Failure report stadium terengganu

January 3, 2018 | Author: Nurul Hidayah Amir | Category: Concrete, Strength Of Materials, Roof, Buckling, Structural Load
Share Embed Donate


Short Description

Something I did for APSC 150 Winter 2013 session....

Description

The University of British Columbia Engineering Failure Investigation Unit

Interdepartmental Memorandum

Date:

March 1, 2013

To:

APSC 150

From:

Dr. Hatzikiriakos, APSC 150 Coordinator

Subject: L 2E APSC 150 Failure of Tuanku Mizan Zainal Abidin (TMZA)Stadium Roof

1. Introduction This memo is a failure analysis Tuanku Mizan Zainal Abidin stadium roof. 60% of the roof collapsed first on 2nd June 2009 after about a year of its completion in 2008. (BERNAMA, 2009).A car is damaged but no injuries were reported during the incident but the failure could have easily harm many people since the capacity of the stadium is 50 000 (The Malay Mail, 2009).This report explains the chronology of events before and during the failures, causes of the failure and lessons to be learnt from the event.

2. Description of Failure TMZA Stadium is designed to have two shell-like roofs supported by concrete buttress and space trusses.Steel columns attached to concrete stumps support the space trusses along the roof while at its two ends, a concrete buttress at each is implemented. Between the end of the steel column and the buttress there exists a wide gap page 1 of 7

spanning more than 30 m. The truss consists of tubular and steel ball joints.(Amir Safuan, 2012) Prior to the collapse,they were reports of structure damage and sporadic loud bangs . In fact, a structural repair job was scheduled to be done on the day of the collapse. A year after opening ceremony, the roof collapsed during a day of typical Malaysian weather (hot and humid with temperature of about 28 Celcius). Roughly 60% of the roof including the section above the royal box collapsed. (Amir Safuan)

3. Reasons for the Failure Major issues includes mistakes at design level, inappropriate choice of materials, incompetency of staff involved in construction, poorly constructed roof, and lack of quality supervision. (The Star, 2009) The skills of the staff hired to construct the roof were inadequate as the roof structure was very complex. Subsequently, the quality of work was not up to standard as required by the design. Besides that, the long gap between the last concrete stump and the concrete buttress was about 30 m wide. There were not enough support for the large magnitude of force from its own weight. In addition to that, buckling occurred in the inclined members (tube), a sign of load exceeding buckling capacity. Pullout of threaded screws out of the

page 2 of 7

steel ball joints can also be observed after the incident. This means that they have been subjected to load beyond their capacities resulting in failure. (Amir Safuan , 2012)

1)The span between last concrete stump and the concrete buttress (Amir Safuan ,2012)

page 3 of 7

2)Buckling and damages in the steel trusses (Amir

page 4 of 7

3)The roof are ripped off the concrete stumps but the attachment base are still.intact (Amir Safuan 2012)

The complex design of the roof and the wide span required more detailed analysis .Other factors that contributed to the stated damage are defective welding in steel components implying poor workmanship and strength of the materials used did not achieve design requirement when tested in preliminary tests thus reducing the mechanical strength of the structure. The roof was also erected poorly causing terrible geometry and thus, catastrophic force distribution along the structure. Non-technical cause includes lack of quality control by project management team which causes mistakes to go unnoticed in page 5 of 7

their early stage. (Jeffrey CL.Chiang, 2010)

3. Lessons to be learnt Many of the failure causes can be eliminated if the engineers and workers comply with the ethical guidelines and prioritize the public safety instead of individual importance. More design proposals should be considered and determine whether or not it is within the capacities of the firm constructing the structure.. They should also have not do the parts they are not competent and outsource it to specialty companies. The project should be halted and alterations should be made as soon as any sign of weakness is observed during the project As engineers, we should also use suitable material instead of the ones that didn’t comply with the design need. Last but not least, quality inspection should be done from time to time to ensure the standards are followed.

4. References BERNAMA(2009) , The Malaysian National News Agency, Roof of Sultan Mizan Abidin Stadium collapses, 2 June 2009. Chiang, Jeffrey CL. (2010) . Quality Engineering Design and Construction in Malaysia: A Fast Disappearing and Endangered Commodity? JURUTERA Magazine Dec 2010 issue pp 35-36 Safuan, Amir (2012) The Collapse of Stadium Roof Pindaan 1 Sebab Dan Kesan Runtuh page 6 of 7

Bumbung Uitm Retrienved February 27 2013 from http://www.scribd.com/doc/104351335/The-CollapseStadium-Roof-Pindaan-1-Sebab-Dan-Kesan-Runtuh-BumbungUitm The Star (2011) Engineer Charged over Terengganu Stadium Collapse. Retrieved February 27 2013 from http://thestar.com.my/news/story.asp? sec=nation&file=/2011/1/31/nation/20110131172229 The Star (2011) Terengganu Opens East Coast's Largest Stadium Retrieved February 27 2013 from http://thestar.com.my/sports/story.asp? file=/2008/5/11/sports/20080511131 934&sec=sports The Malay Mail (2009) Terengganu Stadium Roof Collapses-After One Year of Being Built 2 June 2009

page 7 of 7

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF