APNA Project Implementation Implementa tion at Faisalabad Electric Supply Company Presented to: PMO & Steering Committee

Copyright © 2015 AbacusConsulting. All rights reserved.

Project Status Update  – (14th December to 18 th December 2015)

7 Project Management Keys (Overall Status

 Yellow)

 – 

Keys Status Updated on: 18th December, 2015 Stakeholders • •





Team

Stakeholders are KNOWN Their INTERESTS and INFLUENCE are identified Stakeholders are PLEASED with the work Stakeholders are AVAILABLE









Scope •







Scope is clear and m utually UNDERSTOOD CONTRACT and/or scope statement is agreed upon Deliveries are WITHIN SCOPE; no more, no less





• • •

Delivery Organization Benefits •



• •



Delivery organization stakeholders are KNOWN Knowledge is HARVESTED and leveraged  Actuals are in line with BUDGET Favorable project CITATIONS are established





Work and Schedule

PROJECT PLAN is up to standard DEADLINES are met Work PROCEEDS in line with plan Project Sponsor is UPDATED on status of work

Risks • •

Business Benefits •

Team has required COMPETENCY and CAPACITY There is a constant dialogue between PM and team  Adequate project FACILITIES are in place Team has normal WORKING HOURS Team works EFFICIENTLY PERSONAL DEVELOPMENT is ensured Key PEOPLE STAY with the project



Project Sponsor has CONFIDENCE in Delivery Organization Project Sponsor gains OWNERSHIP Delivery Organization can MEASURE and highlight specific RESULTS



2

Team is AWARE of potential risks Team NOTIFIED PM when work progress is threatened  ACTIONS taken to reduce risk are closely MONITORED Risk and Issue management PROCESSES are ESTABLISHED and FOLLOWED

7 Project Management Keys (Overall Status

 Yellow)

 – 

Keys Status Updated on: 18th December, 2015

The area of Stakeholders and scope is in yellow due to the following reasons: •







Implementation of sites like TRW, RTC, M&T, C-Type stores, etc., installation of IDES environment for FESCO, multiple installations on interim environments, development of RICEFW after BBP signoff, participation in Hardware inspection, additional Divisions and ROs etc. are not part of project scope and will impact project schedule and cost. Request of including 3 additional Divisions and 3 ROs has been received from FESCO. Change request has been submitted to FESCO upon the approval of which, these sites will be included in the scope of work. Training of End Users over and above 160 users is beyond the scope of services. So far, 361 total users have been trained on SAP. Further trainings are being requested by FESCO which will be charged through change management process. Change request for further extension in project timeline has been submitted since further delay is expected in Go-Live date by FESCO.

The area of Work and Schedule is in Yellow due to the following reasons: •







The status of the project is being changed from Red to Yellow since SC has approved the extension in project timeline till Go-Live. Frequent strikes by Employees Union has impacted project progress causing a delay of at least 31 working days so far. The closure of offices for 2 weeks has delayed Go-Live schedule. FESCO’s decision to shift the cutover date from June 30 th 2015 to September 30 th 2015 will cause a delay in the Go-Live date and overall project completion date. Change request to adjust time schedule and cost has been submitted to FESCO. Delays in the readiness of server room and installation of servers caused delay in the cutover 3 schedule and all dependent activities.

7 Project Management Keys (Overall Status

 Yellow)

 – 

Keys Status Updated on: 18th December, 2015 •



Delay in provision of data by FESCO is impacting the Go-Live date. Certain data objects are still awaited despite revision in data provision date. Overall completion of UAT was delayed due to employees union strike, non availability of power users and new requirements (out of project scope) communicated by users.

The area of Team is in yellow due to the following reasons: •





Facilities to be made available by FESCO for Project office are still pending even after several requests e.g. scanner, meeting room, etc. Stable and uninterrupted internet connection is required for migrating data into Production environment since any disconnection during the migration will cause delays and rework for the team and FESCO Power Users. Abacus has arranged own internet device to migrate data.  Activities e.g. preparation and maintenance of FI Master data files, data validation, refresher trainings etc. that are to be conducted by FESCO Power Users are considered the responsibility of  Abacus Team despite several clarifications resulting in excessive engagement of team in such activities.

4

Current Status

 – 

Phase wise We are here

The phase wise status is as follows: Phase Project Preparation Phase Inception Report (Phase 0)

Deliverables • • • • •

Business Blueprint Phase

• • • •

Realization Phase

• • • • • • • • • •

Final Preparation

Status

Project Charter Project Plan Project Management Procedures RFP for Servers and Allied Equipment RFP for Hardware and Networking

Complete

 As-Is Analysis Document Business Blueprint Documents for MM, PS and FICO Gap Analysis Report Business Blueprint – Sign-off 

Complete

Configuration Unit Testing and scripts User Manuals DM Test Cycle 1 System Integration Testing Power User Training UAT Scenario List  ABAP development UAT  Authorization Matrix finalization by FESCO

Complete

Complete



End User Training – Phase 1 Installation of SAP Solution Manager, Development, QA and PRD Transport Configuration and Customization in PRD EU Training – Phase 1, 2 & 3 Cutover Plan Configuration of Auth. Roles



Data collection and preparation by FESCO

In Progress

• • • • •

Project Plan

Status as of 18th Dec, 2015

Project Phase

Duration

Start Date

End Date

Project Preparation Business Blueprint

12 Weeks 17 Weeks

04.08.2014 18.08.2014

31.10.2014 19.12.2014

Realization Final Preparation

28 Weeks 25 Weeks

22.12.2014 25.05.2015

31.07.2015 23.12.2015

23 12 2015

23 12 2015

Go Live

All Phases

Project Plan

 – 

Snap shot*

*Go-Live date and project completion date is dependent on the provision of data by FESCO 7

Current Status

 – 

Project Management

 Activities completed during the reporting period •







Balances of 71 (out of 73) accounting units has been successfully uploaded in the production system. Trial balance for all these offices has been extracted from the system and provided to FESCO for reconciliation. Data of employee vendor is awaited for most of the accounting units. Data entry of tenders has been initiated by MM department in the production system. Excess users (153) have been deleted from the production system in compliance of SAP license policy. The users will be created by FESCO once licenses are procured for these addl. Users. Change request for extension in project timeline has been submitted to FESCO.

 Activities started and in progress: •







Project Plan is being monitored and updated with the changes in schedule of activities. Issues Log and Risk Register is being monitored and updated with current status of issues and risks. Data collection, preparation and validation is being done by FESCO. Data Migration and adjustments in finalized data objects is in progress.

 Activities planned for next reporting period (21st Dec – 25th Dec) •





 All sites will Go-Live by the end of next reporting period subject to the provision of complete data by FESCO. Source files of FICO master data will be shared with AFF for data validation. Data Migration will be completed during next reporting period. 8

Current Status •



 – 

Project Management

Data entry will be initiated for sites that have complete balances in the system e.g. ROs, Regional Stores etc. Change requests for training of addl. users will be submitted in next reporting period.

 Activities delayed from schedule •



Continuous closure of FESCO offices due to employees union strike from November 5 th to November 19th has caused major disruption in cutover activities. As a result, scheduled Go-Live has been delayed. Collection, cleansing and provision of complete data for FICO on data templates (remaining objects) by FESCO is still awaited. Go-Live date is dependent on the provision of data by FESCO. The provision of data has been significantly delayed by FESCO causing increase in backlog data (3 months).

9

Current Status

 – 

Materials Management

 Activities completed during the reporting period •

MM department has initiated entering tenders in the production system in the supervision of  Abacus team.

 Activities started and in progress: •



Support is being provided by Abacus team in the review of backlog data and open transaction data. Guidance is being provided to FESCO users in the data entry by Abacus team.

 Activities planned for next reporting period (21st Dec – 25th Dec) •

Data entry will be initiated for sites that have complete balances in the system e.g. Regional Stores, etc.

 Activities delayed from schedule: •



Continuous closure of FESCO offices due to employees union strike from November 5 th to November 19th has caused major disruption in cutover activities. As a result, scheduled Go-Live has been delayed. Delay in the provision of balances is causing delay in the start of data entry of backlog.

10

Current Status

 – 

Finance and Controlling

 Activities completed during the reporting period •



Balances of 71 (out of 73) accounting units has been successfully uploaded in the production system. Trial balance for all these offices has been extracted from the system and provided to FESCO for reconciliation. Data of employee vendor is awaited for most of the accounting units. Required adjustments in the uploaded data and addl. Master data communicated by FD have been uploaded in the production system.

 Activities started and in progress: •



Balances are being prepared by FD for cutover for remaining accounting units. Finalized data objects are being uploaded in the Production environment.

 Activities planned for next reporting period (21st Dec – 25th Dec) •







Source files of FICO modules will be shared with AFF for data validation. Data Migration will be completed during next reporting period. Data entry will be initiated for sites that have complete balances in the system e.g. ROs etc. Balances will be provided by FD for all remaining sites during next reporting period.

 Activities delayed from schedule: •



Continuous closure of FESCO offices due to employees union strike from November 5 th to November 19th has caused major disruption in cutover activities. As a result, scheduled Go-Live has been delayed. Provision and finalization of balances is still awaited. 11

Current Status

 – 

Project System

 Activities planned for next reporting period (21st Dec – 25th Dec) •

Data entry will be initiated for PDC and PMU in the next reporting period.

 Activities delayed from schedule: •



Continuous closure of FESCO offices due to employees union strike from November 5 th to November 19th has caused major disruption in cutover activities. As a result, scheduled Go-Live has been delayed. Delay in the provision of balances is causing delay in the start of data entry of backlog.

12

Status of Provision of Data for Cutover  Status of Data Collection, Preparation and Provision and Upload MD / Migration Object TD

Data Tea Provided m  /prepare d

Remarks

Data upload status

MD MD MD MD MD

Chart-of-Accounts FI (central) Cost Centers FI Profit Centers FI Cost Elements FI Banks (Bank Keys and FI House Banks) Assets FI Welfare Fund VendorsFI Employee Vendors FI Non Trade Vendors FI Pension Vendors FI

MD

Customers

FI

Yes

MD

Internal Orders

FI

Yes

MD

Fund Centers Funded Programs for Civil Works Commitment Items Material Master Material Extension (each plant)

FI

Yes

Data has been finalized by FESCO Data for RO offices is available that will be created as Customers Data for vehicles has been used to create Internal Orders Master Data file by Abacus Data has been finalized by FESCO

FI

No

Data has not been provided. Dependent upon CWIP data

FI MM

Yes

Data has been finalized by FESCO

Uploaded

Yes

Data has been finalized by FESCO

Uploaded

MM

Yes

Data has been finalized by FESCO

Uploaded

MD MD MD MD MD

MD MD MD MD

Yes

GLs of banks are still to be finalized by FESCO

Uploaded

Yes

Data has been finalized by FESCO

Uploaded

Yes

Data has been finalized by FESCO

Uploaded

Yes

Data has been finalized by FESCO

Uploaded

Yes

Data has been finalized by FESCO

Uploaded

Yes

Data has been finalized by FESCO

Uploaded

Yes

Data has been finalized by FESCO

Uploaded

Yes

Data has been finalized by FESCO

Uploaded

Yes

Data has been finalized by FESCO

Uploaded

Yes

Uploaded

13

Uploaded Uploaded Uploaded

Status of Provision of Data for Cutover Status of Data Collection, Preparation and Provision and Upload MD / Migration Object TD

MD Service Master Data MD Vendor master data Project Master Data MD Project Definition Project Master Data MD WBS Elements

Data Tea Provided/ m prepared

Remarks

Data upload status

MM MM

Yes

Data has been finalized by FESCO

Uploaded

Yes

Data has been finalized by FESCO

Uploaded

PS

Yes

Data has been finalized by FESCO

Uploaded

PS

Yes

Data has been finalized by FESCO

Uploaded

TD

GL Balances (Balance Sheet)

FI

Partial

TD

GL Balances (P&L)

FI

Partial

TD

AP Balances

FI

Partial

TD TD TD

AR Balances CWIP Budget Data Inventory balance migration (Serialization)

FI FI FI

Yes

Data provided for 71 Data is being finalized by FESCO. Data for 71  Accounting units has been accounting units has been provided by FESCO so far. uploaded in the Production system. Data provided for 71 Data is being finalized by FESCO. Data for 71  Accounting units has been accounting units has been provided by FESCO so far. uploaded in the Production system. Data is being finalized by FESCO. Partial data for ROs Data provided for ROs has has been provided by FESCO so far. been uploaded in PRD Data for ROs has been provided by FESCO. Uploaded

Yes

Data has been finalized by FESCO

Uploaded

Yes

Data has been provided by FESCO.

Uploaded

MM

Yes

Data is yet to be finalized by FESCO

Uploaded

TD

14

Status of Provision of Data for Cutover Status of Data Collection, Preparation and Provision and Upload MD / Migration Object TD

Data Tea Provided/ m prepared

TD

Open PRs (Yearly Purchase Plan and Civil MM Works)

Yes

TD

Open POs

Yes

TD TD TD

MM

Open Service POs (work MM orders) Open Stock Transport MM Orders Open Contracts

MD/ WBS BOMs TD TD Planned Cost Actual Cost (Running TD Projects)

Remarks

Data upload status

Yearly purchase plan has been finalized by MM, however, open PRs for Civil works are yet to be NA finalized. Users will enter this data in the system after Go-Live Data has been prepared by MM and PMU for open NA POs which will be entered by users after Go-Live

Yes

Data is being finalized by FESCO which will be manually entered in the system by the users

NA

Yes

Data has been prepared by FESCO for open STOs which will be entered by users after Go-Live

NA

MM

Yes

Data is being finalized by FESCO which will be manually entered in the system by the users

NA

PS

Yes

Data has been provided by FESCO

Uploaded

PS

Yes

Data has been provided by FESCO

Uploaded

PS

Yes

Data has been provided by FESCO

Uploaded

15

Key Risks and Mitigation Strategies Please refer to the attached sheet

16

Key Open Issues Issue

Level

Brief Description

Resolution Steps

Status

Provision of data by Finance Department as per SAP data templates.

High

Data preparation process has not been initiated by Finance department on the SAP data templates despite lapse of several weeks.

Data Owner needs to assign a team with the task of collecting and preparing data on SAP data templates. Priority needs to be given to the data required for configuration.

Open (Data preparation activity is in progress and most of the master data objects have been finalized by FD)

Unsatisfactory response time of hardware vendor for replacement of faulty part

High

The faulty part needing replacement in the affected QA system could not be replaced by HW vendor despite lapse of 1 week. HW vendor is supposed to maintain inventory of critical parts at FESCO premises to avoid such delays.

FESCO needs to ensure that inventory of critical parts is maintained at FESCO premises and HW vendor provides support as per committed response times.

Open

17

Key Assumptions/Critical Success Factors For a successful go live as per the current project plan version it is imperative that following factors are strictly adhered to:  Availability of Process Owners and Power Users for Final Preparation Phase activities as per schedule needs to be ensured. Resources committed 100% to the project (FESCO and Abacus) are not diverted on other tasks/assignments. Delivery organization resources are not forced to undertake any activity that is out of scope and/or that could impact the go live date of the project. Resources are kept interested and motivated. Key decisions to be sought from business users are thought out well in advance so that the decision making time doesn’t impact the go live date. Issues are at best resolved at the execution layer of the project and efforts should be made to not let the issue create an environment of animosity and conflict. If these cant be resolved at this level, the same should be escalated to the appropriate level for resolution without wasting any time.  Availability of Hardware and communications infrastructure for sites needs to be ensured as per schedule. Uninterrupted system access should be available to the team to carryout cutover activities. •















18

Contact us: AbacusConsulting, Abacus House, 4 Noon Avenue, Main Canal, Lahore 54600, Pakistan. Telephone: +92 42 588 4981-5 Facsimile: +92 42 588 4987 email: [email protected]

19