Contract Administration for Construction & Engineering Contracts - 1

November 12, 2016 | Author: Ahmad Firdaus | Category: N/A
Share Embed Donate


Short Description

CONTRACT ADMINISTRATION FOR CONSTRUCTION & ENGINEERING CONTRACTS...

Description

IEM TRAINING CENTRE SDN. BHD.

TWO DAY INTENSIVE COURSE ON

CONTRACT ADMINISTRATION FOR CONSTRUCTION & ENGINEERING CONTRACTS

Presented by:

IR. HARBANS SINGH K.S. B.E. (Mech) S’PORE, LLB (Hons) London CLP, DipICArb, C. Eng, PE.

ABOUT THE COURSE PRESENTER Ir. Harbans Singh K.S. B.E. (Mech) S’pore, LLB (Hons) London, CLP, DipICArb, P.E., C. Eng., MIEM, MIMechE, MIHEEM, MASHRAE, MCIArb, MMIArb.

Ir. Harbans Singh K.S. is a Professional and Chartered Engineer, Arbitrator, Adjudicator, Mediator, Advocate & Solicitor (non-practising). He commenced his career in Malaysia before working in Germany and then locally in various professional capacities. He is presently domiciled in Malaysia where he is active in construction law and dispute resolution. Ir. Harbans is the recipient of IEM’s Tan Sri Hj. Yusoff Prize (2001), the Cedric Barclay and the Chartered Institute of Arbitrator’s Awards for the Diploma in International Commercial Arbitration Examination (Oxford 2003). He is also the author of a series of four books entitled ‘Engineering & Construction Contracts Management’, coauthor of the book ‘The PAM 2006 Standard Form of Building Contract’, contributor to the ‘Malaysian Standard Forms & Precedents: Construction & Engineering Contracts’, ‘The Ingenieur’ and the ‘Malayan Law Journal’.

© HSKS

CONTRACT ADMINISTRATION FOR CONSTRUCTION/ ENGINEERING CONTRACTS DAY 1 - PROGRAMME 8.30 a.m.

-

9.00 a.m.

:

Registration

9.00 a.m.

-

10.30 a.m.

:

Session 1

10.30a.m.

-

10.45a.m.

:

Tea/Coffee Break

10.45 a.m.

-

12.30 noon

:

Session 2

12.30 noon

-

1.00 p.m.

:

Q & A Session

1.00 p.m.

-

2.00 p.m.

:

Lunch Break

2.00 p.m.

-

3.15 p.m.

:

Session 3

3.15 p.m.

-

3.30 p.m.

:

Tea/Coffee Break

3.30 p.m.

-

4.45 p.m.

:

Session 4

4.45 p.m.

-

5.00 p.m.

:

Q & A Session

:

End of Day 1

5.00 p.m.

© HSKS

CONTRACT ADMINISTRATION FOR CONSTRUCTION/ ENGINEERING CONTRACTS DAY 2 - PROGRAMME 9.00 a.m.

-

10.30 a.m.

:

Session 1

10.30a.m.

-

10.45a.m.

:

Tea/Coffee Break

10.45 a.m.

-

12.30 noon

:

Session 2

12.30 noon

-

1.00 p.m.

:

Q & A Session

1.00 p.m.

-

2.00 p.m.

:

Lunch Break

2.00 p.m.

-

3.15 p.m.

:

Session 3

3.15 p.m.

-

3.30 p.m.

:

Tea/Coffee Break

3.30 p.m.

-

4.45 p.m.

:

Session 4

4.45 p.m.

-

5.00 p.m.

:

Q & A Session

:

End of Course

5.00 p.m.

© HSKS

CONTENTS 1.0

CONSTRUCTION/ENGINEERING CONTRACTS: INTRODUCTION

2.0

COMMENCEMENT OF CONTRACT AT SITE

3.0

MONITORING OF WORK PROGRESS

4.0

SUPERVISION OF WORKS/CONTRACT ADMINISTRATION

5.0

PAYMENTS/COMMERCIAL MATTERS

6.0

VARIATIONS/CHANGES

7.0

DELAY AND EXTENSION OF TIME

8.0

NON-COMPLETION AND DAMAGES

9.0

COMPLETION AND HANDING OVER

10.0

DEFECTS

11.0

POST COMPLETION AND FINAL ACCOUNT

© HSKS

CONSTRUCTION/ ENGINEERING CONTRACTS: INTRODUCTION

© HSKS

1.0



CONSTRUCTION/ENGINEERING CONTRACTS: INTRODUCTION TYPES OF CONTRACTS 1.

GENERAL CONTRACTS

2.

ENGINEERING/CONSTRUCTION CONTRACTS



TYPES OF BUILDING CONTRACTS



COMMON CONTRACT PROCUREMENT METHODS 1.

TRADITIONAL GENERAL CONTRACTS

2.

MANAGEMENT TYPES

3.

‘PACKAGE DEAL’ TYPES

4.

MISCELLANEOUS METHODS

© HSKS





BASIC CONTRACT PRINCIPLES 1.

CONTRACT DEFINITIONS

2.

ELEMENTS OF CONTRACT

3.

STANDARD FORMS OF CONTRACT

4.

BREACH OF CONTRACT: REMEDIES

MISCELLANEOUS ISSUES

© HSKS

SIMPLE CONTRACTS SPECIALITY CONTRACTS (DEED)

COLLATERAL CONTRACTS MATERIAL & LABOUR CONTRACTS

ORAL CONTRACTS

LABOUR CONTRACT

EXPRESS CONTRACTS

GENERAL CONTRACTS: TYPES

MATERIAL SUPPLY CONTRACT

MAIN CONTRACTS

INDEPENDENT CONTRACTS

SUB-CONTRACTS EMPLOYMENT CONTRACTS

SUB-SUB CONTRACTS

FIG. 1-1: GENERAL CONTRACTS - TYPES © HSKS

ENGINEERING/ CONSTRUCTION CONTRACTS: TYPES’

FIG. 1-2 : ENGINEERING/CONSTRUCTION CONTRACTS - TYPES © HSKS

TYPE OF CONTRACT

MESUREMENT CONTRACTS

LUMP SUM CONTRACTS

LUMP SUM WITH PLAN AND SPECIFICATION

LUMP SUM WITH BILLS OF QUANTITIES

BASED ON APPROXIMATE QUANTITIES

COST PLUS FIXED FEE

COST REIMBURSEMENT CONTRACTS

COST PLUS PERCENTAGE

BASED ON A SCHEDULE

COST PLUS FLUCTUATING FEE

TARGET COST

VALUE COST

FIG. 1-3 : TYPES OF CONTRACTS BASED ON PRICING MECHANISM © HSKS

COMMON CONTRACT PROCUREMENT METHODS

TRADITIONAL GENERAL CONTRACTTING

PACKAGE DEAL TYPE

MANAGEMENT TYPE

MANAGEMENT CONTRACTING

DESIGN & BUILD/ DESIGN & CONSTRUCT

CONSTRUCTION MANAGEMENT

BUILD, OPERATE & TRANSFER

ENGINEERING, PROCUREMENT, CONSTRUCTION & COMMISSIONING

MISCELLANEOUS METHODS

FAST TRACKING

PARTNERING

‘TURNKEY’ TURNKEY’

FIG. 1-4 : COMMON CONTRACT PROCUREMENT METHODS IN USE © HSKS

FIG. 1-5 : COMPARISON OF COMMON CONTRACT PROCUREMENT METHODS

1985

1990

1995

2000

1.0 TRADITIONAL GENERAL CONTRACTING

95%

76%

31%

20%

2.0 MANAGEMENT CONTRACTING

2%

3%

2%

1%

3.0 CONSTRUCTION MANAGEMENT

1%

3%

9%

10%

4.0 PACKAGE DEAL TYPE’

2%

15%

52%

60%

5.0 BUILD, OPERATE AND TRANSFER

-

2%

5%

8%

6.0 OTHER MISCELLANEOUS

-

1%

1%

1%

© HSKS

FIG. 1-6: TRADITIONAL GENERAL CONTRACTING (TGC) – CONTRACTUAL RELATIONSHIPS

EMPLOYER

PROFESSIONAL TEAM - DESIGN AND CONTRACT ADMINISTRATION

1. 2. 3. 4.

Architect Engineers - C&S, M&E Quantity Surveyor Other Specialist

MAIN CONTRACTOR (MC)

DOMESTIC SUPPLIER (DS)

SUBSUB-SUB CONTRACTORS Key _______ _____

: :

SUB--SUB SUPPLIERS SUB

NOMINATED SUPLLIER (NS)

SUBSUB-SUB CONTRACTORS

SUBSUB-SUB SUPPLIERS

Contractual Link Responsibility

© HSKS

FIG. 1-7: ‘TURNKEY’ CONTRACTS/DESIGN & CONSTRUCT (D&C) - CONTRACTUAL RELATIONSHIPS

EMPLOYER

PROFESSIONAL ADVISORS

1. 2. 3. 4.

Architect Engineers - C&S, M&E Quantity Surveyor Other Specialist

1. Setting up Employers Requirements 2. Auditing role during construction

D & C CONTRACTOR

1. 2. 3. 4.

Architect Engineers - C&S, M&E Quantity Surveyor Other Specialist

PROFESSIONAL TEAM

: :

SUBSUBSUPPLIER

1. Detailed Design 2. Construction supervision

SUBSUB-SUB CONTRACTORS

Key _______ _____

SUBSUBCONTRACTOR

SUBSUB-SUB SUPPLIERS

SUBSUB-SUB CONTRACTORS

SUB--SUB SUPPLIERS SUB

Contractual Link Responsibility

© HSKS

FIG. 1-8: MANAGEMENT CONTRACTING (MC) - CONTRACTUAL RELATIONSHIPS

EMPLOYER

PROFESSIONAL TEAM 1. 2. 3. 4.

MANAGEMENT CONTRACTOR (MC)

Architect Engineers - C&S, M&E Quantity Surveyor Other Specialist

TRADE CONTRACTOR

TRADE CONTRACTOR

TRADE CONTRACTOR

Key

_______ : Contractual Link _____

:

Responsibility

© HSKS

FIG. 1-9: CONSTRUCTION MANAGEMENT (CM) - CONTRACTUAL RELATIONSHIPS

EMPLOYER

PROFESSIONAL TEAM 1. 2. 3. 4.

CONSTRUCTION MANAGER (CM)

Architect Engineers - C&S, M&E Quantity Surveyor Other Specialist

Key

_______

: Contractual Link

_____

: Responsibility

TRADE CONTRACTORS

TRADE CONTRACTORS

© HSKS

* 1.0

DEFINATIONS

PER ANSON * * * *

2.0

CONTRACT -

Legally binding agreement Between two or more parties By which rights are acquired by one or more To acts or forbearances on the part of the other or others

PER SECTION 2(h) MALAYSIAN CONTRACTS ACT 1950 (REV. 1974) * An agreement * Enforceable by Law **

CLEAR + OFFER

CONTRACT - BASIC ELEMENTS

UNQUALIFIED ACCEPTANCE

+ CONSIDERATION =

CONTRACT CONTRACT (LEGAL AGREEMENT)

FIG. 1-10: CONTRACT DEFINITIONS © HSKS

FIRM OFFER/ PROPOSAL

+ UNQUALIFIED ACCEPTANCE

+ CONSIDERATION

INTENTION TO CREATE LEGAL RELATIONS

FREE CONSENT

CERTAINTY OF TERMS

LAWFUL OBJECT AND CONSIDERATION

LEGAL CAPACITY TO CONTRACT

PHYSICAL/LEGAL POSSIBILITY

FIG. 1-11: ELEMENTS OF A VALID/ENFORCEABLE AGREEMENT © HSKS

DEFINITION/ MEANING

CHARACTERISTICS

MAIN TYPES

DISADVANTAGES

ADVANTAGES

FIG. 1-12 :

STANDARD FORMS OF CONTRACT

TYPES

PURPOSE

STANDARD FORMS OF CONTRACT (PART I) © HSKS

STANDARD FORMS OF CONTRACT

GOVERNMENT/ PUBLIC SECTOR

INTERNATIONAL CONTRACTS

PRIVATE SECTOR

1. FIDIC Conditions 2. ICE Conditions

JKR / PWD

MISCELLANEOUS



203 (Rev. 1/2010) - without quantities



203A (Rev. 1/2010) - with quantities



203N (Rev. 1/2010) - For NSC



203P (Rev. 1/2010) - For Nominated Suppliers



PWD Form DB (2007 Edn.) For Design & Build Contracts

3. IEEE Conditions



CIDB Form for:

4. IMechE Conditions

-

Building Contracts 2000 Edn. Form CIDB.B (NSC/2002)

5. JCT Conditions



Modified JKR/PWD Forms e.g. LPK, MHA, etc.

CIVIL ENGINEERING WORKS

BUILDING WORKS •

PAM Contract 2006 (with quantities)



PAM Contract 2006 (without quantities)





M & E WORKS

IEM Conditions



IEM Conditions

- IEM.CE 2011 - IEM.CES 1/90

-

IEM.ME 1/94



TNB Conditions, etc.

PAM Sub-Contract 2006

FIG. 1-13: STANDARD FORMS OF CONTRACT (PART II) © HSKS

COMMENCEMENT OF CONTRACT AT SITE

© HSKS

2.0



APPROACHES IN: 1. 2.



COMMENCEMENT OF CONTRACT AT SITE

TRADITIONAL GENERAL CONTRACTS DESIGN & BUILD / TURNKEY CONTRACTS

FORMALITIES: 1. 2.

CONDITIONS PRECEDENT INSURANCES, PERFORMANCE BONDS, ETC.



SITE POSSESSION : MEANING AND EFFECT



SUBMITTALS : 1. 2. 3. 4. 5. 6.

CONSTRUCTION DRAWINGS SHOP DRAWINGS SAMPLES QA AND QC DOCUMENTS HEALTH AND SAFETY DOCUMENTS METHOD STATEMENTS



TEMPORARY WORKS



ISSUES FOR ATTENDANCE OF NOMINATED SUBSUB-CONTRACTORS



MISCELLANEOUS ISSUES © HSKS



RELEVANT CASES 1. THE RADIO & GENERAL TRADING CO. SDN. BHD. V WYASS & FREYTAG (M) SDN. BHD. [1998] 1 MLJ 346 2. LEC CONTRACTORS (M) SDN. BHD. V CASTLE INN SDN. BHD. & ANOR [2000] 3 MLJ 339 3. KLEINWORT BENSON LTD. V MALAYSIA MINING CORP. BHD [1989] 1 WLR 379 4. NANYANG INSURANCE CO. LTD. V SALBIAH & ANOR [1967] 1 MLJ 94 5. SURREY HEALTH [1988] 42 BLR 25

BOROUGH

COUNCIL

V

LOVELL

CONSTRUCTION

6. FREEMAN V HENSLER [1981] 20 BLR 78 7. TAN HOCK CHAN V KHO TECK SENG [1980] 1 MLJ 308 8. PUTRA PERDANA CONSTRUCTION SDN. BHD. V AMI INSURANCE & ORS [2005] 2 MLJ 123 HC

BHD

9. YIP SHOU SHAN V SIN HEAP LEE – MARUBENI SDN. BHD. [2002] 5 43, HC`

MLJ

© HSKS

TAKING OVER OF THE SITE

SITE POSSESSION

COMMENCEMENT OF CONTRACT

COMMENCEMENT: COMMON LABELS

COMMENCEMENT OF OPERATIONS ON SITE

COMMENCEMENT OF CONTRACT PERIOD

COMMENCEMENT OF WORKS

FIG. 2-1 : COMMENCEMENT - COMMON LABELS © HSKS

PARENT COMPANY GUARANTEE

INSURANCE

PERFORMANCE BOND

PROTECTION AGAINST CONTRACTOR’S FAILURES: COMMON MECHANISMS

LETTER OF COMFORT

STANDBY LETTER OF CREDIT LETTER OF AWARENESS

FIG. 2-2: PROTECTION AGAINST CONTRACTOR’S FAILURES – COMMON MECHANISMS © HSKS

PROTECTION AGAINST CONTRACTOR’S FAILURES: AN OVERVIEW (PART I)

COMMON MECHANISMS/ INSTRUMENTS: TYPES

PURPOSE •

Risk transferring contracts



Parent Company Guarantees



Enable recovery of compensation upon contractor’s default/failure under the contract



Performance Bonds



Miscellaneous Types: 1. 2. 3.

Letters of Comfort Standby Letters of Credit Insurances

NATURE •



Contractual performance of ‘Company within a corporate group is underwritten by other members of group E.g. Subsidiary and Holding Company

PARENT COMPANY GUARANTEES

PROCEDURAL REQUIREMENTS

USE •

For commercial and administrative convenience



Owing to requirements of applicable law e.g. company law, etc.



Preliminary review



Check for legal compliance



Check for compliance with formalities

Cont’d….

FIG. 2-3 : PROTECTION AGAINST CONTRACTOR’S FAILURES – AN OVERVIEW (PART I) © HSKS

Cont’n.

PROTECTION AGAINST CONTRACTOR’S FAILURES: AN OVERVIEW (PART II)

MISCELLANEOUS MECHANISMS/ INSTRUMENTS

PERFORMANCE BONDS

• • •

Reasons for Typical contents Legal effect of letter

• • • •

DEFINITION DEFINITION •

See Robinson and Laver’s definition



Means of guaranteeing to the employer: 1. The contractor’s financial viability and 2. Contractor’s ability to perform obligations under the contract



Two main types: 1. ‘Conditional/ Default’ Bond 2. ‘Unconditional/ On-Demand’ Bond • •

Features of local practice Rules of construction and enforcement

Reasons for Comparison with letters of comfort Typical contents Legal effect of letter

DURATION DURATION OF OF LIABILITY LIABILITY

TYPES TYPES •

STANDBY LETTER OF CREDIT

LETTER OF AWARENESS

LETTER OF COMFORT

Normally stipulated in bond. Types include: 1. Entire duration of contract 2 Up to CPC ‘Construction’ Bond 3 CPC to Final Certificate – ‘Maintenance’ Bond

Reasons for Comparison with ‘Unconditional/On-Demand’ Bond Obligations under Legal effect of letter

• • • •

PROCEDURAL PROCEDURAL REQUIREMENTS

FINANCIAL LIMITS OF LIABILITY •

Normally stipulated in Bond itself.



Normally 5-10%



Sometimes higher



See use of ‘Indexed Performance Bonds’

INSURANCE • • •

Reasons for: Legal effect of Insurance Comparison with the other mechanisms/instruments

NONPROVISION OF OF NON--PROVISION BOND/GUARANTEE

RELEASE OF BOND /GUARANTEE



Preliminary review



Timing for submission



Seven main circumstances



Checks for authenticity



Consequences of failure to submit:





Check for compliance with formalities

Effect of breaches of terms and conditions

1. Contract provisions 2. Common law rules

4 Up to date of release stipulated by guarantor

FIG. 2-4 : PROTECTION AGAINST CONTRACTOR’S FAILURES – AN OVERVIEW (PART II) © HSKS

FIG. 2-5 : CONTRACTOR’S INSURANCE POLICIES – COMMON TYPES © HSKS

INSURANCES: AN OVERVIEW (PART I)



Risk allocation mechanisms



Per Robinson and Lavers



Means of seeking compensation following default/failure



Voluntary assumption of specified risk in return for an agreed payment

CATEGORY I

CATEGORISATION •

Two Main Categorization: 1. 2.



TYPES

DEFINITION

PURPOSES

Liability based Loss based

Difference: basis of compensation

CATEGORY II

PRINICPAL TYPES



Liability based



Loss based



Contractor: Common Types



Indemnification of insured against damages payable to 3rd party



Compensate insured for loss/damage directly incurred by insured



Employer: Common Types



Occupier: Common Types

Examples:



Examples:



Management Corporation: Common Types



1. 2. 3.

3rd Party Liability Insurance Workmen’s Compensation Professional Indemnity Insurance

1. 2.

Contractor’s All Risk Policy Erection All Risk Policy

FIG. 2-6 : INSURANCES – AN OVERVIEW (PART I) © HSKS

Cont’d…….

INSURANCES: AN OVERVIEW (PART II)

FEATURES AND CONDITIONS

PROCEDURAL REQUIREMENTS

FAILURE TO INSURE

• Necessity for checking authenticity of: 1. Cover notes 2. Policy • Necessity to check for compliance with: 1. Contract requirements 2. Formalities

FAILURE TO INSURE

TIMING FOR SUBMISSION •

Normally stipulated in contract



2 Common alternatives:

• Effects dictated by: 1. Governing contractual provisions 2. Common law rules

1. Before commencement of work/contract; or

• Possible options: Employer insures and charges premiums to contractor

2. Within stipulated period of award of contract

IMPORTANT IMPORTANT STANDARD STANDARD CONDITIONS CONDITIONS

BASIS BASIS OF OF CONTRACTING CONTRACTING • Submission of proposal •

Issue of policy



Effect of : 1. Contracts of ‘uberrimae fidei’ 2. Cover notes, etc.



PARTIES PARTIES EFFECTING POLICY POLICY

Six main ones i.e.





4. Following a loss event 5. As to subrogation 6. On contribution

• Various possibilities:

Typical parties: 1. 2. 3. 4.

3. As to risk



Employer Contractor Sub-contractors Selected 3rd parties

Effect of ‘cross liability’ provisions

DURATION DURATION OF OF POLICY POLICY

COMMENCEMENT COMMENCEMENT OF OF POLICY POLICY

1. Named party 2. With insurable interest

1. Condition precedent to liability 2. During work/construction

General rule:

Different formulae:



1. Date of commencement of contract; or

1. Up to issue of CPC

2. Date of commencement of work on site; or

3. Up to issue of Final Certificate

3. Date of delivery of material, etc.

• Function of the nature of contract works

• Apparently not a serious ground to effect determination

2. Up to issue of CMGD

FINANCIAL FINANCIAL LIMITS LIMITS OF OF LIABILITY LIABILITY •



Guidelines for estimating limits.



General rule on deductibles/excess clauses

4. Up to Final Certificate plus fixed period •

Normally stipulated by employer in tender/contract

Requirements pertaining to extension of period

TERMINATION TERMINATION OF OF POLICY POLICY • Three main methods: 1. Satisfaction of conditions precedent in contract e.g. issue of CPC, etc. 2. Termination of policy by breach/mutual agreement 3. Lapse of insurance period and/or extension

FIG. 2-7 : INSURANCES – AN OVERVIEW (PART II) © HSKS

SITE POSSESSION: AN OVERVIEW

PROVISIONS FOR

MEANING

EXPRESS • •

Licence revocable by Employer at any time



Licence to be free from any encumbrances

• If not expressed, by

Or in Contract



Contractor entitled to Sole/exclusive possession

GENERAL LEGAL POSITION

IMPLIED •

No



Freeman & Son v Hensler

EXCEPTIONS TO GENERAL PRINCIPLE •

Express Stipulations



Case Law

POSSESSION ON PIECEMEAL BASIS?

LATEST LEGAL POSITION •

Sufficient degree of possession/ access



To execute work unimpeded



To be able to perform work

FAILURE TO GIVE POSSESSION

EXCEPTIONS

Law

GENERAL PRINCIPLE •



In Letter of Acceptance

POSTPONEMENT

DEGREE

Express contract stipulations permitting postponement

GENERAL LEGAL POSITION

EFFECT



General Position: No



Breach of Contract





Exceptions:



Entitles Contractor to rescind Contract.

Contractor entitled to loss occasioned



Contractor entitled to EOT if expressly permitted contractually



Otherwise, LAD cannot be imposed

a) Express stipulations to contrary b) Where Common Law applies

FIG. 2-8 : SITE POSSESSION – AN OVERVIEW © HSKS

SITE POSSESSION MEETINGS

TIMING

·

On Date of Commencement of Contract /

·

Date of Site Possession

MATTERS DEALT

PURPOS E

·

1. All Project Team Member

To officially handover Possession of Site to the Contractor

WHO PREPARES ? ·

EXPLANATION OF CONTRACT REQUIREMENTS

LETTER OF DELEGATION OF POWERS

PARTICIPANTS

MINUTES

INTRODUCTION OF PROJECT MEMBERS

COPY OF CONTRACT DOCUMENTS

PRICED COPY OF B.Q.

Contract Administrator

DISTRIBUTION/ CIRCULATION ·

To all parties

HANDOVER OF VARIOUS DOCUMENTS

SET OF CONSTRUCTION DRAWINGS

SET OUT PROCEDURES COVERING ·

Document Submittals and Approvals

·

Sample Submittals and Approvals

· ·

Inspection of Work Interim Valuations

·

Claim Procedures

FIG. 2-9 : SITE POSSESSION MEETINGS © HSKS

WORK PROGRAMME MISCELLANOUES REPORTS AND DOCUMENTS

DESIGN AND CALCULATIONS FOR WORKS UNDER P.C. SUM, ‘PACKAGE DEAL’ TYPE CONTRACTS, ETC.

METHOD STATEMENTS

WORKS UNDER CONTRACT: TYPICAL SUBMITTALS BY CONTRACTOR

DESIGN AND CALCULATIONS FOR TEMPORARY WORKS

DRAWINGS I.E. SHOP, FABRICATION, SETTING OUT, ETC.

QA/QC DOCUMENTS

HEALTH AND SAFETY DOCUMENTS

FIG. 2-10: WORKS UNDER CONTRACT – TYPICAL SUBMITTALS BY CONTRACTOR © HSKS

MONITORING OF WORK PROGRESS

© HSKS

3.0

MONITORING OF WORK PROGRESS



PROGRAMMING OF WORKS



PARTIES RESPONSIBLE: 1. 2. 3.

EMPLOYER MAIN CONTRACTOR CONTRACT ADMINISTRATOR



PROGRESS REPORTS



SITE RECORDS



MEETINGS: 1. 2. 3. 4.



SITE POSSESSION PROGRESS/SITE NSC COORDINATION AD-HOC

MISCELLANEOUS ISSUES

© HSKS



RELEVANT CASES 1.

GLENLION CONSTRUCTION LTD. V THE GUINESS TRUST [1987] 39 BLR 89

2.

YORKSHIRE WATER AUTHORITY V (NORTHERN) LTD. [1986] 32 BLR 114

3.

GREATER LONDON COUNCIL V CLEVELAND BRIDGE & ENGINEERING CO. LTD. [1986] 8 Con LR 30

4.

KITSONS SHEET METAL LTD. V MATTHEW HALL MECHANICAL & ELECTRICAL ENGINEERS LTD. [1989] 47 BLR 82

5.

WEST FAULKNER ASSOCIATES V LONDON BOROUGH OF NEWHAM [1994]

SIR ALFRED MCALPINE & SON

71 BLR 1

6.

EQUITABLE DEBENTURES ASSETS CORP. LTD. ROBERTS & ORS [1984] 2-CLD-10-01

V

MORGAN BRANCH

© HSKS

FIG. 3-1 : WORK PROGRAMME - TYPICAL FORMS © HSKS

PRINCIPAL ACTIVITIES IMPORTANT MILESTONES FOR EMPLOYER TO MEET

SEQUENCE OF ACTIVITIES

WORK PROGRAMME: PRINCIPAL CONTENTS

IMPORTANT MILESTONES FOR CONTRACTOR TO MEET

TIMING OF ACTIVITIES IDENTIFICATION OF CRITICAL ACTIVITIES AND CRITICAL PATH

FIG. 3-2 : WORK PROGRAMME – PRINCIPAL CONTENTS © HSKS

WORK PROGRAMME: AN OVERVIEW

RESPONSIBILITY



Express Provisions



By Implication

METHOD OF WORKING

BAR CHARTS

FORM

MEANING

CONTENTS

Sequence and Timing of Activities



Critical Milestones

FOR CONTRACT ADMINISTRATOR

SEQUENCE OF WORKING

CRITICAL PATH ANALYSIS



PERT

PRIMIVERA/ MICROSOFT ‘PROJECT’ PROJECT’

PURPOSE

OPTIONS ON SUBMISSION

PART OF CONTRACT?

• Approval • Rejection • Withholding of Approval

ALTERATION/ REVISION •

General Policies



Mode of Alternatives / Revision



Effect of Alternatives/ Revision

FOR CONTRACTOR

MISCELLANEOUS

PART OF TENDER SUBMISSION?

SUBMITTED AFTER TENDER AWARD

FIG. 3-3 : WORK PROGRAMME – AN OVERVIEW © HSKS

TO LEVY CONTROL OVER PROGRESS OF THE WORKS TO ENSURE CONTRACT IS COMPLETED ACCORDING TO SCHEDULE

MISCELLANEOUS PURPOSES

PROGRESS MONITORING: EMPLOYER’S PURPOSES

TO PLAN AND STREAMLINE FINANCIAL ARRANGEMENTS TO OBVIATE DEFAULT

TO TAKE NECESSARY REMEDIAL MEASURES IF DELAY OCCURS OR IF EMPLOYER IS AT FAULT

TO WARN CONTRACTOR TO TAKE REMEDIAL MEASURES IN CASE DELAY OCCURS

FIG. 3-4 : PROGRESS MONITORING – EMPLOYER’S PURPOSES © HSKS

PROGRESS MONITORING: AN OVERVIEW

PURPOSE

DURATION



From Site Possession



To Issue of Final Certificate



Normally up to Practical Completion only

SITE POSSESSION MEETINGS



Primary Purposes



Secondary Purposes

METHODS



Use of Contractor’s Work Programme

• •

SITE PROGRESS MEETINGS

SUBSUBCONTRACTORS MEETING

Employer/ contract administrator Contractor

COORDINATION/ PROJECT MANAGEMENT MEETINGS



On regular basis



Normally ‘monthly’



Maybe i. Weekly ii. Fortnightly iii. Quarterly, etc.

SITE RECORDS

PROGRESS MEETINGS

FREQUENCY/ NATURE OF CHECKS

PARTIES RESPONSIBLE

BASIS

‘ADAD-HOC’ HOC’ MEETINGS

DURATION

PURPOSE

OFFICIAL WORK RECORDS

METHODS

OFFICIAL PROGRESS REPORTS

EVIDENTIAL VALUE

SITE DIARY

FIG. 3-5 : PROGRESS MONITORING – AN OVERVIEW © HSKS

SITE POSSESSION MEETINGS

MISCELLANEOUS MEETINGS

POST CONTRACT AWARD STAGE: PRINCIPAL TYPES OF MEETINGS

AD-HOC MEETINGS

SUB-CONTRACTOR’S MEETINGS

SITE PROGRESS MEETINGS

COORDINATION/ PROJECT MANAGEMENT MEETINGS

FIG. 3-6 : POST CONTRACT AWARD STAGE – PRINCIPAL TYPES OF MEETINGS © HSKS

SITE PROGRESS MEETINGS: AN OVERVIEW

ENABLE CONTRACTOR TO

PERMIT WORK PROGRESS TO

Officially present progress report



Be reviewed on regular basis



Present problems encountered



Identify areas and causes of delay



Enable Employer/ C.A. to redress delay caused by him/them



Keep track of financial progress/allocation

FINANCIAL ISSUES

3RD PARTY ISSUES AFFECTING CONTRACT

CONTRACT ADMINISTRATOR •

Chairs Meeting



Main participant

• S.O./ Contract Administrator

Main participant

DISTRIBUTION/ CIRCULATION • To all parties/ attendees

MISCELLANEOUS ISSUES

MAIN CONTRACTOR •

PARTICIPANTS

MINUTES

WHO PREPARES?

MISCELLANEOUS



ONLY SITE ISSUES

ISSUES/ MATTERS DEALT

PURPOSE

TIMING

NSCs

CONSULTANTS •

Observers Only



Participants if contract administrator's assistants/ representatives



By invitation only

EMPLOYER •

Observer only

FIG. 3-7 : SITE PROGRESS MEETINGS – AN OVERVIEW © HSKS

SUB-CONTRACTORS MEETINGS: AN OVERVIEW

ISSUES/ MATTERS DEALT

PURPOSE

TIMING



Usually monthly prior to site meetings



If necessary more frequently TO ENABLE SUBSUBCONTRACTOR TO

TO PERMIT CONTRACTOR TO

• Officially present progress report to Contractor

• Review NSC’s progress, areas of delay, etc.

• Present problems encountered

PARTICIPANTS

MINUTES

WHO PREPARES? • Main Contractor

DISTRIBUTION/ CIRCULATION • To all parties/ attendees

• Identify and sort coordination problems CONTRACTOR (MAIN)

NOMINATED SUBSUBCONTRACTORS

DOMESTIC SUBSUBCONTRACTORS

• Chairs Meeting

OTHERS (BY INVITATION) • Employer • Third Parties

COORDINATION MATTERS

SITE PROBLEMS

FINANCIAL ISSUES

3RD PARTY ISSUES

• Design

• Possession

• Payments

• Authorities

• Site Work

• Access

• V.O.s

• Utilities Providers

• Security

• Claims

• Others

MISCELLANEOUS ISSUES

• Contract Administrator

FIG. 3-8 : SUB-CONTRACTORS MEETINGS – AN OVERVIEW © HSKS

‘AD-HOC’ MEETINGS: AN OVERVIEW

CONVENORS (AS APPLICABLE)

TIMING

AS AND WHEN NECESSARY FROM TIME TO TIME



The Employer



The Contract Administrator



The Contractor



The Sub-Contractors

PURPOSE

USUALLY DICTATED BY CIRCUMSTANCES

EMERGENCY ISSUES

TO DISCUSS SPECIFIC ISSUES / MATTERS

ADMINISTRATIVE MATTERS

TECHNICAL ISSUES

FINANCIAL ISSUES



Site Issues



Payments



Design



Training



Design/ Work Issues



V.O.s



Construction/Installation



Maintenance



3rd



Claims



Testing and Commissioning



‘As-Built’ Records



Defects

Party Issues

MISCELLANEOUS ISSUES

FIG. 3-9 : ‘AD-HOC’ MEETINGS – AN OVERVIEW © HSKS

SITE RECORDS: AN OVERVIEW

PURPOSE

DURATION •

From Date of Commencement / Site Possession to



Completion of works



Normally up to Practical Completion only PROVIDE NECESSARY INFORMATION/ EVIDENCE TO

EVALUATE CONTRACTOR’’S CONTRACTOR CLAIMS TO

REVIEW WORK PROGRESS •

Contractor’s Scope



Extension of Time



NSC’s/DSC’s Scope



Additional Work



Direct loss and/or expense



Miscellaneous matters

EVIDENTIAL VALUE

METHODS

OFFICIAL PROGRESS REPORT

OFFICIAL WORK RECORDS

PERMIT DECISION MAKING

SITE DIARY

DULY SIGNED/ ENDORSED RECORDS •

Best evidential value

ACKNOWLEDGEMENT OF RECEIPT RECORDS •

Some evidential value

FIG. 3-10 : SITE RECORDS – AN OVERVIEW © HSKS

OFFICIAL WORK RECORDS: AN OVERVIEW

TIMING OF SUBMISSION

DAILY

WEEKLY

PURPOSE

PROCEDURAL MATTERS

CONTENTS

USE OF DESIGNATED STAFF FOR

FORTNIGHTLY

• Preparing • Maintaining • Submitting RECORD OF SITE INFORMATION

SITE WORK/ ACTIVITIES

FOR CONTRACT ADMINISTRATION

RECORD OF WORKERS

• Planned

• Skilled

• Undertaken

• Unskilled

SIGNING OR ENDORSEMENT • By authorized Person(s)

TIME OF ENTRY

• S.O/ Contract Administrator

• Daily

FOR BASIS OF OFFICIAL PROGRESS REPORT

RECORD OF PLANT/MACHINER Y • On site

WEATHER CONDITIONS

SAFE KEEPING • By S.O./Contract administrator • Up to lapse of period of limitation

PROBLEMS ENCOUNTERED

INSTRUCTIONS

• Affecting work

• Design

• Received

• Delaying site operations

• Site

• Carried Out

• Coordination

• Outstanding

MISCELLANEOUS

• Site/ Factory Visits • Inspections

• Due to 3rd Parties

FIG. 3-11 : OFFICIAL WORK RECORDS – AN OVERVIEW © HSKS

SITE DIARY: AN OVERVIEW

NATURE

DURATION



Preferably kept by each and every site personnel



From commencement of work on site until completion



Personal record of site activities



If necessary until the end of the contract



Otherwise by designated site supervision team member

• Undertaken

ENTRIES ON DAILY BASIS •

SITE WORK/ ACTIVITIES

PROCEDURAL MATTERS

CONTENTS

By designated person

PROBLEMS ENCOUNTERED

INSTRUCTIONS



As to Site Work

• Issued to Contractors



Coordination

• Carried out by Contractor

PRESENTATION ON REQUEST/ DEMAND

CHECKING / ENDORSEMENT •

By Employer’s Representative/ Designated person



Accuracy of entries

RECORD OF • Contractor’s defaults /omissions



By Employer/ S.O./ any interested party

MISCELLANEOUS • Site/ factory visits • Weather conditions • Disruption to site activities

SAFE KEEPING/ CUSTODY •

By S.O./ contract administrator



Up to lapse of period of limitation

ATTACHMENTS • ‘As-Built’ sketches, drawings, diagrams, etc. • ‘As-erected’/ ‘AsInstalled’ Work/ plant, etc.

FIG. 3-12 : SITE DIARY – AN OVERVIEW © HSKS

SUPERVISION OF WORKS/ CONTRACT ADMINISTRATION

© HSKS

4.0 1.0

SUPERVISION OF WORKS/CONTRACT ADMINISTRATION CONTRACT ADMINISTRATION  PURPOSE  DESIGNATION  ROLES  SOURCES OF DUTIES AND POWERS  REPRESENTATIVE/ASSISTANTS  PRINCIPAL DUTIES  LIABILITY

2.0

SUPERVISION  FORMS  DURATION  LEVEL  LIABILITIES

3.0

DISCUSSION OF CASE LAW © HSKS

ENSURE WORKS SATISFACTORILY COMPLETED WITHIN ORIGINAL CONTRACT PERIOD AND PRICE

ENSURE THAT CONTRACTOR FULFILLS HIS OBLIGATIONS UNDER THE CONTRACT ENSURE THAT EMPLOYER FULFILLS HIS OBLIGATIONS UNDER THE CONTRACT

CONTRACT ADMINISTRATION: PRIMARY PURPOSES

ENSURE THAT NEEDS/ OBLIGATIONS OF CONTRACT ADMINISTRATOR UNDER CONTRACT/STATUTE ADEQUATELY FULFILLED

ENSURE THAT EMPLOYER’S POSITION ADEQUATELY PROTECTED AGAINST VARIOUS CLAIMS

ENSURE THAT EMPLOYER FULFILS HIS STATUTORY/LOCAL AUTHORITY REQUIREMENTS

FIG. 4-1 : CONTRACT ADMINISTRATION – PRIMARY PURPOSES © HSKS

SUPERINTENDING OFFICER/ S.O.

CONSTRUCTION MANAGER

PROJECT DIRECTOR

EMPLOYER’S REPRESENTATIVE

CONTRACT ADMINISTRATORS: COMMON DESIGNATIONS

ARCHITECT

ENGINEER

FIG. 4-2 : CONTRACT ADMINISTRATORS – COMMON DESIGNATIONS © HSKS

AS TO RIGHTS/ DUTIES UNDER THE CONTRACT WITH IMPLIED/ OSTENSIBLE AUTHORITY

WITH EXPRESS AUTHORITY

AS TO MATTERS OF COST

AS AN AGENT OF THE EMPLOYER

AS TO OTHER MATTERS

AS AN ADVISOR TO THE EMPLOYER

CONTRACT ADMINISTRATOR: RANGE OF ROLES PERFORMED

AS AN INDEPENDENT/ IMPARTIAL ADJUDICATOR

AS AN INDEPENDENT CONTRACTOR

WHERE SUCH WORK IS REQUIRED POSTCONTRACT

FOR MAINLY DESIGN/ DETAILING WORK

AS TO DISPUTE RESOLUTION

AS TO CERTIFICATION

FIG. 4-3 : CONTRACT ADMINISTRATOR – RANGE OF ROLES PERFORMED © HSKS

TERMS OF REFERENCE OF APPOINTMENT

CONDITIONS OF CONTRACT BEING ADMINISTERED

‘IN-HOUSE’ EMPLOYEE

CONDITIONS OF ENGAGEMENT/ SERVICES AGREEMENT

CONDITIONS OF CONTRACT BEING ADMINISTERED

EXTERNAL BODY/PERSON

CONTRACT ADMINISTRATOR: SOURCES OF DUTIES AND POWERS

FIG. 4-4 : CONTRACT ADMINISTRATOR – SOURCES OF DUTIES AND POWERS © HSKS

ARCHITECT SPECIALIST CONSULTANT

PROJECT MANAGER

CIVIL ENGINEER

CONTRACT ADMINISTRATOR’S REPRESENTATIVES/ ASSISTANTS: TYPICAL EXAMPLES

QUANTITY SURVEYOR

STRUCTURAL ENGINEER

MECHANICAL ENGINEER

ELECTRICAL ENGINEER

FIG. 4-5 : CONTRACT ADMINISTRATOR’S REPRESENTATIVES/ASSISTANTS - TYPICAL EXAMPLES © HSKS

OVERALL SUPERVISION

PROGRESS MONITORING

ADMINISTRATION OF PAYMENTS ISSUING INFORMATION, DRAWINGS, DETAILS, ETC.

ORDERING VARIATIONS ISSUING RELEVANT INSTRUCTIONS

GRANTING APPROVALS, CONSENTS, ETC.

INSPECTIONS OF WORKS

NOMINATING SUB-CONTRACTORS, ETC.

ADVISING EMPLOYER

CONTRACT ADMINISTRATOR’S PRINCIPAL DUTIES FOR TRADITIONAL GENERAL CONTRACTS

ISSUING NECESSARY REPORTS OVERSEEING TRAINING OF EMPLOYER’S O & M PERSONNEL OVERSEEING COMPLETION & HANDING OVER OF WORKS MONITORING RECTIFICATION OF DEFECTS PARTICIPATING IN PREPARATION OF MIGRATION/ FACILITIES MANAGEMENT PLANS

PARTICIPATING IN TESTING AND COMMISSIONING

MONITORING SERVICING AND MAINTENANCE CHECKING AND APPROVING O & M MANUALS & ‘AS-BUILT’ DRAWINGS PREPARING ‘FINAL ACCOUNT’

‘CLOSING-OFF’ CONTRACT

FIG. 4-6: CONTRACT ADMINISTRATOR’S PRINCIPAL DUTIES FOR TRADITIONAL GENERAL CONTRACTS © HSKS

FULL-TIME SUPERVISION

NOMINAL SUPERVISION

STANDING SUPERVISION

FORMS OF SUPERVISION: COMMON LABELS

PERIODIC SUPERVISION

CONSTANT SUPERVISION

PART-TIME SUPERVISION

FIG. 4-7 : FORMS OF SUPERVISION – COMMON LABELS © HSKS

SUPERVISION/INSPECTIONS: OVERVIEW (PART I)

TYPICAL CLAUSES IN AGREEMENTS •

TYPICAL PROVISIONS IN BYBY-LAWS

Engineer’s Agreement:



1. Clause 8.1 and 8.7 BEM Form (1999) •

Building (Federal Territory of Kuala Lumpur) By-Laws 1985: 1. By-Law 6: Supervision of Works

NATURE AND MEANING



Terms used synonymously



See Newey J’s definition



Distinction: Inspection imposes a lesser duty: William Tompkinson v St. Michael in the Hamlet.

Architect’s Agreement 1. Clause 5(4)(iv) Part II: Architects (Scale of Minimum Fees) (Amendment) Rules 1992 2. Clause 9 Conditions of Engagement of Architect

2. By-Law 23(1): Certificate For Occupation • •

By-Law 5(1) City of Kuala Lumpur (Earthworks) By-Laws 1975 •

PURPOSES



See Keating’s definition in ‘Building Contracts’



Three fold purpose:

In absence of express provisions to contrary courts imply a duty of supervision: Alexander Corfield v David Grant. Malaysia: Statutory provisions necessitate ‘supervision’

1. To ensure contractor carries out work in accordance with contract. 2. To enable contract administrator to discharge his obligations to employer. 3. To enable contract administrator to meet his statutory obligations

FIG. 4-8 : SUPERVISION/INSPECTIONS – OVERVIEW (PART I) © HSKS

SUPERVISION/INSPECTIONS: OVERVIEW (PART II)

LEVEL OF SUPERVISION REQUIRED

DURATION



Determining factors:



1. Nature of works under contract Normal periods:

2. Applicable statutory provisions e.g. By-Laws •

1. Up to issue of Practical Completion; or

2. Category II: PartTime/Periodic Supervision

3. Up to issue of Certificate of Making Good Defects Common practice is up to issue of Certificate of Making Good Defects

Necessity for Resident Site Staff (RSS)



Typical examples: 1. Resident architect/engineer 2. Clerk-of-works. 3. Other relevant staff

Prevailing Forms: 1. Category I: Fulltime/Standing/ Constant supervision

2. Up to application of certificate for occupation; or





1. Conditions of engagement

2. Conditions of engagement •

Determined by:

RESIDENT SITE STAFF



2. Must be sufficient to check the important elements

Primary responsibility for supervision: contractor’s. See East Ham Corp. v Bernard Sunley.



Heads of liabilities of contract administrator for defaults/ breaches:

Engagement:



Powers and duties determined by engineering/construction contract being administered and/or letter of delegation of power.



Responsibilities of:

Legal Position: 1. Must be reasonable for works involved



1. Contractual 2. In tort 3. Statutory

1. By employer; or 2. By contract administrator

3. Category III: ‘Nominal’ Supervision •

LIABILITIES



Position of contract administrators who are professional engineers, architects, etc.

1. RSS 2. Contract Administrator

3. Adequate to meet statutory requirements 4. Sufficient to meet obligations of engagement

FIG. 4-9 : SUPERVISION/INSPECTIONS – OVERVIEW (PART II) © HSKS

CONTRACT ADMINISTRATOR’S LIABILITIES: AN OVERVIEW (PART I)





CONTRACTUAL LIABILITY

LEGAL KNOWLEDGE AND PERSONAL DUTY

HEADS OF LIABILITIES Three main categories:



1. Contractual 2. Tortious 3. Statutory

General position: Required to have knowledge of all legal matters relating to work being undertaken



Nature of matters.

Characteristics:



Consequences of failure

1. Not distinct/mutually exclusive



Duty is personal and non-delegable

DEFENCES

2. Concurrent/complementary



Prove no valid express/implied contract of engagement



If there is such valid contract prove:

3. Choice of option on aggrieved part

STANDARD OF CARE

GENERAL POSITION •

Action by employer under terms of contract of engagement



If no express terms, implied by law



Contract of engagement: 1. Standard forms, or 2. ‘Bespoke’ Forms



Duty of care owed to employer



Usually to use ‘reasonable skill and care’



Duty and standard of care either: 1. Expressed in contract of engagement, or 2. Implied by law

EFFECT OF BREACH •

Two options available to employer:

1. Rescind contract and sue for damages; or

1. Contract didn’t impose particular duty breach of which claimed, or 2. Service actually rendered was of the standard reasonably expected under the circumstances

2. Affirm contract and sue for damages •

Right of election of option belongs to employer

FIG. 4-10 : CONTRACT ADMINISTRATOR’S LIABILITIES – AN OVERVIEW (PART I) © HSKS

CONTRACT ADMINISTRATOR’S LIABILITIES: AN OVERVIEW (PART II) TORTIOUS LIABILITY

NEGLIGENCE

GENERAL POSITION •

Duty of care in tort of negligence concurrent with contractual duty: Brown v Boorman



Common Forms: 1. Acts/omissions 2. Mis-statements

BASIC ELEMENTS

DEFINITION •

• •

Laid down in Donoghue v Stevenson ‘Neighbourhood’ principle



D owed P duty of care



Application of the ‘Bolam Test’



D breached this duty





Consequence: P suffered loss/damage

Use of ‘Reasonable Man’ test



Use by Malaysian Courts

Loss/damage suffered not remote



Important elements: 1. Causation 2. Forseeability

STANDARD OF CARE





Criterion: Objective



Less onerous





Proscribe use of hindsight



See Eckersly v Binnie & Partners

Per Hunter v Henley



2. Fitness for purpose •

Need to satisfy all 3 element on balance of probabilities

Only 3 types:



1. Deny existence of duty of care

No liability to contractor



Possible exceptions: See Para 5.9B5.

2. Prove claim made not of type currently recognized

2. D did not adopt the practice 3. Practice adopted by D would not be adopted by another reasonable D

LIABILITY TO 3RD PARTIES

DEFENCES

1. There is a usual and normal practice

Use of standards prevailing at time of default



2 Categories: 1. Reasonable skill & care

ESTABLISHING LIABILITY

REASONABLE SKILL & CARE

3. Show service rendered meets ‘Bolam Test’ •

No immunity to suit: Sutcliffe v Thackrah



Situation per ‘Pure Economic Loss’

FIG. 4-11 : CONTRACT ADMINISTRATOR’S LIABILITIES – AN OVERVIEW (PART II) © HSKS

CONTRACT ADMINISTRATOR’S LIABILITIES: AN OVERVIEW (PART III)

STATUTORY LIABILITY

LIABILITIES UNDER DELEGATED LEGISLATION

DIRECT STATUTORY LIABILITY

GENERAL POSITION

PROFESSIONAL LIABILITY



In addition to Contractual and Tortious Liability



Various Acts of Parliament applicable



Liability under various ByLaws e.g. UBBL, etc.



For professional contract administrator



Various sub-heads:





Penalties/sanctions stipulated in the By-Laws



1. Direct statutory liability 2. Under delegated legislation 3. Professional liability

Principal example: S71 Street, Drainage & Building Act 1974

Under specific Acts of Parliament



Penalty for mis-supervision, etc.



Possible sanctions: 1. Fine 2. Suspension 3. Cancellation of registration

FIG. 4-12 : CONTRACT ADMINISTRATOR’S LIABILITIES – AN OVERVIEW (PART III) © HSKS

PAYMENTS/ COMMERCIAL MATTERS

© HSKS

5.0

PAYMENTS/COMMERCIAL MATTERS



LEGAL OBLIGATION OF EMPLOYER



PAYMENT TO MAIN CONTRACTOR/TURNKEY CONTRACTOR



PAYMENT TO SUBSUB-CONTRACTORS



‘BACK TO BACK’ BACK’ PAYMENTS



BREACHES IN PAYMENT OBLIGATIONS



RELEVANT CASES •

SUTCLIFFE V THACKRAH [1974] 1 ALL ER 319

*

CROUDACE LTD. V THE LONDON BOROUGH OF LAMBETH [1986] 33 BLR 20

*

GUNUNG BAYU SDN. BHD. V SYARIKAT PEMBINAAN PERLIS SDN. BHD. [1987] 2 MLJ 332

*

HAJI ABU KASSIM V TEGAP CONSTRUCTION SDN. BHD. [1981] 2 MLJ 149

*

KAH SENG CONSTRUCTION SDN. BHD. V SELSIN DEVELOPMENT SDN. BHD. [1997] 1 CLJ SUPP 448

*

YONG MOK HIN V UNITED MALAY STATES SUGAR INDUSTRIES LTD. [1966] 2 MLJ 286

*

JALLCON (M) SDN. BHD. V NIKKON METAL (M) SDN. BHD. (No. 2) [2001] 5 MLJ 716, HC.

© HSKS

PROCEDURES AND CONDITIONS PRECEDENT

QUANTUM/AMOUNT

SET-OFF/DEDUCTIONS

ENFORCEMENT/HONOURI NG

TIMING

PAYMENT: ASPECTS OF CONTRACTOR’S ENTITLEMENTS/EMPLOYER’S OBLIGATIONS

FIG. 5-1: PAYMENTS – ASPECTS OF CONTRACTOR’S ENTITLEMENT/EMPLOYER’S OLIGATIONS © HSKS

TIMING OF PAYMENT TO CONTRACTOR: PRINCIPAL SCHEMES/SCHEDULES

PERIODIC SCHEDULE DURING CURRENCY OF THE CONTRACT

OF WHOLE CONTRACT SUM

STAGES/MILESTONE PAYMENT

PHYSICAL WORKS

PERIODIC SCHEDULE AFTER COMPLETION/ END OF CONTRACT

ADVANCE PAYMENT

FINANCIAL

OF PART OF CONTRACT SUM

AFTER ISSUE OF CPC

AFTER COMPLETION/ END OF CONTRACT

AFTER ISSUE OF CPC

AFTER ISSUE OF FINAL CERTIFICATE

MISCELLANEOUS/ METHODS

AFTER ISSUE OF FINAL CERTIFICATE

FIG. 5-2 : TIMING OF PAYMENT TO CONTRACTOR – PRINCIPAL SCHEMES/SCHEDULES © HSKS

START

Contract administrator to resolve all preliminary issues

Yes

Are the preliminary matters expressly stipulated in the contract? No

Yes

Are they included in the Project Procedures Manual? No Have these been sorted- out following award of contract?

No

Yes Have these been formalized by all the parties?

No

Contract administrator to take necessary action forthwith

Yes Contract administrator to issue formal record of issues agreed upon by all relevant parties

All relevant parties to take necessary steps to implement issues

A

FIG. 5-3: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART I) © HSKS

A

Establish if the contractor has fulfilled his first pre -condition to payment

Has the contractor commenced with the work under the contract?

No

Yes Has he executed any physical work?

No

Yes Has he delivered materials to site?

No

Contractor not entitled to any payment

Yes Prima facie, contractor may be entitled to payment

Contract administrator not obliged to initiate the progress payment

Establish if it is necessary for the contractor to apply for the required payment

No

Does the contract contain an express term thereto? Yes

B

C

D

FIG. 5-4: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART II) © HSKS

C

B

Contractor not obliged to apply

No

D

Is it mandatory? Yes

Contract administrator obliged to initiate process on his own volition

Has contractor complied with requirements?

No

Contractor may not be entitled to payment until he satisfies pre -conditions

Yes Contract administrator to proceed with the next stage i.e. valuation

Has the date of valuation been reached?

No

Yes Have the relevant pre-conditions been fulfilled?

No

Prima facie, valuation may not be initiated until achievement of necessary requirements

Yes No

Have the parties involved been identified? Yes

Deficiencies/omissions to be addressed forthwith to enable process to continue

No

Has the method for valuation been confirmed? Yes

E

F

G

FIG. 5-5: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART III) © HSKS

F

E

G

Valuation of works to be carried out jointly by the relevant parties

Valuers to prepare a valuation report

Yes

Does the contractor agree with the valuation? No

Yes

Does he sign off the valuation report?

No Valuation deemed to have been accepted by the contractor

No

Does he officially register his protest with valuers? Yes Do the valuers consider the objections protest? Yes Do they agree with the objections?

No

No

Contractor may protest to the certifier if necessary

Yes Valuers may revise/amend the valuation as necessary

Does the Contractor protest to the certifier?

Valuers to endorse/sign off the valuation report prepared

H

No

Yes

I

J

K

FIG. 5-6: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART IV) © HSKS

H

I

J

K

Valuation report together with all other necessary documents to be submitted to the certifier Certifier to clarify/ discuss deficiencies/ omissions with the valuers

Certifier to carry out preliminary reviews

Is the valuation report complete, sufficient and accurate?

No

Deficiencies/ omissions may compromise the certification

Yes Certifier to take objections into consideration before undertaking certification

Yes

Has the contractor any valid grounds for objecting? No Certifier not to consider objections any further

L

Certifier may exercise No his discretion in undertaking certification

Is the date for certification imminent? Yes

No

Should in his discretion a certificate be issued? Yes

M

Has the stipulated minimum value of work been exceeded?

No

Certifier has no discretion to carry out certification

Yes Certifier to proceed with the necessary certification procedures

N

O

FIG. 5-7: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART V) © HSKS

M

L

N

O

Is the 1st Interim Certificate due?

No

Yes Have all the stipulated pre-conditions been met?

No

Yes Is the subsequent Interim Certificate due?

No

Yes Have all the relevant pre-conditions been met?

No

Prima facie, certificate cannot be issued

Yes Certifier to proceed with preparation of Interim Certificate

Is there a standard form of certificate prescribed?

Yes

Use the standard form as prescribed

No Utilize the form unless found not suitable

Yes

Has a ‘bespoke’ form been generated? No Certifier to develop an ‘ad hoc’ form meeting the necessary criteria/contents requirements

P

Q

R

S

T

FIG. 5-8: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART VI) © HSKS

P

R

Q

T

S

Certifier to fill in all details completely, sufficiently and correctly in certificate Are there any NSCs/Nominated Suppliers?

Yes

No Are there any official assignees?

Yes

Amount certified for such parties to be indicated separately in certificate

No No

Are all procedural requirements met? Yes

No

Are all formal requirements met? Yes

Certificate may be challenged as invalid and unenforceable, if and when issued

No

Is the signatory an authorized person under the contract? Yes Have all the relevant checks for errors, etc. been undertaken?

No

Deficiencies/ errors may compromise validity of certificate

Yes U

V

W

X

FIG. 5-9: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART VII) © HSKS

U

V

W

CA to rectify deficiencies/errors as soon as possible

Contract administrator to issue relevant certificate

Is there a certification period stipulated in the contract?

X

No

Certificate to be issued within a reasonable time of application/ valuation

No

Default in service may constitute a breach of contract on employer’s part. To be corrected/ rectified forthwith

Yes Prima facie, employer may be in breach of contract. Contractor may take appropriate action for employer’s breach

No

Is certificate issued within the said period? Yes

Contractor to be furnished with original copy

No

Is the recipient of the original copy stipulated? Yes Is the certificate issued to the stipulated person? Yes Are copies issued to the relevant parties?

No

Relevant parties have a right to demand the necessary copies from contract administrator

Yes No

Is the service of certificate formally evidenced? Yes

Y

Z

AA

AB

FIG. 5-10: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART VIII) © HSKS

Y

AA

Z

AB

Establish the specific post-certification requirements

Do the recipients formally acknowledge receipt of document?

No

Omission to acknowledge may lead to future evidential problems

Yes No

Contractor may present certificate within a reasonable period of receipt

Contract administrator to procure said acknowledgements as soon as possible

Is presentation of certificate stipulated in the contract? Yes

No

Is there a period stipulated for the presentation? Yes Is presentation formally effected within this period?

No

Delay may postpone employer’s obligation to honour certificate

Yes Does employer formally acknowledges receipt of the certificate from contractor?

No

Omission to acknowledge may lead to future evidential problems and may affect the honouring of certificate

Yes Employer to review certificate for validity

AC

AD

AE

Contractor to procure said acknowledgement as soon as possible

AF

FIG. 5-11: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART IX) © HSKS

AC

AD

AE

Are there grounds for challenging validity of certificate?

AF

Yes

Employer may challenge certificate and refuse to honour it citing the relevant grounds

No Employer to proceed with honouring certificate issued/ presented (as applicable)

No

Are there any set-offs/deductions to be made? Yes

Employer must pay amount as certified to the contractor

No

Are these expressly permitted by the contract? Yes Has the amount certified less the setoffs/ deduction been established? Yes Has the final sum due been paid to the contractor?

No

Employer to determine amount due before the stipulated honouring period lapses

No

Yes Has this been done in the stipulated honouring period?

No

Employer culpable of breach of contract. Contractor to take appropriate action.

Yes

STOP

FIG. 5-12: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART X) © HSKS

RECOVERY OF THE UNPAID AMOUNT MISCELLANEOUS REMEDIES

INTEREST ON THE UNPAID AMOUNT

DEFAULT IN PAYMENT: TYPICAL CONTRACTUAL REMEDIES

RIGHT TO DETERMINE EMPLOYMENT UNDER CONTRACT

RIGHT TO REDUCE RATE OF EXECUTING WORK RIGHT TO SUSPEND WORK

FIG. 5-13 : DEFAULT IN PAYMENT - TYPICAL CONTRACTUAL REMEDIES © HSKS

CERTIFICATE WRONG ON ITS’ FACE

CERTIFICATE FUNDAMENTALLY INACCURATE

CERTIFICATE NOT IN CORRECT FORM

CERTIFICATE ISSUED BY UNAUTHORISED PERSON CERTIFICATE ISSUED IN UNAUTHORISED MANNER

INTERIM CERTIFICATES: TYPICAL CHALLENGES

CERTIFICATE ISSUED OUT OF TIME CERTIFIER ACTING ‘ULTRA VIRES’ CERTIFIER IMPROPERLY PRESSURIZED/INFLUENCED CERTIFICATE SUBJECT TO FRAUD/COLLUSION FRAUD, DISHONESTY/FRAUDULENT CONCEALMENT BY CONTRACTOR MISCELLANEOUS CHALLENGES

FIG. 5-14: INTERIM CERTIFICATES – TYPICAL CHALLENGES © HSKS

DIRECT PAYMENT BY THE EMPLOYER

PAYMENT UPON CERTIFICATION

CONTINGENT PAYMENT

PAYMENT TO SUB-CONTRACTORS: PRINCIPAL METHODS

FIG. 5-15 : PAYMENT TO SUB-CONTRACTORS – PRINICPAL METHODS © HSKS

START Sub-Contractor (SC) forwards details of amount claimed to Main Contractor (MC) officially

SC to make fresh submission in the next application No

Is it within the prescribed time limits? Yes

No

Does the MC accept the submission? Yes

MC to include SC’s details in his claim

MC to submit consolidated claim to the Contract Administrator (CA)

CA to carry out the necessary valuation

CA to issue interim payment certificate to MC

Employer to pay certified amount to MC within the Honouring Period

Establish if there is a Contingent Payment Type II clause in the sub-contract

A

FIG. 5-16: FLOWCHART ON GENERAL PROCEDURE FOR TYPE II ‘CONTINGENT PAYMENT’ (PART I) © HSKS

A Is there such a clause in the contract?

No

Yes Is the period for payment stated?

No

MC may pay SC within a reasonable time of receipt of monies from the Employer

Yes Yes

Does the MC pay the SC within the said period? No SC to pursue the remedies available under the contract

Are there any contractual remedies available?

Yes

SC to initiate the contractual remedies as applicable

Yes

SC to initiate the Arbitration process if necessary

No Is there an arbitration agreement? No SC to pursue his common law remedies if necessary

STOP

FIG. 5-17: FLOWCHART ON GENERAL PROCEDURE FOR TYPE II ‘CONTINGENT PAYMENTS’ (PART II) © HSKS

PAYMENT IN ‘PACKAGE DEAL’ TYPES OF CONTRACTS: AN OVERVIEW

CONTRACT SUM ANALYSIS

PURPOSE

DRAFTING

• For Tender Analysis • For Interim Payment • Valuation of Changes/ Provisional Sums

• Normally by Contractor • Samples may be given by Employer in Employer’s Requirements

• For any Price Adjustment

GENERAL POSITION

MEASUREMENT

QUANTITIES

STRUCTURE • Given in some Forms e.g. JCT 98, PWD Form DB/T, etc. • Required for: 1. Overall Works 2. Sections or Phases

EXPRESS PROVISIONS

• Whenever used, effect not similar to TGC

• Included in most Standard Forms

• Are deemed to be only estimates

• E.g. Clause 55(1) ICE, Clause 13.1(d) FIDIC, etc.

GENERAL POSITION • As based on Lump Sum and due to nature of contract

SITUATIONS WHERE USED • Changes/V.O.s • Unforeseen Conditions

• No requirement for measurement

ERRORS/ OMISSIONS

ACCURACY • Effect of measurement expressly stipulated in some forms • Mostly deals with patent errors

PREPARATION

• Risk on Contractor

• Contractor responsible

• E.g. Clause 55(2) ICE Form

• If Employer prepares, risk for errors/omissions normally passed on to Contractor

FIG. 5-18 : PAYMENT IN ‘PACKAGE DEAL’ TYPES OF CONTRACTS: AN OVERVIEW © HSKS

FINAL AMOUNT TO WHICH CONTRACTOR ENTITLED TO UNDER THE CONTRACT

FINAL ADJUSTMENTS TO THE CONTRACT SUM

FINAL AMOUNT (SET OFFS/ DEDUCTIONS) TO WHICH EMPLOYER ENTITLED TO UNDER THE CONTRACT

FINAL ACCOUNT: PRINCIPAL CONTENTS

FIG. 5-19 : FINAL ACCOUNT – PRINCIPAL CONTENTS © HSKS

APPROVED VARIATIONS TO THE CONTRACT MISCELLANEOUS ADJUSTMENTS

ADJUSTMENT FOR PRICE FLUCTUATION, ETC.

APPROVED CONTRACTOR’S CLAIMS

ADJUSTMENT TO THE CONTRACT SUM: TYPICAL HEADS/ITEMS

ADJUSTMENT FOR P.C. SUMS/ PROVISIONAL SUMS

PERMITTED COSTS FOR TESTING, OPENING UP OF WORK, ETC.

FEES AND CHARGES FOR PERMANENT CONNECTIONS REMEASUREMENT OF ‘PROVISIONAL’ ITEMS/WORK

FIG. 5-20 : ADJUSTMENT TO THE CONTRACT SUM – TYPICAL HEADS/ITEMS © HSKS

VARIATIONS/CHANGES

© HSKS

6.0

VARIATIONS/CHANGES



WHAT CONSTITUTES ‘VARIATIONS/CHANGES’ VARIATIONS/CHANGES’



ISSUES AS TO VALIDITY



PROBLEMS WITH VARIATIONS



INVALID VARIATION ORDERS AND EFFECTS



LIMITATIONS OF VARIATIONS



RELEVANT CASES *

SHARPE V SAN PAULO RAILWAY [1873] L.R. 8 CH. APP. 597

*

RE CHITTICK & TAYLOR [1954] 12 WWR 653

*

MITSUI CONSTRUCTION CO. LTD. V A.G. OF HONG KONG [1986] 33 BLR 1

*

CARR V JA BERRIMAN PTY LTD. [1953] 27 A.L.J.R. 273

*

COMMISSIONER FOR MAIN ROADS V REED & STUART PTY LTD. & ANOR [1974] A.L.J.R. 461

*

SIR LINDSAY PARKINSON & CO. LTD. V COMMISSIONERS OF AND PUBLIC BUILDINGS [1950] 1 ALL ER 2008

HIS MAJESTY’S WORKS

*

ANTARA ELEKTRIK SDN. BHD. V BELL & ORDER BHD [2002] 3 MLJ 321, HC. © HSKS

VARIATIONS

FACTORS DETERMINING A VALID V.O.

TYPES

ADDITION

OMISSION

HYBRID

LEGAL NATURE OF PROPOSED CHANGE

FORMALITIES

ISSUE BY DESIGNATED OFFICER

PROCEDURAL REQUIREMENTS

EXPRESS CONTRACT CONDITIONS APPLICABLE

APPLICABLE COMMON LAW RULES

FIG. 6-1: VARIATIONS: OVERVIEW © HSKS

CHANGE TO BE IN RELATION TO SCOPE OF THE WORK

A CHANGE BEING EFFECTED

SCOPE OF WORK BEING CHANGED MUST BE AS EXPRESSLY OR IMPLIEDLY CONTAINED IN CONTRACT DOCUMENTS

CHANGES/VARIATIONS: BASIC ELEMENTS

FIG. 6-2 : CHANGES/VARIATIONS – BASIC ELEMENTS © HSKS

INCREASE/ DECREASE QUANTITY OF WORK

OMIT WORK

EXECUTE ADDITIONAL WORK OF ANY KIND

CHANGE CHARACTER OF WORK

VARIATIONS: TYPICAL EXAMPLES

CHANGE SEQUENCE OF WORK

CHANGE QUALITY OF WORK

CHANGE TIMING OF WORK ACTIVITIES

CHANGE KIND OF WORK

CHANGE DIMENSIONS OF WORK

CHANGE LEVELS OF WORK CHANGE POSITION OF WORK

FIG. 6-3: VARIATIONS - TYPICAL EXAMPLES © HSKS

OMISSIONS

ADDITIONS

HYBRID

ACCORDING TO NATURE OF THE CHANGE

NSC

CONTRACTOR

TIME IMPLICATIONS CONTRACT ADMINISTRATOR

EMPLOYER

ACCORDING TO IDENTIT Y OF INITIATOR OF CHANGE

COMBINATION OF BOTH

FINANCIAL CONSIDERATIONS

ACCORDING TO CONSEQUENCES/EFFECT OF THE CHANGE

TYPES OF VARIATIONS: MAIN METHODS OF CLASSIFICATION

FIG. 6-4: TYPES OF VARIATIONS – MAIN METHODS OF CLASSIFICATION © HSKS

CHANGES IN EMPLOYER’S REQUIREMENTS

INTEFERENCE BY EMPLOYER

MALADMINISTRATION OF CONTRACT

DEFECTIVE DRAWINGS

DEFECTIVE SPECIFICATIONS

DEFECTIVE CONTRACT DOCUMENTS

ITEMS CONSTITUTING VARIATIONS

WRONG/ NEGLIGENT ADVICE FROM CONTRACT ADMINISTRATOR

DIFFERENCES BETWEEN BILLED AND ACTUAL QUANTITIES CHANGES DUE TO STATUTORY/ LEGISLATIVE CHANGES

FIG. 6-5: ITEMS CONSTITUTING VARIATIONS © HSKS

WHAT CONSTITUTES VARIATION WORKS

LEGAL POSITION

1. Test: What is the intention of the parties at time of contracting 2. Extras: Work not contemplated by parties when contracting and not provided in Contract. 3. Works which are indispensably necessary to give effect to parties intentions: Not extra

CONTRACTS BASED ON BILL OF QUANTITIES 1. Rule: All items intended to be executed by Contractor must be provided for in the Contract. 2. All items not provided for in Contract are extras. 3. Literal interpretation/ strict construction.

CONTRACTS BASED ON DRAWINGS AND SPECIFICATIONS 1. Rule: Contract requires: a) Not only work set out in drawings and/or specifications b) But also all work incidental or necessarily required whether set out in the drawings and/or described in specifications or not

VARIATION TEST PER RE:

CHITTICK & TAYLOR 1. Item specifically provided for in Contract: ‘Not Extra’ 2. If Contractor varies, contract without an instruction: Cannot Claim for ‘Extra’ 3. If Contractor instructed by C.A. to change contract: has basis for claim for ‘Extra’

2. Effect: Difficult to claim extra work [Re: Sharpe v Sao Paulo Railway]

FIG. 6-6 : WHAT CONSTITUTES VARIATION WORKS © HSKS

WORKS CHANGED MUST BE DEFINED IN CONTRACT DOCUMENTS

THERE MUST BE AN ‘INSTRUCTION’

VALID VARIATION ORDER: PRINCIPAL ELEMENTS

INSTRUCTION MUST EFFECT A CHANGE TO THE WORKS

‘INSTRUCTION’ TO BE ISSUED BY CONTRACT ADMINISTRATOR OR BY AUTHORISED PERSON

FIG. 6-7 : VALID VARIATION ORDER – PRINCIPAL ELEMENTS © HSKS

COMPLIANCE WITH THE RELEVANT EXPRESS CONTRACT PROCEDURES

EXISTENCE OF EXPRESS CONTRACTUAL PROVISION PERMITING VARIATION OF WORK UNDER THE CONTRACT

VALIDITY OF VARIATION ORDERS: PRINCIPAL FACTORS DETERMINING

ISSUE OF VARIATION ORDER BY DESIGNATED PERSON

COMPLIANCE WITH THE APPLICABLE COMMON LAW RULES IN RELATION TO VARIATIONS WORKS

FIG. 6-8 : VALIDITY OF VARIATION ORDERS – PRINCIPAL FACTORS DETERMINING © HSKS

LIMITATIONS TO VARIATIONS

LEGAL POSITION

EXERCISE OF POWER BY CONTRACT ADMINISTRATOR 1.

Power to vary work confined to genuine omissions

2.

If effect of omission is to give omitted work to 3rd Parties: Invalid Omission

CARDINAL CHANGES

SCOPE OF WORK 1.

2.

2.

TESTS

Power to vary confined to scope of works contemplated by parties at time of contracting.

1. Was it in the reasonable contemplation of the parties when contracting?

If effect of variation is to substantially change scope of work (‘Cardinal Change’): Invalid Variation

2. Although not included, can it be considered an indispensable part of the Contract?

DEFINITION 1.

NATURE

Changes which render the works substantially different from that contracted for by the parties

3. Functionally is it similar to the intended work or some other work required by the Contract?

EFFECTS 1. General Rule: Invalid 2. Contractor cannot be compelled to carry it out 3. If compelled, breach of contract 4. If Contractor carries out work, Contract rates not applicable

FORM

TYPES 1.

Physical work changes

1.

A Single change

2.

Financial Changes

2.

A large number of otherwise small permissible changes.

Constitutes a fundamental change in the scope of the Contract

FIG. 6-9 : LIMITATIONS TO VARIATIONS © HSKS

PAYMENT FOR VARIED WORK: GENERAL PRINCIPLES/METHODS

VARIED WORK OUTSIDE CONTRACT

VARIED WORK WITHIN CONTRACT

FORMULA VALID AND APPLICABLE

A ‘CARDINAL’ CARDINAL’ CHANGE i.e. FUNDAMENTALLY ALTERS CONTRACT

ABSENCE OF EXPRESS FORMULA IN CONTRACT

EXISTENCE OF EXPRESS FORMULA IN CONTRACT •

Mutually agree upon a formula/rate; or



Any contractual formula rendered invalid /inapplicable



Be paid a reasonable sum i.e. on a ‘quantum meruit’ basis, etc.



Whole works to be paid on ‘measure and value’ basis and on ‘altered’ or ‘adjusted’ rates

NOT A ‘CARDINAL’ CARDINAL’ CHANGE i.e. DOES NOT FUNDAMENTALLY ALTER CONTRACT •

Portion of works within scope of contract to be paid according to the contract formula (if applicable)



Remaining works falling outside scope of contract to be paid at a reasonable rate

FORMULA INVALID AND/OR INAPPLICABLE



Use the formula for valuation and payment



Mutually agree upon a formula/rate; or



No right of election



Be paid a reasonable sum i.e. on ‘quantum meruit’ basis, etc.

FIG. 6-10 : PAYMENT FOR VARIED WORK – GENERAL PRINCIPLES/METHODS © HSKS

COST OF DELAY AND DISRUPTION COST OF VARIED WORK e.g. •

Additions



Omissions

• Direct loss and/or expense • Extended Preliminaries

FINANCIAL EFFECTS

DELAY AND DISRUPTION TO CONTRACT •

Extension of time to Contract Period, etc.

TIME EFFECTS

PRINCIPAL CONTRACTUAL CONSEQUENCES OF VARIATION OF WORK UNDER CONTRACT

FIG. 6-11 : PRINCIPAL CONTRACTUAL CONSEQUENCES OF VARIATION OF WORK UNDER THE CONTRACT © HSKS

VALUATION OF VARIATIONS: COMMON COMPUTATIONAL METHODS

WHERE THERE ARE RATES/ PRICES IN THE CONTRACT

WHERE WORK CANNOT BE MEASURED



Use of B.Q. rates



Use of Daywork Rates in Contract



Use of Schedule of Unit Rates



On a cost-reimbursible basis



Use of Adjusted Contract Rates



Use of Contract Prices in: a) Contract Bills; or b) Summary of Prices; or c) Contract Sum Analysis

MISCELLANEOUS METHODS

WHERE NO RATES/ PRICES IN CONTRACT •

Use of ‘Fair Valuation’ principles



Use of ‘Quotation’ Method



Use of ‘Negotiated’/’Agreed’ Rates



Use of ‘Negotiated’/’Agreed’ Rates



Use of ‘Quotation’ Method



Payment on ‘quantum meruit’ basis or a reasonable sum



Payment of a reasonable sum

FIG. 6-12 : VALUATION OF VARIATIONS – COMMON COMPUTATIONAL METHODS © HSKS

START Establish if the conditions precedent have been satisfied

Has measurement stage been satisfactorily completed?

No

Yes Has the valuation stage been satisfactorily completed?

Prima facie, premature to prepare and issue certificate concerned

No

Yes Contract administrator to prepare certificate of variation of works

No

Is there a contract provision prescribing the same? Yes

A

Yes

Are its requirements clear and complete? No Have the requirements been agreed to by the parties?

No

Yes

B

C

D

FIG. 6-13: FLOWCHART ON THE GENERAL PROCEDURE FOR THE CERTIFICATION OF VALUATION (PART I) © HSKS

A

B

C

Have the requirements been complied with?

D

No

Yes Have the particulars been completely and properly filled in?

No

Yes Is the V.O./instruction attached?

No

Yes Are the measurement and valuation details endorsed?

No

Omissions/deficiencies may render certificate invalid

No

Contract administrator to address omissions /deficiencies forthwith

Yes Has the certificate been checked for sufficiency and accuracy? Yes No

Has it been signed by the authorized person? Yes

E

FIG. 6-14:

F

G

FLOWCHART ON THE GENERAL PROCEDURE FOR THE CERTIFICATION OF VALUATION (PART II) © HSKS

E

F

No

G

Has it been prepared within a reasonable/ prescribed period of completion of measurement and valuation? Yes Contract administrator to issue certificate to the contractor

Contractor to check and undertake necessary action

No

Is the certificate sufficient and accurate? Yes

No

Has it been signed by the authorized person? Yes

Prima facie, certificate is invalid

No

Does it comply with any prescribed requirements? Yes

H

I

J

FIG. 6-15: FLOWCHART ON THE GENERAL PROCEDURE FOR THE CERTIFICATION OF VALUATION (PART III) © HSKS

H

I

J

Does the contractor agree with the content?

Yes

Contractor to formally signify acceptance

No Does he notify the contract administrator officially of his dissent?

No

Yes Are the full particulars/details given?

No

Yes Contractor obliged to give notice within reasonable period only

No

Is there a period stipulated for the giving of the notice? Yes Has the contractor met the time requirements?

No

Contractor deemed to have accepted the measurement and valuation

Yes Contract administrator to review contractor’s notice and make decision

K

FIG. 6-16:

L

M

FLOWCHART ON THE GENERAL PROCEDURE FOR THE CERTIFICATION OF VALUATION (PART IV) © HSKS

M

L

K

Yes

Is the notice sufficient and accurate? No

No

Has the contractor been asked to furnish further details? Yes Has he complied with the request?

No

Yes Is the contractor’s stand reasonable?

Yes

No Is there any reason not to reject the contractor’s application?

Yes

Contract administrator to undertake necessary amendments/ revisions

No

N

Reject the contractor’s application/notice

N

Communicate decision to the contractor

Does the contractor wish to proceed with dispute resolution?

Yes

Contractor to give necessary notice. Contract administrator to use valuation set out in the interim period

No

STOP

FIG. 6-17: FLOWCHART ON THE GENERAL PROCEDURE FOR CERTIFICATION OF VALUATION (PART V) © HSKS

VARIATIONS: PRINCIPAL REQUIREMENTS FOR ‘PACKAGE DEAL’ TYPE OF CONTRACTS

EXPRESS STIPULATIONS

EMPLOYER’ EMPLOYER’S RIGHT TO VARY

CONTRACTOR’ CONTRACTOR’S RIGHT TO VARY

• In most Standard Forms



• Stipulate – Extent, Procedure, etc.



EXPRESS EXPRESS PROVISIONS PROVISIONS • Enshrined in all Standard Forms

NEED NEED FOR FOR CONSULTATION

CONTRACTOR’ CONTRACTOR’’S S RESPONSIBILITY

• Prior to ordering V.O. • Get Contractor’s view on effect of V.O. on programme

• Be pro-active



Most Standard Forms have express clauses Issued by E.R./ P.D.

Permitted expressly in most Standard Forms Due to: 1. Value engineering 2. Buidability 3. Safety 4. Legal/Physical impossibility

VARIATIONS IN WRITING

EFFECT OF PROCEDURE • Formal V.O. Instruction from E.R./P.D. condition precedent to recovery of payment

• Permissible if only expressly allowed by contract • Some Standard Forms do allow e.g. ICE, FIDIC, etc. • Others are silent e.g. JKR, etc.

• Failure of Contractor to observe procedure/ formalities – may compromise recovery

• Not to unreasonably withhold consent, etc.

NECESSITY NECESSITY FOR FOR ‘‘WRITTEN’ WRITTEN’’ INSTRUCTIONS INSTRUCTIONS

CONTRACT CONTRACT PROVISIONS PROVISIONS •

VARIATIONS IN DLP/DCP

• •

Requirement for ‘Writing’ Includes: 1. Letters 2. Minutes of Meetings 3. Drawings

RECOVERY RECOVERY WITHOUT WITHOUT INSTRUCTIONS INSTRUCTIONS

ORAL INSTRUCTIONS • • •

Only if contract expressly allows Need for written confirmation Duty of confirmation either on: 1. Contractor or 2. Employer

• •

Generally no Situations where permitted: 1. If contract expressly allows 2. Under Waiver/Estoppel 3. Under concept of ‘Constructive Change’

FIG. 6-18: VARIATIONS – PRINCIPAL REQUIREMENTS FOR ‘PACKAGE DEAL’ TYPE OF CONTRACT © HSKS

DELAY AND EXTENSION OF TIME

© HSKS

7.0

DELAY AND EXTENSION OF TIME



OPTIONS AVAILABLE TO EMPLOYER



EXTENSION OF TIME ISSUES



ACCELERATION OF WORKS



DRAFTING OF DELAY AND DISRUPTION CLAIMS



MISCELLANEOUS ISSUES



RELEVANT CASES *

PEAK CONSTRUCTION (LIVERPOOL) LTD. V MCKINNEY FOUNDATION LTD. [1970] 1 BLR 114

*

MILLER V L.C.C. [1934] 50 T.L.R. 479, 482

*

MERTON LONDON BOROUGH V STANLEY HUGH LEACH [1985] 32 BLR 55

*

WESTMINSTER CITY COUNCIL V JARVIS & SONS LTD. [1970] 7 BLR 64



SYARIKAT TAN KIM BENG DAN RAKAN-RAKAN V PULAI JAYA SDN. BHD. [1992] 1 MLJ 42

© HSKS

CONSEQUENCES OF DELAY: AN OVERVIEW

BY EMPLOYER (ACTS OF PREVENTION)

BY CONTRACTOR

INSTRUCT CONTRACTOR TO ACCELERATE WORKS

GRANT OF EXTENSION OF TIME • Only if contract expressly permits



Only if contract expressly permits

• Contractor may be entitled to:



To meet original contract deadline



Contractor to be compensated for reasonable expenses incurred

1.

Extended Preliminaries

2.

Direct Loss and/or Expense

DUE TO NEUTRAL EVENTS





Contractor entitled to E.O.T. but not to extended preliminaries or other claims If asked to accelerate works, entitled to reasonable expenses incurred therefrom

DUE TO CONTRACTOR’ CONTRACTOR’S OWN ACTS AND/OR OR OMISSIONS • Contractor culpable

DUE TO CONTRACTOR’ CONTRACTOR’S SUBSUB-CONTRACTORS/ SUPPLIERS •

Contractor vicariously liable to Employer



May seek indemnity from the culpable party e.g. Subcontractor, Supplier, etc.

• May be liable for: 1. Liquidated Damages, or 2. Unliquidated Damages caused to Employer

FIG. 7-1 : CONSEQUENCES OF DELAY – AN OVERVIEW © HSKS

‘FORCE MAJEURE’ EXCEPTIONALLY INCLEMENT WEATHER CIVIL COMMOTION, STRIKES, LOCK-OUT, ETC. LOSS OR DAMAGE TO THE WORKS OCCASIONED BY SPECIFIED PERILS CONTRACTOR’S INABILITY TO SECURE LABOUR, GOODS, MATERIALS, ETC. CARRYING OUT OF WORK BY STATUTORY UNDERTAKERS EXERCISE BY GOVERNMENT OF ANY POWER WHICH DIRECTLY AFFECTS THE WORKS

EXTENSION OF TIME: COMMON ‘RELEVANT EVENTS’ FAILURE OF EMPLOYER TO GIVE POSSESSION/ACCESS IN TIME DELAY IN THE SUPPLY OF INFORMATION/INSTRUCTIONS VARIATIONS AND EXTRA WORKS COMPLIANCE WITH CONTRACT ADMINISTRATOR’S INSTRUCTIONS DELAY ON PART OF NOMINATED SUB-CONTRACTORS/SUPPLIERS EXECUTION OF WORK NOT FORMING PART OF THE CONTRACT LATE SUPPLY OF MATERIALS BY THE EMPLOYER OTHER SPECIAL CIRCUMSTANCES

FIG. 7-2 : EXTENSION OF TIME – COMMON ‘RELEVANT EVENTS’ © HSKS

DEFERMENT/POSTPONEMENT IN GIVING SITE POSSESSION OTHER ACTS OF PREVENTION EXPRESSLY PERMITTED BY THE CONDITIONS OF CONTRACT

LATE SUPPLY OF INFORMATION, DRAWINGS, INSTRUCTIONS, ETC.

‘ACTS OF PREVENTION’: TYPICAL EXAMPLES

LATE SUPPLY OF MATERIALS BY THE EMPLOYER

EXECUTION OF WORK NOT FORMING PART OF THE CONTRACT

COMPLIANCE WITH CONTRACT ADMINISTRATOR’S INSTRUCTIONS, DIRECTIONS, ETC.

FIG. 7-3 : ‘ACTS OF PREVENTION’ – TYPICAL EXAMPLES © HSKS

‘FORCE MAJEURE’ DELAYS BY NOMINATED SUBCONTRACTORS/SUPPLIERS FOR THE SAID ‘NEUTRAL EVENTS’

EXCEPTIONALLY INCLEMENT/ ADVERSE WEATHER

‘NEUTRAL EVENTS’: TYPICAL EXAMPLES

CIVIL COMMOTION, STRIKES, LOCK OUTS INDUSTRIAL ACTION, EMBARGOES, ETC.

CONTRACTOR’S IN ABILITY TO SECURE LABOUR, GOOD, MATERIALS AND/OR OTHER RESOURCES LOSS/DAMAGE TO THE WORKS OCCASIONED BY SPECIFIED PERILS OR CONTINGENCIES

FIG. 7-4 : ‘NEUTRAL EVENTS’ – TYPICAL EXAMPLES © HSKS

CAUSE OF THE DELAY

ALL OTHER SUPPORTING RECORDS, DETAILS, ETC.

APPROPRIATE CONTRACT REFERENCES TO SUCH EVENT OF DELAY

SCHEDULING DOCUMENTATION

DETAILS OF EFFECT OF DELAY ON WORK PROGRAMME

APPLICATION FOR EXTENSION OF TIME: TYPICAL CONTENTS

ESTIMATE OF THE EXTENSION OF TIME REQUIRED

ESTIMATED LENGTH OF THE DELAY STEPS TAKEN/PROPOSED TO MINIMIZE/AVOID DELAY

FIG. 7-5 : APPLICATION FOR EXTENSION OF TIME – TYPICAL CONTENTS © HSKS

OFFICIAL WORK RECORDS OFFICIAL PROGRESS REPORTS SITE DIARIES LETTERS, INSTRUCTIONS, ETC. MEMORANDA FACSIMILE TRANSMISSIONS, ETC. DRAWINGS, ETC.

EXTENSION OF TIME APPLICATION: TYPICAL SOURCES OF INFORMATION

OFFICIAL MINUTES OF MEETING WORK PROGRAMMES, ETC. RECORDS/REPORTS FROM AUTHORITIES/INDEPENDENT BODIES, ETC. SHIPPING/AIRFREIGHT RECORDS, ETC. PROCUREMENT RECORDS, INVOICES, ETC. DELIVERY ORDERS OTHER MISCELLANEOUS RECORDS, DOCUMENTS, ETC.

FIG. 7-6 : EXTENSION OF TIME APPLICATION – TYPICAL SOURCES OF INFORMATION © HSKS

START

Is progress delayed or is likely to be delayed?

No

Yes Does the delaying event constitute one of the ‘relevant events’ /grounds under the provisions of the contract?

No

Yes Initiate notification of the delay procedure

Is the notice given in writing?

No

Yes Is the notice given within the period expressly stipulated?

No

A

Yes

No

Yes Proceed with the application of the extension of time process

Is the notice a condition precedent?

Yes

Has an extension been granted by the contract administrator?

No

B

FIG. 7-7: FLOWCHART ON THE GENERAL PROCEDURE FOR CLAIMING EXTENSION OF TIME (PART I) © HSKS

B

A

Is the application given in writing?

No

Yes Is the application made within the period expressly stipulated?

No

Yes Contract Administrator to check application made

Is the application complete/sufficient and accurate?

Is the application a condition precedent?

Yes

No Yes

No

Yes

Has an extension been granted by the contract administrator?

No

Is the requirement as to sufficiency, etc. a condition precedent?

Yes

No

Establish whether contractor has done all that is reasonably required of him

No

Has the contractor used his ‘best endeavours’ to minimize the delay?

No

Has the contract administrator requested for information, details, etc.?

Yes

Prima facie no extension of time can be granted

Yes Contract Administrator to proceed with further assessment for the possible grant of extension of time

Return to contractor for resubmission or reject application as appropriate

STOP

FIG. 7-8: FLOWCHART ON THE GENERAL PROCEDURE FOR CLAIMING EXTENSION OF TIME (PART II) © HSKS

PROCEDURES FOR CLAIMING EXTENSION OF TIME: AN OVERVIEW (PART I)

NATURE OF APPLICATION

EXPRESS CONTRACT PROVISIONS •

Included in most standard forms of contract

REQUIREMENT REQUIREMENT •



TIMING OF NOTIFICATION

Expressly stipulated in conditions of contract of contract; or



Implied by law

Various formulae used e.g.:

2 broad steps:

VARIATIONS VARIATIONS •



Usually stipulated in the conditions of contract.

2. Stipulation of express time periods



Important to comply with the express requirements

Legal effect of provisions on time:



As a minimum must inform the contract administrator of the occurrence of the delay which is likely to affect the progress or has delayed progress



Otherwise must include:

1. Whether notification/application is a condition precedent to entitlement

Either a:

1. Notification of the delay; and

1. Single exercise, or

2. Making the application

2. Two separate processes •

Depends upon express/ implied requirements

CONTENTS OF THE NOTICE •

1. Use of specific phrases

CATEGORIZATION CATEGORIZATION •

FORM OF THE NOTICE

2. If affirmative, the effect of the breach of the condition precedent

1. Occurrence of the delay

3. Application to acts of prevention/neutral events •

2. Cause of the delay

Review of applicable case-law

3. Relevant events causing the delay; and 4. Contractor’s intention to make a claim

EXPRESS EXPRESS REQUIREMENTS REQUIREMENTS

TYPES TYPES OF OF WRITTEN WRITTEN NOTICES NOTICES /NOTICES /NOTICES IN IN WRITING WRITING

• Included in most standard forms



Correspondence

• Usually stipulated as:



Facsimile transmissions



Entries in official records

1. ‘Written notice’ or 2. ‘Notice in writing’



Entries in site diaries



Official Progress reports

EVIDENTIAL VALUE EVIDENTIAL

GENERAL RULE •

Where the form is expressly stipulated, it must be complied with



A written notice/notice in writing is of immense evidential value



Where not expressly stipulated, may be implied



Therefore, even if not expressly required, must try to give written notice

FIG. 7-9 : PROCEDURES FOR CLAIMING EXTENSION OF TIME – AN OVERVIEW (PART I) © HSKS

PROCEDURES FOR CLAIMING EXTENSION OF TIME: AN OVERVIEW (PART II)

FORM OF THE APPLICATION

TIMING OF THE APPLICATION

EXPRESS REQUIREMENT •

Included in most standard forms

• Formulae include: 1. Specific time periods 2. Within a reasonable period



Similar to ‘Form of the Notice’



Preferably to be in writing



Compliance to any express requirements

GENERAL RULE

• Where specific time periods have been specified these should be adhered to • If not practicable, requirement for express consent for deferment • Otherwise within a reasonable period of notification/delay

CONTENTS OF THE APPLICATION • Dictated by express stipulations in contract • Otherwise by necessary implication. • Typical list includes: 1.

Cause of delay

2.

Appropriate contract reference

3.

Details of effect of delay on programme/progress

4.

Estimated length of delay

5.

Steps taken to mitigate/prevent delay

6.

Scheduling documentation

7.

Miscellaneous details, records, documents, etc.

FIG. 7-10 : PROCEDURES FOR CLAIMING EXTENSION OF TIME – AN OVERVIEW (PART II) © HSKS

PROCEDURES FOR CLAIMING EXTENSION OF TIME: AN OVERVIEW (PART III)

NATURE OF INFORMATION REQUIRED

ADEQUACY OF INFORMATION SUPPLIED

DETERMINING DETERMINING FACTORS FACTORS





Contractor must furnish enough information to enable contract administrator to undertake assessment satisfactorily Information to be: 1. Sufficient/ complete 2. Accurate 3. Relevant



Breach of condition may be fatal to claim depending on its nature and seriousness

Type of relevant event Nature of relevant event



Particular requirements of applicable express provisions



Evidential value of information

CONSEQUENCES CONSEQUENCES WHERE WHERE PROVISION PROVISION IS IS NOT NOT A A CONDITION CONDITION PRECEDENT PRECEDENT

CONSEQUENCES CONSEQUENCES WHERE WHERE PROVISION IS IS A A CONDITION CONDITION PRECEDENT PRECEDENT

BASIS BASIS OF OF REQUIREMENT REQUIREMENT

• •



Contract administrator can: 1. Request for further information 2. Set a new deadline for contractor to respond

FAILURE FAILURE TO TO RESPOND RESPOND AFTER AFTER EXTENSION EXTENSION •

Should contractor fail to respond by: 1. Deadline set, or 2. Within reasonable period of request

PRINCIPAL PRINCIPAL SOURCES SOURCES • • • • • • • • • • • • •

Official work records Official progress reports Site diaries Correspondence Instructions Drawings, etc. Official minutes of meetings, discussions, etc. Work programmes 3rd party reports/records Procurement records, etc. Delivery orders Shipping/airfreight records Miscellaneous records/documents

Contract administrator may not proceed further with assessment

FIG. 7-11 : PROCEDURES FOR CLAIMING EXTENSION OF TIME – AN OVERVIEW (PART III) © HSKS

ASSESSMENT OF THE APPLICATION: AN OVERVIEW (PART I)

EXPRESS CONTRACT PROVISIONS

GENERAL •

Included in most standard forms of conditions of contract

TO WHOM OWED • • •

THE CONTRACT ADMINISTRATOR’S DUTY ADMINISTRATOR’ OF CARE •

DERELICTION DERELICTION OF OF DUTY: DUTY: CONSEQUENCES CONSEQUENCES

DUTY DUTY TO TO EMPLOYER

To Employer To Contractor To Nominated Subcontractors/Suppliers

• •



PRELIMINARY PROCEDURES

Positive duty vis-à-vis ‘acts of prevention’ Satisfaction of: 1. ‘Reasonableness’ Test and 2. ‘Fairness’ Test Help employer: 1. Preserve right to LAD 2. Stave off claims from contractor



May compromise employer’s position



Contract administrator liable to actions in:

• • •

Upon occurrence of delaying event, independently undertake own assessment especially for acts of prevention Must take an active role Issue an interim extension to contractor if one due on facts Contractor can later apply for reassessment based on additional information

1. Breach of contract 2. Tort of negligence

PRELIMINARY PRELIMINARY CHECKS CHECKS TO ESTABLISH MATTERS SUCH MATTERS SUCH AS AS • •

WHO UNDERTAKES WHO • •

Delegated by the employer to authorized person Usually it is the contract administrator

ADDITIONAL ADDITIONAL DUTY DUTY

NATURE NATURE OF OF ROLE ROLE • • •

As an independent adjudicator Decision making function Must act fairly, reasonably and impartially

• •

Per John Baker Construction v London Protman Hotel Ltd. Must adhere to governing express contractual procedures in addition

POST APPLICATION PROCEDURES

• • •

Verification of occurrence of delay Sufficiency, accuracy, relevancy, etc. Compliance with preconditions, procedural requirements, etc. Assessment of evidential value Assessment whether delay in principle entitles contractor to extension

INSUFFICIENT INSUFFICIENT INFORMATION: OPTIONS AVAILABLE AVAILABLE TO TO CONTRACT CONTRACT ADMINISTRATOR ADMINISTRATOR • •

Request contractor to submit more details, etc. or If delaying event of a continuing nature: 1. Proceed with interim assessment 2. Grant an interim extension

FIG. 7-12: ASSESSMENT OF THE APPLICATION – AN OVERVIEW (PART I) © HSKS

ASSESSMENT OF THE APPLICATION: AN OVERVIEW (PART II)

THE ASSESSMENT PROCESS

BASIS OF ASSESSMENT •

Basic principles



Overriding requirements: Satisfaction of: 1. ‘Reasonableness’ Test 2. ‘Fairness’ Test 3. Procedural requirements



MISCELLANEOUS ISSUES

Factors to be taken into consideration:



Multiple extensions



Review of prior decisions/ certificates

1. Previous extensions granted 2. Effect of omissions 3. Effect of concurrent delays



Concurrent delay: effects



Extensions during culpable delay



Extension of time and omissions



Acceleration in lieu of extension



Extension of time and claims



Sources and types of information used



Concluding decision:

Important exceptions 1. Contractor not to be culpable 2. Contractor to mitigate/prevent delay





TIMING FOR GRANTING EXTENSION

1. Rejection of claim; or 2. Grant of extension of time

Definition of ‘best endeavours’

PRINCIPAL ISSUES PRINCIPAL



Factors dictating the timing of the grant



Express stipulations as to time period for granting



Prospective/Retrospective granting of extension

TIME TIME PERIOD PERIOD

FACTORS FACTORS DICTATING DICTATING





The need to preserve the LAD provisions for the benefit of the employer To allow contractor opportunity to reprogramme his works



PROSPECTIVE/ PROSPECTIVE/ RETROSPECTIVE GRANTING GRANTING OF OF EXTENSION EXTENSION

Various formulae:



Where expressly permitted

1. Use of specific time period stipulations



Where implied



Courts approach:

2. Within reasonable time •

Effect of failure to comply



Situation of continuing delay

1. Previous strict interpretation 2. Current liberal approach •

Circumstances where retrospective granting permitted

FIG. 7-13: ASSESSMENT OF THE APPLICATION – AN OVERVIEW (PART II) © HSKS

CERTIFICATE NOT GIVEN ON TIME

OTHER MATERIAL BREACHES

CERTIFICATE NOT IN CORRECT FORM

CONTRACTUAL PROCEDURES NOT FOLLOWED

CERTIFICATE GIVEN BY UNAUTHORIZED PERSON

CHALLENGING CERTIFICATE OF EXTENSION OF TIME: COMMON GROUNDS

CERTIFICATE NOT GIVEN FAIRLY

NO NAMED CERTIFIER

DECISIONS IMPROPERLY DELEGATED

FIG. 7-14: CHALLENGING CERTIFICATE OF EXTENSION OF TIME – COMMON GROUNDS (PER EGGLESTON) © HSKS

DELAY AND EXTENSION OF TIME FOR NOMINATED SUB-CONTRACTORS: AN OVERVIEW

EXPRESS CONTRACTUAL PROVISIONS

GENERAL REQUIREMENTS •

The principles and general requirements similar to that of Main Contract



Principal difference only in some procedural requirements



Applicable only to:



1. Nominated Sub-Contractors and 2. Nominated Suppliers •

Does not encompass:



1. Domestic Sub-Contractors and 2. Domestic Suppliers

PAM PAM 1998 1998 SUB SUB---CONTRACT CONTRACT FORM FORM

JKR 203N FORM JKR (REV. 10/83) •

Clause 26: Delay and Extension of Time

(a): Notice of delay (b): Extension of time (c): Dispute on failure of S.O. to grant extension of time



Clause 8.0: Extension of Time

8.1:Notifying of events causing delay 8.2:Relevant events causing delay for which extension of time may be given 8.3:A Fair and Reasonable extension of time

GENERAL PROCEDURAL REQUIREMENTS

GENERAL CONTRACTUAL POSITION Extension of time under contract can only be validly granted if:

Main steps involved are: 1. Occurrence of delaying event

1. Delaying event is one of the ‘relevant events’/grounds under the conditions of sub-contract

2. Notification of the delay

2. The express formalities or procedures are strictly complied with

4. Contractor forwards application to contract administrator

3. Review by the contractor

5. Contract administrator assesses application

The general contractual position similar to Main Contract

PUTRAJAYA PUTRAJAYA CONDITIONS OF OF NOMINATED SUB-NOMINATED SUBCONTRACT CONTRACT

IEM.CES.1/90 FORM IEM.CES.1/90 •



Clause 26: Delay and Extension of Time



Clause 24: Delay and Extension of Time

6. Contract administrator communicates decision to contractor 7. Contractor informs subcontractor 8. Receipt and acknowledgement •

The rules in the preparation and issuance of the certificate of extension of time similar to that of Main Contract

(a): Notice of delays (b): Extension of time (c): Dispute on failure of Engineer to grant extension of time

8.4:Failure of architect to give written consent for extension of time

FIG. 7-15: DELAY AND EXTENSION OF TIME FOR NOMINATED SUB-CONTRACTORS – AN OVERVIEW © HSKS

NON-COMPLETION AND DAMAGES

© HSKS

8.0

NON COMPLETION AND DAMAGES



COMMON LAW POSITION



CONTRACTUAL FORMULAE



RIGHTS TO IMPOSE



CHALLENGES



MALAYSIAN POSITION



RELEVANT CASES *

DUNLOP PNEUMATIC TYRE CO. LTD. V NEW GARAGE & MOTOR COMPANY LTD. [1915] AC 79

*

TEMLOC LTD. V ERRIL PROPERTIES LTD.

*

GILBERT-ASH (NORTHERN) LTD. V MODERN ENGINEERING (BRISTOL) LTD. [1974] AC 689

*

SIM CHIO HUAT V WENG TED FUI [1983] 1 MLJ 151

*

LION ENGINEERING SDN. BHD. V PAUCHUAN DEVELOPMENT SDN. BHD. [1997] 4 AMR 3315

© HSKS

*

MANIAM V STATE OF PERAK [1957] MLJ 75

*

WEARNE BROTHERS (M) LTD. V JACKSON [1966] 2 MLJ 155

*

SELVA KUMAR A/L MURUGIAH V THIAGARAJAH A/L RETNASAMY [1995] 1 MLJ 817

*

REALVEST PROPERTIES SDN. BHD. V THE COOPERATIVE CENTRAL BANK LTD. (Under Receivership) [1996] 2 AMR 2292, FC.

*

SAKINAS SDN. BHD. V SIEW YIK HAU & ANOR [2002] 5 MLJ 497, HC.

*

ARAB MALAYSIAN CORP. BUILDERS SDN. BHD. & ANOR V ASM DEVELOPMENT SDN. BHD. [1998] 6 MLJ 136, HC.

© HSKS

RECOVERY/PAYMENT TRIGGERED BY OCCURRENCE OF SPECIFIED DEFAULT/BREACH

SUM OF MONEY AGRRED BY THE PARTIES

LIQUIDATED DAMAGES: PRINCIPAL CHARACTERISTICS

SUM STIPULATED IN THE CONTRACT

GENUINE PRE-ESTIMATE OF THE LOSS

FIG. 8-1 : LIQUIDATED DAMAGES – PRINCIPAL CHARACTERISTICS © HSKS

LIQUIDATED DAMAGES: AN OVERVIEW

BASIC CHARACTERISTICS

DEFINITION



Prof. Vincent PowellSmith’s definition



Per Eggleston



Per Robinson and Lavers



1.

2.

3. 4.

GENERAL



Common view



Common view

Sum of money agreed/fixed in advance by parties



Reiteration in Philips Hong Kong Ltd. v AG of Hong Kong.



Disadvantages to:

Sum is a genuine pre-estimate of likely loss







Distinct difference





Position in Malaysia post Selvakumar v Thiagarajah

1. Employer 2. Contractor

Advantages to:

3. Sub-contractor

1. Employer 2. Contractor

Sum is stipulated in the contract

3. Sub-contractor

Recovery of sum is triggered by contractor’s breach e.g. non-completion

DISTINGUISHING BETWEEN THE TWO TERMS

PENALTY: DEFINITION

Use of terms interchangeably



DISADVANTAGES

ADVANTAGES

Four basic characteristics:

LIQUIDATED DAMAGES AND PENALTIES DISTINGUISHED

Per Prof. Vincent PowellSmith Per Lord Dunedin in Dunlop Pneumatic Tyre Co. Ltd. v New Garage & Motor Co. Ltd.



Mere labeling is inclusive



Depends on construction afforded to term by the courts



EXAMPLES OF PENALTY CLAUSES •

Elicited from the relevant case-law

Lord Dunedin’s proposed tests.

LEGAL EFFECTS OF PENALTIES •

Penalty: Invalid and unenforceable



Legal effect per Watts, Watts & Co. Ltd. v Mitsui & Co. Ltd.



See Keating’s view

FIG. 8-2 : LIQUIDATED DAMAGES – AN OVERVIEW © HSKS

INCLUSION OF EXPRESS PROVISION IN CONTRACT PERMITTING DEDUCTION OF THE LIQUIDATED DAMAGES EMPLOYER HAS NOT WAIVED HIS RIGHT TO DEDUCT LIQUIDATED DAMAGES

THE EXPRESS LIQUIDATED DAMAGES CLAUSE IS VALID AND ENFORCEABLE

IMPOSITION OF LIQUIDATED DAMAGES: TYPICAL PRE-CONDITIONS

SPECIFIED CONTRACTUAL PROCEDURES HAVE BEEN STRICTLY COMPLIED WITH

DETAILS ON LIQUIDATED DAMAGES CLEARLY AND PROPERLY FILLED IN DEFINITE DATE FIXED CONTRACTUALLY FROM WHICH DAMAGES CAN RUN

FIG. 8-3 : IMPOSITION OF LIQUIDATED DAMAGES – TYPICAL PRE-CONDITIONS © HSKS

CONTRACTOR SHALL FAIL TO COMPLETE ON TIME

MISCELLANEOUS PRE-CONDITIONS

THE CONTRACT ADMINISTRATOR SHALL DETERMINE AND ISSUE ANY EXTENSIONS OF TIME DUE TO CONTRACT

DEDUCTION OF LIQUIDATED DAMAGES: COMMON CONDITIONS PRECEDENTS USED

THE EMPLOYER SHALL GIVE WRITTEN NOTICE TO THE CONTRACTOR OF HIS INTENTION TO DEDUCT LAD

FIG. 8-4 :

THE CONTRACT ADMINISTRATOR SHALL ISSUE A CERTIFICATE OF NON-COMPLETION

THE CONTRACT ADMINISTRATOR SHALL CERTIFY THAT NO FURTHER EXTENSIONS OF TIME ARE DUE TO CONTRACTOR

DEDUCTION OF LIQUIDATED DAMAGES – COMMON CONDITIONS PRECEDENTS USED © HSKS

PROCEDURAL REQUIREMENTS FOR RECOVERY OF LIQUIDATED DAMAGES: AN OVERVIEW

GENERAL RULE FOR IMPOSITION OF LIQUIDATED DAMAGES

DEFINITION •

Recovery of LAD must be in accordance with the contract



Procedural requirements/conditions precedent must be strictly followed



Effect of the application of the ‘contra proferantum’ rule



Need to satisfy general rule



Six principal pre-conditions:

GENERAL PROCEDURE

1. Existence of express contractual provision on LAD 2. LAD Clause must be valid 3. LAD details must be clearly filled in 4. Contractual provisions must be strictly complied with 5. Definite date from which LAD can run 6. Non-waiver by employer of his rights to the LAD

BASIC STEPS



Five basic steps



See Figures 6-11 to 6-13 on the flowcharts

FIG. 8-5 :



Triggering event: failure of contractor to complete on time



Crucial to enforceability of provision and recovery of LAD

DETERMINE IF RELEVANT CERTIFICATES/ NOTICES HAVE BEEN ISSUED

DETERMINE IF EMPLOYER HAS WAIVED HIS RIGHTS TO LAD

ESTABLISH EXISTENCE AND VALIDITY OF LAD CLAUSE

ESTABLISH DEFAULT OF CONTRACTOR



2 forms of waiver: 1. Express 2. Implied



Was there consideration in return?

• •

Certificate of NonCompletion (CNC) Notice of Intention to deduct LAD

EMPLOYER RECOVERS THE LIQUIDATED DAMAGES •

Conditions precedent



Decision as to recovery



Timing

POST LAD DEDUCTION PROCEDURES



Effect of further E.O.T.



See Fig. 6-14 & 615 for flowchart

PROCEDURAL REQUIREMENTS FOR RECOVERY OF LIQUIDATED DAMAGES – AN OVERVIEW © HSKS

NON-COMPLETION AND DAMAGES IN NOMINATED SUB-CONTRACTS: AN OVERVIEW

EXPRESS CONTRACTUAL PROVISIONS

GENERAL POSITION

NSC’S LIABILITY FOR DAMAGES



Legal principles similar to Main Contractor



Clause 7.0: PAM ‘98 Sub-Contract Form



Liability for 2 types of damages:



Clause 27: JKR 203N (Rev. 10/83)

1. 2.



Clause 27: IEM.CES 1/90 Form



Clause 25: ‘Putrajaya’ Conditions of Nominated Sub-Contract

Liquidated damages, or Unliquidated/general damages

EFFECT OF NSC’S DEFAULT •

Effect of default in completing works in time: breach of contract



Consequences of the said breach - Employer entitled to damages i.e., either: 1. 2.

LAD as stipulated in the subcontract, or General damages enforceable through arbitration/court action

DAMAGES FOR BREACH OF CONTRACT •



EXPRESS CONTRACTUAL FORMULA

Governing Provision: S 74 Contracts Act 1950 (Rev. 1974) ‘Compensation for loss or damage caused by breach of contract’



Called the ‘Financial Contractual Remedy’



Usually an LAD clause

Three main heads of damage per Eggleston:



Express stipulations as to: 1. 2. 3. 4.

1. Main Contractor’s liability to pay LAD to employer of NSC’s default 2. Main Contractor’s own loss consequent to NSC’s default



Rate Scope of coverage Maximum limit Pre-conditions, etc.

Issues pertaining to the ‘stepping down’ of the Main Contractor’s LAD clauses

GENERAL OBSERVATIONS •

Necessity for parties to agree upon and arrive at a genuine preestimate



Need to clearly stipulate conditions precedent to recovery

.



Prudent to cap maximum limit



If LAD clause ‘stepped down’ into sub-contract, sub-contractor bound irrespective of value of the sub-contract

3. Third party claims due to NSC’s default

FIG. 8-6: NON-COMPLETION AND DAMAGES IN NOMINATED SUB-CONTRACTS – AN OVERVIEW © HSKS

CONTRACTUAL PROVISION IS A PENALTY CLAUSE CONTRACTUAL PROVISION IS UNCERTAIN/INCONSISTENT NO CONTRACTUAL PROVISION TO EXTEND TIME FOR ACT OF PROVISION IN QUESTION NO DATE STIPULATED FOR THE COMMENCEMENT OF THE CONTRACT CONTRACT IS AT LARGE CONDITIONS PRECEDENT NOT OBSERVED

LIQUIDATED DAMAGES: TYPICAL GROUNDS FOR CHALLENGING

EMPLOYER HAS WAIVED LIQUIDATED DAMAGES CERTIFICATES OF EXTENSION OF TIME AND/OR PRACTICAL COMPLETION NOT VALID EXTENSIONS OF TIME GRANTED INSUFFICIENT PRACTICAL COMPLETION ACHIEVED EARLIER THAN CERTIFIED MISCELLANEOUS CHALLENGES/DEFENCES

FIG. 8-7: LIQUIDATED DAMAGES – TYPICAL GROUNDS FOR CHALLENGING © HSKS

LAD: MALAYSIAN LEGAL POSITION – AN OVERVIEW

EFFECT OF S75 CONTRACTS ACT 1950 (REV. 1974) 1. No difference between penalty and liquidated damages clauses. 2. All liquidated damages clauses to be treated as penalty clauses under English law.

EFFECT OF SELVAKUMAR V THIAGARAJAH [1995]

CIRCUMVENTING SELVAKUMAR V THIAGARAJAH

1. Employer cannot recover simpliciter sum fixed in contract, whether as a penalty or liquidated damages. 2. Must prove actual damages/reasonable compensation per Hadley v Baxendale. 3. Figure stipulated in Contract is the ceiling amount recoverable.

UNDER DOCTRINE OF FREEDOM TO CONTRACT 1. Parties of equal bargaining strength. 2. Free to agree on any terms between themselves. 3. Philips HK Ltd. v AG of Hong Kong.

MUTUAL AGREEMENT

CLAUSE 22.2: PAM CONTRACT 2006

1. By parties on circumventing decision in Selvakumar v Thiagarajah.

1. Contractor confirms that by entering into the Contract

2. Can draft appropriate clause

2. He agrees to pay such sums 3. Which become due 4. Without Employer having to prove his actual loss/damage

FIG. 8-8 : LAD – MALAYSIAN LEGAL POSITION – AN OVERVIEW © HSKS

START

Is the contractor liable to pay LAD?

No

Yes Have all the conditions precedents been fulfilled?

No

Prima facie, employer cannot recover liquidated damages (LAD)

Yes Employer can proceed to recover simpliciter the sum fixed in the contract as LAD

Does the contractor challenge the employer’s deduction of the LAD?

No

Yes Is there an express clause circumventing rule in Selvakumar Thiagarajah?

Yes

Prima facie, employer can deduct the stipulated LAD amount

No Matter to be resolved through arbitration/litigation

A

B

FIG. 8-9: FLOWCHART ON THE RECOVERY OF LIQUIDATED DAMAGES - THE MALAYSIAN POSITION POST SELVAKUMAR V THIAGARAJAH (PART I) © HSKS

A

B

Employer must prove the actual damages or reasonable compensation per rule in Hadley v Baxendale / S74 Contracts Act

Is employer able to prove damages as required?

No

Employer may not be able to recover any damages at all

Yes

Are the damages more than the sum stipulated in the contract as LAD?

Yes

Prima facie, employer can deduct the stipulated LAD amount

No

Employer can recover only his actual damages or reasonable compensation as decided by the arbitral forum or the court

STOP

FIG. 8-10: FLOWCHART ON THE RECOVERY OF LIQUIDATED DAMAGES - THE MALAYSIAN POSITION POST SELVAKUMAR V THIAGARAJAH (PART II) © HSKS

COMPLETION AND HANDING-OVER

© HSKS

9.0

COMPLETION AND HANDING-OVER



PROBLEMS WITH DEFINITIONS AND TERMINOLOGY



CONDITIONS PRECEDENT



NONNON-ISSUE BY CONTRACT ADMINISTRATOR



CHALLENGES TO CPC



PROBLEMS ARISING FROM CPC ISSUES



SECTIONAL COMPLETION, PARTIAL POSSESSION AND CONDITIONAL CPC



RELEVANT CASES

*

WESTMINSTER CITY COUNCIL V JARVIS & SONS LTD. [1970] 7 BLR 64

*

H.W. NEVILL (SUNBLEST) LTD. V WILLIAM PRESS & SONS LTD. [1981] 20 BLR 78

*

P & M KAYE LTD. V HOSIER DICKINSON LTD. [1972] 1 WLR 64

*

EMSON EASTERN (IN RECEIVERSHIP) V EME DEVELOPMENTS LTD. [1991] 55 BLR 114

*

BRUNO ZORNOW (BUILDERS LTD.) V BEECHCROFT DEVELOPMENTS LTD. [1990] 51 BLR 16

© HSKS

CONTRACT ADMINISTRATOR HAS DISCRETION TO ISSUE C.P.C. WHERE MINOR WORKS ARE LEFT TO BE DONE ON A ‘DE MINIMIS’ BASIS

C.P.C. CAN BE ISSUED NOTWITHSTANDING PRESENCE OF LATENT DEFECTS

GUIDELINES TO DETERMINE PRACTICAL COMPLETION PER KEATING

PRACTICAL COMPLETION MEANS COMPLETION OF ALL WORK THAT HAS TO BE DONE

C.P.C. CANNOT BE ISSUED IF THERE ARE PRESENT PATENT DEFECTS

FIG. 9-1 : GUIDELINES TO DETERMINE PRACTICAL COMPLETION PER KEATING © HSKS

FUNCTIONAL TEST

MISCELLANEOUS TESTS

COMPLETENESS TEST

ESTABLISHING PRACTICAL COMPLETION: PRINICPAL TESTS

AUTHORITIES TEST

SAFETY TEST

INCONVENIENCE TEST

FIG. 9-2 : ESTABLISHING PRACTICAL COMPLETION – PRINICPAL TESTS © HSKS

MARKS END OF CONSTRUCTION PERIOD CONTRACTOR’S RIGHT TO POSSESSION OF SITE CEASES CONTRACTOR’S LIABILITY FOR CARE, SECURITY, ETC., ENDS CERTIFICATION OF INTERIM PAYMENT ENDS EMPLOYER TO RELEASE ONE MOIETY OF RETENTION SUM DEFECT LIABILITY PERIOD COMMENCES

ISSUE OF THE CERTIFICATE OF PRACTICAL COMPLETION: PRINCIPAL EFFECTS FREE SERVICE AND MAINTENANCE PERIOD STARTS TRIGGERS COMMENCEMENT OF PERIOD OF FINAL MEASUREMENT AND VALUATION OF THE WORKS CONTRACTOR’S LIABILITY TO INSURE WORKS ENDS CONTRACTOR’S LIABILITY FOR FURTHER LAD ENDS CONTRACT ADMINISTRATOR’S POWER TO ORDER VARIATIONS CEASES ENDS RESTRICTION ON OPENING OF ARBITRATION

FIG. 9-3 : ISSUE OF THE CERTIFICATE OF PRACTICAL COMPLETION – PRINCIPAL EFFECTS © HSKS

OBLIGATION TO INSURE FOR EACH SECTION ENDS WITH CPC (DEPENDING ON CONTRACT PROVISION)

CERTIFICATE OF PRACTICAL COMPLETION FOR EACH SECTION SEPARATE EXTENSION OF TIME CERTIFICATION FOR EACH SECTION

SECTIONAL COMPLETION: PRINICPAL ISSUES/EFFECTS

RELEASE OF ONE MOIETY OF RETENTION SUM FOR EACH SECTION

SEPARATE LIQUIDATED AND ASCERTAINED DAMAGES FOR EACH SECTION SEPARATE DEFECT LIABILITY PERIOD FOR EACH SECTION

FIG. 9-4 : SECTIONAL COMPLETION – PRINCIPAL ISSUES/EFFECTS © HSKS

RELEASE OF PERFORMANCE BOND AND FINAL PAYMENT UNAFFECTED

ISSUE OF CERTIFICATE OF PARTIAL OCCUPATION OF RELEVANT PART WITHIN STIPULATED PERIOD

COMMENCEMENT OF DEFECT LIABILITY PERIOD FOR RELEVANT PART ON DATE OF POSSESSION/ OCCUPATION

PARTIAL POSSESION/ OCCUPATION: PRINICPAL ISSUES/EFFECTS

CESSATION/REDUCTION OF INSURANCES CORRESPONDINGLY (IF EXPRESSLY PERMITTED)

PROPORTIONING DOWN OF LIQUIDATED AND ASCERTAINED DAMAGES RELEASE OF A PROPORTION OF FIRST HALF OF RETENTION SUM IN RESPECT OF RELEVANT PART WITHIN STIPULATED PERIOD

FIG. 9-5 : PARTIAL POSSESSION/OCCUPATION – PRINCIPAL ISSUES/EFFECTS © HSKS

COMPLETION OF WORKS UNDER THE CONTRACT

LITERAL MEANING/ INTERPRETATION

SECTIONAL COMPLETION

PRACTICAL COMPLETION



Strict View



Also termed ‘Substantial Completion’ in some cases

• Envisages completion in sections/ stages/phases



Absence of any patent defects; and



Adopts an expedient view



Connotates a state of readiness for use or occupation by Employer

• Intention must be agreed/expressed at time of contracting.



Absence of any outstanding works however trifling



Rarely used in practice



Has been abandoned in favour of a more expedient approach



• Contract Documents must identify/ define:

Formalized by issue of Certificate of Practical Completion (CPC) or Taking Over Certificate (TOC)



More common in practice



Provided for expressly in many Standard Forms

a) Each Section b) The Completion dates c) The Corresponding LAD •

Each section has separate: a) Certificate of Practical Completion (CPC)/TOC or Defect Notification Period (DNP)

PARTIAL POSSESSION • Situation where Employer takes over/resumes possession of: a)Whole works, or b) Part of works before Contract Completion Date • Pre-Conditions: a)With consent of Contractor b) Consent not to be unreasonably withheld • Procedural aspects: a)Issue of Certificate of Partial Occupation (CPO) within 7 days of possession. b)

Certificate to identify: i) Relevant part possessed ii) Its estimated value

b) Defects Liability Period (DLP)

c)DLP/DNP starts on date of possession

c) Liquidated and Ascertained Damages (LAD)

d) LAD rate reduced prorata for unoccupied part/portion

FIG. 9-6 : COMPLETION OF WORKS UNDER THE CONTRACT – AN OVERVIEW © HSKS

TEST ON COMPLETION: AN OVERVIEW

TYPES

PURPOSE

PRELIMINARY •

Normally undertaken by Contractor on his own.



Prior to Final Tests on Completion.



Is a necessary prelude to the Final Tests

FINAL •

Normally undertaken by either:



To show compliance with the Performance Specification/ Contract Requirements



To meet applicable statutory requirements.



As a pre-condition to issue of CPC



As a pre-condition to certification by Independent 3rd Party Specialist.

FAILURES

RESPONSIBILITY

a) Contractor in the presence of Contract Administrator (or) b) Independent 3rd Party Specialists •

Is usually a precondition to issue of CPC.

CONTRACT ADMINISTRATOR

CONTRACTOR •

Contractually, responsible for: a) Preliminary and Final Testing and Commissioning. b) Satisfactory Completion

INDEPENDANT TESTER



Active participant and certifier of Final Testing and Commissioning.



Scope as expressly stipulated in Contract.



Default/negligence in certification does not relieve Contractor’s obligations.\



Eg. SIRIM, DNV, Lloyds, TÜV, Statutory authorities, etc.



May also be required under statute.

FIG. 9-7 : TEST ON COMPLETION – AN OVERVIEW © HSKS

OPERATION AND MAINTENANCE MANUALS: AN OVERVIEW

GENERAL GENERAL POSITION •

Must follow express Contract stipulations as to: a) b) c) d)



TIMING TIMING FOR FOR SUBMISSION

Type/Nature Contents Quantity Timing for Submission



Must comply with express Contract stipulations.



Normal practice is:



b)Errors/ inaccuracies

• • Professionals to update • on safety issues and errors detected.

OPERATION & MAINTENANCE MANUALS/ MANUALS/ MAINTENANCE HANDBOOKS



Permanent record of works





Suitably detailed for future reference.

To enable Works to be operated and maintained efficiently and safely.



Contents, etc. to express contract stipulations/industry practice.

Contents, etc. to express contract stipulations/industry practice.

a) O & M manuals due to product improvement.

Usual requirements include draft copies for approval prior to finalization.

ASAS--BUILT/ BUILT/ ASAS--CONSTRUCTED/ CONSTRUCTED/ ASAS-INSTALLED DRAWINGS

ACCURACY ACCURACY

• Contractor’s responsibility at least during Limitation Period for:

a) Before TOC b) After TOC c) Before Performance Certificate

Most Contracts have incorporated such stipulations



UPDATING

TYPES/ TYPES/ NATURE NATURE

In Contract and Tort



In Tort, on joint and several basis

Primary responsibility for errors, omissions, etc.



Especially so for signing-off/ endorsing ‘Qualified Person’.

MISCELLANEOUS RECORDS/ DOCUMENTS RECORDS/

RECORDS RECORDS OF OF FINAL FINAL MEASUREMENT MEASUREMENT •

Undertaken by Contract Administrator jointly with Contractor.



To facilitate preparation of Final Account.

PROFESSIONAL’ PROFESSIONAL’’S S RESPONSBILITY RESPONSBILITY

CONTRACTOR CONTRACTOR ‘‘S S RESPONSBILITY RESPONSBILITY



Final testing and commissioning records

• Servicing and Maintenance records



O & M Training records, etc.

FIG. 9-8 : OPERATION AND MAINTENANCE MANUALS – AN OVERVIEW © HSKS

IDENTIFICATION OF PATENT DEFECTS & OUTSTANDING WORKS

ISSUE OF RELEVANT COMPLETION CERTIFICATE

HANDOVER OF APPROVALS/ CLEARANCES FROM STATUTORY AUTHORITIES

HANDOVER OF ALL NECESSARY SPARES

COMPLETION OF TESTING & COMMISSIONING

TAKING OVER: TYPICAL PRECONDITIONS

TRAINING OF EMPLOYER’S OPERATION & MAINTENANCE PERSONNEL

HANDOVER OF ALL ‘AS-BUILT’ DOCUMENTS/ RECORDS

HANDOVER OF ALL NECESSARY TOOLS

HANDOVER OF ALL KEYS

FIG. 9-9: ‘TAKING OVER’ OF COMPLETED WORKS BY EMPLOYER – TYPICAL PRE-CONDITIONS © HSKS

IDENTIFICATION OF THE TYPES AND DETAILS OF NECESSARY INSPECTIONS IDENTIFICATION OF THE MODE OF FORMALIZING THE TAKING OVER

IDENTIFICATION OF THE SEQUENCE OF TAKING-OVER

TAKING OVER OF COMPLETED WORKS: PROCEDURAL ISSUES

SETTING UP OF THE PROCEDURES FOR RECORDING

ESTABLISHMENT OF TAKING-OVER PROGRAMME ESTABLISHMENT OF THE RELEVANT DELIVERABLES

FIG. 9-10 : TAKING OVER OF COMPLETED WORKS – PROCEDURAL ISSUES © HSKS

DEFECTS

© HSKS

10.0

DEFECTS



PROBLEMS WITH DEFINITIONS AND TERMINOLOGY



DEFECTS FOR WHICH CONTRACTOR RESPONSIBLE



PROBLEMS WITH DEFECT RECTIFICATION



CERTIFICATION – DELAY, NON-ISSUE, ETC.



LIABILITY UNDER LIMITATION ACT



RECENT DEVELOPMENTS



RELEVANT CASES

*

HII SOO CHIONG V BOARD OF MANAGEMENT YEE TING PRIMARY SCHOOL [1973] 2 MLJ 204

*

LEO TENG CHOY V BEETILE CONSTRUCTION [1982] 2 MLJ 304

© HSKS

*

DANCOM ENGINEERING PTE LTD. V TAKASAGO THERMAL ENGINEERING CO. LTD. [1989] BLD [MAY] 606

*

PIRELLI GENERAL CABLE WORKS LTD. V OSCAR FABER & PARTNERS [1983] 2 AC 1

*

PEARCE & HIGH LTD. V JOHN BAXTER & MRS. A.S. BAXTER [1999] BLR 101

*

BAGOT V STEVEN SCANLON & CO. [1996] 1 QB 197

*

DUTTON V BOGNOR REGIS UNITED BUILDING CO. LTD. & ANOR [1972] 1 QB 373

*

STEVEN PHOA CHENG LOON & 72 ORS V HIGHLAND PROPERTIES SDN. BHD. & 9 ORS [2000] 3 AMR 3567

© HSKS

STANDARD OF WORKMANSHIP

PATENT DEFECT

LATENT DEFECT

TYPES

QUALITY OF MATERIAL

STANDARD OF DESIGN

NATURE

DEFECTS: PRINCIPAL TYPES AND NATURE

FIG. 10-1 : DEFECTS – PRINCIPAL TYPES AND NATURE © HSKS

DEFECTS FOR WHICH CONTRACTOR IS GENERALLY RESPONSIBLE

MANAGEMENT FEE CONTRACTING

TRADITIONAL GENERAL CONTRACTING

‘PACKAGE DEAL’ DEAL’ TYPES OF CONTRACTS • Quality of Materials

• Standard of Workmanship WHOLLY EMPLOYER DESIGNED CONTRACT

PARTLY EMPLOYER DESIGNED CONTRACT

• Standard of Design

• Quality of Materials

• Quality of Materials

• Standard of Workmanship

• Standard of Workmanship

• Standard of Design (For elements of design in contractor’s scope of work)

PARTLY EMPLOYER DESIGNED CONTRACT

WHOLLY EMPLOYER DESIGNED CONTRACT •

Quality of Materials



Quality of Materials



Standard of Workmanship



Standard of Workmanship



Standard of Design (For elements of design in contractor’s scope of work)

FIG. 10-2 : DEFECTS FOR WHICH CONTRACTOR IS GENERALLY RESPONSIBLE © HSKS

ARISING FROM ‘FAIR WEAR AND TEAR’ HAVING NUMBER OF CAUSES, CONTRACTOR’S PORTION BEING MINOR

ARISING FROM MISUSE/ ABUSE BY USERS / EMPLOYER

DEFECTS FOR WHICH CONTRACTOR IS GENERALLY NOT RESPONSIBLE

WAIVED BY EMPLOYER

ARISING FROM WORK WHICH IS NOT CONTRACTOR’S RESPONSIBILITY OUT OF TIME OR STATUTE BARRED

FIG. 10-3 : DEFECTS FOR WHICH CONTRACTOR IS GENERALLY NOT RESPONSIBLE © HSKS

POST-COMPLETION STAGE

PRE-COMPLETION STAGE



Or Post-Handing Over Stage



Or During ‘Defects Liability Period’, etc.

POST-CMGD STAGE



Or Pre-Handing Over Stage





Or During Currency of Construction, Installation, etc.

Or Post-Certification of Completion of Making Good Defects



Or During Limitation Period

CONTRACTOR’S LIABILITY FOR DEFECTS: PRINCIPAL STAGES OF CONTRACT

FIG. 10-4 : CONTRACTOR’S LIABILITY FOR DEFECTS – PRINCIPAL STAGES OF CONTRACT © HSKS

DETERMINATION OF CONTRACTOR’S EMPLOYMENT UNDER THE CONTRACT

THIRD PARTY ACTION TO MAKE GOOD DEFECTS

EMPLOYER’S PRINCIPAL REMEDIES FOR CONTRACTOR’S DEFAULT IN RECTIFYING REPORTED DEFECTS AT PRECONTRACT COMPLETION STAGE

POSTPONEMENT/NONCERTIFICATION OF COMPLETION OF WORKS

EMPLOYER MAY UNDERTAKE RECTIFICATION WORKS HIMSELF

FIG. 10-5: EMPLOYER’S PRINCIPAL REMEDIES FOR CONTRACTOR’S DEFAULT IN RECTIFYING REPORTED DEFECTS AT PRE-CONTRACT COMPLETION STAGE © HSKS

MISCELLANEOUS ACTS E.G. RAILWAYS ACT 1991 (SECTION 97) CIVIL LAW ACT 1965 (SECTION 7(5), ETC.

LIMITATION ACT 1953 (REV. 1981) - WEST MALAYSIA LIMITATION ORDINANCE 1959 (REPRINT 1965) SARAWAK

LIMITATION: RELEVANT STATUTORY ENACTMENTS

PUBLIC AUTHORITIES PROTECTION ACT 1948 (REV. 1978)

LIMITATION ORDINANCE 1952 (REPRINT 1966) SABAH LIMITATION ACT (CAP 14) REVISED EDN. 2000 BRUNEI

FIG. 10-6 : LIMITATION – RELEVANT STATUTORY ENACTMENTS © HSKS

EXPIRY OF PERIOD FOR RECTIFYING DEFECTS: OPTIONS AVAILABLE TO CONTRACT ADMINISTRATOR

DEFECTS REMAINING OUTSTANDING AND/OR UNRECTIFIED

ALL DEFECTS SATISFACTORILY MADE GOOD/RECTIFIED • Contract administrator to: a) Prepare and b) Issue the Performance Certificate forthwith.

• See express clauses under ICTAD/SBD/02

DEFECTS ARE EITHER:

DEFECTS ARE EITHER:

• minor or not material

• Serious and/or

• Impracticable or inconvenient for contractor to make good

• Material

Contract administrator to:

• Carry out diminution in value; and • Prepare and Issue Certificate of Making Good Defects

EMPLOYER TO UNDERTAKE WORKS HIMSELF I.E. DEPARTMENTALLY

RD PARTY ACTION TAKE 3RD

• Deduct costs involved from:



Deduct costs involved from:

a) money due to contractor and/or

a) money due to contractor and/or

b) Performance bond and/or

b) Performance bond and/or

c) as a liquidated demand

c) as a liquidated demand

FIG. 10-7 : EXPIRY OF PERIOD FOR RECTIFYING DEFECTS – OPTIONS AVAILABLE TO CONTRACT ADMINISTRATOR © HSKS

OFFICIALLY ENDS THE DEFECT LIABILITY PERIOD (DLP)

OBLIGATIONS UNDER THE CONTRACT ARE NOT RELIEVED

DISCHARGES CONTRACTOR’S RIGHTS UNDER CONTRACT TO PHYSICALLY ATTEND TO DEFECTS

CONTRACTOR’S LIABILITY FOR LATENT AND PATENT DEFECTS CONTINUES FOR THE STATUTORY PERIOD OF LIMITATION

MARKS THE BEGINING OF THE CONTRACTUAL PERIOD FOR PREPARATION OF FINAL ACCOUNT

PARTIES’ OUTSTANDING

ISSUE OF CERTIFICATE MAKING GOOD OF DEFECTS: PRINCIPAL EFFECTS ON PARTIES

DISCHARGES LIABILITY OF

GUARANTORS, INSURERS, ETC. UNDER THE CONTRACT

FIG. 10-8:

EMPLOYER HAS TO RELEASE SECOND MOIETY OF RETENTION SUM THAT IS WITHHELD

MARKS THE COMMENCEMENT OF THE CONTRACTUAL PERIOD FOR CONTRACT ADMINISTRATOR TO ISSUE FINAL CERTIFICATE

ISSUE OF CERTIFICATE OF MAKING GOOD OF DEFECTS – PRINCIPAL EFFECTS ON PARTIES © HSKS

POST-COMPLETION AND FINAL ACCOUNT

© HSKS

11.0

POST COMPLETION AND FINAL ACCOUNT



LIABILITIES ARISING FROM DEFAULTS/OMISSIONS IN:

*

TRAINING

*

O & M MANUALS

*

AS-BUILT DRAWINGS



FINALISATION OF ACCOUNT ISSUES



FINAL CERTIFICATE ISSUES



POSTPOST-FINAL CERTIFICATE PROBLEMS



RELEVANT CASES

*

FAIRWEATHER LTD. V ASDEN SECURITIES LTD. [1979] 12 BLR 40

*

CHEW SIN LONG CONSTRUCTION CO. LTD. V COSY HOUSING DEVELOPMENT PTE LTD. [1988] 1 MLJ 331

*

THAMESA DESIGNS SDN. BHD. & ORS V KUCHING HOTELS SDN. BHD. [1993] 3 MLJ 28

*

TOKEN CONSTRUCTION CO. LTD. V CHARLTON ESTATES LTD. [1973] 1 BLR 48

*

SHEN YUAN PAI V DATO’ WEE HOOD TECK & ORS [1976] 1 MLJ 16

© HSKS

SERVICING & MAINTENANCE: AN OVERVIEW

GENERAL POSITION • •

PURPOSE

Must follow express Contract stipulations



Most Contracts e.g. M&E have such provisions in the specifications.



EXTENT

FREQUENCY

To ensure Contractor meets contractual obligations



Per stipulations in:





Implied from: a) Statutory requirements

To minimize defects and downtime and prolong lifetime and efficiency.

• • • • •

Daily Weekly Monthly Quarterly Yearly

EXPRESS EXPRESS REQUIREMENTS •

As stipulated: a) In Contract b) In Manufacturer’s Warranties/ recommendations c) In O & M Manuals



Generally, most contracts require contractor to do monthly/ quarterly servicing.

To carry out and/or erroneous/negligent servicing.



P.C. may not be issued



Period may be extended



Use of 3rd Parties at Contractor’s Cost



Warranties may be compromised.



Possible action in contract, tort, statute, etc.

b) Trade usage c) Local practice

PREVALENT PREVALENT PRACTICE PRACTICE

EFFECT OF FAILURE

a) Contract and/or b) O & M Manuals

Not to nullify equipment warranties.



PROCEDURE FOR MONITORING

IMPLIED REQUIREMENTS REQUIREMENTS • In absence of express stipulations implied from: a) Trade usage b) Local practice c) Statute • General implication is that Employer will undertake daily and weekly servicing and maintenance.

CONTRACT ADMINISTRATOR’ ADMINISTRATOR’S RESPONSIBILITY

CONTRACTOR’ CONTRACTOR’’S S DUTY DUTY •

Proper and effective record keeping of: a) Compliances b) Deviations c) Unusual observations



Timely recording and signing-off.



Monitoring of Contractor’s work



Signing-off the records



Reporting to Employer of unusual observations

EMPLOYERS EMPLOYERS OBLIGATIONS •

Undertaking of routine servicing and maintenance e.g. daily, weekly, etc.



Affording Contractor proper access to work being serviced.



Attending to unusual observations reported.

FIG. 11-1 : SERVICING AND MAINTENANCE – AN OVERVIEW © HSKS

PLANS OF COMPLETED WORKS

‘AS-BUILT’ DRAWINGS

COMMON LABELS FOR RECORDS/ DRAWINGS OF COMPLETED WORKS

‘AS-INSTALLED’ DRAWINGS

‘AS-CONSTRUCTED’ DRAWINGS

FIG. 11-2 : COMMON LABELS FOR RECORDS/DRAWINGS OF COMPLETED WORKS © HSKS

‘AS-BUILT’ DRAWINGS: AN OVERVIEW

GENERAL POSITION •

Must follow express Contract stipulations as to: a) b) c) d)



Type/Nature Contents Quantity Timing for Submission

Most Contracts have express provisions incorporated.

TIMING FOR SUBMISSION

TYPES/ NATURE



Must comply with express contract stipulations.



Normal practice is:



a) Before CPC b) After CPC c) Before CMGD •

Contractor’s responsibility at least during Limitation Period for: a) Revisions due to product improvement.

Usual requirements include draft copies for approval prior to finalization.

Professionals to update on safety issues and errors detected.

OPERATION & MAINTENANCE SCHEMATICS /DIAGRAMMES



In Contract and Tort



In Tort, on joint and several basis



Primary responsibility for errors, omissions, etc.



Especially so for signing-off/ endorsing ‘Qualified Person’.

RECORDS OF FINAL MEASUREMENT



Permanent record of works



To supplement O&M Manuals



Undertaken by Contract Administrator jointly with Contractor.



Suitably detailed for future reference.



Contents, etc. to express contract stipulations/industry practice.



To facilitate preparation of Final Account.



PROFESSIONAL’S RESPONSBILITY

CONTRACTOR’S RESPONSBILITY

b) Errors/ inaccuracies •

AS-BUILT/ AS-CONSTRUCTED/ AS-INSTALLED DRAWINGS

ACCURACY

UPDATING

Contents, etc. to express contract stipulations/industry practice.

FIG. 11-3: ‘AS-BUILT’ DRAWINGS – AN OVERVIEW © HSKS

FINAL CERTIFICATE MISCELLANEOUS LABELS

FINAL ACCOUNT CERTIFICATE

CERTIFICATION UPON EXPIRY OF CONTRACT PERIOD: COMMON LABELS

PERFORMANCE CERTIFICATE

ULTIMATE CERTIFICATE

FINAL PAYMENT CERTIFICATE

FIG. 11-4 : CERTIFICATION UPON EXPIRY OF CONTRACT PERIOD – COMMON LABELS © HSKS

ISSUED UPON EXPIRY OF THE CONTRACT PERIOD ACTUAL EFFECT DICTATED BY THE PRECISE TERMS OF THE APPLICABLE CONDITIONS OF CONTRACT

ISSUED BY THE CONTRACT ADMINISTRATOR

FINALCERTIFICATE: PRINCIPAL CHARACTERISTICS

RENDERS THE CONTRACT ADMINISTRATOR ‘FUNCTUS OFFICO’

LAST OF THE VARIOUS CERTIFICATES ISSUED DURING CONTRACT PERIOD

PRIMA FACIE, SIGNIFIES DISCHARGE OF THE CONTRACT BY PERFORMANCE

FIG. 11-5 : FINAL CERTIFICATE – PRINCIPAL CHARACTERISTICS © HSKS

ISSUE OF PERFORMANCE CERTIFICATE (P.C.)

SATISFACTION OF ALL OTHER OBLIGATIONS/DUTIES UNDER CONTRACT

EXPIRY OF DEFECT NOTIFICATION PERIOD (DNP)

TYPICAL PRE-CONDITIONS TO THE ISSUE OF THE FINAL CERTIFICATE

FORMAL APPLICATION FOR THE FINAL PAYMENT CERTIFICATE

CERTIFICATION OF COMPLETION OF SERVICING AND MAINTENANCE

PREPARATION AND FINALIZATION OF THE FINAL ACCOUNT

FIG. 11-6 : TYPICAL PRE-CONDITIONS TO THE ISSUE OF THE FINAL PAYMENT CERTIFICATE © HSKS

THAT ALL THE CONTRACTOR’S FINANCIAL CLAIMS HAVE BEEN PROPERLY ACCOUNTED FOR

SATISFACTION OF THE COMPLETION CRITERIA AS SPELT OUT IN THE CONTRACT AND WHERE IT IS STIPULATED TO BE TO THE REASONABLE SATISFACTION OF THE CONTRACT ADMINISTRATOR

EFFECT OF ISSUE OF FINAL PAYMENT CERTIFICATE – PRINCIPAL MATTERS FOR WHICH CERTIFICATE PROVIDES ‘CONCLUSIVE EVIDENCE’

THAT ALL EXTENSIONS OF TIME OFFICIALLY GRANTED ARE CORRECT

FIG. 11-7 :

THAT EXCEPT FOR ANY COMPUTING ERRORS, ETC. ALL RELEVANT ADJUSTMENTS (ADDITIONS/ DEDUCTIONS) HAVE BEEN MADE TO THE CONTRACT SUM

EFFECT OF ISSUE OF FINAL PAYMENT CERTIFICATE – PRINCIPAL MATTERS FOR WHICH CERTIFICATE PROVIDES ‘CONCLUSIVE EVIDENCE’ © HSKS

FRAUD/DISHONESTY/FRAUDULENT CONCEALMENT BY CONTRACTOR UNDISCOVERED DEFECTS E.G. LATENT DEFECTS, ETC. COMPUTATIONAL ERRORS, ACCIDENTAL INCLUSIONS/EXCLUSIONS, ETC. CERTIFICATE NOT GIVEN IN CORRECT FORM CERTIFICATE NOT GIVEN ON TIME CERTIFICATE NOT GIVEN BY AUTHORIZED PERSON

FINAL CERTIFICATE: TYPICAL CHALLENGES TO ‘CONCLUSIVENESS’/’FINALITY’

CERTIFIER ACTING ‘ULTRA VIRES’ CERTIFIER IMPROPERLY PRESSURIZED/INFLUENCED FRAUD/COLLUSION BETWEEN CERTIFIER AND OTHER PARTY CERTIFICATE EMBODIES WRONG DECISION ON A POINT OF LAW THE EFFECT OF THE PRESENCE OF AN ARBITRATION CLAUSE MISCELLANEOUS CHALLENGES/GROUNDS FOR CHALLENGING

FIG. 11-8: FINAL PAYMENT CERTIFICATE – TYPICAL CHALLENGES TO ‘CONCLUSIVENESS’/ ’FINALITY’ © HSKS

THANK YOU

© HSKS

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF