COMMISSIONING PLAN For The

PROJECT NAME Commissioning Plan Overview The purpose of the Commissioning Plan is to provide a clear and concise roadmap for the implementation of the commissioning process and to provide a record of the results of the commissioning process. Since the Commissioning Plan contains the results of the process, it can be considered a living document where the results are added throughout the process. Therefore, to simplify the upkeep of the document, the basic process and procedures to be followed throughout the project are detailed in the main body of the Commissioning Plan. The materials and information that are developed during the commissioning process are included in the appendices.

Systems to Be Commissioned The systems and equipment to be commissioned are outlined in the table below.

Systems to Be Commissioned System 

Pre‐Functional  Checklists 

Equipment  Startup 

Functional  Testing 

Sampling Rate 

Remarks 

Div 22 ‐ Plumbing  Domestic Cold/Hot Water Heaters

Yes

Yes

Yes

100%

P, BAS

Eyewash Showers

No

No

Yes

100%

P

Medical Gas System

No

No

No

NA

P –Installation only

Commissioning Plan – Nov 2013

Date

Page 1.1

Systems to Be Commissioned System 

Pre‐Functional  Checklists 

Equipment  Startup 

Functional  Testing 

Sampling Rate 

Remarks 

Mixing Stations

No

Yes

Yes

100%

P

Trap Primers

No

No

Yes

100%

P

Div 23 – HVAC Air Handling Units

Yes

Yes

Yes

100%

H, P, E, BAS, TAB

OR Air Handling System

Yes

Yes

Yes

100%

H, P, E, BAS, TAB

Makeup Air Units

Yes

Yes

Yes

100%

H, P, E, BAS, TAB

Heating Water/Chilled Water Coils Pipe Correctly

Yes

Yes

Yes

100%

H, P, BAS, TAB

Chilled Water System

Yes

Yes

Yes

100%

H, P, E, BAS, TAB

Boiler System

Yes

Yes

Yes

100%

H, E, BAS, TAB

Condensate Return Systems

Yes

Yes

Yes

100%

H, BAS

Building Automation System

Yes

Yes

Yes

100%

H, BAS, TAB

VAV/CV Boxes

Yes

Yes

Yes

TBD

H, E, BAS, TAB

Venturi Air Valves

Yes

Yes

Yes

100%

H, E, BAS, TAB

Fan Coil Units

Yes

Yes

Yes

100%

H, E

Steam System (Including PRV)

Yes

Yes

Yes

100%

H, TAB

Stairwell Pressurization Fans

Yes

Yes

Yes

100%

H, E, BAS, TAB

Exhaust Fans

Yes

Yes

Yes

100%

H, E, BAS, TAB

Laboratory Exhaust System

Yes

Yes

Yes

100%

H, E, BAS, TAB

Commissioning Plan – Nov 2013

Date

Page 1.2

Systems to Be Commissioned System 

Pre‐Functional  Checklists 

Equipment  Startup 

Functional  Testing 

Sampling Rate 

Remarks 

Laboratory Ventilation System

Yes

Yes

Yes

100%

H, E, BAS, TAB

Reheat Coils

Yes

Yes

Yes

100%

H, E, BAS, TAB

Radiant Panels

Yes

Yes

Yes

100%

H, E, BAS, TAB

Computer Room HVAC Systems

Yes

Yes

Yes

100%

H, E, BAS, TAB

Ductwork - Pressure Testing

Yes

No

No

TBD

H, TAB – Witness

Piping - Flushing

No

No

No

TBD

H, TAB – Witness

Piping - Pressure Testing

No

No

No

TBD

H, TAB – Witness

Div 26 – Electrical Utility service entrance Switchgear Standby Generator Systems Generator Paralleling Switchgear Generator Power Distribution Systems Utility Power Unit Substations Generator Power Unit Substations Automatic Transfer Switches Normal Power Distribution Systems Life Safety Power Distribution Systems Commissioning Plan – Nov 2013

Yes

Yes

Yes

100%

E

Yes

Yes

Yes

100%

E

Yes

Yes

Yes

100%

E

Yes

Yes

Yes

100%

E

Yes

Yes

Yes

100%

E

Yes

Yes

Yes

100%

E

Yes

Yes

Yes

100%

E

Yes

Yes

Yes

TBD

E

Yes

Yes

Yes

100%

Date

E Page 1.3

Systems to Be Commissioned System  Critical Power Distribution Systems Essential Equipment Power Distribution Systems Lighting Controls

Pre‐Functional  Checklists 

Equipment  Startup 

Functional  Testing 

Sampling Rate 

Remarks 

Yes

Yes

Yes

100%

E

Yes

Yes

Yes

100%

Yes

Yes

Yes

TBD

E

E

E

Div 27 - Communications Nurse Call / Code Blue Public Address and Mass Notification Systems Healthcare Intercommunications and Program Systems

Yes

Yes

Yes

TBD

Yes

Yes

Yes

TBD

Yes

Yes

Yes

TBD

E

E

Div 28 – Electronic Safety and Security Fire Detection and Alarm Systems UPS Systems

Yes

Yes

Yes

TBD

E

Yes

Yes

Yes

100%

E

Notes:      

H   ‐  TAB ‐  E    ‐  P    ‐  BAS ‐ 

Heating   Testing, Adjusting and Balancing   Electrical    Plumbing  Building Automation and Controls 

Commissioning Plan – Nov 2013

Date

Page 1.4

Commissioning Communications and Document Distribution The following table outlines the submittal and distribution requirements for various documents used in the commissioning process.

Communication Distribution Matrix  

 

 

 

 

Document 

Prepared by: 

Submitted to: 

Copies to: 

Comments 

Pre-Design Meeting Minutes

Owner's Project Requirements

Basis of Design (Design Narrative)

CxA

Owner

Design Team



Owner



Design Team



Design Team



CxA



Owner



CxA



CM



CM

Commission Specification

CxA



Design Team



Owner

Preliminary Commissioning Plan

CxA



Owner



Design Team



CM

Design Development Documents

Commissioning Plan – Nov 2013



Design Team

Date

CxA

Page 1.5

Communication Distribution Matrix  

 

 

 

 

Document 

Prepared by: 

Submitted to: 

Copies to: 

Comments 

DD Review Comment Log

CxA



Owner

Construction Documents

Design Team



CxA

CD Review Comment Log

CxA



Owner

Commissioned Systems Narrative

Design Team



Owner



CxA



Design Team



Design Team

Commissioned Systems Single Line Diagram

Design team



CxA



Owner

Final Commissioning Plan

CxA



Owner



Design



CM



CxA



Design Team



CM



HC



PC



EC

Construction Kick off Meeting Minutes



CM

Owner

Architect Duration Schedule for Commissioning Activities

Commissioning Plan – Nov 2013



CxA

Date

Owner

Initial submission included in Final Commissioning Plan

Page 1.6

Communication Distribution Matrix  

 

 

 

 

Document 

Prepared by: 

Submitted to: 

Copies to: 

Comments 



Submittals and Shop Drawings on Commissioned Systems

CM

GC



CxA

Submittals and shop Drawings are submitted to the Design Team as separate submission



CM



GC

Design team comments and/or approval provided separately



HC



PC



EC



Owner

GC HC PC EC

Submittal and Shop Drawing Comment Log

Construction Phase Controls Meeting Minutes

Pre-Functional Checklists

Commissioning Plan – Nov 2013

CxA

CxA

CxA

Date



Design Team



BAS



HC



Owner



GC



CM



PC



HC



EC

Page 1.7

Communication Distribution Matrix  

 

 

 

 

Document 

Prepared by: 

Submitted to: 

Copies to: 

Comments 

Executed Pre-Functional checklists

CM



CxA



CxA



CM



GC



HC



PC



EC



BAS



Owner



CM



GC



HC

HC PC EC GC Contractor Startup Reports

CM HC PC EC GC

Contractor Startup Report Comment Log

Preliminary Functional Test Procedures

Commissioning Plan – Nov 2013

CxA

CxA

Date

Page 1.8

Communication Distribution Matrix  

 

 

 

 

Document 

Prepared by: 

Submitted to: 

Copies to: 

Comments 

Preliminary Functional Test Procedure Comments

Owner



PC



EC



BAS



CxA



Owner



CM



GC



HC



PC



EC



BAS



Owner

CM GC HC PC EC BAS

Final Functional Test Procedures

Executed Functional Test Procedures

Commissioning Plan – Nov 2013

CxA

CxA

Date

Page 1.9

Communication Distribution Matrix  

 

 

 

 

Document 

Prepared by: 

Submitted to: 

Copies to: 

Comments 

TAB Plan

TAB Plan Review Comment Log

TAB Final Report

TAB Final Report Comment Log

O & M Manuals

O & M Manual Comment Log



TAB



CxA



TAB

CxA

CxA

CxA

CxA

TAB

HC



Design Team



Owner



Design Team



Design Team



CxA

HC



Owner



TAB



Design Team



Design Team



CxA



Design Team





CxA

Design Team

CxA



Owner

Systems Manual Review Comments

Owner



CxA

Date

Owner



Systems Manual

Commissioning Plan – Nov 2013



Page 1.10

Communication Distribution Matrix  

 

 

 

 

Document 

Prepared by: 

Submitted to: 

Copies to: 

Comments 

Training Plans



HC

CxA

PC



Owner



CM

EC GC Training Plan Comment Log

Warranty and Other Closeout Documents



HC



Owner



PC



CM



EC



GC

HC



CM



CxA

PC



GC



Design Team

CxA



CM



Owner

Design Team



GC

CxA



Owner



CM



GC



HC



PC



EC



Design

CxA

EC GC Warranty and Closeout Comment Log

Systems Functional Testing and Field Reports

Commissioning Plan – Nov 2013

Date

Page 1.11

Communication Distribution Matrix  

 

 

 

 

Document 

Prepared by: 

Submitted to: 

Copies to: 

Comments 

Team

Construction Observations Field Reports

CxA



Owner



CM

Preliminary Commissioning Report

CxA



Owner

Commissioning Report Review Comments

Owner



CxA

Final Commissioning Report

CxA



Owner

Construction Meeting Minutes

Architect



Owner

Commissioning Status Reports

Commissioning Plan – Nov 2013

CxA

Date



Owner



CM



All Contract ors



Designe rs



All Contract ors



CxA



Design Team

Page 1.12

Communication Distribution Matrix  

 

 

 

 

Document 

Prepared by: 

Submitted to: 

Copies to: 

Comments 

Master Issues Log



CxA

Owner CM



BAS



HC



PC



EC



GC



TAB



Designe rs

Change Orders, ASI, RFI

Design Team



Owner



CxA

Deferred/Seasonal Testing Field Report

CxA



Owner



BAS



HC



PC



EC



GC



TAB



Designe rs

Deferred/Seasonal Executed Functional Test Procedures

Commissioning Plan – Nov 2013



CxA

Date

Owner

Page 1.13

Communication Distribution Matrix  

 

 

 

 

Document 

Prepared by: 

Submitted to: 

Copies to: 

Comments 

Lesson Learned/Warranty Review Meeting Minutes

CxA

Master Issues Log

CxA

Commissioning Plan – Nov 2013





Date

Owner



CM



Design Team

Owner

Page 1.14

COMMISSIONING TEAM ROLES AND RESPONSIBILITIES Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

Design

Design

Review Review Owner's Project Owner's Project Requirement document. Requirements

Review Design Narrative

Review the Design Narrative

Owner



Prepare and issue Owner's Project Requirements based on specific requirements.

CxA



Review and comment on Owner's Project Requirements. Submit comments to Owner

Design Team



Review for understanding project requirements.

Owner



Receive and distribute Basis of Design documents to CxA.



Review Design Narrative document.



Provide comment log to Owner and Design Team.

CM

CxA

Commissioning Plan – Nov 2013

Date

Page 1.15

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

Design

Commissioning Specifications

Prepare Commissioning Specifications

Design Team



Prepare Design Narrative to describe design approach.

Owner



Review, comment and approve Cx specifications as part of project manual review.



Prepare Cx Specifications Sections.



Prepare systems commissioning specifications.

Design Team



Incorporate commissioning specifications into Project Manual.

Owner



Review Cx Plan.

CM



Provide comments to Cx.

Design Team



Review Cx Plan relative to Design Team roles and responsibilities.

Owner



Review and approve Commissioning Plan.



Provide comments to CxA.

CM

CxA

Design

Preliminary Commissioning Plan

Construction

Final Commissioning

Prepare Preliminary Commissioning Plan that describes the Commissioning Process, Commissioning Team with specific Roles and Responsibilities. The Commissioning Plan will include description of systems to be commissioned. Based on the final construction documents, update the preliminary Commissioning Plan to identify

Commissioning Plan – Nov 2013

Date

Page 1.16

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

Plan

specific systems to be commissioned. The Final Commissioning Plan will also include specific individual roles and responsibilities and preliminary Pre-Functional Checklists and Functional Test Plans for systems to be commissioned.

CM

CxA

Design Team

BAS

TAB

Construction

Construction Commissioning Kick Off

Conduct an initial commissioning meeting with Contractors and commissioning team members. The purpose of the meeting will be

Commissioning Plan – Nov 2013

Owner

Date



Review Cx Plan relative to CM and installing subcontractor's roles and responsibilities.



Provide comments to CxA.



Prepare Final Commissioning Plan.



Prepare preliminary Pre-Functional Checklists.



Prepare Preliminary Systems Functional Performance Test Procedures.



Issue to Owner.

 

Incorporate comments into Cx Plan revisions as necessary. Review Cx Plan relative to Design Team roles and responsibilities.



Provide comments to Owner.



Review Cx Plan relative to BAS roles and responsibilities.



Provide comments to CxA.



Review Cx Plan relative to TAB roles and responsibilities.



Provide comments to CxA.



Review commissioning schedule data.



Coordinate with Contractors to incorporate commissioning activities into project schedule.

Page 1.17

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

meeting

Construction

Submittal and Shop Drawing Review List

to establish the purpose and proposed process for commissioning this facility in the construction, acceptance and warranties phases of the project. Review the individual roles and responsibilities of each participating commissioning team member as specified in the Construction Documents

Based on final construction documents, prepare a list of selected submittals and shop drawings for review by the Commissioning Agent.

Commissioning Plan – Nov 2013



Prepare and issue commissioning activities schedule, including durations and procedures.



Review project schedule prepared by CM.

Design Team



None.

CM



Incorporate commissioning activities into Master Construction Schedule.

BAS



Review project schedule prepared by CM.

TAB



Review project schedule prepared by CM.

Owner



None.

CxA



Prepare list of submittals and shop drawings to be provided to the CxA.

Design Team



None.

BAS



None.

TAB



None.

CxA

CM

Date

Page 1.18

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

Construction

Controls Meeting



Schedule, facilitate and attend meeting.



Conduct Meeting.



Attend Meeting.



Coordinate and schedule Mechanical, Electrical and Controls Electrical sub-contractors to attend meeting.

BAS



Attend meeting.

TAB



None.

After receipt of the Controls Owner Submittal, participate in or conduct meeting with the Owner's representatives, Owner's Control Vendor, Owner's TAB contractor, CxA Mechanical/Electrical Design team, mechanical sub-contractor to review the Controls Submittal and mechanical/ electrical systems to be installed. Design Team Focus will be on how the selected sequences of operation interact with the mechanical/ electrical systems and how well they meet GC the owner's requirements.

Commissioning Plan – Nov 2013

Date

Page 1.19

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

Construction

Pre-Functional Checklists

Prepare Pre-Functional Checklists for systems, components and/or equipment to be commissioned. These Pre-Functional Checklists will be used to document completion of system, component and/or equipment installation and to determine system readiness for functional testing. Pre-Functional Checklists should be completed by the installing contractors to document the installation process. Completed Pre-Functional Checklists are to be submitted to the commissioning agent a minimum of seven days prior to testing. Completed PreFunctional Checklists will be spot checked by the commissioning

Commissioning Plan – Nov 2013

Owner



Review checklists.

CM



Provide comments to CxA.

CxA



Prepare preliminary checklists.



Issue to Owner for review.



Incorporate changes into final checklists as necessary.

Design Team



None.

CM



Provide copies of sub-contractor QC installation checklists to CxA for review.



Review checklists prepared by CxA.



Provide comments to CxA.

GC

Date

Page 1.20

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

agent to verify systems are ready for testing.



Review checklists prepared by CxA.



Provide comments to CxA.



Review checklists prepared by CxA.



Provide comments to CxA.

Owner



Receive and distribute Contractor Startup Reports.

CxA



Witness selected contractor equipment startups.



Review selected Contractor Startup Reports.



Provide comment log to Owner.

Design Team



Review Contractor Startup Reports.

cm



Complete Contractor Startup Reports.

BAS

TAB

Construction

Review Contractor Equipment Startup Reports

Commissioning agent will review selected equipment startup reports prepared by installing contractor. Commissioning Agent will witness selected equipment startup procedures. Seven days prior notice is required to schedule commissioning agent witnessing the startup.

Commissioning Plan – Nov 2013

Date

Page 1.21

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

Construction

Prepare Functional Test Procedures

Based on final construction documents (including applicable changes), and approved submittals, prepare Functional Test Procedures for systems to be commissioned. Draft Functional Test Procedures will be issued for review by owner, installing contractors and BAS Vendor. Final Functional Test Procedures will be prepared incorporating review comments received from owner, contractors or BAS Vendor.



Issue to CxA.

BAS



Review selected Contractor Startup Reports.

TAB



Review selected Contractor Startup Reports.

Owner



Review preliminary Functional Test Procedures.

CM



Provide comments to CxA.

CxA



Prepare preliminary Functional Test Procedures.



Issue to Contractor and BAS.



Incorporate comments into final Functional Test Procedures as necessary.

Design Team



None.

CM



Distribute preliminary Functional Test Procedures to MC, EC and other installing sub-contractors.



Review preliminary Functional Test Procedures.



Provide comments to CxA.



Review preliminary Functional Test Procedures.



Provide comments to CxA.

GC

BAS

Commissioning Plan – Nov 2013

Date

Page 1.22

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility  

Review preliminary Functional Test Procedures.



Provide comments to CxA.



Distribute TAB Plan to CxA and Design Team.



Review TAB Plan.



Provide comment log to Owner, CM and TAB.

Design Team



Review and approve TAB Plan.

CM



Review TAB Plan.



Provide comments to TAB.



Review TAB Plan.



Provide comments to Owner and CxA.



Prepare preliminary TAB Plan.



Issue to CxA and Owner.



Incorporate comments into Final TAB Plan as necessary.

Owner



Distribute TAB report to Design Team, and CxA.

CM



Approve TAB Report in consultation with Design Team and CxA.

TAB

Construction

TAB Plan Review

Review HVAC systems Test and Balance Plan prepared by the TAB Vendor. Review will be to determine general conformance with owner's requirements.

Owner CM

CxA

BAS

TAB

Construction

TAB Report Review

Review TAB Report prepared by TAB vendor following system air and water balancing. Review will be focused on TAB results that

Commissioning Plan – Nov 2013

Date

Page 1.23

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

affect system performance and/or commissioning. Specific attention will be given to equipment installation and operational issues identified by the TAB vendor.



Review TAB report.



Provide comments to Owner and Design Team.

Design Team



Review and provide recommendations to Owner.

CM



Review and submit TAB Report.

BAS



None.

TAB



Provide preliminary TAB data (daily worksheets) to CxA for preliminary review.



Prepare TAB Report.



Issue TAB report to HC, Owner and CxA.

Owner



Distribute O & M Manuals to CxA and Design Team.

CM



Review and approve O & M Manuals.

CxA



Review O & M Manuals.



Provide comment log to Owner.

Design Team



Review O & M Manuals.

HC



Prepare and issue O & M Manuals to GC.

CxA

HC GC

Construction

Review O & M Manuals

Review Operations and Maintenance Manuals submitted by contractors. Manuals will be reviewed for clarity, organization, usability and general conformance with specifications and owner's requirements.

Commissioning Plan – Nov 2013

Date

Page 1.24

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

PC EC

Construction

Construction

Prepare Systems Manuals for commissioned systems

Review Training Plans

Prepare detailed systems manuals for commissioned systems. The manuals will provide operating staff the information needed to understand and optimally operate the commissioned systems. The manuals will describe system design, components, capacity and sequences of operations. Manuals will include descriptions of interactions with other systems and common systems failure modes and responses.

Review contractor and manufacturer training plans ad agendas for general conformance with specifications and owner's

Commissioning Plan – Nov 2013

BAS



Prepare and issue BAS O & M Manuals to HC.

TAB



None.

Owner



Review and approve Systems Manuals.

CxA



Using O & M Manuals, Basis of Design, and Construction Documents, prepares Systems Manual.

Design Team



Provide Single Line Diagrams and System Narratives.

Owner



Schedule and facilitate training sessions.

CM



Maintenance staff attends training sessions.

Date

Page 1.25

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

requirements. Observe selected training for quality of training and for general conformance with training plan and agenda.



Review Training Plans.



Provide comment log.



Witness selected training sessions.

Design Team



None.

CM



In conjunction with installing sub-contractors and/or manufacturers' representatives, conduct training sessions.

BAS



Conduct BAS training sessions.

TAB



None.

Owner



Distribute warranty documents to Maintenance Staff.

CM



Review and approve warranty documents.

CxA



Review warranty documents.



Provide comment log.

Design Team



Review warranty documents and provide comments.

CM



Prepare and issue warranty documents.



Incorporate comments into final warranty documents.

CxA

HC PC EC

Construction

Warranty Review

Review contractor's and manufacturer's warranties for general conformance with specifications and owner's requirements.

Commissioning Plan – Nov 2013

Date

Page 1.26

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility  

Prepare and issue warranty documents for BAS.



Incorporate comments into final warranty documents.

Owner



Schedule, facilitate and witness systems functional testing.

CM



Maintenance staff should assist in functional testing as additional systems training opportunity.

CxA



Witness systems functional testing using previously prepared Functional Test Procedures.



Document systems testing on Functional Test Procedures.



Issue Field Reports to document deficiencies.



Update Master Commissioning Issues Log to document and track deficiencies.

Design Team



Review test documentation.

CM



HC and EC to conduct functional testing by operating systems in accordance with functional test procedures.



Make corrections, repairs or adjustments to systems during testing as directed by the Owner.



Correct outstanding deficiencies after testing as directed by the Owner.



Report corrective actions to Owner and CxA upon completion.

BAS

Construction

Systems Functional Testing

Witness and document functional testing for systems to be commissioned. Testing will be conducted as detailed on the specific Functional Test Plan for each system to be commissioned. Functional testing will require support from the HC, EC, BAS and TAB Vendors. Installing contractors should be available to respond to issues and problems identified during testing.

HC EC

Commissioning Plan – Nov 2013

Date

Page 1.27

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility  

Conduct functional testing by operating BAS in accordance with CxA directions and functional test procedures.



Assist in troubleshooting and corrective action as necessary.



Assist functional testing as directed by the Owner and functional test procedures.



Verify selected BAS data by spot measurements of air and/or water balancing data.

Owner



Approve retesting as recommended by CxA.

CM



Schedule and coordinate retesting.

CxA



Make recommendations for necessary retesting.



Coordinate with Owner to schedule retesting after deficiencies are corrected.

Design Team



None.

CM



Make necessary system repairs, adjustments and/or corrections prior to retesting.



Coordinate retesting as directed and approved by the Owner.



Conduct systems retesting by operating systems as directed by Owner and functional test procedures.

BAS

TAB

Construction

Systems Functional Retesting

Retest systems with deficiencies as recommended by the CxA and directed by the owner. (Note: Retesting is not included in the scope of commissioning services and is provided as an additional service. The costs associated with retesting maybe recovered from the Contractors in accordance with appropriate contract provisions.)

HC EC

Commissioning Plan – Nov 2013

Date

Page 1.28

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

Construction

Construction Observation

Conduct visits to the construction site to observe construction activities. Specific attention will be given to installation of mechanical, electrical, plumbing systems, and Building Envelope for general conformance with specifications and manufacturer's installation of site utilities, site improvements and building envelope construction for general conformance with plans and specifications, and manufacturer's installation requirements.

BAS



Assist in systems retesting by operating BAS as directed by Owner and functional test procedures.

TAB



None.

Owner



None.



Conduct Construction Observation visits to observe construction progress, system/equipment installation and general quality of construction.



Prepare Field Report to document general and specific observations and issues.



Update Master Issues Log to document and track specific issues reported on Field Report.



Monitor and verify corrective actions.



Update Master Issues Log to document corrective action progress and completion.



Review Master Issues Log.

CM

CxA

Design Team

Commissioning Plan – Nov 2013

Date

Page 1.29

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility  

Review Field Reports.



Review Master Issues Log.



Provide corrective actions as directed actions as directed by the owner to resolve outstanding issues.



Review Field Reports relative to BAS issues.



Review Master Issues Log relative to BAS issues.



Report progress of corrective actions relative to BAS issues.



Review Field Reports relative to issues affecting TAB.



Review Master Issues Log relative to issues affecting TAB.



Report corrective actions relative to issues affecting TAB.

Owner



Review preliminary Commissioning Report.

CM



Provide comments to CxA.



Review and approve Final Commissioning Report.



Prepare preliminary Commissioning Report.



Incorporate comments into final report.



Issue Final Commissioning Report.



None.

CM

BAS

TAB

Construction

Final Commissioning Report

Compile a comprehensive commissioning report documenting all commissioning activities, including but not limited to: Commissioning scope Test methods and results , Outstanding commissioning issues, issues log, Commissioning plan, Status reports, Submittal and O & M manual reviews, Training record, Pre-Functional Checklists, Design Review Comments.

Commissioning Plan – Nov 2013

CxA

Design Team

Date

Page 1.30

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

Construction

Master Issues Log

Maintain a Commissioning Issues Log to document commissioning issues identified during construction and functional testing. The Commissioning Issues Log will include recommended party and recommendations for resolution for the issue. The Commissioning Issues Log will also be used to document progress toward resolution and the final resolution.

Owner

CxA

Design Team

CM

BAS

Commissioning Plan – Nov 2013

Date



Review Master Issues Log.



Coordinate and direct corrective actions to resolve commissioning issues.



Provide monthly updates to Master Commissioning Log.



Provide updated Master Commissioning Log after each Construction Visit to document specific issues observed during the visit.



Update Master Issues Log to document progress on corrective actions.



Update Master Issues Log to document completion of corrective actions.



Review Masters Issues Log.



Provide status of corrective actions.



Provide notification of corrective action completion.



Review Masters Issues Log.



Provide status of corrective actions.



Provide notification of corrective action completion.



Review Master Issues Log.



Provide documentation of punch list or other issues noted by BAS vendor.



Provide status of corrective actions relative to BAS issues.



Provide notification of corrective action completion Page 1.31

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility  relative to BAS issues.



Review Master Issues Log.



Provide documentation of punch list or other issues noted by TAB.



Provide status of corrective actions relative to TAB issues.



Provide notification of corrective action completion relative to TAB issues.

Owner



Issue change orders, ASI and/or RFI.

CM



Provide copies of change orders, ASI and RFI to CxA.

CxA



Review change orders, ASI, and RFI for changes that affect system/equipment design or installation.



Incorporate changes into revised Functional Test Procedures or Pre-Functional Checklists.



Respond to RFI's.



Prepare change orders and/or ASI.



Update construction documents as necessary.



Issue RFI.



Request change orders and ASI as needed.

TAB

Design/ Construction

Review Change Orders, ASI, and RFI

Review change orders, architect's supplemental instructions and requests for information (with design team response) for issues that affect commissioning. Review is for information only and does not constitute technical or contractual approval or disapproval.

Design Team

CM

Commissioning Plan – Nov 2013

Date

Page 1.32

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility  

Monitor system changes for impact on BAS installation and/or sequences of operations.



Update BAS programming or sequences of operations to implement approved changes.



Monitor system changes for impact on TAB.



Update TAB Plan as necessary to implement approved changes.

Owner



Coordinate corrective actions with Contractors as necessary.

CxA



Periodically monitor systems operation using BAS trend data.



Prepare and issue brief narrative reports documenting issues noted during systems monitoring.



Update Master Commissioning Log with issues noted during systems monitoring.

Design Team



None.

CM



Provide corrective actions as directed by owner.

BAS



Provide corrective actions as directed by owner.

TAB



None.

Owner



Schedule, facilitate and witness deferred/seasonal testing.

CM



Maintenance Staff should assist in deferred/seasonal as additional systems training opportunity.

BAS

TAB

Warranty

Warranty

Monitor Systems Operations

Deferred and/or seasonal Testing

Monitor System operation using trend data from BAS.

Direct testing that was deferred due to lack of system readiness or for seasonal requirements. Testing will be conducted in accordance

Commissioning Plan – Nov 2013

Date

Page 1.33

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

with Functional Test Plans. Testing support will be received from the BAS Vendor and Maintenance Staff.



Witness deferred/seasonal testing using previously prepared Functional Test Procedures.



Document deferred/seasonal testing on Functional Test Procedures.



Issue Field Reports to document deficiencies.



Update Master Commissioning Issues Log to document and track deficiencies.

Design Team



None.

GM



HC and EC will conduct seasonal/deferred testing by operating systems in accordance with owner directions and functional test procedures.



Make corrections, repairs or adjustments to systems during testing as directed by the owner.



Correct outstanding deficiencies after testing as directed by the owner.



Report corrective actions to owner and CxA upon completion.



Conduct deferred/seasonal testing by operating BAS in accordance with CxA directions and functional test procedures.



Assist in troubleshooting and corrective action as necessary.



Assist deferred/seasonal testing as directed by the CxA and functional test procedures. Verify selected BAS data

CxA

HC EC

BAS

TAB Commissioning Plan – Nov 2013

Date

Page 1.34

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility  by spot measurements of air and/or water balancing data.

Warranty

PostOccupancy Warranty Checkup

Return to the project approximately 10 months into the 12 month warranty period to review the building operation with the facility staff and discuss outstanding issues related to commissioning and outstanding warranty issues. Provide suggestions for improvements. Assist facility staff in developing reports, documents and requests for service to remedy outstanding problems.

Owner



Schedule and facilitate Warranty Checkup Visit.

CM



Direct GC & BAS to provide corrective action for Warranty claims.

CxA

Commissioning Plan – Nov 2013

Date



Conduct Warranty Checkup Visit.



Interview facility users and/or maintenance staff to identify specific operational concerns.



Review maintenance staff Work Order logs for potential warranty claim issues.



Verify corrective action on outstanding unresolved issues shown on Master Issues Log.



Document other deficiencies noted during Warranty Checkup Visit.



Prepare report of potential Warranty Claims noted during Warranty Checkup Visit. Page 1.35

Commissioning Team Roles and Responsibilities  

 

 

 

 

Project  Phrase 

Cx Task 

Description 

Team Member

Responsibility 

Warranty

Final Commissioning Report Amendment

Amend Final Commissioning Report to document the Warranty Phase commissioning activities

Commissioning Plan – Nov 2013

Design Team



None.

CM



Implement corrective actions on Warranty Claims as directed by owner.

BAS



Implement corrective actions on Warranty Claims as directed by owner.

TAB



None.

Owner



Review and approve Commissioning Agent Amendment.

CxA



Prepare Final Report Amendment to document Warranty phase commissioning activities.

Date

Page 1.36

Commissioning Schedule The following is a general outline of the Commissioning Schedule for the commissioning tasks that will be performed on the project site or at the Commissioning Agent Offices:

Commissioning Schedule  

 

 

 

 

Project Phrase 

Task 

Duration 

Schedule 

Predecessors 

Design

Review Design Narrative

2 weeks

Comments submitted concurrent with design comments

Design

Commissioning Specifications

2 weeks

Specifications issued concurrent Receive drawings and specifications with CD specifications

Design

Preliminary Commissioning Plan

1 week

Preliminary Cx Plan issued concurrent CD documents

Receive drawings and specifications

Design

Focused Final Construction Document Review

2 weeks

Comment log issued 2 weeks after receipt of final CDs

Receive Final Construction Document drawings and specifications

Design

Update Design Narrative

2 weeks

Updated Design Narrative issued 2 weeks after Final CD Design Review Meeting

Final CD Design Review meeting.

Preliminary Commissioning Plan

1 week

Concurrent with Final CD Design review

Receive Final CD drawing and specifications.

Construction

Commissioning Plan – Nov 2013

Date

Receive Design Narrative

Receive Final CD Design review comments from peer reviewer.

Page 1.37

Commissioning Schedule  

 

 

 

 

Project Phrase 

Task 

Duration 

Schedule 

Predecessors 

Construction

Construction Commissioning Kick Off meeting

1 day

Scheduled by Owner

Construction

Duration Schedule for Commissioning Activities

None

Issued as part of Final Commissioning Plan

Preliminary construction schedule

Construction

Submittal and Shop Drawing Request List

None

Issued as part of Final Commissioning Plan

Final Construction Document plans and specifications

Construction

Submittal and Shop Drawing Review

2 weeks

Comment log issued 2 weeks after receipt of shop drawings and submittals

Receipt of submittal or shop drawings.

Controls Meeting

1 day

Scheduled by Owner and CM

Receive major HVAC equipment submittals.

Meeting notes issued 1 week

Receive BAS submittal with sequence of

Construction

Commissioning Plan – Nov 2013

Date

Comment log will be updated after receipt of each requested submittal.

Page 1.38

Commissioning Schedule  

 

 

 

 

Project Phrase 

Task 

Duration 

Schedule 

Predecessors 

after meeting. Construction

Pre-Functional Checklists

TBD

operations.

Preliminary checklists issued Receive equipment submittals approximately 4 months prior to Receive installing contractor's QC checklists substantial completion. Final checklists issued approximately 3 months prior to substantial completion.

Construction

Witness selected Contractor Equipment Startup

1 day

Scheduled by Individual Contractors

1 week written notice of scheduled startup

Construction

Review Contractor Equipment Startup Checklists

1 week

Comment log issued 1 week after receipt of completed checklist

Receive Startup Checklist completed by installing sub-contractor.

Construction

Prepare Functional Test Procedures

TBD

Preliminary Functional Test Procedures issued approximately 4 months prior to substantial completion.

Receive all requested equipment submittals and shop drawings. Receive BAS submittal and final sequences of operations.

Final Functional Test Procedures issued approximately 3 months prior to substantial completion Construction

TAB Review

2 weeks

Comment log issued 2 weeks after receiving TAB Plan

Receive TAB Plan

Construction

TAB Report

2 weeks

Comment log issued 2 weeks

Receive TAB Report

Commissioning Plan – Nov 2013

Date

Page 1.39

Commissioning Schedule  

 

 

 

 

Project Phrase 

Task 

Duration 

Schedule 

Predecessors 

Review

after receiving TAB Report

Construction

Review O & M Manuals

3 weeks

Comment log issued 3 weeks after receiving O & M Manuals

Receive O & M Manuals

Construction

Prepare Systems Manuals

8 weeks

Systems Manuals issued 8 weeks after receiving O & M Manuals

Receive O & M Manuals

Construction

Review Training Plans

2 weeks

Comment log issued 2 weeks after receiving Training Plans

Receive Training Plans

Construction

Warranty Review

2 weeks

Comment log issued 2 weeks after receiving Warranty documents

Receive Warranty documents

Construction

Systems Functional Testing

TBD

Functional testing to begin coordinated with construction schedule and systems completion

See separate table.

Construction

Systems Functional Retesting

TBD

TBD

Corrective actions complete

Construction

Construction Observation

1 day

Construction observations scheduled concurrent with progress meetings – approximately 2 visits per month.

None

More frequent visits may be scheduled during 3 months Commissioning Plan – Nov 2013

Date

Page 1.40

Commissioning Schedule  

 

 

 

 

Project Phrase 

Task 

Duration 

Schedule 

Predecessors 

preceding the substantial completion Cx Specialist will provide a verbal out-brief of significant issues to the CM prior to leaving the construction site. Field Report will be issued 1 week following visit. Construction

Final Commissioning Report

6 weeks

Preliminary Commissioning Report issued approximately 6 weeks after completing Functional Testing

Functional Testing completed.

Construction

Master Issues Log

2 days

Master Issues Log will be updated and issued following each progress meeting and/or Construction Observation visit.

Construction Observation visit and/or progress meeting.

Construction

Review Change Orders, ASI, and RFI

TBD

Ongoing though out construction

Receive Change Orders, ASI or RFI

Warranty

Deferred and/or seasonal Testing

TBD

Seasonal testing scheduled approximately 6 months after completing Functional Testing

Seasonal changeover (i.e. summer-to winter or winter-to summer)

Deferred testing schedule to be determined Commissioning Plan – Nov 2013

Date

Completion of system installation or corrective action completed

Page 1.41

Commissioning Schedule  

 

 

 

 

Project Phrase 

Task 

Duration 

Schedule 

Predecessors 

Warranty

Post-Occupancy Warranty Checkup

Commissioning Plan – Nov 2013

TBD

Scheduled approximately 10 months after substantial completion

Date

Initial Functional Testing is complete. Seasonal/deferred testing is complete.

Page 1.42

Functional Testing Activities The following is a general outline of the Commissioning Schedule for the Functional Testing activities that will be performed at the construction site.

Functional Testing Activities System

Test Duration

Schedule

Predecessors

Notes

Plumbing Systems Domestic Hot Water System

2 - 4 hours

1 week prior notice of startup by CM

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational, TAB water balance

Witness equipment startup

Eyewash showers

1 hour

1 week prior notice by PC

Installation Complete

Review of Installation

Medical Gas System

TBD

1 week prior notice by PC

Installation Complete

Review of Installation during site observation visits and review of test reports

Commissioning Plan – Nov 2013

Date

Functional testing of system

Page 1.43

Functional Testing Activities System

Test Duration

Schedule

Predecessors

Notes

Mixing Stations

TBD

1 week prior notice by PC

Installation Complete

Review of Installation during site observation visits and verify temperature operation

Trap Primers

TBD

1 week prior notice by PC

Installation Complete

Review of Installation during site observation visits and verify operation

Pre-Functional Checklist, Equipment startup, BAS Controls Operational, TAB air & water balance

Functional testing of all air handling units

Pre-Functional Checklist, Equipment startup, BAS Controls Operational, TAB air & water balance

Functional testing of OR air handling units

Pre-Functional Checklist, Equipment startup, BAS Controls Operational, TAB air & water balance

Functional testing of makeup air unit

Mechanical Systems Air Handling Units

1 day per AHU 1 week prior notice of startup by HC Functional Testing TBD

OR Air Handling System

1 day per AHU 1 week prior notice of startup by HC Functional Testing TBD

Makeup Air Unit

4 Hours

Commissioning Plan – Nov 2013

1 week prior notice of startup by HC

Date

Page 1.44

Functional Testing Activities System

Test Duration

Schedule

Predecessors

Notes

Functional Testing TBD Heating Water/Chilled Water Coils

Performed with AHU review

1 week prior notice of startup by HC

Pre-Functional Checklist, Equipment startup, BAS Controls Operational, TAB air & water balance

Functional testing of makeup air unit

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational, TAB water balance

Functional testing of system

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational, TAB water balance

Functional testing of system

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational, TAB water balance

Functional testing of system

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface

Review BAS sequences of

Functional Testing TBD Chilled Water System

1 day

1 week prior notice of startup by HC Functional Testing TBD

Boiler System

1 Day

1 week prior notice of startup by HC Functional Testing TBD

Condensate Return Systems

4 hours

1 week prior notice of startup by HC Functional Testing TBD

BAS

1 day for headCommissioning Plan – Nov 2013

1 week prior notice of startup

Date

Page 1.45

Functional Testing Activities System

Test Duration end testing

Schedule by HC

Predecessors Operational, TAB air & water balance

Functional Testing TBD

Notes operation. Witness selected equipment startup. Functional testing of BAS in conjunction with air handler units, chillers, and other systems controlled. Review of BAS graphics and other human-interface equipment. Review of trend data to support functional testing and verify proper operation of systems controlled

VAV/CV boxes

1 day per AHU 1 week prior system notice of startup by HC

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational, TAB air balance

Functional testing of all boxes

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational, TAB air balance

Functional testing of all valves

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational, TAB air and water

Functional testing of equipment and controls

Functional Testing TBD Venturi Air Valves

1 day total for all valves

1 week prior notice of startup by HC Functional Testing TBD

Fan Coil Units

2 hours per unit

Commissioning Plan – Nov 2013

1 week prior notice by HC

Date

Page 1.46

Functional Testing Activities System

Test Duration

Schedule

Predecessors

Notes

balance Steam System (Including PRV)

4 hours

1 week prior notice of startup by HC

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational

Witness equipment startup

Stairwell Pressurization Fans

2-4 hours per system

1 week prior notice of startup by HC

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational, TAB air balance

Functional testing of equipment and controls

Exhaust Fans

1 -2 hours per system

1 week prior notice of startup by HC

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational, TAB air balance

Witness selected equipment startup.

Laboratory Exhaust System

1 day per system

1 week prior notice of startup by HC

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational, TAB air balance

Witness selected equipment startup.

Laboratory Ventilation System

1 day per system

1 week prior notice of startup by HC

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational, TAB air balance

Witness selected equipment startup.

Reheat Coils

Tested with VAV Boxes

1 week prior notice of startup by HC

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational, TAB complete

Functional testing of a representative sampling of equipment

Commissioning Plan – Nov 2013

Date

Functional testing of system

Functional testing of a representative sampling of equipment in conjunction with testing air handling units or other systems

Page 1.47

Functional Testing Activities System

Test Duration

Schedule

Predecessors

Notes

Radiant Panels

1/4 hour per Panel

1 week prior notice of startup by HC

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational, TAB complete

Functional testing of a representative sampling of equipment

Computer Room HVAC Systems

1 Day per System

1 week prior notice by HC

Pre-Functional Checklist, Equipment startup, Controls & BAS Interface Operational, TAB air and water balance

Functional testing of equipment and controls

TAB

4 Hours

1 week prior notice by HC

TAB activities complete

Verification of TAB measurements on representative sampling quantity

Minimum – copy of preliminary balance report

Ductwork

1 day

1 week prior notice by HC

Ductwork complete

Witness selected duct pressure testing

Piping

1 Day

1 week prior notice by HC

Piping Complete

Witness selected Flushing and Pressure testing

Electrical Systems

Commissioning Plan – Nov 2013

Date

Page 1.48

Electrical Utility Services

1 day

1 week prior notice of startup by CPM

 

Pre-startup testing. Witness startup of service equipment

Switchboards

1 day

1 week prior notice of startup by CPM

 

Pre-startup testing. Witness startup of switchboards

Grounding & Bonding Electrical Systems

1 day

1 week prior notice of 3rd party testing by CPM



Witness 3rd party ground resistance testing

Panelboards

1 – 2 hours per panel

1 week prior notice of startup by CPM

 

Pre-startup testing Witness startup of selected panelboards.

Enclosed Switches & Circuit Breakers

1 – 2 hours per switch or breaker

1 week prior notice of startup by CPM

 

Pre-startup testing Witness startup of selected equipment

Motor Controls

Included in other testing

TBD



Functional testing in conjunction with system testing of equipment controlled

Transfer Switches

Included in other testing

TBD



Functional testing in conjunction with generator testing

Interior Lighting

2 – 4 hours

TBD



Functional testing of daylighting and occupancy sensors

Exterior Lighting

1 – 2 hours

TBD



Functional testing of DDCcontrolled contactors in conjunction with DDC testing

Emergency Lighting

Included in other testing

TBD



Functional testing in conjunction with loss of utility power testing.

Commissioning Plan – Nov 2013

Date

Page 1.49

Diesel Engine Driven Generator Assembly

10 – 12 hours

1 week prior notice of startup by CPM

 

Witness load bank testing Functional testing for compliance with NFPA 110

Lightning Protection for Structures

1 – 2 hours

TBD



Review of UL Master Label

Fire Alarm & Smoke Detection Systems

2 days

TBD



Functional testing of features not tested by local-authority (i.e. battery draw-down tests)

Intrusion Detection

2 – 4 hours

TBD



Functional testing of a representative sample of devices

Video Surveillance System

2 – 4 hours

TBD



Functional testing of a representative sample of devices

Role 

Person 

Company 

Address 

Phone 

Cell 

E­mail 

Commissioning    Authority  (CxA) 

 

 

 

 

 

Owner's    Representative 

 

 

 

 

 

Architect 

 

 

 

 

 

 

Mechanical  Engineer 

 

 

 

 

 

 

Plumbing/Fire  Protection  Engineer 

 

 

 

 

 

 

Electrical 

 

 

 

 

 

 

Commissioning Plan – Nov 2013

Date

Page 1.50

Engineer  Construction  Manager 

 

 

 

 

 

 

General  Contractor 

 

 

 

 

 

 

HVAC  Contractor 

 

 

 

 

 

 

Controls  Contractor 

 

 

 

 

 

 

TAB  Contractor 

 

 

 

 

 

 

Plumbing  Contractor 

 

 

 

 

 

 

Electrical  Contractor 

 

 

 

 

 

 

Commissioning Plan – Nov 2013

Date

Page 1.51