Distance Setting Excel
Short Description
setting calculation...
Description
PTD-HA/3000467425/ED2.121.001.W-0 Document no.- Rev - 2
SIEMENS
RELAY SETTING CALCULATION 220 KV DURSHED FEEDER - 2 DISTANCE PROTECTION RELAY
NEW 400/220KV SUBSTATION AT WARANGAL TRANSMISSION SYSTEM ASSOCIATED WITH GRID STRENGTHENING FOR TAMILNADU & ANDRA PRADESH LOA REF: C-55807-S119A-7/LOA-1/2020 DATED 31.03.2006 POWERGRID CORPORATION OF INDIA LIMITED
Name
Department
Telephone
Place
Date
LAXMINARAYAN
PTD-HA
0124-2846155
GURGAON
-
Signature
Author: Approval:
Rev
Date
Revised items
1
04.10.08
FOR APPROVAL
2
19.12.08
SETTING REVISED
Page no
ALL
Remarks
Name of
Name of
reviser
Approver
KNR
RL
KNR
RL
Total pages
Siemens Ltd., PTD Division Copying this document, and giving it to others and the use or communication of the contents thereof, are forbidden without express authority. Offenders are liable to the payment of damages. All rights are reserved in the event of the grant of patent or registration of a utility model or design
25
400/220 KV WARANGAL SUBSTATION 220kV DURSHED FEEDER SIEMENS DISTANCE PROTECTION RELAY SETTING CALCULATION 1.0 Relay Data: 1.01 ANSI No.
=
21
1.02 Description
= Distance + Over Voltage Prot.
1.03 Make
= SIEMENS
1.04 Model No.
= 7SA522
2.0 Input Data: 2.01 System voltage
=
220
KV
2.02 Source substation
= WARANGAL
2.03 Conductor used
= ACSR Kundah
2.04 Protected Line length
=
71
(R1=R2)
=
0.0791
Ω/KM
(X1=X2)
=
0.403
Ω/KM
R0
=
0.255
Ω/KM
X0
=
1.51
Ω/KM
2.07 Longest Line length
=
50
2.08 Conductor used
= ACSR KUNDAH
400/220KV
Km
2.05 Positive & Negative Sequence Line Impedance /KM
2.06 Zero Sequence Line impedance per KM
Km
2.09 Positive & Negative Sequence Line Impedance /KM (R1=R2)
=
0.079
Ω/KM
(X1=X2)
=
0.403
Ω/KM
R0
=
0.255
Ω/KM
X0
=
1.51
Ω/KM
2.11 Shortest Line length (Durichedu 1 Fdr.)
=
71
2.12 Conductor used
= ACSR KUNDAH
2.10 Zero Sequence Line impedance per KM
1 of 25
Km
2.13 Positive & Negative Sequence Line Impedance /KM (R1=R2)
=
0.079
Ω/KM
(X1=X2)
=
0.403
Ω/KM
R0
=
0.255
Ω/KM
X0
=
1.51
Ω/KM
Magnitude
Angle
2.14 Zero Sequence Line impedance per KM
2.15 3Ф fault current at WARANGAL 220 KV Substation = 2.16 1Ф fault current at WARANGAL 220 KV Substation
40000
-79
Magnitude
Angle
=
40000
-79
2.17 Tower Footing Resistance
=
10
2.18 Direction - Zone I
= Forward
2.19 Direction - Zone II
= Forward
2.20 Direction - Zone III
= Forward
2.21 Direction - Zone IV
= Reverse
2.22 Direction - Zone V
= Disabled
2.23 Direction - Zone 1B
= Forward
2.24 Time delay - Zone I
=
0
sec
2.25 Time delay - Zone II
=
0.4
sec
2.26 Time delay - Zone III
=
1
sec
2.27 Time delay - Zone IV
=
1
sec
2.28 Time delay - Zone V
=
∞
sec
2.29 Time delay - Zone 1B
=
0
sec
Ω
3.0 Err:511 3.01 C.T Ratio
= 1600-800/1A
3.02 Selected Ratio
=
800
3.03 Class
=
PS
3.04 KPV
=
800
2 of 25
/
1
V
3.05 Iex
=
(>): Phase Voltage Stages
9.4
Uph-e> :
Initial Stage for Minor Over voltage
110%of Un=
9.5
TUph-e> :
Time Delay for Initial Stage Setting
=
=
14 of 25
ON 69.85 5
Volts Secs
Protected Length
Time Delay
120%
0
9.6
Uph-e>> :
9.7
TUph-e>> : Time delay for Longer Setting
=
9.8
Uph-e>(>) RESET: Drop out to Pick Up Ratio
=
9.9
CURR.SUP.Uph-e>:
= ON
Stage for Higher Voltage
150%ofUn=
95.25 0
Volts Secs
0.95
11.0 DIRECTIONAL EARTH FAULT 11.1
Zero Sequence Source
=
3 x KV2
Impedance (Z0s)
√3 x 220 x Min.1ph Fault Current = 3 x 220^2 / (√3 x 220 x 12)
11.2
Line Impedance of the Protected Line
11.3
Earth Fault Current Pick-up
=
= 31.755196
Ω
Forward
Ω
= 20% of rated Full load current / C.T ratio
Setting(3I0>) = (0.2 x MVA / (√3 x KV)) / C.T ratio = (0.2 x 150000 / (1.732 x 220)) / ( 800 / 1) = 0.0984149
≈
0.1 A
11.4
Earth Fault Current Pick-up setting(3I0>>)
= Disabled
11.5
Direction
= Forward
11.6
Curve
= Normal Inverse
11.7
TMS
= 0.337
11.8
Zero Sequence Voltage Stage 3U0>
= Enabled
11.9
Characteristic Angle
= Enabled
11.10 Tele protection Earth Fault:
= N/A
Directional Comparison Pick-up 13.0 SOTF O/C 12.1 SOTF OVER CURRENT
= Enabled
12.2 The magnitude of the current for picking up of the switchon to fault
I>>>
= 2.5 times the FLC = 2.5 x 150000 / (1.732 x 220) 15 of 25
= 12.3 Setting adopted = 2.5 times FLC/ CTR
I>>>
16 of 25
984
A
1.23
A
400/220 KV WARANGAL SUBSTATION 220kV DURSHED FEEDER SIEMENS DISTANCE PROTECTION RELAY SETTING 1 Device Configuration No.
Function
Scope
103
Setting Group Change Option
Disabled
110
Trip mode
3 pole
112
Phase Distance
Quadrilateral
113
Earth Distance
Quadrilateral
120
Power Swing detection
Enabled
121
Teleprotection for Distance prot.
POTT
122
DTT Direct Transfer Trip
Disabled
124
Instantaneous HighSpeed SOTF Overcurrent
Enabled
125
Weak Infeed (Trip and/or Echo)
Disabled
126
Backup overcurrent
131
Earth fault overcurrent
Time Overcurrent Curve IEC
132
Teleprotection for Earth fault overcurr.
Disabled
133
Auto-Reclose Function
1 AR-cycle
134
Auto-Reclose control mode
with Trip and Action time
135
Synchronism and Voltage Check
Disabled
136
Over / Underfrequency Protection
Disabled
137
Under / Overvoltage Protection
Enabled
138
Fault Locator
Enabled
140
Trip Circuit Supervision
Disabled
Disabled
2 General Device Settings 2.1 Group Device No.
Settings
Value
610
Fault Display on LED / LCD
Display Targets on TRIP only 15 of 25
640
Start image Default Display
image 1
3 Power System Data 1 3.1 Group Power System Data 1; Group Transformers No.
Settings
Value
201
CT Starpoint
towards Line
203
Rated Primary Voltage
220 KV
204
Rated Secondary Voltage (Ph-Ph)
110 V
205
CT Rated Primary Current
800.00 A
206
CT Rated Secondary Current
1A
210
U4 voltage transformer is
Usy2 transformer
211
Matching ratio Phase-VT To Open-Delta-VT
1.73
215
Matching ratio Usy1 / Usy2
1
220
I4 current transformer is
Neutral Current (of the protected line)
221
Matching ratio I4/Iph for CT's
1
3.2 Group Power System Data 1; Group Power System No.
Settings
Value
207
System Starpoint is
Solid Earthed
230
Rated Frequency
50 Hz
235
Phase Sequence
L1 L2 L3
236
Distance measurement unit
km
237
Setting format for zero seq.comp. format
Zero seq. comp. factors RE/RL and XE/XL
0238A
Earth Fault O/C: setting for 1pole AR
all stages together
3.3 Group Power System Data 1; Group Breaker No.
Settings
Value
0240A
Minimum TRIP Command Duration
0.10 sec
0241A
Maximum Close Command Duration
0.10 sec
242
Dead Time for CB test-autoreclosure
1.00 sec
4 Settings groups
16 of 25
4.1 Group Power System Data 2; Group Power System No.
Settings
Value
1103
Measurement: Full Scale Voltage (100%)
220 KV
1104
Measurement: Full Scale Current (100%)
800.00 A
1105
Line Angle
78.9
1211
Angle of inclination, distance charact.
78.9
1107
P,Q operational measured values sign
not reversed
1110
x' - Line Reactance per length unit
0.164276
1111
Line Length
71.0 KM
1116
Zero seq. comp. factor RE/RL for Z1
0.74
1117
Zero seq. comp. factor XE/XL for Z1
0.92
1118
Zero seq. comp.factor RE/RL for Z1B...Z5
0.74
1119
Zero seq. comp.factor XE/XL for Z1B...Z5
0.92
4.2 Group Power System Data 2; Group Line Status No.
Settings
Value
1130A
Pole Open Current Threshold
0.10 A
1131A
Pole Open Voltage Threshold
30 V
1132A
Seal-in Time after ALL closures
0.20 sec
1133A
minimal time for line open before SOTF
0.25 sec
1134
Recognition of Line Closures with
CBaux OR Current or Manual close BI
1135
RESET of Trip Command
with CBaux open AND I < PoleOpenCurrent
1136
open pole detector
with measurement (U/I,trip,pickup,CBaux)
1140A
CT Saturation Threshold
5.0 A
1150A
Seal-in Time after MANUAL closures
0.30 sec
1151
Manual CLOSE COMMAND generation
NO
1152
MANUAL Closure Impulse after CONTROL
4.3 Group Power System Data 2; Group Trip 1-/3-pole No.
Settings
Value
17 of 25
1155
3 pole coupling
with Trip
1156A
Trip type with 2phase faults
3pole
4.4 Group Distance protection, general settings; Group General No.
Settings
Value
1201
Distance protection
ON
1202
Phase Current threshold for dist. Meas.
0.10 A
1211
Angle of inclination, distance charact.
78.9
1208
Series compensated line
NO
1232
Instantaneous trip after SwitchOnToFault
with Zone Z1B
1241
R load, minimum Load Impedance (ph-e)
129.1 Ohms
1242
PHI load, maximum Load Angle (ph-e)
37 °
1243
R load, minimum Load Impedance (ph-ph)
258.1 Ohms
1244
PHI load, maximum Load Angle (ph-ph)
45 °
1317A
Single pole trip for faults in Z2
NO
1357
Z1B enabled before 1st AR (int. or ext.)
YES
4.5 Group Distance protection, general settings; Group Earth faults No.
Settings
Value
1203
3I0 threshold for neutral current pickup
0.10 A
1204
3U0 threshold zero seq. voltage pickup
5V
1207A
3I0>-pickup-stabilisation (3I0> /Iphmax)
0.15
1209A
criterion of earth fault recognition
3I0> OR 3U0>
1221A
Loop selection with 2Ph-E faults
all loops
4.6 Group Distance protection, general settings; Group Time Delays No.
Settings
Value
1210
Condition for zone timer start
with distance pickup
1305
T1-1phase, delay for single phase faults
0.00 sec
1306
T1multi-ph, delay for multi phase faults
0.00 sec
1315
T2-1phase, delay for single phase faults
0.40 sec
18 of 25
1316
T2multi-ph, delay for multi phase faults
0.40 sec
1325
T3 delay
1.00 sec
1335
T4 delay
1.00 sec
1345
T5 delay
N/A
1355
T1B-1phase, delay for single ph. Faults
0.00 sec
1356
T1B-multi-ph, delay for multi ph. Faults
0.00 sec
4.7 Group Distance zones (quadrilateral); Group Zone Z1 No.
Settings
Value
1301
Operating mode Z1
Forward
1302
R(Z1), Resistance for ph-ph-faults
2.109 Ohms
1303
X(Z1), Reactance
9.156 Ohms
1304
RE(Z1), Resistance for ph-e faults
11.418 Ohms
1305
T1-1phase, delay for single phase faults
0.00 sec
1306
T1multi-ph, delay for multi phase faults
0.00 sec
1307
Zone Reduction Angle (load compensation)
0°
4.8 Group Distance zones (quadrilateral); Group Zone Z1Bexten. No.
Settings
Value
1351
Operating mode Z1B (_verreach zone)
Forward
1352
R(Z1B), Resistance for ph-ph-faults
3.008 Ohms
1353
X(Z1B), Reactance
13.734 Ohms
1354
RE(Z1B), Resistance for ph-e faults
12.236 Ohms
1355
T1B-1phase, delay for single ph. Faults
0.00 sec
1356
T1B-multi-ph, delay for multi ph. Faults
0.00 sec
1357
Z1B enabled before 1st AR (int. or ext.)
YES
4.9 Group Distance zones (quadrilateral); Group Zone Z2 No.
Settings
Value
1311
Operating mode Z2
Forward
1312
R(Z2), Resistance for ph-ph-faults
3.680 Ohms
19 of 25
1313
X(Z2), Reactance
17.168 Ohms
1314
RE(Z2), Resistance for ph-e faults
12.848 Ohms
1315
T2-1phase, delay for single phase faults
0.40 sec
1316
T2multi-ph, delay for multi phase faults
0.40 sec
1317A
Single pole trip for faults in Z2
NO
4.10 Group Distance zones (quadrilateral); Group Zone Z3 No.
Settings
Value
1321
Operating mode Z3
Forward
1322
R(Z3), Resistance for ph-ph-faults
4.362 Ohms
1323
X(Z3), Reactance
20.650 Ohms
1324
RE(Z3), Resistance for ph-e faults
13.833 Ohms
1325
T3 delay
1.00 sec
4.11 Group Distance zones (quadrilateral); Group Zone Z4 No.
Settings
Value
1331
Operating mode Z4
Reverse
1332
R(Z4), Resistance for ph-ph-faults
0.527 Ohms
1333
X(Z4), Reactance
2.289 Ohms
1334
RE(Z4), Resistance for ph-e faults
2.855 Ohms
1335
T4 delay
1.00 sec
4.12 Group Distance zones (quadrilateral); Group Zone Z5 No.
Settings
Value
1341
Operating mode Z5
Inactive
1342
R(Z5), Resistance for ph-ph-faults
N/A
1343
X(Z5)+, Reactance for Forward direction
N/A
1344
RE(Z5), Resistance for ph-e faults
N/A
1345
T5 delay
N/A
1346
X(Z5)-, Reactance for Reverse direction
N/A
4.13 Group Power Swing
20 of 25
No.
Settings
Value
2002
Power Swing Operating mode
Z2 to Z5 Block
2006
Power swing trip
YES
2007
Trip delay after Power Swing Blocking
0.08 sec
4.14 Group Teleprotection for Distance prot. No.
Settings
Value
2101
Teleprotection for Distance protection
PUTT(Z1B)
2102
Type of Line
Two Terminals
2103A
Time for send signal prolongation
0.07 sec
2109A
Transient Block.: Duration external flt.
oo sec
2110A
Transient Block.: Blk.T. after ext. flt.
0.05 sec
4.15 Group Instantaneous HighSpeed SOTF Overcurrent No.
Settings
Value
2401
Inst. High Speed SOTF-O/C is
ON
2404
I>>> Pickup
2.5 A
4.16 Group Measurement Supervision; Group Balance / Summ. No.
Settings
Value
2901
Measurement Supervision
ON
2902A
Voltage Threshold for Balance Monitoring
10
2903A
Balance Factor for Voltage Monitor
0.8
2904A
Current Balance Monitor
0.1
2905A
Balance Factor for Current Monitor
0.05
2906A
Summated Current Monitoring Threshold
0.10 A
2907A
Summated Current Monitoring Factor
0.1
2908A
T Balance Factor for Voltage Monitor
5 sec
2909A
T Current Balance Monitor
5 sec
4.17 Group Measurement Supervision; Group Fuse Fail. Mon. No.
Settings
Value
21 of 25
2910
Fuse Failure Monitor
ON
2911A
Minimum Voltage Threshold U>
50 V
2912A
Maximum Current Threshold I<
0.20 A
2913A
Maximum Voltage Threshold U< (3phase)
5V
2914A
Delta Current Threshold (3phase)
0.10 A
2915
Voltage Failure Supervision
with current supervision
2916A
Delay Voltage Failure Supervision
3.00 sec
4.18 Group Measurement Supervision; Group VT mcb No.
Settings
Value
2921
VT mcb operating time
0 ms
4.19 Group Measurement Supervision; Group Load Angle No.
Settings
Value
2941
Limit setting PhiA
200 °
2942
Limit setting PhiB
340 °
2943
Minimum value I1>
0.05 A
2944
Minimum value U1>
20 V
4.20 Group Earth fault overcurrent; Group General No.
Settings
Value
3101
Earth Fault overcurrent function
ON
3102
Block E/F for Distance protection
with every Pickup
3174
Block E/F for Distance Protection Pickup
in each zone
3103
Block E/F for 1pole Dead time
YES
3104A
Stabilisation Slope with Iphase
10%
3109
Single pole trip with earth flt.prot.
YES
3170
2nd harmonic ratio for inrush restraint
15%
3171
Max.Current, overriding inrush restraint
7.50 A
3172
Instantaneous mode after SwitchOnToFault
with Pickup and direction
3173
Trip time delay after SOTF
0.00 sec
22 of 25
4.21 Group Earth fault overcurrent; Group 3I0>>> No.
Settings
Value
3110
Operating mode
Inactive
3111
3I0>>> Pickup
N/A
3112
T 3I0>>> Time delay
N/A
3113
Instantaneous trip via Teleprot./BI
N/A
3114
Instantaneous trip after SwitchOnToFault
N/A
3115
Inrush Blocking
N/A
4.22 Group Earth fault overcurrent; Group 3I0>> No.
Settings
Value
3120
Operating mode
Inactive
3121
3I0>> Pickup
N/A
3122
T 3I0>> Time Delay
N/A
3123
Instantaneous trip via Teleprot./BI
N/A
3124
Instantaneous trip after SwitchOnToFault
N/A
3125
Inrush Blocking
N/A
4.23 Group Earth fault overcurrent; Group 3I0> No.
Settings
Value
3130
Operating mode
Inactive
3131
3I0> Pickup
N/A
3132
T 3I0> Time Delay
N/A
3133
Instantaneous trip via Teleprot./BI
N/A
3134
Instantaneous trip after SwitchOnToFault
N/A
3135
Inrush Blocking
N/A
4.24 Group Earth fault overcurrent; Group 3I0 InverseTime No.
Settings
Value
3140
Operating mode
Forward
3141
3I0p Pickup
0.10 A
23 of 25
3143
3I0p Time Dial
0.34 sec
3147
Additional Time Delay
0.00 sec
3148
Instantaneous trip via Teleprot./BI
YES
3149
Instantaneous trip after SwitchOnToFault
NO
3150
Inrush Blocking
YES
3151
IEC Curve
Normal Inverse
4.25 Group Earth fault overcurrent; Group Direction No.
Settings
Value
3160
Polarization
with U0 + IY (dual polarized)
3162A
ALPHA, lower angle for forward direction
338 °
3163A
BETA, upper angle for forward direction
122 °
3164
Min. zero seq.voltage 3U0 for polarizing
N/A
3166
Min. neg. seq. polarizing voltage 3U2
5.0 V
3167
Min. neg. seq. polarizing current 3I2
0.50 A
3168
Compensation angle PHI comp. for Sr
255 °
3169
Forward direction power threshold
0.3 VA
4.26 Group Automatic Reclosure; Group General No.
Settings
Value
3401
Auto-Reclose function
ON
3402
CB ready interrogation at 1st trip
NO
3403
Reclaim time after successful AR cycle
3.00 sec
3404
AR blocking duration after manual close
1.00 sec
3406
Evolving fault recognition
with Trip
3407
Evolving fault (during the dead time)
starts 3pole AR-cycle
3408
AR start-signal monitoring time
0.20 sec
3409
Circuit Breaker (CB) Supervision Time
3.00 sec
3410
Send delay for remote close command
∞sec
3411A
Maximum dead time extension
∞sec
24 of 25
4.27 Group Automatic Reclosure; Group 1st AR-cyle No.
Settings
Value
3450
Start of AR allowed in this cycle
YES
3451
Action time
0.20 sec
3456
Dead time after 1pole trip
1.20 sec
3457
Dead time after 3pole trip
0.50 sec
3458
Dead time after evolving fault
1.20 sec
3459
CB ready interrogation before reclosing
NO
3460
Request for synchro-check after 3pole AR
NO
4.28 Group Automatic Reclosure; Group 3pTRIP/DLC/RDT No.
Settings
Value
3430
3pole TRIP by AR
YES
3431
Dead Line Check or Reduced Dead Time
Without
3438
Supervision time for dead/ live voltage
0.10 sec
3440
Voltage threshold for live line or bus
48 V
3441
Voltage threshold for dead line or bus
30 V
4.29 Group Automatic Reclosure; Group Start AR with.. No.
Settings
Value
3420
AR with distance protection
YES
3421
AR with switch-onto-fault overcurrent
NO
3423
AR with earth fault overcurrent prot.
NO
4.30 Group Voltage Protection; Group U> Phase-Earth No.
Settings
Value
3701
Operating mode Uph-e overvoltage prot.
ON
3702
Uph-e> Pickup
69.9 V
3703
T Uph-e> Time Delay
5.00 sec
3704
Uph-e>> Pickup
95.3 V
3705
T Uph-e>> Time Delay
0.10 sec
25 of 25
3709A
Uph-e>(>) Reset ratio
0.95
4.31 Group Fault Locator No.
Settings
Value
3802
Start fault locator with
Pickup
3806
Load Compensation
YES
26 of 25
400/220kV WARANGAL SUBSTATION
SIEMENS
400/220 KV WARANGAL SUBSTATION 220kV DURSHED FEEDER ABB DISTANCE PROTECTION RELAY SETTING CALCULATION Type : ABB make REL670 System Particulars
HOLD
A
Line Parameters
1
Rated line voltage
2
Line Length
3
Max power flow in the line (assumed)
4
Postive sequence resistance
0.0791 ohms/km
5
Postive sequence reactance
0.403 ohms/km
6
Zero sequence resistance
0.255 ohms/km
7
Zero sequence reactance
1.51 ohms/km
8
Zero sequence mutual resistance (MR)
220 KV 71 KM 150 MVA
0 ohms/km
(If Parallel line in service Mutual Impedance is 60% of zero seq.) 9
Zero sequence mutual reactance (MX)
B
Adjoining line parameters
B.1
Adjacent Line(Short Line)
0 ohms/km
1
Length of adjacent line
2
Postive sequence resistance
0.079 ohms/km
3
Postive sequence reactance
0.403 ohms/km
4
Zero sequence resistance
0.255 ohms/km
5
Zero sequence reactance
1.51 ohms/km
B.2
71 KM
longest line
1
Length of longest line
50 KM
2
Postive sequence resistance
0.079 ohms/km
3
Postive sequence reactance
0.403 ohms/km
4
Zero sequence resistance
0.255 ohms/km
5
Zero sequence reactance
1.51 ohms/km
45 OF 205
400/220kV WARANGAL SUBSTATION
SIEMENS
B.3
Transformer
1
Transformer impedance in p.u
0.125
2
Transformer rating
C
Source impedance
1
Local End max. Fault MVA =1.732*220*40
2
Local End min. Fault MVA =30 % of 15241.6
4572 MVA
3
Local End Z magnitude = (220 x 220) / 15241.6
3.176 ohms
4
Local End Z argument
5
Remote End Max. Fault MVA (Assumed -Not available)
7500 MVA
6
Remote End Min. Fault MVA (Assumed -Not available)
3000 MVA
7
Remote End Z magnitude = (220 x 220) / 7500
6.45 ohms
8
Remote End Z argument
9
Postive sequence resistance at local end = line length x + ve seq. R
100 MVA
15241.6 MVA
84 deg.
84 deg.
46 OF 205
5.616 ohms
400/220kV WARANGAL SUBSTATION
SIEMENS
10
Postive sequence reactance at local end = line length x +ve seq.X
28.613 ohms
11
Postive sequence resistance at remote end = line length x +ve seq. R
5.6161 ohms
12
Postive sequence reactance at remote end = line length x +ve seq. X
28.613 ohms
D
CT and PT Detail
1
CT primary rating
2
CT secondary rating
3
PT primary rating
4
PT secondary rating
E
Relay Detail
1
Rated current
1A
2
Rated voltage
110 V
F
System Parameters
1
Arc Resistance + Tower footing resistance - Rfn
50.000 ohms
2
Rf for phase to phase fault
10.000
3
Imp Ratio = CTR / PTR
0.400
4
% for zone-1 setting
0.800
5
% of the adjoining line for Zone2
0.500
6
% of the adjoining line for Zone 3
1.100
G
Protected Line Impedance in CT secondary
1
Postive sequence resistance = line length x + ve seq. R x Imp Ratio =
2.246 ohms
2
Postive sequence reactance = line length x + ve seq. X x Imp Ratio =
11.445 ohms
3
Zero sequence resistance = line length x Z0 x Imp Ratio =
7.242 ohms
4
Zero sequence reactance = line length x Z0X x Imp Ratio =
42.884 ohms
5
Zero sequence mutual resistance = line length x MR x Imp Ratio =
0.000 ohms
6
Zero sequence mutual reactance = line length x MX x Imp Ratio =
0.000 ohms
H
Adjacent Line Impedance in CT secondary
1
Postive sequence resistance = line length x + ve seq. R x Imp Ratio =
2.244 ohms
2
Postive sequence reactance = line length x + ve seq. X x Imp Ratio =
11.445 ohms
3
Zero sequence resistance = line length x Z0 x Imp Ratio =
7.242 ohms
4
Zero sequence reactance = line length x Z0X x Imp Ratio =
42.884 ohms
I
Longest Line Impedance in CT secondary
1
Postive sequence resistance = line length x + ve seq. R x Imp Ratio =
800 A 1A 220000 V 110 V
47 OF 205
1.580 ohms
400/220kV WARANGAL SUBSTATION
SIEMENS
2
Postive sequence reactance = line length x + ve seq. X x Imp Ratio =
8.060 ohms
3
Zero sequence resistance = line length x Z0 x Imp Ratio =
5.100 ohms
4
Zero sequence reactance = line length x Z0X x Imp Ratio =
30.200 ohms
J
Zone I : Reach Setting Proposed at 80% of the protected Line
1
Reach For Postive sequence resistance (80% line length x Postive sequence resistance x Imp Ratio =0.8 x 71 x 0.0791 x 0.4
2
1.797 ohms
Reach For Postive sequence reactance (80% line length x Postive sequence reactance x Imp Ratio =0.8 x 71 x 0.403 x 0.4
3
9.156 ohms
Reach For Zero sequence resistance (80% line length x Zero sequence resistance x Imp Ratio =0.8 x 71 x 0.255 x 0.4
4
5.794 ohms
Reach For Zero sequence reactance (80% line length x Zero sequence reactance x Imp Ratio =0.8 x 71 x 1.51 x 0.4
5
6
34.307 ohms
Fault Resistance - ph-e = 1.797 + ( 9.156 x TAN ( 25 ) =
6.067
= 4.5 x 1.797 =
8.0865
= 50 x 0.4 =
20.000
Maximum of 6.067 and 20 =
20.000
Minimum of 8.0865 and 20 =
8.087 ohms
Hence fault resistance between phase to earth =
8.087 ohms
Fault Resistance - ph-ph = 1.797 + ( 9.156 x TAN ( 25 ) =
6.067
= 3 x 1.797 =
5.391
= 10 x 0.4 =
4.000
48 OF 205
400/220kV WARANGAL SUBSTATION
SIEMENS
Maximum of 6.067 and 4 =
6.067
Minimum of 5.391 and 6.067 =
5.391
Hence fault resistance between phase to phase =2 times of the above
K
10.782 ohms
Zone II: Reach Setting at (100% of the protected Line + 50% of the shortest line at Next substation)
1
Reach For Postive sequence resistance 100% line length x Postive sequence resistance x Imp Ratio + 50% shortest line length x Postive sequence resistance x Imp Ratio =71 x 0.0791 x 0.4 + 0.5 x 71 x 0.0791 x 0.4
2
3.368 ohms
Reach For Postive sequence reactance 100% line length x Postive sequence reactance x Imp Ratio + 50% shortest line length x Postive sequence reactance x Imp Ratio =71 x 0.403 x 0.4 + 0.5 x 71 x 0.403 x 0.4
3
17.168 ohms
Reach For Zero sequence resistance 100% line length x Zero sequence resistance
x Imp Ratio +
50% shortest line length x Zero sequence resistance
x Imp Ratio
=71 x 0.255 x 0.4 + 0.5 x 71 x 0.255 x 0.4
4
10.863 ohms
Reach For Zero sequence reactance 100% line length x Zero sequence reactance
x Imp Ratio +
50% shortest line length x Zero sequence reactance
x Imp Ratio
=71 x 1.51 x 0.4 + 0.5 x 71 x 1.51 x 0.4
64.326 ohms
5
Fault Resistance - ph-e
15.156 ohms
6
Fault Resistance - ph-ph
20.208 ohms
L
Zone III: Reach Setting Proposed at 110% of the prot Line & 100%of the longest line
1
Reach For Postive sequence resistance
49 OF 205
400/220kV WARANGAL SUBSTATION
SIEMENS
110% line length x Postive sequence resistance x Imp Ratio + 100% Longest line length x Postive sequence resistance x Imp Ratio = 1.1 x 71 x 0.0791 x 0.4 + 50 x 0.0791 x 0.4
2
4.053 ohms
Reach For Postive sequence reactance 110% line length x Postive sequence reactance x Imp Ratio + 100% Longest line length x Postive sequence reactance x Imp Ratio = 1.1 x 71 x 0.403 x 0.4 + 50 x 0.403 x 0.4
3
20.650 ohms
Reach For Zero sequence resistance 110% line length x Zero sequence resistance x Imp Ratio + 100% Longest line length x Zero sequence resistance
x Imp Ratio
= 1.1 x 71 x 0.255 x 0.4 + 50 x 0.255 x 0.4
3
13.066 ohms
Reach For Zero sequence reactance 110% line length x Zero sequence reactance x Imp Ratio + 100% Longest line length x Zero sequence reactance x Imp Ratio = 1.1 x 71 x 1.51 x 0.4 + 50 x 1.51 x 0.4
77.372 ohms
5
Fault Resistance - ph-e
18.239 ohms
6
Fault Resistance - ph-ph
24.319 ohms
M
Power Swing Block Function
1
Reactive direction are set so that the inner characteristic covers completely all the distance protection zones,which are to be blocked by the PSD function.At least 10%of additional safely margin
2
Reactive Reach of the Inner characteristic of the Power swing blocking element = 1.1* X3
22.715
3
Reactive Reach of the Inner characteristic of the Power swing blocking element = 1.1(2R3+Rf)
28.980
4
Reactive Reach of the Outer characteristic of the Power swing blocking element
28.393
5
Reactive Reach of the Outer characteristic of the Power swing blocking element
36.224
50 OF 205
400/220kV WARANGAL SUBSTATION
SIEMENS
N
Source Impedance refered to CT secondary
1
Local End Z magnitude
1.270
2
Local End Z argument
80.000
3
Remote End Z magnitude
2.580
4
Remote End Z argument
80.000
5
Postive sequence resistance at local end in ohms(RISA)
2.246
6
Postive sequence reactance at local end in ohms(XISA)
11.445
7
Postive sequence resistance at remote end in ohms(R1SB)
2.246
8
Postive sequence reactance at remote end in ohms(X1SB)
11.445
O
Phase Selection
1
X1Phs
41.299
2
X0Phs
154.745
3
Calculated RFPEphs
50.593
4
Calculated RFPPphs
44.584
5
Zloadmin =(KV)2\MVA
6
RFPEphs
50.593
7
Conditions for 2nd Zone
29.360
8
Conditions for 4th Zone
4.180
9
Conditions for 3-ph fault
51.979
10
RFPPphs
44.584
104.544
9.451
51 OF 205
13.985
SIEMENS
400/220kV WARANGAL SUBSTATION
400/220 KV WARANGAL SUBSTATION 220kV DURSHED FEEDER ABB DISTANCE PROTECTION RELAY SETTING Type : ABB make REL670 DESCRIPTION Max. load current \ CT primary current
Distance Protection zone 1
PARAMETER SETTING lb (FLC \ CT Primary)
0.492
lminop
0.200
HOLD
operating mode and directionaity of zone I
RECOMMENDED
operation
Forward
Settings of Phase to Phase measurement Operation of distance protection zone I for Ph-I
Operation PP
On
Positive sequence reactance of zone 1 for ph-ph fault
X1PP
9.156
Positive sequence reactance of zone 1 for ph-ph fault
R1PP
1.797
Resisitive reach of distance protection for ph-ph faults
RFPP
10.782
Operating mode of time delayed trip for the distance protection zone 1 for ph-ph faults
Timer t1PP
Time delayed trip operation for the distance protection zone 1 for ph-ph faults
t1PP
On 0.000
Settings of Phase to earth element Operation of distance protection zone I for Ph-I
Operation PE
On
X1PE
9.156
R1PE
1.797
Zero sequence line reactance included in distance protection zone I XOPE for Ph-E faults
34.307
Zero sequence line reactance included in distance protection zone I ROPE for Ph-E faults
5.794
Resisitive reach for zone 1 Ph-E faults
RFPE
8.087
Operating mode of time delayed trip for the distance protection zone 1 for ph-E faults
Timer t1PP
Positive sequence resistive reach of distance zone 1 for ph-E fault
48 OF 205
On
SIEMENS
400/220kV WARANGAL SUBSTATION
Time delayed trip operation for the distance protection zone 1 for ph-ph faults
t1PE
49 OF 205
0.000
SIEMENS
400/220kV WARANGAL SUBSTATION
Distance Protection zone II
ZONE II
operating mode and directionaity of distance zone II
operation
Forward
Settings of Phase to Phase measurement Operation of distance protection zone 2 for Ph-Ph fault
Operation PP
On
Positive sequence reactance of zone 2 for ph-ph fault
X1PP
17.168
Positive sequence reactance of zone 2 for ph-ph fault
R1PP
3.368
Resisitive reach of distance protection for ph-ph faults
RFPP
20.208
Operating mode of time delayed trip for the distance protection zone 2 for ph-ph faults
Timer t1PP
Time delayed trip operation for the distance protection zone 2 for ph-ph faults
t1PP
On 0.400
Settings of Phase to earth element Operation of distance protection zone 2 for Ph-E faults
Operation PE
On
X1PE
17.168
R1PE
3.368
Zero sequence line reactance included in distance protection zone XOPE 2 for Ph-E faults
64.326
Zero sequence line reactance included in distance protection zone ROPE 2 for Ph-E faults
10.863
Resisitive reach for zone 2 Ph-E faults
RFPE
15.156
Operating mode of time delayed trip for the distance protection zone 2 for ph-E faults
Timer t1PP
Time delayed trip operation for the distance protection zone 2 for ph-ph faults
t1PE
Distance protection zone lll
ZONEIII
Operating mode and directionality of zone 3
Operation
Positive sequence resistive reach of distance zone 2 for ph-E fault
On 0.400
Forward
SETTINGS OF PHASE TO PHASE MEASUREMENT Operation of Distance protection Zone 3 for Ph fault
Operation PP
Positive sequence reactance of zone 3 for phase to phase faults
X1PP
20.650
Positive sequence resistance of zone 3 for phase to phase faults
R1PP
4.053
Positive reach of distance protectin for phase to phase faults
RFPP
24.319
50 OF 205
On
SIEMENS
400/220kV WARANGAL SUBSTATION
Operating mode of time delayed trip for the distance protection zone 3 for Ph-Ph faults
Timer t3PP
On
Time delaye trip operation for the distnce protection zone 3 for Pht3PP Ph faults
1.000
SETTINGS OF PHASE TO EARTH MEASUREMENT Operating mode of distance protection zone 3 for Ph-E faults
Operation PE
On
Positive sequence reactive reach of distance zone 3 for Ph-E faults X1PE
20.650
Positive sequence resistive reach of distance zone 3 for Ph-E faults R1PE
4.053
zero sequence line reactance included in distance protection zone 3 X0PE for Ph-E faults Zero sequence line reactance included in distance protection zone R0PE 3 for Ph-E faults Resistive reach for zone 3 for Ph-E faults
77.372 10.863
RFPE
Operating mode of time delayed trip for the distance protection zone 3 for Ph-E faults Time delayed trip operation of the distance protection zone 3 for Ph-E faults Manual energising time
18.239
Timer t3PE
On
t3PE
1.000
T manenerg
0.200
PHASE SELECTION operation of phase selection
operation
positive sequence reactive reach for ph-ph loop measurement
X1PP
20.650
Resistive reach for ph-ph loop measurement
RFPP
24.319
positive sequence reactive reach for ph-e loop measurement
X1PE
20.650
Zero sequence reactive for ph-e loop measurement
XOPE
77.372
Resistive reach for ph-e loop measurement
RFPE
18.239
Power swing blocking
On
PSB
power swing function on/off
operation
On
Operating mode of internal PSD function
detection
on
positive sequence reactive reach of the inner boundary
X1IN
22.715
positive sequence reactive reach of the inner boundary
R1IN
28.980
reach multiplication for the outer reactive boundary
KX
1.250
reach multiplication for the outer reactive boundary
KR
1.250
Initial PSD timer
tp1
0.045
Fast PSD timer
tp2
0.015
51 OF 205
SIEMENS
400/220kV WARANGAL SUBSTATION
Hold timer for activation of fast PSD timer
tw
0.250
Hold timer for PSD detected
th
0.5s
Timer over coming 1-phase reclosing dead time
tEF
3s
Timer to time delay block by the residual current
tR1
0.300
On delay timer for blocking of output signal at very slow swings
tR2
2.000
Scheme communication logic
Zcom
Operation of zoom scheme communication logic
Operation
Operation mode
Schemetype
Coordination timer
T coord
Minimum duration of a carrier send signal
T sendmin
0.1s
Operation mode for an unblocking signal
Unblock
Off
Security timer
T security
Operation mode of current reversal function
Currev
Off
Pick up time of current reversal function
T pickup
NA
Time delay for current reversal
T delay
NA
Operation mode of WEI function
WEI
Off
Coordination time for WEI function
Twei
NA
Voltage detection for PH-E faults
UPN<
NA
voltage detection for Ph-Ph faults
UPP<
NA
Automatic SOTF
SOTF
Operation of SOTF
Operation
FUSE FAILURE FUNCTION
FFR
FFR zero sequence function On\Off
Zeroseq
Operating value of voltage U0
3U0>
0.100
Operating value of current I0
3Uo<
0.100
BROKEN CONDUCTOR SUPERISION
SSUP
Broken conductor function On\Off
Operation
Operating phase current as a%
IP>
52 OF 205
On Permissive UR 0.050s
0.035s
On
On
On 0.100
SIEMENS
400/220kV WARANGAL SUBSTATION
Time delay
T
0.200
Loss of voltage
YU<
Loss of voltage function On\Off
Operation
Operating phase voltage as a%
UPE<
overload
I>
Overload function On\Off
Operation
operating value of phase current
IP>
Time delay
T
20s
Unit for presentation of line length
Length unit
Km
Length of protected line
Line length
71.000
Positive sequence reactance of line
X1
28.613
Positive sequence resistance of line
R1
5.616
zero sequence reactance of line
X0
107.210
Zero sequence resistance of line
R1
18.105
Positive sequence reactance of source at local end
X1SA
28.613
Positive sequence resistance of source at local end
R1SA
5.616
Positive source reactance at remote end
X1SB
28.613
Positive source resistance at remote end
R1SB
5.616
Zero sequence mutual reactance for double circuit line
XM0
Zero sequence mutual resistance for double circuit line
RM0
Selection of presentation mode for the distance to fault *
Distance unit
Analogue signal name**
Name
Primary phase-phase voltage
VT prim
220.000
Primary rated current
CT prim
800.000
On 0.700
On 1.000
FAULT LOCATOR
NOTES: ALL parameters of fault locator are set in the menu-settings-functions-group n-line.reference *Settings done in menu: settings - Distrbreport-faultlocator **settings done in menu:configuration-analogue inputs-u1,u2 etc
53 OF 205
Km
SIEMENS
400/220kV WARANGAL SUBSTATION
SYNCRO CHECK AND ENERGISATION CHECK FUNCTIONS: Operation of syncro check function
Operation
On
Reference voltage either phase to ground or phase to phase
Input phase
L1
Phase shift between U bus & U line
Phase shift
10.000
Voltage ratio between U bus & Uline
U ratio
1.000
Bus arrangment for voltage selection
U selection
single bus
Autoenergisation check
Autoenerg
Off
Mannual energisation check
Manenerg
Off
Mannual energisation check
ManDBDL
Off
High voltage limit
Uhigh
0.800
Low voltage limit
Ulow
0.400
Frequency difference limit
Freqdiff
0.200
Phase angle difference limit
Phasediff
20.000
Voltage difference limit
Udiff
0.200
Autoenergisation check
T autoenerg
0.200
Manual energising time
T manenerg
0.200
54 OF 205
View more...
Comments