Design and Planning of Instrumentation Works

May 5, 2018 | Author: Min Min Soe | Category: Deep Foundation, Instrumentation, Tunnel, Safety, Geotechnical Engineering
Share Embed Donate


Short Description

Design and Planning of Instrumentation Works...

Description

Design and Planning of Instrumentation Works

AECOM Singapore LIM Chi-Sharn Associate / Principal Engineer (Geotechnical) [email protected]

09 May 2013

Outline •

Introduction and Objectives



Design of Instrumentation Instrumentation and Monitoring Systems Systems



 –

Bored tunnelling

 –

Mined tunnelling

 –

Deep excavation

Planning of Instrumentation and Monitoring Systems Systems  –

Risk Management

 –

Information Management

 –

 –



Contingency Planning Ensuring Reliability (System Assurance)

Challenges 09 May 2013

Page 2

1

Tunnelling and Excavation causes

Ground Movements & Other Changes which are kept Within Acceptable Limits in order to Ensure Safety & Protectt Adjacent Structures Protec 09 May 2013

Page 3

What is Instrumentation & Monitoring?

Instrumentation is

Monitoring is

a Surveillance System

at Site 09 May 2013

4

2

Tunnelling and Excavation causes

Ground Movements & Other Changes which are kept Within Acceptable Limits in order to Ensure Safety & Protectt Adjacent Structures Protec 09 May 2013

Page 3

What is Instrumentation & Monitoring?

Instrumentation is

Monitoring is

a Surveillance System

at Site 09 May 2013

4

2

Objectives To Verify Design Assumptions Assumptio ns by Comparing Monitored responses against Predicted Values

To Ensure Safety by Limiting Magnitudes & Restricting Trends of Responses

To Minimize Damage of surrounding Structures & Buried Cables, Pipes etc.

09 May 2013

Page 5

Construction Works Works as an Engineered System QUALITY ability to satisfy requirements

Serviceability use for purpose and for conditions

Safety acceptability of risks

Compatibility acceptability of impacts

Durability freedom from unanticipated degradation

(Bea, 1994, 2002) •

Equipment – reliable



Processes – clearly defined



People – clear roles and responsibilities 09 May 2013

Page 6

3

Benefits of Instrumentation & Monitoring (from Dunnicliff, 1993) •

Defines initial site conditions conditio ns such as groundwater, groundwater, background conditions (temperature, (temperature, noise, vibration, tides)



Proof testing (test piles)



Safety and Risk Management



Observational approach to design and design verification that is based on data



Construction control



Legal protection



Enhances public relations 09 May 2013

Page 7

What are Monitored? •



Ground Movement  –

Settlement (& at Depths), Heave (& at Base)

 –

Lateral Displacement Displacement (& along Depths)

Ground Water  –



Structural Forces  –





Water Table / Pore Water Pressure

Strut/Ground-Anchor Supports, Tunnel Lining

Structural Deformations  –

Tilt & Crack Widths of Buildings/Structures

 –

Utilities; Cables & Pipes

 –

Profile & Shape of Tunnels

Vibration and Noise 09 May 2013

Page 8

4

TYPICAL INSTRUMENTATION 09 May 2013

Page 9

Ground Settlement Markers

09 May 2013

Page 10

5

Settlement Plates

09 May 2013

Page 11

Settlement at Depth (Magnetic Extensometer)

09 May 2013

Page 12

6

Settlement at Depth (Hydraulic Hook )

09 May 2013

Page 13

Settlement at Depth (Hook Sensor)

09 May 2013

Page 14

7

Deep Leveling Datum

09 May 2013

Page 15

Water Stand Pipe

09 May 2013

Page 16

8

Water Stand Pipe & Piezometer

09 May 2013

Page 17

09 May 2013

Page 18

9

 Vibrating Wire Piezometer

09 May 2013

Page 19

Piezometer

09 May 2013

Page 20

10

Push-in Type Piezometer

09 May 2013

Page 21

Building Settlement Markers

For Asphalt Surface

For Concrete Surface 09 May 2013

Page 22

11

Building Settlement Markers

09 May 2013

Page 23

Tilt Meter

09 May 2013

Page 24

12

EL Beam Sensor

09 May 2013

Page 25

EL Beam Sensor  As In-Place Inclinometer & for Settlement Profile

09 May 2013

Page 26

13

Convergence Monitoring

09 May 2013

Page 27

Convergence Monitoring

09 May 2013

Page 28

14

Tape Extensometer

09 May 2013

Page 29

Crack Meter

09 May 2013

Page 30

15

09 May 2013

Page 31

09 May 2013

Page 32

16

09 May 2013

Page 33

Strut Load Measurement

09 May 2013

Page 34

17

09 May 2013

Page 35

09 May 2013

Page 36

18

09 May 2013

Page 37

Brillouin optical time domain reflectometry (BOTDR)

Diagram courtesy of ntt.co.jp/news

09 May 2013

Page 38

Distributed strain sensor – BOTDR   Average strain over 1m every 20cm Range ~5-10km Resolution 30με (0.003%) Low cost sensors - optical fibre 5 - 25 minutes per measurement Can link or switch between fibres

19

DESIGN 09 May 2013

Page 39

Design Aspects



Purpose of instrument  –



Location of instrument  –



What are the safe limits?

Frequency and duration  –



Where is it to be installed?

Review levels  –



What is to be monitored?

When and how often is it to be monitored?

Contingencies  –

What should be done when the limits are exceeded, and who should do it?

09 May 2013

Page 40

20

Design Verification – Tunnelling







Verification of parameters  –

Water table

 –

Volume loss

 –

Ground relaxation

Comparing predictions with outcomes  –

Ground movements

 –

Groundwater changes

 –

Convergence / radial displacement

Monitoring at areas of risk  –

To manage residual design risk, construction risk

09 May 2013

Page 41

Trough Measurements Help to Identify Types of Ground Movement

09 May 2013

42

21

Settlements at Surface Vs at Depth

09 May 2013

43

Monitoring Arrays (Tunnelling)

09 May 2013

Page 44

22

Monitoring Arrays (Tunnelling)

09 May 2013

Page 45

Monitoring Arrays (Tunnelling)

09 May 2013

Page 46

23

Monitoring Arrays (Tunnelling)

09 May 2013

Page 47

Monitoring Arrays (Tunnelling)

09 May 2013

Page 48

24

Interpreted Monitoring Data

09 May 2013

Page 49

Convergence Monitoring (Bored Tunnel)





For Both Tunnels,  –

Min 1 for each drive

 –

Min. 1 at each soil type encountered

For 1st tunnel,  –

Min one at every 100m if clear space < 

 –

Min one at every 25m if clear space < 3m

09 May 2013

Page 50

25

Convergence Monitoring (Cross Passages using SCL)



Every 2m from breakout



7m from breakout



Every 20m thereafter

  m   m   m   m    0    2    4   6

  m    7

09 May 2013

  m    0    2

Page 51

Monitoring Ground Water Level





Currently Not Monitored at Close Interval To Determine Correct Face Pressure with Reference to Ground Water Pressure for Both Slurry and EPBM



To limit Ground settlement



To avoid Ground heave, slurry spouts and foam spews



To validate the design of tunnel segment

09 May 2013

52

26

Examples

09 May 2013

Page 53

09 May 2013

Page 54

Examples

27

Examples

09 May 2013

Page 55

09 May 2013

Page 56

Examples

28

Role in Risk Management  – Managing residual design risk and construction risk •

Tunnelling

Before tunnelling under buildings (esp. with mixed ground)

Start of tunnelling

09 May 2013

Page 57

Cavities are Not Always Fully Grouted

Leca, E. & Domieux, L. (1990)

09 May 2013

58

29

Subsurface Monitoring  – Rod extensometers @ Close Intervals?

Drawback  – Risk of Slurry Path

09 May 2013

59

Monitoring for unplanned stoppages

09 May 2013

Page 60

30

09 May 2013

Page 61

Design Verification – Excavation







Verification of parameters  –

Water table

 –

Soil properties

Comparing predictions with outcomes  –

Ground movements

 –

Groundwater changes

 –

Retaining wall deflections

 –

Strut forces

Monitoring at areas of design risk  –

To manage residual design risk

09 May 2013

Page 62

31

Monitoring Arrays - Excavations

09 May 2013

Page 63

Monitoring Arrays - Excavations

09 May 2013

Page 64

32

Examples

09 May 2013

Page 65

09 May 2013

Page 66

Examples

33

Examples

09 May 2013

Page 67

09 May 2013

Page 68

Examples

34

Examples

09 May 2013

Page 69

Interpreted Monitoring Data •

Possible causes  –

Observed soil profile different from design  no F2 at the East Wall

 –

Marine clay Cu and Eu lower than adopted at design

 – 

Back-Analysis of Unpredicted Sway of a Cut-And-Cover Deep Excavation in Singapore Marine Clay (Lim et. al. 2011. Proc of ICAGE) 09 May 2013

Page 70

35

Role in Risk Management  – Managing residual design risk and construction risk •

Excavations 3D (??)

2D (ok)

The Impact of Geometry on Re-Entrant Corner Behaviour in Deep Excavation Retaining Walls: Two Case Studies from Stage 4 of the Circle Line. (Lim C.S. and Jee Y.Y., 2008, Proc. Of ICDE) 09 May 2013

Page 71

Ensuring Safety and Minimizing Impact  – Adjacent Structures





Comparing predictions with outcomes / safety limits  –

Ground movements

 –

Groundwater changes

 –

Building movements and strains

Comparing outcomes with legal limits / guidelines  –

Noise

 –

Vibration

09 May 2013

Page 72

36

Structure Monitoring

09 May 2013

Page 73

09 May 2013

Page 74

37

Structure Monitoring

09 May 2013

Page 75

Structure Monitoring

09 May 2013

Page 76

38

Effects of tunnelling on pile foundations (slide from Mair, 2009)

W

Base Load

W=F+B F

B

Volume Loss B

Shaft Friction F Volume Loss 09 May 2013

Tunnel volume loss causes base load B to reduce, pile settles and shaft friction F increases Page 77

Bored tunnelling below full scale pile trials in the Second Heinenoordtunnel site (Kaalberg et al, 2005) (slide from Mair,

2009)

distance from tunnel (m) -30

-20

-10

0

10

0



4

-10

      )     m     m       ( -20     s      t     n     e     m -30       l      t      t     e     s

      )     m       (       l     e     v     e       l -6       f .     e     r     w     o -11       l     e       b       h      t -16     p     e       d

-1

pile settlement surface settlement piles

-40

 

tunnel

-50

-21 -30

-20

-10

0





10

Field trials : wooden and concrete piles above two 8.3m OD tunnels End-bearing piles , shaft friction very low  Volume losses  – 

Zone B Zone A Zone C

30o

 – 

45o •

• • •

Piles in Zone A settle > ground surface Piles in Zone B settle ~ ground surface 09 May 2013 Page 78 Piles in Zone C settle < ground surface

1st tunnel : 1~2% 2nd tunnel : 0.75%

0.5D was considered to be safe distance between pile toe and tunnel

39

Structure Monitoring (Real Time)

09 May 2013

Page 79

Structure Monitoring (Real Time)

09 May 2013

Page 80

40

Design Role of the Qualified Person for Geotechnical Aspects of GBWs

(Building Control Regulations) 09 May 2013

Page 81

PLANNING (For the construction phase)

09 May 2013

Page 82

41

Supervision Role of the Qualified Person for Geotechnical Aspects of GBWs (8th Schedule, Part II, Building Control Regulations) •

Tunnels

09 May 2013

Page 83

Supervision Role of the Qualified Person for Geotechnical Aspects of GBWs (8th Schedule, Part II, Building Control Regulations) •

Deep excavations

09 May 2013

Page 84

42

Construction Works as an Engineered System QUALITY ability to satisfy requirements

Serviceability use for purpose and for conditions

Safety acceptability of risks

Compatibility acceptability of impacts

Durability freedom from unanticipated degradation

(Bea, 1994, 2002) •

Equipment – reliable



Processes – clearly defined



People – clear roles and responsibilities 09 May 2013

Page 85

Monitoring Works as an Engineered System QUALITY ability to satisfy requirements

Serviceability use for purpose and for conditions

Safety acceptability of risks

Compatibility acceptability of impacts

Durability freedom from unanticipated degradation

(Bea, 1994, 2002) •

Equipment – reliable



Processes – clearly defined



People – clear roles and responsibilities 09 May 2013

Page 86

43

Role in Risk Management

Safety & Design RISKS are Managed by

Setting Limits on Each Response &

Comparing Monitored Responses Against these Set Limits 09 May 2013

Page 87

Interpreting monitoring data  – key information required

3 Activity against trend

2 Trend graphically

FORM IS FUNCTION

visible

1 X-axis annotated with dates

4 Key plan with instrumentation locations

5 Table readings against Review Levels 09 May 2013

Land Transportation Excellence Awards 2011

Best Innovation Partner Page 97

44

Instrumentation & Monitoring Quality Plan (1 of 2)



Sufficient & Correct Instrumentation



Proper Installation & Establishment of Initial Readings



Monitoring Schedule Updated Regularly & Strictly Adhered To



Readings Taken by Competent Technicians



Proper Data Deduction & Verification



Daily Results into Summary Format

09 May 2013

98

Instrumentation & Monitoring Quality Plan (2 of 2) •

Daily Trend Watch



 Daily Check on Results Vs Review Levels



 Weekly Reports with Tables, Trend Plots



 Regular Meetings among Key Personnel



 Full Participation of QP(S) & PE



 Increased Monitoring at High Risk Area



 Increased Monitoring at High Activity Area



 Prompt Replacement of Damaged Instruments



Calibration of Tools as per Schedule



Manual checks of automated real-time monitoring 09 May 2013

99

45

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF