINFALL: Uttar Pradesh, the landlocked state of India with an area of 2, 40,928 sq km is blessed with a plenty of rainfall almost throughout the state. The Tropic of Cancer passes through the southern part of the state touching the tip of Mirzapur district. The state is away from the Bay of Bengal by 625 km and by 800 km from the Arabian Sea. Uttar Pradesh can broadly be divided into two parts –the southern hills and the Ganga plain. The vast expanse of the state, both in the northsouth and the east-west shows appreciable annual and spatial variations of rainfall. On the plain, the rainfall amount received is below 1200mm. It decreases from east to west as recorded in Gorakhpur(1250mm), Basti (1200mm), Faizabad(1050mm), Lucknow (1010mm), Hordoi (970mm), Etah ( 780mm), Agar(770mm) and Mathura(540mm). The annual rainfall and mean temperature conditions of the state of Uttar Pradesh are pictorially shown in Figure 2.2 and Figure 2.3, respectively.
Scott Wilson
2-3
October 2010
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
Final Feasibility Report Project Road Descriptions
Figure 2.2 : Mean Temperature of the state of Uttar Pradesh
Scott Wilson
2-4
October 2010
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
Final Feasibility Report Project Road Descriptions
Figure 2.3 : Annual Rainfall of the state of Uttar Pradesh
Scott Wilson
2-5
October 2010
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
2.3.3
Final Feasibility Report Project Road Descriptions
Existing Carriageway Width The road inventory survey was carried out during the first half of May 2010 and the configuration discussed in this paragraph pertains to the roadway configuration till that period. The roadway for the entire stretch consists generally of the following configuration: Chainage (Km) Length (Km) CW Width (m) Lane Configuration From To 0+000 7+469 7+469 14.0 2x2 Lane with 1m median 7+469 25+500 18.031 10.0 2 Lane with PS 25+500
66+482
40.892
Length of 4- lane section Length of 2- lane with PS section Length of 2- lane section 2.3.4
7.0 : : :
2 Lane 7.469km 18.031km 40.982km
Existing Right of Way The project road does not have any ROW pillars to demark the existing right of way width on ground. Even the PWD office does not have the record for authentic road land width of the road. Collection of village maps from the Revenue Department is ongoing, after getting the village maps, exact width of the road land available as per govt. record can be ascertain.
2.3.5
Cross Drainage Structures The project road has sufficient cross-drainage structures consisting of culverts, major and minor bridges along the corridor. The condition of most of the culverts is fair and hence they require only minor/major repairs, whereas the condition of the bridges is fair and they need application of minor repairs only. There are 6 Minor Bridges, 1 Major Bridge and 67 culverts in the project stretch between Meerut to Bulandshahr. The existing culverts are of the following type:
Pipes RCC Slab Brick Arch
The summarised details of the existing cross drainage structures are given in Table 2.1. Table 2.1: Summarised Details of Cross Drainage Structures
Culvert
Type of Structure
Numbers
Pipe Culvert (Total) Pipe Dia < 0.9 m Pipe Dia ≥ 0.9 m Arch Culvert (Brick) Slab Culvert
43 24 19 4 20 Total Culverts
Scott Wilson
2-6
67
October 2010
DPR for rehabilitation and upgradation of NH stretches under NHDP-IVB [Group B (Package No. UP/DPR/NHDP-IV/07)] in the state of Uttar Pradesh: Meerut-Bulandshahr Section (NH-235)
Bridge
Type of Structure Minor Bridge Carriageway
View more...
Comments