The evolution of EPC contracting

BARON

Welcome to Welcome  to this presentation. It shows the evolution that took place in EPC contrcting schemes over the last 30 years.

Comments are most welcome ([email protected] ([email protected]), ), which I will incorporate for the benefit of all. Hervé

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contracting schemes EPC Contracts

Clients contracting strategy 

Phase 1

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE

Contracting schemes

BARON

Clients contracting strategy 

Phase 1 • EPCM • Re-imbursable

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

Contracting schemes

HERVE BARON

Clients contracting strategy 

Pro’s and Cont’ Cont ’s

Phase 1 • EPCM • Re-imbursable

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

Contracting schemes EPC Contracts

HERVE BARON

Clients contracting strategy 

Phase 1 • EPCM • Re-imbursable

Pro’s and Cont’ Cont ’s 

Phase 1 • All risks with Client • Budget and schedule slippage • Extensive supervision staff

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

Contracting schemes

HERVE BARON

Clients contracting strategy 

Phase 1 • EPCM • Re-imbursable

Pro’s and Cont’ Cont ’s 

Phase 1 • All risks with Client • Slippage budget and schedule • Extensive supervision staff



Phase 2

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

Contracting schemes

HERVE BARON

Clients contracting strategy 

Phase 1 • EPCM • Re-imbursable

Pro’s and Cont’ Cont ’s 

Phase 1 • All risks with Client • Slippage budget and schedule • Extensive supervision staff



Phase 2 • EPCM • LS E&P  

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

Contracting schemes EPC Contracts

HERVE BARON

Clients contracting strategy 

Phase 1 • EPCM • Re-imbursable

Pro’s and Cont’ Cont ’s 

Phase 1 • All risks with Client • Slippage budget and schedule • Extensive supervision staff



Phase 2 • EPCM • LS E&P  

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

Contracting schemes

HERVE BARON

Clients contracting strategy 

Phase 1

Pro’s and Cont’ Cont ’s 

Phase 1 • All risks with Client

• EPCM

• Slippage budget and schedule

• Re-imbursable

• Extensive supervision staff  

Phase 2

Phase 2

• EPCM

• Improvement over Phase 1 on schedule and budget

• LS E&P

• Extensive supervision staff  

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

Contracting schemes

HERVE BARON

Clients contracting strategy 

Phase 1

Pro’s and Cont’ Cont ’s 

Phase 1 • All risks with Client

• EPCM

• Slippage budget and schedule

• Re-imbursable

• Extensive supervision staff  

Phase 2

Phase 2

• EPCM

• Improvement over Phase 1 on schedule and budget

• LS E&P

• Extensive supervision staff  

 ©

What difference did Phase 2 bring compared to Phase 1 for

2   0  1   3  –  H   e  r   v 

Engineering development?

 é  B   a  r   o  n

 

Contracting schemes

HERVE BARON

Clients contracting strategy 

Pro’s and Cont’ Cont ’s 

Phase 1

• All risks with Client

• EPCM

• Slippage budget and schedule

• Re-imbursable

• Extensive supervision staff

Engineering continuum  

Phase 1

Phase 2

Phase 2

• EPCM

• Improvement over Phase 1 on schedule and budget

• LS E&P

• Extensive supervision staff FEED then CFT for EPC

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

Contracting schemes

HERVE BARON

Clients contracting strategy 

Phase 1

Pro’s and Cont’ Cont ’s 

Phase 1 • All risks with Client

• EPCM

• Slippage budget and schedule

• Re-imbursable

• Extensive supervision staff  

Phase 2

Phase 2

• EPCM

• Improvement over Phase 1 on schedule and budget

• LS E&P

• Extensive supervision staff  

 ©



Phase 3

2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

Contracting schemes

HERVE BARON

Clients contracting strategy 

Phase 1

Pro’s and Cont’ Cont ’s 

Phase 1 • All risks with Client

• EPCM

• Slippage budget and schedule

• Re-imbursable

• Extensive supervision staff  

Phase 2

Phase 2

• EPCM

• Improvement over Phase 1 on schedule and budget

• LS E&P

• Extensive supervision staff  

 ©



Phase 3 • LSTK

2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

Contracting schemes

HERVE BARON

Clients contracting strategy 

Phase 1

Pro’s and Cont’ Cont ’s 

Phase 1 • All risks with Client

• EPCM

• Slippage budget and schedule

• Re-imbursable

• Extensive supervision staff  

Phase 2

Phase 2

• EPCM

• Improvement over Phase 1 on schedule and budget

• LS E&P

• Extensive supervision staff  

 ©



Phase 3 • LSTK

2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

Contracting schemes

HERVE BARON

Clients contracting strategy 

Phase 1

Pro’s and Cont’ Cont ’s 

Phase 1 • All risks with Client

• EPCM

• Slippage budget and schedule

• Re-imbursable

• Extensive supervision staff  

Phase 2 • EPCM

• Improvement over Phase 1 on schedule and budget

• LS E&P

• Extensive supervision staff 



Phase 2

Phase 3 • LSTK

Phase 3 • All risks with Contract Contractor or

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

Contracting schemes

HERVE BARON

Clients contracting strategy 

Pro’s and Cont’ Cont ’s 

Phase 1

• All risks with Client

• EPCM

• Slippage budget and schedule

• Re-imbursable Less and less need for a PMC 

• Extensive supervision staff 

Phase 2

Phase 2

• EPCM

• Improvement over Phase 1 on schedule and budget

• LS E&P

• Extensive supervision staff 



Phase 1

Phase 3 • LSTK

Phase 3 • All risks with Contract Contractor or

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Contracting schemes EPC Contracts

Phase 3 • LSTK

How does the Contr Contractor actor mitigate risks?

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Contracting schemes EPC Contracts

Phase 3 • LSTK • Construction sub-contract

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Pro’s and Cont’ Cont ’s

Contracting schemes EPC Contracts

Phase 3 • LSTK • Construction sub-contract

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3 • LSTK

Pro’s and Cont’ Cont ’s 

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing

• Construction sub-contract

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3 • LSTK

Pro’s and Cont’ Cont ’s 

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing

• Construction sub-contract

2 different schemes: 3a and 3b

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3 • LSTK

Pro’s and Cont’ Cont ’s 

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing

• Construction sub-contract

• Phase 3a − General Construction Contractor

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3 • LSTK

Pro’s and Cont’ Cont ’s 

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing

• Construction sub-contract

• Phase 3a − General Construction Contractor

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3 • LSTK

Pro’s and Cont’ Cont ’s 

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing

• Construction sub-contract

• Phase 3a − General Construction Contractor

• Phase 3a − Reduced risk and supervision

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3 • LSTK

Pro’s and Cont’ Cont ’s 

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing

• Construction sub-contract

• Phase 3a − General Construction Contractor

• Phase 3a − Reduced risk and supervision

• Phase 3b – intense cost pressure  

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3

Pro’s and Cont’ Cont ’s 

• LSTK

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing

• Construction sub-contract

• Phase 3a − General Construction Contractor • Phase 3b – intense cost pressure Construction Sub− Multiple Contractors

• Phase 3a − Reduced risk and supervision

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3

Pro’s and Cont’ Cont ’s 

• LSTK

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing

• Construction sub-contract

• Phase 3a − General Construction Contractor • Phase 3b – intense cost pressure Construction Sub− Multiple Contractors

• Phase 3a − Reduced risk and supervision

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3

Pro’s and Cont’ Cont ’s 

• LSTK

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing

• Construction sub-contract

• Phase 3a − General Construction Contractor • Phase 3b – intense cost pressure Construction Sub− Multiple Contractors

• Phase 3a − Reduced risk and supervision

• Phase 3b competition − Increased − Extensive coordination  

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3 • LSTK

Pro’s and Cont’ Cont ’s 

Contracting schemes EPC Contracts

Phase 3

• Partial Partial risk  risk sharing

• Construction sub-contract

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3 • LSTK • Construction sub-contract

Pro’s and Cont’ Cont ’s 

Contracting schemes EPC Contracts

Phase 3

• Partial Partial risk  risk sharing

What usually happened?

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3 • LSTK • Construction sub-contract

Pro’s and Cont’ Cont ’s 

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing • E&P delays => Sub-contractor has to accelerate accelerate hence claims

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3 • LSTK • Construction sub-contract

Pro’s and Cont’ Cont ’s 

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing • E&P delays => Sub-contractor has to accelerate accelerate hence claims

What new scheme was introduced to mitigate?

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3 • LSTK • Construction sub-contract



Pro’s and Cont’ Cont ’s 

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing • E&P delays => Sub-contractor has to accelerate accelerate hence claims

Phase 4

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 

Phase 3



Phase 4

• LSTK • Construction sub-contract

Pro’s and Cont’ Cont ’s 

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing • E&P delays => Sub-contractor has to accelerate accelerate hence claims

• EP / C in Consortium or JV

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 



Phase 3

• LSTK • Construction sub-contract

Pro’s and Cont’ Cont ’s 

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing • E&P delays => Sub-contractor has to accelerate accelerate hence claims

Phase 4 • EP / C in Consortium or JV

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 



Pro’s and Cont’ Cont ’s

Phase 3



Phase 4



• LSTK • Construction sub-contract

• EP / C in Consortium or JV

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing • E&P delays => Sub-contractor has to accelerate accelerate hence claims

Phase 4 − Improved risk sharing − No claims − Less competitive

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

HERVE BARON

Contractor’s strategy 



Pro’s and Cont’ Cont ’s

Phase 3



Phase 4



• LSTK • Construction sub-contract

• EP / C in Consortium or JV

Contracting schemes EPC Contracts

Phase 3

• Partial risk sharing • E&P delays => Sub-contractor has to accelerate accelerate hence claims

Phase 4 − Improved risk sharing − No claims − Less competitive

 

 © 2   0  1   3  –  H   e  r   v 

Which scheme is better for COMPANY: 3 or 4? Why?

 é  B   a  r   o  n

 

HERVE

Typical EPC associations

BARON

 

 © 2   0  1   3  –  H   e  r   v   é  B   a  r   o  n

 

Going further

HERVE BARON

You enjoyed this presentation? Share my experience on other topics:  Engineering  Contract Management  Project Control Attend my classroom training Attend The list and schedule of coming sessions is on my blog at: 