Costo Horario Vibrador de Concreto

November 10, 2023 | Author: Anonymous | Category: N/A
Share Embed Donate


Short Description

Download Costo Horario Vibrador de Concreto...

Description

SEMINARIO DE TITULACIÓN "TECNOLOGÍA PARA EL DESARROLLO URBANO"

ING. VICTOR ALEJANDRO VAZQUEZ MENDEZ ALUMNO FECHA: 12/10/22 ANALISIS DEL COSTO DIRECTO: HORA-MAQUINA DATOS GENERALES CODIGO:

EQ19313-06-39

NUM. SERIE:

4579

MAQUINA:

VIBRADOR DE CONCRETO

MODELO:

J043

CAPACIDAD: PRECIO DE ADQUISICION:

$11,221.10

VIDA ECONOMICA EN AÑOS:

1.88

PRECIO JUEGO LLANTAS:

$00.00

HORAS POR AÑO (Hea):

800 HRS.

VIDA ECONOMICA (Ve):

1,500 HRS.

EQUIPO ADICIONAL: VIDA ECONOMICA DE LLANTAS:

HRS.

POTENCIA NOMINAL 4 HP

PRECIO PZAS ESPECIALES. (Pe):

$00.00

COSTO COMBUSTIBLE(Pc): GASOLINA

VIDA ECONOMICA PZAS ESPEC.(Va):

HRS.

VALOR DE LA MAQUINA (Vm):

$11,221.10

COSTO LUBRICANTE(Pa): ACEITE

VALOR DE RESCATE (Vr):

10%

FACTOR DE OPERACION (Fo):

80.00%

TASA DE INTERES (i):

6.2367%

POTENCIA DE OPERACION (Po):

3.20

PRIMA DE SEGUROS (s):

4%

FACTOR DE MANTENIMIENTO (Ko):

0.85

SALARIO REAL DEL OPERADOR(Sr):

$67.66

COEFICIENTE COMBUSTIBLE(Fc):

0.2271

SALARIO POR OPERACION(So):

$433.01

COEFICIENTE LUBRICANTE(Fa):

0.003

HORAS EFECTIVAS DE TRABAJO POR TURNO (Ht):

6.4

CAPACIDAD DEL CARTER (CC):

1

TIEMPO ENTRE CAMBIO DE LUBRICANTE(Ca):

40

FACTOR DE RENDIMIENTO (Fr):

$1,122.11

$19.48 / LTS.

$113.68 / LTS.

1.0 ACTIVA

CARGOS FIJOS a).- DEPRECIACION.......D = (Vm-Vr)/Ve = 11,221.10 - 1,122.11 / 1,500.00 =

$6.73

b).- INVERSION.................Im = (Vm+Vr)* i/2Hea = (11,221.10 + 1,122.11) * 0.06 / 2 * 800.00 =

$0.48

c).- SEGUROS...................Sm = (Vm+Vr) * S/2Hea = (11,221.10 + 1,122.11) * 0.04 / 2 * 800.00 =

$0.31

d).- MANTENIMIENTO....M = Ko * D = 0.85 * 6.73 =

$5.72

SUMA CARGOS FIJOS CONSUMOS

$13.24

a).- COMBUSTIBLE......GASOLINA Co = Fc * Po * Pc = 0.2271 * 3.20 * 19.48 =

$14.16

b).- OTRAS FUENTES DE ENERGIA:....: = 0 * 0 = $0

$0.00

c).- LUBRICANTE:.....Lb = [(Fa * Po) + CC/Ca] * Pa = [(0.0030 * 3.20) + 1 / 40] * $113.68/Lt. =

$3.93

d).- LLANTAS:.....N = Pn/Vn

$0.00

= $0.00 / 0.00 =

e).- PIEZAS ESPECIALES:.....Ae = Pe/Va

= $0.00 / 0 =

$0.00

SUMA DE CONSUMOS: OPERACION OPERADOR DE EQUIPO MENOR JOR

$18.09 Po = Sr / (Ht) = $599.88/6.4

OPERACION

93.73 $93.73

SUMA DE OPERACION POR HORA

$93.73

COSTO DIRECTO HORA-MAQUINA

$125.06

ING. WALTER FLORES CALVO PERSONA FISICA