CP_MANUAL

August 1, 2017 | Author: Faddy Faris | Category: Corrosion, Pipe (Fluid Conveyance), Pipeline Transport, Welding, Materials
Share Embed Donate


Short Description

Download CP_MANUAL...

Description

CORROSION MATTERS

DESIGN , ENGINEERING AND INSTALLATION MANUAL FOR PERMANENT CATHODIC PROTECTION SYSTEM FOR UNDERGROUND PIPELINE.

CORROSION MATTERS 6-3-899/2, 2ND FLOOR , SWATHI PLAZA RAJBHAVAN ROAD, SOMAJIGAUDA, HYDERABAD – 500082

PHONE NO : +91 40 3240 4595 TELEFAX : +91 40 2341 8786

EMAIL: [email protected] WEBSITE : www.corrmatt.com

Page 1 of 48

CORROSION MATTERS

COMPANY OVERVIEW

Corrosion Matters , this company has been founded by Corrosion and Electrochemical Engineers in 2005 to cater to projects, related to corrosion prevention systems For prevention of corrosion , our team of engineers , are having hands on experience in handling time bound and critical projects of importance. The company is actively engaged in Cathodic Protection related comprehensive design and project management services for projects that are typically , cross country pipelines, complex plant Underground piping, Onshore and Offshore facilities , City Gas and Water mains, above ground storage tanks , concrete steel structures etc. The company has been chosen to foresee and supervise construction projects and key assets of National and International Importance in Oil and Gas sectors. The Objective of the company is to provide services to the industry to the minute detail and innovate user friendly methods of Cathodic Protection Applications which shall help the industries world over in a long way.

REGARDS,

CORROSION MATTERS

Page 2 of 48

CORROSION MATTERS

CATHODIC PROTECTION SYSTEM FOR U/G PIPING ( CROSS-COUNTRY)

1. SCOPE OF WORK :

The scope of work covers the Design, Engineering, Supply of Materials, Installation, Testing & Commissioning of Permanent cathodic protection system for external surface of under ground pipeline including post commissioning surveys such as Coating Conductance Measurements ,CIPL survey, Pearson detection followed by DCVG [for defect classification] at defect locations evinced. Also getting specific approval for major activities like •

Soil Resistivity survey & site data generation/collection.



CP Design & Detailed Engineering



Field Testing & Commissioning



Procedures for interference testing & mitigation



All major installation Procedures



Coating conductance, CPIL & PEARSON Survey.



Post Commissioning, Monitoring methodology & frequency formats

Page 3 of 48

CORROSION MATTERS

1.1 SOIL RESISTIVITY SURVEY Soil resistivity survey should be carried out at at minimum two plots for each proposed CP station as option for selecting best location for construction. Soil resistivity will be carried out at different depth and at all anode bed locations. The locations of anode ground bed plot will be selected based on the land availability to avoid problems during construction & keeping maintenance in view. However from the resistance calculations it can be decided type of anode bed. Land selection for anode ground bed has been taken base on following broad guidelines, however final decision to be taken at site based on land availability. 1.

site for shallow ground bed should have minimum 100 mtr perpendicular distance from the pipeline.

2.

Location shall be remote (anode remoteness requirement to be calculated based on design current rating with local resistivity & criteria)

3.

Accessibility of location and route for laying of anode header cable shall be checked and marked on plot plan drawing.

4.

Anode bed shall not be situated below HT line and near electrical earthing.

5.

Lowest resistivity location shall be considered over options available, for better anode ground bed resistance option.

Page 4 of 48

CORROSION MATTERS

1.2 DESIGN BASIS & CRITERIA The intent of this section is to propose design data and criteria for the Permanent Cathodic Protection System.

1.2.1

Cathodic Protection Design Life & Current Density

In accordance with the project specification, the Cathodic Protection system will be designed to have a desired design life in years. For Example : The Pipeline external surface is coated with 3 Layer Polyethylene (3LPE) coating and the current density considered for the design is as follows: i)

For Polyethylene coated Pipeline (Normal Soil)

ii)

For Polyethylene coated Pipeline (Salt pan Area) : 125 µA/m2

: 25µ µA/m2

A safety margin of 1.3 i.e. 30% has been provided for the current calculations over and above the specified protective current density.

1.2.2

Philosophy of Cathodic Protection System for Permanent CP

The Cathodic protection systems shall be a MMO Lida anodes systems and shall be designed for Deepwell and Horizontal type anode bed.

1.2.3

Codes & Standards

Latest revision of following standards shall be considered BS7361-Cathodic Protection-Part 1

Cathodic Protection –code of Practice for Land and Marine Applications

BS: CP:2008

Protection of Iron & Steel Structures From Corrosion.

NACE RP 0177-2000

Mitigation of alternating current and Lightning Effects on Metallic structures and corrosion control systems

NACE RP 0286-2002

Electrical Isolation of Cathodically protected pipelines

NACE RP 0169-2002

Control of external corrosion on underground or submerged metallic piping system.

CP_MANUAL.doc

Page 5 of 48

CORROSION MATTERS NACE TM 0497-2002

Measurement techniques related to criteria for cathodic protection of underground-submerged metallic piping system.

NACE Publication No 54276 NACE RPO.

1.2.4

Cathodic protection monitoring for buried pipelines. For Deep well CP

Cathodic Protection Design Criteria for Perma nent CP

Cathodic Protection system shall be designed to meet the following criteria: 1.

The pipe to Soil Potential measurements shall be in between (-) 0. 95V “Off ” and (-) 1.1.7V “Off ” as measured between the pipe surface and a copper – copper sulphate reference electrode.

2.

In rare circumstances a minimum polarization shift of (-) 100mV shall indicate adequate levels of cathodic protection for the pipeline with the written permission from owner.

3.

A positive potential swing of >20mV shall be considered as the criteria for presence of an interaction situation requiring investigation and incorporation of mitigation measures.

CP_MANUAL.doc

Page 6 of 48

CORROSION MATTERS

1.3 Cathodic Protection Stations In line with the project specifications and design calculations, location and No. of CP Station shall be proposed as under:-

S.N.

CP St’n. Location

CP Station No.

1

(SV#1)

CP#1

2

(SV#2)

CP#2

3

(SV#3)

CP#3

4

(SV#5)

CP#4

Chainage (Km)

Type

Rating

1.4 DESIGN CALCULATION The following Calculation shall be used for design the permanent cathodic protection system

1.4.1

Total Cathodic Protection Current Requirement

i.

Surface Area

Sa =

Π x Dx L

Where :

ii.

Sa

= Surface area of Pipeline m2

D

= Diameter of pipeline m

L

= length of pipeline m Current Requirement It

=

Sa x Cd x 1.3/1000 Amps.

Where = C.P. current requirement (Amp)

It Sa

= Surface area of Pipeline m2

Id

= C.P. protective current density mA/m2

1.3

= Safety Margin

CP_MANUAL.doc

Page 7 of 48

CORROSION MATTERS The current requirement calculations shall be tabulated as under:

CP station

Area

Classification

Chainage (Km)

Dia. (mm)

Protection span (Km)

From

Total Km

Surface Protective Current Area (m2) Current Required Density (µA) (Amp.)

TO

CP#1 (SV# 1) CP#2 (SV# 2)

CP#3 (SV# 3)

CP#4 (SV# 5)

CP_MANUAL.doc

Page 8 of 48

CORROSION MATTERS

1.4.2

Anode Requirement

Current NA = It /Ia. Where NA =

Total Anode Weight (Kg.)

It

=

C.P. current requirement

Ia

=

Out put current of Anode (4Amps)

Weight W

It x Ct x L/Uf

=

Where W

=

Total Anode weight (Kg)

Ct

=

Consumption Rate of anode (1 mg/Amp-year)

It

=

C.P. current requirement

Uf

=

Anode utilization factor

Total current Location

Out put current

Type of

Anode required

Anode

requirement as per

of individual

Anode

as per current

required as

Anode

design (Amps)

anode (Amps)

(Nos)

per Weight

proposed

(Nos.)

(Nos)

CP#1 (SV#1) CP#2 (SV#2) CP#3 (SV#3) CP#4 (SV#5)

CP_MANUAL.doc

Page 9 of 48

Number of

CORROSION MATTERS

1.4.3 i)

Ground bed Resistance calculation

Horizontal Grounded Resistance Calculation

The resistance of horizontal anode to electrolyte is calculated by the following formula :

Rs = 0.159Ps [ Ln ( 4L2 + 4L ( S2 + L2 ) 0.5) + S – (S2 + L2)0.5 – 1 ) ] L

DS

L

L

Where

ii)

Rs =

Resistance to earth in ohms of the horizontal anode (Ω)

Ps =

Soil Resistivity in Ω - m

L

Length of Active Anode in Mtr

=

D =

Diameter of Active Anode in Mtr

S

Twice the depth of Anode (M)

=

DEEP ANODE BED RESISTANCE CALCULATION

The resistance of deep anode to electrolyte is calculated by the following formula : Rdb = 0.159 Ps [ Ln ( 8 L / d)-1 ] L Where

iii)

Rdb

=

Resistance to earth in ohms of the Deep anode (Ω)

Ps

=

Soil Resistivity in Ω – m

L

=

Length of Active Anode in Mtr

D

=

Diameter of Active Anode in Mtr

INDIVIDUAL ANODE TO BACKFILL RESISTANCE

Rbs = 0.159 P [ Ln ( 8 L / d)-1 ] L

where Rbs =

Individual Anode to backfill resistance in Ω

Ps =

Back fill Resistivity for calcined petroleum coke breeze ( 50 Ω-cm )

L = Length of Anode in mtr. d

=

CP_MANUAL.doc

Diameter of Anode in mtr.

Page 10 of 48

CORROSION MATTERS TOTAL ANODE TO BACKFILL RESISTANCE

Rtbs = Rbs/N where

iv)

Rtbs =

Total Anode to Backfill Resistance in Ω

Rbs =

Individual Anode to backfill resistance in Ω

N

Number of Anodes

=

TOTAL GROUND BED RESISTANCE OF THE BED

Rgb = Rs + Rtbs

Rgb

=

Total Ground bed resistance

Rs

=

Resistance of vertical /Horizontal Anode to earth in (Ω)

Rtbs =

Total Anode to Backfill Resistance in Ω

v)

TOTAL CABLE RESISTANCE



ANODE TAIL CABLE RESISTANCE OF SHALLOW GROUNDBED

Single core copper conductor Armoured cable of 10 sq.mm is selected as Anode Tail Cable as per tender specification.

Ri = Li x R10 Where Ri

=

Individual Anode lead Cable resistance in Ω ( i = 01 to 10 )

Li

=

Length of Anode cable in meters

R10

=

Resistance of 10 sq.mm cable = 1.83 Ω / km 1

Rta =

CP_MANUAL.doc

( 1/R1 + 1/R2 + 1/R3 ........+R/n)

Page 11 of 48

CORROSION MATTERS



HEADER CABLE RESISTANCE FOR CP SYSTEM

Single core copper conductor cable of 35 sq.mm is selected as Anode and Cathode Header cable .

Rac = R35 ( Lac + L cc ) Where Rac =

Resistance of Header Cable

Lac =

Length of Anode Header Cable

Lcc =

Length of Cathode Cable

R35 =

Resistance of 35 sq.mm cable

=

0.529 Ω / km

TOTAL RESISTANCE OFFERED BY ALL CABLES Rtc = Rta + Rac

vi)

Rtc

=

Total cable resistance

Rta

=

Total anode tail cable resistance

Rac

=

Total Header Cable Resistance

TOTAL CIRCUIT RESISTANCE Rtcr = Rgb + Rtotal

vii)

Rtcr

=

Total circuit resistance in Ω

Rtotal =

Total cable resistance in Ω

Rgb

=

Total Ground bed resistance in Ω

OUTPUT OF SYSTEM It

=

current required for CP Station in amps

Rtcr

=

Total Circuit resistance in Ω

Back Voltage

:

2Volts

Additional Voltage to drive the required current (V)

=

It x Rtcr

Total Output Voltage (Vt)

=

V +2

CP_MANUAL.doc

Page 12 of 48

CORROSION MATTERS viii) REMOTE EARTH CALCULATIONS Following Formulae is used to calculate the distance to remote earth VE

=

ρxA/2xπxd

Where ρ

=

Resistivity in Ohm- mtr

A

=

Current in Amps

D

=

Distance between pipeline & Anodebed in mtr

VE

=

Voltage at Pipeline

Remote earth voltage shall be less than the Natural PSP i.e. -0.45V

CP_MANUAL.doc

Page 13 of 48

CORROSION MATTERS

1.4 Summary of Design Calculation

CP

Average Soil

St’n.

Resistivity (Ω Ω-

Locati

mtr

on (1)

Considered (2)

Proposed No. of Anodes

Type (3)

No (4)

Installed

Type of

Anode

Anode Bed

current Rating (Amps) (5)

(Amps) (6)

(7)

Size of Anode bed.

Depth (mtr) (8)

Active Length (mtr) (9)

Dia / Width (mm) (10)

Total

Total out put

Remote

Distance

Total

circuit

required

earth

between

Distance between Anode (11)

bed

cable

R’tance

Voltage

Anode bed to

R’tance -

R’tance

(Rtcr)

(Volts)

Pipeline

Rab (Ω Ω) (12)

SV-1 SV-2 SV-3 SV-5

Note: If column (17) is less than pipeline Natural PSP , the distance of remoteness is sufficient.

CP_MANUAL.doc

Total Ground

Page 14 of 48

(Rtc) (13)

(14)

Amps

Volts

(It)

(Vt)

(15)

(16)

(17)

proposed (mtr) (1.7)

CORROSION MATTERS

1.5 Length Of Pipeline Protected From Drain Point i)

CROSS SECTION AREA OF PIPELINE

Ap

=

Π x t x ( D-t )

in m2

where A

=

Cross section area of Pipe

D

=

Diameter of Pipe

T

=

Thickness of pipe

ii)

LINEAR RESISTANCE OF PIPE

Rs

=

ρs x l / A

in Ω / km

where

iii)

ρs

=

Resistivity of steel pipe

A

=

Cross section area of pipe

l

=

Unit length of pipe

(2.2 x 10-7) ohm meter

COATING LEAKAGE RESISTANCE PER KM FOR 3LPE COATING

Rl

=

Rp/Sakin Ω per km

where Rp

=

Sak =

iv)

Coating resistance in Surface area of pipe per Km

ATTENUATION CONSTANT - α α

=

( Rs/Rl )0.5

Where

v)

Rs

=

Linear Resistance of pipe

Rl

=

Coating leakage resistance

MINIMUM POTENTIAL SHIFT AT END POINT

CP DESIGN / PERM / CORRMATT

Page 15 of 48

CORROSION MATTERS

Edp =

P/s min - P/s nat in Volts

where

vi)

P/s min

= Least negative PSP at end point

P/s nat

= Natural PSP of pipeline

LENGTH OF PIPELINE PROTECTED FROM DRAIN POINT

Lp =

(1/α α) x Cosh-1(Edp/ Ed)

Summary of current Attenuation calculation 01

Dia (mtr)

02

Thickness (mm)

03

Surface Area of 1 Km Pipe (m2)

04

Resistivity of steel pipe (ohm-m)

05

Coating Resistance of Pipe (ohm/ m2)

06

Linear Resistance of pipeline (ohm/km)

07

Coating Leakage resistance of Pipe (ohm/km)

08

Attenuation constant α

09

Least negative PSP at end point

10

Natural PSP of pipeline

11

Minimum potential shift at end point

12

Max. PSP at drain point

13

Length of pipeline protected from drain point

CP DESIGN / PERM / CORRMATT

Page 16 of 48

CORROSION MATTERS

1.6 Sample Design Calculation for CP Station for Span Length from 0 to 28.9 Km Equation 1.6.1 Sa =

P x d x l

1.6.2 It = Sa x Id x 1.3/1000

Description

41165 m2

d

Dia

0.4534 m

l

Length

28900 m

It

Total Current requirement

Sa Surface area Current density

W Total Anode Weight

W = I t x Ct x L / U f

1.6.4

unit

Sa Surface area

Id 1.6.3

Value

It

Total Current

Ct

Consumption Rate

L

Life

Uf

Anode Utilization factor

Nw No of Anode required by weight

1.33 Amps 41165 m2 0.025 mA/mt2 0.062 grams 1.33 Amps 0.001 gm/A-Y 40 Years 0.85 0.25 Nos

W Total Anode Weight

0.062 grams

Wa Weight of Anode

0.240 grams

Nw = W/ Wa (Thickness of MMO Coating 6gm/m2)

CP DESIGN / PERM / CORRMATT

Page 18 of 48

CORROSION MATTERS 1.6.5

Nt = It/ Ia

Nt No of Anode required by current

0.44 Nos

It

1.33 Amps

Total current

Ia Anode output current

3 Amps

GROUND BED RESISTANCE CALCULATION FOR SHALLOW HORIZONTAL ANODE BED

RS Individual anode to backfill resistance

1.6.6

Rs = 0.159Ps/L Ln(4L2 + 4L (S2+L2) 0.5)/DS)+( S/L) – (S2+L2)0.5/L –1)

PS Soil Resistivity

ohm36 mtr

N No of Anodes

8 Nos

L

Active length of anode

D Active diameter of Pre-packed anode bed S

Twice the depth of Anode

Rbs Individual anode to backfill resistance

1.6.7

Rbs = 0.159 Pb/L

Ln ( 8 L / d)-1 

Pb Backfill Resistivity for Calcined Coke L

Length of anode

d

Diameter of anode

Rtbs Total Anode to Backfill Resistance

1.6.8

Rtbs = Rbs/N

Rbs Individual anode to backfill resistance N Number of Anodes

CP DESIGN / PERM / CORRMATT

0.806 Ohms

Page 19 of 48

51 mtr 0.4 mtr 6 mtr 0.38 Ohms ohm0.5 mtr 1 mtr 0.025 mtr 0.047 Ohms 0.38 ohms 8 Nos

CORROSION MATTERS

Rgb = Rs + Rtbs

1.6.9

Rgb Total Ground bed Resistance

0.853 Ohms

Rs Resistance of vertical Anode to earth

0.806 Ohms

Rtbs Total Anode to Backfill Resistance Rta = 1/(1/R1)+(1/R2)……..+1/R6 Ri = Li x R10

Rta Resistance of Anode Tail Cable

Li Length of Anode cable

0.047 Ohms 0.0552 Ohms mtr

R1 & R5 = 8 x 0.001.73 = 0.015ohms 1.6.10 R2 & R6 = 15x0.001.73 = 0.028 ohms R3 & R7 = 22x0.001.73 = 0.040 ohms R4 & R8 = 29x0.001.73 = 0.053 ohms

R25 Resistance of 10 mm2 cable Rac Resistance of Header cable

1.6.11

R35 Resistance of 35 mm2 cable

0.00115 Ohm/Mtr 0.14 Ohms 0.00056 Ohm/mtr

Rac = R35 ( Lac + L cc ) Lac Length of Cathode cable lcc Length of Anode cable Rtc Total Reisistance offered by All cables

1.6.12

Rtc = Rta + Rac

Rac Resistance of Header cable Rta Resistance of Anode tail cable Rtotal Total Circuit Resistance

1.6.13

Rtotal = Rgb + Rtc

CP DESIGN / PERM / CORRMATT

75 mtr 175 mtr 0.143 Ohms 0.14 Ohms 0.00342 Ohms 0.997 Ohms

Rgb Total Ground bed Resistance

0.853 Ohms

Rtc Total Reisistance offered by All cables

0.143 Ohms

Page 20 of 48

CORROSION MATTERS 1.6.14

Vt

Vt Total Output Voltage

3.32 Volts

Rtotal Total Circuit Resistance

0.997 Ohms

= (Rtotal x It)+ 2Volts It

1.6.15

Vx Vx = I /2 L

Total Current

1.33 Amps

Back Voltage

2 Volts

Voltage rise in earth with earth

respect to remote

 Soil Resistivity L

Distance between P/L and Anode bed

I

Maximum current output

0.401 Volts 36 Ohms 100 Mtr 7 Amps

From above electrically remoteness calculations for Anode bed, it can observed that Voltage raise in earth with respect to remote earth at a distance 100 is less than to pipeline Voltage to earth (ie 0.45V) & Remoteness of anode ground bed can be achieved 1.6.16

Ap Cross section area of Pipe

0.0123 Mtr

D

Diameter of Pipe (m)

0.4534 Mtr

t

Thickness of pipe

0.0087 Mtr

Ap = P x t x ( D-t ) P 1.6.17

Rs Linear Resistance of pipeline

Rs = s x l / Ap

s

Resistivity of steel pipe

I

unit length of pipe

Ap Cross section area of Pipe CP DESIGN / PERM / CORRMATT

Page 21 of 48

ohm/K 0.01.70 m 0.0000 0022 ohm-mtr 1000 mtr

0.0123 mtr

CORROSION MATTERS 1.6.1.7

Rl = Rp/Sa

1.6.1.7

=( Rs/Rl )0.5

1.6.20

Rl Coating Leakage Resistance for 3LPE

ohm/K 10.45 m

Rp Coating Resistance

ohm15000 mtr2

Sa Surface area per Km

1435.7 1 mtr2

 attenuation Constant

0.0415

Rs Linear Resistance of pipeline

0.01.70 ohm/Km

Rl Coating Leakage Resistance for 3LPE

10.45 ohm/Km

Edp Maximum potential shift at drain point

-1.05 V

P/s

Edp =P/s max - P/s nat

max

Least negative PSP at drain point

-1.5 V

P/s nat

1.6.21

Natural PSP of pipeline

Ed Maximum potential shift at end point

-0.45 V -0.5 V

P/s

Ed =P/s min - P/s nat

min

Least negative PSP at end point

-0.95 V

Natural PSP of pipeline

-0.45 V

P/s nat

Lp Length of P/L protected from drain point

1.6.22

Lp=(1/) x Cosh-1(Edp/ Ed)

Edp Maximum potential shift at drain point

-1.05 V

Ed Maximum potential shift at end point

-0.5 V

 attenuation Constant

CP DESIGN / PERM / CORRMATT

33.12 Km

Page 22 of 48

0.0415

CORROSION MATTERS

1.7 INSTALLATION PROCEDURES 1.7.1 TEST STATION / JUNCTION BOX INSTALLATION Purpose :

Test stations/ Junction box shall be provided along the pipeline ROW for monitoring the performance of the Cathodic Protection system Materials Required : Shuttering Plates, Reinforcement, Concrete Mix, CableLugs , Ferrules

Detailed Procedure: •

The location of the test stations/junction box shall be marked on row as per approved design with their connection scheme and other related information on alignment sheet.



The test stations/junction box shall be installed with the front of the test station facing the pipeline.



The overall dimensions of foundations shall be 600 mm(W) x 700 mm (H) X 500 mm (D).



Excavate 1m x 1 m x 1 m where the foundation is to cast.



Place reinforcement properly and take TLP bend and place it properly in the reinforcement.



Take MS shuttering and place it in right position.



Fill annular space with RCC Mix. The mixture shall be constantly rammed for proper compaction.



Remove the shuttering after 24 hrs.



The foundation shall be cured properly or it shall be coated with curing compound.



Place the TLP boxes/Junction boxes on the studs of the bend cast in concrete foundation and tighten the bolts.



The bolts shall then be distorted by hitting with a heavy hammer to make the installation vandal/theft proof

CP DESIGN / PERM / CORRMATT

Page 23 of 48

CORROSION MATTERS Precautions: •

All the connections should be checked for proper tightening.



Cable core ferrules are to be provided at end before final termination



Door of the TLP/Junction box should face Pipeline



Cable should be neatly dressed inside the trench and to be terminated inside test station.



In case of location, where sacrificial anode is to be installed, the same should be taken parallel and the anode cable to be terminated at test station.

Documentation: Inspection Reports shall be furnished as per the report formats attached below:

CP DESIGN / PERM / CORRMATT

Page 24 of 48

CORROSION MATTERS INSPECTION AND TEST PLAN FOR TEST STATION / J.B INSTALLATION PROJECT OWNER CONTRACTOR CP CONTRACTOR REFERENCE DOCUMENT PERSONAL RESPONSIBLE

SR NO

ACTIVITY APPROVAL OF TEST STATION INSTALLATION

1

PROCEDURE

2

CHECK LOCATION CONCRETE FOUNDATION SIZE, RCC MIXTURE,

3

REINFORCEMENT & CURING INSTALLATION TEST POST MOUNTING ABOVE

4

FONDATION

5

TERMINATION OF CABLES IN THE TEST STATION

CPC

CONTRACTOR OWNER

P

W

A

P

W

RM

P

W

RM

P P

W W

RM RM

LEGEND A - APPROVAL / ACCEPTANCE; R - REVIEW OF RECORD; RM - RANDOM CHECK W - WITNESS ALL; P- PERFORM

CP DESIGN / PERM / CORRMATT

Page 25 of 48

CORROSION MATTERS

SITE INSPECTION REPORT FOR TEST STATION/ JUNCTION BOX INSTALLATION PROJECT OWNER CONTRACTOR CP CONTRACTOR REF. DOC UMENT Test station Location ( Chainage in Km) Test Station Type Distance from Pipeline Foundation

Acceptable /Not Acceptable

Test Station Mounting

Acceptable /Not Acceptable

Cable Termination

Acceptable /Not Acceptable

Final Restoration

Acceptable /Not Acceptable

Notes :

CPC

CONTRACTOR

OWNER

Name Signature Date

CP DESIGN / PERM / CORRMATT

Page 26 of 48

CORROSION MATTERS

1.7.2 ANODEBED INSTALLATION PROCEDURE FOR ANODE BED INSTALLATION SCOPE This procedure covers installation of Deep ground bed as per standard drawing & design document. MATERIALS REQUIRED Sr.No

Material/Tool

Make

Application/Purpose

01

Crimping Tool

Standard

For crimping cable with lug

02

Excavation tools & Auggers

Standard

For Excavation

03

Measuring Tape

Standard

Measurement

04

Petroleum coke breeze

Goa Carbons

Backfill material

05

Canister

Standard

Sheet steed for Backfilling

06

Tubular anode

Lida® / SME / other approved

Anodes for Anode bed

07

Anode Tail cable

Netco/Suyog

Connection to pipe

08

Cu Sleeves/ Cable Lug/D clamps/Ferrules, PVC pipe & Warning mat etc.

Standard

09

Electrical Tool Box

Standard

10

Casing Pipe for Deep anode bed

Standard

Casing Pipe for Deep anode bed

11

PVC Shrouding Pipe

Standard

For Deep anode ground bed

13

PVC Vent Pipe

Standard

For Deep Well

PROCEDURE FOR DEEP WELL ANODE INSTALLATION •

Locate the Drilling Rig at approved deep well ground bed location.



Start the drilling of borehole with suitable diameter drilling bit and drill a

borehole of

suitable depth as per approved document. •

Lower the casing pipe (3mm) one length at a time and coupling various lengths

with couplers

one after the other. •

After lowering MS casing pipe, a PVC shrouding pipe equal to the inactive length of the deep well ground bed shall be lowered along the casing pipe from the top.



Mark length equal to the required depth on the tail cables of anodes to avoid excessive lowering.

CP DESIGN / PERM / CORRMATT

Page 27 of 48

CORROSION MATTERS •

Tie all MMO anodes with vent pipe and cables to gather, and also install the centralizers for each anodes and End weight to last anode as per design approval.



Anodes shall be lowered with suitable nylon rope. Nylon rope shall be binded with end weight.



Mix the coke breeze with water to form slurry.



Fill the slurry coke breeze inside the bore well up to the active length and rest backfill with metal gravel, this is to ensure proper filling of entire borehole.



Backfilling to be done till overflowing from top of the pit, and than allow it to settle, fill the top of pit as per approved drawing, with metal gravel after settling time of two-three days.



Clamp / Tie the anode tail cable and lay up to anode junction box



All the tail cables and Header cable shall be laid and terminated in anode junction box.



Prepare Anode pit and cover as per approved drawing.

FOR HORIZONTAL BED INSTALLATION •

Length of the ground bed shall be according to the approved design package.



Total depth of excavation in horizontal ground bed shall be as per design document.



Cross section of bottom of the trench should be as per approved design document, as the same is only considered for anode bed resistance calculation. The shape of excavated trench from top to bottom need not be precise. Moreover, it shall depend on nature of soil at the site.



Pour backRill into the trench and tamp it to a level corresponding to 0.150 m from bottom of trench. Pour sufficient water on coke breeze and mix with wooden plank to prepare slurry.



Mark the locations of individual canister anodes alongside the trench as spacing indicated in the approved design package and place the individual anode horizontally within the trench on the bed of the backfill prepared.



Anode tail cables of individual anodes should be coiled and kept on ground adjoining the trench.



Pour backfill into the trench and tamp it to a level corresponding to design requirement. (Take care while tamping the coke breeze so that the anode connection or cable is not damaged). Again pore sufficient water on top of the spread up coke breeze all over the anode so that slurry can be achieved.



Lay Tail cable & header cables and bring them up to proposed anode junction box location as per standard drawing.



PVC sleeve to be provided on all anode tail cables up to entry of anode junction box, for mechanical protection.

CP DESIGN / PERM / CORRMATT

Page 28 of 48

CORROSION MATTERS •

At 1.0 m depth all anode tail cable and anode header cable to be laid as per cable laying procedure.



Earth restoration work with proper compaction to be carried out at cable laying and anode bed location.



Layout of anode installation in anode bed shall be as detailed out in the drawing showing anode installation.

PRECAUTIONS •

Lower anode carefully to avoid damage to tail cable, Canister anodes should never be handled by cables, but rope to be used for the same.



After lowering clamp/Tie the cable to avoid further slide



Tail cables and PVC conduits shall be of sufficient length so as to reach Anode Junction Box without any joint and providing sufficient slack for future maintenance purpose.



Each shallow anode bed shall contain anodes with canisters positioned in the soil with suitable backfill at appropriate depth with due regards to type of configuration.



Keep tail cable lengths sufficient so as to reach anode junction box without any joint and providing sufficient slack for future maintenance purpose



All cables are to be appropriately tagged before lowering cables in to trench/well.



Provide cable core ferrules at end before final termination.

HEALTH, SAFETY & ENVIRONMENT Hazard Identification and risk assessment will be carried out and Operational Control measures shall be adopted for Anode Installation Activities. i.

Necessary PPE to be utilized

ii.

Only trained personnel to be deployed for this activity.

QUALITY ASSURANCE & QUALITY CONTROL Quality Assurance shall be maintained by ensuring the systematic implementation of this Procedure and ensure that necessary quality records are generated as per ITP.

CP DESIGN / PERM / CORRMATT

Page 29 of 48

CORROSION MATTERS INSPECTION AND TEST PLAN FOR DEEPWELL / SHALLOW HORIZONTAL ANODEBED INSTALLATION

PROJECT OWNER CONTRACTOR CP CONTRACTOR

PERSONAL RESPONSIBLE

CPC : SITE ENGINEER / SUPERVISOR CONTRACTOR/ OWNER : INSPECTOR CONTRACTO

SR NO

ACTIVITY

CPC

OWNER R

1

APPROVAL OF DEEP GROUND BED PROCEDURE

P

R

A

2

CHECK LOCATION

P

3

CHECK DEPTH

P

W

A

W

R

4

CHECK CASING PIPE LOWERING

P

5

CHECK ANODE LOWERING

P

W W

R RM

6

FILLING OF COKE BREEZE

P

W

R

LEGEND A - APPROVAL / ACCEPTANCE; R - REVIEW OF RECORD; RM - RANDOM CHECK W - WITNESS ALL; P- PERFORM

CP DESIGN / PERM / CORRMATT

Page 30 of 48

CORROSION MATTERS

SITE INSPECTION REPORT FOR DEEPWELL ANODE INSTALLATION PROJECT OWNER CONTRACTOR CP CONTRACTOR REFERENCE DOC. LOCATION DISTANCE OF ANODE BED FROM PIPELINE DIA OF CASING PIPE LENGTH & DIAMETER OF BORE HOLE NO OF ANODES IN THE STRING ANODE RATING ANODE LOWERING

OK / NOT OK

COKE BREEZE FILLING

OK / NOT OK

Notes:

CPC

CONTRACTOR

OWNER

Name Signature Date

CP DESIGN / PERM / CORRMATT

Page 31 of 48

CORROSION MATTERS

1.7.3 PIPE TO CABLE CONNECTION Pipe To Cable Connection By Thermit Welding Scope This procedure covers Thermit Weld for cable connection to pipeline for all type of cables related to Cathodic Protection System. Cable to Pipe connection during construction shall be done by Thermit welding method. Materials Required

Sr.No

Material/Tool

Make

Application/Purpose

01

Crimping Tool

Standard

For crimping cable with lug/ferrule

02

Thermit Mould & Sparking Gun

Erico, USA

Thermit welding & Igniting

03

Cad Weld Powder, CA15 & CA32

Erico, USA

Welding

03

Cables

Netco

Connection to pipe

04

Hammer & Chisel

Standard

Hammering test for Thermit & Coating cutting

05

Epoxy Dobefil-60

Doctor Beck

06

Hardner-758

Doctor Beck

For sealing of Cable to pipe joints

07

PVC Funnel

Local

Coating Repair Filing.

08

M seal / Mastic

Mahindra / CPC

Sealing for PVC funnel

09

Cu Sleeves

Standard

For Cable Connections

10

Fine File

Local

Surface Cleaning

11

Sand Paper

Local

Surface cleaning

12

Holiday Detector

Caltech

For coating check

Procedure •

Excavate (wherever pipeline backfilled with soil) a pit over the pipeline to expose the pipeline top surface at location of Thermit weld where cable to pipe connection is to be carry out as per design document. Care should be taken not to damage the coating of buried pipeline. Only manual excavation shall be carried out over pipeline.



Mark where connection is to be carried out. If there are more than one connection as per design document, consecutive marking shall be minimum 300 mm apart. Connection location shall be minimum 300mm apart from other connection and Welding joint, Seam or Circumferential Weld

CP DESIGN / PERM / CORRMATT

Page 32 of 48

CORROSION MATTERS Joint of the pipeline. The location for cable to pipe connection shall be selected such that the pipe joints and field-coated areas are avoided. •

Cut open the coating on the pipeline with care and without damaging the pipe for a size of approximately 50 mm x 50 mm (suitable for thermit weld mould).



Clean the surface of the pipeline to white metal finish using sand paper and cleaning with fine file as required.



Depending on the size of cable select the model of cad weld material i.e. CA-15 or CA-32 and mould.



Copper sleeve of suitable size shall be double Crimped on the cable (up to 10 sqmm cable).



Place the mould on the exposed area and pour the cad weld material. Ignite using the gun and wait for 2 minutes cool down period.The resistance of Cable to pipe at thermite connection point shall not exceed 0.1Ω



Test the connection by striking 0.5 Kg hammer directly over the connection. And if connection fails, the above procedure shall be repeated after waiting time of approx.10min.to cool the pipeline surface.



Place a plastic funnel around the exposed area such that about 15mm wide coating remains in side the plastic funnel. Apply mastic/Mseal around the plastic funnel to prevent leakage of encapsulation materials.



Mix proper quantity of epoxy-hardner and keep mixing with wooden rod till it gets heated, Fill up the conical funnel from the top by pouring mix of Epoxy – Dobofil – 60 and hardener – 758 at 1:10 ratio. 3/4th of the cone to be Rilled with mix and remaining plastic cone to cut after setting of the hardener.



Allow the epoxy-hardener to set ensuring every metallic part of joint is completely insulated and test the insulation level by a holiday detector at 25 KV.



Cable shall be laid in accordance with approval cable laying drawings. Cable route shall be carefully measured and cable cut to be required length from test station to pipe. A loop of approx 0.5mtr.of cable shall be kept at both pipe and Test Station end.

Precautions a.

Only Manual excavation to be done without damaging the coating.

b.

All cables are to be appropriately tagged.

c.

Location of cable to pipe connection shall be minimum 300mm apart from other connection and from Pipe weld joint, Seam or Circumferential Weld Joint

CP DESIGN / PERM / CORRMATT

Page 33 of 48

CORROSION MATTERS d.

Check hardness of encapsulation before holiday test by applying pressure with thumb/Wooden Stick.

e.

Coating repair and holiday test should be completed before backfilling.

f.

Maximum 15 grams Ignition powder shall be used for each connection. If one connection fails, wait of approx 10 min for pipeline cooling and then repeat the procedure for connection.

Health,Safety & Environment Hazard Identification and risk assessment will be carried out and Operational Control measures shall be adopted for Anode Installation Activities. •

Necessary PPE to be utilized



Only trained personnel to be deployed for this activity.

CP DESIGN / PERM / CORRMATT

Page 34 of 48

CORROSION MATTERS

SITE INSPECTION REPORT FOR THERMIT WELD CONNECTION PROJECT OWNER CONTRACTOR CP CONTRACTOR REFERENCE DOC. Chainage

Test Station Type Type of Cable to Pipe Connection

Thermit welding

Cable Size

Length

No. of Pipe to Cable Connection

1C x 6 SQMM Cable 1C x 10 SQMM Cable 1C x 25 SQMM Cable Resistance of cable to pipe at thermit connection point

Acceptable / Not Accebtable

Hammer Test Holiday Test

OK / NOT OK

Pipe to soil potential (Natural) w.r.t. Zinc Reference Half cell 1C x 6 SQMM Cable 1C x 10 SQMM Cable 1C x 25 SQMM Cable Sealing of exposed area of pipe with Epoxy Sealing material CPC

CONTRACTOR

OWNER

Signature Name Date

CP DESIGN / PERM / CORRMATT

Page 35 of 48

CORROSION MATTERS

1.8 PROCEDURE FOR COMMISSIONING OF PCP SYSTEM Purpose To describe the procedure for commissioning of Permanent cathodic protection system and provide adequate quality assurance / control of workmanship and inspection at site.

Scope This procedure will cover commissioning of the Impressed Current C.P system installed to protect under ground pipeline from external corrosion. Equipments -

Soil resistivity meter

-

Digital multimeters

-

Portable reference electrodes

-

Megger

Commissioning Procedure



On completion of installation of anode beds and other systems as envisaged in the specification, they shall be individually checked, tested and compared against the agreed specifications and procedure.



The CP commissioning shall be carried out with current interrupter provided in the output of the CPPSM unit to measure CP “ON” & “OFF” potentials.



Current dissipated by each anode shall be corrected through anode lead junction box.



Electrical continuity of the entire pipeline shall be verified in conformity with design.



Input resistance of the pipeline at all the drainage points shall be checked and recorded.



All current measuring test stations shall be calibrated and recorded.



Temporary protection facilities provided (if any) which do not form part of permanent CP shall be disconnected from the sytem & removed unless agreed otherwise.



The pipeline shall be allowed to depolarize for atleast 72 hours after switching ‘off’ the protection (if any) of all other pipelines in the common R.O.W.



Before the pipeline is put on charge by switching ‘on’ CP station, natural structure –to-electrolyte potential values at all the test stations of the system shall be measured with respect to zinc reference cell.

CP DESIGN / PERM / CORRMATT

Page 36 of 48

CORROSION MATTERS •

CP station shall be energized so as to achieve a maximum pipe soil potential (PSP) as specified at the test station nearest to the drainage point, and observations on either spread of protected portion of pipeline under this CP station shall be taken for PSP values pipeline current values across the cross section of the pipeline shall also be determined at all the intended test stations influenced by this CP station.



Another complete set of PSP observations shall be taken after lines have stayed on charge for 24/48 hours. If there are appreciable differences in these observations as compared to those of earlier set, a third set of observations shall be taken after 72 hrs. Maximum drainage point protective potentials shall not be allowed to go beyond the maximum PSP values as specified, in any case.



The output of CP Station shall then be so adjusted that the sites of occurrence of least negative protective potentials are increased to (-) 1.00 V. A full set of observations shall again be taken 72 hrs. after the adjustment of potentials and the protection system shall be left in this state of operation.



Care shall be exercised to ensure that power supply remains uninterrupted during the period of commissioning. In case of an interruption, the test in progress shall be repeated after allowing time for polarization. More sets of observations may be advised to be taken by the owner/owner’s representative in any of the above-mentioned steps.



PSP values at each of the test stations of the existing pipelines shall be measured and plotted where existing pipelines run in parallel to the new pipeline and mutual interference situations between the pipelines shall be identified and necessary mitigation shall be carried out.



Interference situations shall also be identified and mitigated by comparing different sets of readings taken at same test stations at different intervals of time under identical conditions where positive potential swing exceed 50 MV.



Final records of testing and commissioning including graphical representation of final structure to electrolyte potential readings shall be complied with interpretation in consolation with owner/owner’s representative and submitted.



If it is found during commissioning that the sites of occurrence of least negative or most negative protective potentials are less negative than (-) 1.00V even after 72 hrs of operation, then the drainage point potentials shall be adjusted depending upon anode ground bed currents in consultation with Owner/Owner’s representative. In any case, the drainage point protective ‘ON’ potential values shall not exceed the PSP values as per specification and the pipe to soil ‘OFF’ potential shall not exceed a value more negative than (-) 1.20 V at any location on the pipeline.



The current dissipated by the indiviual anodes shall be measured from the anode lead junction box and corrected for equal dissipation to the extent possible keeping the total ground bed current same.

CP DESIGN / PERM / CORRMATT

Page 37 of 48

CORROSION MATTERS

INSPECTION AND TEST PLAN FOR PCP COMMISSIONING PROJECT OWNER CONTRACTOR CP CONTRACTOR REFERENCE DOC PERSONAL RESPONSIBLE CPC : SITE ENGINEER / SUPERVISOR CONTRACTOR / OWNER : INSPECTOR SR NO 1 2

3

4 5

ACTIVITY

CPC

CONTRACTOR

OWNER

Pre commissioning Tests At Anode Bed And TR Unit

S

W

A

Disconnection Of Sacrificial Anode On Entire Spread And

P

W

RM

P

W

RM

P

W

RM

P

W

A

Allow For Depolarization After 72 Hrs. Of Depolarization Collect Natural Potentials At All Test Stations Energize The Cp Unit And Record The Reading To Find Attenuation Submission Of Records

LEGEND

A - APPROVAL / ACCEPTANCE R - REVIEW OF RECORD RM - RANDOM CHECK

CP DESIGN / PERM / CORRMATT

W - WITNESS ALL P- Performed by S – Submitted by

Page 38 of 48

CORROSION MATTERS

PRE-COMMISIONING CHECKS REPORT PROJECT OWNER CONTRACTOR CP CONTRACTOR REFERENCE DOC. LOCATION DATE SR NO

ACTIVITY

OBSERVATION

1

Anode Bed Installation Termination Etc.

OK/NOT OK

CP unit Installation & Earthing , cable termination and tagging etc & No Load operational checks.

OK/NOT OK

2

3

CP system cable termination & taging

OK/NOT OK

4

CP unit working condition (No load)

OK/NOT OK

5

Surge Diverter Installation

OK/NOT OK

6

Reference cell Calibration (mv)

RE-1 RE-2

REMARKS

CPC

CONTRACTOR

OWNER

Name: Sign: Date:

CP DESIGN / PERM / CORRMATT

Page 39 of 48

CORROSION MATTERS INSPECTION REPORT FOR PCP COMMISSIONING (ANODE BED)

PROJECT OWNER CONTRACTOR CP CONTRACTOR REFERENCE DOC. Date CP Station No

Location

GROUND BED DETAILS 1.0

Groundbed Configuration & Type

2.0

Groundbed Rating

3.0

Voltage between Pipe and Anode (Back EMF):

4.0

TR Unit Output

5.0

Total Anode bed Resistance (3 Pin)

Ohms

6.0

Total Anode To Cathode Circuit Resistance (DC O/P Volts/Current)

Ohms

7.0

Individual Anode current at Anode Junction Box

Anode No

Anode Quantity

Voltage

Potential Across the shunt (mV)

Current (amps)

Anode No

A1

A6

A2

A7

A3

A8

A4

A9

A5

A10

REMARKS

Current

Potential Across the shunt (mV)

Current (amps)

Total Current: CPC

CONTRACTOR

OWNER

Name: Sign: Date:

CP DESIGN / PERM / CORRMATT

Page 40 of 48

CORROSION MATTERS

INSPECTION REPORT FOR PCP COMMISSIONING (CP Unit) PROJECT OWNER CONTRACTOR CP CONTRACTOR REFERENCE DOC. Report.No.

Date:

CP Station No:

Chainage & Location :

TR Unit Parameters Hour Meter Reading : Input Voltage (Volts)

Input Current (Amp)

DC

DC output Voltage (Volts)

DC

DC output Current (Amps)

Anode bed Loop Resistance

Calculated V/I from above _______________________Ohm

Mode

Auto/AVCC/Manual

Coarse Control Switch

Fine Control Switch

Pipe to Soil Potential W.r.to Permanent Reference cell (Cu-CuSO4) Reference 1 (-V)

Reference 2 (-V)

Reference 3 (-V)

Set PSP in TR unit (-V) PSP at nearest TS (Drainage) -V

REMARKS

CPC

CONTRACTOR

OWNER

Name: Sign: Date:

CP DESIGN / PERM / CORRMATT

Page 41 of 48

CORROSION MATTERS INSPECTION REPORT FOR PCPCOMMISSIONING (PSP Natural PSP) (Format 1 of 3) PROJECT

VCM PIPELINE PROJECT

OWNER

CHEMPLAST SANMAR LIMITED

CONTRACTOR

CONTRACTOR INFRASTRUCTURE LIMITED

CP ONTRACTOR

CPCRPG LIMITED

REFERENCE DOC.

CPC-CONTRACTOR-VCM-DD-001

Report.No.

Date:

Readings From _______ km to _______km Test station No

Type

PSP (-V) Chainage

Natural PSP

(Km)

AC PSP

Remarks Casing PSP

REMARKS :- PSP after 48 hrs of disconnection of sacriRicial anode connections to pipeline.

CPC

CONTRACTOR

OWNER

Name: Sign: Date:

CP DESIGN / PERM / CORRMATT

Page 42 of 48

CORROSION MATTERS NSPECTION REPORT FOR PCPCOMMISSIONING (PSP reading First Set ) Format 2 of 3 PROJECT OWNER CONTRACTOR CP ONTRACTOR REFERENCE DOC. Report.No.

Date:

CP Unit On : Chainage & Location __________________________ Readings From _______ km to _______km Test station No

Type

PSP (-V) Chainage

`ON` PSP

(Km)

AC PSP

Remarks Casing PSP

REMARKS : Setting of TR unit to be recorded in TR format with note for commissioning first set of readings purpose.

CPC

CONTRACTOR

OWNER

Name: Sign: Date:

CP DESIGN / PERM / CORRMATT

Page 43 of 48

CORROSION MATTERS

INSPECTION REPORT FOR PCPCOMMISSIONING (PSP reading ) Format 3 of 3 PROJECT OWNER CONTRACTOR CP ONTRACTOR REFERENCE DOC. Report.No.

CP section (IJ to IJ) From _________ to __________km Test station

No

Type

Chainage Km

PSP Initial (-V) ON PSP

PSP 48 Hrs (-V) ON PSP

PSP After 72 Hrs (-V). ON PSP

AC PSP

Date: Remarks

CASING

REMARKS

CPC

CONTRACTOR

Name: Sign: Date:

CP DESIGN / PERM / CORRMATT

Page 44 of 48

OWNER

CORROSION MATTERS

1.9 POST COMMISSIONING SURVEY CIPL SURVEY Purpose To define the procedure for the conduction of CIPL Survey on the commissioned Pipeline to evaluate the CP system and to provide adequate quality assurance / control.

Equipment / Accessories Required •

Pipeline locators (if required)



Data collector-Sincoder along with the reference cell Sticks.



Current interrupts with synchronized timer circuits and adjustable time settings



Rodometer



Flexible cable/wire of required length.

Procedure



Before commencing the survey, confirm that the cathodic protection system is operating normally by checking the DC feeders, drain points, insulating joints with commissioning results.



Check the cathodic protection commissioning result to identify the area requiring special attention during the CIPL survey.



Locate the route of the pipeline using the pipeline locator and provide temporary markers (Marking powder) on the route to enable the survey to walk-on the route of the pipeline for carrying out the CIPL survey.



Install current interrupter with synchronized timer in the DC negative output of the DC power source (CP System) at the CP station of the section in which the survey is being carried out.



Set the interrupter switching cycle at a ratio of 4:1 ON:OFF.



With the equipment connected and the pipeline located, move along the pipeline carrying the mobile data collector and Zinc reference cell and measure and store the pipe to soil potentials.



Check reference electrodes regularly for its operation.



Record distance traversed and physical features such as roads, as descriptors to assist locating specific areas after processing the data.

CP DESIGN / PERM / CORRMATT

Page 45 of 48

CORROSION MATTERS •

As each section between TLP connections is completed, real the fine wire for further use and shift continuous chart records to the next section.



Transfer the data from the simcorder to a computer for producing the data print outs and plot of the PSP potential profiles.



The data collected during the survey shall include i. Monitoring results of the sectional T/R Units ii. Data (PSP Values) – ON and Instant OFF Distance location details as a descriptors.



After completing the survey based on the above procedure, the readings in numeric and graphical manner shall be submitted after detailed interpretation.

CP DESIGN / PERM / CORRMATT

Page 46 of 48

CORROSION MATTERS

SITE INSPECTION PLAN FOR CIPL SURVEY PROJECT OWNER CONTRACTOR CP ONTRACTOR

REFERENCE DOCUMENT PERSONAL RESPONSIBLE

CPC : SITE ENGINEER / SUPERVISOR CONTRACTOR/OWNER: INSPECTOR

S.NO

ACTIVITY

Performed By CPC

1

Submission & Obtaining approval of Procedure

P

TR Interrupter Setting

P

Conduction of Survey

2 3 5 5 6

Verification Records Verification By By submission OWNER CONTRACTOR by CPC R

A

R

RM

P

W

RM

Entering of Readings

P

R

RM

Entering of Location Description

P P

R R

RM R

Final Report

LEGEND A - APPROVAL / ACCEPTANCE R - REVIEW RM - RANDOM CHECK W - WITNESS

CP DESIGN / PERM / CORRMATT

Page 47 of 48

CORROSION MATTERS

Inspection Report for CIPL Survey PROJECT OWNER CONTRACTOR CP ONTRACTOR REF. DOC : CPC-CONTRACTOR-VCM-DD-001

DATE

Interrupter Setting

OK / NOT OK

Staring Location , Chainage

Ending Location , Chainage

TRU Section Conduction of Survey

OK / NOT OK

Entering of Datas / Locations

OK / NOT OK

Remarks

CPC

CONTRACTOR

OWNER

Signature Name Date

**********************

CP DESIGN / PERM / CORRMATT

Page 48 of 48

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF