DPWH Estimate Lecture...
Description
NVPILAR 2008
GENERAL GUIDELINES THIS DEPARTMENT ORDER SETS THE FORMULATION OF POLICIES, RULES AND PROCEDURES RELATIVE TO THE PREPARATION OF THE “APPROVED BUDGET FOR THE CONTRACT” (ABC) ISSUED FOR THE GUIDANCE OF ALL CONCERNED. ALL THE ITEMS OF WORK TO BE USED SHALL BE IN ACCORDANCE WITH DPWH STANDARD SPECIFICATIONS.
NVPILAR 2008
COST ESTIMATES (D0 57 S.2002)
INDIRECT COST
DIRECT COST
A. OVERHEAD EXPENSES – (6-7% CEILING) DIRECT COST. 1. ENGINEERING & ADMINISTRATIVE SUPERVISION 2. TRANSPORTATION ALLOWANCES 3. OFFICE EXPENSES (EQPT & SUPPLIES) 4. CONTRACTORS ALL RISK INSURANCE 5. FINANCING COST INCL. -PREMIUM ON BID SECURITY -PREMIUM ON PERFORMANCE SECURITY -PREMIUM/CHARGES ON CREDIT LINES -COST OF MONEY TO FINANCE THE PROJ.
A. COST OF MATERIALS
1. COST AT SOURCE, INCL. PROCESSING ROYALTIES, LOCAL TAXES & ETC. 2. EXPENSES FOR HAULING TO PROJ. SITE 3. HANDLING EXPENSES 4. STORAGE 5. ALLOWANCE FOR WASTE/OR LOSSES
B. COST OF LABOR
1. SALARIES & WAGES AS AUTHORIZED BY DOLE 2. FRINGE BENEFITS SUCH AS VACATION & SICK LEAVES, GSIS & SSS CONTR. ALLOWANCES, BONUSES AND ETC.
C. EQUIPMENT EXPENSES
1. RENTAL RATE SHALL BE BASED ON ACEL RATE AS APPRVD BY DPWH . OPERATED RENTAL RATE ARE PREFERRED OVER BARE RENTAL RATE 2. MOB./DEMOB OF EQUIPMENT SHALL BE ON CASE TO CASE BASIS BUT IN NO CASE EXCEED 1% OF TOTAL CIVIL WORK ITEMS.
B. CONTINGENCY – 3-5% OF DC. C. MISCELLANEOUS – 1% OF DC. INCLUDES LABORATORY TEST. D. CONTRACTORS PROFIT EST. DIRECT COST
OCM
PROFIT MOB/DEMOB MAX. TOTAL
UP TO P1M.
13
15
1
29
ABOVE P1M-5M
12
14
1
27
ABOVE P5M-10M
12
13
11
12
1 1
26
ABOVE P10M-20M ABOVE P20M-50M
11
11
1
23
ABOVE P50M
10
10
1
21
VAT
24
3-5% PM Fee NVPILAR 2008
“ THOSE WHO PREPARED/REVIEWED/CHECKED THE ESTIMATES SHALL SEE TO IT THAT IN CASE THEY ARE CALLED UPON TO MAKE GOOD THEIR ESTIMATES, THEY CAN PERFORM THE JOB THEMSELVES AT THE COST THEY HAVE GENERATED.”
NVPILAR 2008
PURPOSE THIS DEPARTMENT ORDER SETS THE GUIDELINES, RULES AND PROCEDURES, TO BE FOLLOWED BY ALL CONCERNED IN THE IMPLEMENTATION OF DEPARTMENT OF LABOR AND EMPLOYMENT D.O. No. 13(DOLE D.O. No.13), SERIES OF 1998 OTHERWISE KNOWN AS THE “GUIDELINES GOVERNING OCCUPATIONAL SAFETY AND HEALTH IN THE CONSTRUCTION INDUSTRY”, WITH EMPHASIS GIVEN ON THE METHODOLOGY TO BE USED IN ESTIMATING THE COST OF CONSTRUCTION SAFETY AND HEALTH PROGRAM AS REQUIRED IN SECTION 17. GENERAL GUIDELINES IN COMPLIANCE WITH SECTION 17 OF DOLE D.O. No. 13, THE IMPLENTATION OF CONSTRUCTION SAFETY SHALL BE CONSIDERED IN ALL STAGES OF PROJECT PROCUREMENT ( DESIGN, ESTIMATE, AND CONSTRUCTION ) AND ITS COST SHALL BE INTEGRATED TO THE OVERALL PROJECT COST UNDER PAY ITEM “SPLCONSTRUCTION SAFETY AND HEALTH” AS A LUMPSUM AMOUNT, TO BE QUANTIFIED IN THE DETAILED ESTIMATE. LIKEWISE, ALL REQUIREMENTS, PROVISIONS, AND INSTRUCTIONS PERTAINING TO THE IMPLEMENTATION OF CONSTRUCTION SAFETY AND HEALTH IN EVERY PROJECT SHALL BE INCLUDED IN THE PROJECT BIDDING DOCUMENTS SPECIFICALLY UNDER THE INSTRUCTION TO BIDDERS.
NVPILAR 2008
CONCTRUCTION PROJECT (D.O. No. 56 S. 2005) CONSTRUCTION SAFETY AND HEALTH PROGRAM ( CSHP ) THE REQUIRED CSHP FOR SPECIFIC PROJECT SHALL INCLUDE BUT NOT LIMITED TO THE FF : 1. COMPOSITION OF SAFETY & HEALTH PERSONNEL RESPONSIBLE FOR THE IMPLENTATION OF CSHP; 2. SPECIFIC SAFETY POLICIES W/C SHALL BE UNDERTAKEN IN THE CONSTRUCTION SITE INCLUDING FREQUENCY OF & PERSONS RESPONSIBLE FOR CONDUCTING TOOL BOX AND GANG MEETING; 3. PENALTIES AND SANCTIONS FOR VIOLATIONS OF THE CSHP; 4. FREQUENCY, CONTENT AND PERSONS RESPONSIBLE FOR ORIENTING, INSTRUCTING AND TRAINING ALL WORKERS AT THE SITE WITH REGARD TO THE CSHP WHICH THEY OPERATE; & 5. THE MANNER OF DISPOSING WASTE ARISING FROM THE CONSTRUCTION.
MANPOWER
1. SAFETY ENGINEER / OFFICER 2. SAFETY MAN / OFFICER -AS RECOMMENDED BY DOLE, FOR EVERY CONST. PROJ. W 100 & ABOVE WORKERS, AN ACCREDTED SAFETY OFFICER BY DOLE-BWC SHALL BE EMPLOYED. ONLY THE COST FOR THE CONST. SAFETY & HEALTH OFICER , WHETHER ON FULL OR PART TIME BASIS ASSIGNED ON SITE SHALL BE INCLUDED IN THE ESTIMATE. 3. HEALTH PERSONNEL -ONLY THE MEDICAL AND DENTAL PRACTITIONERS ACTUALLY ASSIGNED IN THE PROJECT SHALL BE INCLUDED IN THE COST OF SAFETY.
EQUIPMENT/FACILITIES
1. PERSONAL PROTECTIVE EQUPMENT (PPE) -FOR GENERAL CONST. THE REQUIRED BASIC PPE FOR ALL WORKERS SHALL BE SAFETY HELMET, SAFETY GLOVES AND SAFETY SHOES. SPECIALTY PPE SHALL BE PROVIDED IN ADDITION TO OR IN LIEU OF THE CORRESPONDING PPE AS THE WORK ACTIVITY REQUIRES. 2. SIGNAGES AND BARRICADES -SHALL BE PROVIDED AS A PRECAUTION TO ADVICE THE WORKERS & THE GENERAL PUBLIC OF THE HAZARDS EXISTING AT THE WORKSITE. 3. FACILITIES - W ADEQUTE SAFE DRINKING WATER; SANITARY & WASHING FACILITIES: LIVING ACCOMODATIONS FOR WORKERS.
COSTING PAY ITEM “SPL – CONSTRUCTION SAFETY AND HEALTH” AS A LUMP SUM AMOUNT, TO BE QUANTIFIED IN THE DETAILED ESTIMATE.
NVPILAR 2008
SAFE CONDITION
CAUTION OR RISK
NOTE : DERIVED FROM CPES MANUAL
MANDATORY ACTION
TRAFFIC AND HOUSEKEEPING
ALERT
STOP OR PROHIBITION
RADIATION
NVPILAR 2008
REFERENCE : SPECIFICATIONS DPWH STD.SPECS., VOL. I, 1988, ED. DPWH STD.SPECS.,VOL.II, 2004 ED. DPWH STD.SPECS.,VOL.III, 1995 ED.
BOOKS 1. ESTIMATING BILL OF MATERIALS BY VICENTE TAGAYUN 2. SIMPLIFIED CONSTRUCTION ESTIMATE BY MAX B. FAJARDO JR. 3. HANDBOOK OF CONSTRUCTION ESTIMATE BY RHENO A. VELASCO 4. PLUMBING DESIGN & ESTIMATE BY MAX B. FAJARDO JR. 5. ELECTRICAL LAYOUT & ESTIMATE BY MAX B. FAJARDO JR.
NVPILAR 2008
OTHER CODES AND SPECIFICATIONS: P.D.1096 – NATIONAL BUILDING CODE R.A. 7160 – LOCAL GOVT. CODE OF 1991 DOLE D.O. 13 SERIES 1998 – CONSTRUCTION SAFETY DPWH D.O. 56 SERIES 2005 – CONSTRUCTION SAFETY B.P. 344 – ACCESSIBILITY LAW NATIONAL STRUCTURAL CODE OF THE PHILIPPINES AMERICAN CONCRETE INSTITUTE ( ACI ) AMERICAN SOCIETY OF TESTING MATERIALS ( ASTM ) ELECTRICAL CODE OF THE PHILIPPINES PLUMBING CODE OF THE PHILIPPINES PHILIPPINE MECHANICAL ENGINEERING CODE ALL MATERIALS QUALITY TESTING CODE
NVPILAR 2008
NATIONAL BUILDING CODE
( P.D. 1096 ) 5 MAJOR DIVISIONS IN BUILDING PLANS SUBJECT TO ESTIMATE ARCHITECTURAL ARCHITECTURAL
AESTHETIC AESTHETIC
ARCHITECT ARCHITECT
STRUCTURAL STRUCTURAL
STRENGTH STRENGTH
CIVIL CIVILENGR ENGR
ELECTRICAL/ ELECTRICAL/ ELECTRONIC ELECTRONIC
POWER, POWER,LIGHTING LIGHTING & COMMUNICATION & COMMUNICATION
ELECTL ELECTLENGR/ ENGR/ ELECTRONIC ELECTRONICENGR ENGR
SANITARY/ SANITARY/ PLUMBING PLUMBING
HEALTH HEALTHAND AND SANITATION SANITATION
SANITARY SANITARYENGR/ ENGR/ MASTER MASTERPLUMBER PLUMBER
MECHANICAL MECHANICAL
NECESSITIES NECESSITIES
MECHANICAL MECHANICALENGR ENGR
NVPILAR 2008
CLASSIFICATION OF BUILDING STRUCTURES RESIDENTIAL – SINGLE DETACHED DWELLINGS AND DUPLEXES FOR USE OF OWNER, “ON CAMPUS” DORMITORIES, RECTORIES, CONVENTS AND MONASTERIES, RESIDENTIAL CONDOMINIUMS OWNED BY OCCUPANTS, ARMY BARRACKS, ETC. COMMERCIAL – SINGLE DETACHED DWELLINGS AND DUPLEXES FOR LEASE, BOARDING HOUSES, APARTMENTS, ACCESORIAS, HOTELS AND INNS, “OFF CAMPUS” DORMITORIES, TRANSPORTATION TERMINALS AND STATIONS, NIGHT CLUBS AND DANCE HALLS, RESTAURANTS, MARKETS AND SHOPPING CENTERS, THEATERS, SPORTS STADIA, GRANDSTANDS, GASOLINE SERVICE STATIONS, PARKING GARAGES, FUNERAL PARLORS, ETC. INDUSTRIAL – FACTORIES, PLANTS, MILLS, ARSENALS, BREWERIES, PROCESSING PLANTS, GAS GENERATING PLANTS, SHIPYARDS, AIRCRAFT HANGARS, SLIPWAYS, DRYDOCKS AND PIERS, LUMBER MILLS, WAREHOUSE, STORAGE TANKS, GRAIN AND CEMENT SILOS, ETC.
NVPILAR 2008
INSTITUTIONAL
–
EDUCATIONAL INSTITUTIONS, LIBRARIES, MUSEUMS, CLUBHOUSES, HOSPITALS, SANITARIA, ASYLUMS, HOMES FOR THE AGED, JAILS, POLICE AND FIRE STATIONS, PLACES OF WORSHIP, ETC.
RECREATIONAL
–
CINEMAS, BILLIARD HOUSES, ETC.
HALLS,
DISCO
PADS,
AGRICULTURAL
–
BARNS, POULTRY HOUSES, HATCHERIES, STABLES, GREENHOUSES, GRANARIES, ETC.
AMUSEMENT PIGGERIES,
ANCILLARY – GARAGES, CARPORTS, TANKS, TOWERS, SMOKESTACKS AND CHIMNEYS, VAULTS, SWIMMING POOLS, PELOTA COURTS, AVIARIES, AQUARIUMS, ZOO STRUCTURES, FIERE WALLS AND FENCES OVER 1.8O METERS IN HEIGHT, ETC. TEMPORARY – FIELD OFFICES, LABORERS’ QUARTERS, CANOPIES AND RAILINGS, PROTECTIVE FENCINGS, ETC. OTHERS – CEMETERY STRUCTURES AND MOUSOLEUMS, TOMBS, MULTI-LEVEL NICHES, ETC.
NVPILAR 2008
TYPES OF CONSTRUCTION ( P.D. 1096, CHAPTER 4, SECTION 401 )
TYPE I - TYPE I BUILDING SHALL BE OF WOOD CONSTRUCTION. THE STRUCTURAL ELEMENTS MAY BE ANY OF THE MATERIALS PERMITTED BY THIS CODE. TYPE II - TYPE II BUILDING SHALL BE OF WOOD CONSTRUCTION WITH PROTECTIVE FIRE RESISTANT MATERIALS AND ONE-HOUR FIRE RESISTIVE THROUGHOUT: EXCEPT, THAT PERMANENT NON-BEARING PARTITIONS MAY USE FIRE-RETARDANT TREATED WOOD WITHIN THE FRAMING ASSEMBLY. TYPE III – TYPE III BUILDING SHALL BE OF MASONRY AND WOOD CONSTRUCTION, STRUCTURAL ELEMENTS MAY BE ANY OF THE MATERIALS PERMITTED BY THIS CODE: PROVIDED, THAT THE BUILDING SHALL BE ONE-HOUR FIRE – RESISTIVE THROUGHOUT. EXTERIOR WALLS SHALL BE INCOMBUSTIBLE FIRE-RESISTIVE CONSTRUCTION TYPE IV – TYPE IV BUILDING SHALL BE OF STEEL, IRON, CONCRETE OR MASONRY CONSTRUCTION. WALLS, CEILING AND PERMANENT PARTITIONS SHALL BE OF INCOMBUSTIBLE FIRE RESISTIVE CONSTRUCTION: EXCEPT, THAT PERMANENT NON-BEARING PARTITIONS OF ONE-HOUR FIRE RESISTIVE CONSTRUCTION MAY USE FIRE RETARTANT TREATED WOOD WITHIN THE FRAMING ASSEMBLY. TYPE V - TYPE V BUILDING SHALL BE FIRE-RESISTIVE. THE STRUCTURAL ELEMENTS SHALL BE OF STEEL, IRON, CONCRETE, OR MASONRY CONSTRUCTION. WALLS, CEILING AND PERMANENT PARTITIONS SHALL BE OF INCOMBUSTIBLE FIRE-RESISTIVE CONSTRUCTION.
NVPILAR 2008
BURJ DUBAI ( DUBAI TOWER ) THE BURJ DUBAI IS A SUPERTALL SKYSCRAPER CURRENTLY UNDER CONSTRUCTION IN DUBAI, UNITED ARAB EMIRATES. IT IS CURRENTLY THE TALLEST FREE STANDING STRUCTURES IN THE WORLD HAVING AN EXPECTED HEIGHT OF 818 METERS BUT COULD REACH UP TO 940 METERS UPON THE SCHEDULED COMPLETION IN SEPTEMBER 2009. THE BUILDING IS BEING BUILT BY A JOINT VENTURE OF THE SOUTH KOREAN COMPANY SAMSUNG, THE BELGIAN COMPANY BESIX AND THE UAE COMPANY ARABTEC. IT WAS DESIGN BY ADRIAN SMITH OF SKIDMORE, OWING AND MERRIL CONSULTANCY. THE TOTAL BUDGET FOR THE BURJ DUBAI PROJECT IS ABOUT 4.1 BILLION DOLLARS. *PICTURE & INFO FROM INTERNET
NVPILAR 2008
SCOPE OF WORKS IN BUILDING CONSTRUCTION PART -
A-
MOBILIZATION
PART -
B-
EARTHWORKS
PART -
C-
TERMITE CONTROL & WOOD PRESERVATIONS
PART -
D-
FOUNDATION WORKS
PART -
E-
DAMP PROOFING / MOISTURE CONTROL
PART -
F-
CONCRETE WORKS
PART -
G-
MASONRY WORKS
PART -
H-
CARPENTRY WORKS
PART -
I -
FABRICATED MATERIALS AND HARDWARE
PART -
J-
ROOF FRAMING WORKS
PART -
K-
ROOFING WORKS
PART -
L-
FINISHES
PART -
M - PAINTING / VARNISHING
PART -
N-
WATER PROOFING
PART -
O-
SANITARY WORKS
PART -
P-
ELECTRICAL WORKS
PART -
Q-
MECHANICAL WORKS
PART -
R-
CONSTRUCTION SAFETY AND HEALTH (DO. 56)
NVPILAR 2008
PROJECT: ONE(1) STOREY (7X7 MODIFIED) CLASSROOM SCHOOL BUILDING
ARCHITECTURAL PLAN 1
2
2
3
3
GA 26 CORR. G I. ROOFING
D-1 W-1
2
W-2
W-2
B
A
D-1
W-1
B D-1
CORRIDOR
FLOOR PLAN *PLANS BY BOD
2
W-2
1
3
CROSS SECTION 2
3
SCH. OF DOORS & WINDOWS
C
C
CLASSROOM W-1
1
W-2 CLASSROOM
REAR ELEVATION
3
W-2
C
D-1
FRONT ELEVATION 1
B
GA 26 CORR. G I. ROOFING
D-1 W-1
C
A
1
EXPOSED STEEL ‘C’ PURLINS AND RAFTERS
SLOPE
B SLOPE
A
A REFLECTED CEILING
D-1
FLUSH TYPE HOLLOW CORE DOOR W MARINE PLYWOOD FACING ON WOOD FRAME
W-1 & W-2
GLASS JALOUSIE WINDOWS ON ALUMINUM HOUSIG
ROOF PLAN NVPILAR 2008
STRUCTURAL PLAN B
A
RAFTER
C
ANGULAR BRACE CORR. GI SHEETS C1-F1
COL. FTG.
C1-F1
CLASSROOM WELL COMPACTED GRAVEL FILL
DETAIL CROSS SECTION
FGL NGL
WF-1
CORRIDOR DOWEL
W-2
SLAB ON FILL
WF-1
D-1
WF-1
LB
BASE PLATE W LONG ANCHOR BOLTS ROOF INSULATION CEILING FIN. COMPRESSED BETWEEN PURLINS AND RAFTER
WF-1
FFL
WALL FTG
*PLANS BY BOD
COLUMN
WF-1 C1-F1
C1-F1
C1-F1
FOUNDATION PLAN
LINTEL BEAM FOOTING
WF-1
WF-1
WF-1
LB
C1-F1
C1-F1
C1-F1
C-PURLINS
WALL FOOTING
SPOT DETAIL LINTEL BEAMS NVPILAR 2008
PLUMBING AND SANITARY CYCLE ( ONE STOREY STRUCTURE ) HORIZONTAL VENT PIPE
VENT PIPE THRU ROOF
LAVATORY
WATER CLOSET
KITCHEN SINK
SHOWER
IN-HOUSE WATER SUPPLY PIPE
ROOF GUTTER
DOWNSPOUT
WATER METER
CATCH BASIN
GATE VALVE
SEPTIC VAULT
METER SHUT-OFF WATER PIPE CONN. TO WATER MAIN
TO DRAINAGE CANAL/SEWER CORPORATION COCK
CATCH BASIN
CLEANOUT
SOIL/WASTE PIPE
STORM DRAINAGE PIPE
WATER MAIN
*PICTURE FROM BOOKS OF TAGAYUN
NVPILAR 2008
PLUMBING SYSTEM
WATER LINE INCLUDING DRAINAGE, WASTE AND VENTILATION SYSTEM OF BUILDING VENTILATION THROUGH ROOF ( VTR ) DRY VENT
SHOWER W/ ACCESORIES
MAIN VENT
BATH TUB
HOT WATER RETURN
LAVATORIES FIXTURES
WATER CLOSET FLOOR DRAIN
KITCHEN SINK FIXTURES COLD WATER LINE W/ ACCESORIES HOT WATER LINE W/ ACCESSORIES WATER HEATER
*PICTURE FROM BOOKS OF FAJARDO.
WET VENT
FITTINGS CLEAN OUT WASTE / SOIL PIPE
NVPILAR 2008
ELECTRICAL SYSTEM LAYOUT ( ONE STOREY STRUCTURES )
LIGHTING LAYOUT
CONVENIENCE OUTLET LAYOUT
PANEL BOARD & CABINETS
*PICTURE FROM BOOKS OF FAJARDO.
NVPILAR 2008
PREPARATION OF PROGRAM OF WORKS CONST. OF ONE STOREY SCHOOL BUILDING 2
3
GA 26 CORR. G I. ROOFING
GA 26 CORR. G I. ROOFING
D-1
D-1
W-2
CLASSROOM
CROSS SECTION
2
3
C
W-2
B
CLASSROOM
A
CORRIDOR
FLOOR PLAN
2.29
6,870.00
III. SOIL POISONING
0.56
1,680.00
IV. DAMPROOFING WORKS
0.47
1,410.00
29.65
88,950.00
3.21
9,630.00
VII. CARPENTRY WORKS
3.54
10,620.00
VIII. FAB. MATERIALS & HARDWARE
9.08
27,240.00
IX. ROOF FRAMING WORKS
9.87
29610.00
X.
7.20
21,600.00
12.23
36,690.00
XII. PAINTING WORKS
6.50
19,500.00
XIII. SANITARY / PLUMBING WORKS
4.06
12,180.00
XIV. ELECTRICAL WORKS
5.34
16,020.00
XV. MECHANICAL WORKS
5.00
15,000.00
SLAB ON FILL WF-1
C1-F1
WF-1
C1-F1
C1-F1
SCH. OF DOORS & WINDOWS
W-2
D-1 W-1 W-1 D-1
EARTHWORKS
P3,000.00
VI. MASONRY WORKS
FOUNDATION PLAN 1
II.
1.0
V.
C1-F1
C
MOBILIZATION / DEMOBILIZATION
AMOUNT
C1-F1 C1-F1 C1-F1 WF-1 WF-1 WF-1
B
REAR ELEVATION
WF-1
FRONT ELEVATION A
W-2
W-2
WF-1
W-1
W-1
I.
%
C1-F1
D-1
SCOPE OF WORKS
1
2
3
WF-1
1
D-1
W-1 & W-2
FLUSH TYPE GLASS JALOUSIE HOLLOW CORE WINDOWS ON DOOR W MARINE ALUMINUM HOUSING PLYWOOD FACING ON WOOD FRAME
CONCRETE WORKS
ROOFING WORKS
XI. FINISHES
TOTAL
100.00
300,000.00
NVPILAR 2008
BUILDING CONSTRUCTION METHODOLOGY ( BY PERT/CPM DIAGRAM)
PROJECT: ONE(1) STOREY (7m X 7m) MODIFIED SCHOOL BUILDING PROCUREMENT/DELIVERY OF CONSTRUCTION MATERIALS
D
26 ELECTRICAL/SANITARY ROUGH-IN
14
J
16
INST. ELECT/ MECH/SANITARY FIXTURES
12
CARPENTRY WORKS
1
2
MOVEIN
A
2
EARTH WORKS
B
2
6
4
CONCRETE WORKS
C
WAIT
F
5
MASONRY WORKS
3
WAIT
E
8
H
ROOF FRAMING
5
1
SOIL POISONING
5
3
INST. OF PURLINS WAIT
I
ROOFING
4
2
K
2
BACKFILL
M
W
3
9
O
1
13
1O
N
15
FINISHES WAIT
WAIT
WAIT
G
P
2
4
PAINTING
3
4
R
2
Q
T
S
17
MOVE OUT
2
V
U
INST. FAB. MATLS & HARDWARE
INST. GUTTER & FLUSHING
14
11
DAMPROOFING/SLAB ON FILL
7
1
2
3
4
5
6
7
8
9
10
LEGEND: NETWORK -
ES
A
LS
EF
B
11
12
13
14 15 16 17 CALENDAR DAYS
18
19
20
21
22
23
24
25
26
27
28
29
30
LF
ACTIVITY EVENT -
ES
A
LS
DUMMY CRITICAL PATH -
NVPILAR 2008
SCOPE OF WORKS
WT.(%)
AMOUNT (PHP)
I. MOBILIZATION/DEMOB
1.00
3,000.00
II. EARTHWORKS
2.29
6,870.00
III. SOIL POISONING
0.56
1,680.00
IV. DAMP PROOFING WORKS
0.47
1,410.00
V. CONCRETE WORKS
29.65
88,950.00
VI. MASONRY WORKS
3.21
9,630.00
VII. CARPENTRY WORKS
3.54
10,620.00
VIII. FAB. MATLS & H’WARE
9.08
10,620.00
IX. ROOF FRAMING WORKS
9.87
27,240.00
X. ROOFING WORKS
7.20
29,610.00
12.23
21,600.00
XII. PAINTING WORKS
6.50
36,690.00
XIII. SANITARY WORKS
4.06
19,500.00
XIV. ELECTRICAL WORKS
5.34
16,020.00
XV. MECHANICAL WORKS
5.00
15,000.00
100.00
300,000.00
XI. FINISHES
TOTAL
CALENDAR DAYS 5
10
15
20
25
30
PROJECTED CASH FLOW (P) PROJECTED ACCPLMENT (%) CUMMULATIVE CASH FLOW(P) CUMMULATIVE ACCPLMNT(%) - CRITICAL ACTIVITY - PARALLEL ACTIVITY
NVPILAR 2008
SCOPE OF WORKS
WT.(%)
CALENDAR DAYS
AMOUNT (PHP)
5
I. MOBILIZATION/DEMOB
1.00
3,000.00
1,500.00
II. EARTHWORKS
2.29
6,870.00
3,435.00
III. SOIL POISONING
0.56
1,680.00
1,680.00
IV. DAMP PROOFING WORKS
0.47
1,410.00
10
15
20
25
30 1,500.00
3,435.00 1,410.00
88,950.00 11,118.75 44,475.00 33,356.25
V. CONCRETE WORKS
29.65
VI. MASONRY WORKS
3.21
9,630.00
VII. CARPENTRY WORKS
3.54
10,620.00
10,620.00
VIII. FAB. MATLS & H’WARE
9.08
10,620.00
13,620.00 13,620.00
IX. ROOF FRAMING WORKS
9.87
27,240.00
17,766.00
11,844.00
X. ROOFING WORKS
7.20
29,610.00
16,200.00
5,400.00
12.23
21,600.00
XII. PAINTING WORKS
6.50
36,690.00
XIII. SANITARY WORKS
4.06
19,500.00
676.67
3,383.33
3,383.33
3,383.33
1,353.34
XIV. ELECTRICAL WORKS
5.34
16,020.00
890.00
4,450.00
4,450.00
4,450.00
1,780.00
XV. MECHANICAL WORKS
5.00
15,000.00
833.33
4,166.67
4,166.67
4,166.67
1,666.66
100.00
300,000.00
XI. FINISHES
TOTAL
3,210.00
6,420.00
36,690.00 19,500.00
PROJECTED CASH FLOW (P)
17,733.75 53,520.00
PROJECTED ACCPLMENT (%)
30.06 17.84 17.73 15.32 13.14 5.91 17,733.75 71,253.75 124,440.00 170406.00 260,580.00 300,000.00
CUMMULATIVE CASH FLOW(P) CUMMULATIVE ACCPLMNT(%)
5.91
23.75
53,186.25 45,966.00 90,174.00 39,420.00
41.48
56.80
86.86
100.00
NVPILAR 2008
SCOPE OF WORKS
WT.(%)
AMOUNT (PHP)
I. MOBILIZATION/DEMOB
1.00
3,000.00
II. EARTHWORKS
2.29
6,870.00
III. SOIL POISONING
0.56
1,680.00
IV. DAMP PROOFING WORKS
0.47
1,410.00
V. CONCRETE WORKS
29.65
88,950.00
VI. MASONRY WORKS
3.21
9,630.00
VII. CARPENTRY WORKS
3.54
10,620.00
VIII. FAB. MATLS & H’WARE
9.08
10,620.00
IX. ROOF FRAMING WORKS
9.87
27,240.00
X. ROOFING WORKS
7.20
29,610.00
12.23
21,600.00
XII. PAINTING WORKS
6.50
36,690.00
XIII. SANITARY WORKS
4.06
19,500.00
XIV. ELECTRICAL WORKS
5.34
16,020.00
XV. MECHANICAL WORKS
5.00
15,000.00
100.00
300,000.00
XI. FINISHES
TOTAL
CALENDAR DAYS 5
10
15
20
25
30
100%
86.86 75%
ACTUAL ACCOMPLISHMENT 56.80
50% 41.48
TIME ELAPSED
SCHEDULED ACCOMPLIHMENT
25%
23.75
5.91
PROJECTED CASH FLOW (P)
17,733.75 53,520.00
PROJECTED ACCPLMENT (%)
30.06 17.84 17.73 15.32 13.14 5.91 17,733.75 71,253.75 124,440.00 170406.00 260,580.00 300,000.00
CUMMULATIVE CASH FLOW(P) CUMMULATIVE ACCPLMNT(%)
5.91
23.75
53,186.25 45,966.00 90,174.00 39,420.00
41.48
56.80
86.86
100.00
NVPILAR 2008
MANPOWER RES. ENGINEER CONST. FOREMAN
RATE/DAY
TOTAL AMOUNT
CALENDAR DAYS 10 15
5
25
30
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
CARPENTER
1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2
MASON
1 1
LEADMAN
20
STEEL MAN
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2
2 2
2 2 2 2 2 2 2 2 2 2 2 2
2 2 2
2 2 2 2
2 2 2 2 2 2 2
WELDER TINSMITH
2 2 2 2 2 2 2
PAINTER
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
PLUMBER
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
ELECTRICIAN LABORER
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
SAFETY OFFICER FIRST AIDER NURSES TOTAL
8 8 6 6
131313 1314 10 10 10 1616 101010 10 10 101012121212121210 8 6
NVPILAR 2008
EQUIPTMENT MINOR TOOL ACC. C0NCRETE MIXER
RATE/DAY
TOTAL AMOUNT
5
CALENDAR DAYS 10 15
30
1 1 1 1
CONC. VIBRATOR BAR BENDER
1 1 1 1 1 1 1 1 1
WELDING MACHINE
25
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
BAR CUTTER
20
1 1 1
1 1 1 1 1
TOTAL
NVPILAR 2008
MANPOWER REQUIREMENT
TECHNICAL
PROJECT ENGINEER RESIDENT ENGINEER
SAFETY & HEALTH (DO 56 S.2005)
SAFETY ENGINEER SAFETY OFFICER FIRST AIDER NURSES
SKILLED / UNSKILLED
CONST. FOREMAN LEADMAN
ELECTRICAL ENGINEER
CARPENTER MASON STEEL MAN WELDER TINSMITH
MECHANICAL ENGINEER
INSTALLER
MTQC ENGINEER QTY./COST ENGINEER SANITARY ENGINEER
PAINTER PLUMBER ELECTRICIAN LABORER
NVPILAR 2008
NVPILAR 2008
PILE FOUNDATION DRILLING, DRIVING, BORING, GRABBING EQUIPMENT
SMALL DRILLING EQPT. USE FOR MICRO PILES
EXCAVATOR-USE IN LARGE DIMENSION EXCAVATION & DIGGING
DROP HAMMER DRIVING HEAVY BORING RIG W/ VIBRO RIG FOR PRE CAST PILES HAMMER FOR BORED PILES
TRUCK MIXER TANDEM WITH PUMPCRETE USE IN POURING OF HEAVY FOUNDATIONS.
WHEEL LOADER TANDEM W/ DUMP TRUCK -USE FOR HAULING & DISPOSAL OF DEBRIS AND OTHER EXCAVATED MATERIALS.
HEAVY CABLE GRAB FOR BARRETTE PILES
TRUCK MOUNTED/CRAWLER CRANE -USE TO CARRY & MANEUVER PRE CAST PILE & STEEL CAGES.
GENERATOR SET / WELDING MACHINE – USE AS CONNECTORS ON HEAVY STRUCTURAL STEEL MEMBERS. NVPILAR 2008
MOBILE CRANES – USE TO MANEUVER AROUND & OUTSIDE THE BUILDING TO HOIST MATERIALS & EQUIPMENT FROM VARIOUS LOCATIONS
WHEEL LOADER TANDEM W/ DUMP TRUCK-USE FOR HAULING & DISPOSAL OF DEBRIS AND OTHER MATERIALS WITHIN THE PERIPHERAL OF THE BUILDINGS
TRUCK MIXER TANDEM WITH PUMPCRETE USE IN POURING OF HEAVY SUPERSTRUCTURE MEMBERS.
TOWER CRANE – USE AS CIRCUMFERENTIAL LIFTING MECHANISM TO TRANSPORT VITAL CONSTRUCTION MATERIALS & EQUIPMENT
FORMS & SCAFFOLDING – USE AS GUIDE & SUPPORT SYSTEM IN FORMING & CHECKING ALIGNMENT OF STRUCTURAL MEMBERS IN & AROUND THE BUILDINGS.
GENERATOR SET / WELDING MACHINE – USE AS CONNECTORS ON HEAVY STRUCTURAL STEEL MEMBERS.
NVPILAR 2008
WHEEL LOADER
ROLLER
EXCAVATOR/BREAKER
TRUCK MIXER
BULLDOZER
TRAILER TRUCK
GRADER
DUMP TRUCK
NVPILAR 2008
SAMPLING MOLD
BAR CUTTER
1- BAGGER CONCRETE MIXER
2 – BAGGER CONCRETE MIXER
PLATE COMPACTOR
CONCRETE VIBRATOR
TAMPING RAMMER
PORTA LIFT
RING AND BAR BENDER
HOLLOW BLOCK MACHINE
WALK BEHIND ROLLER
SUBMERSIBLE PUMP NVPILAR 2008
NVPILAR 2008
LABOR COST DISTRIBUTION (BUILDING ESTIMATE)
SCOPE OF WORKS
A. MOBILIZATION / DEMOB. B. EARTHWORKS a) Excavation / Backfill
%LABOR OF MAT’LS. (APPROXIMATE)
MANDAYS
1% OF DC
-
b) Earth fill
30 %
c) Gravel
30 %
C. TERMITE CONTROL / WOOD PRESERVATION a) Soil Poisoning
30 %
b) Wood Preservation
30 %
NVPILAR 2008
LABOR COST DISTRIBUTION (BUILDING ESTIMATE)
SCOPE OF WORKS
%LABOR OF MAT’LS. (APPROXIMATE)
MANDAYS
D. FOUNDATION WORKS 1. SHALLOW FOUNDATION a) Spread
30 %
b) Mat
30 %
c) Raft
30 %
2. DEEP FOUNDATION a) Micro Piles
30 %
b) Pre-Cast Driven Piles
30 %
c) Bored Piles
30 %
d) Barrette Piles
30 %
NVPILAR 2008
LABOR COST DISTRIBUTION (BUILDING ESTIMATE)
SCOPE OF WORKS
E. DAMP PROOFING / MOISTURE CONTROL a) On Ground b) Below Ground F. CONCRETE WORKS a) Concrete a.1) Ready Mix a.2) Job Mix
%LABOR OF MAT’LS. (APPROXIMATE)
MANDAYS
30 % 30 %
10 – 15 % 30 %
b) Re-bars
30 %
c) Formworks
30 %
NVPILAR 2008
LABOR COST DISTRIBUTION (BUILDING ESTIMATE)
SCOPE OF WORKS
%LABOR OF MAT’LS. (APPROXIMATE)
G. MASONRY WORKS a) Concrete Hollow Blocks
30 %
H. CARPENTRY WORKS a) Ceiling
30 %
b) Partitions
30 %
c) Wooden Framing
30 %
d) Stairs
30 %
e) Cabinets
30 %
MANDAYS
NVPILAR 2008
LABOR COST DISTRIBUTION (BUILDING ESTIMATE)
SCOPE OF WORKS
H. FABRICATED MAT’LS AND HARDWARES a) Doors b) Windows
%LABOR OF MAT’LS. (APPROXIMATE)
MANDAYS
30% Fab. + 10% Inst. 30% Fab. + 10% Inst.
c) Hardware Accessories 30% I. ROOF FRAMING WORKS 1. Timber Trusses
30%
2. Steel Trusses a) Fabrication
30%
b) Installation/Erection
20%
c) Equipment
10 - 25 %
d) Consumables e) Painting
8% 7%
NVPILAR 2008
LABOR COST DISTRIBUTION (BUILDING ESTIMATE)
SCOPE OF WORKS
%LABOR OF MAT’LS. (APPROXIMATE)
K. ROOFING WORKS a) Roofing Mat’ls & acc.
30 %
L. FINISHES
30 - 35 %
MANDAYS
M. PAINTING / VARNISHING a) Masonry Paint
30 %
b) Wooden Paint
30 %
c) Metal Paint
30 %
d) Varnishing
30 %
NVPILAR 2008
LABOR COST DISTRIBUTION (BUILDING ESTIMATE)
SCOPE OF WORKS
N. WATERPROOFING a) Cement Base (Integral)
%LABOR OF MAT’LS. (APPROXIMATE)
30 %
b) Membrane Waterproofing
30 %
c) Liquid Waterproofing
30 %
d) Hydrolithic Waterproofing
30 %
O. SANITARY WORKS a) Plumbing Lines
MANDAYS
30 %
b) Drainage, Waste & Vent
30 %
c) Fixtures & Accessories
15 %
NVPILAR 2008
LABOR COST DISTRIBUTION (BUILDING ESTIMATE)
SCOPE OF WORKS
%LABOR OF MAT’LS. (APPROXIMATE)
MANDAYS
P. ELECTRICAL WORKS a) Wires & wiring
30 %
b) Conduit works
30 %
c) Panel boards & Cabinets
5%
d) Fixtures & Accessories
10 %
NVPILAR 2008
LABOR COST DISTRIBUTION (BUILDING ESTIMATE)
SCOPE OF WORKS
%LABOR OF MAT’LS. (APPROXIMATE)
MANDAYS
Q. MECHANICAL WORKS a) Airconditioning & Refrigeration System
10% - Labor(Acc.) 15% - Inst. of units
b) Water Pump
30% - Labor (Pipes & fit.) 15% - Inst. of units
c) Automatic Water Sprinkler System
30% - Labor (Pipes & fit.) 15% - Inst. Of units
d) Electric Elevators
30%
e) Electric Dumbwaiter
30%
NVPILAR 2008
SCOPE OF WORKS IN BUILDING CONSTRUCTION PART -
A-
MOBILIZATION
PART -
B-
EARTHWORKS
PART -
C-
TERMITE CONTROL & WOOD PRESERVATIONS
PART -
D-
FOUNDATION WORKS
PART -
E-
DAMP PROOFING / MOISTURE CONTROL
PART -
F-
CONCRETE WORKS
PART -
G-
MASONRY WORKS
PART -
H-
CARPENTRY WORKS
PART -
I -
FABRICATED MATERIALS AND HARDWARE
PART -
J-
ROOF FRAMING WORKS
PART -
K-
ROOFING WORKS
PART -
L-
FINISHES
PART -
M - PAINTING / VARNISHING
PART -
N-
WATER PROOFING
PART -
O-
SANITARY WORKS
PART -
P-
ELECTRICAL WORKS
PART -
Q-
MECHANICAL WORKS
PART -
R-
CONSTRUCTION SAFETY AND HEALTH (DO. 56)
NVPILAR 2008
DPWH STD. SPECS., VOL. I, 1988, ED. DPWH STD.SPECS.,VOL.II, 2004 ED. DPWH STD.SPECS.,VOL.III, 1995 ED.
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART A – MOBILIZATION - M0VING IN OF MANPOWER, EQUIPTMENT & MATERIALS AT THE PROJECT SITE PART A – FACILITIES F0R THE ENGINEER A.1.1- OFFICES & LABORATORIES
- L.S.
A.1.2- VEHICLES FOR THE ENGINEER
- MO./ EACH
A.1.3- ASSISTANCE TO THE ENGINEER
- MONTHS
A.1.4- PHOTOGRAPHS
- EACH
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART B - EARTHWORKS ITEM 800 – CLEARING & GRUBBING
- CU. M.
ITEM 801 – REMOVAL OF STRUCTURES & OBSTRUCTIONS
- CU. M.
ITEM 802 – EXCAVATION
- CU. M.
ITEM 803 – STRUCTURE EXCAVATION
- CU. M.
ITEM 804 – EMBANKMENT
- CU. M.
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART C – TERMITE CONTROL & WOOD PRESERVATION ITEM 1000(A) – SOIL POISONING
- LITER
ITEM 1000(B) – WOOD PRESERVATION
- LITER
ITEM 1000(C) – POWDER TERMICIDE
- KILOGRAMS
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART D – FOUNDATION WORKS
ITEM 400(1) – UNTREATED TIMBER PILES, FURNISHED
- METER
ITEM 400(2) – TREATED TIMBER PILES, PRESERVATIVE, FURNISHED
- METER
ITEM 400(3) – STEEL H-PILES, FURNISHED
- METER
ITEM 400(4) – PRECAST CONCRETE PILES, FURNISHED
- METER
ITEM 400(5) – PRECAST, PRESTRESSED CONCRETE PILES, FURNISHED
- METER
ITEM 400(6) – STRUCTURAL STEEL SHEET PILES, FURNISHED
- METER
ITEM 400(7) – PRECAST CONCRETE SHEET PILES, FURNISHED
- METER
ITEM 400(8) – UNTREATED TIMBER PILES, DRIVEN
- METER
ITEM 400(9) – TREATED TIMBER PILES, DRIVEN
- METER
ITEM 400(10) – STEEL H-PILES, DRIVEN
- METER
ITEM 400(11) – STEEL PIPES PILES
- METER
ITEM 400(12) – STRUCTURAL STEEL SHEET PILES, DRIVEN
- METER
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
ITEM 400(13) – PRECAST CONCRETE SHEET PILES, DRIVEN
- METER
ITEM 400(14) – PRECAST CONCRETE PILES, DRIVEN
- METER
ITEM 400(15) – PRECAST, PRESTRESSED CONCRETE PILES, DRIVEN
- METER
ITEM 400(16) – TEST PILES, FURNISHED AND DRIVEN
- METER
ITEM 400(17) – CONCRETE PILES CAST IN DRILLED HOLES
- METER
ITEM 400(18) – CONCRETE PILES CAST IN STEEL SHELLS
- METER
ITEM 400(19) – CONCRETE PILES CAST IN STEEL PIPES
- METER
ITEM 400(20) – PILE SHOES
- METER
ITEM 400(21) – SPLICES
- METER
ITEM 400(22) – LOAD TEST
- METER
ITEM 400(23) – BORED PILES (DIA___ M)
- METER
ITEM 400(24) – PERMANENT CASING (DIA___M)
- METER
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART E – DAMP PROOFING/MOISTURE CONTROL SPL (1) – POLYETHELENE SHEETS
- SQ. M.
SPL (2) – HYDROLITHIC WATER PROOFING
- SQ. M.
NVPILAR 2006
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART F - CONCRETE WORKS ITEM 404 –
REINFORCING STEEL
- KGS.
ITEM 406(1) – PRE STRESSED STRUCTURAL CONC. MEMBERS - EACH ITEM 406(2) – PRE STRESSED CONCRETE ITEM 900 R. C. CONCRETE***
- L.S. -CU.M.
***- Such prices and payment shall be full compensation for furnishing all materials, including metal water stops, joint fillers, weep holes, and rock backing and timber bumpers; for all form and false work; for mixing, placing, furnishing, and curing the concrete; and for all labor, materials, equipment, tools and incidentals necessary to complete the item…
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART G – MASONRY WORKS
ITEM 506(1)A- MASONRY UNIT (CHB)
- SQ. M.
PART H – CARPENTRY AND JOINERY WORKS ITEM 1OO3(A) – WOODEN CEILING
- BD. FT.
ITEM 1OO3(B) – WOODEN PARTITION
- BD. FT.
ITEM 1OO3(C) – WOODEN CABINETS
- BD. FT.
ITEM 1OO3(D) – WOODEN STAIRS & OTHERS AS SPECIFIED ON PLANS
- BD. FT.
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART I – FABRICATED MATERIALS & HARDWARE
ITEM 1004 – HARDWARE
-
ITEM 1004.2.1 – ROUGH HARDWARE
- PCS/KILO
ITEM 1004.2.2 – FINISHING HARDWARE
- PCS/SET
ITEM 1005 – STEEL WINDOWS ITEM 1005(A) – RESIDENTIAL CASEMENT
- SQ.M.
ITEM 1005(B) – HEAVY DUTY SIDE HINGED VENTILATOR - SQ.M. ITEM 1005(C) – PROJECTED VENTILATOR
- SQ.M.
ITEM 1005(D) – AWNING VENTILATOR
- SQ.M.
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
ITEM 1006 – STEEL DOORS AND FRAMES ITEM 1006(A) – HOLLOW STEEL DOORS
- SQ.M./SET
ITEM 1006(B) – FLUSH DOOR
- SQ.M./SET
ITEM 1006(C) – GRILLE DOOR
- SQ.M./SET
ITEM 1006(D) – STEEL LOUVER DOOR
- SQ.M./SET
ITEM 1007 – ALUMINUM GLASS DOORS
-
ITEM 1007 – ALUMINUM GLASS DOOR, SLIDING TYPE, DESIGNATED AS D – ON THE SCHEDULE
- SQ.M.
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
ITEM 1008 – ALUMINUM GLASS WINDOWS ITEM 10O8(1) – ALUMINUM SLIDING WINDOWS
- SQ.M.
ITEM 1008(2) – ALUMINUM CASEMENT WINDOWS
- SQ.M.
ITEM 1008(3) – ALUMINUM AWNING WINDOWS
- SQ.M.
ITEM 1009 – JALOUSIE WINDOWS
-
ITEM 1009(1) – GLASS JALOUSIE WINDOWS
- SQ.M.
ITEM 1009(2) – WOOD JALOUSIE WINDOWS
- SQ.M.
ITEM 1010 – WOODEN DOORS AND WINDOWS
-
ITEM 1010(A) – FRAMES(JAMBS, SILLS, HEAD, TRANSOMS AND MULLIONS - SET ITEM 1010(B) – DOOR(FLUSH OR PANEL)
- SQ.M.
ITEM 1010(C) – WINDOW SACHES
- SQ.M.
ITEM 1010(D) – DOOR LOCKS
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
ITEM 1011 – ROLLING UP DOORS
-
ITEM 1011(A) – ROLLING UP DOOR(INDICATE METAL SIZE AND TYPE OF CURTAIN SLATE) ITEM 1012 – GLASS AND GLAZING
- UNIT/SET -
ITEM 1012(A) – FLOAT GLASS
- SQ.M.
ITEM 1012(B) – ORDINARY WINDOW & SHEET GLASS
- SQ.M.
ITEM 1012(C) – PLATE GLASS (MIRROR)
- SQ.M.
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART J – ROOF FRAMING WORKS ITEM 402(1) – TIMBER STRUCTURES
- SPAN
ITEM 402(2) – TIMBER TRUSSES
- BD. FT.
ITEM 403(1) – STRUCTURAL STEEL ,FURNISHED, FABRICATED AND ERECTED
- KGS
ITEM 403(2) – STRUCTURAL STEEL ,FURNISHED, FABRICATED AND ERECTED
- KGS
ITEM 403(3) – STRUCTURAL STEEL ,FURNISHED & FABRICATED
- KGS
ITEM 403(4) – STRUCTURAL STEEL ,FURNISHED & FABRICATED
- KGS
ITEM 403(5) – STRUCTURAL STEEL ,ERECTED
- KGS
ITEM 403(6) – STRUCTURAL STEEL ,ERECTED
- KGS
ITEM 403(7) – STRUCTURAL STEEL ,FURNISHED, FABRICATED AND ERECTED
- KGS
* - Where separate payment is to be made for certain metals or for certain particular components, other than under the general provision for structural steel, designations of those particular cases shall be inserted in the space provided in the pay names for Item 403(2), 403(4) or 403(6), as the case may be.
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART K – ROOFING WORKS -
ITEM 1013 – CORRUGATED METAL ROOFING ITEM 1013(A) – ROOF INSULATION ITEM 1013.2.1 – CORRUGATED ROOFING GAUGE 26
- SQ.M. - SQ.M .
ITEM 1013.2.2 – FABRICATED METAL ROOFING ACCESSORIES (A) – RIDGED/HIP ROLLS, FLASHING, GUTTER & DOWNSPOUT GAUGE 26
- L.M.
(B) – VALLEYS, COUNTER FLASHING GUTTER & DOWNSPOUT GAUGE 24 ITEM 1013.2.3 – ROOF VENTILATORS
- L.M. - EACH
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
ITEM 1014 – PRE-PAINTED METAL SHEETS ITEM 1014(A) – PRE-PAINTED METAL SHEETS ITEM 1015 – CLAY ROOF TILES
- SQ.M. -
ITEM 1015(A) – CLAY ROOF TILES
- SQ.M.
ITEM 1017 – ROOF DRAINS WITH STRAINERS
- PCS/SET
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART L - FINISHES ITEM 1018 – CERAMIC TILES ITEM 1018.2.1.1 – GLAZED TILES AND TRIMS
- SQ.M.
ITEM 1018.2.1.2 – UNGLAZED TILES ITEM 1019 – WOOD TILES
- SQ.M
ITEM 1019(A) – NARRA WOOD TILES
- SQ.M.
ITEM 1019(B) – TANGUILE WOOD TILES
- SQ.M.
ITEM 1019(C) – OTHER SPECIES AS SPECIFIED
- SQ.M.
ITEM 1020 – VINYL FLOOR TILES
- SQ.M. OR L.M OR # OF PCS.
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
ITEM 1021 - CEMENT FLOOR FINISH ITEM 1021(A) – PLAIN CEMENT FLOOR FINISH
- SQ.M.
ITEM 1021(B) – COLORED CEMENT FLOOR FINISH
- SQ.M.
ITEM 1021(A) – CEMENT FLOOR FINISH W/FLOOR HARDINER
- SQ.M.
ITEM 1022 - STUCCO FINISH ITEM 1022(A) - STUCCO FINISH ITEM 1023 – GRANOLITHIC MARBLE WORKS ITEM 1023(A) – CORRIDORS ITEM ITEM ITEM ITEM
1023(B) – STAIRS LANDING, RISERS, ETC. 1023(C) – ROOMS AND OTHERS 1024 – PEA GRAVEL WASHOUT FINISH 1024(A) – PEA GRAVEL WASHOUT FINISH
- SQ.M. - SQ.M. - SQ. M. OR L.M. - SQ.M. - SQ.M. - SQ.M.
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
ITEM 1025 – BUSH HAMMERED FINISH ITEM 1025(A) – BUSH HAMMERED FINISH ITEM 1025(B) – FLUTED BUSH HAMMERED FINISH
- SQ.M. - SQ.M.
ITEM 1026 – PEBBLE WASHOUT FINISH ITEM 1026(A) – PEBBLE WASHOUT FINISH
- SQ.M.
ITEM ITEM ITEM ITEM ITEM
1027 – CEMENT PLASTER FINISH 1027(A) – CEMENT PLASTER FINISH 1027(B) – SIMULATED RED BRICKS, pn. 142 1028 – SYNTHETIC ADOBE 1028(A) – BUSH HAMMERED SYNTHETIC ADOBE FINISH
ITEM 1028(B) – FLUTTEDBUSH HAMMERED SYNTHETIC ADOBE FINISH
ITEM 1028(C) - PIQUETA TOOL FINISH / SYNTHETIC FINISH
- SQ.M. - SQ.M. - SQ.M. - SQ.M.
- SQ.M.
NVPILAR 2006
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
ITEM ITEM ITEM ITEM
1O29 – GRANATITE WASHOUT FINISH 1O29(1) – GRANATITE WASHOUT FINISH 1030 – ACCOUSTICAL CEILING 1030(A) – ACCOUSTICAL CEILING PANEL
- SQ.M., LM - SQ.M OR # OF PCS.
ITEM 1031 – ACCOUSTICAL TREATMENT ITEM 1031.2.1 – ACCOUSTICAL TILE/BOARD/PANEL ITEM 1031.2.2 – SPRAYED-ON ACCOUSTICAL MATERIALS
- SQ.M. - SQ.M.
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART M – PAINTING, VARNISHING & OTHER RELATED WORKS ITEM ITEM ITEM ITEM ITEM
1032 1032 1032 1032 1032
A – PAINTING WOKS A(1) – PAINTING WOKS (MASONRY PAINT) A(2) – PAINTING WOKS (WOOD PAINT) A(1) – PAINTING WOKS (ROOF PAINT) B – VARNISHING
ITEM 1032 C – SEA-MIST FINISH ITEM 1032 D – DUCCO FINISH ITEM 1032 E – TEXTURE FINISH
- SQ.M. - SQ.M. - SQ.M. - SQ.M. - SQ.M. - SQ.M. - SQ.M.
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART N – WATERPROOFING WORKS ITEM 1016 - WATERPROOFING ITEM 1016(A) – CEMENT BASE WATERPROOFING
- SQ.M.
ITEM 1016(B) – LIQUID WATERPROOFING
- SQ.M.
ITEM 1016(C) – BUILT-UP AND PREFORMED MEMBRANE
- SQ.M.
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART O – SANITARY WORKS ITEM 1001 – STORM DRAINAGE AND SEWERAGE SYSTEM ITEM ITEM ITEM ITEM ITEM ITEM ITEM
1001.2(A) – PIPE (KIND AND SIZE) 1001.2(B) – FITTINGS (KIND AND SIZE) 1001.2(C) – CONCRETE GUTTER 1001.2(D) – CONCRETE CANAL 1001.2(E) – W.I. GRATING 1001.2(F) – CATCH BASIN 1001.2(G) – JUNCTION BOX
- METER - EACH - METER - METER - METER - EACH - EACH
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART P – ELECTRICAL WORKS
ITEM 1100 – CONDUITS, FOXES & FITTINGS (1)-RSC CONDUIT PIPE- MM DIA W/ COUPLING (2)-LOCKNUT & BUSHING (3)-CONDULET TYPE (4)-CONDUIT PIPE ELBOW (5)-CONNECTOR (6)-CONDUIT CLAMP (7)-PVC ADAPTER (8)-G.I. WIRE G.A. #14 (9)-HACKSAW BLADE (10)-PVC TAPE 19MM DIA X 18MM (11)-RUBBER TAPE 19MM DIA X 227G (12)-PVC SOLVENT CEMENT @ 400 CC. (13)-PVC END BALL (14)-OCTAGONAL JUNCTION BOX (15)-UTILITY BOXES (16)-METAL PULL BOX (17)-SQUARE BOX (18)-TELEPHONE CABINET (19)-REINFORCED CONCRETE PEDESTAL POLE (20)-RED LEAD PAINT (21)-WEATHER HEAD W/ TYPE F CONDULET (22)-GROUNDING ROD COPPERWELD 20MM DIA. X 3.00M (23)-APITONG OR APPROVED EQUAL CRESOTED WOOD POLE (24)-ANCHOR ROD__ MM DIA (25)-ANCHOR LOG__ MM DIA (26)-POWERLOAD STUDS WITH NUTS
- LENGTH - PAIRS - PIECES - PIECES - PIECES - PIECES - PIECES - KILOS - PIECES - ROLLS - ROLLS - CANS - PIECES - PIECES - PIECES - PIECES - PIECES - SET - LOT - LOT - PIECES -LENGTH - PIECES - PIECES - PIECES - PIECES NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
ITEM 1101 – WIRES AND WIRING DEVICES (1)- ELECTRIC WIRE - METER OR ROLLS (2)- SINGLE POLE TUMBLER SWITCH - PIECES (3)- TWO-GANG TUMBLER SWITCH - PIECES (4)- THREE-GANG TUMBLER SWITCH - PIECES (5)- THREE-WAY TUMBLER SWITCH - PIECES (6)- DUPLEX CONVENIENCE RECEPTACLES - SET (7)- HEAVY DUTY CONVENIENCE RECEPTACLES - SET (8)- STD. TELEPHONE OUTLET BAKELITE COVER W/ 9.52 CENTER HOLE - PIECES (9)- WDO TYPE AIRCONDITIONING OUTLET 3- PRONG POLARIZED TYPE - PIECES (10)- BARE COPPER WIRE METERS (11)- GROUNDING CLAMPS FOR ELECTRIC WIRES - PIECES (12)- MESSENGER WIRE METERS (13)- GUY WIRE METERS (14)- VIBRATING BELL - SET (15)- TRAFFIC LIGHT CONTROL PANEL - SET (16)- TRAFFIC LIGHT METAL ENCLOSURES COMPLET WITH RED & GREEN LIGHT PROVIDED WITH REFLECTORS & 152MM DIAMETER VIBRATING BELL - SET NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
ITEM 1102 – POWER LOAD CENTER, SWITCHGEAR & PANEL BOARDS (1)- PANEL BOARD (CIRCUIT BREAKER TYPE) (2)- PANEL BOARD (SAFETY SWITCH TYPE) (3)- LOW-VOLTAGE SWITCHGEAR (LVS) COMPLETE W/ METERING DEVICES AND ACCESSORIES (4)- POWER FUSES PIECES (5)- LIGHTING ARRESTERS (6)- AIR BREAK SWITCH (7)- ENCLOSED ACB NEMA TYPE 1 (8)- ENCLOSED ACB NEMA TYPE 3R (9)- AUTOMATIC TRANSFER SWITCH (10)- MANUAL TRANSFER SWITCH WITHOUT FUSES (11)- MOTOR CONTROLLER
- SET - SET - SET - PIECES - SET - SET - SET - SET - PIECES - SET
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART Q – MECHANICAL WORKS ITEM 1200 – AIR CONDITIONING AND REFRIGERATION SYSTEM (A)- COMPRESSOR, CONDENSER AND EVAPORATOR (B)- DIFFUSSER, GRILLES AND VALVES (C)- PIPES (D)- DUCTS AND INSULATIONS (E)- PIPE INSULATIONS
ITEM 1201 – WATER PUMPING (A)(B)(C)(D)-
PUMP AND WATER TANK AIR COMPRESSOR PIPES VALVES AND FITTINGS
- SET - PIECES - LENGTH - SQ.M. - METER
- SET - SET - LENGTH - PIECE
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
ITEM 1202 – AUTOMATIC WATER SPRINKLER SYSTEM (A)- FIRE AND JOCKEY PUMPS (B)- SPRINKLER HEAD, VALVES AND FITTINGS (C)- PIPES
ITEM 1203 – ELECTRIC ELEVATOR
(A)- TRACTION OR HYDRAULIC MACHINE AND CAR (B)- HOISTWAY DOORS, COUNTER WEIGHT, GUIDE RAILS, ANNUNCIATORS, AND HALL POSITION INDICATORS (C)- ELECTRICAL WIRES AND CONDUITS
ITEM 1204 – ELECTRIC DUMPWAITER (A)- MACHINE (B)- CAR, DOOR AND CABLE (C)- ELECTRICAL WIRES AND CONDUITS
- SET - PIECE - LENGHT - SET - PIECE - LENGTH - SET - PIECE - LENGHT
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
ITEM 1205 – OXYGEN, NITROUS OXIDE, VACUUM & FUEL GAS SYSTEM (A)- OXYGEN, NITROUS OXIDE, GAS MANIFOLD AND DUPLEX VACUUM PUMP (B)- HUMIDIFIER, VACUUM TRAP BOTTLE, OUTLETS, VALVES (C)- PIPES AND TUBINGS LENGHT
- SET - PIECE -
ITEM 1206 – HEATING SYSTEM
(A)- BOILERS, FUEL PUMP, STORAGE TANKS AND FUEL DAY TANK INCLUDING FOUNDATION (B)- PIPES (C)- VALVES AND FITTINGS
- SET - LENGTH - PIECES
ITEM 1207 - BOILERS
(A)- STEAM BOILERS, AIR COMPRESSOR, HEAT EXCHANGER AND FUEL PUMP (B)- PIPES WITH INSULATION (C)- VALVES AND FITTINGS
- SET - LENGTH - PIECE
NVPILAR 2008
COST ESTIMATION SYSTEM FOR BUILDINGS ITEMS OF WORKS IN BUILDING CONSTRUCTION (BASED ON DPWH STD. SPECS.)
PART R- CONSTRUCTION SAFETY AND HEALTH (DO 56) SPL -1 – PERSONAL PROTECTIVE EQUIPTMENT (PPE)
- PCS.
SPL -2 – SAFETY AND HEALTH PERSONNEL
- NOS.
SPL -3 – SIGNAGES AND BARRICADES
- PCS.
NVPILAR 2008
NVPILAR 2008