CONSTRUCTION SITE LAYOUT LEGEND FENCE FENCE (EXISTING) EXCAVATION ROUTE
FOUNDATION CONSTRUCTION RE BARWORKS & FORMWORKS Initial rebar works & formworks to start as excavation progresses towards Area 1 going to Area 3.
DIRECTION OF EXCAVATION
AREA 2
AREA 1
FOUNDATION CONCRETING
READY MIX CONCRETE WILL BE FROM FOUR SOURCE AROUND METRO MANILA.
CONCRETE
WILL BE PLACED TO THE SITE BY CRANE & BUCKET
& DIRECT POURING FOR FOUNDATION.
14 MONTHS CONCRETING SCHEDULE. AVERAGE POURING PER WEEK OF 450 CU. M.
Concreting
of footings & columns shall be by direct pouring,and backed up by Mobile Crane & Bucket.
BASEMENT
COLUMN CONSTRUCTION
RE BARWORKS & FORMWORKS After pouring of footing, initial rebar works & formworks for column will start at Tower D1 & D2 as construction of footing progresses towards Tower E1 going to Tower E2
AREA 1
AREA 2
CONCRETE WORKS Upon concreting operation of columns we will use Crane & Bucket system.
COLUMNS: Completion
dates of Concreting works: 3-LEVEL BASEMENT/FOUNDATION