METHOD STATEMENT UE Construction Sdn Bhd

Page No. : 1 of 6 Revision : 2 Issued : Oct 2001

UEC/MS/BR570/AR/001

Electrified Double Track Project Between Ipoh and Rawang CONTROLLED COPY NO:

METHOD STATEMENT FOR CONSTRUCTION OF ACCESS ROAD TO BR 570 - SG. BATANG PADANG (CH 232.316)

(PACKAGE KAMPAR TO BIDOR)

Prepared by Sheikh Faizal

Date

Reviewed by Mohd Fauzi

Date

Approved by B.T Tee

Date

METHOD STATEMENT UE Construction Sdn Bhd

Page No. : 2 of 6 Revision : 2 Issued : Oct 2001

UEC/MS/BR570/AR/001

Electrified Double Track Project Between Ipoh and Rawang IMPORTANT: The information contained herein is the proprietary property of UE CONSTRUCTION SDN BHD. The holder agrees to the following: 1. Not to reproduce; copy; reveal; publish; or, distribute it in whole or any portion of in without authorisation; and, 2. To maintain this document in confidence.

CONTENTS 1.0

SCOPE

2.0

MATERIALS

3.0

EQUIPMENT & RESOURCES

4.0

METHOD

5.0

QUALITY CONTROL PROCEDURE

6.0

HEALTH, SAFETY AND ENVIRONMENT

7.0

TRACK POSSESSION

8.0

SUMMARY OF FORMS

9.0

DOCUMENTATION

METHOD STATEMENT UE Construction Sdn Bhd

Page No. : 3 of 6 Revision : 2 Issued : Oct 2001

UEC/MS/BR570/AR/001

Electrified Double Track Project Between Ipoh and Rawang

1.0

SCOPE This method statement outlines and describes the scope of work, construction sequence, safety and other related items generally applicable for the construction of the proposed access road to Abutment A2 RB 570 – Sg Batang Padang. The proposed access is through R.O.W. from Tapah Road Station. The scope of works shall include: a) Construction of a new 6.0m wide access road. b) Widening existing tracks to achieve 6.0m width. c) Relocation of services if necessary. d) Provide temporary earth drain where appropriate. e) Provide new pipe culvert where required. f) Maintaining drain within access boundary. g) Construction of wash trough if necessary. h) Construction of silt trap if necessary. i) Provide necessary traffic management scheme if necessary. j) Obtaining all necessary approvals from local authorities.

2.0

MATERIALS Materials to be used will be : a) Suitable materials (Sand or Earth) b) Pipe culverts c) Crusher run d) Barriers and signages where appropriate.

3.0

EQUIPMENT & RESOURCES

3.1

The following is a list of equipment to be used. However, the actual number of units would depend on the area involved.

Page No. : 4 of 6 Revision : 2 Issued : Oct 2001

METHOD STATEMENT UE Construction Sdn Bhd

UEC/MS/BR570/AR/001

Electrified Double Track Project Between Ipoh and Rawang a) Survey equipment b) Licensed lorry/dump truck c) Excavator/backhoe d) Compactor e) Back pusher f) Water bowser to control dust when necessary 3.2

All plants and machinery will be with valid documents or licences.

4.0

METHOD

4.1

Project Engineer (PE) to carry out joint inspection with Project Management Consultant (PMC) or Supervising Engineer (SE) or both at the proposed route for approval and to confirm the requirements and identify any obstacles.

4.2

Identify biomass disposal site.

4.3

Obtain approval relocation

from

Tenaga

4.4

Obtain approval relocation.

from

Telekom

4.5

Obtain approval relocation.

4.6

Inform Jabatan Kerja Raya (JKR) and Majlis regarding construction of the access road.

4.7

Install appropriate warning and traffic controlling signs such as “Awas”, “Kurangkan Laju”, and “Kenderaan Berat Keluar/Masuk” as per JKR’s Arahan Teknik.

4.8

To provide flagmen at the entrance of the access (if necessary).

4.9

Relocate Telekom pole routes, TNB pole routes and 100mm  LAP water pipes which is under the scope of permanent relocation by DRB utilities subcontractor.

4.10

Carry out site clearance from CH 232325 to CH 232525 as per Method Statement for Site Clearing inclusive of stripping topsoil and dispose surplus material to approved dumping area. (Ref : UEC/MS/GEN/M/002)

4.11

Site clearance from CH 232525 to CH 233175 to be done by Emrail/DRB.

4.12

Excavate and remove unsuitable material where instructed by SE and dispose to approved dumping area.

4.13

Provide 600 mm  pipe culvert at specified location.

from

Nasional Malaysia

Lembaga

Air

Berhad

(TNB)

for

services

Berhad

(TMB)

for

services

Perak

(LAP) Daerah

for

services

Tapah

(MDT)

METHOD STATEMENT UE Construction Sdn Bhd

Page No. : 5 of 6 Revision : 2 Issued : Oct 2001

UEC/MS/BR570/AR/001

Electrified Double Track Project Between Ipoh and Rawang 4.14

Provide temporary drainage alongside the proposed access road where required.

4.15

Supply, spread, level and compact suitable material to a maximum of 500mm thick.

4.16

Supply, spread, level and compact 300mm thick crusher run for the running surface.

4.17

However, changes may be made to the above method of construction and alignment of the proposed access road to suit existing ground condition and local requirements subject to PMC/SE approval.

5.0

QUALITY CONTROL PROCEDURE Not applicable.

6.0

HEALTH, SAFETY AND ENVIRONMENT

6.1

Work will be carried out in accordance with the Project Safety Plan.

6.2

Toolbox meeting will be carried out on construction area at regular intervals to ensure compliance with the Safety Plan and familiarity with accident and emergency procedures.

6.3

Conduct safety induction course to workers before commencement of work.

6.4

Provide PPE to all workers including safety helmet, safety shoe, vest, ear protector, etc.

6.5

Provide signboards to warn workers and public of dangers associated with construction works.

6.6

Advanced traffic warning signs will be positioned in place along and at entrance of access roads and designated flagmen will be used when working in the vicinity of existing roads if required.

6.7

Ensure all affected utilities are relocated or protected prior to commencement of work.

6.8

Water bowser will be used to control dust when necessary.

6.9

Inspect all machinery at site and certificate and is safe to operate.

7.0

TRACK POSSESSION

ensure

that

it

has

competent

Not applicable. Track monitoring and rectification of railway track will be provided as per method statement UEC/MS/BR570/RM/006 if necessary.

8.0

SUMMARY OF FORMS Not applicable.

METHOD STATEMENT UE Construction Sdn Bhd

Page No. : 6 of 6 Revision : 2 Issued : Oct 2001

UEC/MS/BR570/AR/001

Electrified Double Track Project Between Ipoh and Rawang

9.0

DOCUMENTATION

9.1

Appendix A - Proposed access road (Plan and cross section).

9.2

Appendix B - Proposed traffic management at access entrance.

9.3

Appendix C – Construction of temporary culvert.

9.4

Appendix D – Bill of Quantities.