Cost Sheets (Road Construction) DUPA
February 8, 2017 | Author: Neb Bie | Category: N/A
Short Description
Download Cost Sheets (Road Construction) DUPA...
Description
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
100(1)
Clearing & Grubbing (with Stripping) sq.m. 500.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
2 1 1
1 1 1
1,352.00 1,733.00 2,299.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Dump Truck (10 cu.m.) b. Payloader (1.50 cu.m.) c. Bulldozer (155 Hp), D65A-8 (Hauling Distance - within three (3) km.) Assumed 150mm cut
Sub - Total for B C. Total (A + B) D. Output per hour = 500.00 sq.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
100(2)a
Individual Removal of Trees (small a, 150-300mm Ø) ea. 3.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.50 0.50 0.50
1,537.00 1,352.00 121.50
Unit
Quantity
Unit Cost
m.
20.00
3.50
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Dump Truck (10 cu.m.) c. Chain Saw Minor Tools (5% of labor) * Boom Truck - if necessary for trimming in Urban Areas
Sub - Total for B C. Total (A + B) D. Output per hour = 3.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Rope, 1" dia.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
100(2)b
Individual Removal of Trees (small b, 301-500mm Ø) ea. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.50 0.50 0.50
1,537.00 1,352.00 121.50
Unit
Quantity
Unit Cost
m.
20.00
3.50
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Dump Truck (10 cu.m.) c. Chain Saw Minor Tools (5% of labor) * Boom Truck - if necessary for trimming in Urban Areas
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Rope, 1" dia.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
100(3)a
Individual Removal of Trees (large a, 501-750mm Ø) ea. 0.25
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 1
1,537.00 1,352.00 121.50
Unit
Quantity
Unit Cost
m.
20.00
3.50
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Dump Truck (10 cu.m.) c. Chain Saw Minor Tools (5% of labor) * Boom Truck - if necessary for trimming in Urban Areas
Sub - Total for B C. Total (A + B) D. Output per hour = 0.25 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Rope, 1" dia.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
100(3)b
Individual Removal of Trees (large b, 751-900mm Ø) ea. 0.125
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 1
1,537.00 1,352.00 121.50
Unit
Quantity
Unit Cost
m.
20.00
3.50
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Dump Truck (10 cu.m.) c. Chain Saw Minor Tools (5% of labor) * Boom Truck - if necessary for trimming in Urban Areas
Sub - Total for B C. Total (A + B) D. Output per hour = 0.125 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Rope, 1" dia.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(1)
Removal of Structures and Obstruction (other than concrete) cu.m. 10.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Backhoe (0.80 cu.m.)
1
1
1,537.00
b. Dump Truck (10 cu.m.) Minor Tools (10% of Labor)
1
1
1,352.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 10.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(2)
Removal of Concrete Bridge Structures cu.m. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Backhoe w/ Breaker (0.80 cu.m.)
1
0.50
2,074.95
b. Jackhammer c. Air Compressor (103 Hp) d. Dump Truck (10 cu.m.) e. Payloader (1.50 cu.m.) f. Truck Mounted Crane (35 T) g. Cutting Outfit
2 1 1 1 1 1
1 1 0.125 0.125 0.25 1
514.31 675.00 1,352.00 1,733.00 1,553.00 45.00
Unit
Quantity
Unit Cost
set
0.10
2,500.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Oxy/Acytelene
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(2)
Removal of Steel Bridge Structures kg. 1,000.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Service Truck/Cargo Truck
1
1
b. Welding Machine
1
1
712.00 391.00
c. Truck Mounted Crane (35 T) d. Cutting Outfit Minor Tools (10% of Labor)
1 1
1 1
1,553.00 45.00
Unit
Quantity
Unit Cost
set kg. m.
0.00025 0.002 0.05
2,500.00 90.00 3.50
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 1000.00 kg. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Oxy/Acytelene b. Welding Rod c. Rope 1" dia. * Include shoring materials if needed based on actual field condition
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(2)
Removal of Stone Masonry Lined Drainage Structures cu.m. 5.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Backhoe w/ Breaker (0.80 cu.m.)
1
0.50
2,074.95
b. Backhoe (0.80 cu.m.) c. Dump Truck (10 cu.m.)
1 1
0.50 0.25
1,537.00 1,352.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 5.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Sub - Total for F G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) I. Contractor's Profit (CP)
9% of G 8% of G
J. Value Added Tax (VAT) K. Total Unit Cost
12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(2)
Removal of Concrete Drainage Structures cu.m. 2.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Backhoe w/ Breaker (0.80 cu.m.)
1
0.50
b. Backhoe (0.80 cu.m.)
1
0.50
2,074.95 1,537.00
d. Dump Truck (10 cu.m.) e. Cutting Outfit
1 1
0.125 1
1,352.00 45.00
Unit
Quantity
Unit Cost
set
0.10
2,500.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Oxy/Acetylene
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(2)a
Removal of RCPC (24" dia.) - 610mm l.m. 6.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.)
1
1
b. Boom Truck
1
0.50
1,537.00 961.20
Unit
Quantity
Unit Cost
Minor Tools (10 % of Labor)
Note: Exclude Excavation Works
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 6.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(2)b
Removal of RCPC (30" dia.) - 760mm l.m. 5.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.)
1
1
b. Boom Truck
1
0.50
1,537.00 961.20
Unit
Quantity
Unit Cost
Minor Tools (10 % of Labor)
Note: Exclude Excavation Works
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 5.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(2)c
Removal of RCPC (36" dia.) - 910mm l.m. 4.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.)
1
1
b. Boom Truck
1
0.50
1,537.00 961.20
Unit
Quantity
Unit Cost
Minor Tools (10 % of Labor)
Note: Exclude Excavation Works
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 4.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(2)d
Removal of RCPC (42" dia.) - 1070mm l.m. 4.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 0.50
1,537.00 961.20
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck Minor Tools (10 % of Labor)
Note: Exclude Excavation Works
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 4.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(2)e
Removal of RCPC (48" dia.) - 1220mm l.m. 3.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 0.50
1,537.00 961.20
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck Minor Tools (10 % of Labor)
Note: Exclude Excavation Works
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 3.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(2)f
Removal of RCPC (60" dia.) - 1520mm l.m. 2.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 0.50
1,537.00 961.20
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck Minor Tools (10 % of Labor)
Note: Exclude Excavation Works
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(2)g
Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200mm Ø), L=10 ft. ea. 2.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.25
1,102.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (10 T) Minor Tools (10% of Labor)
Note: Exclude Excavation Works
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(3)a.1 Removal of Existing Concrete Pavement (0.23m thk.) sq.m. 40.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.50
2,074.95 1,733.00 1,352.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe w/ Pavement Breaker (0.80 cu.m.) b. Payloader (1.50 cu.m.), LX80-2C c. Dump Truck (10 cu.m.) Minor Tools (10% of Labor) * Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 40.00 sq.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(3)a.2 Removal of Existing PCC Pavement, 0.23m thk. (for Reblocking at intermittent section) sq.m. 30.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1
1 1 0.50 0.50
2,074.95 1,733.00 1,352.00 167.38
Unit
Quantity
Unit Cost
pc.
0.00015
8,000.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe w/ Pavement Breaker (0.80 cu.m.) b. Payloader (1.50 cu.m.), LX80-2C c. Dump Truck (10 cu.m.) d. Concrete Saw, Blade Ø 14" (7.5 Hp) Minor Tools (10% of Labor) * Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 30.00 sq.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Concrete Saw (diamond blade 14")
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(3)b
Removal of Existing Asphalt Pavement (100mm thk.) sq.m. 60.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.50
2,173.00 1,733.00 1,352.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Motorized Road Grader w/ Scarifier, G710A b. Payloader (1.50 cu.m.), LX80-2C c. Dump Truck (10 cu.m.) Minor Tools (10% of Labor) * Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 60.00 sq.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(3)c
Removal of Sidewalk sq.m. 60.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.50 0.50 0.50
2,074.95 1,537.00 1,352.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe w/ Pavement Breaker (0.80 cu.m.) b. Backhoe (0.80 cu.m.) c. Dump Truck (10 cu.m.) * Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 60.00 sq.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(4)a
Removal of Curb l.m. 50.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.50 0.50 0.50
2,074.95 1,537.00 1,352.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe w/ Breaker (0.80 cu.m.) b. Backhoe (0.80 cu.m.) c. Dump Truck (10 cu.m.) * Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
101(4)b
Removal of Curb & Gutter l.m. 30.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.50 0.50 0.50
2,074.95 1,537.00 1,352.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe w/ Breaker (0.80 cu.m.) b. Backhoe (0.80 cu.m.) c. Dump Truck (10 cu.m.) * Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 30.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
102(1)
Roadway Excavation (Unsuitable) cu.m. 20.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
2 1 1
1 1 0.10
1,352.00 1,537.00 1,733.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Dump Truck (10 cu.m.) b. Backhoe (0.80 cu.m.) c. Payloader (1.50 cu.m.) at disposal site Minor Tools (10% of Labor) * Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 20.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
102(2)a
Roadway Excavation (Surplus Common) cu.m. 60.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 2
1 1 0.25 1
2,299.00 1,733.00 1,733.00 1,352.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Bulldozer (155 Hp), D65A-8 b. Payloader (1.50 cu.m.) c. Payloader (1.50 cu.m.) - at disposal area d. Dump Truck (10 cu.m.) (Hauling Distance - within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 60.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,704.00 1,733.00 2,299.00
6,736.00 6,968.07 13.94 Amount
0.00 13.94 1.25 1.11 1.96 18.26
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 79.70 122.88
311.77 Amount
768.50 676.00 60.75 15.59
1,520.84 1,832.61 610.87 Amount
70.00
70.00 680.87 61.28 54.47 95.59 892.21
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 79.70 122.88
311.77 Amount
768.50 676.00 60.75 15.59
1,520.84 1,832.61 1,832.61 Amount
70.00
70.00 1,902.61 171.23 152.21 267.13 2,493.18
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 79.70 122.88
311.77 Amount
1,537.00 1,352.00 121.50 15.59
3,026.09 3,337.86 13,351.43 Amount
70.00
70.00 13,421.43 1,207.93 1,073.71 1,884.37 17,587.45
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 79.70 122.88
311.77 Amount
1,537.00 1,352.00 121.50 15.59
3,026.09 3,337.86 26,702.87 Amount
70.00
70.00 26,772.87 2,409.56 2,141.83 3,758.91 35,083.17
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 79.7 122.88
311.77 Amount
1,537.00 1,352.00 31.18
2,920.18 3,231.95 323.19 Amount
0.00 323.19 29.09 25.86 45.38
423.51
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
1,037.48 1,028.62 675.00 169.00 216.63 388.25 45.00
3,559.97 4,074.32 4,074.32 Amount
250.00
250.00 4,324.32 389.19 345.95 607.13
5,666.59
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
712.00 391.00 1,553.00 45.00 51.44
2,752.44 3,266.79 3.27 Amount
0.63 0.18 0.18
0.98 4.25 0.38 0.34 0.60
5.56
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
1,037.48 768.50 338.00
2,143.98 2,658.33 531.67 Amount
0.00 531.67 47.85 42.53
74.65 696.69
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
1,037.48 768.50 169.00 45.00
2,019.98 2,534.33 1,267.16 Amount
250.00
250.00 1,517.16 136.54 121.37 213.01
1,988.09
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
1,537.00 480.60 23.21
2,040.81 2,272.88 378.81 Amount
0.00 378.81 34.09 30.31 53.19
496.40
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
1,537.00 480.60 23.21
2,040.81 2,272.88 454.58 Amount
0.00 454.58 40.91 36.37 63.82
595.68
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
1,537.00 480.60 23.21
2,040.81 2,272.88 568.22 Amount
0.00 568.22 51.14 45.46 79.78
744.59
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
1,537.00 480.60 23.21
2,040.81 2,272.88 568.22 Amount
0.00 568.22 51.14 45.46 79.78
744.59
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
1,537.00 480.60 23.21
2,040.81 2,272.88 757.63 Amount
0.00 757.63 68.19 60.61 106.37
992.79
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
1,537.00 480.60 23.21
2,040.81 2,272.88 1,136.44 Amount
0.00 1,136.44 102.28 90.92 159.56 1,489.19
DETAILED UNIT PRICE ANALYSIS (DUPA) Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200mm Ø), L=10 ft.
Amount
109.19 79.70 122.88
311.77 Amount
275.50 31.18
306.68 618.45 309.22 Amount
0.00 309.22 27.83 24.74 43.41 405.21
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,074.95 1,733.00 676.00 23.21
4,507.16 4,739.23 118.48 Amount
0.00 118.48 10.66 9.48 16.63 155.26
DETAILED UNIT PRICE ANALYSIS (DUPA) Removal of Existing PCC Pavement, 0.23m thk. (for Reblocking at intermittent section)
Amount
109.19 122.88
232.07 Amount
2,074.95 1,733.00 676.00 83.69 23.21
4,590.85 4,822.92 160.76 Amount
1.20
1.20 161.96 14.58 12.96 22.74 212.24
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,173.00 1,733.00 676.00 23.21
4,605.21 4,837.28 80.62 Amount
0.00 80.62 7.26 6.45 11.32 105.65
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
1,037.48 768.50 676.00
2,481.98 2,714.05 45.23 Amount
0.00 45.23 4.07 3.62 6.35 59.27
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
1,037.48 768.50 676.00
2,481.98 2,714.05 54.28 Amount
0.00 54.28 4.89 4.34 7.62 71.13
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
1,037.48 768.50 676.00
2,481.98 2,714.05 90.47 Amount
0.00 90.47 8.14 7.24 12.70 118.55
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 184.32
293.51 Amount
2,704.00 1,537.00 173.30 29.35
4,443.65 4,737.16 236.86 Amount
0.00 236.86 21.32 18.95 33.25 310.38
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,299.00 1,733.00 433.25 2,704.00
7,169.25 7,401.32 123.36 Amount
0.00 123.36 11.10 9.87 17.32 161.64
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
102(2)b
Roadway Excavation (Surplus Common) cu.m. 80.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 3 1
1 1 0.30 1 1
2,299.00 1,733.00 1,733.00 1,352.00 1,537.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Bulldozer (155 Hp), D65A-8 b. Payloader (1.50 cu.m.) c. Payloader (1.50 cu.m.) - at disposal area d. Dump Truck (10 cu.m.) e. Backhoe (0.80 cu.m.) (Hauling Distance - within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 80.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
102(3)a
Roadway Excavation (Surplus Soft Rock) cu.m. 56.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 2 1
1 1 0.25 1 1
2,758.80 1,733.00 1,733.00 1,352.00 2,074.95
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Bulldozer w/ Ripper (155 Hp), D65A-8 b. Payloader (1.50 cu.m.) c. Payloader (1.50 cu.m.) at disposal area d. Dump Truck (10 cu.m.) e. Backhoe (0.80 cu.m.) w/ attachment (Hauling Distance - within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 56.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
102(3)b
Roadway Excavation (Surplus Soft Rock) cu.m. 42.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 2
1 1 0.20 1
2,758.80 1,733.00 1,733.00 1,352.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Bulldozer w/ Ripper (155 Hp), D65A-8 b. Payloader (1.50 cu.m.) c. Payloader (1.50 cu.m.) at disposal area d. Dump Truck (10 cu.m.) (Hauling Distance - within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 42.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
102(3)c
Roadway Excavation (Surplus Hard Rock) - Blasting cu.m. 10.00
Designation A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer a. Construction Foreman b. Skilled Laborer c. Laborer a. Construction Foreman b Laborer Sub - Total for A
(Drilling)
(Blasting)
(Disposal)
Name and Capacity
No. of Person
No. of Hours
Hourly Rate
1 2 4 1 1 2 1 2
1 1 1 1 1 1 1 1
109.19 79.70 61.44 109.19 79.70 61.44 109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1 2 1
0.25 0.25 0.05 0.50 1 1
1,537.00 1,733.00 1,733.00 1,352.00 514.31 358.00
Unit
Quantity
Unit Cost
kg. m. pc. kg. pc. m.
0.40 2.00 0.15 0.20 0.30 0.10
280.00 80.00 260.00 75.00 45.00 40.00
B. Equipment a. Backhoe (0.80 cu.m.) b. Payloader (1.50 cu.m.) c. Payloader (1.50 cu.m.) - at disposal area d. Dump Truck (10 cu.m.) e. Pneumatic Drilling Machine f. Compressor (Hauling Distance - within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 10.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Dynamite b. Detonation Cord c. Detonator d. Ammonium Sulfate e. Blasting Cap f. Safety Fuse
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
102(3)d
Roadway Excavation (Surplus Hard Rock) - Blasting (Tunnel Excavation) cu.m. 6.50
Designation A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer a. Construction Foreman b. Skilled Laborer c. Laborer a. Construction Foreman b Laborer Sub - Total for A
(Drilling)
(Blasting)
(Disposal)
Name and Capacity
No. of Person
No. of Hours
Hourly Rate
1 1 2 1 1 2 1 1
4 4 4 1.50 1.50 1.50 1 1
109.19 79.70 61.44 109.19 79.70 61.44 109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 2 1 1 1
0.50 0.30 4 4 0.15 0.03
1,537.00 1,352.00 514.31 358.00 1,733.00 1,733.00
Unit
Quantity
Unit Cost
kg. m. pc. kg. pc. m.
3.10 2.30 3.10 1.50 0.50 0.15
280.00 80.00 260.00 75.00 45.00 40.00
B. Equipment a. Backhoe (0.80 cu.m.) b. Dump Truck (10 cu.m.) c. Pneumatic Drilling Machine d. Compressor e. Payloader (1.50 cu.m.) f. Payloader (1.50 cu.m.) - at disposal area (Hauling Distance - within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 6.50 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Dynamite b. Detonation Cord c. Detonator d. Ammonium Sulfate e. Blasting Cap f. Safety Fuse
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
102(4)
Roadway Excavation (Unclassified) cu.m. 50.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
a. Bulldozer (155 Hp), D65A-8
1
1
2,299.00
b. Payloader (1.50 cu.m.) c. Payloader (1.50 cu.m.) - at disposal area d. Dump Truck (10 cu.m.)
1 1 2
1 0.20 1
1,733.00 1,733.00 1,352.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment
(Hauling Distance - within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
103(1)a
Structure Excavation (Common Soil) cu.m. 20.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
a. Dump Truck (10 cu.m.)
2
1
1,352.00
b. Backhoe (0.80 cu.m.) Minor Tools (10% of Labor)
1
1
1,537.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 20.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
103(1)b
Structure Excavation (Soft Rock) cu.m. 14.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Dump Truck (10 cu.m.)
2
1
b. Backhoe (0.80 cu.m.)
1
0.50
1,352.00 1,537.00
c. Backhoe w/ Breaker (0.80 cu.m.) Minor Tools (10% of Labor)
1
0.50
2,074.95
Unit
Quantity
Unit Cost
Sub - Total for B C. Total (A + B) D. Output per hour = 14.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
103(1)c
Structure Excavation (Solid Rock) cu.m. 4.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Dump Truck (10 cu.m.)
1
1
1,352.00
b. Backhoe (0.80 cu.m.) c. Backhoe w/ Breaker (0.80 cu.m.) Minor Tools (10% of Labor)
1 1
0.50 0.50
1,537.00 2,074.95
Unit
Quantity
Unit Cost
Sub - Total for B C. Total (A + B) D. Output per hour = 4.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Sub - Total for F G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) I. Contractor's Profit (CP)
9% of G 8% of G
J. Value Added Tax (VAT) K. Total Unit Cost
12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
103(2)a
Bridge Excavation (Common Soil) cu.m. 20.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
b. Backhoe (0.80 cu.m.)
1
1
b. Dump Truck (10 cu.m.)
2
1
1,537.00 1,352.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 20.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
103(2)b
Bridge Excavation (Soft Rock) cu.m. 14.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Backhoe (0.80 cu.m.)
1
0.50
b. Backhoe w/ Breaker (0.80 cu.m.)
1
0.50
1,537.00 2,074.95
c. Dump Truck (10 cu.m.) Minor Tools (10% of Labor)
2
1
1,352.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 14.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
103(2)c
Bridge Excavation (Solid Rock) cu.m. 4.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Backhoe (0.80 cu.m.)
1
0.50
b. Backhoe w/ Breaker (0.80 cu.m.)
1
0.50
1,537.00 2,074.95
c. Dump Truck (10 cu.m.) Minor Tools (10% of Labor)
1
1
1,352.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 4.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
103(3)
Foundation Fill cu.m. 1.25
Designation
No. of Person
No. of Hours
Hourly Rate
1 4
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Plate Compactor (5 Hp)
1
1
b. Water Truck (1000 gal.)
1
0.01
123.00 1,065.00
Unit
Quantity
Unit Cost
cu.m.
1.15
465.00
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Filling Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
103(4)
Excavation ordered below Plan Elevation cu.m. 20.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
2 1
1 1
1,352.00 1,537.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Dump Truck (10 cu.m.) b. Backhoe (0.80 cu.m.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 20.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
103(5)a
Shoring l.s. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
A. Labor Note: *) The component quantity of items of work involved such as item 404/405/509 shall be based on the actual design of the shoring. **) Costing of this item shall be based on the standard Detailed Unit Price Analysis (DUPA) of item 404/405/509 as processed component pay item.
Sub - Total for A Name and Capacity
No of Units
No. of Hours
Unit
Quantity
kg. cu.m. l.m.
* * *
Hourly Rate
B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1.00 l.s. E. Direct Unit Cost (C ÷ D) Name and Specification
Direct
Unit Cost
F. Materials/Processed Component Pay Item a. 404 - Reinforcing Steel Bar b. 405 - Structural Concrete c. 509 - Steel Sheet Pile
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
103(5)b
Cribbing/Cofferdamming l.s. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
135 135 135
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1 1
135 135 33.75 33.75 135
1,729.00 1,800.00 391.00 45.45 266.25
Unit
Quantity
Unit Cost
kg. kg.
51,840.00 7,323.77
48.00 48.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Crawler Crane (36 - 40 T) b. Vibro Hammer (Hydraulic Operated) c. Welding Machine d. Cutting Outfit e. Water Pump, 100mm suction diameter
Sub - Total for B C. Total (A + B) D. Output = 1.00 l.s. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Steel Sheet Pile b. Walling, Bracing, Diagonal, etc. Miscellaneous (1% of Materials)
Note: a.) The assume dimesion of area to be provided with cofferdam is 12m x 12m square with Steel Sheet Piles depth of 9m at 48 kg./m. b.) The quantity of component materials requirement may vary depending on the actual design of Cribbing/Cofferdamming.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
103(6)
Pipe Culvert and Drain Excavation cu.m. 20.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
2 1
1 1
1,352.00 1,537.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Dump Truck (10 cu.m.) b. Backhoe (0.80 cu.m.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 20.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
104(1)a
Embankment (from Borrow) cu.m. 50.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.25
2,173.00 1,507.00 1,065.00
Unit
Quantity
Unit Cost
cu.m.
1.25
400.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Motorized Road Grader, G710A b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Common Borrow (w/ 25% Shrinkage Factor)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
104(1)b
Embankment from Roadway Excavation cu.m. 50.00
Designation A. Labor For Excavation Work: a. Construction Foreman b. Laborer Spreading and Compaction: a. Construction Foreman b. Laborer
No. of Person
No. of Hours
Hourly Rate
1 2
0.83 0.83
109.19 61.44
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 2
0.83 0.83 0.83
2,299.00 1,733.00 1,352.00
1 1 1
1 1 0.25
2,173.00 1,507.00 1,065.00
Unit
Quantity
Unit Cost
Sub - Total for A Name and Capacity B. Equipment For Excavation Work: a. Bulldozer (155 Hp), D65A-8 b. Payloader (1.50 cu.m.) c. Dump Truck (10 cu.m.) Spreading and Compaction: a. Motorized Road Grader, G710A b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
104(2)
Selected Borrow for topping , case 1 cu.m. 50.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.25
2,173.00 1,507.00 1,065.00
Unit
Quantity
Unit Cost
cu.m.
1.25
420.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Motorized Road Grader, G710A b. Vibratory Roller (10 m.t.) c. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Selected Borrow (w/ 25% Shrinkage Factor)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
104(3)
Selected Borrow for topping , case 2 cu.m. 50.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.25
2,173.00 1,507.00 1,065.00
Unit
Quantity
Unit Cost
cu.m.
1.25
420.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Motorized Road Grader, G710A b. Vibratory Roller (10 m.t.) c. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Selected Borrow (w/ 25% Shrinkage Factor)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
104(4)
Earth Berm cu.m. 1.25
Designation
No. of Person
No. of Hours
Hourly Rate
1 4
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 0.01
123.00 1,065.00
Unit
Quantity
Unit Cost
cu.m.
1.25
420.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Plate Compactor (5 Hp) b. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Filling Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
105(1)
Subgrade Preparation (Common Material) sq.m. 300.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.25
2,173.00 1,507.00 1,065.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Motorized Road Grader, G710A b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 300.00 sq.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
105(2)
Subgrade Preparation (Existing Pavement) sq.m. 300.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.25
2,173.00 1,507.00 1,065.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Motorized Road Grader, G710A b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 300.00 sq.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
105(3)
Subgrade Preparation (Unsuitable Material) sq.m. 300.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.25
2,173.00 1,507.00 1,065.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Motorized Road Grader, G710A b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 300.00 sq.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,299.00 1,733.00 519.90 4,056.00 1,537.00
10,144.90 10,376.97 129.71 Amount
0.00 129.71 11.67 10.38 18.21 169.97
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,758.80 1,733.00 433.25 2,704.00 2,074.95
9,704.00 9,936.07 177.43 Amount
0.00 177.43 15.97 14.19 24.91 232.50
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,758.80 1,733.00 346.60 2,704.00
7,542.40 7,774.47 185.11 Amount
0.00 185.11 16.66 14.81 25.99 242.56
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount 109.19 159.4 245.76 109.19 79.7 122.88 109.19 122.88 1,058.19 Amount
384.25 433.25 86.65 676.00 1,028.62 358.00
2,966.77 4,024.96 402.50 Amount
112.00 160.00 39.00 15.00 13.50 4.00
343.50 746.00 67.14 59.68 104.74 977.55
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount 436.76 318.8 491.52 163.785 119.55 184.32 109.19 61.44 1,885.37 Amount
768.50 405.60 4,114.48 1,432.00 259.95 51.99
7,032.52 8,917.89 1,371.98 Amount
868.00 184.00 806.00 112.50 22.50 6.00
1,999.00 3,370.98 303.39 269.68 473.29 4,417.34
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,299.00 1,733.00 346.60 2,704.00
7,082.60 7,314.67 146.29 Amount
0.00 146.29 13.17 11.70 20.54
191.70
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 184.32
293.51 Amount
2,704.00 1,537.00 29.35
4,270.35 4,563.86 228.19 Amount
0.00 228.19 20.54 18.26 32.04
299.02
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 184.32
293.51 Amount
2,704.00 768.50 1,037.48 29.35
4,539.33 4,832.84 345.20 Amount
0.00 345.20 31.07 27.62 48.47
452.35
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 184.32
293.51 Amount
1,352.00 768.50 1,037.48 29.35
3,187.33 3,480.84 870.21 Amount
0.00 870.21 78.32 69.62
122.18 1,140.32
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 79.70 122.88
311.77 Amount
1,537.00 2,704.00 31.18
4,272.18 4,583.95 229.20 Amount
0.00 229.20 20.63 18.34 32.18
300.34
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 79.70 122.88
311.77 Amount
768.50 1,037.48 2,704.00 31.18
4,541.15 4,852.92 346.64 Amount
0.00 346.64 31.20 27.73 48.67
454.23
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 79.70 122.88
311.77 Amount
768.50 1,037.48 1,352.00 31.18
3,189.15 3,500.92 875.23 Amount
0.00 875.23 78.77 70.02 122.88
1,146.90
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 245.76
354.95 Amount
123.00 10.65 35.50
169.15 524.10 419.28 Amount
534.75
534.75 954.03 85.86 76.32 133.95
1,250.16
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 184.32
293.51 Amount
2,704.00 1,537.00 29.35
4,270.35 4,563.86 228.19 Amount
0.00 228.19 20.54 18.26 32.04
299.02
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
y of items of work involved such as item 404/405/509 shall be based on the horing. ll be based on the standard Detailed Unit Price Analysis (DUPA) of item 404/405/509 ent pay item.
Amount
Direct Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
14,740.65 21,519.00 33,177.60
69,437.25 Amount
233,415.00 243,000.00 13,196.25 1,533.94 35,943.75
527,088.94 596,526.19 596,526.19 Amount
2,488,320.00 351,540.96 28,398.61
2,868,259.57 3,464,785.76 311,830.72 277,182.86 486,455.92 4,540,255.26
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 184.32
293.51 Amount
2,704.00 1,537.00 29.35
4,270.35 4,563.86 228.19 Amount
0.00 228.19 20.54 18.26 32.04 299.02
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,173.00 1,507.00 266.25
3,946.25 4,178.32 83.57 Amount
500.00
500.00 583.57 52.52 46.69 81.93 764.71
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
90.63 101.99
109.19 122.88 424.69 Amount
1,908.17 1,438.39 2,244.32
2,173.00 1,507.00 266.25
9,537.13 9,961.82 199.24 Amount
0.00 199.24 17.93 15.94 27.97 261.08
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,173.00 1,507.00 266.25
3,946.25 4,178.32 83.57 Amount
525.00
525.00 608.57 54.77 48.69 85.44 797.47
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,173.00 1,507.00 266.25
3,946.25 4,178.32 83.57 Amount
525.00
525.00 608.57 54.77 48.69 85.44 797.47
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 245.76
354.95 Amount
123.00 10.65 35.50
169.15 524.10 419.28 Amount
525.00
525.00 944.28 84.98 75.54 132.58 1,237.38
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,173.00 1,507.00 266.25
3,946.25 4,178.32 13.93 Amount
0.00 13.93 1.25 1.11 1.96 18.25
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,173.00 1,507.00 266.25
3,946.25 4,178.32 13.93 Amount
0.00 13.93 1.25 1.11 1.96 18.25
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,173.00 1,507.00 266.25
3,946.25 4,178.32 13.93 Amount
0.00 13.93 1.25 1.11 1.96 18.25
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
200
Aggregate Subbase Course cu.m 50.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.25
2,173.00 1,507.00 1,065.00
Unit
Quantity
Unit Cost
cu.m.
1.15
580.00
A. Labor a. Construction Foreman b. Laborers
Sub - Total for A Name and Capacity B. Equipment a. Motorized Road Grader, G710A b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Aggregate Subbase Course (w/ 15% Shrinkage Factor)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
200(1)
Aggregate Subbase Course (for Intermittent Reblocking) cu.m 40.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
a. Motorized Road Grader, G710A
1
1
2,173.00
b. Vibratory Roller (10 m.t.), SP56 c. Plate Compactor (5 Hp) d. Water Truck (1000 gal.)
1 1 1
1 0.25 0.25
1,507.00 123.00 1,065.00
Unit
Quantity
Unit Cost
cu.m.
1.15
580.00
A. Labor a. Construction Foreman b. Laborers
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 40.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Aggregate Subbase Course (w/ 15% Shrinkage Factor)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
201
Aggregate Base Course cu.m 50.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
a. Motorized Road Grader, G710A
1
1
2,173.00
b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.)
1 1
1 0.25
1,507.00 1,065.00
Unit
Quantity
Unit Cost
cu.m.
1.15
650.00
A. Labor a. Construction Foreman b. Laborers
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Aggregate Base Course (w/ 15% Shrinkage Factor)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
201(1)
Aggregate Base Course (for Reblocking) cu.m 40.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1
1 1 0.25 0.25
2,173.00 1,507.00 123.00 1,065.00
Unit
Quantity
Unit Cost
cu.m.
1.15
650.00
A. Labor a. Construction Foreman b. Laborers
Sub - Total for A Name and Capacity B. Equipment a. Motorized Road Grader, G710A b. Vibratory Roller (10 m.t.), SP56 c. Plate Compactor (5 Hp) d. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 40.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Aggregate Base Course (w/ 15% Shrinkage Factor)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
202
Crushed Aggregate Base Course cu.m 50.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.25
2,173.00 1,507.00 1,065.00
Unit
Quantity
Unit Cost
cu.m.
1.15
700.00
A. Labor a. Construction Foreman b. Laborers
Sub - Total for A Name and Capacity B. Equipment a. Motorized Road Grader, G710A b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Crushed Aggregate Base Course (w/ 15% Shrinkage Factor)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,173.00 1,507.00 266.25
3,946.25 4,178.32 83.57 Amount
667.00
667.00 750.57 67.55 60.05 105.38 983.54
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,173.00 1,507.00 30.75 266.25
3,977.00 4,209.07 105.23 Amount
667.00
667.00 772.23 69.50 61.78 108.42
1,011.93
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,173.00 1,507.00 266.25
3,946.25 4,178.32 83.57 Amount
747.50
747.50 831.07 74.80 66.49 116.68
1,089.03
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,173.00 1,507.00 30.75 266.25
3,977.00 4,209.07 105.23 Amount
747.50
747.50 852.73 76.75 68.22 119.72
1,117.41
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 122.88
232.07 Amount
2,173.00 1,507.00 266.25
3,946.25 4,178.32 83.57 Amount
805.00
805.00 888.57 79.97 71.09 124.75
1,164.38
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
203
Lime Stabilized Road Mix Base Course cu.m. 15.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 10
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.25
2,173.00 1,507.00 1,065.00
Unit
Quantity
Unit Cost
bag cu.m.
2.80 1.15
180.00 650.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Motorized Road Grader (140 Hp) b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 15.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Hydrated Lime, Type N (Normal) b. Aggregate Base Course
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
204
Portland Cement Stabilized Road Mix Base Course cu.m. 15.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 10
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
a. Motorized Road Grader (140 Hp)
1
1
2,173.00
b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.)
1 1
1 0.25
1,507.00 1,065.00
Unit
Quantity
Unit Cost
bag cu.m.
3 1.15
220.00 650.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 15.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Aggregate Base Course
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
205
Asphalt Stabilized Road Mix Base Course cu.m. 15.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 10
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
a. Motorized Road Grader (140 Hp)
1
1
2,173.00
b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.) d. Asphalt Distributor, 10 ft. wide (5 tons)
1 1 1
1 0.25 1
1,507.00 1,065.00 936.00
Unit
Quantity
Unit Cost
m.t. cu.m.
0.07 1.15
44,000.00 650.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 15.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Emulsified Asphalt SS-1 b. Aggregate Base Course
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
206
Portland Cement Treated Plant Mix Base Course cu.m. 15.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 3 1 1 1 1 1
0.50 0.50 0.50 0.50 0.50 0.25 0.10
1,208.03 1,352.00 2,173.00 1,507.00 1,733.00 1,065.00 936.00
Unit
Quantity
Unit Cost
bag cu.m. m.t.
3 1.15 0.0075
220.00 650.00 40,300.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Batching Plant (30 cu.m.) b. Dump Truck (10 cu.m.) c. Motorized Road Grader, G710A d. Vibratory Roller (10 m.t.), SP56 e. Payloader (1.50 cu.m.), LX80-2C f. Water Truck (1000 gal.) g. Asphalt Distributor, 10 ft. wide (5 tons)
Sub - Total for B C. Total (A + B) D. Output per hour = 15.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Aggregate Base Course c. MC 70 Cut-back Asphalt
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 614.40
723.59 Amount
2,173.00 1,507.00 266.25
3,946.25 4,669.84 311.32 Amount
504.00 747.50
1,251.50 1,562.82 140.65 125.03 219.42 2,047.92
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 614.40
723.59 Amount
2,173.00 1,507.00 266.25
3,946.25 4,669.84 311.32 Amount
660.00 747.50
1,407.50 1,718.82 154.69 137.51 241.32
2,252.35
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 614.40
723.59 Amount
2,173.00 1,507.00 266.25 936.00
4,882.25 5,605.84 373.72 Amount
3,080.00 747.50
3,827.50 4,201.22 378.11 336.10 589.85
5,505.28
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
604.02 2,028.00 1,086.50 753.50 866.50 266.25 93.60
5,698.37 6,212.72 414.18 Amount
660.00 747.50 302.25
1,709.75 2,123.93 191.15 169.91 298.20
2,783.20
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
300(1)
Gravel Surface Course (Uncrushed) cu.m 50.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
a. Motorized Road Grader, G710A
1
1
2,173.00
b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.), All Make
1 1
1 0.25
1,507.00 1,065.00
Unit
Quantity
Unit Cost
cu.m.
1.15
700.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Uncrushed Aggregate Surface Course (w/ 15% Shrinkage Factor)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
1762
K. Total Unit Cost
(G + H + I + J)
5485
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
300(2)
Crushed Aggregate Surface Course cu.m 50.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
a. Motorized Road Grader, G710A
1
1
2,173.00
b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.), All Make
1 1
1 0.25
1,507.00 1,065.00
Name and Specification
Unit
Quantity
Unit Cost
a. Crushed Aggregate Surface Course (w/ 15% Shrinkage Factor)
cu.m.
1.15
750.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00 cu.m. E. Direct Unit Cost (C ÷ D)
F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
1782
K. Total Unit Cost
(G + H + I + J)
5485
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
301(1)
Bituminous Prime Coat (MC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
a. Asphalt Distributor, 10 ft. wide (5 tons)
1
1
936.00
b. Power Broom (20 m. wide)
1
1
130.54
Unit
Quantity
Unit Cost
m.t.
1.05
40,300.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 0.30 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. MC 70 Cut-back Asphalt (w/ 5% wastage)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
1802
K. Total Unit Cost
(G + H + I + J)
5485
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
301(2)
Bituminous Prime Coat (RC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
a. Asphalt Distributor, 10 ft. wide (5 tons)
1
1
936.00
b. Power Broom (20 m. wide)
1
1
130.54
Unit
Quantity
Unit Cost
m.t.
1.05
41,575.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 0.30 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. RC 70 Cut-back Asphalt (w/ 5% wastage)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
1822
K. Total Unit Cost
(G + H + I + J)
5485
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
302(1)
Bituminous Tack Coat (RC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
a. Asphalt Distributor, 10 ft. wide (5 tons)
1
1
936.00
b. Power Broom (20 m. wide)
1
1
130.54
Unit
Quantity
Unit Cost
m.t.
1.05
41,575.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 0.30 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. RC 70 Cut-back Asphalt (w/ 5% wastage)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
1842
K. Total Unit Cost
(G + H + I + J)
5485
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
302(2)
Bituminous Tack Coat (Emulsified Asphalt) m.t. 0.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 1
936.00 130.54
Unit
Quantity
Unit Cost
m.t.
1.05
44,000.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.30 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Emulsified Asphalt SS-1 (w/ 5% wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
1862
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
303(1)
Bituminous Seal Coat (Cover Aggregate) m.t. 16.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 20
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 0.25
1,652.00 1,065.00
Unit
Quantity
Unit Cost
m.t.
1.15
406.25
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Tandem Steel Roller (10.1 m.t.), CC421 b. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 16.00 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cover Aggregate (w/ 15% Shrinkage Factor) Note: 1.60 m.t./cu.m. using unit wt. of 1,600 kg./m³
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
5485
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
303(2)
Bituminous Seal Coat (MC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 1
936.00 130.54
Unit
Quantity
Unit Cost
m.t.
1.05
40,300.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.30 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. MC Cut-back Asphalt (w/ 5% Wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
1882
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
303(3)
Bituminous Seal Coat (RC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 1
936.00 130.54
Unit
Quantity
Unit Cost
m.t.
1.05
41,575.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.30 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. RC 70 Cut-back Asphalt (w/ 5% Wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
5485
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
303(4)
Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-150) m.t. 0.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 1
936.00 130.54
Unit
Quantity
Unit Cost
m.t.
1.05
50,775.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.30 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Asphalt Cement Penetration Grade 120-150 (w/ 5% Wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
1902
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
304(1)
Bituminous Surface Treatment (Aggregate Grading) m.t. 16.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 20
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 0.25
1,507.00 1,065.00
Unit
Quantity
Unit Cost
m.t.
1.15
406.25
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Vibratory Roller (10 m.t.), SP56 b. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 16.00 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Aggregates (w/ 15% Shrinkage Factor)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
5485
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
304(2)
Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150) m.t. 0.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 1
936.00 130.54
Unit
Quantity
Unit Cost
m.t.
1.05
50,775.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.30 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Asphalt Cement Penetration Grade 120-150 (w/ 5% Wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
1922
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
304(3)
Bituminous Surface Treatment (MC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 1
936.00 130.54
Unit
Quantity
Unit Cost
m.t.
1.05
40,300.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.30 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. MC Cut-back Asphalt (w/ 5% Wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
5485
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
304(4)
Bituminous Surface Treatment (RC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 1
936.00 130.54
Unit
Quantity
Unit Cost
m.t.
1.05
41,575.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.30 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. RC 70 Cut-back Asphalt (w/ 5% Wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
1942
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
304(5)
Bituminous Surface Treatment (Emulsified Asphalt) m.t. 0.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 1
936.00 130.54
Unit
Quantity
Unit Cost
m.t.
1.05
44,000.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.30 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Emulsified Asphalt SS-1 (w/ 5% wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
5485
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
305(1)
Bituminous Penetration Macadam Pavement (Aggregates) m.t. 16.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 20
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 0.25
1,507.00 1,065.00
Unit
Quantity
Unit Cost
m.t.
1.15
406.25
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Vibratory Roller (10 m.t.), SP56 b. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 16.00 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Aggregates (w/ 15% Shrinkage Factor)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
1962
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
305(2)
Bituminous Penetration Macadam Pavement (Asphalt Cement) m.t. 0.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 1
936.00 130.54
Unit
Quantity
Unit Cost
m.t.
1.05
50,775.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.30 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Asphalt Cement (w/ 5% Wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
5485
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
305(3)
Bituminous Penetration Macadam Pavement (RC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 1
936.00 130.54
Unit
Quantity
Unit Cost
m.t.
1.05
41,575.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.30 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. RC 70 Cut-back Asphalt (w/ 5% Wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
1982
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
305(4)
Bituminous Penetration Macadam Pavement (Emulsified Asphalt) m.t. 0.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 3
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 1
936.00 130.54
Unit
Quantity
Unit Cost
m.t.
1.05
44,000.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.30 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Emulsified Asphalt SS-1 (w/ 5% wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
5485
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
306(a)
Bituminous Road Mix Surface Course m.t. 12.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 3
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1 1
1 1 1 1 0.25
2,933.55 1,652.00 553.00 936.00 1,065.00
Unit
Quantity
Unit Cost
m.t. m.t. bag
1.15 0.07 0.30
406.25 40,300.00 180.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Road Grader w/ Scarifier, G710A b. Tandem Steel Roller (10.1 m.t.), CC421 c. Pneumatic Tire Roller (10 m.t.) d. Asphalt Distributor, 10 ft. wide (5 tons) e. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 12.00 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Crushed Gravel b. MC Cut-back Asphalt (7%) c. Hydrated Lime (0.75%)
0.0575(2.335)(1.05) = 0.141 0.0075(35.29) = 0.26, say 0.30
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
2002
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
306(b)
Bituminous Road Mix Surface Course m.t. 12.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 3
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1 1
1 1 1 1 0.25
2,933.55 1,652.00 553.00 936.00 1,065.00
Unit
Quantity
Unit Cost
m.t. m.t. bag
1.15 0.10 0.30
406.25 44,000.00 180.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Road Grader w/ Scarifier, G710A b. Tandem Steel Roller (10.1 m.t.), CC421 c. Pneumatic Tire Roller (10 m.t.) d. Asphalt Distributor, 10 ft. wide (5 tons) e. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 12.00 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Crushed Gravel b. Emulsified Asphalt (10%) c. Hydrated Lime (0.75%)
0.08(2.335)(1.05) = 0.196 0.0075(35.29) = 0.26, say 0.30
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
5485
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
306(1)
Aggregates for Bituminous Road Mix Surface Course m.t. 12.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 3
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1
1 1 1 0.25
2,933.55 1,652.00 553.00 1,065.00
Unit
Quantity
Unit Cost
m.t.
1.15
406.25
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Road Grader w/ Scarifier, G710A b. Tandem Steel Roller (10.1 m.t.), CC421 c. Pneumatic Tire Roller (10 m.t.) d. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 12.00 m.t. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Crushed Gravel
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
2022
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
306(2)
Bituminous Material for Bituminous Road Mix Surface Course m.t. 1.00
Designation
No. of Person
No. of Hours
1 1 3
1 1 1
No of Units
No. of Hours
1
1.00
Unit
Quantity
m.t.
1.05
A. Labor 109.19 122.88
a. Construction Foreman b. Skilled Laborer c. Laborer
232.07
Sub - Total for A
Amount
Name and Capacity B. Equipment
2,173.00
a. Asphalt Distributor, 10 ft. wide (5 tons)
1,507.00 266.25
3,946.25 4,178.32 83.57
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 m.t. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
805.00
805.00 888.57 79.97 71.09 124.75
a. MC Cut-back Asphalt
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
5485
9% 8% 12%
1,164.38
K. Total Unit Cost
2042
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
307
Bituminous Plant Mix Surface Course-General (50mm thk.) sq.m. 171.30
Designation
No. of Person
No. of Hours
1 6 12
1 1 1
No of Units
No. of Hours
A. Labor 109.19 122.88
a. Construction Foreman b. Skilled Laborer c. Laborer
232.07
Sub - Total for A
Amount
Name and Capacity B. Equipment
2,173.00
a. Asphalt Paver (80 Hp), NF220BIIVDM
1
1
1,507.00 266.25
b. Pneumatic Tire Roller (10 m.t.) c. Tandem Steel Roller (10.1 m.t.), CC421 d. Dump Truck (10 cu.m.) e. Asphalt Batch Plant ( 60-80 TPH) f. Water Truck (1000 gal.) g. Payloader (1.50 cu.m.), LX80-2C Minor Tools (10% of Labor)
1 1 2 1 1 1
1 1 1 1 1 1
Unit
Quantity
m.t cu.m. bag
0.00981 0.0488 0.13
3,946.25 4,178.32 83.57
Sub - Total for B C. Total (A + B) D. Output per hour = 171.30 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
862.50
862.50 946.07 85.15 75.69 132.83
a. Bituminous Material (8%) b. Aggregates (93%) c. Mineral Filler (7%) (w/ 5% wastage)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
5485
9% 8% 12%
1,239.73
K. Total Unit Cost
2062
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
308(a)
Cold Asphalt Plant Mix (50mm thk.) sq.m. 171.30
Designation
No. of Person
No. of Hours
1 6 12
1 1 1
No of Units
No. of Hours
A. Labor 109.19 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
293.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00
a. Asphalt Paver (80 Hp), NF220BIIVDM
1
1
130.54
b. Pneumatic Tire Roller (10 m.t.) c. Tandem Steel Roller (10.1 m.t.), CC421 d. Dump Truck (10 cu.m.) e. Asphalt Batch Plant ( 60-80 TPH) f. Water Truck (1000 gal.) g. Payloader (1.50 cu.m.), LX80-2C Minor Tools (10% of Labor)
1 1 2 1 1 1
1 1 1 1 1 1
Unit
Quantity
m.t cu.m. bag
0.01226 0.0488 0.13
1,066.54 1,360.05 4,533.50
Sub - Total for B C. Total (A + B) D. Output per hour = 171.30 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
42,315.00
42,315.00 46,848.50 4,216.37 3,747.88 6,577.53
a. Emulsified Asphalt (10%) b. Aggregates (93%) c. Mineral Filler (7%) (w/ 5% wastage)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
5485
9% 8% 12%
61,390.27
K. Total Unit Cost
2082
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
308(b)
Cold Asphalt Plant Mix (50mm thk.) sq.m. 171.30
Designation
No. of Person
No. of Hours
1 6 12
1 1 1
No of Units
No. of Hours
A. Labor 109.19 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
293.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00
a. Asphalt Paver (80 Hp), NF220BIIVDM
1
1
130.54
b. Pneumatic Tire Roller (10 m.t.) c. Tandem Steel Roller (10.1 m.t.), CC421 d. Dump Truck (10 cu.m.) e. Asphalt Batch Plant ( 60-80 TPH) f. Water Truck (1000 gal.) g. Payloader (1.50 cu.m.), LX80-2C Minor Tools (10% of Labor)
1 1 2 1 1 1
1 1 1 1 1 1
Unit
Quantity
m.t cu.m. bag
0.00858 0.0488 0.13
1,066.54 1,360.05 4,533.50
Sub - Total for B C. Total (A + B) D. Output per hour = 171.30 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
43,653.75
43,653.75 48,187.25 4,336.85 3,854.98 6,765.49
a. MC - 70 Cut-back Asphalt (7%) b. Aggregates (93%) c. Mineral Filler (7%) (w/ 5% wastage)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
5485
9% 8% 12%
63,144.57
K. Total Unit Cost
2102
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
309
Bituminous Plant Mix (Stockpile Maintenance Mixture) sq.m. 171.30
Designation
No. of Person
No. of Hours
1 6 12
1 1 1
No of Units
No. of Hours
A. Labor 109.19 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
293.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00
a. Dump Truck (10 cu.m.)
2
1
130.54
b. Asphalt Batch Plant ( 60-80 TPH) c. Water Truck (1000 gal.) d. Payloader (1.50 cu.m.), LX80-2C Minor Tools (10% of Labor)
1 1 1
1 1 1
Unit
Quantity
m.t cu.m. bag
0.00981 0.0488 0.13
1,066.54 1,360.05 4,533.50
Sub - Total for B C. Total (A + B) D. Output per hour = 171.30 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
43,653.75
43,653.75 48,187.25 4,336.85 3,854.98 6,765.49
a. MC - 70 Cut-back Asphalt (10%) b. Aggregates (93%) c. Mineral Filler (7%) (w/ 5% wastage)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
5485
9% 8% 12%
63,144.57
K. Total Unit Cost
2122
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
310(a.1)
Bituminous Concrete Surface Course (30mm thk.) sq.m. 285.51
Designation
No. of Person
No. of Hours
1 4 8
1 1 1
No of Units
No. of Hours
1 1 1 1
1 1 1 1
Unit
Quantity
m.t.
0.074
A. Labor 109.19 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
293.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00 130.54
1,066.54 1,360.05 4,533.50
a. Asphalt Paver (80 Hp) b. Pneumatic Tire Roller (10 m.t.) c. Tandem Steel Roller (10.1 m.t.), CC421 d. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 285.51 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
46,200.00
46,200.00 50,733.50 4,566.02 4,058.68 7,122.98 66,481.18
a. Bituminous Concrete Surface Course thickness = 30mm (w/ 5% wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
5485
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
310(a.2)
Bituminous Concrete Surface Course (40mm thk.) sq.m. 214.13
Designation
No. of Person
No. of Hours
1 4 8
1 1 1
No of Units
No. of Hours
1 1 1 1
1 1 1 1
Unit
Quantity
m.t.
0.098
A. Labor 109.19 1,228.80
a. Construction Foreman b. Skilled Laborer c. Laborer
1,337.99
Sub - Total for A
Amount
Name and Capacity B. Equipment
1,652.00 266.25
1,918.25 3,256.24 203.52
a. Asphalt Paver (80 Hp) b. Pneumatic Tire Roller (10 m.t.) c. Tandem Steel Roller (10.1 m.t.), CC421 d. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 214.13 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
467.19
467.19 670.70 60.36 53.66 94.17 878.89
a. Bituminous Concrete Surface Course thickness = 40mm (w/ 5% wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
2142
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
310(a.3)
Bituminous Concrete Surface Course (50mm thk.) sq.m. 171.30
Designation
No. of Person
No. of Hours
1 4 8
1 1 1
No of Units
No. of Hours
1 1 1 1
1 1 1 1
Unit
Quantity
m.t.
0.123
A. Labor 109.19 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
293.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00 130.54
1,066.54 1,360.05 4,533.50
a. Asphalt Paver (80 Hp) b. Pneumatic Tire Roller (10 m.t.) c. Tandem Steel Roller (10.1 m.t.), CC421 d. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 171.30 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
42,315.00
42,315.00 46,848.50 4,216.37 3,747.88 6,577.53 61,390.27
a. Bituminous Concrete Surface Course thickness = 50mm (w/ 5% wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
5485
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
310(b.1)
Bituminous Concrete Surface Course (30mm thk.) sq.m. 285.51
Designation
No. of Person
No. of Hours
1 6 12
1 1 1
No of Units
No. of Hours
1 1 1 2 1 1 1
1 1 1 1 1 1 1
Unit
Quantity
m.t cu.m. bag
0.00588 0.0293 0.078
A. Labor 109.19 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
293.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00 130.54
1,066.54 1,360.05 4,533.50
a. Asphalt Paver (80 Hp), NF220BIIVDM b. Pneumatic Tire Roller (10 m.t.) c. Tandem Steel Roller (10.1 m.t.), CC421 d. Dump Truck (10 cu.m.) e. Asphalt Batch Plant ( 60-80 TPH) f. Water Truck (1000 gal.) g. Payloader (1.50 cu.m.), LX80-2C Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 285.51 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
43,653.75
43,653.75 48,187.25 4,336.85 3,854.98 6,765.49 63,144.57
a. Asphalt Cement (8%) b. Aggregates (93%) c. Mineral Filler (7%) (w/ 5% wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
2162
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
310(b.2)
Bituminous Concrete Surface Course (40mm thk.) sq.m. 214.13
Designation
No. of Person
No. of Hours
1 6 12
1 1 1
No of Units
No. of Hours
1 1 1 2 1 1 1
1 1 1 1 1 1 1
Unit
Quantity
m.t cu.m. bag
0.00785 0.0391 0.104
A. Labor 109.19 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
293.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00 130.54
1,066.54 1,360.05 4,533.50
a. Asphalt Paver (80 Hp), NF220BIIVDM b. Pneumatic Tire Roller (10 m.t.) c. Tandem Steel Roller (10.1 m.t.), CC421 d. Dump Truck (10 cu.m.) e. Asphalt Batch Plant ( 60-80 TPH) f. Water Truck (1000 gal.) g. Payloader (1.50 cu.m.), LX80-2C Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 214.13 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
53,313.75
53,313.75 57,847.25 5,206.25 4,627.78 8,121.75 75,803.04
a. Asphalt Cement (8%) b. Aggregates (93%) c. Mineral Filler (7%) (w/ 5% wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
5485
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
310(b.3)
Bituminous Concrete Surface Course (50mm thk.) sq.m. 171.30
Designation
No. of Person
No. of Hours
1 6 12
1 1 1
No of Units
No. of Hours
1 1 1 2 1 1 1
1 1 1 1 1 1 1
Unit
Quantity
m.t cu.m. bag
0.00981 0.0488 0.13
A. Labor 109.19 1,228.80
a. Construction Foreman b. Skilled Laborer c. Laborer
1,337.99
Sub - Total for A
Amount
Name and Capacity B. Equipment
1,507.00 266.25
1,773.25 3,111.24 194.45
a. Asphalt Paver (80 Hp), NF220BIIVDM b. Pneumatic Tire Roller (10 m.t.) c. Tandem Steel Roller (10.1 m.t.), CC421 d. Dump Truck (10 cu.m.) e. Asphalt Batch Plant ( 60-80 TPH) f. Water Truck (1000 gal.) g. Payloader (1.50 cu.m.), LX80-2C Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 171.30 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
467.19
467.19 661.64 59.55 52.93 92.89 867.01
a. Asphalt Cement (8%) b. Aggregates (93%) c. Mineral Filler (7%) (w/ 5% wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
2182
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA)
ement Penetration Grade 120-150)
Item No./Description Unit of Measurement Output per hour Amount
: : :
311(1)a.1 PCC Pavement (Plain) - Conventional Method, 150mm thk. sq.m. 107.33
Designation
No. of Person
No. of Hours
1 4 12
1 1 1
No of Units
No. of Hours
4 2 1 1 1 1 1 1
1 1 1 1 1 1 1 0.10
Unit
Quantity
kg. lit. lit. l.m. cu.m. cu.m. bag pc. l.m. lit.
0.33 0.29 0.12 0.46 0.0825 0.15 1.43 0.00015 0.0078 0.0015
A. Labor 109.19 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
293.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00 130.54
1,066.54 1,360.05 4,533.50
a. Transit Mixer (5 cu.m.) b. Concrete Vibrator c. Batching Plant (30 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Concrete Screeder (5.5 Hp) f. Water Truck (1000 gal.) g. Concrete Saw, Blade Ø 14" (7.5 Hp) h. Bar Cutter, Single Phase Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 107.33 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
53,313.75
53,313.75 57,847.25 5,206.25 4,627.78 8,121.75 75,803.04
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental) e. Sand f. Gravel g. Cement h. Concrete Saw (diamond blade 14") i. Pipe Sleeve, 1" dia. j. Grease/Tar
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
5485
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
311(1)a.2 PCC Pavement (Plain) - Conventional Method, 200mm thk. sq.m. 80.50
Designation
No. of Person
No. of Hours
1 4 12
1 1 1
No of Units
No. of Hours
4 2 1 1 1 1 1 1
1 1 1 1 1 1 1 0.10
Unit
Quantity
kg. lit. lit. l.m. cu.m. cu.m. bag pc. l.m. lit.
0.39 0.29 0.12 0.46 0.11 0.20 1.90 0.00015 0.0086 0.0056
A. Labor 109.19 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
293.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00 130.54
1,066.54 1,360.05 4,533.50
a. Transit Mixer (5 cu.m.) b. Concrete Vibrator c. Batching Plant (30 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Concrete Screeder (5.5 Hp) f. Water Truck (1000 gal.) g. Concrete Saw, Blade Ø 14" (7.5 Hp) h. Bar Cutter, Single Phase Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 80.50 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
42,315.00
42,315.00 46,848.50 4,216.37 3,747.88 6,577.53 61,390.27
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental) e. Sand f. Gravel g. Cement h. Concrete Saw (diamond blade 14") i. Pipe Sleeve, 1 1/2" dia. j. Grease/Tar
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
2202
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
311(1)a.3 PCC Pavement (Plain) - Conventional Method, 230mm thk. sq.m. 70.00
Designation
No. of Person
No. of Hours
1 4 12
1 1 1
No of Units
No. of Hours
4 2 1 1 1 1 1 1
1 1 1 1 1 1 1 0.10
Unit
Quantity
kg. lit. lit. l.m. cu.m. cu.m. bag pc. l.m. lit.
0.43 0.29 0.12 0.46 0.1265 0.23 2.19 0.00015 0.0071 0.0087
A. Labor 109.19 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
293.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00 130.54
1,066.54 1,360.05 4,533.50
a. Transit Mixer (5 cu.m.) b. Concrete Vibrator c. Batching Plant (30 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Concrete Screeder (5.5 Hp) f. Water Truck (1000 gal.) g. Concrete Saw, Blade Ø 14" (7.5 Hp) h. Bar Cutter, Single Phase Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 70.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
43,653.75
43,653.75 48,187.25 4,336.85 3,854.98 6,765.49 63,144.57
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental) e. Sand f. Gravel g. Cement h. Concrete Saw (diamond blade 14") i. Pipe Sleeve, 2" dia. j. Grease/Tar
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
5485
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
311(1)a.4 PCC Pavement (Plain) - Conventional Method, 250mm thk. sq.m. 64.40
Designation
No. of Person
No. of Hours
1 4 12
1 1 1
No of Units
No. of Hours
4 2 1 1 1 1 1 1
1 1 1 1 1 1 1 0.10
Unit
Quantity
kg. lit. lit. l.m. cu.m. cu.m. bag pc. l.m. lit.
0.45 0.29 0.15 0.46 0.1375 0.25 2.38 0.00015 0.0078 0.0095
A. Labor 109.19 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
293.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00 130.54
1,066.54 1,360.05 4,533.50
a. Transit Mixer (5 cu.m.) b. Concrete Vibrator c. Batching Plant (30 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Concrete Screeder (5.5 Hp) f. Water Truck (1000 gal.) g. Concrete Saw, Blade Ø 14" (7.5 Hp) h. Bar Cutter, Single Phase Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 64.40 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
46,200.00
46,200.00 50,733.50 4,566.02 4,058.68 7,122.98 66,481.18
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental) e. Sand f. Gravel g. Cement h. Concrete Saw (diamond blade 14") i. Pipe Sleeve, 2" dia. j. Grease/Tar
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
2222
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
311(1)a.5 PCC Pavement (Plain) - Conventional Method, 280mm thk. sq.m. 57.50
Designation
No. of Person
No. of Hours
1 4 12
1 1 1
No of Units
No. of Hours
4 2 1 1 1 1 1 1
1 1 1 1 1 1 1 0.10
Unit
Quantity
kg. lit. lit. l.m. cu.m. cu.m. bag pc. l.m. lit.
0.50 0.29 0.17 0.46 0.154 0.28 2.66 0.00015 0.0078 0.0078
A. Labor 109.19 1,228.80
a. Construction Foreman b. Skilled Laborer c. Laborer
1,337.99
Sub - Total for A
Amount
Name and Capacity B. Equipment
1,507.00 266.25
1,773.25 3,111.24 194.45
a. Transit Mixer (5 cu.m.) b. Concrete Vibrator c. Batching Plant (30 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Concrete Screeder (5.5 Hp) f. Water Truck (1000 gal.) g. Concrete Saw, Blade Ø 14" (7.5 Hp) h. Bar Cutter, Single Phase Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 57.50 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
467.19
467.19 661.64 59.55 52.93 92.89 867.01
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental) e. Sand f. Gravel g. Cement h. Concrete Saw (diamond blade 14") i. Pipe Sleeve, 2" dia. j. Grease/Tar
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
5485
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
311(1)a.6 PCC Pavement (Plain) - Conventional Method, 300mm thk. sq.m. 53.67
Designation
No. of Person
No. of Hours
1 4 12
1 1 1
No of Units
No. of Hours
4 2 1 1 1 1 1 1
1 1 1 1 1 1 1 0.10
Unit
Quantity
kg. lit. lit. l.m. cu.m. cu.m. bag pc. l.m. lit.
0.55 0.29 0.18 0.46 0.165 0.30 2.85 0.00015 0.0094 0.0094
A. Labor 109.19 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
293.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00 130.54
1,066.54 1,360.05 4,533.50
a. Transit Mixer (5 cu.m.) b. Concrete Vibrator c. Batching Plant (30 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Concrete Screeder (5.5 Hp) f. Water Truck (1000 gal.) g. Concrete Saw, Blade Ø 14" (7.5 Hp) h. Bar Cutter, Single Phase Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 53.67 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
53,313.75
53,313.75 57,847.25 5,206.25 4,627.78 8,121.75 75,803.04
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental) e. Sand f. Gravel g. Cement h. Concrete Saw (diamond blade 14") i. Pipe Sleeve, 2" dia. j. Grease/Tar
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
2242
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
311(1)b.1 PCC Pavement (Plain) - Using Concrete Paver, 230mm thk. sq.m. 90.00
Designation
No. of Person
No. of Hours
1 4 10
1 1 1
No of Units
No. of Hours
1 1 4 1 1 1 1 1
1 1 1 1 1 1 0.10 0.10
Unit
Quantity
kg. lit. lit. cu.m. cu.m. bag pc. l.m. lit.
0.43 0.29 0.12 0.1265 0.23 2.19 0.00015 0.0071 0.0087
A. Labor 109.19 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
293.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00 130.54
1,066.54 1,360.05 4,533.50
a. Batching Plant (30 cu.m.) b. Concrete Paver, GP-2000 Slipform c. Transit Mixer (5 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Water Truck (1000 gal.) f. Concrete Saw, Blade Ø 14" (7.5 Hp) g. Concrete Vibrator h. Bar Cutter, Single Phase
Sub - Total for B C. Total (A + B) D. Output per hour = 90.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
43,653.75
43,653.75 48,187.25 4,336.85 3,854.98 6,765.49 63,144.57
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Sand e. Gravel f. Cement g. Concrete Saw (diamond blade 14") h. Pipe Sleeve, 2" dia. i. Grease/Tar
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
5485
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
311(1)b.2 PCC Pavement (Plain) - Using Concrete Paver, 250mm thk. sq.m. 82.80
Designation
No. of Person
No. of Hours
1 4 10
1 1 1
No of Units
No. of Hours
1 1 4 1 1 1 1 1
1 1 1 1 1 1 0.10 0.10
Unit
Quantity
kg. lit. lit. cu.m. cu.m. bag pc. l.m. lit.
0.45 0.29 0.15 0.1375 0.25 2.38 0.00015 0.0078 0.0095
A. Labor 109.19 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
293.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00 130.54
1,066.54 1,360.05 4,533.50
a. Batching Plant (30 cu.m.) b. Concrete Paver, GP-2000 Slipform c. Transit Mixer (5 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Water Truck (1000 gal.) f. Concrete Saw, Blade Ø 14" (7.5 Hp) g. Concrete Vibrator h. Bar Cutter, Single Phase
Sub - Total for B C. Total (A + B) D. Output per hour = 82.80 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
46,200.00
46,200.00 50,733.50 4,566.02 4,058.68 7,122.98 66,481.18
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Sand e. Gravel f. Cement g. Concrete Saw (diamond blade 14") h. Pipe Sleeve, 2" dia. i. Grease/Tar
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
2262
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
311(1)b.3 PCC Pavement (Plain) - Using Concrete Paver, 280mm thk. sq.m. 73.93
Designation
No. of Person
No. of Hours
1 4 10
1 1 1
No of Units
No. of Hours
1 1 4 1 1 1 1 1
1 1 1 1 1 1 0.10 0.10
Unit
Quantity
kg. lit. lit. cu.m. cu.m. bag pc. l.m. lit.
0.50 0.29 0.17 0.154 0.28 2.66 0.00015 0.0078 0.0078
A. Labor 109.19 79.70 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
373.21
Sub - Total for A
Amount
Name and Capacity B. Equipment
2,933.55 1,652.00 553.00 936.00 266.25 37.32
6,378.12 6,751.33 562.61
a. Batching Plant (30 cu.m.) b. Concrete Paver, GP-2000 Slipform c. Transit Mixer (5 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Water Truck (1000 gal.) f. Concrete Saw, Blade Ø 14" (7.5 Hp) g. Concrete Vibrator h. Bar Cutter, Single Phase
Sub - Total for B C. Total (A + B) D. Output per hour = 73.93 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
467.19 2,821.00 54.00
3,342.19 3,904.80 351.43 312.38 548.23 5,116.85
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Sand e. Gravel f. Cement g. Concrete Saw (diamond blade 14") h. Pipe Sleeve, 2" dia. i. Grease/Tar
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
5485
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
311(1)b.4 PCC Pavement (Plain) - Using Concrete Paver, 300mm thk. sq.m. 69.00
Designation
No. of Person
No. of Hours
1 4 10
1 1 1
No of Units
No. of Hours
1 1 4 1 1 1 1 1
1 1 1 1 1 1 0.10 0.10
Unit
Quantity
kg. lit. lit. cu.m. cu.m. bag pc. l.m. lit.
0.55 0.29 0.18 0.165 0.30 2.85 0.00015 0.0094 0.0094
A. Labor 109.19 79.70 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
373.21
Sub - Total for A
Amount
Name and Capacity B. Equipment
2,933.55 1,652.00 553.00 936.00 266.25 37.32
6,378.12 6,751.33 562.61
a. Batching Plant (30 cu.m.) b. Concrete Paver, GP-2000 Slipform c. Transit Mixer (5 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Water Truck (1000 gal.) f. Concrete Saw, Blade Ø 14" (7.5 Hp) g. Concrete Vibrator h. Bar Cutter, Single Phase
Sub - Total for B C. Total (A + B) D. Output per hour = 69.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
467.19 4,400.00 54.00
4,921.19 5,483.80 493.54 438.70 769.93 7,185.97
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Sand e. Gravel f. Cement g. Concrete Saw (diamond blade 14") h. Pipe Sleeve, 2" dia. i. Grease/Tar
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
2282
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
311(1)c
PCC Pavement (Plain) - Conventional Method, 150mm thk. sq.m. 12.00
Designation
No. of Person
No. of Hours
1 8 16
1 1 1
No of Units
No. of Hours
1 1 2 1 1
1 0.05 1 0.05 0.10
Unit
Quantity
kg. lit. lit. l.m. cu.m. cu.m. bag pc. l.m. lit.
0.33 0.29 0.12 0.46 0.0825 0.15 1.43 0.00015 0.0078 0.0015
A. Labor 109.19 79.70 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
373.21
Sub - Total for A
Amount
Name and Capacity B. Equipment
2,933.55 1,652.00 553.00 266.25 37.32
5,442.12 5,815.33 484.61
a. One Bagger Mixer b. Water Truck (1000 gal.) c. Concrete Vibrator d. Bar Cutter, Single Phase e. Concrete Saw, Blade Ø 14" (7.5 Hp) Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 12.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
467.19
467.19 951.80 85.66 76.14 133.63 1,247.24
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental) e. Sand f. Gravel g. Cement h. Concrete Saw (diamond blade 14") i. Pipe Sleeve, 1" dia. j. Grease/Tar
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
5485
9% 8% 12%
IT PRICE ANALYSIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA
r Bituminous Road Mix Surface Course
Hourly Rate
Item No./Description Unit of Measurement Output per hour Amount
: : :
311(2)
PCC Pavement (Reinforced), 230mm thk. sq.m. 6.00
Designation
No. of Person
A. Labor 109.19 79.70 61.44
Hourly Rate
109.19 79.70 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
373.21
Sub - Total for A
Amount
Name and Capacity
1 4 12
No of Units
B. Equipment 936.00
936.00
936.00 1,309.21 1,309.21 Unit Cost
a. Batching Plant (30 cu.m.)
1
b. Concrete Screeder (5.5 Hp) c. Transit Mixer (5 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Water Truck (1000 gal.) f. Concrete Vibrator g. Bar Cutter, Single Phase h. Bar Bender Minor Tools (5% of Labor)
1 3 1 1 2 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 6.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification
Unit
F. Materials 40,300.00
of G of G of (G + H + I)
42,315.00
42,315.00 43,624.21 3,926.18 3,489.94 6,124.84
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental) e. Sand f. Gravel g. Cement h. # 16 GI Tie Wire (2% of RSB)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
2302
kg. lit. lit. l.m. cu.m. cu.m. bag kg.
(G + H + I + J)
57,165.16
K. Total Unit Cost
5485
IT PRICE ANALYSIS (DUPA)
Surface Course-General (50mm thk.)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 478.20 737.28
1,324.67 Hourly Rate
Amount
1,833.00
1,833.00
553.00 1,652.00 1,352.00 1,214.73 1,065.00 1,733.00
553.00 1,652.00 2,704.00 1,214.73 1,065.00 1,733.00 132.47
10,887.20 12,211.87 71.29 Unit Cost
Amount
44,000.00 650.00 240.56
431.64 31.72 31.27
of G of G of (G + H + I)
494.63 565.92 50.93 45.27 79.46
2322
(G + H + I + J)
741.58
5485
IT PRICE ANALYSIS (DUPA)
x (50mm thk.)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 478.20 737.28
1,324.67 Hourly Rate
Amount
1,833.00
1,833.00
553.00 1,652.00 1,352.00 1,214.73 1,065.00 1,733.00
553.00 1,652.00 2,704.00 1,214.73 1,065.00 1,733.00 132.47
10,887.20 12,211.87 71.29 Unit Cost
Amount
44,000.00 650.00 240.56
539.44 31.72 31.27
of G of G of (G + H + I)
602.43 673.72 60.63 53.90 94.59
2342
(G + H + I + J)
882.85
5485
IT PRICE ANALYSIS (DUPA)
x (50mm thk.)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 478.20 737.28
1,324.67 Hourly Rate
Amount
1,833.00
1,833.00
553.00 1,652.00 1,352.00 1,214.73 1,065.00 1,733.00
553.00 1,652.00 2,704.00 1,214.73 1,065.00 1,733.00 132.47
10,887.20 12,211.87 71.29 Unit Cost
Amount
40,300.00 650.00 240.56
345.77 31.72 31.27
of G of G of (G + H + I)
408.77 480.06 43.21 38.40 67.40
2362
(G + H + I + J)
629.07
5485
IT PRICE ANALYSIS (DUPA)
Stockpile Maintenance Mixture)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 478.20 737.28
1,324.67 Hourly Rate
Amount
1,352.00
2,704.00
1,214.73 1,065.00 1,733.00
1,214.73 1,065.00 1,733.00 132.47
6,849.20 8,173.87 47.72 Unit Cost
Amount
40,300.00 650.00 240.56
395.34 31.72 31.27
of G of G of (G + H + I)
458.34 506.05 45.54 40.48 71.05
2382
(G + H + I + J)
663.13
5485
IT PRICE ANALYSIS (DUPA)
Surface Course (30mm thk.)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 318.80 491.52
919.51 Hourly Rate
Amount
1,833.00 553.00 1,652.00 1,065.00
1,833.00 553.00 1,652.00 1,065.00 91.95
5,194.95 6,114.46 21.42 Unit Cost
Amount
4,500.00
333.00
of G of G of (G + H + I) (G + H + I + J)
333.00 354.42 31.90 28.35 49.76 464.43
2402
IT PRICE ANALYSIS (DUPA)
Surface Course (40mm thk.)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 318.80 491.52
919.51 Hourly Rate
Amount
1,833.00 553.00 1,652.00 1,065.00
1,833.00 553.00 1,652.00 1,065.00 91.95
5,194.95 6,114.46 28.55 Unit Cost
Amount
4,500.00
441.00
of G of G of (G + H + I) (G + H + I + J)
441.00 469.55 42.26 37.56 65.93 615.30
5485
IT PRICE ANALYSIS (DUPA)
Surface Course (50mm thk.)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 318.80 491.52
919.51 Hourly Rate
Amount
1,833.00 553.00 1,652.00 1,065.00
1,833.00 553.00 1,652.00 1,065.00 91.95
5,194.95 6,114.46 35.69 Unit Cost
Amount
4,500.00
553.50
of G of G of (G + H + I) (G + H + I + J)
553.50 589.19 53.03 47.14 82.72 772.08
2422
IT PRICE ANALYSIS (DUPA)
Surface Course (30mm thk.)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 478.20 737.28
1,324.67 Hourly Rate
Amount
1,833.00 553.00 1,652.00 1,352.00 1,214.73 1,065.00 1,733.00
1,833.00 553.00 1,652.00 2,704.00 1,214.73 1,065.00 1,733.00 132.47
10,887.20 12,211.87 42.77 Unit Cost
Amount
50,775.00 650.00 240.56
298.56 19.05 18.76
of G of G of (G + H + I) (G + H + I + J)
336.37 379.14 34.12 30.33 53.23 496.82
5485
IT PRICE ANALYSIS (DUPA)
Surface Course (40mm thk.)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 478.20 737.28
1,324.67 Hourly Rate
Amount
1,833.00 553.00 1,652.00 1,352.00 1,214.73 1,065.00 1,733.00
1,833.00 553.00 1,652.00 2,704.00 1,214.73 1,065.00 1,733.00 132.47
10,887.20 12,211.87 57.03 Unit Cost
Amount
50,775.00 650.00 240.56
398.58 25.42 25.02
of G of G of (G + H + I) (G + H + I + J)
449.02 506.05 45.54 40.48 71.05 663.12
2442
IT PRICE ANALYSIS (DUPA)
Surface Course (50mm thk.)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 478.20 737.28
1,324.67 Hourly Rate
Amount
1,833.00 553.00 1,652.00 1,352.00 1,214.73 1,065.00 1,733.00
1,833.00 553.00 1,652.00 2,704.00 1,214.73 1,065.00 1,733.00 132.47
10,887.20 12,211.87 71.29 Unit Cost
Amount
50,775.00 650.00 240.56
498.10 31.72 31.27
of G of G of (G + H + I) (G + H + I + J)
561.10 632.38 56.91 50.59 88.79 828.68
5485
IT PRICE ANALYSIS (DUPA)
) - Conventional Method, 150mm thk.
Hourly Rate
Amount
109.19 79.70 61.44
109.19 318.80 737.28
1,165.27 Hourly Rate
Amount
1,279.00 148.88 1,208.03 1,733.00 545.00 1,065.00 167.38 219.75
5,116.00 297.76 1,208.03 1,733.00 545.00 1,065.00 167.38 21.98 58.26
10,212.41 11,377.68 106.01 Unit Cost
Amount
40.00 28.00 44.00 50.00 850.00 650.00 220.00 8,000.00 34.33 300.00
13.20 8.12 5.28 23.00 70.13 97.50 314.60 1.20 0.27 0.45
of G of G of (G + H + I) (G + H + I + J)
533.74 639.75 57.58 51.18 89.82 838.33
2462
IT PRICE ANALYSIS (DUPA)
) - Conventional Method, 200mm thk.
Hourly Rate
Amount
109.19 79.70 61.44
109.19 318.80 737.28
1,165.27 Hourly Rate
Amount
1,279.00 148.88 1,208.03 1,733.00 545.00 1,065.00 167.38 219.75
5,116.00 297.76 1,208.03 1,733.00 545.00 1,065.00 167.38 21.98 58.26
10,212.41 11,377.68 141.34 Unit Cost
Amount
40.00 28.00 44.00 50.00 850.00 650.00 220.00 8,000.00 67.67 300.00
15.60 8.12 5.28 23.00 93.50 130.00 418.00 1.20 0.58 1.68
of G of G of (G + H + I) (G + H + I + J)
696.96 838.30 75.45 67.06 117.70 1,098.51
5485
IT PRICE ANALYSIS (DUPA)
) - Conventional Method, 230mm thk.
Hourly Rate
Amount
109.19 79.70 61.44
109.19 318.80 737.28
1,165.27 Hourly Rate
Amount
1,279.00 148.88 1,208.03 1,733.00 545.00 1,065.00 167.38 219.75
5,116.00 297.76 1,208.03 1,733.00 545.00 1,065.00 167.38 21.98 58.26
10,212.41 11,377.68 162.54 Unit Cost
Amount
40.00 28.00 44.00 50.00 850.00 650.00 220.00 8,000.00 97.00 300.00
17.20 8.12 5.28 23.00 107.53 149.50 481.80 1.20 0.69 2.61
of G of G of (G + H + I) (G + H + I + J)
796.92 959.46 86.35 76.76 134.71 1,257.28
2482
IT PRICE ANALYSIS (DUPA)
) - Conventional Method, 250mm thk.
Hourly Rate
Amount
109.19 79.70 61.44
109.19 318.80 737.28
1,165.27 Hourly Rate
Amount
1,279.00 148.88 1,208.03 1,733.00 545.00 1,065.00 167.38 219.75
5,116.00 297.76 1,208.03 1,733.00 545.00 1,065.00 167.38 21.98 58.26
10,212.41 11,377.68 176.67 Unit Cost
Amount
40.00 28.00 44.00 50.00 850.00 650.00 220.00 8,000.00 97.00 300.00
18.00 8.12 6.60 23.00 116.88 162.50 523.60 1.20 0.76 2.85
of G of G of (G + H + I) (G + H + I + J)
863.50 1,040.17 93.62 83.21 146.04 1,363.04
5485
IT PRICE ANALYSIS (DUPA)
) - Conventional Method, 280mm thk.
Hourly Rate
Amount
109.19 79.70 61.44
109.19 318.80 737.28
1,165.27 Hourly Rate
Amount
1,279.00 148.88 1,208.03 1,733.00 545.00 1,065.00 167.38 219.75
5,116.00 297.76 1,208.03 1,733.00 545.00 1,065.00 167.38 21.98 58.26
10,212.41 11,377.68 197.87 Unit Cost
Amount
40.00 28.00 44.00 50.00 850.00 650.00 220.00 8,000.00 97.00 300.00
20.00 8.12 7.48 23.00 130.90 182.00 585.20 1.20 0.76 2.34
of G of G of (G + H + I) (G + H + I + J)
961.00 1,158.87 104.30 92.71 162.71 1,518.58
2502
IT PRICE ANALYSIS (DUPA)
) - Conventional Method, 300mm thk.
Hourly Rate
Amount
109.19 79.70 61.44
109.19 318.80 737.28
1,165.27 Hourly Rate
Amount
1,279.00 148.88 1,208.03 1,733.00 545.00 1,065.00 167.38 219.75
5,116.00 297.76 1,208.03 1,733.00 545.00 1,065.00 167.38 21.98 58.26
10,212.41 11,377.68 211.99 Unit Cost
Amount
40.00 28.00 44.00 50.00 850.00 650.00 220.00 8,000.00 97.00 300.00
22.00 8.12 7.92 23.00 140.25 195.00 627.00 1.20 0.91 2.82
of G of G of (G + H + I) (G + H + I + J)
1,028.22 1,240.22 111.62 99.22 174.13 1,625.18
5485
IT PRICE ANALYSIS (DUPA)
) - Using Concrete Paver, 230mm thk.
Hourly Rate
Amount
109.19 79.70 61.44
109.19 318.80 614.40
1,042.39 Hourly Rate
Amount
1,208.03 6,765.00 1,279.00 1,733.00 1,065.00 167.38 148.88 219.75
1,208.03 6,765.00 5,116.00 1,733.00 1,065.00 167.38 14.89 21.98
16,091.27 17,133.66 190.37 Unit Cost
Amount
40.00 28.00 44.00 850.00 650.00 220.00 8,000.00 97.00 300.00
17.20 8.12 5.28 107.53 149.50 481.80 1.20 0.69 2.61
of G of G of (G + H + I) (G + H + I + J)
773.92 964.30 86.79 77.14 135.39 1,263.62
2522
IT PRICE ANALYSIS (DUPA)
) - Using Concrete Paver, 250mm thk.
Hourly Rate
Amount
109.19 79.70 61.44
109.19 318.80 614.40
1,042.39 Hourly Rate
Amount
1,208.03 6,765.00 1,279.00 1,733.00 1,065.00 167.38 148.88 219.75
1,208.03 6,765.00 5,116.00 1,733.00 1,065.00 167.38 14.89 21.98
16,091.27 17,133.66 206.93 Unit Cost
Amount
40.00 28.00 44.00 850.00 650.00 220.00 8,000.00 97.00 300.00
18.00 8.12 6.60 116.88 162.50 523.60 1.20 0.76 2.85
of G of G of (G + H + I) (G + H + I + J)
840.50 1,047.43 94.27 83.79 147.06 1,372.55
5485
IT PRICE ANALYSIS (DUPA)
) - Using Concrete Paver, 280mm thk.
Hourly Rate
Amount
109.19 79.70 61.44
109.19 318.80 614.40
1,042.39 Hourly Rate
Amount
1,208.03 6,765.00 1,279.00 1,733.00 1,065.00 167.38 148.88 219.75
1,208.03 6,765.00 5,116.00 1,733.00 1,065.00 167.38 14.89 21.98
16,091.27 17,133.66 231.76 Unit Cost
Amount
40.00 28.00 44.00 850.00 650.00 220.00 8,000.00 97.00 300.00
20.00 8.12 7.48 130.90 182.00 585.20 1.20 0.76 2.34
of G of G of (G + H + I) (G + H + I + J)
938.00 1,169.75 105.28 93.58 164.23 1,532.84
2542
IT PRICE ANALYSIS (DUPA)
) - Using Concrete Paver, 300mm thk.
Hourly Rate
Amount
109.19 79.70 61.44
109.19 318.80 614.40
1,042.39 Hourly Rate
Amount
1,208.03 6,765.00 1,279.00 1,733.00 1,065.00 167.38 148.88 219.75
1,208.03 6,765.00 5,116.00 1,733.00 1,065.00 167.38 14.89 21.98
16,091.27 17,133.66 248.31 Unit Cost
Amount
40.00 28.00 44.00 850.00 650.00 220.00 8,000.00 97.00 300.00
22.00 8.12 7.92 140.25 195.00 627.00 1.20 0.91 2.82
of G of G of (G + H + I) (G + H + I + J)
1,005.22 1,253.54 112.82 100.28 176.00 1,642.63
5485
IT PRICE ANALYSIS (DUPA)
) - Conventional Method, 150mm thk.
Hourly Rate
Amount
109.19 79.70 61.44
109.19 637.60 983.04
1,729.83 Hourly Rate
Amount
172.00 1,065.00 148.88 219.75 167.38
172.00 53.25 297.76 10.99 16.74 86.49
637.23 2,367.06 197.25 Unit Cost
Amount
40.00 28.00 44.00 50.00 850.00 650.00 220.00 8,000.00 34.33 300.00
13.20 8.12 5.28 23.00 70.13 97.50 314.60 1.20 0.27 0.45
of G of G of (G + H + I) (G + H + I + J)
533.74 731.00 65.79 58.48 102.63 957.90
2562
DETAILED UNIT PRICE ANALYSIS (DUPA) PCC Pavement (Reinforced), 230mm thk.
No. of Hours
Hourly Rate
Amount
1 1 1
109.19 79.70 61.44
109.19 318.80 737.28
1,165.27 No. of Hours
Hourly Rate
Amount
0.10
1,208.03
120.80
0.10 0.10 0.10 0.10 0.10 0.25 0.25
545.00 1,279.00 1,733.00 1,065.00 148.88 219.75 351.50
54.50 383.70 173.30 106.50 29.78 54.94 87.88 58.26
1,069.66 2,234.93
hour = 6.00 sq.m. 372.49 Quantity
Unit Cost
Amount
40.86 0.29 0.12 0.46 0.1265 0.23 2.19 0.817
40.00 28.00 44.00 50.00 850.00 650.00 220.00 47.00
1,634.40 8.12 5.28 23.00 107.53 149.50 481.80 38.40
9% of G 8% of G 12% of (G + H + I)
2,448.02 2,820.51 253.85 225.64 396.00
5485
(G + H + I + J)
2582
3,696.00
5485
2602
5485
2622
5485
2642
5485
2662
5485
2682
5485
2702
5485
2722
5485
2742
5485
2762
5485
2782
5485
2802
5485
2822
5485
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
404
Reinforcing Steel Bar, Grade 40 (Minor Structures) kg. 180.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 8
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.50 0.50 0.15
219.75 351.50 1,102.00
Unit
Quantity
Unit Cost
kg. kg.
0.021 1.05
47.00 40.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Bar Cutter b. Bar Bender c. Cargo Truck (10 T, 270 Hp)
Sub - Total for B C. Total (A + B) D. Output per hour = 180.00 kg. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Tie Wire (2% of RSB) b. Reinforcing Steel Bar, Grade 40 (w/ 5% Wastage)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
405
Structural Concrete Class A (Minor Structures) cu.m. 1.40
Designation
No. of Person
No. of Hours
Hourly Rate
a. Construction Foreman b. Skilled Laborer c. Laborer
1 4 8
1 1 1
109.19 79.70 61.44
Installation/Removal of Formworks a. Skilled Laborer b. Laborer Sub - Total for A
4 8
1 1
79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.10
172.00 148.88 1,065.00
Unit
Quantity
Unit Cost
bd.ft. pc. kg. bag cu.m. cu.m.
* 70.00 * 1.60 * 0.70 9.50 0.50 1
40.00 700.00 68.00 220.00 850.00 650.00
A. Labor
Name and Capacity B. Equipment a. One Bagger Mixer b. Concrete Vibrator c. Water Truck (1000 gal.) Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.40 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Lumber, Good - 4 uses b. Marine Plywood (1/2" x 4' x 8') - 4 uses c. Assorted CWN (1kg./100 bd.ft. of Lumber) d. Cement e. Sand f. Gravel Note: *Quantities for lumber, plywood and CWN are dependent on the type of minor structure. The above-computed quantities are based on box culvert.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 491.52
760.11 Amount
109.88 175.75 165.30
450.93 1,211.04 6.73 Amount
0.99 42.00
42.99 49.71 4.47 3.98 6.98 65.15
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 318.80 491.52
318.80 491.52 1,729.83 Amount
172.00 148.88 106.50 86.49
513.87 2,243.70 1,602.64 Amount
700.00 280.00 47.60 2,090.00 425.00 650.00
4,192.60 5,795.24 521.57 463.62 813.65 7,594.09
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
500(1)a
Pipe Culverts, 610mm dia. (24" Ø) l.m. 2.25
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1
0.50 0.50
1,537.00 123.00
Unit
Quantity
Unit Cost
bag cu.m. pc. cu.m.
0.774 0.044 1 0.088
220.00 850.00 950.00 850.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Plate Compactor (5 Hp) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.25 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Portland Cement b. Sand c. R.C. Pipes (610mm dia.) d. Sand Bedding/Selected Sandy Soil
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
500(1)b
Pipe Culverts, 760mm dia. (30" Ø) l.m. 2.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Backhoe (0.80 cu.m.)
1
0.50
1,537.00
b. Plate Compactor (5 Hp) Minor Tools (10 % of Labor)
1
0.50
123.00
Unit
Quantity
Unit Cost
bag cu.m. pc. cu.m.
0.918 0.052 1 0.108
220.00 850.00 1,750.00 850.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 2.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Portland Cement b. Sand c. R.C. Pipes (760mm dia.) d. Sand Bedding/Selected Sandy Soil
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
500(1)c
Pipe Culverts, 910mm dia. (36" Ø) l.m. 1.75
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Backhoe (0.80 cu.m.)
1
0.50
1,537.00
b. Plate Compactor (5 Hp) Minor Tools (10 % of Labor)
1
0.50
123.00
Unit
Quantity
Unit Cost
bag cu.m. pc. cu.m.
1.080 0.061 1 0.128
220.00 850.00 2,170.00 850.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 1.75 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Portland Cement b. Sand c. R.C. Pipes (910mm dia.) d. Sand Bedding/Selected Sandy Soil
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
500(1)d
Pipe Culverts, 1070mm dia. (42" Ø) l.m. 1.50
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Backhoe (0.80 cu.m.)
1
0.50
1,537.00
b. Plate Compactor (5 Hp) Minor Tools (10 % of Labor)
1
0.50
123.00
Unit
Quantity
Unit Cost
bag cu.m. pc. cu.m.
1.242 0.070 1 0.149
220.00 850.00 2,900.00 850.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 1.50 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Portland Cement b. Sand c. R.C. Pipes (1070mm dia.) d. Sand Bedding/Selected Sandy Soil
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
500(1)e
Pipe Culverts, 1220mm dia. (48" Ø) l.m. 1.25
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Backhoe (0.80 cu.m.)
1
0.50
1,537.00
b. Plate Compactor (5 Hp) Minor Tools (10 % of Labor)
1
0.50
123.00
Unit
Quantity
Unit Cost
bag cu.m. pc. cu.m.
1.404 0.080 1 0.170
220.00 850.00 3,800.00 850.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Portland Cement b. Sand c. R.C. Pipes (1220mm dia.) d. Sand Bedding/Selected Sandy Soil
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
500(1)f
Pipe Culverts, 1520mm dia. (60" Ø) l.m. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Backhoe (0.80 cu.m.)
1
0.50
1,537.00
b. Plate Compactor (5 Hp) Minor Tools (10 % of Labor)
1
0.50
123.00
Unit
Quantity
Unit Cost
bag cu.m. pc. cu.m.
1.710 0.097 1 0.210
220.00 850.00 6,175.00 850.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Portland Cement b. Sand c. R.C. Pipes (1520mm dia.) d. Sand Bedding/Selected Sandy Soil
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
501(1)
Underdrain l.m. 1.25
Designation
No. of Person
No. of Hours
Hourly Rate
1 4
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1
0.50
123.00
Unit
Quantity
Unit Cost
cu.m. cu.m. sq.m. pc.
0.20 0.39 2 1.05
900.00 850.00 275.00 230.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Plate Compactor (5 Hp) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Coarse Aggregates b. Fine Aggregates c. Filter Cloth d. 150 mm. dia. Concrete Perforated Pipe
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
501(2)
Blind Drain l.m. 1.25
Designation
No. of Person
No. of Hours
Hourly Rate
1 4
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
Unit
Quantity
Unit Cost
cu.m. cu.m. sq.m.
0.22 0.39 2
900.00 850.00 275.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Coarse Aggregates b. Fine Aggregates c. Filter Cloth
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
501(3)
Granular Backfill filter material for Underdrains cu.m. 1.25
Designation
No. of Person
No. of Hours
Hourly Rate
1 4
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1
1
123.00
Name and Specification
Unit
Quantity
Unit Cost
a. Coarse Aggregates (Granular Backfill Materials) (w/ 15% Shrinkage Factor)
cu.m.
1.15
900.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Plate Compactor (5 Hp) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 cu.m. E. Direct Unit Cost (C ÷ D)
F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J) DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description Unit of Measurement Output
: : :
502
Manhole/Catch Basin/Inlet ea. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
No of Units
No. of Hours
Hourly Rate
Unit
Quantity
A. Labor
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification
Direct
Unit Cost
F. Materials/Processed Component Pay Item a. 103(3) - Foundation Fill b. 404 - Reinforcing Steel Bar c. 405 - Structural Concrete
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
cu.m. kg. cu.m.
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
502(4)
Concrete Covers ea. 5.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1 1
0.50 0.50 0.50 0.25 0.05
172.00 219.75 148.88 391.00 1,065.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. kg. kg. kg. kg. pc. set kg.
1.31 0.06 0.12 48.25 0.97 36.79 2.83 0.30 2.00 0.02
220.00 850.00 650.00 40.00 47.00 48.00 48.00 620.00 250.00 90.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. One Bagger Mixer b. Bar Cutter c. Concrete Vibrator d. Welding Machine (GasType) e. Water Truck Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output = 5.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials Dimension: 1.31m x 0.573m x 0.20m a. Portland Cement b. Sand c. Gravel d. Reinforcing Steel Bar e. #16 GI Tie Wire (2% of RSB) f. 6mm thk. Steel Plate g. 16mm thk. Steel Plate h. 1/2" Ordinary Plywood - 2 uses i. 16mm dia. U-bolt & Knot j. Welding Rod (1 kg./2000 kg. of Steel)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
502(5)
Metal Frames and Gratings pair 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 1
0.50 0.50 0.50
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
Unit
Quantity
Unit Cost
set
1.00
4,700.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output = 1.00 pair E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 410mmx660mmx60mm, C.I. Cover with Frame
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
502(6)
Metal Frames and Covers (Circular) pair 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 1
0.50 0.50 0.50
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
Unit
Quantity
Unit Cost
set
1.00
5,700.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output = 1.00 pair E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 580mm dia. C.I. Manhole Cover with Frame
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
503(a)
Drainage Steel Grating with Frame (675mm x 975mm Sump Grating) set 0.25
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 1
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1
0.50 1
219.75 391.00
Unit
Quantity
Unit Cost
kg. kg. kg. kg.
62.557 1.244 38.36 0.051
48.00 48.00 48.00 90.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Bar Cutter b. Welding Machine
Sub - Total for B C. Total (A + B) D. Output per hour = 0.25 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 65mm x 5mm Flat Bar b. 6mm dia. x 975mm Twisted Cross Rod c. 75mm x 75mm x 9mm Angle Bar d. Welding Rod (1 kg./2000 kg. of Steel)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
503(b)
Drainage Steel Grating with Frame (715mm x 2000mm Trench Grating) set 0.125
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 1
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1
0.50 1
219.75 391.00
Unit
Quantity
Unit Cost
kg. kg. kg. kg.
127.066 3.174 41.64 0.086
48.00 48.00 48.00 90.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Bar Cutter b. Welding Machine
Sub - Total for B C. Total (A + B) D. Output per hour = 0.125 set E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 65mm x 5mm Flat Bar b. 6mm dia. x 975mm Twisted Cross Rod c. 75mm x 75mm x 9mm Angle Bar d. Welding Rod (1 kg./2000 kg. of Steel)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(1)a
Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (24" dia) - 610mm l.m. 3.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.50 0.50 0.25
1,537.00 961.20 1,065.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck c. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 3.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(1)b
Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (30" dia.) - 760mm l.m. 2.50
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.50 0.50 0.25
1,537.00 961.20 1,065.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck c. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.50 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(1)c
Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (36" dia.) - 910mm l.m. 2.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.50 0.50 0.25
1,537.00 961.20 1,065.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck c. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(1)d
Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (42" dia.) - 1070mm l.m. 2.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.50 0.50 0.25
1,537.00 961.20 1,065.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck c. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(1)e
Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (48" dia.) - 1220mm l.m. 1.50
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.50 0.50 0.25
1,537.00 961.20 1,065.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck c. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.50 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(2)a
Removing, Cleaning and Re-laying Salvaged Culvert Pipe (24" dia.) - 610mm l.m. 1.50
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.60 0.50 0.15
1,537.00 123.00 1,065.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m.
0.774 0.044 0.088
220.00 850.00 850.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Plate Compactor (5 Hp) c. Water Truck (1000 gal.) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.50 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
a. Portland Cement b. Sand c. Sand Bedding
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(2)b
Removing, Cleaning and Re-laying Salvaged Culvert Pipe (30" dia.) - 760mm l.m. 1.25
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.60 0.50 0.15
1,537.00 123.00 1,065.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m.
0.918 0.052 0.108
220.00 850.00 850.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Plate Compactor (5 Hp) c. Water Truck (1000 gal.) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
a. Portland Cement b. Sand c. Sand Bedding
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(2)c
Removing, Cleaning and Re-laying Salvaged Culvert Pipe (36" dia.) - 910mm l.m. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.60 0.50 0.15
1,537.00 123.00 1,065.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m.
1.080 0.061 0.128
220.00 850.00 850.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Plate Compactor (5 Hp) c. Water Truck (1000 gal.) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
a. Portland Cement b. Sand c. Sand Bedding
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(2)d
Removing, Cleaning and Re-laying Salvaged Culvert Pipe (42" dia.) - 1070mm l.m. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.60 0.50 0.15
1,537.00 123.00 1,065.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m.
1.242 0.070 0.149
220.00 850.00 850.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Plate Compactor (5 Hp) c. Water Truck (1000 gal.) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
a. Portland Cement b. Sand c. Sand Bedding
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(2)e
Removing, Cleaning and Re-laying Salvaged Culvert Pipe (48" dia.) - 1220mm l.m. 0.75
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
0.60 0.50 0.15
1,537.00 123.00 1,065.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m.
1.404 0.080 0.170
220.00 850.00 850.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (0.80 cu.m.) b. Plate Compactor (5 Hp) c. Water Truck (1000 gal.) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.75 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
a. Portland Cement b. Sand c. Sand Bedding
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(3)a
Cleaning Culvert Pipe in place (610mm dia.) - Half Silted l.m. 8.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 l.s. l.s.
1
1,102.00 300.00 200.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (10 T) b. Steel Wheel with Nylon Rope c. Improvised Bamboo with Bucket Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 8.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(3)b
Cleaning Culvert Pipe in place (760mm dia.) - Half Silted l.m. 5.25
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 l.s. l.s.
1
1,102.00 300.00 200.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (10 T) b. Steel Wheel with Nylon Rope c. Improvised Bamboo with Bucket Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 5.25 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
768.50 61.50 51.44
881.44 1,395.79 620.35 Amount
170.28 37.40 950.00 74.80
1,232.48 1,852.83 166.75 148.23 260.14 2,427.95
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
768.50 61.50 51.44
881.44 1,395.79 697.89 Amount
201.96 44.20 1,750.00 91.80
2,087.96 2,785.85 250.73 222.87 391.13
3,650.58
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
768.50 61.50 51.44
881.44 1,395.79 797.59 Amount
237.60 51.85 2,170.00 108.80
2,568.25 3,365.84 302.93 269.27 472.56
4,410.60
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
768.50 61.50 51.44
881.44 1,395.79 930.52 Amount
273.24 59.50 2,900.00 126.65
3,359.39 4,289.91 386.09 343.19 602.30
5,621.50
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
768.50 61.50 51.44
881.44 1,395.79 1,116.63 Amount
308.88 68.00 3,800.00 144.50
4,321.38 5,438.01 489.42 435.04 763.50
7,125.97
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
768.50 61.50 51.44
881.44 1,395.79 1,395.79 Amount
376.20 82.45 6,175.00 178.50
6,812.15 8,207.94 738.71 656.63 1,152.39
10,755.68
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 245.76
354.95 Amount
61.50 35.50
97.00 451.95 361.56 Amount
180.00 331.50 550.00 241.50
1,303.00 1,664.56 149.81 133.16 233.70
2,181.23
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 245.76
354.95 Amount
35.50
35.50 390.45 312.36 Amount
198.00 331.50 550.00
1,079.50 1,391.86 125.27 111.35 195.42
1,823.89
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 245.76
354.95 Amount
123.00 35.50
158.50 513.45 410.76 Amount
1,035.00
1,035.00 1,445.76 130.12 115.66 202.98
1,894.52 DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
Amount
Direct Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
86.00 109.88 74.44 97.75 53.25 51.44
472.75 987.10 197.42 Amount
288.20 51.00 78.00 1,930.00 45.59 1,765.92 67.92 93.00 250.00 0.90
4,570.53 4,767.95 429.12 381.44 669.42 6,247.92
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
54.60 39.85 30.72
125.17 Amount
12.52
12.52 137.68 137.68 Amount
4,700.00
4,700.00 4,837.68 435.39 387.01 679.21 6,339.30
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
54.60 39.85 30.72
125.17 Amount
12.52
12.52 137.68 137.68 Amount
5,700.00
5,700.00 5,837.68 525.39 467.01 819.61 7,649.70
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 79.70 61.44
250.33 Amount
109.88 391.00
500.88 751.21 3,004.82 Amount
3,002.74 59.71 1,841.28 4.59
4,908.32 7,913.14 712.18 633.05 1,111.00 10,369.38
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 79.70 61.44
250.33 Amount
109.88 391.00
500.88 751.21 6,009.64 Amount
6,099.17 152.35 1,998.72 7.74
8,257.98 14,267.62 1,284.09 1,141.41 2,003.17 18,696.29
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
768.50 480.60 266.25 51.44
1,566.79 2,081.14 693.71 Amount
0.00 693.71 62.43 55.50 97.40 909.04
DETAILED UNIT PRICE ANALYSIS (DUPA) Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (30" dia.) - 760mm
Amount
109.19 159.40 245.76
514.35 Amount
768.50 480.60 266.25 51.44
1,566.79 2,081.14 832.45 Amount
0.00 832.45 74.92 66.60 116.88 1,090.85
DETAILED UNIT PRICE ANALYSIS (DUPA) Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (36" dia.) - 910mm
Amount
109.19 159.40 245.76
514.35 Amount
768.50 480.60 266.25 51.44
1,566.79 2,081.14 1,040.57 Amount
0.00 1,040.57 93.65 83.25 146.10 1,363.56
DETAILED UNIT PRICE ANALYSIS (DUPA) Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (42" dia.) - 1070mm
Amount
109.19 159.40 245.76
514.35 Amount
768.50 480.60 266.25 51.44
1,566.79 2,081.14 1,040.57 Amount
0.00 1,040.57 93.65 83.25 146.10 1,363.56
DETAILED UNIT PRICE ANALYSIS (DUPA) Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (48" dia.) - 1220mm
Amount
109.19 159.40 245.76
514.35 Amount
768.50 480.60 266.25 51.44
1,566.79 2,081.14 1,387.42 Amount
0.00 1,387.42 124.87 110.99 194.79 1,818.08
DETAILED UNIT PRICE ANALYSIS (DUPA) Removing, Cleaning and Re-laying Salvaged Culvert Pipe (24" dia.) - 610mm
Amount
109.19 159.40 245.76
514.35 Amount
922.20 61.50 159.75 51.44
1,194.89 1,709.24 1,139.49 Amount
170.28 37.40 74.80
282.48 1,421.97 127.98 113.76 199.64 1,863.35
DETAILED UNIT PRICE ANALYSIS (DUPA) Removing, Cleaning and Re-laying Salvaged Culvert Pipe (30" dia.) - 760mm
Amount
109.19 159.40 245.76
514.35 Amount
922.20 61.50 159.75 51.44
1,194.89 1,709.24 1,367.39 Amount
201.96 44.20 91.80
337.96 1,705.35 153.48 136.43 239.43 2,234.69
DETAILED UNIT PRICE ANALYSIS (DUPA) Removing, Cleaning and Re-laying Salvaged Culvert Pipe (36" dia.) - 910mm
Amount
109.19 159.40 245.76
514.35 Amount
922.20 61.50 159.75 51.44
1,194.89 1,709.24 1,709.24 Amount
237.60 51.85 108.80
398.25 2,107.49 189.67 168.60 295.89 2,761.65
DETAILED UNIT PRICE ANALYSIS (DUPA) Removing, Cleaning and Re-laying Salvaged Culvert Pipe (42" dia.) - 1070mm
Amount
109.19 159.40 245.76
514.35 Amount
922.20 61.50 159.75 51.44
1,194.89 1,709.24 1,709.24 Amount
273.24 59.50 126.65
459.39 2,168.63 195.18 173.49 304.47 2,841.77
DETAILED UNIT PRICE ANALYSIS (DUPA) Removing, Cleaning and Re-laying Salvaged Culvert Pipe (48" dia.) - 1220mm
Amount
109.19 159.40 245.76
514.35 Amount
922.20 61.50 159.75 51.44
1,194.89 1,709.24 2,278.98 Amount
308.88 68.00 144.50
521.38 2,800.36 252.03 224.03 393.17 3,669.59
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
1,102.00 300.00 200.00 51.44
1,653.44 2,167.79 270.97 Amount
0.00 270.97 24.39 21.68 38.04 355.08
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
1,102.00 300.00 200.00 51.44
1,653.44 2,167.79 412.91 Amount
0.00 412.91 37.16 33.03 57.97 541.08
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(3)c
Cleaning Culvert Pipe in place (910mm dia.) - Half Silted l.m. 3.75
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
1
1,102.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (10 T) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 3.75 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(3)d
Cleaning Culvert Pipe in place (1070mm dia.) - Half Silted l.m. 2.75
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
1
1,102.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (10 T) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.75 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(3)e
Cleaning Culvert Pipe in place (1220mm dia.) - Half Silted l.m. 2.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
1
1,102.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (10 T) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
504(3)f
Cleaning Culvert Pipe in place (1520mm dia.) - Half Silted l.m. 1.50
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
1
1,102.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (10 T) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.50 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
504(4)
Reconditioning Drainage Structures ea. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
0.50 0.50 0.50
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Cargo Truck (10 T)
1
0.25
1,102.00
b. Bamboo with Bucket - 4 uses Minor Tools (10% of Labor)
1
1
200.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials * If some repair is needed, component materials required and corresponding man-hour will be added to DUPA
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
505(1)
Riprap (Class A) cu.m. 1.50
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 8
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
Unit
Quantity
Unit Cost
cu.m.
1.05
920.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.50 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Boulders (15 - 25 kg.) Miscellaneous (1% of Materials)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
505(2)
Riprap (Class B) cu.m. 1.25
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.50
840.00
Unit
Quantity
Unit Cost
cu.m.
1.05
810.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Boulders (30 - 70 kg.) Miscellaneous (1% of Materials)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
505(3)
Riprap (Class C) cu.m. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.75
840.00
Unit
Quantity
Unit Cost
cu.m.
1.05
740.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment c. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Boulders (50 - 100 kg.) Miscellaneous (1% of Materials)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
505(4)
Riprap (Class D) cu.m. 0.75
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
1.00
840.00
Unit
Quantity
Unit Cost
cu.m.
1.05
650.00
A. Labor a. Construction Foreman b. Skilled Laborers c. Laborers
Sub - Total for A Name and Capacity B. Equipment a. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.75 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Boulders (100 - 200 kg.) Miscellaneous (1% of Materials)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
505(5)
Grouted Riprap (Class A) cu.m. 1.25
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 8
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 0.05
172.00 1,065.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. l.m. sq.m. cu.m.
3.00 0.25 0.015 0.30 0.015 1.05
220.00 850.00 650.00 144.67 275.00 920.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. One Bagger Mixer b. Water Truck (1000 gal.) Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Sand c. Gravel Fill d. Weep Holes (PVC) e. Filter Cloth f. Boulders (15 - 25 kg.) Miscellaneous (1% of Materials)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
505(6)
Grouted Riprap (Class B) cu.m. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 0.05 0.50
172.00 1,065.00 840.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. l.m. sq.m. cu.m.
2.50 0.21 0.015 0.30 0.015 1.05
220.00 850.00 650.00 144.67 275.00 810.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. One Bagger Mixer b. Water Truck (1000 gal.) c. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Sand c. Gravel Fill d. Weep Holes (PVC) e. Filter Cloth f. Boulders (30 - 70 kg.) Miscellaneous (1% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
505(7)
Grouted Riprap (Class C) cu.m. 0.75
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 0.05 0.75
172.00 1,065.00 840.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. l.m. sq.m. cu.m.
2.20 0.18 0.015 0.30 0.015 1.05
220.00 850.00 650.00 144.67 275.00 730.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. One Bagger Mixer b. Water Truck (1000 gal.) c. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.75 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Sand c. Gravel Fill d. Weep Holes (PVC) e. Filter Cloth f. Boulders (60 - 100 kg.) Miscellaneous (1% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
505(8)
Grouted Riprap (Class D) cu.m. 0.50
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 0.05 1
172.00 1,065.00 840.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. l.m. sq.m. cu.m.
1.80 0.15 0.015 0.30 0.015 1.05
220.00 850.00 650.00 144.67 275.00 650.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. One Bagger Mixer b. Water Truck (1000 gal.) c. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.50 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Sand c. Gravel Fill d. Weep Holes (PVC) e. Filter Cloth f. Boulders (100 - 200 kg.) Miscellaneous (1% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
505(9)
Filter Layer of Granular Material cu.m. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
Unit
Quantity
Unit Cost
cu.m.
1.05
900.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Granular Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
506
Stone Masonry cu.m. 1.5625
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 8
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 0.05 0.10
172.00 1,065.00 840.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. l.m. sq.m. cu.m.
5.50 0.30 0.02 0.30 0.015 1.05
220.00 850.00 650.00 144.67 275.00 920.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. One Bagger Mixer b. Water Truck (1000 gal.) c. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (10% Labor)
Sub - Total for B C. Total (A + B) D. Output per hour =1.5625 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Sand c. Gravel Fill d. Weep Holes (PVC) e. Filter Cloth f. Boulders Miscellaneous (1% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
507
Rubble Concrete cu.m. 1.40
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 8
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 0.05 0.10
172.00 1,065.00 840.00
Name and Specification
Unit
Quantity
Unit Cost
a. Cement b. Sand c. Gravel Fill d. Weep Holes (PVC) e. Filter Cloth f. Boulders g. Gravel Miscellaneous (2% of Materials) Note: 60% Boulder 50% Class "B" Concrete (w/ side forms only)
bag cu.m. cu.m. l.m. sq.m. cu.m. cu.m.
4.20 0.2625 0.02 0.30 0.015 0.63 0.525
220.00 850.00 650.00 144.67 275.00 810.00 650.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. One Bagger Mixer b. Water Truck (1000 gal.) c. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (10% Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.40 cu.m. E. Direct Unit Cost (C ÷ D)
F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
508
Hand Laid Rock Embankment cu.m. 3.125
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 8
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
Unit
Quantity
Unit Cost
cu.m.
1.05
920.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 3.125 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Boulders
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
509(a)
Timber Sheet Pile l.m. 4.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1
1 1
1,772.00 200.00
Unit
Quantity
Unit Cost
bd.ft. m. bd.ft. kg.
52.25 1.00 16.00 0.16
40.00 350.00 40.00 68.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Crawler Crane (45 T) b. Drop Hammer (15 T) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 4.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Timber Sheet Piles, ave. dia. 395mm b. Coco Log - 2 uses c. Lumber (Falsework) - 4 uses d. Nail/Spike (1 kg./100 bd.ft. of Lumber)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
509(b.1)
Steel Sheet Pile (Slope Protection) l.m. 10.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1
1 1 0.25 0.25
1,729.00 1,800.00 371.00 45.45
Unit
Quantity
Unit Cost
kg.
48.00
48.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Crawler Crane (36 - 40 T) b. Vibro Hammer (Hydraulic Operated) c. Welding Machine (Gas Operated) d. Cutting Outfit
Sub - Total for B C. Total (A + B) D. Output per hour = 10.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Steel Sheet Piles (48 kg./l.m.) Miscellaneous (3% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
509(b.2)
Steel Sheet Pile (for Cofferdaming) l.m. 10.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1 1
1 1 0.25 0.25 1
1,729.00 1,800.00 391.00 45.45 266.25
Unit
Quantity
Unit Cost
kg. kg.
48.00 4.80
48.00 48.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Crawler Crane (36 - 40 T) b. Vibro Hammer (Hydraulic Operated) c. Welding Machine d. Cutting Outfit e. Water Pump, 100mm suction diameter
Sub - Total for B C. Total (A + B) D. Output per hour = 10.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Steel Sheet Piles (48 kg./l.m.) b. Structural Steel (Walling, Bracing, Diagonal etc.) c. (Miscellaneous 1% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
509(c)
Concrete Sheet Pile, furnished and driven l.m. 1.20
Designation
No. of Person
No. of Hours
Hourly Rate
1 4 6
1 1 1
109.19 79.70 61.44
2 4
1 1
79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1 1 1 1 1 1 1
0.10 0.40 0.15 0.03 0.03 0.03 0.10 0.10 0.10 0.03
1,772.00 172.00 148.88 1,065.00 219.75 351.50 200.00 514.31 675.00 123.00
Unit
Quantity
Unit Cost
kg. bag cu.m. cu.m. pc. bd.ft. kg. kg.
28.11 1.44 0.08 0.15 0.15 5.90 0.562 0.059
40.00 220.00 850.00 650.00 700.00 40.00 47.00 68.00
cu.m bd.ft. cu.m
0.030 1.500 0.030
2,840.00 20.00 530.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer Formworks b. Skilled Laborer c. Laborer Sub - Total for A Name and Capacity B. Equipment a. Crawler Crane (45 T) b. One Bagger Mixer c. Concrete Vibrator d. Water Truck (1000 gal.) e. Bar Cutter f. Bar Bender g. Drop Hammer h. Jack Hammer i. Air Compressor (103 Hp) j. Plate Compactor (5 Hp) Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.20 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Reinforcing Steel Bar b. Cement c. Sand d. Gravel e. Marine Plywood, 1/2" x 4' x 8' f. Lumber, 2' x 2' g. # 16 GI Tie Wire (2% of RSB) h. Assorted CWN (1 kg./100 bd.ft. of Lumber) Casting Bed a. Ready Mix Concrete b. Coco Lumber - 4 uses c. Base Course
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
510(1)
Bed Course Granular Material cu.m. in-place 1.25
Designation
No. of Person
No. of Hours
Hourly Rate
1 4
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1
1
123.00
Unit
Quantity
Unit Cost
cu.m.
1.15
580.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Plate Compactor Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 cu.m. in-place E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Aggregate Subbase Course (w/ 15% Shrinkage Factor)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
510(2)
Concrete Slope Protection cu.m. in-place 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 4 8
1 1 1
109.19 79.70 61.44
2 4
1 1
79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1 1 1
1 0.05 0.10 0.05 0.05 0.05
172.00 1,065.00 840.00 148.88 219.75 351.50
Unit
Quantity
Unit Cost
bag cu.m. l.m. sq.m. cu.m. cu.m. kg. pc. bd.ft. kg. kg.
8.40 0.50 0.21 0.015 1 0.016 * 26.03 0.48 18.76 0.521 0.188
220.00 850.00 144.67 275.00 650.00 650.00 40.00 700.00 40.00 47.00 68.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer Installation of Formworks & Rebars a. Skilled Laborer b. Laborer Sub - Total for A Name and Capacity B. Equipment a. One Bagger Mixer b. Water Truck (1000 gal.) c. Backhoe (Wheel Type 0.28 cu.m.) d. Concrete Vibrator e. Bar Cutter f. Bar Bender Minor Tools (10% Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 cu.m. in-place E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Sand c. Weep Holes (PVC) d. Filter Cloth e. Gravel f. Granular Filter f. Reinforcing Steel Bar g. Marine Plywood 1/2" x 4' x 8' - 4 uses h. Lumber - 4 uses i. #16 GI Tie Wire (2% of RSB) j. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J. K. *
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost Note: RSB quantity is variable based on approved plan.
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
511(1)
Gabions cu.m. 2.50
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 8
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
Unit
Quantity
Unit Cost
pc.
0.50
2,900.00
cu.m.
1.05
920.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment Note: Exclude Excavation Works Backhoe excluded, excavation should be separate as the quantity is variable.
Sub - Total for B C. Total (A + B) D. Output per hour = 2.50 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Gabion Wire Mesh (1 x 1 x 2) (w/ complete accessories) b. Boulders
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
511(2)
Mattresses cu.m. 3.125
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 8
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
Unit
Quantity
Unit Cost
pc.
0.28
5,000.00
cu.m.
1.05
920.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment Note: Exclude Excavation Works Backhoe excluded, excavation should be separate as the quantity is variable.
Sub - Total for B C. Total (A + B) D. Output per hour = 3.125 cu.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Mattresses (6 x 2 x 0.3 ) (w/ complete accessories) b. Boulders
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
511(3)
Filter Cloth sq.m. 100.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 8
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.25
1,102.00
Unit
Quantity
Unit Cost
sq.m.
1.05
275.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (10 T)
Sub - Total for B C. Total (A + B) D. Output per hour = 100.00 sq.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Filter Cloth Miscellaneous (5% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
1,102.00 51.44
1,153.44 1,667.79 444.74 Amount
0.00 444.74 40.03 35.58 62.44 582.79
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
1,102.00 51.44
1,153.44 1,667.79 606.47 Amount
0.00 606.47 54.58 48.52 85.15
794.71
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
1,102.00 51.44
1,153.44 1,667.79 833.89 Amount
0.00 833.89 75.05 66.71 117.08
1,092.73
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
1,102.00 51.44
1,153.44 1,667.79 1,111.86 Amount
0.00 1,111.86 100.07 88.95 156.10
1,456.98
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
54.60 39.85 61.44
155.89 Amount
275.50 50.00 15.59
341.09 496.97 496.97 Amount
0.00 496.97 44.73 39.76 69.78
651.23
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 491.52
760.11 Amount
38.01
38.01 798.12 532.08 Amount
966.00 9.66
975.66 1,507.74 135.70 120.62 211.69
1,975.74
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
420.00 25.72
445.72 960.07 768.05 Amount
850.50 8.51
859.01 1,627.06 146.44 130.16 228.44
2,132.10
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
630.00 25.72
655.72 1,170.07 1,170.07 Amount
777.00 7.77
784.77 1,954.84 175.94 156.39 274.46
2,561.62
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
840.00 25.72
865.72 1,380.07 1,840.09 Amount
682.50 6.83
689.33 2,529.42 227.65 202.35 355.13
3,314.55
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 491.52
760.11 Amount
172.00 53.25 38.01
263.26 1,023.37 818.69 Amount
660.00 212.50 9.75 43.40 4.13 966.00 18.96
1,914.73 2,733.43 246.01 218.67 383.77
3,581.88
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
172.00 53.25 420.00 25.72
670.97 1,185.32 1,185.32 Amount
550.00 178.50 9.75 43.40 4.13 850.50 16.36
1,652.64 2,837.96 255.42 227.04 398.45 3,718.86
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
172.00 53.25 630.00 25.72
880.97 1,395.32 1,860.42 Amount
484.00 153.00 9.75 43.40 4.13 766.50 14.61
1,475.38 3,335.81 300.22 266.86 468.35 4,371.24
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
172.00 53.25 840.00 25.72
1,090.97 1,605.32 3,210.64 Amount
396.00 127.50 9.75 43.40 4.13 682.50 12.63
1,275.91 4,486.54 403.79 358.92 629.91 5,879.17
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 79.70 122.88
311.77 Amount
31.18
31.18 342.95 342.95 Amount
945.00
945.00 1,287.95 115.92 103.04 180.83 1,687.73
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 491.52
760.11 Amount
172.00 53.25 84.00 76.01
385.26 1,145.37 733.04 Amount
1,210.00 255.00 13.00 43.40 4.13 966.00 24.92
2,516.44 3,249.48 292.45 259.96 456.23 4,258.12
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 491.52
760.11 Amount
172.00 53.25 84.00 76.01
385.26 1,145.37 818.12 Amount
924.00 223.13 13.00 43.40 4.13 510.30 341.25 36.72
2,095.92 2,914.04 262.26 233.12 409.13 3,818.56
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 491.52
760.11 Amount
76.01
76.01 836.12 267.56 Amount
966.00
966.00 1,233.56 111.02 98.68 173.19 1,616.46
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 79.70 122.88
311.77 Amount
1,772.00 200.00 31.18
2,003.18 2,314.95 578.74 Amount
2,090.00 175.00 160.00 10.88
2,435.88 3,014.62 271.32 241.17 423.25 3,950.35
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
1,729.00 1,800.00 92.75 11.36
3,633.11 4,147.46 414.75 Amount
2,304.00 69.12
2,373.12 2,787.87 250.91 223.03 391.42 3,653.22
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 245.76
514.35 Amount
1,729.00 1,800.00 97.75 11.36 266.25
3,904.36 4,418.71 441.87 Amount
2,304.00 230.40 25.34
2,559.74 3,001.62 270.15 240.13 421.43 3,933.32
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 318.80 368.64 159.40 245.76 1,201.79 Amount
177.20 68.80 22.33 31.95 6.59 10.55 20.00 51.43 67.50 3.69 60.09
520.13 1,721.92 1,434.93 Amount
1,124.40 316.80 68.00 97.50 105.00 236.00 26.41 4.01 85.20 7.50 15.90 2,086.73 3,521.66 316.95 281.73 494.44 4,614.78
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 245.76
354.95 Amount
123.00 35.50
158.50 513.45 410.76 Amount
667.00
667.00 1,077.76 97.00 86.22 151.32 1,412.29
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 318.80 491.52 159.40 245.76 1,324.67 Amount
172.00 53.25 84.00 7.44 10.99 17.58 132.47
477.72 1,802.39 1,802.39 Amount
1,848.00 425.00 30.38 4.13 650.00 10.40 1,041.20 84.00 187.60 24.49 12.78
4,317.98 6,120.37 550.83 489.63 859.30 8,020.13
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 491.52
760.11 Amount
0.00 760.11 304.04 Amount
1,450.00 966.00
2,416.00 2,720.04 244.80 217.60 381.89 3,564.35
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 491.52
760.11 Amount
0.00 760.11 243.24 Amount
1,400.00 966.00
2,366.00 2,609.24 234.83 208.74 366.34 3,419.14
DETAILED UNIT PRICE ANALYSIS (DUPA)
Amount
109.19 159.40 491.52
760.11 Amount
275.50
275.50 1,035.61 10.36 Amount
288.75 14.44
303.19 313.54 28.22 25.08 44.02 410.87
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
600(1)
Concrete Curb (Cast in place) - 0.45m x 0.15/0.20m l.m. 17.50
Designation
No. of Person
No. of Hours
Hourly Rate
1 4 8
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.05
148.88 172.00 1,065.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. pc. bd.ft. kg.
0.72 0.04 0.08 0.28 12.16 0.12
220.00 850.00 650.00 700.00 40.00 68.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Concrete Vibrator b. One Bagger Mixer c. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 17.50 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Sand c. Gravel d. Plywood Marine, 1/2" thk. x 4' x 8 - 4 uses e. Form Lumber - 4 uses f. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
600(2)
Concrete Gutter (Cast in place) - 0.50m x 0.15m l.m. 17.50
Designation
No. of Person
No. of Hours
Hourly Rate
1 4 8
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.05
148.88 172.00 1,065.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. bd.ft. kg.
0.72 0.04 0.08 6.56 0.07
220.00 850.00 650.00 40.00 68.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Concrete Vibrator b. One Bagger Mixer c. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 17.50 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Sand c. Gravel d. Good Lumber - 4 uses e. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
600(3)
Concrete Curb and Gutter, Type A (Cast in place) - National Road l.m. 10.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 4 8
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1
1 1 0.05
148.88 172.00 1,065.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. pc. bd.ft. kg.
1.29 0.07 0.14 0.24 11.47 0.11
220.00 850.00 650.00 700.00 40.00 68.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Concrete Vibrator b. One Bagger Mixer c. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 10.30 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Sand c. Gravel d. Plywood Marine, 1/2" thk. x 4' x 8 - 4 uses e. Form Lumber - 4 uses f. Assorted CWN (1 kg./100 bd.ft. of Lumber) Miscellaneous (2% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
600(4)
Concrete Curb (Precast) pc. 4.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 1
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.50
961.20
Unit
Quantity
Unit Cost
l.m.
1.00
690.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Boom Truck Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 4.00 pc. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Fabricated Concrete Curb Miscellaneous (5% of materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
600(5)
Concrete Gutter (Precast) pc. 4.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 1
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.50
961.20
Unit
Quantity
Unit Cost
l.m.
1.00
680.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Boom Truck Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 4.00 pc. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Fabricated Concrete Gutter Miscellaneous (5% of materials)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
600(6)
Concrete Curb and Gutter (Precast) pc. 3.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 1
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.50
961.20
Unit
Quantity
Unit Cost
l.m.
1.00
1,750.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Boom Truck Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 3.00 pc. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Fabricated Concrete Curb and Gutter Miscellaneous (5% of materials)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
601(a)
Sidewalk (100mm thk.) sq.m. 161.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 4 12
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Transit Mixer (5 cu.m.)
4
1
1,279.00
b. Concrete Vibrator c. Batching Plant (30 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Concrete Screeder (5.5 Hp) f. Water Truck (1000 gal.) g. Concrete Saw, Blade Ø 14" (7.5 Hp) Minor Tools (5% of Labor)
2 1 1 1 1 1
1 1 1 1 1 1
148.88 1,208.03 1,733.00 545.00 1,065.00 167.38
Unit
Quantity
Unit Cost
lit. lit. l.m. cu.m. cu.m. bag
0.29 0.12 0.46 0.055 0.10 0.95
28.00 44.00 250.00 850.00 650.00 220.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 161.00 sq.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Curing Compound b. Asphalt Sealant c. Forms d. Sand e. Gravel f. Cement Note : Bed Course excluded
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
601(b)
Sidewalk (100mm thk.) sq.m. 20.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 4 12
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. One Bagger Mixer
1
1
172.00
b. Concrete Vibrator c. Water Truck (1000 gal.) d. Concrete Saw, Blade Ø 14" (7.5 Hp) Minor Tools (5% of Labor)
2 1 1
1 0.125 1
148.88 1,065.00 167.38
Unit
Quantity
Unit Cost
lit. lit. l.m. cu.m. cu.m. bag
0.29 0.12 0.46 0.055 0.10 0.95
28.00 44.00 250.00 850.00 650.00 220.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 20.00 sq.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Curing Compound b. Asphalt Sealant c. Forms d. Sand e. Gravel f. Cement Note : Bed Course excluded
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
602(1)a
Right-of-Way Monument ea. 2.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.20
148.88
1
0.05
1,102.00
Unit
Quantity
Unit Cost
cu.m. kg. pc. bd.ft. lit. kg. kg.
0.03 7.15 0.22 13.53 0.10 0.14 0.14
3,538.78 40.00 700.00 40.00 475.00 47.00 68.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Concrete Vibrator b. Cargo Truck (10 T) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Concrete Class "A" b. Reinforcing Steel Bar, Grade 40 c. Plywood, 1/2" x 4' x 8' - 4 uses d. Form Lumber, Good - 4 uses e. Reflectorized Paint, Marker f. # 16 Tie Wire (2% of RSB) g. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
602(1)b
Right-of-Way Monument (Precast) ea. 4.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.05
1,102.00
Name and Specification
Unit
Quantity
Unit Cost
a. Fabricated Right-of-Way Monument (delivered at site)
ea.
1
3,320.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (10 T) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 4.00 ea. E. Direct Unit Cost (C ÷ D)
F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
602(2)a
Maintenance Marker Post ea. 2.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.20
148.88
1
0.05
1,102.00
Unit
Quantity
Unit Cost
cu.m. kg. pc. bd.ft. lit. kg. kg.
0.03 7.00 0.22 13.53 0.10 0.14 0.14
3,400.00 40.00 700.00 40.00 475.00 47.00 68.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Concrete Vibrator b. Cargo Truck (10 T) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Concrete Class "A" b. Reinforcing Steel Bar, Grade 40 c. Plywood, 1/2" x 4' x 8' - 4 uses d. Form Lumber, Good - 4 uses e. Reflectorized Paint, Marker f. # 16 Tie Wire (2% of RSB) g. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
602(2)b
Maintenance Marker Post (Precast) ea. 4.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.05
1,102.00
Unit
Quantity
Unit Cost
ea.
1
1,650.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (10 T) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 4.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Fabricated Maintenance Marker Post (delivered at site)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
602(3)a
Kilometer Post ea. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1.50 1.50 1.50
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
a. Cargo Truck (10 T)
1
0.50
1,102.00
b. Concrete Vibrator Minor Tools (10% of Labor)
1
0.10
148.88
Unit
Quantity
Unit Cost
cu.m. kg. pc. bd.ft. bag cu.m. lit. kg. kg.
0.184 7.59 0.604 7.15 0.775 0.044 0.20 0.14 0.07
3,400.00 40.00 700.00 20.00 220.00 900.00 475.00 47.00 68.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Concrete Class "A" b. Reinforcing Steel Bar c. Plywood 1/2" x 4' x 8' - 2 uses d. Lumber - 2 uses e. Portland Cement f. Pebble g. Reflectorized Paint, Marker h. # 16 Tie Wire (2% of RSB) i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
602(3)b
Kilometer Post (Precast) ea. 2.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1.50 1.50 1.50
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1
0.50 0.05
1,102.00 148.88
Unit
Quantity
Unit Cost
ea. cu.m. lit.
1 0.095 0.20
4,150.00 3,400.00 475.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (10 T) b. Concrete Vibrator Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output = 2.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Fabricated Kilometer Post b. Concrete Class "A" c. Reflectorized Paint, Marker
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
602(4)
Guide Post ea. 50.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
Unit
Quantity
Unit Cost
ea. ea.
1 1
1,240.00 85.00
A. Labor a. Construction Foreman b. Laborer
Sub - Total for A Name and Capacity B. Equipment Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Guide Post (Portable) b. Post Reflector Miscellaneous (5% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
603(1)
Cable Wire Guardrail l.m. 1.15
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 8
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1
1 1 0.10 0.25
172.00 148.88 1,065.00 712.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. set kg. set ea. unit sq.m. set
4.18 0.22 0.43 0.27 4.92 0.22 0.33 0.11 0.11 0.65
220.00 850.00 650.00 *1,800.00 186.44 *750.00 *350.00 *1,200.00 *295.00 *1,000.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. One Bagger Mixer b. Concrete Vibrator c. Water Truck (1000 gal.) d. Cargo Truck (5 T) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.15 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Sand c. Gravel d. Guardrail Post e. Galvanized Wire Rope (1.21 kg./m) f. Check Rope g. Hook Bolt h. Anchor Bracket i. Wire Mesh j. Tension Fittings Miscellaneous (5% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost * Tentative Canvass Price
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
603(3)a
Metal Guardrails (Metal Beam) including Concrete Post l.m. 4.20
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1
0.50 0.50 0.05 0.25
172.00 148.88 1,065.00 1,102.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. l.m. pc. bd.ft. kg. kg. kg. pc. pc.
0.33 0.018 0.036 1 0.25 8 4 0.08 0.08 0.50 2
220.00 850.00 650.00 1,950.00 700.00 40.00 40.00 47.00 68.00 28.00 21.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. One Bagger Mixer b. Concrete Vibrator c. Water Truck (1000 gal.) d. Cargo Truck (10 T) Minor Tools (5 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 4.20 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Sand c. Gravel d. Metal Beam Guardrail e. Plywood Marine, 1/2" thk. x 4' x 8' - 4 uses f. Lumber - 4 uses g. Reinforcing Steel Bars, Grade 40 h. Tie Wire (2% of RSB) i. Assorted CWN (1 kg./100 bd.ft. of Lumber) j. Bolt, Nut & Washer 5/8" dia. x 9" k. Bolt, Nut & Washer 5/8" dia. x 1"
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
603(3)b
Metal Beam End Piece ea. 6.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
1
1,102.00
Unit
Quantity
Unit Cost
ea.
1.00
1,350.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (10 T) Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 6.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Metal Guardrail End Piece
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
603(4)
Guardrail (Timber) l.m. 5.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 4
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.50
1,102.00
Unit
Quantity
Unit Cost
bd.ft. bd.ft. pc.
14.67 6.67 1.60
90.00 55.00 350.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (10 T) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 5.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Lumber, 8" x 8" x 5.5' Treated Post (Tanguile) b. Lumber, 3" x 8" Plank (Tanguile) - Untreated c. Carriage Bolt, 1/2"Ø x 12" Miscellaneous (5% of Materials)
Note: Exclude Excavation Works
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
604(1)
Fencing (Barbed Wire) l.m. 18.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.10
391.00
Unit
Quantity
Unit Cost
l.m. kg. pc.
1 0.52 0.67
15.00 48.00 81.15
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Welding Machine Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 18.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 3-Strand Galvanized Barbed Wire, Ga 12.5 b. 50mmx50mmx6m Angle Bar c. Ga. 9 Twisted Wire Fastener Miscellaneous (2% of Materials, Welding Rod & etc.)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
604(2)
Fencing (Chain Link Fence Fabric) l.m. 5.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 8
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1
1 0.50 0.10 0.50
172.00 148.88 1,065.00 391.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. l.m. pc. pc. pc. kg. kg. l.m.
1.623 0.085 0.171 1 0.03 0.12 0.50 0.14 0.30 2
220.00 850.00 650.00 661.67 1,500.00 1,140.00 1,140.00 48.00 40.00 134.44
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. One Bagger Mixer b. Concrete Vibrator c. Water Truck (1000 gal.) d. Welding Machine Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 5.00 l.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Sand c. Gravel, G1 d. Chainlink Fence, 4' e. G.I. Pipe 2" dia. (corner or pull posts) f. G.I. Pipe 1 1/4" dia. (line post) g. G.I. Pipe 1 1/4" dia. (brace) h. Flat Bar, 3/16" x 3/4" (stretch bar) i. Plain Bar, 3/8" dia. (truss rod) j. Tension Wire, 0.177" dia. Miscellaneous (5% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
604(3)
Fencing (Post) ea. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 2 2
1.50 1.50 1.50
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1 1 1 1
0.75 0.50 0.50 0.05
172.00 219.75 351.50 1,065.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. kg. kg. pc. bd.ft. kg.
2.105 0.095 0.185 20.615 0.412 0.760 22.695 0.227
220.00 850.00 650.00 40.00 47.00 350.00 20.00 68.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. One Bagger Mixer b. Bar Cutter c. Bar Bender d. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output = 1.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Cement b. Sand c. Gravel d. Reinforcing Steel Bar e. # 16 Tie Wire (2% of RSB) f. Plywood 1/4' x 4' x 8' - 2 uses g. Lumber - 2 uses h. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output
: : :
604(4)
Fencing (Gates) - (Height 3m. & Length 4.24m.) ea. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
3 3 3
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
2
391.00
Unit
Quantity
Unit Cost
pc. l.m. gal. kg. kg. kg.
5 4.24 1.06 1.607 9.743 0.006
1,550.00 3,300.00 565.00 40.00 48.00 90.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Welding Machine Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output = 1.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. 50 mm. Ø G.I. Pipe, Schedule 40 b. Cyclone Wire Galvanized 10' Gauge 10 c. Aluminum Paint d. 6mm dia. Plain Bar e. Gate Lock/Hinge (12mm thk. Plate) b. Welding Rod (1 kg./2000 kg. of Steel)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
605(1)a
Danger/Warning Signs (60cm Triangle) ea. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.25
712.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. bd.ft. m. kg. pc. pc. kg.
0.48 0.025 0.050 8 3.10 2 12 1 0.08
220.00 850.00 650.00 40.00 530.00 48.00 10.00 2,800.00 68.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (5 T) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Aluminum Sheet i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
605(1)b
Danger/Warning Signs (90cm Triangle) ea. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.25
712.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. bd.ft. m. kg. pc. pc. kg.
0.48 0.025 0.050 8 3.10 2 12 1 0.08
220.00 850.00 650.00 40.00 530.00 48.00 10.00 4,200.00 68.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (5 T) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Aluminum Sheet i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
605(2)a
Regulatory Signs (60cm Triangle) ea. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.25
712.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. bd.ft. m. kg. pc. pc. kg.
0.48 0.025 0.050 8 3.10 2 12 1 0.08
220.00 850.00 650.00 40.00 530.00 48.00 10.00 2,800.00 68.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (5 T) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Aluminum Sheet i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
605(2)b
Regulatory Signs (90cm Triangle) ea. 1.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Hourly Rate
1
0.25
712.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. bd.ft. m. kg. pc. pc. kg.
0.48 0.025 0.050 8 3.10 2 12 1 0.08
220.00 850.00 650.00 40.00 530.00 48.00 10.00 4,200.00 68.00
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Cargo Truck (5 T) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Aluminum Sheet i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
605(2)c
Regulatory Signs (60cm Octagon) ea. 1.00
Designation
No. of Person
No. of Hours
1 1 2
1 1 1
No of Units
No. of Hours
1
0.25
Unit
Quantity
bag cu.m. cu.m. bd.ft. m. kg. pc. pc. kg.
0.48 0.025 0.050 8 3.10 2 12 1 0.08
A. Labor 109.19 318.80 491.52
a. Construction Foreman b. Skilled Laborer c. Laborer
919.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
148.88 172.00 53.25 91.95
466.08 1,385.59 79.18
a. Cargo Truck (5 T) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
158.40 34.00 52.00 49.00 121.60 8.16
423.16 502.34 45.21 40.19 70.53 658.26
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Aluminum Sheet i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
605(2)d
Regulatory Signs (90cm Octagon) ea. 1.00
Designation
No. of Person
No. of Hours
1 1 2
1 1 1
No of Units
No. of Hours
1
0.25
Unit
Quantity
bag cu.m. cu.m. bd.ft. m. kg. pc. pc. kg.
0.48 0.025 0.050 8 3.10 2 12 1 0.08
A. Labor 109.19 318.80 491.52
a. Construction Foreman b. Skilled Laborer c. Laborer
919.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
148.88 172.00 53.25 91.95
466.08 1,385.59 79.18
a. Cargo Truck (5 T) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
158.40 34.00 52.00 65.60 4.76
314.76 393.94 35.45 31.51 55.31 516.21
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Aluminum Sheet i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
605(3)a
Informative Signs (12"x24") ea. 1.00
Designation
No. of Person
No. of Hours
1 1 2
1 1 1
No of Units
No. of Hours
1
0.25
Unit
Quantity
bag cu.m. cu.m. bd.ft. m. kg. pc. pc. kg.
1.320 0.073 0.145 8 3.10 2 12 1 0.08
A. Labor 109.19 318.80 491.52
a. Construction Foreman b. Skilled Laborer c. Laborer
919.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
148.88 172.00 53.25 91.95
466.08 1,385.59 134.52
a. Cargo Truck (5 T) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
283.80 59.50 91.00 42.00 114.70 7.48 11.97
610.45 744.97 67.05 59.60 104.59 976.21
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Aluminum Sheet i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
605(3)b
Informative Signs (12"x48") ea. 1.00
Designation
No. of Person
No. of Hours
1 1 2
1 1 1
No of Units
No. of Hours
1
0.25
Unit
Quantity
bag cu.m. cu.m. bd.ft. m. kg. pc. pc. kg.
1.320 0.073 0.145 8 3.10 2 12 1 0.08
A. Labor 109.19 79.70 61.44
a. Construction Foreman b. Skilled Laborer c. Laborer
250.33
Sub - Total for A
Amount
Name and Capacity B. Equipment
480.60 25.03
505.63 755.96 188.99
a. Cargo Truck (5 T) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
690.00 34.50
724.50 913.49 82.21 73.08 128.25 1,197.04
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Aluminum Sheet i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
605(3)c
Informative Signs (18"x24") ea. 1.00
Designation
No. of Person
No. of Hours
1 1 2
1 1 1
No of Units
No. of Hours
1
0.25
Unit
Quantity
bag cu.m. cu.m. bd.ft. m. kg. pc. pc. kg.
1.320 0.073 0.145 8 3.10 2 12 1 0.08
A. Labor 109.19 79.70 61.44
a. Construction Foreman b. Skilled Laborer c. Laborer
250.33
Sub - Total for A
Amount
Name and Capacity B. Equipment
480.60
a. Cargo Truck (5 T)
25.03
Minor Tools (10 % of Labor)
505.63 755.96 188.99
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
680.00 34.00
714.00 902.99 81.27 72.24 126.78
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Aluminum Sheet i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% 8% 12%
1,183.28
K. Total Unit Cost
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
605(3)d
Informative Signs (18"x48") ea. 1.00
Designation
No. of Person
No. of Hours
1 1 2
1 1 1
No of Units
No. of Hours
1
0.25
Unit
Quantity
bag cu.m. cu.m. bd.ft. m. kg. pc. pc. kg.
1.320 0.073 0.145 8 3.10 2 12 1 0.08
A. Labor 109.19 79.70 61.44
a. Construction Foreman b. Skilled Laborer c. Laborer
250.33
Sub - Total for A
Amount
Name and Capacity B. Equipment
480.60
a. Cargo Truck (5 T)
25.03
Minor Tools (10 % of Labor)
505.63 755.96 251.99
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
1,750.00 87.50
1,837.50 2,089.49 188.05 167.16 293.36
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Aluminum Sheet i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% 8% 12%
2,738.06
K. Total Unit Cost
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
606(1)
Pavement Marking (Premix Reflectorized) sq.m. 10.00
Designation
No. of Person
No. of Hours
1 1 2
1 1 1
No of Units
No. of Hours
1
0.05
Unit
Quantity
lit.
1.00
A. Labor 109.19 318.80 737.28
a. Construction Foreman b. Skilled Laborer c. Laborer
1,165.27
Sub - Total for A
Amount
Name and Capacity B. Equipment
5,116.00
a. Cargo Truck (5 T)
297.76 1,208.03 1,733.00 545.00 1,065.00 167.38 58.26
Minor Tools (5% of Labor)
10,190.43 11,355.70 70.53
Sub - Total for B C. Total (A + B) D. Output per hour = 10.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
8.12 5.28 115.00 46.75 65.00 209.00
449.15 519.68 46.77 41.57 72.96
a. Pavement Markings (White) Miscellaneous (5% of above)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% 8% 12%
680.99
K. Total Unit Cost
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
606(2)a
Pavement Markings (Reflectorized Thermoplastic) sq.m. 10.00
Designation
No. of Person
No. of Hours
1 1 2
1 1 1
No of Units
No. of Hours
1
0.05
Unit
Quantity
lit.
1.00
A. Labor 109.19 318.80 737.28
a. Construction Foreman b. Skilled Laborer c. Laborer
1,165.27
Sub - Total for A
Amount
Name and Capacity B. Equipment
172.00
a. Cargo Truck (5 T)
297.76 133.13 167.38 58.26
828.53 1,993.80 99.69
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 10.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
8.12 5.28 115.00 46.75 65.00 209.00
449.15 548.84 49.40 43.91 77.06
a. Reflectorized Traffic Paint (White) Miscellaneous (5% of above)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% 8% 12%
719.20
K. Total Unit Cost
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
606(2)b
Pavement Markings (Reflectorized Thermoplastic) sq.m. 10.00
Designation
No. of Person
No. of Hours
1 1 2
1 1 1
No of Units
No. of Hours
1
0.05
Unit
Quantity
lit.
1.00
A. Labor 109.19 79.70 122.88
a. Construction Foreman b. Skilled Laborer c. Laborer
311.77
Sub - Total for A
Amount
Name and Capacity B. Equipment
29.78
a. Cargo Truck (5 T)
55.10 31.18
116.05 427.82 213.91
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 10.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
106.16 286.00 38.50 135.30 47.50 6.58 9.52
629.56 843.47 75.91 67.48 118.42
a. Reflectorized Traffic Paint (Yellow) Miscellaneous (5% of above)
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% 8% 12%
1,105.29
K. Total Unit Cost
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
607
Reflective Pavement Studs (4" RPM) ea. 10.00
Designation
No. of Person
No. of Hours
1 3
1 1
No of Units
No. of Hours
A. Labor 109.19 79.70 122.88
a. Construction Foreman b. Laborer
311.77
Sub - Total for A
Amount
Name and Capacity B. Equipment
55.10
a. Drill, CP-8 with attachment
1
1
31.18
b. Cargo Truck (5 T) c. Compressor (20 Hp) Minor Tools (5% of Labor)
1 1
0.25 1
Unit
Quantity
pc.
1
lit.
0.012
86.28 398.05 99.51
Sub - Total for B C. Total (A + B) D. Output per hour = 10.00 ea. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
3,320.00
3,320.00 3,419.51 307.76 273.56 480.10
a. Reflective Stud Catcheye Raised Surface 100mm x 100mm (type depends on the req.) b. Concrete Epoxy A & B
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% 8% 12%
4,480.93
K. Total Unit Cost
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
Amount
608(1)
Furnishing and Placing Topsoil cu.m. 1.25
Designation
No. of Person
No. of Hours
1 2 2
1 1 1
No of Units
No. of Hours
1
1
Unit
Quantity
cu.m.
1.05
A. Labor 109.19 79.70 122.88
a. Construction Foreman b. Skilled Laborer c. Laborer
311.77
Sub - Total for A
Amount
Name and Capacity B. Equipment
29.78
a. Plate Compactor
55.10 31.18
Minor Tools (10% of Labor)
116.05 427.82 213.91
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 cu.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
102.00 280.00 38.50 135.30 47.50 6.58 9.52
619.40 833.31 75.00 66.66 117.00
a. Topsoil
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% 8% 12%
1,091.97
K. Total Unit Cost
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
Amount
608(2)
Placing Topsoil cu.m. 1.25
Designation
No. of Person
No. of Hours
1 2 2
1 1 1
No of Units
No. of Hours
1
1
Unit
Quantity
A. Labor 109.19 79.70 122.88
a. Construction Foreman b. Skilled Laborer c. Laborer
311.77
Sub - Total for A
Amount
Name and Capacity B. Equipment
55.10
a. Plate Compactor
31.18
Minor Tools (10% of Labor)
86.28 398.05 99.51
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 cu.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
1,650.00
1,650.00 1,749.51 157.46 139.96 245.63
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% 8% 12%
2,292.56
K. Total Unit Cost
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
609
Sprigging sq.m. 35.00
Designation
No. of Person
No. of Hours
1 2 2
1 1 1
No of Units
No. of Hours
1
0.25
Unit
Quantity
sq.m. kg.
1.05 0.10
A. Labor 163.79 119.55 184.32
a. Construction Foreman b. Skilled Laborer c. Laborer
467.66
Sub - Total for A
Amount
Name and Capacity B. Equipment
551.00
a. Water Truck (1000 gal.)
14.89 46.77
Minor Tools (10% of Labor)
612.65 1,080.31 1,080.31
Sub - Total for B C. Total (A + B) D. Output per hour = 35.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
625.60 303.60 211.40 71.50 170.50 39.60 95.00 6.58 4.76
1,528.54 2,608.85 234.80 208.71 366.28
a. Sprigs b. Fertilizer
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% 8% 12%
3,418.64
K. Total Unit Cost
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
610
Sodding sq.m. 25.00
Designation
No. of Person
No. of Hours
1 8
1 1
No of Units
No. of Hours
1
0.50
Unit
Quantity
sq.m.
1.05
A. Labor 163.79 119.55 184.32
a. Construction Foreman b. Laborer
467.66
Sub - Total for A
Amount
Name and Capacity B. Equipment
551.00 7.44 46.77
605.21 1,072.86 536.43
a. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 25.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
4,150.00 323.00 95.00
4,568.00 5,104.43 459.40 408.35 716.66 6,688.85
a. Sods
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
611(1)
Trees (Furnishing and Transplanting), 150mm dia. or less ea. 1.00
Designation
No. of Person
No. of Hours
1 1 2
1 1 1
No of Units
No. of Hours
1 1 1
1 1 0.50
Unit
Quantity
pc. kg. pc. sq.m. kg.
1 3 3 3 0.25
A. Labor 109.19 122.88
a. Construction Foreman b. Skilled Laborer c. Laborer
232.07
Sub - Total for A
Amount
Name and Capacity B. Equipment
23.21
a. Cargo Truck (10 T) b. Backhoe (0.80 cu.m.) c. Water Truck (1000 gal.) Minor Tools (10% of Labor) Note: Includes watering for three (3) months
23.21 255.28 5.11
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
1,240.00 85.00 66.25
1,391.25 1,396.36 125.67 111.71 196.05 1,829.78
a. Trees (Delivered at Site) b. Fertilizers c. Bamboo Pole d. Polyethylene Sheets e. Tie Wire
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
611(2)
Trees (Transplanting), 150mm dia. or less ea. 1.00
Designation
No. of Person
No. of Hours
1 1 2
1 1 1
No of Units
No. of Hours
1 1 1
1 1 0.50
Unit
Quantity
kg. pc. sq.m. kg.
3 3 3 0.25
A. Labor 109.19 159.40 491.52
a. Construction Foreman b. Skilled Laborer c. Laborer
760.11
Sub - Total for A
Amount
Name and Capacity B. Equipment
172.00 148.88 106.50 178.00 76.01
681.39 1,441.50 1,253.48
a. Cargo Truck (10 T) b. Backhoe (0.80 cu.m.) c. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
919.60 187.00 279.50 486.00 917.28 165.00 115.50 132.00 32.45 650.00 194.22 4,078.55 5,332.03 479.88 426.56 748.62 6,987.09
a. Fertilizers b. Bamboo Pole c. Polyethylene Sheets d. Tie Wire
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
612(1)
Reflectorized Thermoplastic Pavement Markings (White) sq.m. 25.00
Designation
No. of Person
No. of Hours
1 2 6
1 1 1
No of Units
No. of Hours
1 1 1
1 1 1
Unit
Quantity
bag bag liter cyl. cyl. kg.
0.325 0.033 0.120 0.004 0.002 0.125
A. Labor 109.19 159.40 245.76
a. Construction Foreman b. Skilled Laborer c. Laborer
514.35
Sub - Total for A
Amount
Name and Capacity B. Equipment
86.00 74.44 53.25 275.50 25.72
514.91 1,029.26 245.06
a. Cargo Truck/Delivery Truck (5 T) b. Applicator Machine c. Kneading Machine Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 25.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
72.60 15.30 23.40 1,950.00 43.75 80.00 160.00 3.76 5.44 14.00 42.00
2,410.25 2,655.31 238.98 212.42 372.81 3,479.52
a. Thermoplastic Paint (White) b. Glass Beads c. Primer d. LPG (50 kg.) e. LPG (12 kg.) f. Calsumine Miscellaneous (5% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
612(2)
Reflectorized Thermoplastic Pavement Markings (Yellow) sq.m. 25.00
Designation
No. of Person
No. of Hours
1 2 6
1 1 1
No of Units
No. of Hours
1 1 1
1 1 1
Unit
Quantity
bag bag liter cyl. cyl. kg.
0.325 0.033 0.120 0.004 0.002 0.125
A. Labor 109.19 79.70 122.88
a. Construction Foreman b. Skilled Laborer c. Laborer
311.77
Sub - Total for A
Amount
Name and Capacity B. Equipment
1,102.00 15.59
1,117.59 1,429.36 238.23
a. Cargo Truck/Delivery Truck (5 T) b. Applicator Machine c. Kneading Machine Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 25.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
1,350.00
1,350.00 1,588.23 142.94 127.06 222.99 2,081.21
a. Thermoplastic Paint (Yellow)) b. Glass Beads c. Primer d. LPG (50 kg.) e. LPG (12 kg.) f. Calsumine Miscellaneous (5% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
613
Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types) kg. 20.00 .
Designation
No. of Person
No. of Hours
1 6
1 1
No of Units
No. of Hours
1
1
Unit
Quantity
kg.
1.05
A. Labor 109.19 159.40 245.76
a. Construction Foreman b. Laborer
514.35
Sub - Total for A
Amount
Name and Capacity B. Equipment
551.00 51.44
602.44 1,116.79 223.36
a. Asphalt Kettle/Drum Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 20.00 kg. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
1,320.30 366.85 560.00 112.36
2,359.51 2,582.86 232.46 206.63 362.63 3,384.59
a. Blown Asphalt Miscellaneous (5% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
620(a)
Chevron Signs (450mmx600mm) ea. 1.00
Designation
No. of Person
No. of Hours
1 1 2
1 1 1
No of Units
No. of Hours
1
0.25
Unit
Quantity
bag cu.m. cu.m. bd.ft. m. kg. pc. pc. pc. kg.
0.48 0.025 0.050 8 3.25 5 3 12 2 0.08
A. Labor 109.19 79.70 122.88
a. Construction Foreman b. Skilled Laborer c. Laborer
311.77
Sub - Total for A
Amount
Name and Capacity B. Equipment
39.10 31.18
70.28 382.05 21.22
a. Cargo Truck (5 T) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
15.00 24.96 54.37 1.89
96.22 117.44 10.57 9.40 16.49 153.90
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses e. 75mm Ø G.I. Pipe f. G.I. Flat Bar, 1 1/2"x1/8" g. G.I. Bolts w/ Nuts & Washer, 5mm Ø h. G.I. Bolts w/ Nuts & Washer, 2mm Ø i. Sign Face, 3mm thk. Aluminum Sheet j. Assorted CWN (1 kg./100 bd.ft. of Lumber) Miscellaneous (0.3% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
620(b)
Chevron Signs (600mmx800mm) ea. 1.00
Designation
No. of Person
No. of Hours
1 1 2
1 1 1
No of Units
No. of Hours
1
0.25
Unit
Quantity
bag cu.m. cu.m. bd.ft. m. kg. pc. pc. pc. kg.
0.48 0.025 0.050 8 3.45 5 3 12 2 0.08
A. Labor 109.19 159.40 491.52
a. Construction Foreman b. Skilled Laborer c. Laborer
760.11
Sub - Total for A
Amount
Name and Capacity B. Equipment
172.00 74.44 106.50 195.50 76.01
624.45 1,384.56 276.91
a. Cargo Truck (5 T) Minor Tools (10 % of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00 ea. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
357.06 72.25 111.15 661.67 45.00 136.80 570.00 6.72 12.00 268.89 112.08
2,353.61 2,630.53 236.75 210.44 369.33 3,447.04
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses e. 75mm Ø G.I. Pipe f. G.I. Flat Bar, 1 1/2"x1/8" g. G.I. Bolts w/ Nuts & Washer, 5mm Ø h. G.I. Bolts w/ Nuts & Washer, 2mm Ø i. Sign Face, 3mm thk. Aluminum Sheet j. Assorted CWN (1 kg./100 bd.ft. of Lumber) Miscellaneous (0.2% of Materials)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
622(1)a
Bio-Engineering Solutions (Coco-net) sq.m. 50.00
Designation
No. of Person
No. of Hours
1 8
1 1
No of Units
No. of Hours
1
0.25
Unit
Quantity
sq.m.
1.05
A. Labor 163.79 239.10 184.32
a. Construction Foreman b. Laborer
587.21
Sub - Total for A
Amount
Name and Capacity B. Equipment
129.00 109.88 175.75 53.25 58.72
526.60 1,113.80 1,113.80
a. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
463.10 80.75 120.25 824.60 19.36 133.00 226.95 15.44
1,883.45 2,997.25 269.75 239.78 420.81 3,927.60
a. Erosion Control Net CGN 400 w/ 5 % wastage (Price includes bamboo pegs)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
622(1)b
Bio-Engineering Solutions (Coco-net) sq.m. 50.00
Designation
No. of Person
No. of Hours
1 8
1 1
No of Units
No. of Hours
1
0.25
Unit
Quantity
sq.m.
1.05
A. Labor 327.57 239.10 368.64
a. Construction Foreman b. Laborer
935.31
Sub - Total for A
Amount
Name and Capacity B. Equipment
782.00 93.53
875.53 1,810.84 1,810.84
a. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
7,750.00 13,992.00 598.90 64.28 467.66 0.54
22,873.38 24,684.23 2,221.58 1,974.74 3,465.67 32,346.21
a. Erosion Control Net CGN 700 w/ 5 % wastage (Price includes bamboo pegs)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
622(2)a
Bio-Engineering Solutions (Coco-logs/Fascine) l.m. 15.00
Designation
No. of Person
No. of Hours
1 8
1 1
No of Units
No. of Hours
Unit
Quantity
l.m.
1.05
A. Labor 109.19 79.70 122.88
a. Construction Foreman b. Laborer
311.77
Sub - Total for A
Amount
Name and Capacity B. Equipment
178.00 31.18
209.18 520.95 520.95
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 15.00 l.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
105.60 21.25 32.50 80.00 1,643.00 96.00 120.00 2,800.00 5.44
4,903.79 5,424.74 488.23 433.98 761.63 7,108.58
a. Coco Fiber Roll (CGR 200) (Price includes nylon ropes and live stakes)
`
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
622(2)b
Bio-Engineering Solutions (Coco-logs/Fascine) l.m. 15.00
Designation
No. of Person
No. of Hours
1 8
1 1
No of Units
No. of Hours
Unit
Quantity
l.m.
1.05
A. Labor 109.19 79.70 122.88
a. Construction Foreman b. Laborer
311.77
Sub - Total for A
Amount
Name and Capacity B. Equipment
178.00 31.18
209.18 520.95 520.95
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 15.00 l.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
105.60 21.25 32.50 80.00 1,643.00 96.00 120.00 4,200.00 5.44
6,303.79 6,824.74 614.23 545.98 958.19 8,943.14
a. Coco Fiber Roll (CGR 300) (Price includes nylon ropes and live stakes)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
622(3)a
Bio-Engineering Solutions (Vegetation) sq.m. 62.50
Designation
No. of Person
No. of Hours
1 2
1 1
No of Units
No. of Hours
1 1
1 1
Unit
Quantity
sq.m.
1.05
A. Labor 109.19 79.70 122.88
a. Construction Foreman b. Laborer
311.77
Sub - Total for A
Amount
Name and Capacity B. Equipment
178.00 31.18
209.18 520.95 520.95
a. Hydroseeding Machine b. Water Truck (1000 gal.) (including maintenance time)
Sub - Total for B C. Total (A + B) D. Output per hour = 62.50 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
105.60 21.25 32.50 80.00 1,643.00 96.00 120.00 2,800.00 5.44
4,903.79 5,424.74 488.23 433.98 761.63 7,108.58
a. Grass Cover (Price includes grass seeds, mulch, cocopeat & binding agent for hydroseeding)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
622(3)b
Bio-Engineering Solutions (Vegetation) sq.m. 35.00
Designation
No. of Person
No. of Hours
1 8
1 1
No of Units
No. of Hours
1
0.50
Unit
Quantity
sq.m.
1.05
A. Labor 109.19 79.70 122.88
a. Construction Foreman b. Laborer
311.77
Sub - Total for A
Amount
Name and Capacity B. Equipment
178.00 31.18
209.18 520.95 520.95
a. Water Truck (1000 gal.) Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 35.00 sq.m. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
105.60 21.25 32.50 80.00 1,643.00 96.00 120.00 4,200.00 5.44
6,303.79 6,824.74 614.23 545.98 958.19 8,943.14
a. Vetiver Grass System (Price includes cocopeat fertilizer)
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
9% 8% 12%
DETAILED UNIT PRICE ANALYSIS (DUPA) Regulatory Signs (60cm Octagon)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 79.70 122.88
311.77 Hourly Rate
Amount
712.00
178.00 31.18
209.18 520.95 520.95 Unit Cost
Amount
220.00 850.00 650.00 40.00 530.00 70.78 10.00 4,500.00 68.00
105.60 21.25 32.50 80.00 1,643.00 141.56 120.00 4,500.00 5.44
of G of G of (G + H + I) (G + H + I + J)
6,649.35 7,170.30 645.33 573.62 1,006.71 9,395.96
DETAILED UNIT PRICE ANALYSIS (DUPA) Regulatory Signs (90cm Octagon)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 79.70 122.88
311.77 Hourly Rate
Amount
712.00
178.00 31.18
209.18 520.95 520.95 Unit Cost
Amount
220.00 850.00 650.00 40.00 530.00 48.00 10.00 7,500.00 68.00
105.60 21.25 32.50 80.00 1,643.00 96.00 120.00 7,500.00 5.44
of G of G of (G + H + I) (G + H + I + J)
9,603.79 10,124.74 911.23 809.98 1,421.51 13,267.46
DETAILED UNIT PRICE ANALYSIS (DUPA) Informative Signs (12"x24")
Hourly Rate
Amount
109.19 79.70 61.44
109.19 79.70 122.88
311.77 Hourly Rate
Amount
712.00
178.00 31.18
209.18 520.95 520.95 Unit Cost
Amount
220.00 850.00 650.00 40.00 530.00 48.00 10.00 2,750.00 68.00
290.40 62.05 94.25 80.00 1,643.00 96.00 120.00 2,750.00 5.44
of G of G of (G + H + I) (G + H + I + J)
5,141.14 5,662.09 509.59 452.97 794.96 7,419.60
DETAILED UNIT PRICE ANALYSIS (DUPA) Informative Signs (12"x48")
Hourly Rate
Amount
109.19 79.70 61.44
109.19 79.70 122.88
311.77 Hourly Rate
Amount
712.00
178.00 31.18
209.18 520.95 520.95 Unit Cost
Amount
220.00 850.00 650.00 40.00 530.00 48.00 10.00 5,450.00 68.00
290.40 62.05 94.25 80.00 1,643.00 96.00 120.00 5,450.00 5.44
of G of G of (G + H + I) (G + H + I + J)
7,841.14 8,362.09 752.59 668.97 1,174.04 10,957.68
DETAILED UNIT PRICE ANALYSIS (DUPA) Informative Signs (18"x24")
Hourly Rate
Amount
109.19 79.70 61.44
109.19 79.70 122.88
311.77 Hourly Rate
Amount
712.00
178.00 31.18
209.18 520.95 520.95 Unit Cost
Amount
220.00 850.00 650.00 40.00 530.00 48.00 10.00 3,750.00 68.00
290.40 62.05 94.25 80.00 1,643.00 96.00 120.00 3,750.00 5.44
of G of G of (G + H + I)
6,141.14 6,662.09 599.59 532.97 935.36
(G + H + I + J)
8,730.00
DETAILED UNIT PRICE ANALYSIS (DUPA) Informative Signs (18"x48")
Hourly Rate
Amount
109.19 79.70 61.44
109.19 79.70 122.88
311.77 Hourly Rate
Amount
712.00
178.00 31.18
209.18 520.95 520.95 Unit Cost
Amount
220.00 850.00 650.00 40.00 530.00 48.00 10.00 8,200.00 68.00
290.40 62.05 94.25 80.00 1,643.00 96.00 120.00 8,200.00 5.44
of G of G of (G + H + I)
10,591.14 11,112.09 1,000.09 888.97 1,560.14
(G + H + I + J)
14,561.28
DETAILED UNIT PRICE ANALYSIS (DUPA) Pavement Marking (Premix Reflectorized)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 79.70 122.88
311.77 Hourly Rate
Amount
712.00
35.60 15.59
51.19 362.96 36.30 Unit Cost
Amount
450.00
450.00 22.50
of G of G of (G + H + I)
472.50 508.80 45.79 40.70 71.43
(G + H + I + J)
666.73
DETAILED UNIT PRICE ANALYSIS (DUPA) Pavement Markings (Reflectorized Thermoplastic)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 79.70 122.88
311.77 Hourly Rate
Amount
712.00
35.60 31.18
66.78 378.55 37.85 Unit Cost
Amount
450.00
450.00 22.50
of G of G of (G + H + I)
472.50 510.35 45.93 40.83 71.65
(G + H + I + J)
668.77
DETAILED UNIT PRICE ANALYSIS (DUPA) Pavement Markings (Reflectorized Thermoplastic)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 79.70 122.88
311.77 Hourly Rate
Amount
712.00
35.60 31.18
66.78 378.55 37.85 Unit Cost
Amount
475.00
475.00 23.75
of G of G of (G + H + I)
498.75 536.60 48.29 42.93 75.34
(G + H + I + J)
703.17
DETAILED UNIT PRICE ANALYSIS (DUPA)
Hourly Rate
Amount
109.19 61.44
109.19 184.32
293.51 Hourly Rate
Amount
201.25
201.25
712.00 189.00
178.00 189.00 14.68
582.93 876.44 87.64 Unit Cost
Amount
3,465.00
3,465.00
1,200.00
14.40
of G of G of (G + H + I)
3,479.40 3,567.04 321.03 285.36 500.81
(G + H + I + J)
4,674.25
DETAILED UNIT PRICE ANALYSIS (DUPA)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 159.40 122.88
391.47 Hourly Rate
Amount
123.00
123.00 39.15
162.15 553.62 442.89 Unit Cost
Amount
490.00
514.50
of G of G of (G + H + I)
514.50 957.39 86.17 76.59 134.42
(G + H + I + J)
1,254.57
DETAILED UNIT PRICE ANALYSIS (DUPA)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 159.40 122.88
391.47 Hourly Rate
Amount
123.00
123.00 39.15
162.15 553.62 442.89 Unit Cost
of G of G of (G + H + I)
Amount
0.00 442.89 39.86 35.43 62.18
(G + H + I + J)
580.37
DETAILED UNIT PRICE ANALYSIS (DUPA)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 159.40 122.88
391.47 Hourly Rate
Amount
1,065.00
266.25 39.15
305.40 696.87 19.91 Unit Cost
Amount
89.00 26.00
93.45 2.60
of G of G of (G + H + I)
96.05 115.96 10.44 9.28 16.28
(G + H + I + J)
151.95
DETAILED UNIT PRICE ANALYSIS (DUPA)
Hourly Rate
Amount
109.19 61.44
109.19 491.52
600.71 Hourly Rate
Amount
1,065.00
532.50 60.07
592.57 1,193.28 47.73 Unit Cost
Amount
89.00
93.45
of G of G of (G + H + I) (G + H + I + J)
93.45 141.18 12.71 11.29 19.82 185.00
DETAILED UNIT PRICE ANALYSIS (DUPA) Trees (Furnishing and Transplanting), 150mm dia. or less
Hourly Rate
Amount
109.19 79.70 61.44
109.19 79.70 122.88
311.77 Hourly Rate
Amount
1,102.00 1,537.00 1,065.00
1,102.00 1,537.00 532.50 31.18
3,202.68 3,514.45 3,514.45 Unit Cost
Amount
400.00 26.00 50.00 10.00 46.67
400.00 78.00 150.00 30.00 11.67
of G of G of (G + H + I) (G + H + I + J)
669.67 4,184.11 376.57 334.73 587.45 5,482.86
DETAILED UNIT PRICE ANALYSIS (DUPA)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 79.70 122.88
311.77 Hourly Rate
Amount
1,102.00 1,537.00 1,065.00
1,102.00 1,537.00 532.50 31.18
3,202.68 3,514.45 3,514.45 Unit Cost
Amount
26.00 50.00 10.00 46.67
78.00 150.00 30.00 11.67
of G of G of (G + H + I) (G + H + I + J)
269.67 3,784.11 340.57 302.73 531.29 4,958.70
DETAILED UNIT PRICE ANALYSIS (DUPA) Reflectorized Thermoplastic Pavement Markings (White)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 159.40 368.64
637.23 Hourly Rate
Amount
712.00 93.75 187.50
712.00 93.75 187.50 63.72
1,056.97 1,694.20 67.77 Unit Cost
Amount
1,565.00 650.00 160.00 3,800.00 735.00 3.00
508.63 21.45 19.20 15.20 1.47 0.38 28.32
of G of G of (G + H + I) (G + H + I + J)
594.64 662.40 59.62 52.99 93.00 868.01
DETAILED UNIT PRICE ANALYSIS (DUPA) Reflectorized Thermoplastic Pavement Markings (Yellow)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 159.40 368.64
637.23 Hourly Rate
Amount
712.00 93.75 187.50
712.00 93.75 187.50 63.72
1,056.97 1,694.20 67.77 Unit Cost
Amount
1,780.00 650.00 175.00 3,800.00 735.00 3.00
578.50 21.45 21.00 15.20 1.47 0.38 31.90
of G of G of (G + H + I) (G + H + I + J)
669.89 737.66 66.39 59.01 103.57 966.63
DETAILED UNIT PRICE ANALYSIS (DUPA) Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types)
Hourly Rate
Amount
109.19 61.44
109.19 368.64
477.83 Hourly Rate
Amount
10.00
10.00 23.89
33.89 511.72 25.59 Unit Cost
Amount
250.00
262.50 13.13
of G of G of (G + H + I) (G + H + I + J)
275.63 301.21 27.11 24.10 42.29 394.71
DETAILED UNIT PRICE ANALYSIS (DUPA) Chevron Signs (450mmx600mm)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 79.70 122.88
311.77 Hourly Rate
Amount
712.00
178.00 31.18
209.18 520.95 520.95 Unit Cost
Amount
220.00 850.00 650.00 40.00 530.00 48.00 10.00 10.00 3,750.00 68.00
105.60 21.25 32.50 80.00 1,722.50 240.00 30.00 120.00 7,500.00 5.44 29.57
of G of G of (G + H + I) (G + H + I + J)
9,886.86 10,407.81 936.70 832.62 1,461.26 13,638.39
DETAILED UNIT PRICE ANALYSIS (DUPA) Chevron Signs (600mmx800mm)
Hourly Rate
Amount
109.19 79.70 61.44
109.19 79.70 122.88
311.77 Hourly Rate
Amount
712.00
178.00 31.18
209.18 520.95 520.95 Unit Cost
Amount
220.00 850.00 650.00 40.00 530.00 48.00 10.00 10.00 7,500.00 68.00
105.60 21.25 32.50 80.00 1,828.50 240.00 30.00 120.00 15,000.00 5.44 34.93
of G of G of (G + H + I) (G + H + I + J)
17,498.22 18,019.16 1,621.72 1,441.53 2,529.89 23,612.31
DETAILED UNIT PRICE ANALYSIS (DUPA) Bio-Engineering Solutions (Coco-net)
Hourly Rate
Amount
109.19 61.44
109.19 491.52
600.71 Hourly Rate
Amount
1,065.00
266.25 60.07
326.32 927.03 18.54 Unit Cost
Amount
110.00
115.50
of G of G of (G + H + I) (G + H + I + J)
115.50 134.04 12.06 10.72 18.82 175.65
DETAILED UNIT PRICE ANALYSIS (DUPA) Bio-Engineering Solutions (Coco-net)
Hourly Rate
Amount
109.19 61.44
109.19 491.52
600.71 Hourly Rate
Amount
1,065.00
266.25 60.07
326.32 927.03 18.54 Unit Cost
Amount
156.00
163.80
of G of G of (G + H + I) (G + H + I + J)
163.80 182.34 16.41 14.59 25.60 238.94
DETAILED UNIT PRICE ANALYSIS (DUPA) Bio-Engineering Solutions (Coco-logs/Fascine)
Hourly Rate
Amount
109.19 61.44
109.19 491.52
600.71 Hourly Rate
Amount
60.07
60.07 660.78 44.05 Unit Cost
Amount
388.00
407.40
of G of G of (G + H + I) (G + H + I + J)
407.40 451.45 40.63 36.12 63.38 591.58
DETAILED UNIT PRICE ANALYSIS (DUPA) Bio-Engineering Solutions (Coco-logs/Fascine)
Hourly Rate
Amount
109.19 61.44
109.19 491.52
600.71 Hourly Rate
Amount
60.07
60.07 660.78 44.05 Unit Cost
Amount
509.00
534.45
of G of G of (G + H + I) (G + H + I + J)
534.45 578.50 52.07 46.28 81.22 758.07
DETAILED UNIT PRICE ANALYSIS (DUPA) Bio-Engineering Solutions (Vegetation)
Hourly Rate
Amount
109.19 61.44
109.19 122.88
232.07 Hourly Rate
Amount
952.00 1,065.00
952.00 1,065.00
2,017.00 2,249.07 35.99 Unit Cost
Amount
45.00
47.25
of G of G of (G + H + I) (G + H + I + J)
47.25 83.24 7.49 6.66 11.69 109.07
DETAILED UNIT PRICE ANALYSIS (DUPA) Bio-Engineering Solutions (Vegetation)
Hourly Rate
Amount
109.19 61.44
109.19 491.52
600.71 Hourly Rate
Amount
1,065.00
532.50 60.07
592.57 1,193.28 34.09 Unit Cost
Amount
70.00
73.50
of G of G of (G + H + I) (G + H + I + J)
73.50 107.59 9.68 8.61 15.11 140.99
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
SPL 2(a)
Crack and Seat sq.m. 35.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Rental Rate
a. Backhoe w/ Breaker (0.80 cu.m.)
1
1.00
b. Vibratory Roller (10 m.t.), SP56
1
0.75
2,074.95 1,507.00
c. Water Truck (1000 gal.)
1
0.10
1,065.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment
Sub - Total for B C. Total (A + B) D. Output per hour = 35.00 sq.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% of G 8% of G 12% of (G + H + I)
K. Total Unit Cost
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour
: : :
SPL 2(b)
Crack and Seat sq.m. 30.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 1 2
1 1 1
109.19 79.70 61.44
No of Units
No. of Hours
Rental Rate
1
1.00
1,485.84
1 1
0.75 0.10
1,507.00 1,065.00
Unit
Quantity
Unit Cost
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
Sub - Total for A Name and Capacity B. Equipment a. Arrow Master D 500 (Additional 35% for Oil and Lubricants) b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.)
Sub - Total for B C. Total (A + B) D. Output per hour = 30.00 sq.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Sub - Total for F G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) I. Contractor's Profit (CP)
9% of G 8% of G
J. Value Added Tax (VAT) K. Total Unit Cost
12% of (G + H + I) (G + H + I + J)
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
SPL 3(a)
Tree Planting pc. 60.00
Designation
No. of Person
No. of Hours
1 10
1 1
No of Units
No. of Hours
a. Cargo Truck (5 T)
1
0.25
b. Water Truck (1000 gal.)
1
0.25
Unit
Quantity
pc. bd.ft. kg. kg.
1 8 0.08 0.10
A. Labor 109.19 79.70 122.88
a. Construction Foreman b. Laborer
311.77
Sub - Total for A
Amount
Name and Capacity B. Equipment
2,074.95 1,130.25 106.50
3,311.70 3,623.47 103.53
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 60.00 pc. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials a. Saplings b. Coco Lumber c. Assorted CWN (1 kg./100 bd.ft.) d. Fertilizers
0.00 103.53 9.32 8.28 14.54
G. H. I. J.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT)
9% 8% 12%
135.66
K. Total Unit Cost
SIS (DUPA)
DETAILED UNIT PRICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour Amount
: : :
SPL 3(b)
Tree Planting pc. 60.00
Designation
No. of Person
No. of Hours
1 10
1 1
No of Units
No. of Hours
a. Cargo Truck (5 T)
1
0.25
b. Water Truck (1000 gal.)
1
0.25
Unit
Quantity
pc. kg.
1 0.10
A. Labor 109.19 79.70 122.88
a. Construction Foreman b. Laborer
311.77
Sub - Total for A
Amount
Name and Capacity B. Equipment
1,485.84 1,130.25 106.50
2,722.59 3,034.36 101.15
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 60.00 pc. E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials a. Saplings b. Fertilizers
0.00 101.15 9.10 8.09
Sub - Total for F G. Direct Unit Cost (E + F) H. Overhead, Contingencies & Miscellaneous (OCM) I. Contractor's Profit (CP)
9% 8%
14.20 132.54
J. Value Added Tax (VAT) K. Total Unit Cost
12%
DETAILED UNIT PRICE ANALYSIS (DUPA) Tree Planting
Hourly Rate
Amount
109.19 61.44
109.19 614.40
723.59 Hourly Rate
Amount
712.00 1,065.00
178.00 266.25 72.36
516.61 1,240.20 20.67 Unit Cost
Amount
50.00 20.00 68.00 50.00
50.00 160.00 5.44 5.00
of G of G of (G + H + I)
220.44 241.11 21.70 19.29 33.85
(G + H + I + J)
315.95
DETAILED UNIT PRICE ANALYSIS (DUPA) Tree Planting
Hourly Rate
Amount
109.19 61.44
109.19 614.40
723.59 Hourly Rate
Amount
712.00 1,065.00
178.00 266.25 72.36
516.61 1,240.20 20.67
of G of G
Unit Cost
Amount
50.00 26.00
50.00 2.60
52.60 73.27 6.59 5.86
of (G + H + I) (G + H + I + J)
10.29 96.01
ITEM NO. PART C 100(1) 100(2)a 100(2)b 100(3)a 100(3)b 101(1) 101(2) 101(2) 101(2) 101(2) 101(2)a 101(2)b 101(2)c 101(2)d 101(2)e 101(2)f 101(2)g 101(3)a.1 101(3)a.2 101(3)b 101(3)c 101(4)a 101(4)b 102(1) 102(2)a 102(2)b 102(3)a 102(3)b 102(3)c 102(3)d 102(4) 103(1)a 103(1)b 103(1)c 103(2)a 103(2)b 103(2)c 103(3) 103(4) 103(5)a 103(5)b 103(6) 104(1)a 104(1)b
DESCRIPTION EARTHWORKS Clearing and Grubbing (with Stripping) Individual Removal of Trees (small a,150-300mm Ø) Individual Removal of Trees (small b, 301-500mm Ø) Individual Removal of Trees (large a, 501-750mm Ø) Individual Removal of Trees (large b, 751-900mm Ø) Removal of Structures and Obstruction (other than concrete) Removal of Concrete Bridge Structures Removal of Steel Bridge Structures Removal of Stone Masonry Lined Drainage Structures Removal of Concrete Drainage Structures Removal of RCPC (24" dia.) - 610mm Removal of RCPC (30" dia.) - 760mm Removal of RCPC (36" dia.) - 910mm Removal of RCPC (42" dia.) - 1070mm Removal of RCPC (48" dia.) - 1220mm Removal of RCPC (60" dia.) - 1520mm Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200mm Ø), L = 10 ft. Removal of Existing Concrete Pavement (0.23m thk.) Removal of Existing PCC Pavement, 0.23m thk. (for Reblocking at intermittent section)) Removal of Existing Asphalt Pavement (100mm thk.) Removal of Sidewalk Removal of Curb Removal of Existing Curbs & Gutter Roadway Excavation (Unsuitable) Roadway Excavation (Surplus Common) Roadway Excavation (Surplus Common) - w/ Backhoe Roadway Excavation (Surplus Soft Rock) - w/ Backhoe Roadway Excavation (Surplus Soft Rock) Roadway Excavation (Surplus Hard Rock) - Blasting Roadway Excavation (Surplus Hard Rock) - Blasting (Tunnel Excavation) Roadway Excavation (Unclassified) Structure Excavation (Common Soil) Structure Excavation (Soft Rock) Structure Excavation (Solid Rock) Bridge Excavation (Common Soil) Bridge Excavation (Soft Rock) Bridge Excavation (Solid Rock) Foundation Fill Excavation ordered below Plan Elevation Shoring Cribbing/Cofferdamming Pipe Culvert and Drain Excavation Embankment from Borrow Embankment from Roadway Excavation
ITEM NO. 104(2) 104(3) 104(4) 105(1) 105(2) 105(3) PART D
200 200(1) 201 201(1) 202 203 204 205 206 PART E 300(1) 300(2) 301(1) 301(2) 302(1) 302(2) 303(1) 303(2) 303(3) 303(4) 304(1) 304(2) 304(3) 304(4) 304(5) 305(1) 305(2) 305(3) 305(4) 306(a) 306(b) 306(1) 306(2) 307 308(a) 308(b) 309 310(a.1)
DESCRIPTION Selected Borrow for topping, case 1 Selected Borrow for topping, case 2 Earth Berm Subgrade Preparation (Common Material) Subgrade Preparation (Existing Pavement) Subgrade Preparation (Unsuitable Material) SUBBASE AND BASE COURSE Aggregate Subbase Course Aggregate Subbase Course (for intermittent Reblocking) Aggregate Base Course Aggregate Base Course (for Reblocking) Crushed Aggregate Base Course Lime Stabilized Road Mix Base Course Portland Cement Stabilized Road Mix Base Course Asphalt Stabilized Road Mix Base Course Portland Cement Treated Plant Mix Base Course SURFACE COURSE Gravel Surface Course (Uncrushed) Crushed Aggregate Surface Course Bituminous Prime Coat (MC Cut-back Asphalt) Bituminous Prime Coat (RC Cut-back Asphalt) Bituminous Tack Coat (RC Cut-back Asphalt) Bituminous Tack Coat (Emulsified Asphalt) Bituminous Seal Coat (Cover Aggregate) Bituminous Seal Coat (MC Cut-back Asphalt) Bituminous Seal Coat (RC Cut-back Asphalt) Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-150) Bituminous Surface Treatment (Aggregate Grading) Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150) Bituminous Surface Treatment (MC Cut-back Asphalt) Bituminous Surface Treatment (RC Cut-back Asphalt) Bituminous Surface Treatment (Emulsified Asphalt) Bituminous Penetration Macadam Pavement (Aggregates) Bituminous Penetration Macadam Pavement (Asphalt Cement) Bituminous Penetration Macadam Pavement (RC Cut-back Asphalt) Bituminous Penetration Macadam Pavement (Emulsified Asphalt) Bituminous Road Mix Surface Course (MC Cut-back Asphalt) Bituminous Road Mix Surface Course (Emulsified Asphalt) Aggregate for Bituminous Road Mix Surface Course Bituminous Material for Bituminous Road Mix Surface Course Bituminous Plant Mix Surface Course-General - 50mm thk. Cold Asphalt Plant Mix (Emulsified Asphalt) - 50mm thk. Cold Asphalt Plant Mix (Cut-back Asphalt) - 50mm thk. Bituminous Plant Mix (Stockpile Maintenance Mixture) Bituminous Concrete Surface Course, Hot Laid - 30mm thk. (Delivered)
ITEM NO. 310(a.2) 310(a.3) 310(b.1) 310(b.2) 310(b.3) 311(1)a.1 311(1)a.2 311(1)a.3 311(1)a.4 311(1)a.5 311(1)a.6 311(1)b.1 311(1)b.2 311(1)b.3 311(1)b.4 311(1)c 311(2) PART G 404 405
500(1)a 500(1)b
500(1)c 500(1)d 500(1)e 500(1)f 501(1) 501(2)
501(3) 502 502(4) 502(5) 502(6) 503(a) 503(b) 504(1)a 504(1)b 504(1)c 504(1)d 504(1)e 504(2)a 504(2)b 504(2)c 504(2)d 504(2)e 504(3)a
DESCRIPTION Bituminous Concrete Surface Course, Hot Laid - 40mm thk. (Delivered) Bituminous Concrete Surface Course, Hot Laid - 50mm thk. (Delivered) Bituminous Concrete Surface Course, Hot Laid - 30mm thk. (Batching Plant) Bituminous Concrete Surface Course, Hot Laid - 40mm thk. (Batching Plant) Bituminous Concrete Surface Course, Hot Laid - 50mm thk. (Batching Plant) PCC Pavement (Plain) - Conventional Method, 150mm thk. PCC Pavement (Plain) - Conventional Method, 200mm thk. PCC Pavement (Plain) - Conventional Method, 230mm thk. PCC Pavement (Plain) - Conventional Method, 250mm thk. PCC Pavement (Plain) - Conventional Method, 280mm thk. PCC Pavement (Plain) - Conventional Method, 300mm thk. PCC Pavement (Plain) - Using Concrete Paver, 230mm thk. PCC Pavement (Plain) - Using Concrete Paver, 250mm thk. PCC Pavement (Plain) - Using Concrete Paver, 280mm thk. PCC Pavement (Plain) - Using Concrete Paver, 300mm thk. PCC Pavement (Plain) - Conventional Method, 150mm thk. (Using One Bagger Mixer) PCC Pavement (Reinforced), 230mm thk. DRAINAGE AND SLOPE PROTECTION STRUCTURES Reinforcing Steel Bar, Grade 40 (Minor Structures) Structural Concrete Class A (Minor Structures) Pipe Culverts, 610mm dia. (24" Ø) Pipe Culverts, 760mm dia. (30" Ø) Pipe Culverts, 910mm dia. (36" Ø) Pipe Culverts, 1070mm dia. (42" Ø) Pipe Culverts, 1220mm dia. (48" Ø) Pipe Culverts, 1520mm dia. (60" Ø) Underdrain Blind drain Granular Backfill filter material for Underdrains Manhole/Catch Basin/Inlet Concrete Covers Metal Frames and Gratings Metal Frames and Covers (Circular) Drainage Steel Grating w/ Frame (675mm x 975mm Sump Grating) Drainage Steel Grating w/ Frame (715mm x 2000mm Trench Grating) Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (24" dia.) - 610mm Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (30" dia.) - 760mm Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (36" dia.) - 910mm Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (42" dia.) - 1070mm Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (48" dia.) - 1220mm Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (24" dia.) - 610mm Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (30" dia.) - 760mm Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (36" dia.) - 910mm Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (42" dia.) - 1070mm Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (48" dia.) - 1220mm Cleaning Culvert Pipe in place (610mm dia.) - Half Silted
ITEM NO. 504(3)b 504(3)c 504(3)d 504(3)e 504(3)f 504(4) 505(1) 505(2) 505(3) 505(4) 505(5) 505(6) 505(7) 505(8) 505(9) 506 507 508 509(a) 509(b.1) 509(b.2) 509(c) 510(1) 510(2) 511(1) 511(2) 511(3) PART H 600(1) 600(2) 600(3) 600(4) 600(5) 600(6) 601(a) 601(b) 602(1)a 602(1)b 602(2)a 602(2)b 602(3)a 602(3)b 602(4) 603(1) 603(3)a
DESCRIPTION Cleaning Culvert Pipe in place (760mm dia.) - Half Silted Cleaning Culvert Pipe in place (910mm dia.) - Half Silted Cleaning Culvert Pipe in place (1070mm dia.) - Half Silted Cleaning Culvert Pipe in place (1220mm dia.) - Half Silted Cleaning Culvert Pipe in place (1520mm dia.) - Half Silted Reconditioning Drainage Structures Riprap, Class A Riprap, Class B Riprap, Class C Riprap, Class D Grouted Riprap, Class A Grouted Riprap, Class B Grouted Riprap, Class C Grouted Riprap, Class D Filter Layer of Granular Material Stone Masonry Rubble Concrete Hand-Laid Rock Embankment Sheet Piles (Timber) Sheet Piles (Steel) - Slope Protection Sheet Piles (Steel) - Cofferdamming Sheet Piles (Concrete), furnished and driven Bed Course Granular Material Concrete Slope Protection Gabions Mattresses Filter Cloth MISCELLANEOUS STRUCTURES Concrete Curb (Cast in place) Concrete Gutter (Cast in place) Concrete Curb and Gutter, Type A (Cast in place) - National Road Concrete Curb (Precast) Concrete Gutter (Precast) Concrete Curb & Gutter (Precast) Sidewalk (100mm thk.) Sidewalk - Using One Bagger Mixer, (100mm thk.) Right-of-Way Monuments (Cast in place) Right-of-Way Monuments (Precast) Maintenance Marker Posts (Cast in place) Maintenance Marker Posts (Precast) Kilometer Post (Cast in Place) Kilometer Post (Precast) Guide Post Cable Wire Guardrail Metal Guardrail (Metal Beam) including Concrete Post
ITEM NO. 603(3)b 603(4) 604(1) 604(2) 604(3) 604(4) 605(1)a 605(1)b 605(2)a 605(2)b 605(2)c 605(2)d 605(3)a 605(3)b 605(3)c 605(3)d 606(1) 606(2)a 606(2)b 607(1) 607(2) 608(1) 608(2) 609 610 611(1) 611(2) 612(1) 612(2) 613 620(a) 620(b) 622(1)a 622(1)b 622(2)a 622(2)b 622(3)a 622(3)b PART J SPL 2(a) SPL 2(b) SPL 3(a) SPL 3(b)
DESCRIPTION Metal Beam End Piece Guardrail (Timber) Fencing (Barbed Wire) Fencing (Chain Link Fence Fabric) Fencing (Posts) Fencing (Gates) - (Height = 3m & length = 4.24m) Danger/Warning Signs (60cm Triangle) Danger/Warning Signs (90cm Triangle) Regulatory Signs (60cm Triangle) Regulatory Signs (90cm Triangle) Regulatory Signs (60cm Octagon) Regulatory Signs (90cm Octagon) Informative Signs (12" x 24") Informative Signs (12" x 48") Informative Signs (18" x 24") Informative Signs (18" x 48") Pavement Markings (Premix Reflectorized) Pavement Markings (Reflectorized Thermoplastic), White Pavement Markings (Reflectorized Thermoplastic), Yellow Reflectorized Pavement Studs (Flush Type) Reflectorized Pavement Studs (Raised Profile Type) Furnishing and Placing Topsoil Placing Topsoil Sprigging Sodding Trees (Furnishing and Transplanting), 150mm dia. or less Trees (Transplanting), 150mm dia. or less Reflectorized Thermoplastic Pavement Markings (White) Reflectorized Thermoplastic Pavement Markings (Yellow) Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types) Chevron Signs (450mmx600mm) Chevron Signs (600mmx800mm) Bio-Engineering Solutions (Coco-net), CGN 400 Bio-Engineering Solutions (Coco-net), CGN 700 Bio-Engineering Solutions (Coco-logs/Fascine), CGR 200 Bio-Engineering Solutions (Coco-logs/Fascine), CGR 300 Bio-Engineering Solutions (Vegetation), Hydroseeding Bio-Engineering Solutions (Vegetation), Vetiver Grass System SPECIAL ITEMS Crack and Seat - Using Backhoe Crack and Seat - Using Arrow Master Tree Planting - With Tree Guard Tree Planting
ITEM NO.
DESCRIPTION
ITEM NO.
DESCRIPTION
View more...
Comments