Hefei Jinshan CONTENTS 1
BELT-SCALE STRUCTURE..................................................................... 2
2
BELT-SCALE MACHINERY INSTALLATION........................................................ 3
3
BELT-SCALE ELECTRICAL INSTALLATION....................................................... 4 3.1
THE
CONTROLLER INSTALLATION
............................................................... 4
3.1.1
Open the controller packaging ..................................................... 4
3.1.2
Putting the Controller into control cabinet ....................................... 5
3.2
THE
SENSOR INSTALLATION
.................................................................. 6
3.2.1
The Z6 sensor installation ........................................................ 6
3.2.2
The general sensor installation ................................................... 8
3.2.3
The Measure Speed Sensor installation ............................................. 9
3.3 4
THE
CABLING CONNECT THE CONTROL CABINET WITH THE BELT SCALE AND ITS REQUIREMENTS.
..................... 9
THE BELT SCALE POWER UP AND DEBUG...................................................... 10 4.1
SET
4.2
GENERAL
4.3
THE
4.4
CORRECTS THE SLANTING OF
4.5
CHECK
5
UP THE FREQUENCY CONVERTER PARAMETER
................................................... 10
OPERATION OF THE CONTROLLER
....................................................... 11
BELT SCALE MECHANICAL PARAMETER
....................................................... 13
THE
BELT RUNNING CORRECTS
SIGNALS OF THE CONTROLLER
........................................... 14
: ....................................................... 15
THE BELT SCALE CALIBRATION............................................................. 15 5.1
DETERMINED THE TOTAL WEIGHT OF THE WEIGHT AND THE CALIBRATION POLE.
.............................. 15
5.2
ENTER CALIBRATION INTERFACE ............................................................. 16
5.3
TARE
CALIBRATION ......................................................................
16
5.4
STATIC HUNGING WEIGHT CALIBRATION .........................................................
17
5.4.1
Zero calibration ................................................................ 17
5.4.2
Full calibration ................................................................ 17
5.5
DYNAMIC
5.6
REAL
6
HUNGING WEIGHT CALIBRATION ........................................................
18
MATERIAL CALIBRATION ...............................................................
18
COMMUNICATIONS CORRECTION.............................................................. 20 6.1
COMMUNICATIONS
CORRECTION FUNCTION ........................................................
20
6.2
I/O
INPUT TEST .......................................................................
20
6.3
ANALOG
OUTPUT TEST
.................................................................... 20
APPENDIX 1:REPLACEMENT BELT ................................................................ 21 APPENDIX 2:THE USE OF LUBRICANTS MODEL ..................................................... 22 APPENDIX 3:THE CONTROLLER BACK PANEL TERMINAL DRAWING ...................................... 23 APPENDIX 4:PARAMETER TABLE 1 ............................................................... 24 APPENDIX 5:PARAMETER TABLE 2 ............................................................... 25
- 1 -
Hefei Jinshan
FCO-461 controller is a new generation of controllers introduced by Hefei Cement Research & Design Institute Jinshan factory Electrical & Automation Equipment Plant in recent years.FCO-461 as a multi-function controller, can be used for a single measurement equipment or the measurement equipment with pre-feeding equipment.
1
Belt-scale structure The significance of uderstanding the belt scale’s setup,debugging,calibration and safeguardi is very important
Figure 1 Figure 1 shows major part of the belt scale.
(1) Initiative Drum:Initiative Drum is driven by reduce motor ,and drag the belt. (2)
Passive Drum:By adjusting the screws of the Tension Slip Block (4), change the location of Passive Drum, you can adjust the belt tension and deviation
(3) Cross Reed: Cross Reed used to link Scale body and Measurement Framework. (4)
Tension Slip Block:It can adjust Belt-scale deviation and take-up - 2 -
Hefei Jinshan (5)
Measurement Framework.:It is Transmission Structures of Belt Scale,It spread material weight on belt to sensors.
(6)
Automatic Tension Denice:It can make Belt to maintain a certain degree of tension,and make the belt weight to change in a very small range。
(7)
Discharging hopper:passing by the discharging hopper ,stuff come from the Silo to the belt,and it can adjust thickness of the material layer by adjusting the opening of the hopper strobe. Geared Motor:the Driving Device of belt scale,it have the speed sensor which convert the angular velocity controller to
the identify electronic signals. (8)
Sensor:it convert weight to electronic signal which can be transmited to the contoller. Otherwise, On the surface of the scale, there are a the small drum roller which is parallel by Initiative Drum & Passive
Drum. According to their different functions, can be divided into Measurement Drum and Support Drum.
Figure 2
2
Belt-scale machinery installation The gradient of surface of the belt scale should be Less than 3/1000.
Figure 3 According to figure 3 , adjust installation location of discharging hopper,and when it is over ,the distance - 3 -
Hefei Jinshan from the underside the discharging hopper underside to the belt upper surface is 10~15mm,and the distance from the
Flange center of the discharging hopper to the center line of the Passive Drum is 250~300mm. Check whether the belt weighing components intact.
3
Belt-scale electrical installation Used a four-way Control panel as an example.
figure 4
3.1 The controller installation The Control panel ought to installed in the indoor with less dust and the Control panel shell should be connected to a good grounding. 3.1.1
Open the controller packaging
figure 5
- 4 -
Hefei Jinshan 3.1.2
Putting the Controller into control cabinet
figure 6 Let us see the backup of the controller.
figure 7 there are some connection terminal rows and some computer plugs.the terminal row is pluggable,their have connected before it outed the factory,you only need to insert correct plugs to the right faucet. Each connection terminal number is not the same.According to its number and direction,you can finish right connection. And nearby connection terminal row,it marked "1" is No. 1 terminal Notice: Do not inserted connection terminal rows wrong,it will make the controller to go wrong or damage.
- 5 -
Hefei Jinshan
figure 8
3.2 The sensor installation 3.2.1
The Z6 sensor installation
A set of components for the installation of sensor devices include a Pressure head screw and a fixed nut, a Z6 sensor, a steel Ball, a steel ball installed Block,two Fixed screw. The first step
figure 9 The second step
- 6 -
Hefei Jinshan
Figure 10 The third step
Figure 11 The fourth step
- 7 -
Hefei Jinshan
Figure 12 3.2.2
The general sensor installation
General sensor installation steps are Almost the same with Z6 sensor,but their installation foundations are different. Please refer to the Figure 13,put the sensor into its installation foundation,and Tighten the screws to Fix sensors(there are some corresponding position screw hole.)
Figure 13
- 8 -
Hefei Jinshan 3.2.3
The Measure Speed Sensor installation
Figure 14
Figure 15 ▲ Please refer to the Figure 15,put the measure speed sensor into its installation foundation,and fix the sensor,then turn motor fan by your hand,check weather the sensor fight the gear) 1.If Yes, adjust the fixed copper pipe forward slowly,then repet ▲ step until just do not fight Gear,and revolve the copper piper backward one loop,and fix the fix screw nut.Insert the sensor into its installation foundation again,fix the screw. 2.if not, adjust the fixed copper pipe backward slowly,then repet ▲ step until just fight Gear,then do 1 step.
3.3 The cabling connect the control cabinet with the belt scale and its requirements. There are three type line between the control cabinet and the belt scale ,their is the signal line and the electrical line, the Control line three types.
The Signal line must be Shielded cable,and how to place different lines please to the drawings with the scale. The signal line demands to wear in charge of laying or the thread goes along the special-purpose bridge shelfing while connecting up, The line of signal should carry on earthing the single-end of shielding layer in the switch board to enter the switch board. All shielding layer all unsettled while wiring, no earthing, In scene, all shielding layer all unsettled while wiring, no earthing, please. Be careful:There are triangles to connect France and star and connect two kinds of laws quantitatively for the electromechanics machine wiring of material,Generally speaking the single-phase frequency converter which enters the line adopts the triangle to connect the law,And the frequency converter that three phases enter the line adopts the star to connect
- 9 -
Hefei Jinshan the law. The detailed conditions please consult the frequency converter selected for use to prove. Please measure every wiring carefully after all wiring finish. Strong electricity and weak electricity have errorless to connect especially, so as not to lead to the fact unnecessary loss pay cable. The following is a wiring design of the line of signal between a belt balance and switch board, concrete wiring consults the paper of figure.
Figure 16
4
The belt scale power up and debug
4.1 Set up the frequency converter parameter Turn on the back door of the switch board, close the air switch from left to right, give electricity of the switch board, the controller and frequency converter are with electricity at this moment. Turn on the forward door the control cabinet, establish the frequency converter parameter. Take frequency converter F11S of Fuji as an example below, provide the parameter form that the frequency converter needs to revise, other parameters are subject to that dispatched from the factory and established。 Frequency
Parameter meaning
Number value 0 The panel is operated
F01
Signal mode
Generally establish 1 Voltage
signal 2 Electric current signal electric current signal
- 10 -
3 Voltage and
2
Hefei Jinshan 0 Panel launched
F02
Start set
F03
the highest frequency
50~400Hz
50
F04
Basic frequency
50~400Hz
50
F07
First acceleration time
6
10
F08
First moderation time
6
10
F11
,1external signal
1
Hot protection electric current
Establish according to the
of the motor
motor
4.2 General operation of the controller First of all, make us familiar with the operation interface of the controller:
Figure 17 FCO-461 controller adopts systematic menu type way to carry on the function to manage,you can consult the chart of making and combine the manual to familiar with it to generally operate.
- 11 -
Hefei Jinshan
Figure 18 The normal display status:Display picture of acquiescence when being electric each time of the controller. Operation 1: Method to enter main menu,Push The
main menu and return the normal display status, press the
key can enter the main menu,If you want to withdraw the
key.
Operation 2: Select the necessary function and method to enter the next grade of menu in each menu. At first ,Use the key moves the necessary function to and reveals the down area of the area(the up area of the area reveal the name of this menu),press the
key to enter the next grade of menu or sub function. If you want to get back to the menu at a
higher level and only need to press the
key.
Figure 19 For example:In Figure 19, We pass in the picture of having Move” Programing” to the down area of the area by pressing
- 12 -
Hefei Jinshan
the
key. Push the
key and enter the next grade of menu.
Figure 20 Be careful:When you select the sub menu with black arrow point in the list and enter the next grade of menu, it will spring a menu Password _ _ _ _ _ _ _ _ and require you to input the password. It will enter the next grade of menu or sub function after only inputting the correct password Operation 3: Method to revise number value. Describe in the list as the parameter of revising, in fact this operation mode not only merely revise the parameter, but also revise the flow of establishing or establish the rotational speed under revealing the state normally. Number value is changed and generally gone on by this method. The concrete step:when you enter concrete parameter unit of the parameter form(As the upper list shows the procedure), If need to revise the parameter to push The
key is entered and press the
key confirms inputting, press the
Key input digit and press the
key deletes the single figure, press the
key cancel inputting.
4.3 The belt scale mechanical parameter When at being the initial electricity debug ,you only need input some parameters of the C mechanicals parameters mechanicals. The following is relevant number value of input of the necessary parameter. address
English
Explanation
Default value
simplification
Position in the figure 21
and
proving correspondingly
C00
Roller dia.
Cylinder diameter
0.22 m
1
C01
Speed Reducer
motor speed ratio
51
3 Mark in the plate of reduce machine.
C02
Eff.Platf.Length
The
effective
Weigh
0.45 m
length C03
Gear Number
Half of shown length
in the
position 2.
The number of pulses
30
when motor rotates a circle C04
Nominal Load
Nominal Load of the
100 kg
5 Mark in the plate of sensor.
3.95 m
4
sensor C05
Belt Length
Belt girth
- 13 -
Hefei Jinshan
figure 21
4.4 corrects the slanting of The belt running corrects the figure 22 show me installation sites and panels of the locate box.
figure 22 turn the change-over switch of the locate box to the " manual " status,press the Starting button of the locate box,and adjust the potentiometer,to the belt scale a suitable speed. Monitor the running and leaning towards the direction of the belt scale,In general belt driven to the location as the passive drum. If the belt deviation to the left side, tighten the nut on the back of tension sliding block on the belt scale left side .If the belt deviate to the right side, tighten the nut on the back of tension sliding block on the belt scale right side. every time twist a nut one, two laps , After finish the work , should allowed the belt to run continutely, observe the effects.
- 14 -
Hefei Jinshan
figure 23 Be careful:The new scale should run for several days and Observe status of its machinery, You need to carry out regular checks of belt running deviation status,and revise it。
4.5 Check signals of the controller : When the belt scale runing,you can check whether the load signaal and the measure speed signal are normal.If the singals are irregular,please shut off the power of th controller at once and check whether sensor and sensor’s line connection are damage, and ensure that there are no short and circuit Opening situation. When the belt scale runing,press the Speed = Motor speed value.Unit:rpm。
key,observe the controller Following the two state: Numerical range:0~1500rpm
The value should be relative the speed on frequency converter. Load.AD = Load signal AD conversion value
Numerical range:100~4000
If these data are not in the numerical range or inconsistent with the requirements,please shut off the power of the controller, check whether sensor and sensor’s line connection are damage, and ensure that there are no short and circuit Opening situation.
5
The belt scale calibration
5.1 determined the total weight of the weight and the calibration pole. Record the total weight the weight and the calibration pole,mark as P(Kg).
figure 24 Now assume that P = 20.7 (Kg), input this value as a weight weight into the D00 unit of the parameters list D00 unit
- 15 -
Hefei Jinshan
figure 26
5.2 Enter Calibration Interface
figure 27 According to the process the figure provided by the figure 27 the calibration process enter the calibration sub-menu. At this time the manul/automatic switch of the locate box should be turned to "automatic" status.
5.3 Tare calibration After finish the second step,do the belt weight calibration.
figure 28 Then turn the controller status to the Volume mode. Interrelated step:
- 16 -
Hefei Jinshan
figure 29 If system have a pre-feeding equipment ,you must stop the pre-feeding equipment. Continuously press the
3,press the
key and return to the nomally display status,set the motor speed as 600rpm by operation
key and start the belt scale.
Select “Tare calibration”on the calibration submenu and enter. The display will shows the percentage of the belt running 1 lap or N lap and the AD average value of belt weight.when the percentage change into 100%,the belt scale will stop automatically and display a ultimate value,press the
key and the
ultimate value will be written into the controller corresponding Parameter, the belt weight calibration process is over.If you aren’t satisfied with the reslute ,press the
key to cancel the operation.
5.4 static hunging weight calibration 5.4.1
Zero calibration
Let belt scales in the empty status and static status。Immediately following the above steps,select“zero calibration”on the calibration submenu and enter.The controller will sample A / D numers,system automatically stop after 10 seconds and show average AD sampling value, press the
key and the ultimate value will be written into the controller corresponding
Parameter,the zero calibration is over. If you aren’t satisfied with the reslute ,press the 5.4.2
key to cancel the operation.
Full calibration
Maintain the belt weighing stop,put the weight and the calibration pope on the scale.Then select“full calibration”on the calibration submenu and enter.
figure 30 system automatically stop after 10 seconds and show average AD sampling value, press the
key and the ultimate
value will be written into the controller corresponding Parameter,the zero calibration is over. If you aren’t satisfied with the
- 17 -
Hefei Jinshan
reslute ,press the
key to cancel the operation.
5.5 Dynamic hunging weight calibration Don’t move the weight on the belt scale,stop volum mode and enter gravity mode. Interrelated step:
figure 31 Continuously press the
the flow as S1(t/h),press the
key and return to the nomally display status,set the motor flow (t/h) by operation 3,record
key and start the belt scale.
Using a stopwatch to record the time T1 (seconds)how long the belt circle one loop,and calculate the theoretical time T2 how long the belt circle one loop. computing formula T2=3.6×P×the belt loop length/S1/ The effective Weigh length then calculate Errors value Error=
T1-T2 × 100% ,the value ought to be less than 1%。 T2
If the result Is greater than or equal 1%,enter the parameter D05. The original values of the parameter D05 multiplied byT2/T1 and input the result to the parameter D05 again. Restart the belt scale and repeat the test with a stopwatch,and calculate Errors value,until the result is satisfied with requirement. 。
5.6 Real material calibration whether do real material calibration should be dependent on the scene condition . if the belt scale is used for the dosage of raw material,the process should be finished.
- 18 -
Hefei Jinshan
figure 32 change the controller mode to Volume mode.According to the figure 32, divide the process of the real material calibration in four steps. 1.
Preparation step
Open the strobe of the discharging hopper, let materials fall
Start the belt scale by pressing the
key.When the material overspead the upper belt,press the
key and
stop the belt scale,the material status is as shown in the dawing 1 of figure 32, materials just spread to materials fall position of the initiative drum. Clean the Surplus material fallen from the initiative drum during the belt runing.
Press the
key,clear cumulation。 2.
Press the
Strat the belt scale
key,set the motor speed (for example 600rpm)according to operation 3,then press the
key and
strat the belt scale,let material fall. 3. Press the
monitoring the cumulation value key,observe the display value of Z1 or Z2.
When the value reach the amount of material calibration,press the
key ,stop material to fall.
Be careful:the material calibration must be not less than 1/20 of the belt scale maximum production per hour.
- 19 -
Hefei Jinshan 4.
Calculated correction
when the belt scale stop,the status is as shown in the dawing 1 of figure 32。Weigh total weight wich is fallen from belt start to belt stop this time,record total weight as W1. record the controller display cumulation as W2. The correction factor K2=W1/W2 If the absolute value of K2-1 is less than 1%,the calibration pass demand,no need to modify any parameter. If the Absolute value of K2-1 isn’t less than 1%,do follow steps: 1.
The original values of the parameter D06 multiplied by K2 and input the result to the parameter D06
again. 2.
6
have done the Real material calibration until the absolute value of K2-1 is less than 1% .
communications correction the primary fuction of communication correction is used for correcting analog output signal in system which have a host
computer. Interrelated step: Calling function list
6.1 Communications correction function Select OUTPUT Test
Please input Password. Password
Display “DO TEST
___111___
I/O output test
” DA1-DA7
OFF
I/O output don’t take out
DA1-DA7
ON
I/O output take out
Return Higher-level menu.
6.2 I/O input test Select DI TEST
Display “ RUN STOP SPEED P S “ When RUN have signal,the display of RUN will disappear,Etc. Return Higher-level menu.
6.3 Analog output test Select AO TEST - 20 -
Hefei Jinshan
when set DAC0-DAC1 4 mA,the current of DAC0 and DAC1 will be up to 4mA When DAC0 out put minimum current,check by multimeter whether the A0 analog terminal is equal to 4mA,if not,modify the E00 parameter and make it to be 4mA. When DAC1 out put minimum current,check by multimeter whether the A0 analog terminal is equal to 4mA,if not,modify the B04 parameter and make it to be 4mA. when set DAC0-DAC1 20 mA,the current of DAC0 and DAC1 will be up to20mA When DAC0 output maximum current,check by multimeter whether the A0 analog terminal is equal to 4mA,if not,modify the E01 parameter and make it to be 20mA. When DAC1 output maximum current,check by multimeter whether the A0 analog terminal is equal to 4mA,if not,modify the B05 parameter and make it to be 20mA. Return Higher-level menu.
Appendix 1:Replacement belt
figure 33 1.
Remove corresponding components on no motor side of belt scale,let the side hang in the air
2.
Screw off the screw of the tension sliding block on the side,and put the end of passive drum into inside.
3.
Screw off the fixed screw of the tension sliding block on the side,and remove it.
4.
Remove the long screw of the tension sliding block rest part. - 21 -
Hefei Jinshan 5.
move belt along the arrow of the drawing display.
6.
Replace new belt and setup the rest part by inverse order of steps.
Appendix 2:The use of lubricants model 1.
Recommend to use the special lubricant of 2*supramoly or 2L-2 Li radical , 90# Industrial gear oil in
reduction machine.before the belt scan run,you must check the smooth condition , maintain adequate lubrication and the filling volume of lubricant is the 1/3~1/2 empty volume of reduction machine. 2.
There are two filler well on the top of the reduction machine,and there are one screw plug on the bottom of
the reduction machine. 3.
The reduction machine lubricant should be replace once every 2,500 hours, appropriatily shorten the time of
replacing lubricant in the bad condition 4.
When the belt scale go out of factory,the reduction machine have be fillen with 2*supramoly,you need
appropriatily supply the lubricant after three month. 5.
The rest mechanical bearings of the belt scale only need be supplied with general lubricant.
- 22 -
Hefei Jinshan Appendix 3:The controller back panel terminal drawing
figure 34
- 23 -
Hefei Jinshan Appendix 4:Parameter table 1 Code
function
Initiali-zation
Unit
data A00
Setpoint mode
Configure mode
0
A01
Control mode
Control mode
0
A02
Speed mode
Measure speed mode
0
A03
Load_Max
Load max limit set
90
%
A04
Load_Min
Load min limit set
10
%
A05
Speed_Max
Speed max limit set
1200
rpm
A06
Speed_Min
Speed min limit set
300
rpm
A07
Par.ini
Initialization parameters
1
A08
BAK
backup
0
B00
Nominal Feed Rate
Rated flow
100
T/h
B01
Ex.Setpoint Min
External min signal value
4
mA
B02
Ex.setpoint Max
External max signal value
20
mA
B03
Ex.sp min
External signal threshold value
4
mA
B04
Flow_Out Min
flow output min value
4
mA
B05
Flow_Out Max
Flow output max value
20
mA
C00
Roller dia.
Drum diameter
C01
Speed Reducer
speed ratio
51
C02
Eff.Platf.Length
The effective Weigh length
0.45
m
C03
Gear Number
The number of measure speed gear
30
integer
teeth C04
Nominal Load
The load sensor standard range
100
kg
C05
Belt Length
Belt length
3.95
m
C06
Nominal Speed
Motor standard rotate speed
1500
rpm
D00
Calibrate load
Weigh weight
10
Kg
D01
Zero
Zero parameter
0
Sampling word
D02
Full
Full parameter
2000
Sampling word
D03
Tare
Belt weight parameter
0
Sampling word
D04
Test load
Test load
10
D05
Flow_K
Flow parameter
1
D06
Modify_K
Modify parameter
1
D07
N Circle Belt
Calibration laps
1
integer
D08
Load mode
Simulation load mode
0
integer
- 24 -
Kg
User settings
Hefei Jinshan Appendix 5:Parameter table 2 Code
function
Initialization
Unit
data E00
Ctronl_Out Min
The min value of control output
4
mA
E01
Ctronl_Out Max
The max value of control output
20
mA
E02
Filter constant
Filtering constant
10
integer
E03
DEAD
Dead area
0.1
%
E04
PID_K
Pid parameter
E05
YUZHI_PIANCHA
Preferences deviation
30
%
E06
MIN_PROTECT
Preferences protection
5
Kg
F00
ADDress
Communications address
1
F01
Baud Rate
Baudrate
1
F02
Mode
Communications mode
1
G00
PROFIBUS_ADDr
PROFIBUS address
1
G01
PROFIBUS_mode
PROFIBUS mode
0
H00
Ctronl_2 Min
Pre-feeding control min output
4
mA
H01
Ctronl_2 Max
Pre-feeding control max output
20
mA
H02
Pre_control_mode
Pre-feeding control mode
0
H03
Pre_Feed Rate
Pre-feeding machine capability
100
T/h
H04
Pre_control time
Preferences adjustment time
8
s
H05
PIANCHA limit
Deviation limit
40
%
H06
Pre_ctrl limit
Preferences adjustment limit
40
%
H07
P.C_limit_k
Limit parameter
1
H08
DEAD2
adjustment dead area
1
H09
PP1
P1 parameter
10
H10
PI1
I1 parameter
4
H11
PD1
D1 parameter
0
H12
PP2
P2 parameter
8
H13
PI2
I2 parameter
3
H14
PD2
D2 parameter
0
H15
PP3
P3 parameter
5
H16
PI3
I3 parameter
4
H17
PD3
D3 parameter
0
H18
time-lapse start
Delay time
1
technical support : 0551-3439417
- 25 -
%
s
User settings