Deep Excavation and Tunnelling Past Experience and Future Challanges

January 6, 2017 | Author: Chin Thau Wui | Category: N/A
Share Embed Donate


Short Description

Download Deep Excavation and Tunnelling Past Experience and Future Challanges...

Description

09/08/2012

Deep Excavation and Tunnelling Past Experience and Future Challenges

• Review of Major Underground Infrastructure Construction and Singapore Geology • Managing Ground Risk • Managing Risk of Ground Movement • Durability of Bored Tunnels • Conclusions

Deep Excavation and Tunnelling Past Experience and Future Challenges D Wen, BSc, PhD PE, PE(Geo), AC(Geo), CEng, MICE, MIEAust, CPEng

GeoSS 7 Aug 2012

温大志

1

2

GeoSS 7 Aug 2012

Major Underground Road Tunnels

MRT Network in Singapore North

Woodsville Interchange: Total tunnel length: 0.69km; Opened 28 Jan 2012

North-East

North South Expressway Tunnel and Semi Tunnel : 12.3 km to be completed around 2020

NSL East

EWL

Singapore Underground Road System: underground road tunnels

GeoSS 7 Aug 2012

KPE: Total tunnel length: 9km; Opened 26 Oct 2007 and 20 Sep 2008

CTE: North Tunnel: 0.7 km; South Tunnel: 1.7 km; Opened: 21 Sep 1991

3

Fort Canning Tunnel: 0.35 km; Opened 16 Jan 2007 MCE Tunnel : 3.5km to be opened at end 2013

4

GeoSS 7 Aug 2012

Deep Tunnel Sewerage System

Cable Tunnels

• Cable Tunnels – Tuas and Seraya • Gombas/Woodlands to Senoko • Pasir Panjang Road • Current 6 cable tunnel projects under tender

GeoSS 7 Aug 2012

5

GeoSS 7 Aug 2012

6

1

09/08/2012

Geological Process

Caverns • Rock Caverns in Jurong Formation • Rock Caverns in Bukit Timah Granite Formation

M OA

FCBB

GV

F/E

S4 GIV

GI/GII/GIII Jurong Formation (Sedimentary Rock)

Bukit Timah Granite (Igneous Rock)

In-filled Valleys Deep weathering of granite

7

GeoSS 7 Aug 2012

Mandai

Deep Excavation and Tunnelling

Punggol

Past Experience and Future Challenges

Serangoon Dhoby Ghaut

Boon Lay Scale : -2

0 1 2

Newton 4 (Km)

Outram Park

Kallang Formation

Geological Map

Old Alluvium Jurong Formation

Bukit Timah Granite Gombak Norite

• Review of Major Underground Infrastructure Construction and Singapore Geology • Managing Ground Risk • Managing Risk of Ground Movement • Durability of Bored Tunnels • Conclusions

Reclamation 9

GeoSS 7 Aug 2012

10

GeoSS 7 Aug 2012

SITE INVESTIGATION PHASES

Site Investigation

• Continuous process for entire duration of project • Phased approach

• To provide sufficient ground and ground water data  for a proper description of essential ground properties / behaviour to plan the most appropriate construction method; and  for a reliable assessment of characteristic values of ground parameters to achieve a safe and cost-effective design

GeoSS 7 Aug 2012

8

GeoSS 7 Aug 2012

Desk study Preliminary Detailed SI during construction 11

GeoSS 7 Aug 2012

12

12

2

09/08/2012

COST OF SITE INVESTIGATION

DESK STUDY

Cost of Risk and SI Efforts

• Geological archives/maps • Previous site investigations at the area • Historical land use survey • Published case histories

Optimum Effort Combined Cost

Cost of SI

Cost of Risk Increased Effects of Site Investigation

GeoSS 7 Aug 2012

13

13

COST OF SITE INVESTIGATION

14

GeoSS 7 Aug 2012

COST OF SITE INVESTIGATION

• USNCTT (1984): 3% of predicted construction cost • USNCTT: 1.5m borehole for every I m of tunnel • Hong Kong – major projects – around 1%

Source: Westland, J.R. et al (1998) Managing subsurface risk for Toronto’s rapid transit expansion program. Proc. North American Tunnelling. I. Ozdemir ed. Balkema. GeoSS 7 Aug 2012

15

COST OF SITE INVESTIGATION

Source: United States National Committee on Tunnelling Technology. (1984) Geotechnical site investigations for underground projects. National Academy Press. 16

GeoSS 7 Aug 2012

Site Investigation Report Site Investigation: field and laboratory works

• NEL: Average borehole spacing 36.5m Geotechnical Factual Report (GFR)

• NEL SI Cost to Civil Cost: 0.216%

Geotechnical Interpretative Report (GIR)

• DTL3: Average spacing 17.5m • DTL3 SI Cost to Civil Cost: 0.283%

Interpreted ground conditions for design, e.g. design sections, design parameters

From DTL

Geotechnical Interpretative Baseline Report (GIBR) GeoSS 7 Aug 2012

Contains the factual data from site investigation & laboratory tests

17

GeoSS 7 Aug 2012

Nature, form, composition, properties and structure of the ground and groundwater, artificial obstructions 18

3

09/08/2012

GIBR

Challenges

• To explicitly share the commercial risk with contractors  Set “Baseline” for commercial purpose  Set minimum requirements for design

Tunnel Alignment 19

GeoSS 7 Aug 2012

20

GeoSS 7 Aug 2012

Geophysical Survey

Challenges

• Commonly used methods

• To have more boreholes – practical

    

problems

• To carry out geophysical survey

Electrical resistivity Seismic refraction Seismic reflection Surface wave method Geo-tomography

22 21

GeoSS 7 Aug 2012

22

GeoSS 7 Aug 2012

Soil / Rock Interface – Accuracy ?

Geophysical Survey • Methods commonly used for soil / rock interface identification • Results are

Interpreted Profile of Surface Wave Velocity

 indirect interpretation of ground condition  influenced by many factors, e.g. utilities, traffic noise Interpreted Rock Profile GeoSS 7 Aug 2012

23

GeoSS 7 Aug 2012

24

4

09/08/2012

Detection of Pile Depth – Accuracy?

Soil / Rock Interface – Accuracy ?

ABH2 6 FILL F1

ABH2 1 FILL F1

GV & GVI GV & GVI

GII & GI

ABH1 8 FILL

F2 E F1 F2 F1 GVI & GV GIII, GII & G1

GIII & GII

Estimated Pile Penetration: 21~22m (or) 26~27 m GeoSS 7 Aug 2012

25

26

GeoSS 7 Aug 2012

Detection of Pile Depth – Accuracy?

Challenges • More efficient and accurate methods are required to determine 

rock levels



depth of piles

to minimise risk of underground construction in urban areas

GeoSS 7 Aug 2012

27

Deep Excavation and Tunnelling

28

Managing Risk of Ground Movement

Past Experience and Future Challenges

• Review of Major Underground Infrastructure Construction and Singapore Geology • Managing Ground Risk • Managing Risk of Ground Movement • Durability of Bored Tunnels • Conclusions GeoSS 7 Aug 2012

GeoSS 7 Aug 2012

• Ground Stability  Ultimate limit state to prevent collapse

• Ground Movement  Serviceability limit state to prevent damage to adjacent properties / underground utilities

29

GeoSS 7 Aug 2012

30

5

09/08/2012

Managing Risk of Ground Movement

Managing Risk of Ground Movement

Deep Excavation

Deep Excavation

Cut Slope at Tanjong Pagar Station: Original Design vs Revised Design

Cut Slope at Orchard Station: Original Design vs Revised Design After Hulme, Potter & Shirlaw (1986)

GeoSS 7 Aug 2012

After Hulme, Potter & Shirlaw (1986)

31

32

GeoSS 7 Aug 2012

Managing Risk of Ground Movement

Managing Risk of Ground Movement

Deep Excavation

Deep Excavation

Singapore Art Museum Cathedral of the Good Shepherd

Reflection Pool Bras Basah Rd

B1 Level

Connection SMU

B2 Level B3 Level B4 Level B5 Level

33

GeoSS 7 Aug 2012

34

GeoSS 7 Aug 2012

Managing Risk of Ground Movement

Managing Risk of Ground Movement

Deep Excavation

Challenges in Urban Environment

Deep Excavations in Soft Clay without Ground Treatment

After Goh (2008)

Ground Treatment Deep Excavations in Soft Clay with Ground Treatment

GeoSS 7 Aug 2012

35

GeoSS 7 Aug 2012

36

6

09/08/2012

Jet Grouting System

Effectiveness of Jet Grout in Marine Clay 160 Jet Grouted slab, 800mm wall

Air Grout Air

Air Water Air Grout

Single tube jet grouting system

Wall deflection, mm

140 Grout

120 100 TREND LINE, 1m to 1.2m DIAPHRAGM WALLS, NO JET GROUT

80 60 40 20

Double tube jet grouting system

Triple tube jet grouting system

0 0

10

20

30

40

Depth from ground surface to hard strata, m After Shirlaw, Tan & Waong (2005)

37

GeoSS 7 Aug 2012

38

GeoSS 7 Aug 2012

Hybrid ground treatment

Deep Soil Mixing (DSM) / Deep Cement Mixing (DCM)

Deep soil mixing + Jet grouting (Eg RASJET)

2.8m diameter columns achieved below formation level for C828 Nicoll Highway Station (φ1.6m internal column by mixing blades) 39

GeoSS 7 Aug 2012

40

GeoSS 7 Aug 2012

Use of Cross Walls

Use of Cross Walls

114E/W

Masjid Wak Tanjong

115E

EWL VIADUCT

EXISTING PIERS TO BE UNDERPINNED

EXISTING PILECAP

FILL

STRUT S2a

Cross Walls

Marine Clay

115E/W SOIL IMPROVEMENT WORKS by Cross Walls (lean concrete wall)

BOTTOM OF MARINE CLAY

OA

DIAPHRAGM WALL

116E/W

Circle Line Paya Lebar Station – Use of Cross Walls GeoSS 7 Aug 2012

41

EXISTING BORED PILES

Circle Line Paya Lebar Station – Use of Cross Walls GeoSS 7 Aug 2012

42

7

09/08/2012

Use of Cross Walls

Future Challenges

DTL1 C906 -65 100

-55

-45

-35

-25

-15

-5

5

Existing Tunnels

100

Sand Fill

90

90

87.0 (16m Excavation)

80

80

CROSS WALL 70

70

60

60

OA

50

Monitoring at DTL1 C906

-5

Transfer Beams and Barrettes for Underpinning Top tunnel in Marine Clay Future Tunnels Bottom tunnel in OA

Existing Piles / Barrettes

50

40

30

Depth (m)

Depth (m)

Kallang

5

GeoSS 7 Aug 2012

40

IW 894

Design prediction @ IW894

IW 900

Design prediction @ IW 900

15

25

35

45

55

Displacement (mm)

65

30

43

44

GeoSS 7 Aug 2012

Managing Risk of Ground Movement

Future Challenges

Bored Tunnels 3

• To match the design of soil improvement methods to be selected based on  the groutability of the ground encountered  the targeted engineering property of soil to be improved • To have minimum disturbance to surrounding structures • To develop new method and technology, e.g. horizontal grouting techniques 45

GeoSS 7 Aug 2012

5 4

1

1. 2. 3. 4. 5.

2 Loss into tunnel face Loss between the face and leading edge of shield Tail void Lining deformation Consolidation 46

GeoSS 7 Aug 2012

Managing Risk of Ground Movement

Managing Risk of Ground Movement

Bored Tunnels

Bored Tunnels

• Phase 1/2 MRT Construction in 1980s: Greathead Shield with hydraulic backhoe excavator or roadheaders / 1 EPBM / 1 TBM • Compressed air used extensively • Grouting done through the segments

• NEL: 14 EPBMs (2 Dual Modes), 2 Open Face TBMs • Automatic tail void grouting • Face pressure and stability by controlling the extrusion of the spoil through the screw conveyor and the advancement of the machine

Greathead Shield GeoSS 7 Aug 2012

EPBM (C301) 47

EPBM (C705) GeoSS 7 Aug 2012

EPBM (C706)

EPBM (C710)

48

8

09/08/2012

Automatic Tail Void Grout

Over Cutting

Marine clay

Extrados of segment Tail void grout

49

GeoSS 7 Aug 2012

50

GeoSS 7 Aug 2012

Managing Risk of Ground Movement

Managing Risk of Ground Movement

EPBM

EPBM 1. Stability Number N = (σv + q – σt) / cu 2. Stability Number, Nc at collapse

Increase / Lowering of Shield Advance Rate Increase / Lowering of

Surcharge q

Screw Discharge Rate

C Z

σT

D

Water

P

Earth

Pressure 51

GeoSS 7 Aug 2012

52

GeoSS 7 Aug 2012

Managing Risk of Ground Movement

Managing Risk of Ground Movement

EPBM

EPBM cu

50

kPa

density

18

kN/m^3

surcharge

10

kPa

depth

20

m

Nc overburden

Typical Volume Loss for a tunnel of D = 6m by EPB

9 370

Face Pressure (% of overburden) Face Pressure

kN/m^2

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

37

74

111

148

185

222

259

296

333

370

N

6.66

5.92

5.18

4.44

3.70

2.96

2.22

1.48

0.74

0.00

1/F

0.74

0.66

0.58

0.49

0.41

0.33

0.25

0.16

0.08

0.00

Volume Loss (%)

6.0

4.0

3.0

2.0

1.3

1.0

0.5

0.2

0.1

0

CIRIA Report 30, March 1996 GeoSS 7 Aug 2012

53

GeoSS 7 Aug 2012

54

9

09/08/2012

Managing Risk of Ground Movement

Managing Risk of Ground Movement

EPBM

EPBM

Plastic Nature of Spoils to Maintain Face Pressure No Plug, Material Saturated and Flowing 55

GeoSS 7 Aug 2012

56

GeoSS 7 Aug 2012

Managing Risk of Ground Movement

Managing Risk of Ground Movement

EPBM

Bored Tunnels • Circle Line: 19 EPBM, 8 Slurry TBMs • Scanners / belt weighing experimented and adopted subsequently • Slurry TBM used for sections with granite

Over-excavation in Mixed Tunnel Face by EPBM Slurry TBM (C854) 57

GeoSS 7 Aug 2012

Slurry Treatment Plant

EPBM (C823) 58

GeoSS 7 Aug 2012

Managing Risk of Ground Movement

Managing Risk of Ground Movement

Slurry TBM

Bored Tunnels • DTL1: 3 EPBMs • DTL2: 10 EPBMs + 9 Slurry TBMs • DTL3: 19 TBMs

Face pressure is maintained by controlling the volume difference of the bentonite suspension supplied to the chamber and the suspension combined with excavated material removed from it GeoSS 7 Aug 2012

EPBM (C902) 59

GeoSS 7 Aug 2012

Slurry TBM (C915)

EPBM (C917) 60

10

09/08/2012

Deep Excavation and Tunnelling

Durability

Past Experience and Future Challenges

• Review of Major Underground Infrastructure Construction and Singapore Geology • Managing Ground Risk • Managing Risk of Ground Movement • Durability of Bored Tunnels • Conclusions

• The durability objective is to achieve a service life, with appropriate maintenance, of 120 years • Design measures need to be taken to achieve the objective.

61

GeoSS 7 Aug 2012

GeoSS 7 Aug 2012

Durability Measures

62

Typical Durability Problems

• Concrete with low permeability and low chloride diffusion

• Protective coating to extrados of segment • Detailing – adequate cover to re-bars, including drilling positions / bolt pockets.

• Electrically continuous steel cages as provision for future cathodic protection, if required. GeoSS 7 Aug 2012

63

GeoSS 7 Aug 2012

Typical Durability Problems

64

Technology Development

• Simple bitumastic sealing strip • Composite neoprene and bitumastic • •

GeoSS 7 Aug 2012

65

strips Neoprene gaskets “Hydrotite” gaskets

GeoSS 7 Aug 2012

66

11

09/08/2012

Neoprene Gaskets / Bitumastic Strips

Waterproofing Bored Tunnels NEL

 Contract specification required the use of both EPDM gaskets and hydrophilic sealing strips

67

GeoSS 7 Aug 2012

68

GeoSS 7 Aug 2012

Waterproofing Bored Tunnels

Waterproofing Bored Tunnels

NEL

CCL

Gasket details specified on design drawing

Proposed and accepted gasket

69

GeoSS 7 Aug 2012

70

GeoSS 7 Aug 2012

Waterproofing Bored Tunnels

Waterproofing Bored Tunnels

CCL

CCL

GeoSS 7 Aug 2012

71

GeoSS 7 Aug 2012

72

12

09/08/2012

Durable SFRC Segments

Durable SFRC Segments

• Elimination of risk of steel bar corrosion • Elimination of concrete spalling risk • More durable segment with min maintenance effort.

73

GeoSS 7 Aug 2012

74

GeoSS 7 Aug 2012

Challenges for Future Projects

Durable SFRC Segments • SFRC segments for DTL3: 2350m of bored tunnel

• A more responsive earth excavation management

Cross Over at Jln Besar Both tracks in Kallang ~350m Tunnel Escape Shaft

Sungei Road Station

Tunnel Escape Shaft

Both tracks in Old Alluvium ~1350m

Jalan Besar Station

• Continued development of new Upper track in Kallang; Lower track in OA, short length in Kallang ~650m

technology for durability

Kalang Bahru Station

75

GeoSS 7 Aug 2012

76

GeoSS 7 Aug 2012

Conclusions • Major land transport facilities to be built in Singapore • Progresses have been made

THANK YOU

• Challenges to the industry • Looking for new methods and technologies to address the challenges

GeoSS 7 Aug 2012

77

GeoSS 7 Aug 2012

78

13

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF