Construction Schedule
March 26, 2017 | Author: Dhananjay Singh | Category: N/A
Short Description
Download Construction Schedule...
Description
ID 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
Task Name
Qtr 2, 2011
Duration
Start
Finish
Predecessors
Successors May
Resource Names S
Construction Schedule2007
406 days
Tue 5/17/11
1 SUB-STRUCTURE 107 days 1.1 Driving Piles 15 days 1.2 Excavation 10 days 1.3 Breaking Piles upto cut-off level 2 days 1.4 PCC 15 days 1.5 Formwork for foundation 5 days 1.6 Reinforcement for pile cap 3 days 1.7 Casting of pile cap 7 days 1.8 Formwork for individual or combined footing 9 days 1.9 Reinforcement for individual or combined footing 11 days 1.10 Casting of individual or combined footing 28 days 1.11 Backfilling, Compacting the filled earth 10 days 1.12 PCC below plinth beam 2 days 1.13 Formwork for plinth beam 10 days 1.14 Reinforcement for plinth beam 5 days 1.15 Casting of plinth beam 6 days 1.16 Anti-Termite treatment 4 days 2 SUPER-STRUCTURE 191 days 2.1 Formwork for column upto first floor 3 days 2.2 Reinforcement for column 5 days 2.3 Erecting the column upto first floor 5 days 2.4 Formwork for slab and beam 12 days 2.5 Reinforcement for slab and beam 6 days 2.6 Casting the first floor slab and beam monolithically 3 days 2.7 Formwork for staircase upto first floor 9 days 2.8 Reinforcement for staircase 1 day 2.9 Staircase upto first floor 3 days 2.10 Formwork for column upto second floor 3 days 2.11 Reinforcement for column 5 days 2.12 Erecting the column upto second floor 5 days 2.13 Formwork for slab and beam 12 days 2.14 Reinforcement for slab and beam 6 days 2.15 Casting the second floor slab and beam monolithically 3 days 2.16 Formwork for staircase upto second floor 9 days 2.17 Reinforcement for staircase 1 day 2.18 Staircase upto second floor 3 days 2.19 Formwork for column upto third floor 3 days 2.20 Reinforcement for column 5 days 2.21 Erecting the column upto third floor 5 days 2.22 Formwork for slab and beam 12 days 2.23 Reinforcement for slab and beam 6 days 2.24 Casting the third floor slab and beam monolithically 3 days 2.25 Formwork for staircase upto third floor 9 days 2.26 Reinforcement for staircase 1 day 2.27 Staircase upto third floor 3 days 2.28 Constructing brick walls 28 days 2.29 Fixing doors and windows frames 3 days 3 PLUMBING WORK 9 days 3.1 Completing the pipeline work and connecting it to municipal chambers 6 days 3.2 Plumbing work in lab 2 days 3.3 Plumbing work in WC 1 day 3.4 Plumbing work in Bathrooms 1 day 3.5 Wash-Hand basins 1 day 3.6 Connecting pipes from electric motor to elevated tank 2 days 4 FINISH WORK 111 days
Tue 5/17/11 Tue 5/17/11 Mon 5/30/11 Thu 6/9/11 Mon 6/13/11 Tue 6/28/11 Sun 7/3/11 Wed 7/6/11 Sun 6/19/11 Tue 6/28/11 Sat 7/2/11 Sat 7/30/11 Tue 8/9/11 Thu 8/11/11 Sun 8/21/11 Fri 8/26/11 Sat 8/20/11 Thu 9/1/11 Thu 9/1/11 Mon 9/5/11 Sun 9/11/11 Fri 9/23/11 Wed 10/5/11 Mon 10/10/11 Sun 9/4/11 Tue 9/13/11 Wed 9/14/11 Mon 10/24/11 Fri 10/28/11 Thu 11/3/11 Tue 11/15/11 Sun 11/27/11 Fri 12/2/11 Tue 12/6/11 Thu 12/15/11 Fri 12/16/11 Mon 12/19/11 Fri 12/23/11 Thu 12/29/11 Thu 1/5/12 Tue 1/17/12 Sun 1/22/12 Thu 1/26/12 Sat 2/4/12 Sun 2/5/12 Wed 2/8/12 Wed 3/7/12 Wed 3/7/12 Sat 3/10/12 Wed 3/7/12 Wed 3/7/12 Wed 3/7/12 Wed 3/7/12 Wed 3/7/12 Wed 3/7/12
Project: Construction Schedule2007 Date: Thu 3/20/14
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
June W
Mon 6/25/12 Wed 8/31/11 Tue 5/31/11 Wed 6/8/11 2SS+13 days Fri 6/10/11 3FF+2 days Mon 6/27/11 4FS+2 days Sat 7/2/11 5SF+20 days Tue 7/5/11 6 Tue 7/12/11 7 Mon 6/27/11 3SS+20 days Fri 7/8/11 9 Fri 7/29/11 10SS+4 days Mon 8/8/11 11,8 Wed 8/10/11 12 Sat 8/20/11 13 Thu 8/25/11 14 Wed 8/31/11 15 Tue 8/23/11 12SS+21 days Fri 3/9/12 Sat 9/3/11 16,17 Fri 9/9/11 19SS+4 days Thu 9/15/11 20SS+6 days Tue 10/4/11 21FS+7 days Mon 10/10/11 22 Thu 10/13/11 23 Mon 9/12/11 19 Tue 9/13/11 25 Fri 9/16/11 26 Wed 10/26/11 27,24SS+13 days Tue 11/1/1128SS+4 days Mon 11/7/1129SS+6 days Sat 11/26/1130FS+7 days Fri 12/2/11 31 Mon 12/5/11 32 Wed 12/14/11 28,33 Thu 12/15/11 34 Sun 12/18/11 35 Wed 12/21/11 32SS+13 days,36 Tue 12/27/11 37SS+4 days Mon 1/2/12 38SS+6 days Mon 1/16/12 39SS+7 days Sun 1/22/12 40 Wed 1/25/12 41 Fri 2/3/12 37,42 Sat 2/4/12 43 Tue 2/7/12 44 Tue 3/6/12 16,24SS+90 days,45 Fri 3/9/12 46 Thu 3/15/12 Thu 3/15/12 46,47 Thu 3/8/12 46 Wed 3/7/12 46 Wed 3/7/12 46 Wed 3/7/12 46 Thu 3/8/12 46 Mon 6/25/12
3SS+13 days 4FF+2 days,9SS+20 days 5FS+2 days 6SF+20 days 7 8 12 10 11SS+4 days 12 13,17SS+21 days 14 15 16 19,46 19 20SS+4 days,25 21SS+6 days 22FS+7 days 23 24 46SS+90 days,28SS+13 days 26 27 28 29SS+4 days,34 30SS+6 days 31FS+7 days 32 33,37SS+13 days 34 35 36 37 38SS+4 days,43 39SS+6 days 40SS+7 days 41 42 43 44 45 46 47,49,50,51,52,53,54,61 49 58 58 58 58 58 56
Labor[20],
Labor[20],Machine,Mason Labor[32] Labor[12] Labor[32],Bhisti[15],Mason[2],Machine[3] Carpenter[14],Labor[14] Labor[5],Fitter[5] Labor[15],Bhisti[8],Machine,Mason[2] Carpenter[8],Labor[8] Fitter[11],Labor[11] Labor[35],Bhisti[18],Mason[4] Labor[32] Labor[10],Bhisti[4],Mason,Machine Carpenter[9],Labor[9] Fitter[9],Labor[9] Labor[7],Bhisti[4],Mason Labor[7]
Labo
Carpenter[42],Labor[42] Fitter[13],Labor[13] Labor[15],Bhisti[8],Mason[2],Machine Carpenter[59],Labor[52] Fitter[20],Labor[20] Labor[164],Bhisti[66],Mason[20],Machine[6] Carpenter[19],Labor[14] Fitter[5],Labor[5] Bhisti[5],Labor[25],Mason[2] Carpenter[42],Labor[42] Fitter[13],Labor[13] Labor[15],Bhisti[8],Mason[2],Machine Carpenter[59],Labor[52] Fitter[20],Labor[20] Labor[164],Bhisti[66],Mason[20],Machine[6] Carpenter[19],Labor[14] Fitter[5],Labor[5] Bhisti[5],Labor[25],Mason[2] Carpenter[42],Labor[42] Fitter[13],Labor[13] Labor[15],Bhisti[8],Mason[2],Machine Carpenter[59],Labor[52] Fitter[20],Labor[20] Labor[164],Bhisti[66],Mason[20],Machine[6] Carpenter[19],Labor[14] Fitter[5],Labor[5] Bhisti[5],Labor[25],Mason[2] Labor[48],Bhisti[5],Mason[24] Carpenter[9],Labor[2] Fitter,Labor[16] Labor[24],Bhisti[11],Mason[18] Labor[18],Bhisti[14],Mason[17] Labor[15],Bhisti[7],Mason[11] Labor[15],Bhisti[7],Mason[11] Labor[15],Bhisti[7],Mason[11]
Task
Project Summary
Inactive Milestone
Manual Summary Rollup
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 1
ID 56 57 58 59 60 61 62 63 64 65 66 67 68 69
Task Name
Qtr 2, 2011
Duration
4.1 External plastering first coat 4.2 External plastering second coat 4.3 Internal plastering first floor 4.4 Internal plastering second floor 4.5 Internal plastering third floor 4.6 Floorings of first floor 4.7 Flooring of second floor 4.8 Flooring of Third floor 4.9 Fittings of wall tiles in lab, water closet and bathroom 4.10 Applying Putty in two coats 4.11 Internal painting first floor 4.12 Internal painting second floor 4.13 Internal painting third floor 4.14 External painting
Project: Construction Schedule2007 Date: Thu 3/20/14
7 days 5 days 12 days 12 days 12 days 17 days 17 days 17 days 9 days 19 days 6 days 6 days 6 days 14 days
Start Fri 3/9/12 Fri 3/16/12 Fri 3/16/12 Wed 3/28/12 Mon 4/9/12 Wed 3/7/12 Sat 3/24/12 Tue 4/10/12 Fri 4/27/12 Sun 5/6/12 Fri 5/25/12 Thu 5/31/12 Wed 6/6/12 Tue 6/12/12
Finish
Predecessors
Successors May
Thu 3/15/12 54 Tue 3/20/12 56 Tue 3/27/12 49,50,51,52,53 Sun 4/8/12 58 Fri 4/20/12 59 Fri 3/23/12 46 Mon 4/9/12 61 Thu 4/26/12 62 Sat 5/5/12 60,63 Thu 5/24/12 64 Wed 5/30/12 65 Tue 6/5/12 66 Mon 6/11/12 67 Mon 6/25/12 57,68
57 69 59 60 64 62 63 64 65 66 67 68 69
Resource Names Labor[24],Bhisti[11],Mason[18] Labor[18],Bhisti[14],Mason[17] Bhisti[7],Labor[15],Mason[11] Bhisti[7],Labor[15],Mason[11] Bhisti[7],Labor[15],Mason[11] Labor[7],Mason[11],Machine[5] Labor[7],Mason[11],Machine[5] Labor[7],Mason[11],Machine[5] Labor[19],Mason[19] Labor[83],Painter[83] Labor[8],Bhisti,Painter[17] Labor[8],Bhisti,Painter[17] Labor[8],Bhisti,Painter[17] Labor[12],Bhisti[2],Painter[23]
S
M
T
W
Task
Project Summary
Inactive Milestone
Manual Summary Rollup
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 2
T
F
S
S
M
T
W
T
F
S
S
M
T
June W
June W T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
Qtr 3, 2011 July T F S S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
August M T
W
T
F
S
S
Labor[20],Machine,Mason Labor[32] Labor[12] Labor[32],Bhisti[15],Mason[2],Machine[3] Carpenter[14],Labor[14] Labor[5],Fitter[5] Labor[15],Bhisti[8],Machine,Mason[2] Carpenter[8],Labor[8] Fitter[11],Labor[11] Labor[35],Bhisti[18],Mason[4]
Labo
Project: Construction Schedule2007 Date: Thu 3/20/14
Task
Project Summary
Inactive Milestone
Manual Summary Rollup
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 3
June W T
F
S
S
M
T
W
Project: Construction Schedule2007 Date: Thu 3/20/14
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
Qtr 3, 2011 July T F S S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
Task
Project Summary
Inactive Milestone
Manual Summary Rollup
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 4
S
M
T
W
T
F
S
S
August M T
W
T
F
S
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
September W T F S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
Qtr 4, 2011 October F S S M
T
W
T
F
S
S
M
T
W
T
son[4] Labor[32] Labor[10],Bhisti[4],Mason,Machine Carpenter[9],Labor[9] Fitter[9],Labor[9] Labor[7],Bhisti[4],Mason Labor[7] Carpenter[42],Labor[42] Fitter[13],Labor[13] Labor[15],Bhisti[8],Mason[2],Machine Carpenter[59],Labor[52]
Fitter[20],Labor[2 Labo Carpenter[19],Labor[14] Fitter[5],Labor[5] Bhisti[5],Labor[25],Mason[2]
Carpe
Project: Construction Schedule2007 Date: Thu 3/20/14
Task
Project Summary
Inactive Milestone
Manual Summary Rollup
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 5
S
M
T
W
T
F
S
S
Project: Construction Schedule2007 Date: Thu 3/20/14
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
September W T F S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
Task
Project Summary
Inactive Milestone
Manual Summary Rollup
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 6
T
Qtr 4, 2011 October F S S M
T
W
T
F
S
S
M
T
W
T
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
November T W T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
December T F S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
] Fitter[20],Labor[20] Labor[164],Bhisti[66],Mason[20],Machine[6]
Carpenter[42],Labor[42] Fitter[13],Labor[13] Labor[15],Bhisti[8],Mason[2],Machine Carpenter[59],Labor[52]
Fitter[20],Labor[20] Labor[164],Bhisti[66],Mason[20],Machine[6] Carpenter[19],Labor[14] Fitter[5],Labor[5] Bhisti[5],
Labo
Project: Construction Schedule2007 Date: Thu 3/20/14
Task
Project Summary
Inactive Milestone
Manual Summary Rollup
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 7
T
F
S
S
M
T
W
T
Project: Construction Schedule2007 Date: Thu 3/20/14
F
S
S
M
T
W
T
F
S
S
M
November T W T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
December T F S
S
M
Task
Project Summary
Inactive Milestone
Manual Summary Rollup
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 8
T
W
T
F
S
S
M
T
W
T
F
S
S
M
M
T
W
T
F
S
S
M
T
W
T
F
Qtr 1, 2012 January S S M T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
February W T F
S
S
M
T
W
T
F
S
S
M
T
enter[19],Labor[14] itter[5],Labor[5] Bhisti[5],Labor[25],Mason[2] Carpenter[42],Labor[42] Fitter[13],Labor[13] Labor[15],Bhisti[8],Mason[2],Machine Carpenter[59],Labor[52] Fitter[20],Labor[20] Labor[164],Bhisti[66],Mason[20],Machine[6] Carpenter[19],Labor[14] Fitter[5],Labor[5] Bhisti[5],Labor[25],Mason[2]
Project: Construction Schedule2007 Date: Thu 3/20/14
Task
Project Summary
Inactive Milestone
Manual Summary Rollup
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 9
W
T
F
S
S
M
T
W
T
F
M
T
W
T
F
S
S
M
T
W
T
F
Qtr 1, 2012 January S S M T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
February W T F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
Labo
Project: Construction Schedule2007 Date: Thu 3/20/14
Task
Project Summary
Inactive Milestone
Manual Summary Rollup
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 10
F
S
S
M
T
March W T F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
Qtr 2, 2012 April S S M T
W
T
F
S
S
M
T
W
T
F
S
S
M
Labor[48],Bhisti[5],Mason[24] Carpenter[9],Labor[2] Fitter,Labor[16] Labor[24],Bhisti[11],Mason[18] Labor[18],Bhisti[14],Mason[17] Labor[15],Bhisti[7],Mason[11] Labor[15],Bhisti[7],Mason[11] Labor[15],Bhisti[7],Mason[11]
Project: Construction Schedule2007 Date: Thu 3/20/14
Task
Project Summary
Inactive Milestone
Manual Summary Rollup
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 11
T
W
T
F
S
S
M
T
W
T
F
S
S
M
May T
F
S
S
M
T
March W T F
S
S
M
T
W
T
F
S
S
M
T
W
T
Qtr 2, 2012 April S S M T
F S S M T W T F S S M T W T F W Labor[24],Bhisti[11],Mason[18] Labor[18],Bhisti[14],Mason[17] Bhisti[7],Labor[15],Mason[11]
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
May T
Bhisti[7],Labor[15],Mason[11] Bhisti[7],Labor[15],Mason[11] Labor[7],Mason[11],Machine[5] Labor[7],Mason[11],Machine[5]
Labor[7],Mason[11],Machi
Project: Construction Schedule2007 Date: Thu 3/20/14
Task
Project Summary
Inactive Milestone
Manual Summary Rollup
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 12
May T W
T
F
S
S
M
T
Project: Construction Schedule2007 Date: Thu 3/20/14
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
June T F S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
Task
Project Summary
Inactive Milestone
Manual Summary Rollup
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 13
S
S
M
T
W
T
F
Qtr 3, 2012 July S S M T
W
T
F
S
May T W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
June T F S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
T
F
Qtr 3, 2012 July S S M T
r[7],Mason[11],Machine[5] Labor[19],Mason[19] Labor[83],Painter[83] Labor[8],Bhisti,Painter[17] Labor[8],Bhisti,Painter[17] Labor[8],Bhisti,Painter[17] Labor[12],Bhisti[2],Painter[23]
Project: Construction Schedule2007 Date: Thu 3/20/14
Task
Project Summary
Inactive Milestone
Manual Summary Rollup
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 14
W
T
F
S
View more...
Comments