Construction Productivity

March 11, 2017 | Author: Sara Vanan | Category: N/A
Share Embed Donate


Short Description

Download Construction Productivity...

Description

All the Productivity Rates are for working 8 hours/day Description Earth Works

Qty

Rate

Resource

Excavation work in soft soil Excavation Work in Hard Soil

120 50

m3/day m3/day

Excavator (bucket type) Rock breaker

In layer of 150 mm thickness with 95% MDD value

150

m2/day

1 Skilled, 4 Unskilled, 1 shovel,1 Roller compactor

Including surface preparation Horizontal/Vertical surface Horizontal/Vertical Surface

200 150 80

m2/day m2/day m2/day

1 skilled + 1 unskilled 1 skilled + 1 unskilled 1 skilled + 1 unskilled

75/100 mm thick Blinding works

120

m2/day

1 Mason + 2 Helper

40/50 mm thick C/S Screed 75/100 mm thick screed with welded steel fabric

200

m2/day

1 Mason + 2 Helper

120

m2/day

Up to 16 mm dia bars Above 16 mm dia bars Up to 12 mm 16 mm and Above

200 300 200 300 400

kg kg kg kg kg

With Ordinary(Ply wood) shutter " "

8 6 12

m2/day m2/day m2/day

60 40

m3/hr m3/hr

Concrete Placing and Trowel Finishing " "

160 60 150

m3/day m3/day m3/day

1 Mason + 3 helper 1 Mason + 2 helper 2 Mason + 3 Helper

Placing in line and level

400

m2/day

2 Rigger + 1 Mason + 2 Helper

10/15/20 cm thick Block works

10

m2/day

1 mason + 1 Helper

15 mm thick Plaster Works with Acc. 20 mm thick Plaster Works with Acc.

12 10

m2/day m2/day

1 Plaster Mason + 1 Helper 1 Plaster Mason + 1 Helper

Including Surface preparation works First Coat Second Coat

150 75 250 350

m2/day m2/day m2/day m2/day

1 Painter + 1 Helper 1 Painter + 1 Helper 1 painter 1 Painter

Surface Prep + Priming Painting

50 100

m2/day m2/day

1 Painter + 1 Helper 1 Painter + 1 Helper

Frame + Gypsum Partition Installation

120

m2/day

1 Mason + 1 Helper

Frame + False Ceiling Fixing

30

m2/day

1 Mason + 1 Helper

Tile Works

On Floor On Walls

15 12

m2/day m2/day

1 Mason + 1 Helper 1 Mason + 1 Helper

Marble/Granite Works

on Floor

20

m2/day

2 Mason + 1 Helper

Back Filling + Compaction

Concrete Protection Works Bitumen Priming Works Bitustic works Protection works (torch applied) Concrete Blinding Works Screed Works

Reinforcement Works Isolated/ Strap Footing Column/Corewall/Staircase Slab with beam/Raft

Shuttering Footing Column/Core Wall/Staircase Slab Concrete Pumping Works Placing with concrete Pump Boom Placer Concrete Works Footings Staircase Slab Placing Precast/Hollow Core Slab

Block works Plaster Works

Ordinary Painting Priming Works Putty Works Painting Works

Epoxy Paint

Gypsum Partition Works False Ceiling

1 Mason + 2 Helper

1 SF + 1 SF + 1 SF + 1 SF + 1 SF +

1 Helper 1 Helper 1 Helper 1 Helper 1 Helper

1 Carpenter + 1 Helper 1 Carpenter + 1 Helper 1 Carpenter + 1 Helper