Design Data Sheet for Box Culvert
Short Description
Descripción: Box culvert design data...
Description
ﺻﻠﺏ ﺍﻟﺟﺯﻳﺭﺓ ﻟﻠﺧﺭﺳﺎﻧﺔ Sulb Aljazeera Concrete
DESIGN DATA SHEET FOR BOX CULVERT, SAPAC
–ﺍﻟﻤﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔﺍﻟﺴﻌﻮﺩﻳﺔ+966 (013) 895 4529 :– ﺗﻠﻔﺎﻛﺲ31473 ﺍﻟﺪﻣﺎﻡ12172 ﺏ.ﻁﺮﻳﻖ ﺑﻘﻴﻖ – ﺹ1080 ﺍﻟﺪﻣﺎﻡ –ﻣﺨﻄﻂ 2nd Industrial Area, Abqaiq Road, Dammam – PO Box 12172 Dammam 31473 – Tel/Fax: +966 (0) 3 895 4529
C.R: 2050092468
www.sulbaljazeera.com
2050092468: ﺕ.ﺱ
SULB AL‐JAZEERA CONCRETE MANUFACTURING Project: Client:
BOX CULVERT
Designed:
DJ
Checked :
VR
Approved :
VR
Location: SAUDI ARABIA
SAPAC
BOX CULVERT SIZE 1000 X 800
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =800 mm & Depth from GL =4500
Size:
Introduction:
g p (H) above the culvert are as per the Inside dimensions of the box culvert (SPAN x RISE) The fill height below table. A typical section of the culvert is shown in Figure. Material and design parameters are given in Table.
Material and Design Parameters Reinforced Concrete, c
24
kN/m3
Soil, s
18
kN/m3
Compressive Strength, f’c
35
Span p L
1000
Mpa mm
Rise R
800
mm
Top Slab Thickness, Tt
200
mm
Bottom Slab Thickness, Tb
240
mm
4500
mm
200
mm
Haunch Thickness, Th
50
mm
Reinforcement Clear Cover
40
mm
420
Mpa
Height of Fill H Wall Thickness, Ts
Yield Strength, fy
Modulus Elasticity of Concrete, Ec
27789.4 Mpa
Modulus Elasticity of Steel Reinforcement, Es
200000
Mpa
SULB AL-JAZEERA CONCRETE MANUFACTURING
Designed:
DJ
Checked :
VR
Approved :
VR
Element BOX CULVERT SAPAC L =1000 X W =800 mm & Depth from GL =4500 Customer: Size: The approximate strip method is used for the design with the 1m wide design strip oriented parallel to the direction of traffic. A 2-Dimensional (2D) plane frame model is used to analyze the box culvert. Beam elements in the 2D model are assumed to be centered in the concrete members. The model is assumed to be externally supported by a pinned support on one end and a roller support on the other end. In addition, the model is always assumed to be in equilibrium so external reactions to loads applied to the structure were assumed to act equal and opposite. A “w” dimension of 1 m is added to the calculations to convert the units to kN/m for consistency with national conventions.
A.
Dead Load The total self-weight of
the culvert top slab is: 26.40
kN (for 1 m wide)
The self-weight of one culvert side wall is: 4.90
kN (for 1 m wide)
Self weight of Haunch 0.03 kN (for 1 m wide)
The top slab weight, wall weights, and all four haunch weights are applied to the bottom slab as an upward reaction from the soil assuming an equivalent uniform pressure. The bottom slab weight is not applied in the model because its load is assumed to be directly resisted by the soil.
Dc bottom B.
=
34.68
kN (for 1 m wide)
Earth Pressure Loads The weight of fill on top of the culvert produces vertical earth pressure (EV). The fill height is measured from the top surface of the top slab to the top of the pavement or fill. The unit weight of the fill is 19.2 kN/m3 The interaction factor for embankment conditions is dependent on the height of fill (H) and the outside width of the culvert (Bc): 1.64
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =800 mm & Depth from GL =4500
The design vertical earth pressure at the top of the culvert is: 133.07
kN/m
The lateral earth pressure (EH) on the culvert is found using the equivalent fluid method. For atrest conditions, a maximum stage full soil unit weight and a minimum stage half soil unit weight will be are used. At the top of the culvert, the lateral earth pressure is: 81.00
kN/m
(Top)
40.50
kN/m
(Top)
At the bottom of the culvert, the lateral earth pressure is:
C.
=
103.32
kN/m
(Bottom)
=
51.66
kN/m
(Bottom)
Live Load Surcharge Use an active coefficient of lateral earth pressur
0.2827
g for the live load surcharge g calculation at the top p of the culvert is the distance from The height the top surface of the top slab to the top of the pavement or fill. The height is: H
top of culvert
=
4500 mm
The equivalent fill height, heq is dependent on the depth of fill and can be found using AASHTO Table 3.11.6.4-1.
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
By interpolation, the equivalent height for a fill depth of =
heq
=
DJ
Checked :
VR
Approved :
VR
L =1000 X W =800 mm & Depth from GL =4500
Size:
heq
Designed:
4500
mm is:
2.52 ft 0.77
m
The corresponding lateral live load surcharge on the top of the culvert is given as: 3.91
kN/m
The height for the live load surcharge calculation at the bottom of the culvert is the distance from the bottom surface of the bottom slab to the top of the pavement or fill. 5740 mm Again using interpolation and AASHTO Table 3.11.6.4.1, the equivalent height is: heq
=
heq
=
2.12 ft 0.65
m
The lateral live load surcharge located at the bottom of the culvert is given as: 3.29 D.
kN/m
Water Load Designers need to consider load cases where the culvert is full of water as well as cases where the culvert is empty. A simple hydrostatic distribution is used for the water load: At the inside of the culvert, the lateral water pressure is: WAtop =
0 kN/m2 7.85
kN/m2
Using a 2D frame model there is an opposite upward reaction from the soil caused by the water inside the culvert: Wabottom
reaction
=
WA bottom * Span
=
6.54
kN/m
(Span + Ts) E.
Live Load The design live loads include the HL-93 truck and tandem loads. Since the span of the box culvert is less than 15 ft, no lane load is applied. Dynamic Load Allowance The dynamic load allowance (IM) for culverts and other buried structures is reduced based on the depth of fill over the culvert. For strength and service limit states: -27.885
=
The dynamic load may not be t taken less th than zero. Th d i l d allowance ll t b k l
0
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =800 mm & Depth from GL =4500
Live Load Distribution Live loads are assumed to distribute laterally with depth. The specifications permit designers to increase the footprint of the load with increasing depth of fill. The load is assumed to spread laterally 1.15 times H horizontally in each direction for every foot of fill above the culvert. The intensity of live loads at any depth is assumed to be uniform over the entire footprint.
The assumed tire contact area for each wheel has a width of 20 inches and a length of 10 inches.
Using the distances between wheel lines and axles, the live load intensities at the top of the box culvert can be found. For truck and tandem loadings, the influence area or footprint of the live load is found first. Then the sum of the weights of the wheels is used to determine the intensity of the live load. T d To determine t i th the li live l load, d use multiple lti l presence f factors t (MPF) (MPF). A single i l loaded l d d l lane with ith a MPF of 1.20 is used for strength and service limit states. A single 3 Axle
where
with 600 kN Truck
Pw =
Axlespacing = Wtire = W =
Ltire =
130 kN
1.8 m 0.51 m 7.49
m
0.25 m
L=
7.23
m
=
5.77
kN/m
Therefore WLL+IM
configuration produces a live load intensity of:
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =800 mm & Depth from GL =4500
Size:
A tandem truck axle configuration produces a live load intensity of:
where
Pw =
105 kN 6.73
m
where Axlespacing = WLL+IM
=
1.3 m 10.01
kN/m
The live load intensities of the single and tandem axle configurations are compared. Since the tandem axle configuration produces a live load intensity slightly larger than that of the single axle configuration, the tandem axle configuration is used for design in both the strength and service limit states. 10.01 kN therefore WLL+IM =
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer: F.
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =800 mm & Depth from GL =4500
Load Combination Strength Limit states 1 Maximum Vertical Load and Maximum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+ (1.35)(1.05)EHmax + 1.75LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+1.00WA+(0.9/1.05)EHmin 3 Minimum Vertical load and Maximum Horizontal Load 0.90 DC + (0.9/1.05)EV + (1.35)(1.05) EHmax +1.75LS Service Limit State 1 Maximum Vertical Load and Maximum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00EHmax + 1.00LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00WA+1.00EHmin 3 Minimum Vertical load and Maximum Horizontal Load 1.00 DC + 1.00EV + 1.00EHmax +1.00LS
A structural analysis is performed using a standard commercial matrix-analysis program. The bottom slab of the box culvert is assumed rigid compared to the subgrade. Reactions to vertical loads applied to the culvert (earth, water, live load) are assumed to be carried by uniform, triangular or trapezoidal distributed reactions applied to the bottom slab. Box culverts supported on stiff or rigid subgrades (rock) would require further investigation. The haunches are included in the analysis by increasing the thickness of members near each corner. Reinforcement Design
where, F =
1
fy =
420 Mpa
fc' =
35 MPa
b =
1 m
therefore, a =
As x 420 0.85 x 35 x1000
a=
420∗
0.0141
As
Mu =
1 x As x 420 x (d - .0141 * As/2)
Mu =
420 x As*d - 2.961 As^2
√ 176400 ^2 11.844
/5.922
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
VR
Approved :
VR
L =1000 X W =800 mm & Depth from GL =4500
Side Wall
Max @ Mid Slab@IS
Max @ Slab End@OS
From staad Model Outside
Mu =
17.73 kNm
Main bar dia =
10
mm
d = thickness - Cover - dm/2 d= As =
155 mm 275.81
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Ts
As =
400.00
=
10 mm dia X
for 1 m length
10 mm dia X Mu =
mm2
mm2
As Provided = Inside
400.00
13.63 kNm
150 c/c 6.67
Pcs
Main bar dia =
523.60 10
mm2 mm
d = thickness - Cover - dm/2 d= As =
155 mm 211.40
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Ts 400.00
=
400.00
mm2
mm2
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
523.60
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
VR
Approved :
VR
L =1000 X W =800 mm & Depth from GL =4500
Top Slab
Max @ Mid Slab @IS Max @ Slab End @OS Max @ Slab End @OS
From staad Model Inside
Mu =
27.28 kNm
Main bar dia =
10
mm
d = thickness - Cover - dm/2 d= As =
155 mm 427.35
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tt
As =
427.35
=
10 mm dia X
for 1 m length
10 mm dia X Mu =
mm2
mm2
As Provided =
Outside
400.00
4.09 kNm
150 c/c 6.67
Pcs
Main bar dia =
523.60 10
mm2 mm
k d = thi thickness - C Cover - dm/2 d= As =
155 mm 63.01
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tt 400.00
=
400.00
mm2
mm2
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
150 c/c 6 67 6.67
DJ
Checked :
Pcs
523 60 523.60
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
VR
Approved :
VR
L =1000 X W =800 mm & Depth from GL =4500
Bottom Slab
Max @ Slab End@OS Max @ Mid Slab @IS
From staad Model Inside
Mu =
20.85 kNm
Main bar dia =
10
mm
d = thickness - Cover - dm/2 d= As =
195 mm 256.97
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tb
As =
480.00
=
10 mm dia X
for 1 m length
10 mm dia X Mu =
mm2
mm2
As Provided =
Outside
480.00
14.01 kNm
150 c/c 6.67
Pcs
Main bar dia =
523.60 10
mm2 mm
k d = thi thickness - C Cover - dm/2 d= As =
195 mm 172.13
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tb 480.00
=
480.00
mm2
mm2
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
150 c/c 6 67 6.67
DJ
Checked :
Pcs
523 60 523.60
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Checking of Shear Top Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
107.23 kN
0.17∗√ 60.9 160.92
^′ kN
> Vu u
Bottom Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
113.58 kN
0.17∗√ 201.15
^′ kN
> Vu
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =800 mm & Depth from GL =4500
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Side Wall
Maximum Shear (Vu) = Shear Capacity
(Vc) =
65.09 kN
0.17∗√ 160.92
^′ kN
> Vu
Final Size and Reinforcement Box culvert Inside Dimensions = 1000 x 800 Top Slab Thickness =
mm
200 mm
Bottom Slab Thickness =
240 mm
Side Wall Thickness =
200 mm
Reinforcement Inside
Location
Outside
Dia (mm)
C/C
Dia (mm)
C/C
Top Slab
10
150
10
150
B tt Bottom Sl Slab b
10
150
10
150
Side Wall
10
150
10
150
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =800 mm & Depth from GL =4500
SULB AL‐JAZEERA CONCRETE MANUFACTURING Project: Client:
BOX CULVERT
Designed:
DJ
Checked :
VR
Approved :
VR
Location: SAUDI ARABIA
SAPAC
BOX CULVERT SIZE 1000 X 1000
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =1000 mm & Depth from GL =4500
Size:
Introduction:
Inside dimensions of the box culvert (SPAN x RISE) The fill height (H) above the culvert are as per the below table A typical section of the culvert is shown in Figure table. Figure. Material and design parameters are given in Table.
Material and Design Parameters Reinforced Concrete, c
24
kN/m3
Soil, s
18
kN/m3
Compressive Strength, f’c
35
Span L
1000
Mpa mm
Rise R
1000
mm
T Top Slab Sl b Thi Thickness, k Tt
200
mm
Bottom Slab Thickness, Tb
240
mm
4500
mm
200
mm
Haunch Thickness, Th
50
mm
Reinforcement Clear Cover
40
mm
Height of Fill H Wall Thickness, Ts
Yield Strength, fy
Modulus Elasticity of Concrete, Ec Modulus Elasticity of Steel Reinforcement, Es
420
Mpa
27789.4
Mpa
200000
Mpa
SULB AL-JAZEERA CONCRETE MANUFACTURING
Designed:
DJ
Checked :
VR
Approved :
VR
Element BOX CULVERT SAPAC L =1000 X W =1000 mm & Depth from GL =4500 Customer: Size: The approximate strip method is used for the design with the 1m wide design strip oriented parallel to the direction of traffic. A 2-Dimensional (2D) plane frame model is used to analyze the box culvert. Beam elements in the 2D model are assumed to be centered in the concrete members. The model is assumed to be externally supported by a pinned support on one end and a roller support on the other end. In addition, the model is always assumed to be in equilibrium so external reactions to loads applied to the structure were assumed to act equal and opposite opposite. A “w” dimension of 1 m is added to the calculations to convert the units to kN/m for consistency with national conventions.
A.
Dead Load The total self-weight of
the culvert top slab is: 26.40
kN (for 1 m wide)
The self-weight of one culvert side wall is: 5.86
kN (for 1 m wide)
Self weight of Haunch 0.03 kN (for 1 m wide)
The top slab weight, wall weights, and all four haunch weights are applied to the bottom slab as an upward reaction from the soil assuming an equivalent uniform pressure. The bottom slab weight is not applied in the model because its load is assumed to be directly resisted by the soil.
Dc bottom B.
=
36.28
kN (for 1 m wide)
Earth Pressure Loads The weight of fill on top of the culvert produces vertical earth pressure (EV). The fill height is measured from the top surface of the top slab to the top of the pavement or fill. The unit weight of the fill is 19.2 kN/m3 The interaction factor for embankment conditions is dependent on the height of fill (H) and the outside width of the culvert (Bc): 1.64
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =1000 mm & Depth from GL =4500
Size:
The design vertical earth pressure at the top of the culvert is: 133.07
kN/m
The lateral earth pressure (EH) on the culvert is found using the equivalent fluid method. For atrest conditions conditions, a maximum stage full soil unit weight and a minimum stage half soil unit weight will be are used. At the top of the culvert, the lateral earth pressure is: 81.00
kN/m
(Top)
40.50
kN/m
(Top)
At the bottom of the culvert, the lateral earth pressure is:
C.
=
106.92
kN/m
(Bottom)
=
53.46
kN/m
(Bottom)
Live Load Surcharge Use an active coefficient of lateral earth pressure ka
0.2827
The height for the live load surcharge calculation at the top of the culvert is the distance from the top surface of the top slab to the top of the pavement or fill. The height is: H
top of culvert
=
4500 mm
The equivalent fill height, heq is dependent on the depth of fill and can be found using AASHTO Table 3.11.6.4-1.
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
By interpolation, the equivalent height for a fill depth of =
heq
=
DJ
Checked :
VR
Approved :
VR
L =1000 X W =1000 mm & Depth from GL =4500
Size:
heq
Designed:
4500
mm is:
2.52 ft 0.77
m
The corresponding lateral live load surcharge on the top of the culvert is given as: 3.91
kN/m
The height for the live load surcharge calculation at the bottom of the culvert is the distance from the bottom surface of the bottom slab to the top of the pavement or fill. 5940 mm Again using interpolation and AASHTO Table 3.11.6.4.1, the equivalent height is: heq
=
heq
=
2.05 ft 0.63
m
The lateral live load surcharge located at the bottom of the culvert is given as: 3.18 D.
kN/m
Water Load Designers need to consider load cases where the culvert is full of water as well as cases where the culvert is empty. A simple hydrostatic distribution is used for the water load: At the inside of the culvert, the lateral water pressure is: WAtop =
0 kN/m2 9.81
kN/m2
Using a 2D frame model there is an opposite upward reaction from the soil caused by the water inside the culvert: Wabottom
reaction
=
WA bottom * Span
=
8.18
kN/m
(Span + Ts) E.
Live Load The d Th design i li live l loads d i include l d th the HL HL-93 93 t truck k and d t tandem d l loads. d Si Since th the span of f th the b box culvert l t i is less than 15 ft, no lane load is applied. Dynamic Load Allowance The dynamic load allowance (IM) for culverts and other buried structures is reduced based on the depth of fill over the culvert. For strength and service limit states: -27.885
=
The dynamic load allowance may not be taken less than zero.
0
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =1000 mm & Depth from GL =4500
Live Load Distribution Live loads are assumed to distribute laterally with depth. The specifications permit designers to increase the footprint of the load with increasing depth of fill. The load is assumed to spread laterally 1.15 times H horizontally in each direction for every foot of fill above the culvert. The intensity of live loads at any depth is assumed to be uniform over the entire footprint.
The assumed tire contact area for each wheel has a width of 20 inches and a length of 10 inches.
Using the distances between wheel lines and axles, the live load intensities at the top of the box culvert can be found. For truck and tandem loadings, the influence area or footprint of the live load is found first. Then the sum of the weights of the wheels is used to determine the intensity of the live load. To determine the live load, use multiple presence factors (MPF). A single loaded lane with a MPF of 1.20 is used for strength and service limit states. A single 3 Axle
where
with 600 kN Truck
Pw =
130 kN
Axlespacing =
1.8 m
Wtire =
0.51 m
W =
Ltire = L=
7.49
m
0.25 m 7.23
m
5.77
kN/m
Therefore WLL+IM
=
configuration produces a live load intensity of:
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =1000 mm & Depth from GL =4500
Size:
A tandem truck axle configuration produces a live load intensity of:
where
Pw =
105 kN 6.73
m
where Axlespacing =
1.3 m
=
WLL+IM
10.01
kN/m
The live load intensities of the single and tandem axle configurations are compared. Since the tandem axle configuration produces a live load intensity slightly larger than that of the single axle configuration, the tandem axle configuration is used for design in both the strength and service limit states. 10 01 kN 10.01 therefore WLL+IM = Final Loading DC DC
=
Sel weight of Culvert
=
36.28
EV =
133.07
kN/m
EHTmax =
81.00
kN/m
EHBmax =
106.92
kN/m
EHTmin =
40.50
kN/m
EHBmin =
bottom reaction
53.46
kN/m
=
3.91
kN/m
LLSbottom =
3.18
LLStop
WAtop=
F.
kN/m
kN/m 0 kN/m
WAbottom=
9.81
kN/m
WAbottomreaction=
8.18
kN/m
LL+IMW =
10 01 10.01
kN/ kN/m
Load Combination Strength Limit states 1 Maximum Vertical Load and Maximum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+ (1.35)(1.05)EHmax + 1.75LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+1.00WA+(0.9/1.05)EHmin
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =1000 mm & Depth from GL =4500
3 Minimum Vertical load and Maximum Horizontal Load 0.90 DC + (0.9/1.05)EV + (1.35)(1.05) EHmax +1.75LS Service Limit State 1 Maximum Vertical Load and Maximum Horizontal Load (LL+IM)+1.00EH 1.00 .00 DC C + 1.00 .00 EV + 1.00 .00 ( ) .00 max + 1.00LS .00 S 2 Maximum Vertical Lod and Minimum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00WA+1.00EHmin 3 Minimum Vertical load and Maximum Horizontal Load 1.00 DC + 1.00EV + 1.00EHmax +1.00LS
A structural analysis is performed using a standard commercial matrix-analysis program. The bottom slab of the box culvert is assumed rigid compared to the subgrade. Reactions to vertical loads applied li d to the h culvert l ( (earth, h water, li live l load) d) are assumed d to b be carried i d b by uniform, if triangular i l or trapezoidal distributed reactions applied to the bottom slab. Box culverts supported on stiff or rigid subgrades (rock) would require further investigation. The haunches are included in the analysis by increasing the thickness of members near each corner. Reinforcement Design
where, where F =
1
fy =
420 Mpa
fc' =
35 MPa
b =
1 m
therefore, a =
As x 420 0.85 x 35 x1000
a=
420∗
0.0141
As
Mu =
1 x As x 420 x (d - .0141 * As/2)
Mu =
420 x As*d - 2.961 As^2
√ 176400 ^2 11.844
/5.922
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =1000 X W =1000 mm & Depth from GL =4500
Size:
Side Wall
Max @ Mid Slab@IS
Max @ Slab End@OS
From staad Model Outside
Mu =
17.196 kNm
Main bar dia =
10
mm
d = thickness - Cover - dm/2 d= As =
155 mm 267.40
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 0 002 x b x Ts
As =
400.00
=
10 mm dia X
for 1 m length
10 mm dia X Mu =
mm2
mm2
As Provided = Inside
400 00 400.00
13.237 kNm
150 c/c 6.67
Pcs
Main bar dia =
523.60 10
mm2 mm
d = thickness - Cover - dm/2 d= As =
155 mm 205.25
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Ts 400.00
=
400.00
mm2
mm2
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
523.60
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =1000 X W =1000 mm & Depth from GL =4500
Size:
Top Slab
Max @ Mid Slab @IS
Max @ Slab End @OS From staad Model Inside
Mu =
27.496 kNm
Main bar dia =
10
mm
d = thickness - Cover - dm/2 d= As =
155 mm 430.81
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tt
As =
430.81
=
10 mm dia X
for 1 m length
10 mm dia X Mu =
mm2
mm2
As Provided =
Outside
400.00
6.618 kNm
150 c/c 6.67
Pcs
Main bar dia =
523.60 10
mm2 mm
d = thickness - Cover - dm/2 d= As =
155 mm 102.13
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tt 400.00
=
400.00
mm2
mm2
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
523.60
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =1000 mm & Depth from GL =4500
Size:
Bottom Slab
Max @ Slab End@OS Max @ Mid Slab @IS
From staad Model Inside
Mu =
20.383 kNm
Main bar dia =
10
mm
d = thickness - Cover - dm/2 d= As =
195 mm 251.16
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tb
As =
480.00
=
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
Outside
Mu =
480.00
mm2
mm2
13.623 kNm
150 c/c 6.67
Pcs
Main bar dia =
523.60 10
mm2 mm
d = thickness - Cover - dm/2 d= As =
195 mm 167.35
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tb 480.00
=
480.00
mm2
mm2
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
150 c/c 6.67
Pcs
523.60
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Checking of Shear Top Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
105.468 kN
0.17∗√ 160.92
^′ kN
> Vu
Bottom Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
111.385 kN
0.17∗√ 201.15
^′ kN
> Vu
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =1000 mm & Depth from GL =4500
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Side Wall
Maximum Shear (Vu) = Shear Capacity
(Vc) =
74.07 kN
0.17∗√
^′
160.92
kN
> Vu
Final Size and Reinforcement Box culvert Inside Dimensions = 1000 x 1000 mm Top Slab Thickness =
200 mm
Bottom Slab Thickness =
240 mm
Side Wall Thickness =
200 mm
Reinforcement Inside
Location
Outside
Top Slab
Dia (mm) 10
C/C 150
Dia (mm) 10
C/C 150
Bottom Slab
10
150
10
150
Side Wall
10
150
10
150
Designed:
DJ
Checked :
VR
Approved :
VR
L =1000 X W =1000 mm & Depth from GL =4500
SULB AL‐JAZEERA CONCRETE MANUFACTURING Project: Client:
BOX CULVERT
Designed:
DJ
Checked :
VR
Approved :
VR
Location: SAUDI ARABIA
SAPAC
BOX CULVERT SIZE 3000 X 1500
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved:
VR
L =3000 X W =1500 mm & Depth from GL =4500
Size:
Introduction:
Inside dimensions of the box culvert (SPAN x RISE) The fill height (H) above the culvert are as per the below t bl table. A t typical i l section ti of f th the culvert l t i is shown h i in Fi Figure. M Material t i l and d d design i parameters t are given i i in T Table. bl
Material and Design Parameters Reinforced Concrete, c
24
kN/m3
Soil, s
18
kN/m3
Compressive Strength, f’c
35
Span L
3000
Mpa mm
Rise R
1500
mm
Top Slab Thickness, Tt
320
mm
Thickness Tb Bottom Slab Thickness,
360
mm
4500
mm
Height of Fill H Wall Thickness, Ts
320
mm
Haunch Thickness, Th
50
mm
Reinforcement Clear Cover
40
mm
Yield Strength, fy
Modulus Elasticity of Concrete, Ec Modulus Elasticity of Steel Reinforcement, Es
420
Mpa
27789.4
Mpa
200000
Mpa
SULB AL-JAZEERA CONCRETE MANUFACTURING
Designed:
DJ
Checked :
VR
Approved:
VR
Element BOX CULVERT SAPAC L =3000 X W =1500 mm & Depth from GL =4500 Customer: Size: The approximate strip method is used for the design with the 1m wide design strip oriented parallel to the direction of traffic. A 2-Dimensional (2D) plane frame model is used to analyze the box culvert. Beam elements in the 2D model are assumed to be centered in the concrete members. The model is assumed to be externally supported by a pinned support on one end and a roller support on the other end. In addition, the model is always assumed to be in equilibrium so external reactions to loads applied to the structure were assumed to act equal and opposite. A “w” dimension of 1 m is added to the calculations to convert the units to kN/m for consistency with national conventions.
A.
Dead Load The total self-weight of
the culvert top slab is: 57.60
kN (for 1 m wide)
The self-weight of one culvert side wall is: 14.13
kN (for 1 m wide)
Self weight of Haunch 0.03 kN (for 1 m wide)
The top slab weight, wall weights, and all four haunch weights are applied to the bottom slab as an upward reaction from the soil assuming an equivalent uniform pressure. The bottom slab weight is not applied in the model because its load is assumed to be directly resisted by the soil.
Dc bottom B.
=
66.23
kN (for 1 m wide)
Earth Pressure Loads The weight of fill on top of the culvert produces vertical earth pressure (EV). The fill height is measured from the top surface of the top slab to the top of the pavement or fill. The unit weight of the fill is 19.2 kN/m3 The interaction factor for embankment conditions is dependent on the height of fill (H) and the outside width of the culvert (Bc): 1.25
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved:
VR
L =3000 X W =1500 mm & Depth from GL =4500
Size:
The design vertical earth pressure at the top of the culvert is: 101.03
kN/m
The lateral earth pressure (EH) on the culvert is found using the equivalent fluid method. For at-rest conditions, a maximum stage full soil unit weight and a minimum stage half soil unit weight will be are used. At the top of the culvert, the lateral earth pressure is: 81.00
kN/m
(Top)
40.50
kN/m
(Top)
At the bottom of the culvert, the lateral earth pressure is:
C.
=
120.24
kN/m
(Bottom)
=
60.12
kN/m
(Bottom)
Live Load Surcharge Use an active coefficient of lateral earth pressure ka =
0.2827
The height for the live load surcharge calculation at the top of the culvert is the distance from the top surface of the top slab to the top of the pavement or fill. The height is: H
top p of culvert
=
4500 mm
The equivalent fill height, heq is dependent on the depth of fill and can be found using AASHTO Table 3.11.6.4-1.
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
By interpolation, the equivalent height for a fill depth of =
heq
=
DJ
Checked :
VR
Approved:
VR
L =3000 X W =1500 mm & Depth from GL =4500
Size:
heq
Designed:
4500
mm is:
2.52 ft 0.77
m
The corresponding lateral live load surcharge on the top of the culvert is given as: 3.91
kN/m
The height for the live load surcharge calculation at the bottom of the culvert is the distance from the bottom surface of the bottom slab to the top of the pavement or fill. 6680 mm Again using interpolation and AASHTO Table 3.11.6.4.1, the equivalent height is: heq
=
heq
=
2 ft 0.61
m
The lateral live load surcharge located at the bottom of the culvert is given as: 3.10 D.
kN/m
Water Load Designers need to consider load cases where the culvert is full of water as well as cases where the culvert is empty. A simple hydrostatic distribution is used for the water load: At the inside of the culvert, the lateral water pressure is: WAtop =
0 kN/m2 14.72
kN/m2
Using a 2D frame model there is an opposite upward reaction from the soil caused by the water inside the culvert: Wabottom
reaction
=
WA bottom * Span
=
13.30
kN/m
(Span + Ts) E.
Live Load The design live loads include the HL-93 truck and tandem loads. Since the span of the box culvert is less than 15 ft, no lane load is applied. Dynamic Load Allowance The dynamic load allowance (IM) for culverts and other buried structures is reduced based on the depth of fill over the culvert. For strength and service limit states: -27.885 The dynamic load allowance may not be taken less than zero.
=
0
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved:
VR
L =3000 X W =1500 mm & Depth from GL =4500
Live Load Distribution Live loads are assumed to distribute laterally with depth. The specifications permit designers to increase the footprint of the load with increasing depth of fill. The load is assumed to spread laterally 1.15 times H horizontally in each direction for every foot of fill above the culvert. The intensity of live loads at any depth is assumed to be uniform over the entire footprint.
The assumed tire contact area for each wheel has a width of 20 inches and a length of 10 inches.
Using the distances between wheel lines and axles, the live load intensities at the top of the box culvert can be found. For truck and tandem loadings, the influence area or footprint of the live load is found first. Then the sum of the weights of the wheels is used to determine the intensity of the live load. To determine the live load, use multiple presence factors (MPF). A single loaded lane with a MPF of 1.20 is used for strength g and service limit states. A single 3 Axle
where
with 600 kN Truck
Pw =
130 kN
Axlespacing =
1.8 m
Wtire =
0.51 m
W =
Ltire = L=
configuration produces a live load intensity of:
7.49
m
0.25 m 7.23
m
5.77
kN/m
Therefore WLL+IM
=
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved:
VR
L =3000 X W =1500 mm & Depth from GL =4500
Size:
A tandem truck axle configuration produces a live load intensity of:
where
Pw =
105 kN 6 73 6.73
m
where Axlespacing = WLL+IM
1.3 m
=
10.01
kN/m
The live load intensities of the single and tandem axle configurations are compared. Since the tandem axle configuration produces a live load intensity slightly larger than that of the single axle configuration, the tandem axle configuration is used for design in both the strength and service limit states. 10.01 kN therefore WLL+IM = Final Loading DC DC
bottom reaction
=
Sel weight of Culvert
=
66.23
EV =
101.03
kN/m
EHTmax =
81.00
kN/m
EHBmax =
120.24
kN/m
EHTmin =
40.50
kN/m
EHBmin =
60.12
kN/m
=
3.91
kN/m
LLSbottom =
3.10
LLStop
WAtop=
F.
kN/m
kN/m 0 kN/m
WAbottom=
14.72
WAbottomreaction=
13.30
kN/m
LL+IMW =
10.01
kN/m
kN/m
Load Combination Strength Limit states 1 Maximum Vertical Load and Maximum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+ (1.35)(1.05)EHmax + 1.75LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+1.00WA+(0.9/1.05)EHmin 3 Minimum Vertical load and Maximum Horizontal Load 0.90 DC + (0.9/1.05)EV + (1.35)(1.05) EHmax +1.75LS
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved:
VR
L =3000 X W =1500 mm & Depth from GL =4500
Service Limit State 1 Maximum Vertical Load and Maximum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00EHmax + 1.00LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00WA+1.00EHmin 3 Minimum Vertical load and Maximum Horizontal Load 1.00 DC + 1.00EV + 1.00EHmax +1.00LS
A structural analysis is performed using a standard commercial matrix-analysis program. The bottom slab of the box culvert is assumed rigid compared to the subgrade. Reactions to vertical loads applied to the culvert (earth, water, live load) are assumed to be carried by uniform, triangular or trapezoidal distributed reactions applied to the bottom slab. Box culverts supported on stiff or rigid subgrades (rock) would require further investigation. The haunches are included in the analysis by increasing the thickness of members near each corner corner. Reinforcement Design
where, F =
1
fy =
420 Mpa
fc' =
35 MPa
b =
1 m
therefore, a =
As x 420 0.85 x 35 x1000
a=
420∗
0.0141
As
Mu =
1 x As x 420 x (d - .0141 * As/2)
Mu =
420 x As*d - 2.961 As^2
√ 176400 ^2 11.844
/5.922
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved:
VR
L =3000 X W =1500 mm & Depth from GL =4500
Size:
Side Wall
Max @ Mid Slab@IS Max @ Slab End@OS
From staad Model Outside
Mu =
118.29 kNm
Main bar dia =
16
mm
d = thickness - Cover - dm/2 d= As =
272 mm 1,064.84
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Ts
As =
1,064.84 1 064 84
=
As Provided =
16 mm dia X
for 1 m length
16 mm dia X
Inside
Mu =
640.00
mm2
mm2
64.1 kNm
150 c/c 6.67
Pcs
Main bar dia =
1,340.41
mm2
16
mm
1,340.41
mm2
d = thickness - Cover - dm/2 d= As =
272 mm 569.51
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 0 002 x b x Ts 640.00
=
640 00 640.00
mm2
mm2
As Provided =
16 mm dia X
for 1 m length
16 mm dia X
150 c/c 6.67
Pcs
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved:
VR
L =3000 X W =1500 mm & Depth from GL =4500
Size:
Top Slab
Max @ Slab End @OS
Max @ Mid Slab @IS
From staad Model Inside
Mu =
139.01 kNm
Main bar dia =
16
mm
1,340.41
mm2
14
mm
1,026.25
mm2
d = thickness - Cover - dm/2 d= As =
272 mm 1,257.83
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tt
As =
1,257.83
=
As Provided =
16 mm dia X
for 1 m length
16 mm dia X
Outside
Mu =
640.00
mm2
mm2
68.21 kNm
150 c/c 6.67
Pcs
Main bar dia =
d = thickness - Cover - dm/2 d= As =
273 mm 604.32 604 32
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tt 640.00
=
640.00
mm2
mm2
As Provided =
14 mm dia X
for 1 m length
14 mm dia X
150 c/c 6.67
Pcs
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved:
VR
L =3000 X W =1500 mm & Depth from GL =4500
Size:
Bottom Slab
Max @ Slab End@OS Max @ Mid Slab @IS
From staad Model Inside
Mu =
95.74 kNm
Main bar dia =
16
mm
1,340.41
mm2
14
mm
1,026.25
mm2
d = thickness - Cover - dm/2 d= As =
312 mm 743.09
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tb
As =
743.09
=
As Provided =
16 mm dia X
for 1 m length
16 mm dia X
Outside
Mu =
720.00
mm2
mm2
110.02 kNm
150 c/c 6.67
Pcs
Main bar dia =
d = thickness - Cover - dm/2 d= As =
313 mm 853.31 853 31
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tb 853.31
=
720.00
mm2
mm2
As Provided =
14 mm dia X
for 1 m length
14 mm dia X
150 c/c 6.67
Pcs
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Checking of Shear Top Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
262.78 kN
0.17∗√
^′
281.61
kN
> Vu
Bottom Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
228.11 kN
0.17∗√
^′
321.83
kN
> Vu
Designed:
DJ
Checked :
VR
Approved:
VR
L =3000 X W =1500 mm & Depth from GL =4500
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Side Wall
Maximum Shear (Vu) = Shear Capacity
155.38 kN
0.17∗√
(Vc) =
^′
281.61
kN
> Vu
Final Size and Reinforcement Box culvert Inside Dimensions = 3000 x 1500 mm Top Slab Thickness =
320 mm
Bottom Slab Thickness =
360 mm
Side = id Wall ll Thickness hi k
320 mm
Reinforcement Inside
Location
Outside
Top Slab
Dia (mm) 16
C/C 150
Dia (mm) 14
C/C 150
Bottom Slab
16
150
14
150
Side Wall
16
150
16
150
Designed:
DJ
Checked :
VR
Approved:
VR
L =3000 X W =1500 mm & Depth from GL =4500
SULB AL‐JAZEERA CONCRETE MANUFACTURING Project: Client:
BOX CULVERT
Designed:
DJ
Checked :
VR
Approved :
VR
Location: SAUDI ARABIA
SAPAC
BOX CULVERT SIZE 2500 X 1000
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =2500 X W =1000 mm & Depth from GL =4500
Size:
Introduction:
Inside dimensions of the box culvert (SPAN x RISE) The fill height (H) above the culvert are as per the below t bl table. A t typical i l section ti of f th the culvert l t i is shown h i in Fi Figure. M Material t i l and d d design i parameters t are given i i in T Table. bl
Material and Design Parameters Reinforced Concrete, c
24
kN/m3
Soil, s
18
kN/m3
Compressive Strength, f’c
35
Span L
2500
Mpa mm
Rise R
1000
mm
Top Slab Thickness, Tt
280
mm
Thickness Tb Bottom Slab Thickness,
320
mm
4500
mm
Height of Fill H Wall Thickness, Ts
280
mm
Haunch Thickness, Th
50
mm
Reinforcement Clear Cover
40
mm
Yield Strength, fy
Modulus Elasticity of Concrete, Ec Modulus Elasticity of Steel Reinforcement, Es
420
Mpa
27789.4
Mpa
200000
Mpa
SULB AL-JAZEERA CONCRETE MANUFACTURING
Designed:
DJ
Checked :
VR
Approved :
VR
Element BOX CULVERT SAPAC L =2500 X W =1000 mm & Depth from GL =4500 Customer: Size: The approximate strip method is used for the design with the 1m wide design strip oriented parallel to the direction of traffic. A 2-Dimensional (2D) plane frame model is used to analyze the box culvert. Beam elements in the 2D model are assumed to be centered in the concrete members. The model is assumed to be externally supported by a pinned support on one end and a roller support on the other end. In addition, the model is always assumed to be in equilibrium so external reactions to loads applied to the structure were assumed to act equal and opposite. A “w” dimension of 1 m is added to the calculations to convert the units to kN/m for consistency with national conventions.
A.
Dead Load The total self-weight of
the culvert top slab is: 47.04
kN (for 1 m wide)
The self-weight of one culvert side wall is: 8.74
kN (for 1 m wide)
Self weight of Haunch 0.03 kN (for 1 m wide)
The top slab weight, wall weights, and all four haunch weights are applied to the bottom slab as an upward reaction from the soil assuming an equivalent uniform pressure. The bottom slab weight is not applied in the model because its load is assumed to be directly resisted by the soil.
Dc bottom B.
=
53.44
kN (for 1 m wide)
Earth Pressure Loads The weight of fill on top of the culvert produces vertical earth pressure (EV). The fill height is measured from the top surface of the top slab to the top of the pavement or fill. The unit weight of the fill is 19.2 kN/m3 The interaction factor for embankment conditions is dependent on the height of fill (H) and the outside width of the culvert (Bc): 1.29
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =2500 X W =1000 mm & Depth from GL =4500
Size:
The design vertical earth pressure at the top of the culvert is: 104.82
kN/m
The lateral earth pressure (EH) on the culvert is found using the equivalent fluid method. For at-rest conditions, a maximum stage full soil unit weight and a minimum stage half soil unit weight will be are used. At the top of the culvert, the lateral earth pressure is: 81.00
kN/m
(Top)
40.50
kN/m
(Top)
At the bottom of the culvert, the lateral earth pressure is:
C.
=
109.80
kN/m
(Bottom)
=
54.90
kN/m
(Bottom)
Live Load Surcharge Use an active coefficient of lateral earth pressure ka =
0.2827
The height for the live load surcharge calculation at the top of the culvert is the distance from the top surface of the top slab to the top of the pavement or fill. The height is: H
top p of culvert
=
4500 mm
The equivalent fill height, heq is dependent on the depth of fill and can be found using AASHTO Table 3.11.6.4-1.
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
By interpolation, the equivalent height for a fill depth of =
heq
=
DJ
Checked :
VR
Approved :
VR
L =2500 X W =1000 mm & Depth from GL =4500
Size:
heq
Designed:
4500
mm is:
2.52 ft 0.77
m
The corresponding lateral live load surcharge on the top of the culvert is given as: 3.91
kN/m
The height for the live load surcharge calculation at the bottom of the culvert is the distance from the bottom surface of the bottom slab to the top of the pavement or fill. 6100 mm Again using interpolation and AASHTO Table 3.11.6.4.1, the equivalent height is: heq
=
heq
=
2 ft 0.61
m
The lateral live load surcharge located at the bottom of the culvert is given as: 3.10 D.
kN/m
Water Load Designers need to consider load cases where the culvert is full of water as well as cases where the culvert is empty. A simple hydrostatic distribution is used for the water load: At the inside of the culvert, the lateral water pressure is: WAtop =
0 kN/m2 9.81
kN/m2
Using a 2D frame model there is an opposite upward reaction from the soil caused by the water inside the culvert: Wabottom
reaction
=
WA bottom * Span
=
8.82
kN/m
(Span + Ts) E.
Live Load The design live loads include the HL-93 truck and tandem loads. Since the span of the box culvert is less than 15 ft, no lane load is applied. Dynamic Load Allowance The dynamic load allowance (IM) for culverts and other buried structures is reduced based on the depth of fill over the culvert. For strength and service limit states: -27.885 The dynamic load allowance may not be taken less than zero.
=
0
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =2500 X W =1000 mm & Depth from GL =4500
Live Load Distribution Live loads are assumed to distribute laterally with depth. The specifications permit designers to increase the footprint of the load with increasing depth of fill. The load is assumed to spread laterally 1.15 times H horizontally in each direction for every foot of fill above the culvert. The intensity of live loads at any depth is assumed to be uniform over the entire footprint.
The assumed tire contact area for each wheel has a width of 20 inches and a length of 10 inches.
Using the distances between wheel lines and axles, the live load intensities at the top of the box culvert can be found. For truck and tandem loadings, the influence area or footprint of the live load is found first. Then the sum of the weights of the wheels is used to determine the intensity of the live load. To determine the live load, use multiple presence factors (MPF). A single loaded lane with a MPF of 1.20 is used for strength g and service limit states. A single 3 Axle
where
with 600 kN Truck
Pw =
130 kN
Axlespacing =
1.8 m
Wtire =
0.51 m
W =
Ltire = L=
configuration produces a live load intensity of:
7.49
m
0.25 m 7.23
m
5.77
kN/m
Therefore WLL+IM
=
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =2500 X W =1000 mm & Depth from GL =4500
Size:
A tandem truck axle configuration produces a live load intensity of:
where
Pw =
105 kN 6 73 6.73
m
where Axlespacing = WLL+IM
1.3 m
=
10.01
kN/m
The live load intensities of the single and tandem axle configurations are compared. Since the tandem axle configuration produces a live load intensity slightly larger than that of the single axle configuration, the tandem axle configuration is used for design in both the strength and service limit states. 10.01 kN therefore WLL+IM = Final Loading DC DC
bottom reaction
=
Sel weight of Culvert
=
53.44
EV =
104.82
kN/m
EHTmax =
81.00
kN/m
EHBmax =
109.80
kN/m
EHTmin =
40.50
kN/m
EHBmin =
54.90
kN/m
=
3.91
kN/m
LLSbottom =
3.10
LLStop
WAtop=
F.
kN/m
kN/m 0 kN/m
WAbottom=
9.81
kN/m
WAbottomreaction=
8.82
kN/m
LL+IMW =
10.01
kN/m
Load Combination Strength Limit states 1 Maximum Vertical Load and Maximum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+ (1.35)(1.05)EHmax + 1.75LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+1.00WA+(0.9/1.05)EHmin 3 Minimum Vertical load and Maximum Horizontal Load 0.90 DC + (0.9/1.05)EV + (1.35)(1.05) EHmax +1.75LS
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =2500 X W =1000 mm & Depth from GL =4500
Service Limit State 1 Maximum Vertical Load and Maximum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00EHmax + 1.00LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00WA+1.00EHmin 3 Minimum Vertical load and Maximum Horizontal Load 1.00 DC + 1.00EV + 1.00EHmax +1.00LS
A structural analysis is performed using a standard commercial matrix-analysis program. The bottom slab of the box culvert is assumed rigid compared to the subgrade. Reactions to vertical loads applied to the culvert (earth, water, live load) are assumed to be carried by uniform, triangular or trapezoidal distributed reactions applied to the bottom slab. Box culverts supported on stiff or rigid subgrades (rock) would require further investigation. The haunches are included in the analysis by increasing the thickness of members near each corner corner. Reinforcement Design
where, F =
1
fy =
420 Mpa
fc' =
35 MPa
b =
1 m
therefore, a =
As x 420 0.85 x 35 x1000
a=
420∗
0.0141
As
Mu =
1 x As x 420 x (d - .0141 * As/2)
Mu =
420 x As*d - 2.961 As^2
√ 176400 ^2 11.844
/5.922
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =2500 X W =1000 mm & Depth from GL =4500
Size:
Side Wall
Max @ Mid Slab@IS Max @ Slab End@OS
From staad Model Outside
Mu =
86.88 kNm
Main bar dia =
14
mm
d = thickness - Cover - dm/2 d= As =
233 mm 913.02
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Ts
As =
913.02 913 02
=
14 mm dia X
for 1 m length
14 mm dia X Mu =
mm2
mm2
As Provided = Inside
560.00
53.33 kNm
150 c/c 6.67
Pcs
Main bar dia =
1,026.25
mm2
14
mm
1,026.25
mm2
d = thickness - Cover - dm/2 d= As =
233 mm 554.26
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 0 002 x b x Ts 560.00
=
560 00 560.00
mm2
mm2
As Provided =
14 mm dia X
for 1 m length
14 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =2500 X W =1000 mm & Depth from GL =4500
Size:
Top Slab
Max @ Slab End @OS
Max @ Mid Slab @IS
From staad Model Inside
Mu =
98.83 kNm
Main bar dia =
16
mm
1,340.41
mm2
12
mm
d = thickness - Cover - dm/2 d= As =
232 mm 1,047.62
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tt
As =
1,047.62
=
16 mm dia X
for 1 m length
16 mm dia X Mu =
mm2
mm2
As Provided =
Outside
560.00
47.09 kNm
150 c/c 6.67
Pcs
Main bar dia =
d = thickness - Cover - dm/2 d= As =
234 mm 486.27 486 27
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tt 560.00
=
560.00
mm2
mm2
As Provided =
12 mm dia X
for 1 m length
12 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
753.98
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =2500 X W =1000 mm & Depth from GL =4500
Size:
Bottom Slab
Max @ Slab End@OS Max @ Mid Slab @IS
From staad Model Inside
Mu =
73.58 kNm
Main bar dia =
16
mm
1,340.41
mm2
12
mm
d = thickness - Cover - dm/2 d= As =
272 mm 655.21
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tb
As =
655.21
=
16 mm dia X
for 1 m length
16 mm dia X Mu =
mm2
mm2
As Provided =
Outside
640.00
82 kNm
150 c/c 6.67
Pcs
Main bar dia =
d = thickness - Cover - dm/2 d= As =
274 mm 726.11 726 11
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tb 726.11
=
640.00
mm2
mm2
As Provided =
12 mm dia X
for 1 m length
12 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
753.98
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Checking of Shear Top Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
225.17 kN
0.17∗√
^′
241.38
kN
> Vu
Bottom Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
207.29 kN
0.17∗√
^′
281.61
kN
> Vu
Designed:
DJ
Checked :
VR
Approved :
VR
L =2500 X W =1000 mm & Depth from GL =4500
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Side Wall
Maximum Shear (Vu) = Shear Capacity
121.96 kN
0.17∗√
(Vc) =
^′
241.38
kN
> Vu
Final Size and Reinforcement Box culvert Inside Dimensions = 2500 x 1000 mm Top Slab Thickness =
280 mm
Bottom Slab Thickness =
320 mm
Side = id Wall ll Thickness hi k
280 mm
Reinforcement Inside
Location
Outside
Top Slab
Dia (mm) 16
C/C 150
Dia (mm) 12
C/C 150
Bottom Slab
16
150
12
150
Side Wall
14
150
14
150
Designed:
DJ
Checked :
VR
Approved :
VR
L =2500 X W =1000 mm & Depth from GL =4500
SULB AL‐JAZEERA CONCRETE MANUFACTURING Project: Client:
BOX CULVERT
Designed:
DJ
Checked :
VR
Approved :
VR
Location: SAUDI ARABIA
SAPAC
BOX CULVERT SIZE 3000 X 1000
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =3000 X W =1000 mm & Depth from GL =4500
Size:
Introduction:
Inside dimensions of the box culvert (SPAN x RISE) The fill height (H) above the culvert are as per the below table. yp section of the culvert is shown in Figure. g Material and design g p parameters are g given in Table. A typical
Material and Design Parameters Reinforced Concrete, c
24
kN/m3
Soil, s
18
kN/m3
Compressive Strength, f’c
35
Span L
3000
Mpa mm
Rise R
1000
mm
Top Slab Thickness, Tt
320
mm
Bottom Slab Thickness, Tb
360
mm
4500
mm
320
mm
Haunch Thickness, Th
50
mm
Reinforcement Clear Cover
40
mm
420
Mpa
Height of Fill H Wall Thickness, Ts
Yield Strength, fy
Modulus Elasticity of Concrete, Ec
27789.4
Mpa
Modulus Elasticity of Steel Reinforcement, Es
200000
Mpa
SULB AL-JAZEERA CONCRETE MANUFACTURING
Designed:
DJ
Checked :
VR
Approved :
VR
Element BOX CULVERT SAPAC L =3000 X W =1000 mm & Depth from GL =4500 Customer: Size: The approximate strip method is used for the design with the 1m wide design strip oriented parallel to the direction of traffic. A 2-Dimensional (2D) plane frame model is used to analyze the box culvert. Beam elements in the 2D model are assumed to be centered in the concrete members. The model is assumed to be externally supported by a pinned support on one end and a roller support on the other end. In addition, the model is always assumed to be in equilibrium so external reactions to loads applied to the structure were assumed to act equal and opposite. A “w” dimension of 1 m is added to the calculations to convert the units to kN/m for consistency with national conventions conventions.
A.
Dead Load The total self-weight of
the culvert top slab is: 57.60
kN (for 1 m wide)
The self-weight of one culvert side wall is: 10.29
kN (for 1 m wide)
Self weight of Haunch 0.03 kN ( (for 1 m wide) )
The top slab weight, wall weights, and all four haunch weights are applied to the bottom slab as an upward reaction from the soil assuming an equivalent uniform pressure. The bottom slab weight is not applied in the model because its load is assumed to be directly resisted by the soil.
Dc bottom B B.
=
63.92
kN (for 1 m wide)
E th P Earth Pressure L Loads d The weight of fill on top of the culvert produces vertical earth pressure (EV). The fill height is measured from the top surface of the top slab to the top of the pavement or fill. The unit weight of the fill is 19.2 kN/m3 The interaction factor for embankment conditions is dependent on the height of fill (H) and the outside width of the culvert (Bc): 1.25
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =3000 X W =1000 mm & Depth from GL =4500
Size:
The design vertical earth pressure at the top of the culvert is: 101.03
kN/m
The lateral earth pressure (EH) on the culvert is found using the equivalent fluid method. For at-rest conditions, a maximum stage full soil unit weight and a minimum stage half soil unit weight will be are used used. At the top of the culvert, the lateral earth pressure is: 81.00
kN/m
(Top)
40.50
kN/m
(Top)
At the bottom of the culvert, the lateral earth pressure is:
C.
=
111 24 111.24
kN/m
(B tt ) (Bottom)
=
55.62
kN/m
(Bottom)
Live Load Surcharge Use an active coefficient of lateral earth pressure ka =
0.2827
The height for the live load surcharge calculation at the top of the culvert is the distance from the top surface of the top slab to the top of the pavement or fill. The height is: H
top of culvert
=
4500 mm
The equivalent q fill height, g , heq q is dependent p on the depth p of fill and can be found using g AASHTO Table 3.11.6.4-1.
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
By interpolation, the equivalent height for a fill depth of =
heq
=
DJ
Checked :
VR
Approved :
VR
L =3000 X W =1000 mm & Depth from GL =4500
Size:
heq
Designed:
4500
mm is:
2.52 ft 0.77
m
The corresponding lateral live load surcharge on the top of the culvert is given as: 3.91
kN/m
The height for the live load surcharge calculation at the bottom of the culvert is the distance from the bottom surface of the bottom slab to the top of the pavement or fill. 6180 mm Again using interpolation and AASHTO Table 3.11.6.4.1, the equivalent height is: heq
=
heq
=
2.03 ft 0.62
m
The lateral live load surcharge located at the bottom of the culvert is given as: 3.15 D.
kN/m
Water Load Designers need to consider load cases where the culvert is full of water as well as cases where the culvert is empty. A simple hydrostatic distribution is used for the water load: At the inside of the culvert, the lateral water pressure is: WAtop =
0 kN/m2 9.81
kN/m2
Using a 2D frame model there is an opposite upward reaction from the soil caused by the water inside the culvert: Wabottom
reaction
=
WA bottom * Span
=
8.86
kN/m
(Span + Ts) E.
Live Load The design live loads include the HL-93 truck and tandem loads. Since the span of the box culvert is less than 15 ft, no lane load is applied. Dynamic Load Allowance The dynamic load allowance (IM) for culverts and other buried structures is reduced based on the depth of fill over the culvert. For strength and service limit states: -27.885 The dynamic load allowance may not be taken less than zero.
=
0
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =3000 X W =1000 mm & Depth from GL =4500
Live Load Distribution Live loads are assumed to distribute laterally with depth. The specifications permit designers to increase the footprint of the load with increasing depth of fill. The load is assumed to spread laterally 1.15 times H horizontally in each direction for every foot of fill above the culvert. The intensity of live loads at any depth is assumed to be uniform over the entire footprint.
The assumed tire contact area for each wheel has a width of 20 inches and a length of 10 inches.
Using the distances between wheel lines and axles, the live load intensities at the top of the box culvert can be found. For truck and tandem loadings, the influence area or footprint of the live load is found first. Then the sum of the weights of the wheels is used to determine the intensity of the live load. To determine the live load, use multiple presence factors (MPF). A single loaded lane with a MPF of 1.20 is used for strength and service limit states. A single 3 Axle
where
with 600 kN Truck
Pw =
130 kN
Axlespacing =
1.8 m
Wtire =
0.51 m
W =
Ltire = L=
configuration produces a live load intensity of:
7 49 7.49
m
0.25 m 7.23
m
5.77
kN/m
Therefore WLL+IM
=
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =3000 X W =1000 mm & Depth from GL =4500
Size:
A tandem truck axle configuration produces a live load intensity of:
where
Pw =
105 kN 6.73
m
where Axlespacing =
1.3 m
=
WLL+IM
10.01
kN/m
The live load intensities of the single and tandem axle configurations are compared. Since the tandem axle configuration produces a live load intensity slightly larger than that of the single axle configuration, the tandem axle configuration is used for design in both the strength and service limit states. 10.01 kN therefore WLL+IM = Final Loading DC DC
=
Sel weight of Culvert
=
63.92
EV =
101.03
kN/m
EHTmax =
81.00
kN/m
EHBmax =
111.24
kN/m
EHTmin =
40.50
kN/m
EHBmin =
55.62
kN/m
bottom reaction
LLStop
=
3 91 3.91
kN/m
LLSbottom =
3.15
kN/m
WAtop=
F.
kN/m
0 kN/m
WAbottom=
9.81
kN/m
WAbottomreaction=
8.86
kN/m
LL+IMW =
10.01
kN/m
Load Combination Strength Limit states 1 Maximum Ma im m Vertical Load and Ma Maximum im m Hori Horizontal ontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+ (1.35)(1.05)EHmax + 1.75LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+1.00WA+(0.9/1.05)EHmin 3 Minimum Vertical load and Maximum Horizontal Load 0.90 DC + (0.9/1.05)EV + (1.35)(1.05) EHmax +1.75LS Service Limit State 1 Maximum Vertical Load and Maximum Horizontal Load
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =3000 X W =1000 mm & Depth from GL =4500
1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00EHmax + 1.00LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00WA+1.00EHmin 3 Minimum Vertical load and Maximum Horizontal Load 1.00 DC + 1.00EV + 1.00EHmax +1.00LS
A structural analysis is performed using a standard commercial matrix-analysis program. The bottom slab of the box culvert is assumed rigid compared to the subgrade. Reactions to vertical loads applied to the culvert (earth, water, live load) are assumed to be carried by uniform, triangular or trapezoidal distributed reactions applied to the bottom slab. Box culverts supported on stiff or rigid subgrades (rock) would require further investigation. The haunches are included in the analysis by increasing the thickness of members near each corner. Reinforcement Design
where, F =
1
fy =
420 Mpa
fc' =
35 MPa
b =
1 m
therefore, a =
As x 420 0.85 x 35 x1000
a=
420∗
0.0141
As
Mu =
1 x As x 420 x (d - .0141 * As/2)
Mu =
420 x As*d - 2.961 As^2
√ 176400 ^2 11.844
/5.922
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =3000 X W =1000 mm & Depth from GL =4500
Size:
Side Wall
Max @ Mid Slab@IS Max @ Slab End@OS
From staad Model Outside
Mu =
123.24 kNm
Main bar dia =
16
mm
d = thickness - Cover - dm/2 d= As =
272 mm 1,110.76
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Ts
As =
1,110.76
=
16 mm dia X
for 1 m length
16 mm dia X Mu =
mm2
mm2
As Provided = Inside
640.00
80.63 kNm
150 c/c / 6.67
Pcs
Main bar dia =
1,340.41 16
mm2 mm
d = thickness - Cover - dm/2 d= As =
272 mm 719.20
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Ts 719.20
=
640.00
mm2
mm2
As Provided =
16 mm dia X
for 1 m length
16 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
1,340.41
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =3000 X W =1000 mm & Depth from GL =4500
Size:
Top Slab
Max @ Slab End @OS
Max @ Mid Slab @IS
From staad Model Inside
Mu =
133.81 kNm
Main bar dia =
16
mm
d = thickness - Cover - dm/2 d= As =
272 mm 1,209.20
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tt
As =
1 209 20 1,209.20
=
16 mm dia X
for 1 m length
16 mm dia X Mu =
mm2
mm2
As Provided =
Outside
640.00
70.7 kNm
150 c/c 6.67
Pcs
Main bar dia =
1,340.41 14
mm2 mm
d = thickness - Cover - dm/2 d= As =
273 mm 626.75
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tt 640.00
=
640.00
mm2
mm2
As Provided =
14 mm dia X
for 1 m length
14 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
1,026.25
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =3000 X W =1000 mm & Depth from GL =4500
Size:
Bottom Slab
Max @ Slab End@OS Max @ Mid Slab @IS
From staad Model Inside
Mu =
97.86 kNm
Main bar dia =
16
mm
d = thickness - Cover - dm/2 d= As =
312 mm 759.84
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tb
As =
759 84 759.84
=
As Provided =
16 mm dia X
for 1 m length
16 mm dia X
Outside
Mu =
720.00
mm2
mm2
111.99 kNm
150 c/c 6.67
Pcs
Main bar dia =
1,340.41 14
mm2 mm
d = thickness - Cover - dm/2 d= As =
313 mm 868.90
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tb 868.90
=
720.00
mm2
mm2
As Provided =
14 mm dia X
for 1 m length
14 mm dia X
150 c/c 6.67
Pcs
1,026.25
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Checking of Shear Top Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
264.84 kN
0.17∗√
^′
281.61
kN
> Vu
Bottom Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
234.51 kN
0.17∗√
^′
321.83
kN
> Vu
Designed:
DJ
Checked :
VR
Approved :
VR
L =3000 X W =1000 mm & Depth from GL =4500
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Side Wall
Maximum Shear (Vu) = Shear Capacity
(Vc) =
142.17 kN
0.17∗√
^′
281.61
kN
> Vu
Final Size and Reinforcement Box culvert Inside Dimensions = 3000 x 1000 mm Top Slab Thickness =
320 mm
Bottom Slab Thickness =
360 mm
Side Wall Thickness =
320 mm
R i f Reinforcement t Inside
Location
Outside
Top Slab
Dia (mm) 16
C/C 150
Dia (mm) 14
C/C 150
Bottom Slab
16
150
14
150
Side Wall
16
150
16
150
Designed:
DJ
Checked :
VR
Approved :
VR
L =3000 X W =1000 mm & Depth from GL =4500
SULB AL‐JAZEERA CONCRETE MANUFACTURING Project: Client:
BOX CULVERT
Designed:
DJ
Checked :
VR
Approved :
VR
Location: SAUDI ARABIA
SAPAC
BOX CULVERT SIZE 2200 X 1000
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =2200 X W =1000 mm & Depth from GL =4500
Size:
Introduction:
Inside dimensions of the box culvert (SPAN x RISE) The fill height (H) above the culvert are as per the below table. A typical section of the culvert is shown in Figure. Material and design parameters are given in Table.
Material and Design Parameters Reinforced Concrete, c
24
kN/m3
Soil, s
18
kN/m3
Compressive Strength, f’c
35
Span L
2200
Mpa mm
Rise R
1000
mm
T Top Sl Slab b Thi Thickness, k Tt
240
mm
Bottom Slab Thickness, Tb
280
mm
4500
mm
240
mm
Haunch Thickness, Th
50
mm
Reinforcement Clear Cover
40
mm
Height of Fill H Wall Thickness, Ts
Yield Strength, fy
Modulus Elasticity of Concrete, Ec Modulus Elasticity of Steel Reinforcement, Es
420
Mpa
27789.4
Mpa
200000
Mpa
SULB AL-JAZEERA CONCRETE MANUFACTURING
Designed:
DJ
Checked :
VR
Approved :
VR
Element BOX CULVERT SAPAC L =2200 X W =1000 mm & Depth from GL =4500 Customer: Size: The approximate strip method is used for the design with the 1m wide design strip oriented parallel to the direction of traffic. A 2-Dimensional (2D) plane frame model is used to analyze the box culvert. Beam elements in the 2D model are assumed to be centered in the concrete members. The model is assumed to be externally supported by a pinned support on one end and a roller support on the other end. In addition, the model is always assumed to be in equilibrium so external reactions to loads applied to the structure were assumed to act equal and opposite opposite. A “w” dimension of 1 m is added to the calculations to convert the units to kN/m for consistency with national conventions.
A.
Dead Load The total self-weight of
the culvert top slab is: 38.59
kN (for 1 m wide)
The self-weight of one culvert side wall is: 7.26
kN (for 1 m wide)
Self weight of Haunch 0.03 kN (for 1 m wide)
The top slab weight, wall weights, and all four haunch weights are applied to the bottom slab as an upward reaction from the soil assuming an equivalent uniform pressure. The bottom slab weight is not applied in the model because its load is assumed to be directly resisted by the soil.
Dc bottom B.
=
44.66
kN (for 1 m wide)
Earth Pressure Loads The weight of fill on top of the culvert produces vertical earth pressure (EV). The fill height is measured from the top surface of the top slab to the top of the pavement or fill. The unit weight of the fill is 19.2 kN/m3 The interaction factor for embankment conditions is dependent on the height of fill (H) and the outside width of the culvert (Bc): 1.34
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =2200 X W =1000 mm & Depth from GL =4500
Size:
The design vertical earth pressure at the top of the culvert is: 108.20
kN/m
The lateral earth pressure (EH) on the culvert is found using the equivalent fluid method. For atrest conditions conditions, a maximum stage full soil unit weight and a minimum stage half soil unit weight will be are used. At the top of the culvert, the lateral earth pressure is: 81.00
kN/m
(Top)
40.50
kN/m
(Top)
At the bottom of the culvert, the lateral earth pressure is:
C.
=
108.36
kN/m
(Bottom)
=
54.18
kN/m
(Bottom)
Live Load Surcharge Use an active coefficient of lateral earth pressure ka
0.2827
The height for the live load surcharge calculation at the top of the culvert is the distance from the top surface of the top slab to the top of the pavement or fill. The height is: H
top of culvert
=
4500 mm
The equivalent fill height, heq is dependent on the depth of fill and can be found using AASHTO Table 3.11.6.4-1.
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
By interpolation, the equivalent height for a fill depth of =
heq
=
DJ
Checked :
VR
Approved :
VR
L =2200 X W =1000 mm & Depth from GL =4500
Size:
heq
Designed:
4500
mm is:
2.52 ft 0.77
m
The corresponding lateral live load surcharge on the top of the culvert is given as: 3.91
kN/m
The height for the live load surcharge calculation at the bottom of the culvert is the distance from the bottom surface of the bottom slab to the top of the pavement or fill. 6020 mm Again using interpolation and AASHTO Table 3.11.6.4.1, the equivalent height is: heq
=
heq
=
2 ft 0.61
m
The lateral live load surcharge located at the bottom of the culvert is given as: 3.10 D.
kN/m
Water Load Designers need to consider load cases where the culvert is full of water as well as cases where the culvert is empty. A simple hydrostatic distribution is used for the water load: At the inside of the culvert, the lateral water pressure is: WAtop =
0 kN/m2 9.81
kN/m2
Using a 2D frame model there is an opposite upward reaction from the soil caused by the water inside the culvert: Wabottom
reaction
=
WA bottom * Span
=
8.85
kN/m
(Span + Ts) E.
Live Load The d Th design i li live l loads d i include l d th the HL HL-93 93 t truck k and d t tandem d l loads. d Si Since th the span of f th the b box culvert l t i is less than 15 ft, no lane load is applied. Dynamic Load Allowance The dynamic load allowance (IM) for culverts and other buried structures is reduced based on the depth of fill over the culvert. For strength and service limit states: -27.885
=
The dynamic load allowance may not be taken less than zero.
0
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =2200 X W =1000 mm & Depth from GL =4500
Live Load Distribution Live loads are assumed to distribute laterally with depth. The specifications permit designers to increase the footprint of the load with increasing depth of fill. The load is assumed to spread laterally 1.15 times H horizontally in each direction for every foot of fill above the culvert. The intensity of live loads at any depth is assumed to be uniform over the entire footprint.
The assumed tire contact area for each wheel has a width of 20 inches and a length of 10 inches.
Using the distances between wheel lines and axles, the live load intensities at the top of the box culvert can be found. For truck and tandem loadings, the influence area or footprint of the live load is found first. Then the sum of the weights of the wheels is used to determine the intensity of the live load. To determine the live load, use multiple presence factors (MPF). A single loaded lane with a MPF of 1.20 is used for strength and service limit states. A single 3 Axle
where
with 600 kN Truck
Pw =
130 kN
Axlespacing =
1.8 m
Wtire =
0.51 m
W =
Ltire = L=
7.49
m
0.25 m 7.23
m
5.77
kN/m
Therefore WLL+IM
=
configuration produces a live load intensity of:
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =2200 X W =1000 mm & Depth from GL =4500
Size:
A tandem truck axle configuration produces a live load intensity of:
where
Pw =
105 kN 6.73
m
where Axlespacing =
1.3 m
=
WLL+IM
10.01
kN/m
The live load intensities of the single and tandem axle configurations are compared. Since the tandem axle configuration produces a live load intensity slightly larger than that of the single axle configuration, the tandem axle configuration is used for design in both the strength and service limit states. 10 01 kN 10.01 therefore WLL+IM = Final Loading DC DC
=
Sel weight of Culvert
=
44.66
EV =
108.20
kN/m
EHTmax =
81.00
kN/m
EHBmax =
108.36
kN/m
EHTmin =
40.50
kN/m
EHBmin =
bottom reaction
54.18
kN/m
=
3.91
kN/m
LLSbottom =
3.10
LLStop
WAtop=
F.
kN/m
kN/m 0 kN/m
WAbottom=
9.81
kN/m
WAbottomreaction=
8.85
kN/m
LL+IMW =
10 01 10.01
kN/ kN/m
Load Combination Strength Limit states 1 Maximum Vertical Load and Maximum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+ (1.35)(1.05)EHmax + 1.75LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+1.00WA+(0.9/1.05)EHmin
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =2200 X W =1000 mm & Depth from GL =4500
3 Minimum Vertical load and Maximum Horizontal Load 0.90 DC + (0.9/1.05)EV + (1.35)(1.05) EHmax +1.75LS Service Limit State 1 Maximum Vertical Load and Maximum Horizontal Load (LL+IM)+1.00EH 1.00 .00 DC C + 1.00 .00 EV + 1.00 .00 ( ) .00 max + 1.00LS .00 S 2 Maximum Vertical Lod and Minimum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00WA+1.00EHmin 3 Minimum Vertical load and Maximum Horizontal Load 1.00 DC + 1.00EV + 1.00EHmax +1.00LS
A structural analysis is performed using a standard commercial matrix-analysis program. The bottom slab of the box culvert is assumed rigid compared to the subgrade. Reactions to vertical loads applied li d to the h culvert l ( (earth, h water, li live l load) d) are assumed d to b be carried i d b by uniform, if triangular i l or trapezoidal distributed reactions applied to the bottom slab. Box culverts supported on stiff or rigid subgrades (rock) would require further investigation. The haunches are included in the analysis by increasing the thickness of members near each corner. Reinforcement Design
where, where F =
1
fy =
420 Mpa
fc' =
35 MPa
b =
1 m
therefore, a =
As x 420 0.85 x 35 x1000
a=
420∗
0.0141
As
Mu =
1 x As x 420 x (d - .0141 * As/2)
Mu =
420 x As*d - 2.961 As^2
√ 176400 ^2 11.844
/5.922
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =2200 X W =1000 mm & Depth from GL =4500
Size:
Side Wall
Max @ Mid Slab@IS
Max @ Slab End@OS
From staad Model Outside
Mu =
67.42 kNm
Main bar dia =
14
mm
d = thickness - Cover - dm/2 d= As =
193 mm 858.66
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 0 002 x b x Ts
As =
858.66
=
14 mm dia X
for 1 m length
14 mm dia X Mu =
mm2
mm2
As Provided = Inside
480 00 480.00
60.77 kNm
150 c/c 6.67
Pcs
Main bar dia =
1,026.25 14
mm2 mm
d = thickness - Cover - dm/2 d= As =
193 mm 771.43
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Ts 771.43
=
480.00
mm2
mm2
As Provided =
14 mm dia X
for 1 m length
14 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
1,026.25
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =2200 X W =1000 mm & Depth from GL =4500
Size:
Top Slab
Max @ Slab End @OS
Max @ Mid Slab @IS
From staad Model Inside
Mu =
74.24 kNm
Main bar dia =
14
mm
d = thickness - Cover - dm/2 d= As =
193 mm 948.74
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tt
As =
948.74
=
14 mm dia X
for 1 m length
14 mm dia X Mu =
mm2
mm2
As Provided =
Outside
480.00
35.43 kNm
150 c/c 6.67
Pcs
Main bar dia =
1,026.25 12
mm2 mm
d = thickness - Cover - dm/2 d= As =
194 mm 441.93
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tt 480.00
=
480.00
mm2
mm2
As Provided =
12 mm dia X
for 1 m length
12 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
753.98
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =2200 X W =1000 mm & Depth from GL =4500
Size:
Bottom Slab
Max @ Slab End@OS Max @ Mid Slab @IS
From staad Model Inside
Mu =
59.52 kNm
Main bar dia =
14
mm
d = thickness - Cover - dm/2 d= As =
233 mm 619.84
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tb
As =
619.84
=
14 mm dia X
for 1 m length
14 mm dia X Mu =
mm2
mm2
As Provided =
Outside
560.00
67.49 kNm
150 c/c 6.67
Pcs
Main bar dia =
1,026.25 12
mm2 mm
d = thickness - Cover - dm/2 d= As =
234 mm 701.54
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tb 701.54
=
560.00
mm2
mm2
As Provided =
12 mm dia X
for 1 m length
12 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
753.98
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Checking of Shear Top Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
191.69 kN
0.17∗√ 201.15
^′ kN
> Vu
Bottom Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
191.55 kN
0.17∗√ 241.38
^′ kN
> Vu
Designed:
DJ
Checked :
VR
Approved :
VR
L =2200 X W =1000 mm & Depth from GL =4500
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Side Wall
Maximum Shear (Vu) = Shear Capacity
(Vc) =
110.83 kN
0.17∗√
^′
201.15
kN
> Vu
Final Size and Reinforcement Box culvert Inside Dimensions = 2200 x 1000 mm Top Slab Thickness =
240 mm
Bottom Slab Thickness =
280 mm
Side Wall Thickness =
240 mm
Reinforcement Inside
Location
Outside
Top Slab
Dia (mm) 14
C/C 150
Dia (mm) 12
C/C 150
Bottom Slab
14
150
12
150
Side Wall
14
150
14
150
Designed:
DJ
Checked :
VR
Approved :
VR
L =2200 X W =1000 mm & Depth from GL =4500
SULB AL‐JAZEERA CONCRETE MANUFACTURING Project: Client:
BOX CULVERT
Designed:
DJ
Checked :
VR
Approved :
VR
Location: SAUDI ARABIA
SAPAC
BOX CULVERT SIZE 2000 X 1000
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =2000 X W =1000 mm & Depth from GL =4500
Size:
Introduction:
Inside dimensions of the box culvert (SPAN x RISE) The fill height (H) above the culvert are as per the below table. A typical section of the culvert is shown in Figure. Material and design parameters are given in Table.
Material and Design Parameters Reinforced Concrete, c
24
kN/m3
Soil, s
18
kN/m3
Compressive Strength, f’c
35
Span L
2000
Mpa mm
Rise R
1000
mm
Top Slab Thickness, Tt
240
mm
Bottom Slab Thickness, Tb
280
mm
4500
mm
240
mm
Haunch Thickness, Th
50
mm
Reinforcement Clear Cover
40
mm
420
Mpa
Modulus Elasticity of Concrete, Ec
27789.4
Mpa
Modulus d l Elasticity l off Steell Reinforcement, f Es
200000
Mpa
Height of Fill H Wall Thickness, Ts
Yield Strength, fy
SULB AL-JAZEERA CONCRETE MANUFACTURING
Designed:
DJ
Checked :
VR
Approved :
VR
Element BOX CULVERT SAPAC L =2000 X W =1000 mm & Depth from GL =4500 Customer: Size: The approximate strip method is used for the design with the 1m wide design strip oriented parallel to the direction of traffic. A 2-Dimensional (2D) plane frame model is used to analyze the box culvert. Beam elements in the 2D model are assumed to be centered in the concrete members. The model is assumed to be externally supported by a pinned support on one end and a roller support on the other end. In addition, the model is always assumed to be in equilibrium q so external reactions to loads applied pp to the structure were assumed to act equal q and opposite. pp A “w” dimension of 1 m is added to the calculations to convert the units to kN/m for consistency with national conventions.
A.
Dead Load The total self-weight of
the culvert top slab is: 37.44
kN (for 1 m wide)
The self-weight of one culvert side wall is: 7.26
kN (for 1 m wide)
Self weight of Haunch 0.03 kN (for 1 m wide)
The top slab weight, wall weights, and all four haunch weights are applied to the bottom slab as an upward reaction from the soil assuming an equivalent uniform pressure. The bottom slab weight is not applied in the model because its load is assumed to be directly resisted by the soil.
Dc bottom B.
=
44.04
kN (for 1 m wide)
Earth Pressure Loads The weight of fill on top of the culvert produces vertical earth pressure (EV). The fill height is measured from the top surface of the top slab to the top of the pavement or fill. The unit weight of the fill is 19.2 kN/m3 The interaction factor for embankment conditions is dependent on the height of fill (H) and the outside width of the culvert (Bc): 1.36
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =2000 X W =1000 mm & Depth from GL =4500
Size:
The design vertical earth pressure at the top of the culvert is: 110.40
kN/m
The lateral earth pressure (EH) on the culvert is found using the equivalent fluid method. For at-rest conditions, , a maximum stage g full soil unit weight g and a minimum stage g half soil unit weight g will be are used. At the top of the culvert, the lateral earth pressure is: 81.00
kN/m
(Top)
40.50
kN/m
(Top)
At the bottom of the culvert, the lateral earth pressure is:
C.
=
108.36
kN/m
(Bottom)
=
54.18
kN/m
(Bottom)
Live Load Surcharge Use an active coefficient of lateral earth pressure ka
0.2827
The height for the live load surcharge calculation at the top of the culvert is the distance from the top surface of the top slab to the top of the pavement or fill. The height is: H
top of culvert
=
4500 mm
The equivalent fill height, heq is dependent on the depth of fill and can be found using AASHTO Table 3.11.6.4-1.
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
By interpolation, the equivalent height for a fill depth of =
heq
=
DJ
Checked :
VR
Approved :
VR
L =2000 X W =1000 mm & Depth from GL =4500
Size:
heq
Designed:
4500
mm is:
2.52 ft 0.77
m
The corresponding lateral live load surcharge on the top of the culvert is given as: 3.91
kN/m
The height for the live load surcharge calculation at the bottom of the culvert is the distance from the bottom surface of the bottom slab to the top of the pavement or fill. 6020 mm Again using interpolation and AASHTO Table 3.11.6.4.1, the equivalent height is: heq
=
heq
=
2 ft 0 61 0.61
m
The lateral live load surcharge located at the bottom of the culvert is given as: 3.10 D.
kN/m
Water Load Designers need to consider load cases where the culvert is full of water as well as cases where the culvert is empty. A simple hydrostatic distribution is used for the water load: At the inside of the culvert, the lateral water pressure is: WAtop =
0 kN/m2 9.81
kN/m2
Using a 2D frame model there is an opposite upward reaction from the soil caused by the water inside the culvert: Wabottom
reaction
=
WA bottom * Span
=
8.76
kN/m
(Span + Ts) E.
Live Load The design live loads include the HL-93 truck and tandem loads. Since the span of the box culvert is less than 15 ft, no lane load is applied. Dynamic Load Allowance The dynamic load allowance (IM) for culverts and other buried structures is reduced based on the depth of fill over the culvert. For strength and service limit states: -27.885
=
The dynamic load allowance may not be taken less than zero.
0
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =2000 X W =1000 mm & Depth from GL =4500
Live Load Distribution Live loads are assumed to distribute laterally with depth. The specifications permit designers to increase the footprint of the load with increasing depth of fill. The load is assumed to spread laterally 1.15 times H horizontally in each direction for every foot of fill above the culvert. The intensity of live loads at any depth is assumed to be uniform over the entire footprint.
The assumed tire contact area for each wheel has a width of 20 inches and a length of 10 inches.
Using the distances between wheel lines and axles, the live load intensities at the top of the box culvert can be found. For truck and tandem loadings, the influence area or footprint of the live load is found first. Then the sum of the weights of the wheels is used to determine the intensity of the live load. To determine the live load, use multiple presence factors (MPF). A single loaded lane with a MPF of 1 20 is used for strength and service limit states 1.20 states. A single 3 Axle
where
with 600 kN Truck
Pw =
130 kN
Axlespacing =
1.8 m
Wtire =
0 51 m 0.51
W =
Ltire = L=
7.49
m
0.25 m 7.23
m
5.77
kN/m
Therefore WLL+IM
=
configuration produces a live load intensity of:
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =2000 X W =1000 mm & Depth from GL =4500
Size:
A tandem truck axle configuration produces a live load intensity of:
where
Pw =
105 kN 6.73
m
where Axlespacing =
1.3 m
=
WLL+IM
10.01
kN/m
The live load intensities of the single and tandem axle configurations are compared. Since the tandem axle configuration produces a live load intensity slightly larger than that of the single axle configuration, the tandem axle configuration is used for design in both the strength and service limit states. 10.01 kN therefore WLL+IM = Final Loading DC DC
=
Sel weight of Culvert
=
44.04
EV =
110.40
kN/m
EHTmax =
81.00
kN/m
EHBmax =
108.36
kN/m
bottom reaction
EHTmin = T i
40.50 40 50
kN/m
EHBmin =
54.18
kN/m
=
3.91
kN/m
LLSbottom =
3.10
kN/m
LLStop
WAtop=
F.
kN/m
0 kN/m
WAbottom=
9.81
kN/m
WAbottomreaction=
8.76
kN/m
LL+IMW =
10.01
kN/m
Load Combination Strength Limit states 1 Maximum Vertical Load and Maximum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+ (1.35)(1.05)EHmax + 1.75LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+1.00WA+(0.9/1.05)EHmin 3 Minimum Vertical load and Maximum Horizontal Load
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =2000 X W =1000 mm & Depth from GL =4500
0.90 DC + (0.9/1.05)EV + (1.35)(1.05) EHmax +1.75LS Service Limit State 1 Maximum Vertical Load and Maximum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00EHmax + 1.00LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00WA+1.00EHmin 3 Minimum Vertical load and Maximum Horizontal Load 1.00 DC + 1.00EV + 1.00EHmax +1.00LS
A structural analysis is performed using a standard commercial matrix-analysis program. The bottom slab of the box culvert is assumed rigid compared to the subgrade. Reactions to vertical loads applied to the culvert (earth, water, live load) are assumed to be carried by uniform, triangular or trapezoidal p distributed reactions applied pp to the bottom slab. Box culverts supported pp on stiff or rigid g subgrades (rock) would require further investigation. The haunches are included in the analysis by increasing the thickness of members near each corner. Reinforcement Design
where, F =
1
fy =
420 Mpa
fc' =
35 MPa
b =
1 m
therefore, a =
As x 420 0.85 x 35 x1000
a=
420∗
0.0141
As
Mu =
1 x As x 420 x ( (d - .0141 * As/2) / )
Mu =
420 x As*d - 2.961 As^2
√ 176400 ^2 11.844
/5.922
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =2000 X W =1000 mm & Depth from GL =4500
Size:
Side Wall
Max @ Mid Slab@IS
Max @ Slab End@OS
From staad Model Outside
Mu =
56.943 kNm
Main bar dia =
12
mm
d = thickness - Cover - dm/2 d= As =
194 mm 717.57
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Ts
As =
717.57
=
As Provided =
12 mm dia X
for 1 m length
12 mm dia X
Inside
Mu =
480.00
mm2
mm2
50.254 kNm
150 c/c 6.67
Pcs
Main bar dia =
753.98 12
mm2 mm
d = thickness - Cover - dm/2 d= As =
194 mm 631.25
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Ts 631.25
=
480.00
mm2
mm2
As Provided =
12 mm dia X
for 1 m length
12 mm dia X
150 c/c 6.67
Pcs
753.98
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =2000 X W =1000 mm & Depth from GL =4500
Size:
Top Slab
Max @ Slab End @OS
Max @ Mid Slab @IS
From staad Model Inside
Mu =
69.1 kNm
Main bar dia =
14
mm
d = thickness - Cover - dm/2 d= As =
193 mm 880.79
mm2
Minimum sidewall flexural reinforcement A i Asmin therefore
= 0.002 0 002 x b x Tt
As =
880.79
=
As Provided =
14 mm dia X
for 1 m length
14 mm dia X
Outside
Mu =
480 00 480.00
mm2 2
mm2
28.65 kNm
150 c/c 6.67
Pcs
Main bar dia =
1,026.25 12
mm2 mm
d = thickness - Cover - dm/2 d= As =
194 mm 356.23
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tt 480.00
=
480.00
mm2
mm2
As Provided =
12 mm dia X
for 1 m length
12 mm dia X
150 c/c 6.67
Pcs
753.98
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =2000 X W =1000 mm & Depth from GL =4500
Size:
Bottom Slab
Max @ Slab End@OS Max @ Mid Slab @IS
From staad Model Inside
Mu =
52.204 kNm
Main bar dia =
14
mm
d = thickness - Cover - dm/2 d= As =
233 mm 542.36
mm2
Minimum sidewall flexural reinforcement A i Asmin therefore
= 0.002 0 002 x b x Tb
As =
560.00
=
As Provided =
14 mm dia X
for 1 m length
14 mm dia X
Outside
Mu =
560 00 560.00
mm2 2
mm2
55.824 kNm
150 c/c 6.67
Pcs
Main bar dia =
1,026.25 12
mm2 mm
d = thickness - Cover - dm/2 d= As =
234 mm 578.08
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tb 578.08
=
560.00
mm2
mm2
As Provided =
12 mm dia X
for 1 m length
12 mm dia X
150 c/c 6.67
Pcs
753.98
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Checking of Shear Top Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
185.94 kN
0.17∗√ 201.15
^′ kN
> Vu
Bottom Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
178.7 kN
0.17∗√ 0 17 √ 241.38
^′ kN
> Vu
Designed:
DJ
Checked :
VR
Approved :
VR
L =2000 X W =1000 mm & Depth from GL =4500
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Side Wall
Maximum Shear (Vu) = Shear Capacity
(Vc) =
103.526 kN
0.17∗√
^′
201.15
kN
> Vu
Final Size and Reinforcement Box culvert Inside Dimensions = 2000 x 1000 mm Top Slab Thickness =
240 mm
Bottom Slab Thickness =
280 mm
Side Wall Thickness =
240 mm
Reinforcement Inside
Location
Outside
Top Slab
Dia (mm) 14
C/C 150
Dia (mm) 12
C/C 150
Bottom Slab
14
150
12
150
Side Wall
12
150
12
150
Designed:
DJ
Checked :
VR
Approved :
VR
L =2000 X W =1000 mm & Depth from GL =4500
SULB AL‐JAZEERA CONCRETE MANUFACTURING Project: Client:
BOX CULVERT
Designed:
DJ
Checked :
VR
Approved :
VR
Location: SAUDI ARABIA
SAPAC
BOX CULVERT SIZE 1800 X 1000
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =1800 X W =1000 mm & Depth from GL =3500
Size:
Introduction:
Inside dimensions of the box culvert (SPAN x RISE) The fill height (H) above the culvert are as per the below table. t bl A t typical i l section ti of f th the culvert l t i is shown h i in Fi Figure. M Material t i l and d d design i parameters t are given i i in T Table. bl
Material and Design Parameters Reinforced Concrete, c
24
kN/m3
Soil, s
18
kN/m3
Compressive Strength, f’c
35
Span L
1800
Mpa mm
Rise R
1000
mm
Top Slab Thickness, Tt
240
mm
Bottom Slab Thickness, Tb
280
mm
3500
mm
Height of Fill H Wall Thickness, Ts
240
mm
Haunch Thickness, Th
50
mm
Reinforcement Clear Cover
40
mm
Yield Strength, fy
Modulus Elasticity of Concrete, Ec Modulus Elasticity of Steel Reinforcement, Es
420
Mpa
27789.4
Mpa
200000
Mpa
SULB AL-JAZEERA CONCRETE MANUFACTURING
Designed:
DJ
Checked :
VR
Approved :
VR
Element BOX CULVERT SAPAC L =1800 X W =1000 mm & Depth from GL =3500 Customer: Size: The approximate strip method is used for the design with the 1m wide design strip oriented parallel to the direction of traffic. A 2-Dimensional (2D) plane frame model is used to analyze the box culvert. Beam elements in the 2D model are assumed to be centered in the concrete members. The model is assumed to be externally supported by a pinned support on one end and a roller support on the other end. In addition, the model is always assumed to be in equilibrium so external reactions to loads applied to the structure were assumed to act equal and opposite. A “w” dimension of 1 m is added to the calculations to convert the units to kN/m for consistency with national conventions.
A.
Dead Load The total self-weight of
the culvert top slab is: 30.53
kN (for 1 m wide)
The self-weight of one culvert side wall is: 7.26
kN (for 1 m wide)
Self weight of Haunch 0.03 kN (for 1 m wide)
The top slab weight, wall weights, and all four haunch weights are applied to the bottom slab as an upward reaction from the soil assuming an equivalent uniform pressure. The bottom slab weight is not applied in the model because its load is assumed to be directly resisted by the soil.
Dc bottom B.
=
37.76
kN (for 1 m wide)
Earth Pressure Loads The weight of fill on top of the culvert produces vertical earth pressure (EV). The fill height is measured from the top surface of the top slab to the top of the pavement or fill. The unit weight of the fill is 19.2 kN/m3 The interaction factor for embankment conditions is dependent on the height of fill (H) and the outside width of the culvert (Bc): 1 31 1.31
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =1800 X W =1000 mm & Depth from GL =3500
Size:
The design vertical earth pressure at the top of the culvert is: 82.34
kN/m
The lateral earth pressure (EH) on the culvert is found using the equivalent fluid method. For at-rest conditions, a maximum stage full soil unit weight and a minimum stage half soil unit weight will be are used. At the top of the culvert, the lateral earth pressure is: 63.00
kN/m
(Top)
31.50
kN/m
(Top)
At the bottom of the culvert, the lateral earth pressure is:
C.
=
90.36
kN/m
(Bottom)
=
45.18
kN/m
(Bottom)
Live Load Surcharge Use an active coefficient of lateral earth pressure ka
0.2827
The height for the live load surcharge calculation at the top of the culvert is the distance from the top surface of the top slab to the top of the pavement or fill. The height is: H
top p of culvert
=
3500 mm
The equivalent fill height, heq is dependent on the depth of fill and can be found using AASHTO Table 3.11.6.4-1.
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
By interpolation, the equivalent height for a fill depth of =
heq
=
DJ
Checked :
VR
Approved :
VR
L =1800 X W =1000 mm & Depth from GL =3500
Size:
heq
Designed:
3500
mm is:
2.85 ft 0.87
m
The corresponding lateral live load surcharge on the top of the culvert is given as: 4.42
kN/m
The height for the live load surcharge calculation at the bottom of the culvert is the distance from the bottom surface of the bottom slab to the top of the pavement or fill. 5020 mm Again using interpolation and AASHTO Table 3.11.6.4.1, the equivalent height is: heq
=
heq
=
2.35 ft 0.72
m
The lateral live load surcharge located at the bottom of the culvert is given as: 3.65 D.
kN/m
Water Load Designers need to consider load cases where the culvert is full of water as well as cases where the culvert is empty. A simple hydrostatic distribution is used for the water load: At the inside of the culvert, the lateral water pressure is: WAtop =
0 kN/m2 9.81
kN/m2
Using a 2D frame model there is an opposite upward reaction from the soil caused by the water inside the culvert: Wabottom
reaction
=
WA bottom * Span
=
8.66
kN/m
(Span + Ts) E.
Live Load The design live loads include the HL-93 truck and tandem loads. Since the span of the box culvert is less than 15 ft, no lane load is applied. Dynamic Load Allowance The dynamic load allowance (IM) for culverts and other buried structures is reduced based on the depth of fill over the culvert. For strength and service limit states: -14.355 The dynamic load allowance may not be taken less than zero.
=
0
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =1800 X W =1000 mm & Depth from GL =3500
Live Load Distribution Live loads are assumed to distribute laterally with depth. The specifications permit designers to increase the footprint of the load with increasing depth of fill. The load is assumed to spread laterally 1.15 times H horizontally in each direction for every foot of fill above the culvert. The intensity of live loads at any depth is assumed to be uniform over the entire footprint.
The assumed tire contact area for each wheel has a width of 20 inches and a length of 10 inches.
Using the distances between wheel lines and axles, the live load intensities at the top of the box culvert can be found. For truck and tandem loadings, the influence area or footprint of the live load is found first. Then the sum of the weights of the wheels is used to determine the intensity of the live load. To determine the live load, use multiple presence factors (MPF). A single loaded lane with a MPF of 1.20 is used for strength g and service limit states. A single 3 Axle
where
with 600 kN Truck
Pw =
130 kN
Axlespacing =
1.8 m
Wtire =
0.51 m
W =
Ltire = L=
6.34
m
0.25 m 6.08
m
8.11
kN/m
Therefore WLL+IM
=
configuration produces a live load intensity of:
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =1800 X W =1000 mm & Depth from GL =3500
Size:
A tandem truck axle configuration produces a live load intensity of:
where
Pw =
105 kN 5 58 5.58
m
where Axlespacing = WLL+IM
1.3 m
=
14.27
kN/m
The live load intensities of the single and tandem axle configurations are compared. Since the tandem axle configuration produces a live load intensity slightly larger than that of the single axle configuration, the tandem axle configuration is used for design in both the strength and service limit states. 14.27 kN therefore WLL+IM = Final Loading DC DC
bottom reaction
=
Sel weight of Culvert
=
37.76
EV =
82.34
kN/m
EHTmax =
63.00
kN/m
EHBmax =
90.36
kN/m
EHTmin =
31.50
kN/m
EHBmin =
45.18
kN/m
=
4.42
kN/m
LLSbottom =
3.65
LLStop
WAtop=
F.
kN/m
kN/m 0 kN/m
WAbottom=
9.81
kN/m
WAbottomreaction=
8.66
kN/m
LL+IMW =
14.27
kN/m
Load Combination Strength Limit states 1 Maximum Vertical Load and Maximum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+ (1.35)(1.05)EHmax + 1.75LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+1.00WA+(0.9/1.05)EHmin 3 Minimum Vertical load and Maximum Horizontal Load 0.90 DC + (0.9/1.05)EV + (1.35)(1.05) EHmax +1.75LS
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =1800 X W =1000 mm & Depth from GL =3500
Service Limit State 1 Maximum Vertical Load and Maximum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00EHmax + 1.00LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00WA+1.00EHmin 3 Minimum Vertical load and Maximum Horizontal Load 1.00 DC + 1.00EV + 1.00EHmax +1.00LS
A structural analysis is performed using a standard commercial matrix-analysis program. The bottom slab of the box culvert is assumed rigid compared to the subgrade. Reactions to vertical loads applied to the culvert (earth, water, live load) are assumed to be carried by uniform, triangular or trapezoidal distributed reactions applied to the bottom slab. Box culverts supported on stiff or rigid subgrades (rock) would require further investigation. The haunches are included in the analysis by increasing the thickness of members near each corner corner. Reinforcement Design
where, F =
1
fy =
420 Mpa
fc' =
35 MPa
b =
1 m
therefore, a =
As x 420 0.85 x 35 x1000
a=
420∗
0.0141
As
Mu =
1 x As x 420 x (d - .0141 * As/2)
Mu =
420 x As*d - 2.961 As^2
√ 176400 ^2 11.844
/5.922
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =1800 X W =1000 mm & Depth from GL =3500
Size:
Side Wall
Max @ Mid Slab@IS Max @ Slab End@OS
From staad Model Outside
Mu =
37.9 kNm
Main bar dia =
10
mm
d = thickness - Cover - dm/2 d= As =
195 mm 470.77
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Ts
As =
480.00 480 00
=
10 mm dia X
for 1 m length
10 mm dia X Mu =
mm2
mm2
As Provided = Inside
480.00
19.55 kNm
150 c/c 6.67
Pcs
Main bar dia =
523.60 10
mm2 mm
d = thickness - Cover - dm/2 d= As =
195 mm 240.80
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 0 002 x b x Ts 480.00
=
480 00 480.00
mm2
mm2
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
523.60
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =1800 X W =1000 mm & Depth from GL =3500
Size:
Top Slab
Max @ Slab End @OS
Max @ Mid Slab @IS
From staad Model Inside
Mu =
48.63 kNm
Main bar dia =
12
mm
d = thickness - Cover - dm/2 d= As =
194 mm 610.37
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tt
As =
610.37
=
12 mm dia X
for 1 m length
12 mm dia X Mu =
mm2
mm2
As Provided =
Outside
480.00
17.13 kNm
150 c/c 6.67
Pcs
Main bar dia =
753.98 10
mm2 mm
d = thickness - Cover - dm/2 d= As =
195 mm 210.76 210 76
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tt 480.00
=
480.00
mm2
mm2
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
523.60
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =1800 X W =1000 mm & Depth from GL =3500
Size:
Bottom Slab
Max @ Slab End@OS Max @ Mid Slab @IS
From staad Model Inside
Mu =
32.55 kNm
Main bar dia =
12
mm
d = thickness - Cover - dm/2 d= As =
234 mm 334.57
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tb
As =
560.00
=
12 mm dia X
for 1 m length
12 mm dia X Mu =
mm2
mm2
As Provided =
Outside
560.00
32.45 kNm
150 c/c 6.67
Pcs
Main bar dia =
753.98 12
mm2 mm
d = thickness - Cover - dm/2 d= As =
234 mm 333.53 333 53
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tb 560.00
=
560.00
mm2
mm2
As Provided =
12 mm dia X
for 1 m length
12 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
753.98
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Checking of Shear Top Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
139.15 kN
0.17∗√ 201.15
^′ kN
> Vu
Bottom Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
170.25 kN
0.17∗√ 241.38
^′ kN
> Vu
Designed:
DJ
Checked :
VR
Approved :
VR
L =1800 X W =1000 mm & Depth from GL =3500
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Side Wall
Maximum Shear (Vu) = Shear Capacity
(Vc) =
79.95 kN
0.17∗√
^′
201.15
kN
> Vu
Final Size and Reinforcement Box culvert Inside Dimensions = 1800 x 1000 mm Top Slab Thickness =
240 mm
Bottom Slab Thickness =
280 mm
Side = id Wall ll Thickness hi k
240 mm
Reinforcement Inside
Location
Outside
Top Slab
Dia (mm) 12
C/C 150
Dia (mm) 10
C/C 150
Bottom Slab
12
150
12
150
Side Wall
10
150
10
150
Designed:
DJ
Checked :
VR
Approved :
VR
L =1800 X W =1000 mm & Depth from GL =3500
SULB AL‐JAZEERA CONCRETE MANUFACTURING Project: Client:
BOX CULVERT
Designed:
DJ
Checked :
VR
Approved :
VR
Location: SAUDI ARABIA
SAPAC
BOX CULVERT SIZE 1400 X 1000
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
ID
Checked :
VR
Approved :
VR
L =1400 X W =1000 mm & Depth from GL =4500
Size:
Introduction:
Inside dimensions of the box culvert (SPAN x RISE) The fill height (H) above the culvert are as per the below table. A typical section of the culvert is shown in Figure. Material and design parameters are given in Table.
Material and Design Parameters Reinforced Concrete, c
24
kN/m3
Soil, s
18
kN/m3
Compressive Strength, f’c
35
Span L
1400
Mpa mm
Rise R
1000
mm
T Top Sl Slab b Thi Thickness, k Tt
220
mm
Bottom Slab Thickness, Tb
260
mm
4500
mm
220
mm
Haunch Thickness, Th
50
mm
Reinforcement Clear Cover
40
mm
Height of Fill H Wall Thickness, Ts
Yield Strength, fy
Modulus Elasticity of Concrete, Ec Modulus Elasticity of Steel Reinforcement, Es
420
Mpa
27789.4
Mpa
200000
Mpa
SULB AL-JAZEERA CONCRETE MANUFACTURING
Designed:
ID
Checked :
VR
Approved :
VR
Element BOX CULVERT SAPAC L =1400 X W =1000 mm & Depth from GL =4500 Customer: Size: The approximate strip method is used for the design with the 1m wide design strip oriented parallel to the direction of traffic. A 2-Dimensional (2D) plane frame model is used to analyze the box culvert. Beam elements in the 2D model are assumed to be centered in the concrete members. The model is assumed to be externally supported by a pinned support on one end and a roller support on the other end. In addition, the model is always assumed to be in equilibrium so external reactions to loads applied to the structure were assumed to act equal and opposite opposite. A “w” dimension of 1 m is added to the calculations to convert the units to kN/m for consistency with national conventions.
A.
Dead Load The total self-weight of
the culvert top slab is: 31.15
kN (for 1 m wide)
The self-weight of one culvert side wall is: 6.55
kN (for 1 m wide)
Self weight of Haunch 0.03 kN (for 1 m wide)
The top slab weight, wall weights, and all four haunch weights are applied to the bottom slab as an upward reaction from the soil assuming an equivalent uniform pressure. The bottom slab weight is not applied in the model because its load is assumed to be directly resisted by the soil.
Dc bottom B.
=
39.35
kN (for 1 m wide)
Earth Pressure Loads The weight of fill on top of the culvert produces vertical earth pressure (EV). The fill height is measured from the top surface of the top slab to the top of the pavement or fill. The unit weight of the fill is 19.2 kN/m3 The interaction factor for embankment conditions is dependent on the height of fill (H) and the outside width of the culvert (Bc): 1.49
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
ID
Checked :
VR
Approved :
VR
L =1400 X W =1000 mm & Depth from GL =4500
Size:
The design vertical earth pressure at the top of the culvert is: 120.62
kN/m
The lateral earth pressure (EH) on the culvert is found using the equivalent fluid method. For atrest conditions conditions, a maximum stage full soil unit weight and a minimum stage half soil unit weight will be are used. At the top of the culvert, the lateral earth pressure is: 81.00
kN/m
(Top)
40.50
kN/m
(Top)
At the bottom of the culvert, the lateral earth pressure is:
C.
=
107.64
kN/m
(Bottom)
=
53.82
kN/m
(Bottom)
Live Load Surcharge Use an active coefficient of lateral earth pressure ka
0.2827
The height for the live load surcharge calculation at the top of the culvert is the distance from the top surface of the top slab to the top of the pavement or fill. The height is: H
top of culvert
=
4500 mm
The equivalent fill height, heq is dependent on the depth of fill and can be found using AASHTO Table 3.11.6.4-1.
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
By interpolation, the equivalent height for a fill depth of =
heq
=
ID
Checked :
VR
Approved :
VR
L =1400 X W =1000 mm & Depth from GL =4500
Size:
heq
Designed:
4500
mm is:
2.52 ft 0.77
m
The corresponding lateral live load surcharge on the top of the culvert is given as: 3.91
kN/m
The height for the live load surcharge calculation at the bottom of the culvert is the distance from the bottom surface of the bottom slab to the top of the pavement or fill. 5980 mm Again using interpolation and AASHTO Table 3.11.6.4.1, the equivalent height is: heq
=
heq
=
2.04 ft 0.62
m
The lateral live load surcharge located at the bottom of the culvert is given as: 3.16 D.
kN/m
Water Load Designers need to consider load cases where the culvert is full of water as well as cases where the culvert is empty. A simple hydrostatic distribution is used for the water load: At the inside of the culvert, the lateral water pressure is: WAtop =
0 kN/m2 9.81
kN/m2
Using a 2D frame model there is an opposite upward reaction from the soil caused by the water inside the culvert: Wabottom
reaction
=
WA bottom * Span
=
8.48
kN/m
(Span + Ts) E.
Live Load The d Th design i li live l loads d i include l d th the HL HL-93 93 t truck k and d t tandem d l loads. d Si Since th the span of f th the b box culvert l t i is less than 15 ft, no lane load is applied. Dynamic Load Allowance The dynamic load allowance (IM) for culverts and other buried structures is reduced based on the depth of fill over the culvert. For strength and service limit states: -27.885
=
The dynamic load allowance may not be taken less than zero.
0
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
ID
Checked :
VR
Approved :
VR
L =1400 X W =1000 mm & Depth from GL =4500
Live Load Distribution Live loads are assumed to distribute laterally with depth. The specifications permit designers to increase the footprint of the load with increasing depth of fill. The load is assumed to spread laterally 1.15 times H horizontally in each direction for every foot of fill above the culvert. The intensity of live loads at any depth is assumed to be uniform over the entire footprint.
The assumed tire contact area for each wheel has a width of 20 inches and a length of 10 inches.
Using the distances between wheel lines and axles, the live load intensities at the top of the box culvert can be found. For truck and tandem loadings, the influence area or footprint of the live load is found first. Then the sum of the weights of the wheels is used to determine the intensity of the live load. To determine the live load, use multiple presence factors (MPF). A single loaded lane with a MPF of 1.20 is used for strength and service limit states. A single 3 Axle
where
with 600 kN Truck
Pw =
130 kN
Axlespacing =
1.8 m
Wtire =
0.51 m
W =
Ltire = L=
7.49
m
0.25 m 7.23
m
5.77
kN/m
Therefore WLL+IM
=
configuration produces a live load intensity of:
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
ID
Checked :
VR
Approved :
VR
L =1400 X W =1000 mm & Depth from GL =4500
Size:
A tandem truck axle configuration produces a live load intensity of:
where
Pw =
105 kN 6.73
m
where Axlespacing =
1.3 m
=
WLL+IM
10.01
kN/m
The live load intensities of the single and tandem axle configurations are compared. Since the tandem axle configuration produces a live load intensity slightly larger than that of the single axle configuration, the tandem axle configuration is used for design in both the strength and service limit states. 10 01 kN 10.01 therefore WLL+IM = Final Loading DC DC
=
Sel weight of Culvert
=
39.35
EV =
120.62
kN/m
EHTmax =
81.00
kN/m
EHBmax =
107.64
kN/m
EHTmin =
40.50
kN/m
EHBmin =
bottom reaction
53.82
kN/m
=
3.91
kN/m
LLSbottom =
3.16
LLStop
WAtop=
F.
kN/m
kN/m 0 kN/m
WAbottom=
9.81
kN/m
WAbottomreaction=
8.48
kN/m
LL+IMW =
10 01 10.01
kN/ kN/m
Load Combination Strength Limit states 1 Maximum Vertical Load and Maximum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+ (1.35)(1.05)EHmax + 1.75LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+1.00WA+(0.9/1.05)EHmin
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
ID
Checked :
VR
Approved :
VR
L =1400 X W =1000 mm & Depth from GL =4500
3 Minimum Vertical load and Maximum Horizontal Load 0.90 DC + (0.9/1.05)EV + (1.35)(1.05) EHmax +1.75LS Service Limit State 1 Maximum Vertical Load and Maximum Horizontal Load (LL+IM)+1.00EH 1.00 .00 DC C + 1.00 .00 EV + 1.00 .00 ( ) .00 max + 1.00LS .00 S 2 Maximum Vertical Lod and Minimum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00WA+1.00EHmin 3 Minimum Vertical load and Maximum Horizontal Load 1.00 DC + 1.00EV + 1.00EHmax +1.00LS
A structural analysis is performed using a standard commercial matrix-analysis program. The bottom slab of the box culvert is assumed rigid compared to the subgrade. Reactions to vertical loads applied li d to the h culvert l ( (earth, h water, li live l load) d) are assumed d to b be carried i d b by uniform, if triangular i l or trapezoidal distributed reactions applied to the bottom slab. Box culverts supported on stiff or rigid subgrades (rock) would require further investigation. The haunches are included in the analysis by increasing the thickness of members near each corner. Reinforcement Design
where, where F =
1
fy =
420 Mpa
fc' =
35 MPa
b =
1 m
therefore, a =
As x 420 0.85 x 35 x1000
a=
420∗
0.0141
As
Mu =
1 x As x 420 x (d - .0141 * As/2)
Mu =
420 x As*d - 2.961 As^2
√ 176400 ^2 11.844
/5.922
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =1400 X W =1000 mm & Depth from GL =4500
Size:
Side Wall
Max @ Mid Slab@IS
Max @ Slab End@OS
From staad Model Outside
Mu =
34.061 kNm
Main bar dia =
10
mm
d = thickness - Cover - dm/2 d= As =
175 mm 472.41
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 0 002 x b x Ts
As =
472.41
=
10 mm dia X
for 1 m length
10 mm dia X Mu =
mm2
mm2
As Provided = Inside
440 00 440.00
28.536 kNm
150 c/c 6.67
Pcs
Main bar dia =
523.60 10
mm2 mm
d = thickness - Cover - dm/2 d= As =
175 mm 394.52
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Ts 440.00
=
440.00
mm2
mm2
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
150 c/c 6.67
ID
Checked :
Pcs
523.60
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =1400 X W =1000 mm & Depth from GL =4500
Size:
Top Slab
Max @ Slab End @OS
Max @ Mid Slab @IS
From staad Model Inside
Mu =
46.33 kNm
Main bar dia =
12
mm
d = thickness - Cover - dm/2 d= As =
174 mm 651.14
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tt
As =
651.14
=
12 mm dia X
for 1 m length
12 mm dia X Mu =
mm2
mm2
As Provided =
Outside
440.00
13.67 kNm
150 c/c 6.67
Pcs
Main bar dia =
753.98 10
mm2 mm
d = thickness - Cover - dm/2 d= As =
175 mm 187.40
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tt 440.00
=
440.00
mm2
mm2
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
150 c/c 6.67
ID
Checked :
Pcs
523.60
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =1400 X W =1000 mm & Depth from GL =4500
Size:
Bottom Slab
Max @ Slab End@OS Max @ Mid Slab @IS
From staad Model Inside
Mu =
34.81 kNm
Main bar dia =
12
mm
d = thickness - Cover - dm/2 d= As =
214 mm 392.37
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tb
As =
520.00
=
12 mm dia X
for 1 m length
12 mm dia X Mu =
mm2
mm2
As Provided =
Outside
520.00
32.12 kNm
150 c/c 6.67
Pcs
Main bar dia =
753.98 10
mm2 mm
d = thickness - Cover - dm/2 d= As =
215 mm 359.95
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tb 520.00
=
520.00
mm2
mm2
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
150 c/c 6.67
ID
Checked :
Pcs
523.60
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Checking of Shear Top Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
146.68 kN
0.17∗√
^′
181.03
kN
> Vu
Bottom Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
146 kN
0.17∗√ 221.26
^′ kN
> Vu
Designed:
ID
Checked :
VR
Approved :
VR
L =1400 X W =1000 mm & Depth from GL =4500
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Side Wall
Maximum Shear (Vu) = Shear Capacity
(Vc) =
87.2 kN
0.17∗√
^′
181.03
kN
> Vu
Final Size and Reinforcement Box culvert Inside Dimensions = 1400 x 1000 mm Top Slab Thickness =
220 mm
Bottom Slab Thickness =
260 mm
Side Wall Thickness =
220 mm
Reinforcement Inside
Location
Outside
Top Slab
Dia (mm) 12
C/C 150
Dia (mm) 10
C/C 150
Bottom Slab
12
150
10
150
Side Wall
10
150
10
150
Designed:
ID
Checked :
VR
Approved :
VR
L =1400 X W =1000 mm & Depth from GL =4500
SULB AL‐JAZEERA CONCRETE MANUFACTURING Project: Client:
BOX CULVERT
Designed:
DJ
Checked :
VR
Approved :
VR
Location: SAUDI ARABIA
SAPAC
BOX CULVERT SIZE 1200 X 1000
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =1200 X W =1000 mm & Depth from GL =3500
Size:
Introduction:
Inside dimensions of the box culvert (SPAN x RISE) The fill height (H) above the culvert are as per the below table. A typical section of the culvert is shown in Figure. Material and design parameters are given in Table.
Material and Design Parameters Reinforced Concrete, c
24
kN/m3
Soil, s
18
kN/m3
Compressive Strength, f’c
35
Span L
1200
Mpa mm
Rise R
1000
mm
T Top Sl Slab b Thi Thickness, k Tt
200
mm
Bottom Slab Thickness, Tb
240
mm
3500
mm
200
mm
Haunch Thickness, Th
50
mm
Reinforcement Clear Cover
40
mm
Height of Fill H Wall Thickness, Ts
Yield Strength, fy
Modulus Elasticity of Concrete, Ec Modulus Elasticity of Steel Reinforcement, Es
420
Mpa
27789.4
Mpa
200000
Mpa
SULB AL-JAZEERA CONCRETE MANUFACTURING
Designed:
DJ
Checked :
VR
Approved :
VR
Element BOX CULVERT SAPAC L =1200 X W =1000 mm & Depth from GL =3500 Customer: Size: The approximate strip method is used for the design with the 1m wide design strip oriented parallel to the direction of traffic. A 2-Dimensional (2D) plane frame model is used to analyze the box culvert. Beam elements in the 2D model are assumed to be centered in the concrete members. The model is assumed to be externally supported by a pinned support on one end and a roller support on the other end. In addition, the model is always assumed to be in equilibrium so external reactions to loads applied to the structure were assumed to act equal and opposite opposite. A “w” dimension of 1 m is added to the calculations to convert the units to kN/m for consistency with national conventions.
A.
Dead Load The total self-weight of
the culvert top slab is: 22.56
kN (for 1 m wide)
The self-weight of one culvert side wall is: 5.86
kN (for 1 m wide)
Self weight of Haunch 0.03 kN (for 1 m wide)
The top slab weight, wall weights, and all four haunch weights are applied to the bottom slab as an upward reaction from the soil assuming an equivalent uniform pressure. The bottom slab weight is not applied in the model because its load is assumed to be directly resisted by the soil.
Dc bottom B.
=
31.05
kN (for 1 m wide)
Earth Pressure Loads The weight of fill on top of the culvert produces vertical earth pressure (EV). The fill height is measured from the top surface of the top slab to the top of the pavement or fill. The unit weight of the fill is 19.2 kN/m3 The interaction factor for embankment conditions is dependent on the height of fill (H) and the outside width of the culvert (Bc): 1.44
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =1200 X W =1000 mm & Depth from GL =3500
Size:
The design vertical earth pressure at the top of the culvert is: 90.56
kN/m
The lateral earth pressure (EH) on the culvert is found using the equivalent fluid method. For atrest conditions conditions, a maximum stage full soil unit weight and a minimum stage half soil unit weight will be are used. At the top of the culvert, the lateral earth pressure is: 63.00
kN/m
(Top)
31.50
kN/m
(Top)
At the bottom of the culvert, the lateral earth pressure is:
C.
=
88.92
kN/m
(Bottom)
=
44.46
kN/m
(Bottom)
Live Load Surcharge Use an active coefficient of lateral earth pressure ka
0.2827
The height for the live load surcharge calculation at the top of the culvert is the distance from the top surface of the top slab to the top of the pavement or fill. The height is: H
top of culvert
=
3500 mm
The equivalent fill height, heq is dependent on the depth of fill and can be found using AASHTO Table 3.11.6.4-1.
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
By interpolation, the equivalent height for a fill depth of =
heq
=
DJ
Checked :
VR
Approved :
VR
L =1200 X W =1000 mm & Depth from GL =3500
Size:
heq
Designed:
3500
mm is:
2.7 ft 0.82
m
The corresponding lateral live load surcharge on the top of the culvert is given as: 4.19
kN/m
The height for the live load surcharge calculation at the bottom of the culvert is the distance from the bottom surface of the bottom slab to the top of the pavement or fill. 4940 mm Again using interpolation and AASHTO Table 3.11.6.4.1, the equivalent height is: heq
=
heq
=
2.38 ft 0.73
m
The lateral live load surcharge located at the bottom of the culvert is given as: 3.69 D.
kN/m
Water Load Designers need to consider load cases where the culvert is full of water as well as cases where the culvert is empty. A simple hydrostatic distribution is used for the water load: At the inside of the culvert, the lateral water pressure is: WAtop =
0 kN/m2 9.81
kN/m2
Using a 2D frame model there is an opposite upward reaction from the soil caused by the water inside the culvert: Wabottom
reaction
=
WA bottom * Span
=
8.41
kN/m
(Span + Ts) E.
Live Load The d Th design i li live l loads d i include l d th the HL HL-93 93 t truck k and d t tandem d l loads. d Si Since th the span of f th the b box culvert l t i is less than 15 ft, no lane load is applied. Dynamic Load Allowance The dynamic load allowance (IM) for culverts and other buried structures is reduced based on the depth of fill over the culvert. For strength and service limit states: -14.355
=
The dynamic load allowance may not be taken less than zero.
0
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =1200 X W =1000 mm & Depth from GL =3500
Live Load Distribution Live loads are assumed to distribute laterally with depth. The specifications permit designers to increase the footprint of the load with increasing depth of fill. The load is assumed to spread laterally 1.15 times H horizontally in each direction for every foot of fill above the culvert. The intensity of live loads at any depth is assumed to be uniform over the entire footprint.
The assumed tire contact area for each wheel has a width of 20 inches and a length of 10 inches.
Using the distances between wheel lines and axles, the live load intensities at the top of the box culvert can be found. For truck and tandem loadings, the influence area or footprint of the live load is found first. Then the sum of the weights of the wheels is used to determine the intensity of the live load. To determine the live load, use multiple presence factors (MPF). A single loaded lane with a MPF of 1.20 is used for strength and service limit states. A single 3 Axle
where
with 600 kN Truck
Pw =
130 kN
Axlespacing =
1.8 m
Wtire =
0.51 m
W =
Ltire = L=
6.34
m
0.25 m 6.08
m
8.11
kN/m
Therefore WLL+IM
=
configuration produces a live load intensity of:
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
DJ
Checked :
VR
Approved :
VR
L =1200 X W =1000 mm & Depth from GL =3500
Size:
A tandem truck axle configuration produces a live load intensity of:
where
Pw =
105 kN 5.58
m
where Axlespacing =
1.3 m
=
WLL+IM
14.27
kN/m
The live load intensities of the single and tandem axle configurations are compared. Since the tandem axle configuration produces a live load intensity slightly larger than that of the single axle configuration, the tandem axle configuration is used for design in both the strength and service limit states. 14 27 kN 14.27 therefore WLL+IM = Final Loading DC DC
=
Sel weight of Culvert
=
31.05
EV =
90.56
kN/m
EHTmax =
63.00
kN/m
EHBmax =
88.92
kN/m
EHTmin =
31.50
kN/m
EHBmin =
bottom reaction
44.46
kN/m
=
4.19
kN/m
LLSbottom =
3.69
LLStop
WAtop=
F.
kN/m
kN/m 0 kN/m
WAbottom=
9.81
kN/m
WAbottomreaction=
8.41
kN/m
LL+IMW =
14 27 14.27
kN/ kN/m
Load Combination Strength Limit states 1 Maximum Vertical Load and Maximum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+ (1.35)(1.05)EHmax + 1.75LS 2 Maximum Vertical Lod and Minimum Horizontal Load 1.25 DC + (1.30)(1.05) EV +1.75 (LL+IM)+1.00WA+(0.9/1.05)EHmin
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Designed:
DJ
Checked :
VR
Approved :
VR
L =1200 X W =1000 mm & Depth from GL =3500
3 Minimum Vertical load and Maximum Horizontal Load 0.90 DC + (0.9/1.05)EV + (1.35)(1.05) EHmax +1.75LS Service Limit State 1 Maximum Vertical Load and Maximum Horizontal Load (LL+IM)+1.00EH 1.00 .00 DC C + 1.00 .00 EV + 1.00 .00 ( ) .00 max + 1.00LS .00 S 2 Maximum Vertical Lod and Minimum Horizontal Load 1.00 DC + 1.00 EV + 1.00 (LL+IM)+1.00WA+1.00EHmin 3 Minimum Vertical load and Maximum Horizontal Load 1.00 DC + 1.00EV + 1.00EHmax +1.00LS
A structural analysis is performed using a standard commercial matrix-analysis program. The bottom slab of the box culvert is assumed rigid compared to the subgrade. Reactions to vertical loads applied li d to the h culvert l ( (earth, h water, li live l load) d) are assumed d to b be carried i d b by uniform, if triangular i l or trapezoidal distributed reactions applied to the bottom slab. Box culverts supported on stiff or rigid subgrades (rock) would require further investigation. The haunches are included in the analysis by increasing the thickness of members near each corner. Reinforcement Design
where, where F =
1
fy =
420 Mpa
fc' =
35 MPa
b =
1 m
therefore, a =
As x 420 0.85 x 35 x1000
a=
420∗
0.0141
As
Mu =
1 x As x 420 x (d - .0141 * As/2)
Mu =
420 x As*d - 2.961 As^2
√ 176400 ^2 11.844
/5.922
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =1200 X W =1000 mm & Depth from GL =3500
Size:
Side Wall
Max @ Mid Slab@IS
Max @ Slab End@OS
From staad Model Outside
Mu =
18 kNm
Main bar dia =
10
mm
d = thickness - Cover - dm/2 d= As =
155 mm 280.07
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 0 002 x b x Ts
As =
400.00
=
10 mm dia X
for 1 m length
10 mm dia X Mu =
mm2
mm2
As Provided = Inside
400 00 400.00
14.75 kNm
150 c/c 6.67
Pcs
Main bar dia =
523.60 10
mm2 mm
d = thickness - Cover - dm/2 d= As =
155 mm 228.96
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Ts 400.00
=
400.00
mm2
mm2
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
523.60
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =1200 X W =1000 mm & Depth from GL =3500
Size:
Top Slab
Max @ Mid Slab @IS
Max @ Slab End @OS From staad Model Inside
Mu =
26.62 kNm
Main bar dia =
10
mm
d = thickness - Cover - dm/2 d= As =
155 mm 416.81
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tt
As =
416.81
=
10 mm dia X
for 1 m length
10 mm dia X Mu =
mm2
mm2
As Provided =
Outside
400.00
6.57 kNm
150 c/c 6.67
Pcs
Main bar dia =
523.60 10
mm2 mm
d = thickness - Cover - dm/2 d= As =
155 mm 101.39
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tt 400.00
=
400.00
mm2
mm2
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
523.60
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Designed:
VR
Approved :
VR
L =1200 X W =1000 mm & Depth from GL =3500
Size:
Bottom Slab
Max @ Slab End@OS Max @ Mid Slab @IS
From staad Model Inside
Mu =
17.95 kNm
Main bar dia =
10
mm
d = thickness - Cover - dm/2 d= As =
195 mm 220.93
mm2
Minimum sidewall flexural reinforcement Asmin therefore
= 0.002 x b x Tb
As =
480.00
=
10 mm dia X
for 1 m length
10 mm dia X Mu =
mm2
mm2
As Provided =
Outside
480.00
14.77 kNm
150 c/c 6.67
Pcs
Main bar dia =
523.60 10
mm2 mm
d = thickness - Cover - dm/2 d= As =
195 mm 181.53
mm2
Minimum sidewall flexural reinforcement Asmin therefore
As =
= 0.002 x b x Tb 480.00
=
480.00
mm2
mm2
As Provided =
10 mm dia X
for 1 m length
10 mm dia X
150 c/c 6.67
DJ
Checked :
Pcs
523.60
mm2
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Checking of Shear Top Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
97.78 kN
0.17∗√ 160.92
^′ kN
> Vu
Bottom Slab
Maximum Shear (Vu) = Shear Capacity
(Vc) =
89.16 kN
0.17∗√ 201.15
^′ kN
> Vu
Designed:
DJ
Checked :
VR
Approved :
VR
L =1200 X W =1000 mm & Depth from GL =3500
SULB AL-JAZEERA CONCRETE MANUFACTURING Element BOX CULVERT Customer:
SAPAC
Size:
Side Wall
Maximum Shear (Vu) = Shear Capacity
(Vc) =
63.79 kN
0.17∗√
^′
160.92
kN
> Vu
Final Size and Reinforcement Box culvert Inside Dimensions = 1200 x 1000 mm Top Slab Thickness =
200 mm
Bottom Slab Thickness =
240 mm
Side Wall Thickness =
200 mm
Reinforcement Inside
Location
Outside
Top Slab
Dia (mm) 10
C/C 150
Dia (mm) 10
C/C 150
Bottom Slab
10
150
10
150
Side Wall
10
150
10
150
Designed:
DJ
Checked :
VR
Approved :
VR
L =1200 X W =1000 mm & Depth from GL =3500
View more...
Comments