OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

Page 2 / 27

INDEX INDEX ........................................................................................................................... 2  AMENDMENTS AND REVISIONS .............................................................................. 4  1. 

INTRODUCTION .................................................................................................. 5  1.1  PROJECT OVERVIEW ..............................................................................................5  1.2  PIPELINE SYSTEM DESCRIPTION ..........................................................................5 

2. 

DEFINITIONS AND ABBREVIATIONS .............................................................. 6  2.1  DEFINITIONS .............................................................................................................6  2.2  ABBREVIATIONS ......................................................................................................7 

3. 

REFERENCE RULES, CODES AND STANDARDS .......................................... 7  3.1  CODES AND STANDARDS .......................................................................................7  3.2  OWNER DOCUMENTS ..............................................................................................7  3.3  CONTRACTOR DOCUMENTS ..................................................................................7 

4. 

SCOPE OF DOCUMENT ..................................................................................... 8 

5. 

RESPONSIBILITIES ............................................................................................ 8 

6. 

PROCEDURE ...................................................................................................... 9  6.1  ORGANIZATION OF PROJECT FILES ...................................................................10  6.2  HANDLING OF CORRESPONDENCE DOCUMENTS ............................................10  6.3  HANDLING OF TECHNICAL DOCUMENTS ...........................................................10  6.4  HANDLING OF INCOMING TECHNICAL DOCUMENTS........................................12  6.4.1 

Logging of Technical Documents ....................................................................12 

6.4.2 

Deciding of the Distribution List and the Necessary Actions ...........................12 

6.4.3 

Distribution of Technical Documents ...............................................................12 

6.4.4 

Examination of Technical Documents .............................................................12 

6.4.5 

Contractor’s Evaluation of Comments on Technical Documents ....................12 

6.4.6 

Updating of the MDR .......................................................................................13 

6.4.7 

Approval of the MDR .......................................................................................13 

6.4.8 

Handling of Master Documentation .................................................................13 

6.5  HANDLING OF OUTGOING TECHNICAL DOCUMENTS ......................................13 

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

Page 3 / 27

6.6  TECHNICAL DOCUMENTS REFERENCES ...........................................................13  6.6.1 

Technical Documents Template ......................................................................13 

6.6.2 

Technical Drawing Template ...........................................................................14 

6.6.3 

Technical Documents Checks .........................................................................14 

6.6.4 

Documents development phases ....................................................................14 

6.7  DOCUMENT NUMBERING ......................................................................................16  6.7.1 

Codification for Technical Documents .............................................................16 

6.7.2 

Codification for Technical Specifications .........................................................17 

6.7.3 

Codification for Drawings.................................................................................17 

6.7.4 

ANNEX 1 – Codes for Technical Documents and Technical Specifications Subject (D).......................................................................................................19 

6.7.5 

ANNEX 2 – Codes for Technical Document Category (E) ..............................20 

6.7.6 

Forms – Records .............................................................................................20 

6.7.7 

ANNEX 3 – Codes for Drawings Category ......................................................21 

6.7.8 

Sheet Number (Drawings) ...............................................................................21 

6.7.9 

Revision Number .............................................................................................22 

6.8  ELECTRONIC FILING OF DOCUMENTS................................................................22  6.9  FINAL DOCUMENTATION ......................................................................................23 

7. 

ATTACHMENTS ................................................................................................ 24 

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

Page 4 / 27

AMENDMENTS AND REVISIONS

Amendment and revision A1

Date

Page

Description

16/12/11

All

Issued for Comments/Approval

Project Manager

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

1.

Page 5 / 27

INTRODUCTION

1.1 PROJECT OVERVIEW

Public Natural Gas System Operator (DESFA) of Greece plans to install an N.G.T.S. Offshore Natural Gas Pressure Pipeline Varnavas-Karavos (Aliveri) whose purpose will be to supply natural gas to Evvia Island. The southern landfall in Attiki is named Varnavas while the previous names used for this landfall are Ag. Apostoli or Grammatiko. The northern landfall in Evvia is named Karavos which is also indicated as Aliveri landfall. The maximum water depth along the 20” Gas Pipeline route is approx. 70m (MSL).

Figure 1-1 – Natural Gas Pressure Pipeline Varnavas-Karavos route layout

1.2 PIPELINE SYSTEM DESCRIPTION The offshore pipeline system consist of an 20” Natural Gas High Pressure Pipeline from the battery limit at Varnavas landfall, Attiki to the battery limit at Karavos landfall at Evvia island. The length of the new 20” Natural Gas High Pressure Pipeline is about 14.2 km. The 20” Natural Gas High Pressure Pipeline will consist of the two offshore sections, joined together offshore by Above Water Tie In method. The Varnavas side offshore pipeline section commences at the KP -0.020 and finishes at AWTI Target point at KP 13.360 in water depth of 31.2m. Along the pipeline section route, maximum water depth is 70m. The Karavos side offshore pipeline section commences at the KP 14.205 and finishes at AWTI Target point at KP 13.360 in water depth of 31.2m. Along the pipeline section route, maximum water depth is 31.2m. Both pipeline sections will be manufactured from carbon steel with internal corrosion coating.

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

2.

Page 6 / 27

DEFINITIONS AND ABBREVIATIONS

2.1 DEFINITIONS

The following definitions will be applicable in this document: CONTRACTOR

CONSORTIUM SAIPEM - ELTER

OWNER

DESFA – HELLENIC GAS TRANSMISSION SYSTEM OPERATOR S.A.

PROJECT

Detailed Engineering, Procurement Of Materials & Construction Of The Offshore Part Of The Stefani-Aliveri Natural Gas High Pressure Pipeline

PROJECT MANAGER

Means, respectively, the entity and the person appointed by OWNER to provide project management services

SITE

Means the lands, waters and other places on, under, in or through which the WORKS are to be performed including offshore installations, floating construction equipment, vessels (including the area covered by approved anchor patterns) design offices, workshops and places where equipment, materials or supplies are being obtained, storied or used for the purposes of the CONTRACT and any and all other places where the PERMANENT WORKS are to be executed and to which PLANT and Materials are to be delivered and any other places as may be specified in the CONTRACT as forming part of the SITE.

SUBCONTRACTOR

Selected Sub-Contractor to perform the work described in this document

SUPERVISING ENGINEER

Means the company(ies) appointed by OWNER to carry out the Construction Supervision duties, as well as the review of the detailed design issued by CONTRACTOR, as defined in Clause 2 hereof and in other CONTRACT DOCUMENTS

WORKS

Means all CONTRACTOR’s services and supplies to be rendered and PLANT furnished in accordance with the CONTRACT including both TEMPORARY WORKS and PERMANENT WORKS. Without limitation to items set out in the CONTRACT DOCUMENTS, the WORKS include everything of whatever nature that is required for the achievement of the objective of the CONTRACT, except for any exclusion that are specifically itemized in the CONTRACT DOCUMENTS

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

Page 7 / 27

2.2 ABBREVIATIONS DC

Document Controller

MDR

Master Document Register

PE

Project Engineer

CPM

Contractor Project Manager

CIM

Contractor Installation Manager

CEM

Contractor Engineering Manager

PMT

Project Management Team

3.

REFERENCE RULES, CODES AND STANDARDS

3.1 CODES AND STANDARDS

Ref

Document Number

Title

/1/

ISO 9001:2000

Quality management system - Requirements

3.2 OWNER DOCUMENTS Ref

Document Number

Title

Specifications /2/

APENDIX F

Contractor Documents Requirements

/3/

DC-028

Review/Approval of Contractors Technical Documents using Document Approval Form

3.3 CONTRACTOR DOCUMENTS

Ref

Document Number

Title

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

Page 8 / 27

Procedures /4/

WI-SMS-PCON-100-E

Documentation Management

/5/

DSF-1101401-436-6300-QACMAN-0200

Overall Quality Manual

/6/

DSF-1101401-436-6300-PRMMAN-0100

Project Overview Manual

/7/

WI-SMS-INST-101-E

Offshore Installation Engineering Documents and Approval

/8/

WI-SMS-OOFS-111-E

Work Instruction documentation”

/9/

WI-SMS-INST-112-E

Work Instruction “Preparation of Drawings”

/10/

WI-SMS-INST-104-E

Work Instruction “Installation methods / design control”

4.

“Offshore

“AS

BUILT”

SCOPE OF DOCUMENT

This procedure describes the system for handling the documents concerning the OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH PRESSURE PIPELINE PROJECT. The objective is to guarantee the traceability, distribution, monitoring, disposal when necessary, and the safekeeping of the Documents.

5.

RESPONSIBILITIES

The DC is the focal point for the control of the Project Documentation during the whole project life. The mission of the DC is to insure the implementation of Project Document Control within the Project as follows: 

To make available the applicable project documentation to the project team (including Owner Subcontractors, Partners…);



To manage all project documentation flow (paper and electronic)

The Document controller responsibilities include: 

Assigning on the request of the originator, a unique identification number for all project documents (including Subcontractors documents);

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

Page 9 / 27



Listing and controlling Project documents number within the project MDR;



Only the duly endorsed documents (signed and approved by CONTRACTOR’s responsible persons) are sent to OWNER for review/approval;



That all transmittals are duly indentified, numbered and filed ;



Issuing Transmittals;



Ensures that the MDR is updated and that transmittals and reports are issued embracing all documents generated in-house and by Vendor/Subcontractors or Third Parties during the Project Life (Engineering documents, Project Procedures, Queries, Vendor documents, OWNER) ;



That the MDR is updated on daily basis with the support of the PMT and available on the Project drive in the last revision;



All documents are available to CONTRACTOR interested personnel, at any utilization point ;



To upload all the issued documents on the FTP server that CONTRACTOR has set up in order to exchange the Project documentation with the OWNER, or to send all the documents and transmittals by e-mail, and to send all the transmittals by fax;



Information flow within the Project Team about documents status;



Ensuring the collection of final AS BUILT and transmission to OWNER;



To alert of any delays in pending documentation.

ProjectTeam shall comply with this procedure and shall assist the DC in number assignment.

6.

PROCEDURE

The project Document Control System includes:     

receipt; issuing; numbering logging; distribution;

Document flowchart is shown in chapter 6.3.

All incoming and outgoing transmittals and documents shall be transmitted at the following address:

Mr. Giorgio Danieli Contractor Project Manager e-mail: [email protected]

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

Page 10 / 27

Mrs. Lorena Jerkovic Document Controller 51000 Rijeka, A. Colonnella 2, Croatia Tel.: 00 385 51 651 908 Fax: 00 385 51 651 940 e-mail: [email protected]

6.1 ORGANIZATION OF PROJECT FILES The CPM in collaboration with the DC shall establish the list of the “incoming” and “outgoing” files, and the related logs:  

for the OWNER; On the basis of any other classifications the PM wishes to use.

This system shall be kept active, and updated with any new items, for the entire duration of this project. The DC carries out the following activities:   

organises the file, labels the back of the file volumes, to facilitate consultation, Prepares the logs and keeps them updated.

6.2 HANDLING OF CORRESPONDENCE DOCUMENTS All correspondence between CONTRACTOR and OWNER should be approved and signed by CPM, who decides the distribution list and necessary actions.

6.3 HANDLING OF TECHNICAL DOCUMENTS Management of CONTRACTOR’s project Technical documents should be carried out accordingly to its Quality System and the following flow chart:

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

Covering Consequent actions documents

Flow chart

Page 11 / 27

Action by

START

Discipline check Document issued for comments/approval / reissued / revised by Contractor

IDC Form

Interdisciplinary check Archiving documents

Contractor

Updating MDR Sending / receiving documents Insert OWNER comments Insert OWNER comments

Contractor

Archiving transmittals transmittal

Updating LOG’s Documents review and comment / approve

OWNER comments

Sending / receiving documents

OWNER

(when required)

YES Sending documents NO

transmittal Document issued approved for construction

Archiving documents

Contractor

Updating MDR Updating LOG’s Implementation of documents

All involved persons

END

All documents issued for this project shall be signed by the Originator (Prepared), Checker (Verified) and CONTRACTOR’s Project Manager (Approved), in the absence of the CPM, all documents can be signed by CIM or CEM. All documents issued by SUBCONTRACTOR shall go through their document control and approval process before being sent to the CONTRACTOR. All transfers of documentation should be accompanied with established Transmittal form. Project documents shall be approved by OWNER.

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

Page 12 / 27

6.4 HANDLING OF INCOMING TECHNICAL DOCUMENTS The handling of the incoming technical documents includes the following activities:    

6.4.1

Logging, Deciding the distribution list and necessary actions, Distribution. Archiving

Logging of Technical Documents

Logging of the technical documents is DC responsibilities and has to do the following actions:    

LOG the Document in MDR or other registers check the technical documents by the list of documents on the transmittal form; record the transmittal form and file the original, updating the “Transmittal Log – IN” (FORMDESFA-003 ); return to the sender, when required, a copy of the transmittal form signed for receipt;

The DC turns over all incoming technical documents to the CPM.

6.4.2

Deciding of the Distribution List and the Necessary Actions

The CPM examines the incoming external documents and indicates the distribution list, specifying the action requested by Project Team members for each document if it’s necessary.

6.4.3

Distribution of Technical Documents

The DC distributes the technical documents as per the distribution list so that they return to the CPM with the information requested.

6.4.4

Examination of Technical Documents

The persons indicated by the CPM examine received technical documents and carry out the requested actions. Comments to the technical documents have to be written, using Comment sheet form. The documents, with the comments incorporated, have to be returned to the DC.

6.4.5

Contractor’s Evaluation of Comments on Technical Documents

The CPM, or person indicated by CPM, after evaluating the comments received on the technical documents, decides to:   

reject the documents, returning them with the comments to the originator for the preparation of a new revision; Approve them, upon approval document should be sent to OWNER for review/approval; Approve them, upon approval document should be issued for IFC (Issued for Construction) to the OWNER.

The OWNER evaluates the documents and returns them as R – Reviewed, WC - reviewed with comments,

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

Page 13 / 27

or RWMC – Reviewed with Minor Comments.

6.4.6

Updating of the MDR

The DC updates the MDR, on the basis of the CPM’s instructions, throughout the life of the project, preparing each time a new revision to be issued.

6.4.7

Approval of the MDR

The CPM approves the MDR, after the PE has checked the document. The DC arranges the distribution of the updated MDR to all Project Team members, and to any other specified by CPM, including the OWNER. MDR will be issued to OWNER on monthly basis.

6.4.8

Handling of Master Documentation

The DC organises, manages, and keeps the master documentation up to date replacing each document with the latest revision. Prior revisions shall be stamped “SUPERSEDED”

6.5 HANDLING OF OUTGOING TECHNICAL DOCUMENTS The DC handles all outgoing technical documentation, prepared according to this Procedure, and approved by the CPM, in the following manner:    

files the document originals; prepares the Transmittal form (FORM-DESFA-001), which is to be sent to the receiver; updates the “Transmittal Log – OUT” (FORM-DESFA-002) and MDR Take the different numbers and filing system for outgoing documentation to the OWNER, and the other one for outgoing documentation to the Subcontractor’s.

6.6 TECHNICAL DOCUMENTS REFERENCES All Technical documents shall be written in the English and shall bear the Project references, as displayed on the cover of this document and as described below in detail.

6.6.1

Technical Documents Template

A Technical document cover page and title block format, will display the following:  Project Title – OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH PRESSURE PIPELINE  Owner Logo, Main Contractor Logo, Contractor Logo;  Title of Document  Document Number;  Issue Date and Revision number, Description of issue;  Area for Originator, Checker and Engineering and OWNER approval sign-offs The Technical document Template is shown in Attachment 1 and it is prepared in Word format. Project Document, shall always include as minimum the following sections (drawings excluded):

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

Page 14 / 27

Each Technical Document shall contain the table “Revision Status Log” which shall be positioned after page with table of contents.

6.6.2

Technical Drawing Template

Technical Drawing Template used for the Drawings in this Project corresponds to the requirements of CONTRACTOR’s document system. The CONTRACTOR Technical Drawing Template is shown in Attachment 2 and it is prepared in AutoCAD 2004 (DWG) format. In case that newer AutoCAD is used, drawing will be always saved in 2004 format. Drawing identification table placed in the bottom right side of the template shall be filled according to this procedure.

6.6.3

Technical Documents Checks

Each Technical document prepared utilising the Technical document Template, shall be checked as follows. 

Self-Check – Check made by the Originator on his own work.

On completion of the document the Originator shall sign off the original document in order to confirm the correctness of his work. One clean copy shall be forwarded at this stage to the respective Lead Discipline Engineer for further processing.  Discipline Check – Check made by a Discipline Specialist (Checker). Discipline Check shall be carried out by the Discipline function. A qualified person, different form the originator, shall subject each design deliverable to a Discipline Check.  Inter-discipline Check – if required. Check regarding item(s) interfacing with other design disciplines, performed by the respective Discipline Specialist. The PE shall be responsible for deciding which documents shall be subject to IDC and by which disciplines.

6.6.4

Documents development phases

Phases of document development shall be defined, as it is described bellow:

PHASE

PROGRESS

Start Date of the document

0%

Issued for Internal Review

10%

Issued for Comments / Approval (IFA)

60%

Issued for Construction (IFC)

100%

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

Page 15 / 27

NOTE: Documents issued for Information (I1) shall be issued to OWNER after Internal Review cycle and will have 100% progress.

Engineering documents shall be issued with status clearly indicated in the description column of title block as follows:   

Issued (or Re-issued in case of any further rev ) for Internal Review Issued (or Re-issued in case of any further rev ) for comments / approval Issued (or Re-issued in case of any further rev ) for construction

OWNER will review and comment on the document within maximum of 10 calendar days. Urgent documents may require shorter review period, but it shall never be less than two working days. Documents / drawings returned by OWNER with comments shall be reviewed by relevant Originator. Whenever these comments can be incorporated without further questions the document / drawing shall be revised by the Originator, rechecked by the Checker approved by CPM and issued as “Issued for construction”. Upon document issue in new revision, the previous one shall be stamped “SUPERSEDED”.

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

Page 16 / 27

6.7 DOCUMENT NUMBERING

Control of issued documents is established through the Master Document register (MDR). Each technical document (drawings, specifications, calculations, technical reports) originated for this Project by CONTRACTOR and by its SUBCONTRACTORS shall be assigned with an unequivocal OWNER’s identification number as per the scheme as follows:

6.7.1

Codification for Technical Documents

Document code as per the following structure:

A–B–C–D–E-F

(A)

Project Code:

DSF-1101401

(B)

Contract No.:

436

(C)

Unit No.:

6300

(D)

Document subject according to Annex 1

(E)

Document category according to Annex 2

(F)

Document Serial Number

Example: DSF-1101401-436-6300-CNV-STU-001

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

6.7.2

Page 17 / 27

Codification for Technical Specifications

Specification code as per the following structure:

A–B–C–D–E

(A)

Project Code:

DSF-1101401

(B)

Contract No.:

436

(C)

Specification Code:

SPC

(D)

Specification subject according to Annex 1

(E)

Specification Serial Number:

1XX – for Material Technical Specifications 2XX – for Job Technical Specifications

Example: DSF-1101401-436-SPC-CON-201

6.7.3

Codification for Drawings

Drawing code as per the following structure:

A–B–C–D–E-F

(A)

Project Code:

DSF-1101401

(B)

Contract No.:

436

(C)

Unit Code:

6300

Note: In case of Issue of Standard Drawings the above Unit Number shall be replaced by the code STD.

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

(D)

Page 18 / 27

XXX/ZZ

The first part XXX designates this drawing Category according to the Annex 3 and the second part ZZ designates the Drawing Subject and is valid only for the category 55 (pipeline plans and longitudinal sections) as follows:

01 – for recording plans 02 – for longitudinal sections

(E)

Drawing Size:

0 – for drawing standard size A0 1 – for drawing standard size A1 2 – for drawing standard size A2 3 – for drawing standard size A3 4 – for drawing standard size A4 N – for non-standard size drawings

(F)

Drawing Serial Number:

a.) For the Drawings category 03 (Annex 3) as follows:

001, 002 etc. for Engineering Flow Diagrams 101, 102 etc. for Process Flow, Utility Balance, Block Flow Diagrams 201, 202 etc. for Materials of Construction diagrams 301, 302 etc. for Design Pressure / Temperature Diagrams 401, 402 etc. for packaged Unit Diagrams

b.) For all other drawings: Serial Number

Example: DSF-1101401-436-6300-93-2-001

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

6.7.4 (D)

Page 19 / 27

ANNEX 1 – Codes for Technical Documents and Technical Specifications Subject

The following are the letters for the types of technical documents (3) to be used in the documents identification code: D ADM

Administration

COA

Coating

CON

Construction

CPR

Cathodic Protection

DCC

Document Control

ENV

Environmental

GEO

Geological

GET

Geotechnical

NAV

Naval

NDT

Non Destructive Testing

PCO

Project Control

PLN

Pipeline (Natural Gas Service)

POS

Positioning

PRC

Procurement

PRJ

Project Engineering

PRM

Project Management

QAC

Quality Assurance / Control

SAF

Safety

SEI

Seismic

STA

Stress Analysis

STR

Structural (Steel Structures)

SUR

Survey

TOP

Topographical

WEL

Welding

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

6.7.5

Page 20 / 27

ANNEX 2 – Codes for Technical Document Category (E)

The following are the letters for the types of technical documents (3) to be used in the documents identification code: E

6.7.6

CHT

Chart

CLC

Calculation

DAB

Data Book

DAT

Data Sheet

IND

Index

LST

List

MAN

Manual

MST

Method Statement

MTO

Material Take Off

PHL

Philosophy

PLN

Plan

PRC

Procedure

REG

Register

REP

Report

REQ

Requisition

SCH

Schedule

SHT

Sheet

SOW

Scope of Work

SPE

Specification

STU

Study

GEN

General Document

Forms – Records

Forms – Records shall be numbered as follows:

DESFA – FORM-xxx

xxx – progressive number

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

6.7.7

Page 21 / 27

ANNEX 3 – Codes for Drawings Category

D

6.7.8

01

Plot Plan and elevations

46

Steel Structures

55

Pipeline plans & Longitudinal sections

59

Pipe Supports

78

Cathodic Protection

89

Pre-commissioning (heads, layouts,…)

90

Rigging Laouyts

91

Survey dwgs – Scale 1:1000

92

Survey dwgs – Details

93

Survey dwgs – Scale 1:5000

94

Survey dwgs – Scale 1:50000

95

Survey maps

96

Anchor Patterns

97

Vessels Equipment, Layouts

98

Pipeline installation aids (heads, clamps,…)

99

Installation sequence drawings (story boards)

Sheet Number (Drawings)

Each drawing issued regarding this procedure shall contain sheet number. Sheet number shall consist of two numerical digit starting from "01".

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

6.7.9

Page 22 / 27

Revision Number

Documents circulated internally for review / comments can be assigned with revision number “0” (zero) (text in the description of revision shall be “Issued for Internal Review). Document ready to be submitted to the OWNER for comments / approval, it shall be assigned with revision number “A1” (text in the description of revision shall be “Issued for Comments / Approval”). In case of resubmission of a document following the OWNER comments subsequent numbers (i.e. A2, A3.,) shall be assigned until the document is finally approved. Once the document has been approved by the OWNER, it shall be re-issued with revision code “C1” (text in the description of revision shall be “Approved for Construction”). In case of re-submission of a document following the OWNER comments subsequent numbers (i.e. C2, C3.) shall be assigned until the document is finally approved. Document ready to be submitted to the OWNER for Info, it shall be assigned with revision number “I1” (text in the description of revision shall be “Issued for Information”). CONTRACTOR does not expect comments on such documents, but in case of required changes document will be issued in next revision (I2, I3, etc.).

6.8 ELECTRONIC FILING OF DOCUMENTS All documents shall be stored in the computer system, in the OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Project dedicated area. The document number together with the revision number shall constitute the name of the electronic file of each document, for example: DSF-1101401-436-6300-SAF-MAN-0400_A1.doc

All drawings shall be stored in AutoCAD 2004 version. The drawing number together with the sheet number and revision number shall constitute the name of the electronic file of each drawing, for example: DSF-1101401-436-6300-5501-3-0700_A1.dwg

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

Page 23 / 27

6.9 FINAL DOCUMENTATION

Prior to issue the final As-Built document/drawings CONTRACTOR shall submit to OWNER for review/comments As-Built documents/drawings. The final As-Built drawings must fully conform to the final arrangement. The final As-Built drawings shall be based on the drawings issued for construction but shall include modifications, alterations, corrections or remarks concerning changes effected during construction. Documents to be included in the As–built shall be defined by issuing “As built Dossier Index” (Doc. No. DSF1101401-436-6300-PCO-IND-0303) and shall be sent to OWNER for approval. Subcontractor shall submit to CONTRACTOR a proposed Index of As-Built Documentation for approval prior commencement of the Supply of the Work. CONTRACTOR shall also submit to OWNER the final “As-built” drawings and documents in digital file form in CD-ROM’s. The drawings shall be submitted in standard DXF or DWG format for AutoCAD latest release. All other final Technical Documentation (reports, tables, lists, etc…) shall be also submitted in “Microsoft Office Word/Excel” files.

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DSF-1101401-436-6300-DCCPRC-0302 DOCUMENT CONTROL PROCEDURE REV. A1

7.

Page 24 / 27

ATTACHMENTS

Attachment 1 – Technical Document Template - Word format for technical documents consisting more than 1 page (pages 7) Attachment 2 – Technical Drawing Template – AutoCAD format (pages 1/1) Attachment 3 – Transmittal Form (page 1)

Attachment 1 – Technical document Template

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DOCUMENT TITLE

DSF-1101401-436-6300-xxx-xxxxxxx REV. X

Page 1 / 7

DOCUMENT TITLE

Rev

Date

Description of Revision

Prepared

Checked

Approved

Owner

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DOCUMENT TITLE

DSF-1101401-436-6300-xxx-xxxxxxx REV. X

Page 2 / 7

INDEX 1.  INTRODUCTION ...................................................................................................................... 4  1.1  PROJECT OVERVIEW ..................................................................................................... 4  1.2  PIPELINE SYSTEM DESCRIPTION ................................................................................. 4  2.  DEFINITIONS AND ABBREVIATIONS .................................................................................... 5  2.1  DEFINITIONS ................................................................................................................... 5  2.2  ABBREVIATIONS ............................................................................................................. 6  2.3  REFERENCES.................................................................................................................. 6  3.  RESPONSIBILITIES AND OBLIGATIONS ............................................................................... 6  4.  SCOPE OF DOCUMENT ......................................................................................................... 6  5.  HEADING 01 (PROCEDURE DESCRIPTION) ........................................................................ 7  5.1  HEADING02 (STYLE HEADING 02, FONT: ARIAL 10PT) ............................................... 7  5.1.1.  TITLE 03 (STYLE HEADING 03, FONT: ARIAL 10PT) .............................................. 7  6.  ATTACHMENTS ....................................................................................................................... 7 

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DOCUMENT TITLE

DSF-1101401-436-6300-xxx-xxxxxxx REV. X

AMENDMENTS AND REVISIONS

Amendment and revision

Date

Page

Description

Page 3 / 7

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DOCUMENT TITLE

DSF-1101401-436-6300-xxx-xxxxxxx REV. X

1.

INTRODUCTION

1.1

PROJECT OVERVIEW

Page 4 / 7

Public Natural Gas System Operator (DESFA) of Greece plans to install an N.G.T.S. Offshore Natural Gas Pressure Pipeline Varnavas-Karavos (Aliveri) whose purpose will be to supply natural gas to Evvia island. The southern landfall in Attiki is named Varnavas while the previous names used for this landfall are Ag. Apostoli or Grammatiko. The northern landfall in Evvia is named Karavos which is also indicated as Aliveri landfall. The maximum water depth along the 20” Gas Pipeline route is approx. 70m (MSL).

Figure 1-1 – Natural Gas Pressure Pipeline Varnavas-Karavos route layout 1.2

PIPELINE SYSTEM DESCRIPTION

The offshore pipeline system consist of an 20” Natural Gas High Pressure Pipeline from the battery limit at Varnavas landfall, Attiki to the battery limit at Karavos landfall at Evvia island. The length of the new 20” Natural Gas High Pressure Pipeline is about 14.2 km. The 20” Natural Gas High Pressure Pipeline will consist of the two offshore sections, joined together offshore by Above Water Tie In method. The Varnavas side offshore pipeline section commences at the KP -0.020 and finishes at AWTI Target point at KP 13.360 in water depth of 31.2m. Along the pipeline section route, maximum water depth is 70m. The Karavos side offshore pipeline section commences at the KP 14.205 and finishes at AWTI Target point at KP 13.360 in water depth of 31.2m. Along the pipeline section route, maximum water depth is 31.2m. Both pipeline sections will be manufactured from carbon steel with internal corrosion coating.

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DOCUMENT TITLE

DSF-1101401-436-6300-xxx-xxxxxxx REV. X

2.

DEFINITIONS AND ABBREVIATIONS

2.1

DEFINITIONS

Page 5 / 7

The following definitions will be applicable in this document:

CONTRACTOR

CONSORTIUM SAIPEM - ELTER

OWNER

DESFA – HELLENIC GAS TRANSMISSION SYSTEM OPERATOR S.A.

PROJECT

Detailed Engineering, Procurement Of Materials & Construction Of The Offshore Part Of The Stefani-Aliveri Natural Gas High Pressure Pipeline

PROJECT MANAGER

Means, respectively, the entity and the person appointed by OWNER to provide project management services

SITE

Means the lands, waters and other places on, under, in or trhough which the WORKS are to be performed including offshore installations, floating construction equipment, vessels (including the area covered by approved anchor patterns) design offices, workshops and places where equipment, materials or supplies are being obtained, storied or used for the purposes of the CONTRACT and any and all other places where the PERMANENT WORKS are to be executed and to which PLANT and Materials are to be delivered and any other places as may be specified in the CONTRACT as forming part of the SITE.

SUBCONTRACTOR

Selected Sub-Contractor to perform the work described in this document

SUPERVISING ENGINEER

Means the company(ies) appointed by OWNER to carry out the Construction Supervision duties, as well as the review of the detailed design issued by CONTRACTOR, as defined in Clause 2 hereof and in other CONTRACT DOCUMENTS.

WORKS

Means all CONTRACTOR’s services and supplies to be rendered and PLANT furnished in accordance with the CONTRACT including both TEMPORARY WORKS and PERMANENT WORKS. Without limitation to items set out in the CONTRACT DOCUMENTS, the WORKS include everything of whatever nature that is required for the achievement of the objective of the CONTRACT, except for any exclusions that are specifically itemized in the CONTRACT DOCUMENTS.

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DOCUMENT TITLE

DSF-1101401-436-6300-xxx-xxxxxxx REV. X

2.2

ABBREVIATIONS

The following abbreviations will be applicable in this document:

CPM

2.3

Contractor Project Manager

REFERENCES

Ref.

Document No.

Document Title

1 2 3 4 5 6 7 8 9

3.

RESPONSIBILITIES AND OBLIGATIONS

Text (Style P1, Font: Arial 10 pt) Bullet (Style P1, Font: Arial 10pt)

Text (Style P1, Font: Arial 10pt)

4.

SCOPE OF DOCUMENT

Text (Style P1, Font: Arial 10 pt) Bullet (Style P1, Font: Arial 10pt)

Text (Style P1, Font: Arial 10pt)

Page 6 / 7

OFFSHORE PART OF THE STEFANIALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Contract No. 436/11

DOCUMENT TITLE

DSF-1101401-436-6300-xxx-xxxxxxx REV. X

5.

HEADING 01 (PROCEDURE DESCRIPTION)

Text (Style P1, Font: Arial 10 pt) Bullet (Style P1, Font: Arial 10pt)

Text (Style P1, Font: Arial 10pt) 5.1

HEADING02 (STYLE HEADING 02, FONT: ARIAL 10PT)

Text (Style P1, Font: Arial 10 pt) Bullet (Style P1, Font: Arial 10pt)

Text (Style P1, Font: Arial 10pt)

5.1.1.

Title 03 (Style Heading 03, Font: ARIAL 10pt)

Text (Style P1, Font: Arial 10 pt) Bullet (Style P1, Font: Arial 10pt)

Text (Style P1, Font: Arial 10pt)

6.

ATTACHMENTS

Attachment 1 - Text (Style P1, Font: Arial 10pt) Attachment 2 - Text (Style P1, Font: Arial 10pt)

Page 7 / 7

Attachment 2 – Technical Drawing Template

Attachment 3 – Transmittal Form

Form no.: FORM-DESFA-0001 Rev. 01 DatE: 17.11.2011

TRANSMITTAL FORM Pag. 1 of 1

CLIENT: DESFA- HELLENIC GAS TRANSMISSION SYSTEM OPERATOR S.A.

PROJECT NAME: OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH PRESSURE PIPELINE Project No.: DSF-1101401 CONTRACT No.: 436/11

Ref.No.:

Distribution

Date: Correspondence number: From: SAIPEM To: Address:

Subject: Quantity:

ACTION CODE: 1 = For Approval 2 = For Comment 3 = For Information No.off

RESPONSE CODE: 4= For Bid 5= For Construction 6= For Design Document No.

A = Approved B = Approved on condition

Rev.

C= Unnaceptable D= No comment - For info only Title / Description

Action Code

1

Transmitted by: Date: PLESE SIGN AND RETURN COPY Received by: Date:

This document is property of Saipem Mediterranean Services Llc who will safeguard its rights according to the civil and penal provisions of the law.

Resp. Code

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF