Cost Estimating Manual

April 9, 2017 | Author: prens11us | Category: N/A
Share Embed Donate


Short Description

cost estimaiton...

Description

COST ESTIMATING MANUAL

CHEVRON RESEARCH AND TECHNOLOGY COMPANY RICHMOND, CA

December 1998

Manual sponsor:

For information or help regarding this manual, contact Daniel E. Moore at (925) 842-2120

Printing History Cost Estimating Manual First Edition Second Edition Third Edition Fourth Edition

April 1995 November 1997 June 1998 December 1998

Restricted Material Technical Memorandum This material is transmitted subject to the Export Control Laws of the United States Department of Commerce for technical data. Furthermore, you hereby assure us that the material transmitted herewith shall not be exported or re-exported by you in violation of these export controls.

The information in this Manual has been jointly developed by Chevron Corporation and its Operating Companies. The Manual has been written to assist Chevron personnel in their work; as such, it may be interpreted and used as seen fit by operating management. Copyright  1989, 1990, 1992, 1995, 1997, 1998 CHEVRON CORPORATION. All rights reserved. This document contains proprietary information for use by Chevron Corporation, its subsidiaries, and affiliates. All other uses require written permission.

Cost Estimating Manual Page-2

December 1998

List of Current Pages Cost Estimating Manual The following list shows publication or revision dates for the contents of this manual. To verify that your manual contains current material, check the sections in question with the list below. If your copy is not current, contact the Technical Standards Team, Chevron Research and Technology Company, Richmond, CA (510) 242-7241.

Section Title Page Front Matter Table of Contents Section 50 (Preface) Section 100 Section 101 Section 102 Section 103 Section 104 Section 105 Section 200 Section 201 Section 202 Section 203 Section 204 Section 205 Section 206 Section 210 Section 211 Section 212 Section 220 Section 221 Section 222 Section 223 Section 224 Section 300 Section 301 Section 302 Section 303 Section 304 Section 305

Date December 1998 December 1998 April 1995 April 1997 April 1995 April 1995 April 1995 April 1995 April 1995 April 1995 April 1995 April 1995 April 1995 April 1995 December 1996 April 1995 April 1995 April 1995 April 1995 April 1995 April 1995 December 1998 April 1995 April 1995 April 1995 April 1995

Cost Estimating Manual December 1998

Page-3

Section Section 310 Section 311 Section 312 Section 313 Section 400 Section 401 Section 402 Section 403 Section 404 Section 405 Section 406 Section 407 Section 408 Section 410 Section 411 Section 420 Section 421 Section 422 Section 423 Section 424 Section 500 Section 501 Section 510 Section 511 Section 512 Section 520 Section 521 Section 522 Section 523 Section 600 Section 601 Section 602 Section 603 Appendices Appendix A Appendix B Appendix C Appendix D Appendix E

Date April 1995 April 1995 April 1995 April 1995 April 1995 December 1995 April 1995 December 1998 April 1995 April 1995 April 1995 April 1995 April 1995 March 1995 (draft) March 1995 (draft) December 1998 April 1995 April 1995 April 1995 April 1995 December 1998 April 1995 April 1995 April 1995 April 1995 April 1995 April 1995 April 1995 April 1995 April 1995

Cost Estimating Manual Page-4

December 1998

Maintaining This Manual Cost Estimating Manual If you have moved or you want to change the distribution of this manual, use the form below. Once you have completed the information, fold, staple, and send by company mail. You can also FAX your change to (510) 242-2157. ❑ Change addressee as shown below. ❑ Replace manual owner with name below. ❑ Remove the name shown below. Previous Owner:

Title: Last

First

M.I.

Current Owner:

Title: Last

First

M.I.

Company:

Dept/Div:

Street:

P.O. Box:

City:

State:

Requesting Signature

Zip:

Date

Send this completed form to: Document Control, Room 50-4328 Chevron Research and Technology Company 100 Chevron Way (P.O. Box 1627) Richmond, CA 94802

CRTC Consultants Card The Chevron Research and Technology Company (CRTC) is a full-service, in-house engineering organization. CRTC periodically publishes a Consultants Card listing primary contacts in the CRTC specialty divisions. To order a Consultants Card, contact Ken Wasilchin of the CRTC Technical Standards Team at (510) 242-7241, or email him at “KWAS.”

Cost Estimating Manual December 1998

Page-5

(This page reserved for future use.)

Reader Response Form Cost Estimating Manual We are very interested in comments and suggestions for improving this manual and keeping it up to date. Please use this form to suggest changes; notify us of errors or inaccuracies; provide information that reflects changing technology; or submit material (drawings, specifications, procedures, etc.) that should be considered for inclusion. Feel free to include photocopies of page(s) you have comments about. All suggestions will be reviewed as part of the update cycle for the next revision of this manual. Send your comments to:

Page or Section Number

Document Control, Room 50-4328 Chevron Research and Technology Company 100 Chevron Way (P.O.Box 1627) Richmond, CA 94802 Comments

Name Address

Phone

Cost Estimating Manual December 1998

Page-7

(This page reserved for future use.)

Cost Estimating Manual Manual Sponsor: Daniel E. Moore / Phone: (510) 842-2120 / E-mail: [email protected] This document contains extensive hyperlinks to figures and cross-referenced sections. The pointer will change to a pointing finger when positioned over text which contains a link.

List of Current Pages 50

Using this Manual

50-1

100

Introduction to Cost Estimating

100-1

200

Primary Methods—Process Plants

200-1

210

Primary Methods—Offplot Facilities

210-1

220

Primary Methods—Other Facilities

220-1

300

Secondary Methods—Individual Cost Adjustments

300-1

310

Secondary Methods—Bottom-Line Cost Adjustments

310-1

400

Direct Cost Data—Equipment (Major Material)

400-1

410

Direct Cost Data—Bulk Materials (Minor Material)

410-1

420

Direct Cost Data—Construction Labor

420-1

500

Indirect Costs and Special Charges—Indirect Field Costs

500-1

510

Indirect Costs and Special Charges—Technical Services

510-1

520

Indirect Costs and Special Charges—Special Charges

520-1

600

Estimate Presentation and Review

600-1

Appendices Appendix A Appendix B Appendix C Appendix D Appendix E

Chevron Corporation

Estimating Checklists Process Licensors' Sales Factors Code of Accounts (EG-2757) Code of Accoounts for Buildings Projects Glossary

April 1995

Preface he intent of the Cost Estimating Manual is to provide uniform procedures and accompanying data for developing cost estimates for capital projects throughout Chevron. We hope that the material in this manual will contribute to a common understanding and consistent application of the cost-estimating process.

T

Using This Manual The manual is arranged to follow the flow of a typical cost estimate: Chapter 100 provides an overview of cost estimating, estimate classes and estimating methods. Chapter 200 describes the principal methods for making cost estimates—primarily for process plants, but also for offplot and other types of facilities. Method-specific data is also included. Chapter 300 includes factors and data to use with two or more methods described in the previous chapter. Chapter 400 contains instructions and data for estimating individual components of direct costs. The data includes material, labor, and subcontract costs associated with purchasing and erecting the physical facilities. Chapter 500 covers indirect costs and special charges. Indirect costs include construction indirect, engineering, and project management costs. Special charges are costs that may be unique to a project and, therefore, require specific identification and analysis. Chapter 600 contains guidance for reviewing, presenting, and documenting completed cost estimates. The Appendices contain general estimating reference materials, including checklists and a glossary. This manual is sponsored by Project Resource Services, Project Resources. Questions, comments, and suggestions for improvement are welcome and encouraged, and may be addressed to the Manager, Project Resource Services, San Ramon.

Cost Estimating Manual April 1997

Page 1

100

Introduction to Cost Estimating

101

Cost Estimating in General

102

Cost Estimating and the Phases of a Project

103

The Classes of Cost Estimates

104

Methods of Cost Estimating

105

Selecting a Method

Cost Estimating Manual

101 Cost Estimating in General ebster defines an estimate as an approximate computation of probable cost. According to the American Association of Cost Engineers (AACE), cost estimating is the predicting or forecasting ... of the costs required to construct and equip a facility, to manufacture goods, or to furnish a service. The latter definition more closely aligns with the objectives of this manual.

W

Objectives of this Manual While the concept of estimating is familiar to most people, the process may not be familiar. To help you estimate projects for Chevron, the objectives of this manual are to explain the various types of estimates and techniques for making them provide you with estimating data and guidance Although this manual is written primarily for major downstream projects, it can also be applied to upstream projects and smaller downstream projects.

Reasons for Cost Estimating Capital Construction

Generally, you associate estimates with capital construction projects to establish capital budgets evaluate project economics obtain funding approval monitor and control the execution of work

Annual Budgets

Chevron operating companies and staffs base their annual operating expense budgets on estimates.

Other Acitivities

Activities such as these also require estimates: Shutting down refinery plants for maintenance Overhauling tankers Leasing buildings or equipment

Cost Estimating Manual April 1995

Page 101 -1

101

Cost Estimating in General

Providing technical services for studies Writing computer programs Planning business trips The AACE definition points out that you may make a variety of types of estimates. In the next section, you’ll see how estimates fit into the different phases of Chevron project management.

Cost Estimating Manual Page 101 -2

April 1995

102 Cost Estimating and the Phases of a Project ost estimates are important in all phases of project management. In Figure 102-1, note the role of estimating (shown in bold italic) in the Chevron Project Development and Execution Process (CPDEP).

C

Phase

1

2

3

4

5

1

CPDEP Phase

Identify & Assess Opportunities

Select Alternative(s)

Develop Alternative(s)

Execute

Operate & Evaluate

CPMP2 Phase

Concept Development

Feasibility

Front-End Engineering

Execution

Operation & Evaluation

OBJECTIVES

Identify Opportunities Generate Alternatives Fully Define Scope

DELIVERABLES

Develop Detailed Execution Plans

Test for Strategic Fit

Preliminary Development of Alternatives

Preliminary Overall Plan

Develop Preliminary Project Economics

Refine Estimate Develop Final Project Economics

Preliminary Assessment

Identify Preferred Alternative(s)

Submit Request for Funding Approval

Plan for Phase 2

Plan for Phase 3

Plan for Phase 4

Clearly Frame Goal

Business Objectives Preliminary Facility & Final Facility & Project Objectives & Project Framework Project Objectives

Implement Execution Operate Asset Plan Monitor and Evaluate Finalize Operating Performance Plan Business Plan for Phase 5

Identify New Opportunities

Project Review

Operating Facility

Post-Project Assessment

Documentation Block Flow Diagram & Preliminary Capacity

Process Flow Diagrams & Equipment Lists

Preliminary Milestone Schedule

Preliminary Project Schedule

Class 1 Estimate

Class 2 Estimate

Set & Freeze Business Objectives Concept Development FEL Checklist

P&IDs, Plot Plans, One-Line Diagrams

1 2

Lessons Learned & Best Practices Benchmark Performance

Class 3 Estimate

Class 4 (& perhaps 5) Estimates and Final Project Cost

Freeze Capacity, Technology & Site

Freeze Definition Documents

Freeze Design Details

Post-Project Assessment

Feasibility FEL Checklist

Front-End Engineering FEL Checklist

Execute

Review & Share Lessons Learned

Detailed Schedule

TOOLS & PROCESS

Lessons Learned

CPDEP = Chevron Project Development and Execution Process CPMP = Chevron Project Management Process (Downstream Adaptation of CPDEP)

Figure 102-1. Estimating During the Phases of CPDEP and CPMP

Cost Estimating Manual April 1995

Page 102-1

103 The Classes of Cost Estimates hevron has adopted a series of cost estimate classifications as a part of the CPDEP. These classifications establish a common understanding among estimators, project managers, and their clients regarding these factors: Variability in the information required Appropriate estimating methods for each class Resulting estimate quality

C

The Five Classes Figure 103-1 summarizes the five classes. The first three are linked to the three phases of CPDEP Front-End Loading, where their purpose is to provide information to assist decision-makers. Classes 1 & 2

Because the first two project phases may extend over a long time (two to three years for large projects), several Class 1 and Class 2 estimates may be necessary as the project team studies various alternatives.

Class 3

Class 3 is often called an appropriation estimate because it is the basis for preparing an appropriation request. Again, large projects may have more than one Class 3 estimate, especially if the first one exceeds the funds budgeted for the project. In that case, the team must adjust the scope of the project.

Classes 4 & 5

Contractors usually prepare the last two classes of estimates during project execution. Contractors may call the Class 4 a control estimate because it establishes a basis for managing (controlling) the contractor’s work during the construction phase. Class 5 is appropriate only for very large, multiyear projects. It is really a re-forecast of remaining work (and thus the final cost) because much of the cost is fixed by that time.

Cost Estimating Manual April 1995

Page 103-1

103

The Classes of Cost Estimates

Contingency The values shown in the Contingency column of Figure 103-1 indicate relative requirements only and show the benefit of improvement to the project definition as projects progress. For Classes 1 and 2, especially, the typical contingencies shown apply to facilities known at the time of the estimate. Estimates can double or triple as the definition of required facilities evolves. You should not use this table to determine the actual contingency required for any estimate, but determine it from the characteristics of the specific project and estimate (see Section 313).

Cost Estimating Manual Page 103-2

April 1995

Contingency

Class & Project Phase

Engr’g

Contingency

Estimate Methods Used/Cost Basis Information Required Major Equipment

Class 1

1

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF