HERVE BARON
The execution of a Complex Project… a guided tour
© 2015 – Hervé Baron
HERVE BARON
The COMPANY “Client”
The actors
The suppliers
The EPC Contractor Impossible d’afficher l’image.
© 2015 – Hervé Baron
The sub-contractors
HERVE BARON
The phases
Sanction
Basic Engineering By ENGINEERING
Project Execution by EPC CONTRACTOR
© 2015 – Hervé Baron
Conceptual evaluation + Pre-Project By COMPANY
Sanction
HERVE BARON
Design
Procurement
Manufacturing
Installation
Construction & erection
Inspection & tests
Shipping
Hand-over
© 2015 – Hervé Baron
HERVE BARON
The multiple sides of a Project
Project Control
PROJECT
© 2015 – Hervé Baron
Human Resources Management
HERVE BARON
The multiple sites of a Project Home office (Paris) •Project management •Detail Engineering (part) •Procurement
Engineering Sub-Contractor (India) Detail Engineering (part)
Shipyard (Korea) Hull Engineering & Fabrication
Satellite office Detail Engineering (part)
Fabrication yard (Nigeria): Fabrication (part)
Installation, commissioning, start-up
Shipyards (Singapore & Malaysia) Topsides Fabrication & Integration
© 2015 – Hervé Baron
Offshore (Nigeria):
HERVE BARON
Project
Engineering
Procurement
Construction
© 2015 – Hervé Baron
HERVE BARON
Project
Engineering
Procurement
Construction
© 2015 – Hervé Baron
HERVE BARON
The facilities design basis Infrastructure:
Feedstock and products flow Feedstock composition Battery limit conditions
Pressure (bar)
Process facilities:
50
Administrative and technical buildings
45 40
Control room
35
Access road
30
Equipment Spare
Site fencing, gates, check point
25 20
Performance: Products specifications
15
Design criteria:
10
% of over design
5
Energy efficiency, emissions
0 -85
-80
-75
-70
-65
-60
-55
Environment data:
Utilities:
Min/max temperature
Electric power supply
Rain/snow fall
Other utilities
Wind Geological conditions
Process control
Applicable codes and standards:
Fire/gas alarm
International standards
Public address, LAN, PABX
Local rules
© 2015 – Hervé Baron
Systems:
HERVE BARON
Engineering in the Project
Design basis:
Documents for Construction:
- Functional requirements
Construction drawings & specifications
- Client specifications
Engineering
Documents for Purchase: bill of quantity & specification
- Design codes © 2015 – Hervé Baron
HERVE BARON
Project
Instruments& Control
Layout & Piping
Process
Engineering
Procurement
Construction
Electrical
Equipment
Civil
Safety
© 2015 – Hervé Baron
HERVE BARON
Project
Instruments& Control
Layout & Piping
Process
Engineering
Procurement
Construction
Electrical
Equipment
Civil
Safety
© 2015 – Hervé Baron
HERVE BARON
Process simulations
© 2015 – Hervé Baron
HERVE BARON
Thermodynamic calculations
© 2015 – Hervé Baron
Process Flow Diagram (PFD)
Heat & Material balance
HERVE BARON
Equipment list
© 2015 – Hervé Baron
HERVE BARON
Equipment duty
© 2015 – Hervé Baron
HERVE BARON
Process data sheet
© 2015 – Hervé Baron
HERVE BARON
Process Flow Diagram (PFD)
© 2015 – Hervé Baron
HERVE BARON
Piping & Instrumentation Diagram (P&ID)
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
Piping & Instrumentation Diagram (P&ID)
HERVE BARON
Process control
© 2015 – Hervé Baron
HERVE BARON
Emergency shut down
© 2015 – Hervé Baron
HERVE BARON
Emergency relief
© 2015 – Hervé Baron
HERVE BARON
Operating manual
© 2015 – Hervé Baron
HERVE BARON
Project
Instruments& Control
Layout & Piping
Process
Engineering
Procurement
Construction
Electrical
Equipment
Civil
Safety
© 2015 – Hervé Baron
HERVE BARON
Rotating machinery
© 2015 – Hervé Baron
HERVE BARON
Pressure vessels
© 2015 – Hervé Baron
HERVE BARON
Heat exchangers
© 2015 – Hervé Baron
HERVE BARON
Packages, Fired Equipment
© 2015 – Hervé Baron
HERVE BARON
Process data sheet Mechanical data sheet
© 2015 – Hervé Baron
HERVE BARON
Material Requisition
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Project
Instruments& Control
Layout & Piping
Process
Engineering
Procurement
Construction
Electrical
Equipment
Civil
Safety
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Fire fighting
© 2015 – Hervé Baron
HERVE BARON
Passive fire protection
© 2015 – Hervé Baron
HERVE BARON
Fire & Gas detection layout
© 2015 – Hervé Baron
HERVE BARON
Environmental Impact Assessment
© 2015 – Hervé Baron
HERVE BARON
Project
Instruments& Control
Layout & Piping
Process
Engineering
Procurement
Construction
Electrical
Equipment
Civil
Safety
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
Equipment supporting structures
HERVE BARON
© 2015 – Hervé Baron
Piping supporting structures (pipe-racks)
HERVE BARON
Structural design
© 2015 – Hervé Baron
HERVE BARON
Structural design
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
Structural drawings
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Architectural drawings
© 2015 – Hervé Baron
Equipment layout drawing
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Project
Instruments& Control
Layout & Piping
Process
Engineering
Procurement
Construction
Electrical
Equipment
Civil
Safety
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Layout/ principles
© 2015 – Hervé Baron
HERVE BARON
Layout/consideration for all networks
© 2015 – Hervé Baron
HERVE BARON
General Plot Plan
© 2015 – Hervé Baron
HERVE BARON
Piping Layout drawing © 2015 – Hervé Baron
HERVE BARON
3D modelling
© 2015 – Hervé Baron
HERVE BARON
3D model clash check
3D model review © 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Piping Design
Design code for Process plants: ASME B31.3
P*D t= (2SWE + PY) P design pressure D (outside) diameter S stress value for material as per table in ASME B31.3 W weld joint reduction factor – for long term strength of weld at elevated temperature E quality factor, from table in ASME B31.3 (1 for seamless, 0.85 for ER welded pipe, etc.) Y coefficient from table in ASME B31.3 (from 0.4 to 0.7 depending on material and temperature) © 2015 – Hervé Baron
To the above calculated thickness shall be added: - The corrosion allowance, e.g., 3 mm - The manufacturing tolerance: 12.5%
HERVE BARON
Thickness (mm) Number of passes
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Isometric drawing
© 2015 – Hervé Baron
HERVE BARON
Piping Pre-fabrication
© 2015 – Hervé Baron
HERVE BARON
Piping General Arrangement drawing
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Standard Pipe Support drawings
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Material Selection
© 2015 – Hervé Baron
HERVE BARON
Material Specification
© 2015 – Hervé Baron
HERVE BARON
Material Specification
© 2015 – Hervé Baron
HERVE BARON
Project
Instruments& Control
Layout & Piping
Process
Engineering
Procurement
Construction
Electrical
Equipment
Civil
Safety
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Instrument data sheet
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
Process Control System
HERVE BARON
System architecture drawing
© 2015 – Hervé Baron
HERVE BARON
Mechanical Equipment Control
© 2015 – Hervé Baron
HERVE BARON
The instrumentation hardware Instrument room Marshalling
Controller
cabinet
cabinet
Control room
VDU
PT
JB
Process line
CPU
LAN Secondary cable Multi cable
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
Building detail drawing/Telecom and PAGA layout
HERVE BARON
Cable routing drawings
© 2015 – Hervé Baron
Cable list
HERVE BARON
© 2015 – Hervé Baron
Cable routing inside technical rooms
HERVE BARON
Project
Instruments& Control
Layout & Piping
Process
Engineering
Procurement
Construction
Electrical
Equipment
Civil
Safety
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
Electrical consumers list
HERVE BARON
Electrical Load Summary
© 2015 – Hervé Baron
HERVE BARON
Electrical distribution
© 2015 – Hervé Baron
HERVE BARON
General One Line Diagram
© 2015 – Hervé Baron
HERVE BARON Generators
Equipment specification
Switchgear
Transformer © 2015 – Hervé Baron
HERVE BARON
Electrical equipment layout
© 2015 – Hervé Baron
HERVE BARON
Electrical Control System
© 2015 – Hervé Baron
HERVE BARON
Process design PFDs H&M balance
© 2015 – Hervé Baron
HERVE BARON
Process design PFDs H&M balance
Process data sheet
Equipment specification
© 2015 – Hervé Baron
Rotating Pressure vessels Fired equipment Heat exchangers Packages etc.
HERVE BARON
Process design PFDs
P&IDs
H&M balance
© 2015 – Hervé Baron
HERVE BARON
Process design PFDs
P&IDs
H&M balance
Piping Instrumentation
Process data sheet
Equipment specification Vendor drawings
Layout Civil Electrical
© 2015 – Hervé Baron
Rotating Pressure vessels Fired equipment Heat exchangers Packages etc.
HERVE BARON
Engineering work sequence
© 2015 – Hervé Baron
Extract from the book: ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, 2015, page 209
HERVE BARON
Typical 3 year EPC Project Engineering schedule
PR = Process, EQ = Equipment, PL = Plant Layout, PI = Piping, I&C = Instrumentation & Control, EL = ELectrcial, HSE = Safety & Environment, CIV = Civil
© 2015 – Hervé Baron
Extract from the book: ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, 2015, page 211
HERVE BARON
Process design PFDs
P&IDs
H&M balance
Piping Instrumentation
Process data sheet
Equipment specification Vendor drawings
Layout Civil Electrical
© 2015 – Hervé Baron
Rotating Pressure vessels Fired equipment Heat exchangers Packages etc.
HERVE BARON
Electrical Layout Piping
Vendor
Instrumentation & Control Process
Civil
© 2015 – Hervé Baron
Engineering / Vendor interfaces
HERVE BARON
Electrical
Process Utility consumption
Power consumption
Battery limit conditions
General Arrangement
Layout
P&ID
Vendor
Piping
Functional analysis C&E
Instrumentation & Control
Terminals dwgs Purchaser Mechanical connection list and dwg
Civil
© 2015 – Hervé Baron
Foundation drawing and loads, including auxiliaries!
HERVE BARON
Interested and wanting to know more on Engineering?
A unique synthesis for the busy Project professional 270 pages 300 illustrations
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide 2nd edition Order direct from the publisher: http://www.editionstechnip.com/en/catal ogue-detail/1111/oil-gas-engineeringguide-the.html
© 2015 – Hervé Baron
HERVE BARON
Project
Engineering
Procurement
Construction
© 2015 – Hervé Baron
HERVE BARON
Procurement
© 2015 – Hervé Baron
HERVE BARON
Procurement / Steps
Inquiry (Call for Tender) Short listing Bid analysis Clarifications Negotiations Purchase Order Expediting Inspection
Warranty Period
© 2015 – Hervé Baron
Delivery
HERVE BARON
Procurement / Supplier selection criteria Technical Compliance Price Qualification of supplier Schedule Load of workshop References References with final Client Financial situation
Internal feed-back
© 2015 – Hervé Baron
Annual turn-over
HERVE BARON
Procurement
© 2015 – Hervé Baron
HERVE BARON
Expediting
© 2015 – Hervé Baron
HERVE BARON
Expediting
© 2015 – Hervé Baron
HERVE BARON
Inspection
© 2015 – Hervé Baron
HERVE BARON
Inspection
© 2015 – Hervé Baron
Shipping HERVE BARON
© 2015 – Hervé Baron
Shipping HERVE BARON
© 2015 – Hervé Baron
Shipping HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Project
Engineering
Procurement
Construction
© 2015 – Hervé Baron
HERVE BARON
Earthworks
© 2015 – Hervé Baron
Pipeline HERVE BARON
© 2015 – Hervé Baron
Pipeline HERVE BARON
© 2015 – Hervé Baron
Roads HERVE BARON
© 2015 – Hervé Baron
Buildings HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Civil Works
Sand Aggregate
Cement Admixtures © 2015 – Hervé Baron
HERVE BARON
Civil Works
© 2015 – Hervé Baron
HERVE BARON
Civil Works
© 2015 – Hervé Baron
HERVE BARON
Civil Works
© 2015 – Hervé Baron
HERVE BARON
Civil Works
© 2015 – Hervé Baron
HERVE BARON
Civil Works
© 2015 – Hervé Baron
HERVE BARON
Pre-fabrication
© 2015 – Hervé Baron
Erection HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Underground networks
© 2015 – Hervé Baron
HERVE BARON
Plant erection
© 2015 – Hervé Baron
HERVE BARON
Steel structure erection
© 2015 – Hervé Baron
HERVE BARON
Equipment installation
© 2015 – Hervé Baron
HERVE BARON
Equipment installation
© 2015 – Hervé Baron
HERVE BARON
Piping Pre-fabrication
© 2015 – Hervé Baron
HERVE BARON
Piping erection
© 2015 – Hervé Baron
HERVE BARON
Piping erection
© 2015 – Hervé Baron
HERVE BARON
Field Instrumentation Installation
© 2015 – Hervé Baron
HERVE BARON
Electrical equipment connection
© 2015 – Hervé Baron
HERVE BARON
Cable pulling
© 2015 – Hervé Baron
HERVE BARON
Arrangement of Technical rooms
© 2015 – Hervé Baron
HERVE BARON
Cable connections
© 2015 – Hervé Baron
HERVE BARON
Other Systems Field Equipment Installation
© 2015 – Hervé Baron
HERVE BARON
Control room consoles installation
© 2015 – Hervé Baron
Testing HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Commissioning Handover System
Sub-System Document Folder
Circuit
Elect Equip
Mech Equip Instrument Loop
Instrument Cable
Instrument Tag
© 2015 – Hervé Baron
Junction Box
HERVE BARON
The multiple sides of a Project
Project Control
PROJECT
© 2015 – Hervé Baron
Human Resources Management
HERVE BARON
Project Organisation
Project Manager
Engineering Manager
Project Engineers
Procurement Manager
Discipline Engineers
Process
Civil
Instrumentation
Electrical
Expediters
Inspectors
Construction Manager
Contract Manager
Scheduling Manager
Cost Control
Construction Superintendent
Construction supervisor
Construction superintendent
Construction supervisor © 2015 – Hervé Baron
Equipment
Purchasers
Project Control Manager
Site Manager
HERVE BARON
Project procedures
© 2015 – Hervé Baron
HERVE BARON
Project temporary facilities
© 2015 – Hervé Baron
HERVE BARON
Project temporary facilities
© 2015 – Hervé Baron
HERVE BARON
Project temporary facilities
© 2015 – Hervé Baron
HERVE BARON
Project temporary facilities
© 2015 – Hervé Baron
HERVE BARON
Project temporary facilities
© 2015 – Hervé Baron
HERVE BARON
Construction Procedures
© 2015 – Hervé Baron
HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Quality Control
© 2015 – Hervé Baron
HERVE BARON
Quality Control
Temperature
Sampling Slump © 2015 – Hervé Baron
HERVE BARON
Quality Control
© 2015 – Hervé Baron
HERVE BARON
Cost Control
© 2015 – Hervé Baron
Insurance HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Contracts
P.O.
P.O.
Purchase Orders
P.O.
EPC Main Contract
Sub-Contracts
Sub
© 2015 – Hervé Baron
Sub
HERVE BARON
Contracts Terms and Conditions Price Schedule
EPC Main Contract
Performance guarantees Technical basis Specifications, codes & stds © 2015 – Hervé Baron
HERVE BARON
Contracts
E P C © 2015 – Hervé Baron
HERVE BARON
Contracts
© 2015 – Hervé Baron
∑ + x%
HERVE BARON
Construction contracts
Civil
© 2015 – Hervé Baron
HERVE BARON
Construction contracts
Mechanical
© 2015 – Hervé Baron
HERVE BARON
Construction contracts
E&I
© 2015 – Hervé Baron
HERVE BARON
Construction contracts
General Contractor © 2015 – Hervé Baron
HERVE BARON
Contracts Terms and Conditions
EPC Main Contract
Obligations of the 2 parties Penalties in case of bad performance Conflict resolution
© 2015 – Hervé Baron
Limit of liability
HERVE BARON
Quality Assurance (QA)
© 2015 – Hervé Baron
HERVE BARON
Quality Assurance (QA)
© 2015 – Hervé Baron
HERVE BARON
Quality Assurance (QA)
© 2015 – Hervé Baron
HERVE BARON
Quality Assurance (QA)
© 2015 – Hervé Baron
HERVE BARON
Document Control Document code 1
Installation drawings
2
Detail drawings
3
Diagrams
4
Lists – Bill of Quantities
5
Isometrics
6
Calculation notes
7
Specifications
8
Data sheets
9
Requisitions Discipline code Instrumentation & Control
C
Civil engineering
E
Electrical
G
Project general documents
J
Mechanical
K
Safety
M
Piping & Layout
P
Processes
S
Steel Structures
V
Vessels – Heat exchangers
W
Materials – Welding
© 2015 – Hervé Baron
A
HERVE BARON
Document Control
© 2015 – Hervé Baron
HERVE BARON
Document Control Client Documents submitted to client
Approval/ Comments
Engineering
Comments
Vendors
© 2015 – Hervé Baron
Documents submission
HERVE BARON
Electronic Document Management System
Center 1 Sr. Mgmt
Intranet / Internet
Center 2 Sr. Mgmt
Correspondence etc.
Electronic Document Management System Projects
Breakdown structures
Engineering documents
Reports Interfaces
Satellite Engineering Center
Vendor documents Construction Site
© 2015 – Hervé Baron
Intranet / Internet
HERVE BARON
Interface Management
© 2015 – Hervé Baron
HERVE BARON
Scheduling
MONTH PROJECT SCHEDULE 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 PLANT START-UP PIPING PRE-FABRICATION & INSTALLATION X X X X X X X X X X PIPING MATERIAL & DRAWINGS AT SITE PIPING MATERIAL MANUFACTURING & SHIPPING X X X X X X PURCHASE OF PIPING MATERIAL TECHNICAL & COMMERCIAL CLARIFICATIONS X X CALL FOR TENDER FOR PIPING MATERIAL PREPARE PIPING MATERIAL TAKE-OFF X PIPING ROUTING STUDIES X X X PIPING & INSTRUMENTATION DIAGRAMS (PIDs)
5
4
1
1
2 3
5
3
4
5
2 © 2015 – Hervé Baron
HERVE BARON
Critical path of an Oil & Gas Project
© 2015 – Hervé Baron
Extract from the book: ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, 2015, page 225
HERVE BARON
Progress Monitoring How would you measure progress?
© 2015 – Hervé Baron
HERVE BARON
Progress Monitoring
© 2015 – Hervé Baron
HERVE BARON
Progress Monitoring
© 2015 – Hervé Baron
HERVE BARON
Progress Monitoring
© 2015 – Hervé Baron
HERVE BARON
IT
Today: 3D 15 years ago: 2D
Tomorrow: 3D & data
© 2015 – Hervé Baron
IT HERVE BARON
© 2015 – Hervé Baron
Safety HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Safety
Guard Rail System with Toe Boards
Planking
Runner
Bearer
Post
Cross Bracing
Longitudinal Brace
© 2015 – Hervé Baron
Sill
Safety HERVE BARON
© 2015 – Hervé Baron
HERVE BARON
Human resources / career path Graduate Engineer, 25 years old
Process Engineer
Project Engineer
Engineering Manager/ Deputy Project Manager
Project Manager
3-5 yrs
5 yrs
5-7 yrs
40-45 yrs old © 2015 – Hervé Baron
Note: the career pattern shown here is a very fast track one to the PM position... One would enjoy oneself just as well taking more time!
HERVE BARON
The Oil & Gas Engineering Guide 2nd edition
Do you want to know more... Much more?
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition Table of Contents
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition Table of Contents
Discipline presentation: activities and deliverables
© 2015 – Hervé Baron
HERVE BARON
The work of each Engineering discipline is described
© 2015 – Hervé Baron
HERVE BARON
Design activities are explained, e.g., Plant Equipment layout
© 2015 – Hervé Baron
HERVE BARON
Complex activities, such as QRA, are explained through a practical example.
© 2015 – Hervé Baron
HERVE BARON
A sample of all common Engineering documents is included
© 2015 – Hervé Baron
HERVE BARON
Difference between Engineering and Shop drawings
© 2015 – Hervé Baron
HERVE BARON
Understand the main technical aspects, e.g., DCS vs ESD
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition Table of Contents
The overall process © 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition Table of Contents
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition Table of Contents
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition Table of Contents