Deep Excavation and Tunnelling Past Experience and Future Challanges
January 6, 2017 | Author: Chin Thau Wui | Category: N/A
Short Description
Download Deep Excavation and Tunnelling Past Experience and Future Challanges...
Description
09/08/2012
Deep Excavation and Tunnelling Past Experience and Future Challenges
• Review of Major Underground Infrastructure Construction and Singapore Geology • Managing Ground Risk • Managing Risk of Ground Movement • Durability of Bored Tunnels • Conclusions
Deep Excavation and Tunnelling Past Experience and Future Challenges D Wen, BSc, PhD PE, PE(Geo), AC(Geo), CEng, MICE, MIEAust, CPEng
GeoSS 7 Aug 2012
温大志
1
2
GeoSS 7 Aug 2012
Major Underground Road Tunnels
MRT Network in Singapore North
Woodsville Interchange: Total tunnel length: 0.69km; Opened 28 Jan 2012
North-East
North South Expressway Tunnel and Semi Tunnel : 12.3 km to be completed around 2020
NSL East
EWL
Singapore Underground Road System: underground road tunnels
GeoSS 7 Aug 2012
KPE: Total tunnel length: 9km; Opened 26 Oct 2007 and 20 Sep 2008
CTE: North Tunnel: 0.7 km; South Tunnel: 1.7 km; Opened: 21 Sep 1991
3
Fort Canning Tunnel: 0.35 km; Opened 16 Jan 2007 MCE Tunnel : 3.5km to be opened at end 2013
4
GeoSS 7 Aug 2012
Deep Tunnel Sewerage System
Cable Tunnels
• Cable Tunnels – Tuas and Seraya • Gombas/Woodlands to Senoko • Pasir Panjang Road • Current 6 cable tunnel projects under tender
GeoSS 7 Aug 2012
5
GeoSS 7 Aug 2012
6
1
09/08/2012
Geological Process
Caverns • Rock Caverns in Jurong Formation • Rock Caverns in Bukit Timah Granite Formation
M OA
FCBB
GV
F/E
S4 GIV
GI/GII/GIII Jurong Formation (Sedimentary Rock)
Bukit Timah Granite (Igneous Rock)
In-filled Valleys Deep weathering of granite
7
GeoSS 7 Aug 2012
Mandai
Deep Excavation and Tunnelling
Punggol
Past Experience and Future Challenges
Serangoon Dhoby Ghaut
Boon Lay Scale : -2
0 1 2
Newton 4 (Km)
Outram Park
Kallang Formation
Geological Map
Old Alluvium Jurong Formation
Bukit Timah Granite Gombak Norite
• Review of Major Underground Infrastructure Construction and Singapore Geology • Managing Ground Risk • Managing Risk of Ground Movement • Durability of Bored Tunnels • Conclusions
Reclamation 9
GeoSS 7 Aug 2012
10
GeoSS 7 Aug 2012
SITE INVESTIGATION PHASES
Site Investigation
• Continuous process for entire duration of project • Phased approach
• To provide sufficient ground and ground water data for a proper description of essential ground properties / behaviour to plan the most appropriate construction method; and for a reliable assessment of characteristic values of ground parameters to achieve a safe and cost-effective design
GeoSS 7 Aug 2012
8
GeoSS 7 Aug 2012
Desk study Preliminary Detailed SI during construction 11
GeoSS 7 Aug 2012
12
12
2
09/08/2012
COST OF SITE INVESTIGATION
DESK STUDY
Cost of Risk and SI Efforts
• Geological archives/maps • Previous site investigations at the area • Historical land use survey • Published case histories
Optimum Effort Combined Cost
Cost of SI
Cost of Risk Increased Effects of Site Investigation
GeoSS 7 Aug 2012
13
13
COST OF SITE INVESTIGATION
14
GeoSS 7 Aug 2012
COST OF SITE INVESTIGATION
• USNCTT (1984): 3% of predicted construction cost • USNCTT: 1.5m borehole for every I m of tunnel • Hong Kong – major projects – around 1%
Source: Westland, J.R. et al (1998) Managing subsurface risk for Toronto’s rapid transit expansion program. Proc. North American Tunnelling. I. Ozdemir ed. Balkema. GeoSS 7 Aug 2012
15
COST OF SITE INVESTIGATION
Source: United States National Committee on Tunnelling Technology. (1984) Geotechnical site investigations for underground projects. National Academy Press. 16
GeoSS 7 Aug 2012
Site Investigation Report Site Investigation: field and laboratory works
• NEL: Average borehole spacing 36.5m Geotechnical Factual Report (GFR)
• NEL SI Cost to Civil Cost: 0.216%
Geotechnical Interpretative Report (GIR)
• DTL3: Average spacing 17.5m • DTL3 SI Cost to Civil Cost: 0.283%
Interpreted ground conditions for design, e.g. design sections, design parameters
From DTL
Geotechnical Interpretative Baseline Report (GIBR) GeoSS 7 Aug 2012
Contains the factual data from site investigation & laboratory tests
17
GeoSS 7 Aug 2012
Nature, form, composition, properties and structure of the ground and groundwater, artificial obstructions 18
3
09/08/2012
GIBR
Challenges
• To explicitly share the commercial risk with contractors Set “Baseline” for commercial purpose Set minimum requirements for design
Tunnel Alignment 19
GeoSS 7 Aug 2012
20
GeoSS 7 Aug 2012
Geophysical Survey
Challenges
• Commonly used methods
• To have more boreholes – practical
problems
• To carry out geophysical survey
Electrical resistivity Seismic refraction Seismic reflection Surface wave method Geo-tomography
22 21
GeoSS 7 Aug 2012
22
GeoSS 7 Aug 2012
Soil / Rock Interface – Accuracy ?
Geophysical Survey • Methods commonly used for soil / rock interface identification • Results are
Interpreted Profile of Surface Wave Velocity
indirect interpretation of ground condition influenced by many factors, e.g. utilities, traffic noise Interpreted Rock Profile GeoSS 7 Aug 2012
23
GeoSS 7 Aug 2012
24
4
09/08/2012
Detection of Pile Depth – Accuracy?
Soil / Rock Interface – Accuracy ?
ABH2 6 FILL F1
ABH2 1 FILL F1
GV & GVI GV & GVI
GII & GI
ABH1 8 FILL
F2 E F1 F2 F1 GVI & GV GIII, GII & G1
GIII & GII
Estimated Pile Penetration: 21~22m (or) 26~27 m GeoSS 7 Aug 2012
25
26
GeoSS 7 Aug 2012
Detection of Pile Depth – Accuracy?
Challenges • More efficient and accurate methods are required to determine
rock levels
depth of piles
to minimise risk of underground construction in urban areas
GeoSS 7 Aug 2012
27
Deep Excavation and Tunnelling
28
Managing Risk of Ground Movement
Past Experience and Future Challenges
• Review of Major Underground Infrastructure Construction and Singapore Geology • Managing Ground Risk • Managing Risk of Ground Movement • Durability of Bored Tunnels • Conclusions GeoSS 7 Aug 2012
GeoSS 7 Aug 2012
• Ground Stability Ultimate limit state to prevent collapse
• Ground Movement Serviceability limit state to prevent damage to adjacent properties / underground utilities
29
GeoSS 7 Aug 2012
30
5
09/08/2012
Managing Risk of Ground Movement
Managing Risk of Ground Movement
Deep Excavation
Deep Excavation
Cut Slope at Tanjong Pagar Station: Original Design vs Revised Design
Cut Slope at Orchard Station: Original Design vs Revised Design After Hulme, Potter & Shirlaw (1986)
GeoSS 7 Aug 2012
After Hulme, Potter & Shirlaw (1986)
31
32
GeoSS 7 Aug 2012
Managing Risk of Ground Movement
Managing Risk of Ground Movement
Deep Excavation
Deep Excavation
Singapore Art Museum Cathedral of the Good Shepherd
Reflection Pool Bras Basah Rd
B1 Level
Connection SMU
B2 Level B3 Level B4 Level B5 Level
33
GeoSS 7 Aug 2012
34
GeoSS 7 Aug 2012
Managing Risk of Ground Movement
Managing Risk of Ground Movement
Deep Excavation
Challenges in Urban Environment
Deep Excavations in Soft Clay without Ground Treatment
After Goh (2008)
Ground Treatment Deep Excavations in Soft Clay with Ground Treatment
GeoSS 7 Aug 2012
35
GeoSS 7 Aug 2012
36
6
09/08/2012
Jet Grouting System
Effectiveness of Jet Grout in Marine Clay 160 Jet Grouted slab, 800mm wall
Air Grout Air
Air Water Air Grout
Single tube jet grouting system
Wall deflection, mm
140 Grout
120 100 TREND LINE, 1m to 1.2m DIAPHRAGM WALLS, NO JET GROUT
80 60 40 20
Double tube jet grouting system
Triple tube jet grouting system
0 0
10
20
30
40
Depth from ground surface to hard strata, m After Shirlaw, Tan & Waong (2005)
37
GeoSS 7 Aug 2012
38
GeoSS 7 Aug 2012
Hybrid ground treatment
Deep Soil Mixing (DSM) / Deep Cement Mixing (DCM)
Deep soil mixing + Jet grouting (Eg RASJET)
2.8m diameter columns achieved below formation level for C828 Nicoll Highway Station (φ1.6m internal column by mixing blades) 39
GeoSS 7 Aug 2012
40
GeoSS 7 Aug 2012
Use of Cross Walls
Use of Cross Walls
114E/W
Masjid Wak Tanjong
115E
EWL VIADUCT
EXISTING PIERS TO BE UNDERPINNED
EXISTING PILECAP
FILL
STRUT S2a
Cross Walls
Marine Clay
115E/W SOIL IMPROVEMENT WORKS by Cross Walls (lean concrete wall)
BOTTOM OF MARINE CLAY
OA
DIAPHRAGM WALL
116E/W
Circle Line Paya Lebar Station – Use of Cross Walls GeoSS 7 Aug 2012
41
EXISTING BORED PILES
Circle Line Paya Lebar Station – Use of Cross Walls GeoSS 7 Aug 2012
42
7
09/08/2012
Use of Cross Walls
Future Challenges
DTL1 C906 -65 100
-55
-45
-35
-25
-15
-5
5
Existing Tunnels
100
Sand Fill
90
90
87.0 (16m Excavation)
80
80
CROSS WALL 70
70
60
60
OA
50
Monitoring at DTL1 C906
-5
Transfer Beams and Barrettes for Underpinning Top tunnel in Marine Clay Future Tunnels Bottom tunnel in OA
Existing Piles / Barrettes
50
40
30
Depth (m)
Depth (m)
Kallang
5
GeoSS 7 Aug 2012
40
IW 894
Design prediction @ IW894
IW 900
Design prediction @ IW 900
15
25
35
45
55
Displacement (mm)
65
30
43
44
GeoSS 7 Aug 2012
Managing Risk of Ground Movement
Future Challenges
Bored Tunnels 3
• To match the design of soil improvement methods to be selected based on the groutability of the ground encountered the targeted engineering property of soil to be improved • To have minimum disturbance to surrounding structures • To develop new method and technology, e.g. horizontal grouting techniques 45
GeoSS 7 Aug 2012
5 4
1
1. 2. 3. 4. 5.
2 Loss into tunnel face Loss between the face and leading edge of shield Tail void Lining deformation Consolidation 46
GeoSS 7 Aug 2012
Managing Risk of Ground Movement
Managing Risk of Ground Movement
Bored Tunnels
Bored Tunnels
• Phase 1/2 MRT Construction in 1980s: Greathead Shield with hydraulic backhoe excavator or roadheaders / 1 EPBM / 1 TBM • Compressed air used extensively • Grouting done through the segments
• NEL: 14 EPBMs (2 Dual Modes), 2 Open Face TBMs • Automatic tail void grouting • Face pressure and stability by controlling the extrusion of the spoil through the screw conveyor and the advancement of the machine
Greathead Shield GeoSS 7 Aug 2012
EPBM (C301) 47
EPBM (C705) GeoSS 7 Aug 2012
EPBM (C706)
EPBM (C710)
48
8
09/08/2012
Automatic Tail Void Grout
Over Cutting
Marine clay
Extrados of segment Tail void grout
49
GeoSS 7 Aug 2012
50
GeoSS 7 Aug 2012
Managing Risk of Ground Movement
Managing Risk of Ground Movement
EPBM
EPBM 1. Stability Number N = (σv + q – σt) / cu 2. Stability Number, Nc at collapse
Increase / Lowering of Shield Advance Rate Increase / Lowering of
Surcharge q
Screw Discharge Rate
C Z
σT
D
Water
P
Earth
Pressure 51
GeoSS 7 Aug 2012
52
GeoSS 7 Aug 2012
Managing Risk of Ground Movement
Managing Risk of Ground Movement
EPBM
EPBM cu
50
kPa
density
18
kN/m^3
surcharge
10
kPa
depth
20
m
Nc overburden
Typical Volume Loss for a tunnel of D = 6m by EPB
9 370
Face Pressure (% of overburden) Face Pressure
kN/m^2
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
37
74
111
148
185
222
259
296
333
370
N
6.66
5.92
5.18
4.44
3.70
2.96
2.22
1.48
0.74
0.00
1/F
0.74
0.66
0.58
0.49
0.41
0.33
0.25
0.16
0.08
0.00
Volume Loss (%)
6.0
4.0
3.0
2.0
1.3
1.0
0.5
0.2
0.1
0
CIRIA Report 30, March 1996 GeoSS 7 Aug 2012
53
GeoSS 7 Aug 2012
54
9
09/08/2012
Managing Risk of Ground Movement
Managing Risk of Ground Movement
EPBM
EPBM
Plastic Nature of Spoils to Maintain Face Pressure No Plug, Material Saturated and Flowing 55
GeoSS 7 Aug 2012
56
GeoSS 7 Aug 2012
Managing Risk of Ground Movement
Managing Risk of Ground Movement
EPBM
Bored Tunnels • Circle Line: 19 EPBM, 8 Slurry TBMs • Scanners / belt weighing experimented and adopted subsequently • Slurry TBM used for sections with granite
Over-excavation in Mixed Tunnel Face by EPBM Slurry TBM (C854) 57
GeoSS 7 Aug 2012
Slurry Treatment Plant
EPBM (C823) 58
GeoSS 7 Aug 2012
Managing Risk of Ground Movement
Managing Risk of Ground Movement
Slurry TBM
Bored Tunnels • DTL1: 3 EPBMs • DTL2: 10 EPBMs + 9 Slurry TBMs • DTL3: 19 TBMs
Face pressure is maintained by controlling the volume difference of the bentonite suspension supplied to the chamber and the suspension combined with excavated material removed from it GeoSS 7 Aug 2012
EPBM (C902) 59
GeoSS 7 Aug 2012
Slurry TBM (C915)
EPBM (C917) 60
10
09/08/2012
Deep Excavation and Tunnelling
Durability
Past Experience and Future Challenges
• Review of Major Underground Infrastructure Construction and Singapore Geology • Managing Ground Risk • Managing Risk of Ground Movement • Durability of Bored Tunnels • Conclusions
• The durability objective is to achieve a service life, with appropriate maintenance, of 120 years • Design measures need to be taken to achieve the objective.
61
GeoSS 7 Aug 2012
GeoSS 7 Aug 2012
Durability Measures
62
Typical Durability Problems
• Concrete with low permeability and low chloride diffusion
• Protective coating to extrados of segment • Detailing – adequate cover to re-bars, including drilling positions / bolt pockets.
• Electrically continuous steel cages as provision for future cathodic protection, if required. GeoSS 7 Aug 2012
63
GeoSS 7 Aug 2012
Typical Durability Problems
64
Technology Development
• Simple bitumastic sealing strip • Composite neoprene and bitumastic • •
GeoSS 7 Aug 2012
65
strips Neoprene gaskets “Hydrotite” gaskets
GeoSS 7 Aug 2012
66
11
09/08/2012
Neoprene Gaskets / Bitumastic Strips
Waterproofing Bored Tunnels NEL
Contract specification required the use of both EPDM gaskets and hydrophilic sealing strips
67
GeoSS 7 Aug 2012
68
GeoSS 7 Aug 2012
Waterproofing Bored Tunnels
Waterproofing Bored Tunnels
NEL
CCL
Gasket details specified on design drawing
Proposed and accepted gasket
69
GeoSS 7 Aug 2012
70
GeoSS 7 Aug 2012
Waterproofing Bored Tunnels
Waterproofing Bored Tunnels
CCL
CCL
GeoSS 7 Aug 2012
71
GeoSS 7 Aug 2012
72
12
09/08/2012
Durable SFRC Segments
Durable SFRC Segments
• Elimination of risk of steel bar corrosion • Elimination of concrete spalling risk • More durable segment with min maintenance effort.
73
GeoSS 7 Aug 2012
74
GeoSS 7 Aug 2012
Challenges for Future Projects
Durable SFRC Segments • SFRC segments for DTL3: 2350m of bored tunnel
• A more responsive earth excavation management
Cross Over at Jln Besar Both tracks in Kallang ~350m Tunnel Escape Shaft
Sungei Road Station
Tunnel Escape Shaft
Both tracks in Old Alluvium ~1350m
Jalan Besar Station
• Continued development of new Upper track in Kallang; Lower track in OA, short length in Kallang ~650m
technology for durability
Kalang Bahru Station
75
GeoSS 7 Aug 2012
76
GeoSS 7 Aug 2012
Conclusions • Major land transport facilities to be built in Singapore • Progresses have been made
THANK YOU
• Challenges to the industry • Looking for new methods and technologies to address the challenges
GeoSS 7 Aug 2012
77
GeoSS 7 Aug 2012
78
13
View more...
Comments