Construction Activities and Process

August 18, 2017 | Author: J.j. Hayashi | Category: Deep Foundation, Concrete, Plumbing, Tile, Carpentry
Share Embed Donate


Short Description

Download Construction Activities and Process...

Description

Site preparation Survey work setting out Earthwork

Roof Slab 1 week 1 week 1-2 weeks

Foundation Pile pile cap Stump Ground Beam

3 weeks 2 weeks 2 weeks 2 weeks

Ground Floor Slab Column Beam Staircase wall plastering

2 weeks 2 weeks 2 weeks 2 weeks 2 weeks 2 weeks

First Floor Slab Column Beam Staircase wall plastering

2 weeks 2 weeks 2 weeks 2 weeks 2 weeks 2 weeks

Second Floor Slab Column Beam Staircase wall plastering

2 weeks 2 weeks 2 weeks 2 weeks 2 weeks 2 weeks

Utility Electrical Supply Water Supply

1 week 1 week

Door and Windows

Total: 2 week

Finishes 1st floor Kitchen Plumbing Plastering interiors 1st floor Plastering Interiors 2nd floor Skidding floors Painting - first coat Painting - second coat Sanitary fitting of bathroom and kitchen Electrical fitting

1 week 2 week 1 week 2 week 2 week

1 week 1 week Total 57 week

1|Page

WEEK 1 Activity 1: Site survey Duration: 7 days Materials: Equipment:Skilled Workers: Backhoe Loader Operator(1), General workers(4), Lorry driver(1) Technical Information: Analysis is done to the construction site by surveyor and further planning and advices to the site for construction preparation and development. Activity 2: Mobilization Duration: 2-3 days Materials: Machineries Equipment: Lorries(2), mobile crane(1), backhoe loaders(1), Hydraulic Piling Hammer(1), excavator(1), compactor (1), boring machine(1) Skilled Workers: lorry drivers(2), excavator operator(1), backhoe loader operator(1), Hydraulic Piling Hammer operator(1), compactor operators (1), boring machine operator(1) Technical Information: Machineries required is delivered to the site and wait for job to be executed.

Activity 3: Site Clearing Duration: 7 days Materials: Equipment: Backhoe Loader, chainsaw, lorry truck (carry earth & plants away) Skilled Workers: Backhoe Loader Operator(1), General workers(4), Lorry driver(1) Technical Information: Excavation of unfavorable soil and substances such as stones and tree barks. Initial leveling is done for the preparation of earthwork.

2|Page

WEEK 2

Activity 1: Hoarding (setting out), staking (plan boundary) Duration: 5 days Materials: blue metal decks, nails, wooden pegs, planks, stakes, Builder’s line Equipment: hammer, measuring tape, theodolite, Dummy level, construction sign board Skilled Workers: quantity surveyor (2), general workers (4) Technical Information: Boundary of the construction site is precisely measured and borders the site where the construction takes place. The site is marked with gridlines with a setback of 20 feet from the road and 10 feet for the porch according to UBBL and the location of the pile is marked.

Activity 2: Earthwork Duration: 7 days Materials: Equipment: excavator, compactor Skilled Workers: Excavator Operator (1), Compactor Operator (1) Technical Information: Removal of top soil and land leveling. The land is excavated to around 300mm of the top soil. Keep away or stored well for reuse due to its high water retentive characteristic.

3|Page

WEEK 3 Activity 1: Earthwork (continued) Duration: 7 days (continued from last week) Materials: Equipment: excavator, compactor Skilled Workers: Excavator Operator (1), Compactor Operator (1) Technical information: Removal of top soil and land leveling. The land is excavated to around 300mm of the top soil. Keep away or stored well for reuse due to its high water retentive characteristic Activity 2: Piling (Grid 13- Grid 15) Duration: 10-14 days Materials: Reinforced concrete piles, Concrete Grade 30, Reinforcement, wooden formworks Equipment: Hydraulic Piling Hammer(1), Rebar Bending machine(1), Boring Machine(1), cement concrete mixer (1), hacker (1) Skilled Workers: Hydraulic Piling Hammer Operator (1), Boring Machine Operator (1), Rebar Bender (1), General construction workers (6) Technical Information: The depth/length of the piles is depending on the soil condition based on the soil test, after that the engineers will decide the pile length to fit the soil condition of the site, based on the result of the test. Difference in height of the piles will be cut below cap using hacker. The rebar connected to the piles are then removed and left for the joining of capping reinforcement. Soil specimen is taken for soil test experiment to determine the length of the pile. The pile integrity test (Load test) is done to determine the strength to support the load.

4|Page

Week 4 Activity 1: Piling (Grid 8 - Grid 12) Duration: 10-14 days Materials: Reinforced concrete piles, Concrete Grade 30, Reinforcement, wooden formworks Equipment: Hydraulic Piling Hammer(1), Rebar Bending machine(1), Boring Machine(1), cement concrete mixer (1) Skilled Workers: Hydraulic Piling Hammer Operator (1), Boring Machine Operator (1), Rebar Bender (1), General construction workers (6) Technical Information: The depth/length of the piles is depending on the soil condition based on the soil test, after that the engineers will decide the pile length to fit the soil condition of the site, based on the result of the test. Difference in height of the piles will be cut below cap using hacker. The rebar connected to the piles are then removed and left for the joining of capping reinforcement. Soil specimen is taken for soil test experiment to determine the length of the pile. The pile integrity test (Load test) is done to determine the strength to support the load.

5|Page

Week 5 Activity 1: Leveling of Piles before capping Duration: 3 days Materials: Reinforced concrete piles, Concrete Grade 30, Reinforcement, wooden formworks Equipment: Hydraulic Piling Hammer(1), Rebar Bending machine(1), Boring Machine(1), cement concrete mixer (1) Skilled Workers: Hydraulic Piling Hammer Operator (1), Boring Machine Operator (1), Rebar Bender (1), General construction workers (6) Technical Information: When the piling is penetrated into the soil, the piles are in different height. The piles need to be cut before cap by using hacker. The rebar are removed and then the capping reinforcement are applied.

Activity 2: Pile capping Duration: 7 -14 days Materials: Reinforced concrete piles, Concrete Grade 30, Reinforcement, wooden formworks Equipment: Hydraulic Piling Hammer(1), Rebar Bending machine(1), Boring Machine(1), cement concrete mixer (1) Skilled Workers: Hydraulic Piling Hammer Operator (1), Boring Machine Operator (1), Rebar Bender (1), General construction workers (6) Technical Information: pile caps takes around 2 weeks to reach its maximum strength, but usually it can be done after it is left curing for about a week. Stumping can be constructed around that time.

6|Page

Week 6 Activity 1: Stump from Pile caps Duration:7 days-14 days Materials: Concrete Grade 30, reinforcements, timber formworks. Equipment: Concrete Vibrator(1), Rebar bending machine(1), tablesaw(1) Skilled Workers: Land Surveyor (1), Carpenter(2), Bar Bender (1), General worker (2) Technical Information: After pilings , the land surveyor will identity of the height required of the stumps and thereafter construct the stumps based on the data. Steel rebar are bent into cage form, with starter bar protruding upward to connect for latter construction of columns. Constructed the same way as the pile capping, the stumps are left for curing in order to achieve its required structural strength before the construction of the beams. It is left to cure for a week.

7|Page

WEEK 7 Activity 1: Ground Beam (Grid 13-Grid 17) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical information: Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting form and left for curing around a week time.

8|Page

WEEK 8 Activity 1: Ground Beam (Grid 8-Grid 13) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical information: Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting form and left for curing around a week time.

9|Page

Week 9 Activity 1: Ground floor slab (grid 12- grid 17) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beam, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting form and left for curing around a week time. DPM is laid on the concrete and screeded with long even plank.

10 | P a g e

Week 10 Activity 1: Ground floor slab (grid 8 - 12 ,continued from the first ) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beam, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting form and left for curing around a week time. DPM is laid on the concrete and screeded with long even plank.

11 | P a g e

Week 11 Activity 1: Ground Floor Columns (Grid 12 – Grid 15) Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: Same as the construction of beams, the formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time.

12 | P a g e

Week 12 Activity 1: Ground Floor Columns (Grid 8-Grid 11) Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: Same as the construction of beams, the formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time. Activity 2: First Floor Beam (Grid 12- Grid 17) , first half Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: The formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time.

13 | P a g e

Week 13 Activity 2: First Floor Beam (Grid 8 - Grid 12) , second half Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: The formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time.

14 | P a g e

Week 14 Activity 1: First Floor Slab (Grid 13-grid 17) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beams, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting, screeded with plank and then left for curing around a week time. A layer of protection is laid on top of the concrete during curing.

15 | P a g e

Week 15 Activity 1: First Floor Slab ( second half floor) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beams, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting, screeded with plank and then left for curing around a week time. A layer of protection is laid on top of the concrete during curing.

16 | P a g e

Week 16 Activity 1: first floor column (grid 12-grid 17), first half Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: Same as the construction of beams, the formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time. Activity 2: Ground Floor Staircase (to level 1) Duration: 8-14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), spirit level. Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3) Technical Information: The formworks of the stairs is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time. A concrete test is taken to check the strength of the casting after it was left to cure for a week.

17 | P a g e

Week 17 Activity 1: first floor column (grid 8-grid 12), second half Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: Same as the construction of beams, the formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time.

Technical Information: The formworks of the stairs is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time. A concrete test is taken to check the strength of the casting after it was left to cure for a week.

Activity 2: Second Floor Beam (Grid 12- Grid 17) , first half Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: The formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time. Activity 3: Ground Floor Staircase (to level 1, continued) Duration: 8-14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), spirit level. Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3) 18 | P a g e

Week 18 Activity 1: Second Floor Beam (Grid 8- Grid 12) , second half Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: The formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time.

19 | P a g e

Week 19 Activity 1: Second Floor Slab (first half) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beams, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting, screeded with plank and then left for curing around a week time. A layer of protection is laid on top of the concrete during curing.

20 | P a g e

Week 20 Activity 1: Second Floor Slab (second half) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beams, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting, screeded with plank and then left for curing around a week time. A layer of protection is laid on top of the concrete during curing.

21 | P a g e

Week 21 Activity 1: Second floor column (grid 8-grid 13) Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: Same as the construction of beams, the formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time.

Activity 2: First Floor Staircase (to level 2) Duration: 8-14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), spirit level. Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3) Technical Information: The formworks of the stairs is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time. A concrete test is taken to check the strength of the casting after it was left to cure for a week.

22 | P a g e

Week 22 Activity 1: Roof floor Beams (Grid 8- Grid 13) , All floor Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: The formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time.

23 | P a g e

Week 23 Activity 1: third floor Slab (all floor) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beams, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting, screeded with plank and then left for curing around a week time. A layer of protection is laid on top of the concrete during curing.

24 | P a g e

WEEK 24 Activity 1: brickwalls Ground Level (Grid 3- 4) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.

25 | P a g e

WEEK 25 Activity 1: brickwalls Ground Level (Grid 4-5) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.

26 | P a g e

Week 26 Activity 1: brickwalls Ground Level (Grid 5-6) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.

27 | P a g e

Week 27 Activity 1: Brickwall First Level (Grid 3-4) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.

28 | P a g e

Week 28 Activity 1: Brickwall First Level (Grid 4-5) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.

29 | P a g e

Week 29 Activity 1: Brickwall First Level (Grid 4-5) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.

30 | P a g e

Week 30

Activity 1: Brickwall Second Level (Grid 3-4a) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.

31 | P a g e

Week 31 Activity 1: Brickwall Second Level (Grid 4a-5) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.

32 | P a g e

Week 32 Activity 1: Brickwall Second Level (Grid 13 -17) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls. Activitity 2: Façade roof slab Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beam, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting form and left for curing around a week time. DPM is laid on the concrete and screeded with long even plank.

33 | P a g e

Week 33

Week 34

Activity 1: Framing (ground floor) Durations: 7 days Materials: Openings wooden frame (for door and windows) Equipment: Spirit level, Measuring tape Skilled Workers: General Workers (4) Technical Information: The opening frames are constructed in position and align after the brick wall is done. Architrave is added after the door/window frame is added.

Activity 1: Framing (First floor) Durations: 7 days Materials: Openings wooden frame (for door and windows) Equipment: Spirit level, Measuring tape Skilled Workers: General Workers (4) Technical Information: The opening frames are constructed in position and align after the brick wall is done. Architrave is added after the door/window frame is added.

Activity 2: Incoming Electrical Circuit Supply Installation Duration: 10-14 days Materials: Copper Cables (different sizes), Kilowatt hour meter Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Skilled Workers: Electric Technician (2), Plumbers (2) Technical Information: Incoming electricity cables are brought into the house and connected to a circuit box in the house to facilitate the plumbing works later on.

Activity 2: Incoming Electrical Circuit Supply Installation Duration: 10-14 days (continued) Materials: Copper Cables (different sizes), Kilowatt hour meter Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Skilled Workers: Electric Technician (2), Plumbers (2) Technical Information: Incoming electricity cables are brought into the house and connected to a circuit box in the house to facilitate the plumbing works later on.

34 | P a g e

Week 35 Activity 1: Framing (Second floor) Durations: 7 days Materials: Openings wooden frame (for door and windows) Equipment: Spirit level, Measuring tape Skilled Workers: General Workers (4) Technical Information: The opening frames are constructed in position and align after the brick wall is done. Architrave is added after the door/window frame is added.

Activity 2: Ground Floor Plumbing (First Fix) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electricians(2), Plumbers (2) Technical Information: Technicians will determine the location of the sockets according to the engineering blue print. The brick wall is hacked to accommodate the wiring pipe from the top to the ground according UBBL requirements. The wall sockets will be installed after the wiring is done.

35 | P a g e

Week 36 Activity 1: First Floor Plumbing (First Fix) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electricians(2), Plumbers (2) Technical Information: Technicians will determine the location of the sockets according to the engineering blue print. The brick wall is hacked to accommodate the wiring pipe from the top to the ground according UBBL requirements. The wall sockets will be installed after the wiring is done.

Week 37 Activity 1: First Floor Plumbing (First Fix) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electricians(2), Plumbers (2) Technical Information: Technicians will determine the location of the sockets according to the engineering blue print. The brick wall is hacked to accommodate the wiring pipe from the top to the ground according UBBL requirements. The wall sockets will be installed after the wiring is done.

Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electricians(2), Plumbers (2) Technical Information: Technicians will determine the location of the sockets according to the engineering blue print. The brick wall is hacked to accommodate the wiring pipe from the top to the ground according UBBL requirements. The wall sockets will be installed after the wiring is done.

Activity 3: Plumbing (Sanitary and Kitchen) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electricians(2), Plumbers (2) Technical Information: Technicians will determine the location of the sockets according to the engineering blue print. The brick wall is hacked to accommodate the wiring pipe from the top to the ground according UBBL requirements. The wall sockets will be installed after the wiring is done.

Activity 2: Second Floor Plumbing (First Fix) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box 36 | P a g e

Week 38 Activity 1: Plumbing (Sanitary and Kitchen) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electricians(2), Plumbers (2) Technical Information: Technicians will determine the location of the sockets according to the engineering blue print. The brick wall is hacked to accommodate the wiring pipe from the top to the ground according UBBL requirements. The wall sockets will be installed after the wiring is done.

Week 39 Activity 1: Ground floor Wall Plastering (Grid 1-Grid 3) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The first coating thickness is around 1/2 to 3/4 inches while the finishing coat will be around 3/16 inches thick. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor. 37 | P a g e

Week 40 Activity 1: Ground floor wall plastering (Grid 4-4a) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The first coating thickness is around 1/2 to 3/4 inches while the finishing coat will be around 3/16 inches thick. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor.

38 | P a g e

Week 41 Activity 1: Ground floor plastering (Grid 4a-6) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The first coating thickness is around 1/2 to 3/4 inches while the finishing coat will be around 3/16 inches thick. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor. Activity 2: First floor plastering (Grid 1- Grid 4) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor.

39 | P a g e

Week 42 Activity 1: First floor plastering (Grid 4- Grid 4a) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The first coating thickness is around 1/2 to 3/4 inches while the finishing coat will be around 3/16 inches thick. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor.

40 | P a g e

Week 43 Activity 1: First floor plastering (Grid 4a-6) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor. Activity 2: Second floor plastering (Grid 1-Grid 4) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor.

41 | P a g e

Activity 3: Ground Floor Tiling (Grid 13- Grid 17) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.

42 | P a g e

Week 44 Activity 1: second floor plastering (Grid 4-4b) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The first coating thickness is around 1/2 to 3/4 inches while the finishing coat will be around 3/16 inches thick. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor.

43 | P a g e

Activity 2: Ground Floor Tiling (Grid 10-13) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.

44 | P a g e

Week 45 Activity 1: Second floor plastering (Grid 4b-6) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The first coating thickness is around 1/2 to 3/4 inches while the finishing coat will be around 3/16 inches thick. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor.

45 | P a g e

Activity 2: Ground Floor Tiling (Grid 8- Grid 10) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.

46 | P a g e

Activity 3: First Floor Tiling (Grid 14-17) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.

47 | P a g e

Week 46 Activity 1: First Floor Tiling (Grid 10-14) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.

48 | P a g e

Week 47 Activity 1: First Floor Tiling (Grid 8-10) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.

49 | P a g e

Activity 2 : Second Floor Tiling (Grid 10 – Grid 13) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.

50 | P a g e

Week 48 Activity 1: Second Floor Tiling (Grid 8- Grid 10) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.

51 | P a g e

Week 49

Week 50:

Activity 1: Finishing – undercoat (Ground floor) Duration: 21 days Materials: Wall Sealer Equipment: Edgers, groovers, screed plank, Paint brushes, Point rollers Skilled Worker: Painter (5) Technical Information: Sealer is required to seal the holes, hairline cracks of the walls. The walls are needed to seal to prevent the drywall from absorbing the moisture and the paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain.

Activity 1: Finishing – Undercoat (First floor) Duration: 21 days Materials: Wall Sealer Equipment: Edgers, groovers,plank, Paint brushes, Point rollers Skilled Worker: Painter (5) Technical Information: Sealer is required to seal the holes, hairline cracks of the walls. The walls are needed to seal to prevent the drywall from absorbing the moisture and the paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain. Activity 2: Painting – Uppercoat (Ground floor) Duration: 14 days Materials: Paint Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Painting for finishing should be done after the plastering and undercoating are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few layers for better surface finishes.

52 | P a g e

Week 51 Activity 1: Finishing – Undercoat (Second floor) Duration: 21 days Materials: Wall Sealer Equipment: Edgers, groovers,plank, Paint brushes, Point rollers Skilled Worker: Painter (5) Technical Information: Sealer is required to seal the holes, hairline cracks of the walls. The walls are needed to seal to prevent the drywall from absorbing the moisture and the paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain. Activity 2: Painting – First coat (First Floor) Duration: 14 days Materials: Paint Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Painting for finishing should be done after the plastering and undercoating are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few layers for better surface finishes.

53 | P a g e

Week 52 Activity 1: Painting – First coat (Second Floor) Duration: 14 days Materials: Paint Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Painting for finishing should be done after the plastering and undercoating are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few layers for better surface finishes.

54 | P a g e

Week 53 Activity 1: Doors, Windows and Screens installation Durations: 10-14 days Materials: precast aluminum window frames, doors, glass windows panels, door frames, pre-manufactured wooden,wooden crossed screen , screws, sealer Equipment: Bolts and Nuts, Screwdriver and related toolkit. Skilled worker: General worker (4) Technical information: The doors and windows are then installed to the walls, replacing the temporary frames and secured with screws and sealer.

55 | P a g e

Week 54 Activity 1: Doors, Windows and Screens installation Durations: 10-14 days (continued) Materials: precast aluminum window frames, doors, glass windows panels, door frames, pre-manufactured wooden,wooden crossed screen , screws, sealer Equipment: Bolts and Nuts, Screwdriver and related toolkit. Skilled worker: General worker (4) Technical information: The doors and windows are then installed to the walls, replacing the temporary frames and secured with screws and sealer. Prefabricated screen is secured with fixtures and nut onto the walls.

Activity 2: Electrical & Sanitary fittings Durations: 14 days Materials: Wall sockets, Wall plugs and bathroom porcelain appliances Equipment: Bolts and Nuts, Screwdriver and related toolkit. Skilled worker: General worker (4) Technical information: Standard electrical appliances are then fixed during the last phase.

56 | P a g e

Week 55

Week 57

Activity 1: Pavings Duration: 10-15 days Materials: paving stones, bricks, Concrete Grade 30, reinforcements, timber formworks,plank Equipment: wheel barrow, Concrete Mixer(1), (1), table saw Skilled Workers: general workers (4) Technical information: Paving stones to be laid on the soil as pavement of walkway, parking, and garden.

Activity 1: Grass turfing – External work Duration: 7 days Materials: lawn turf rolls (depends on the size of garden), bricks Equipment: wheel barrow, gardening tool kits, water pipes Skilled Workers: lawn turf layers(2), general workers (2) Technical information: Soil preparation is done before laying the rolls of grass turf on the soil surfaces. Excavated soil can be reused as the base of the courtyard. Loose stones and building rubble will prevent the turves roots from making contact with the soil and could make the turf die in patches. The top soil should then be thoroughly rotivated down to about the first 6 inches to aerate it properly. It is then raked level and gently treaded down.

Week 56 Activity 1: Pavings Duration: 10-15 days (continued) Materials: paving stones, bricks, Concrete Grade 30, reinforcements, timber formworks,plank Equipment: wheel barrow, Concrete Mixer(1), (1), table saw Skilled Workers: general workers (4) Technical information: Paving stones to be laid on the soil as pavement of walkway, parking, and garden.

57 | P a g e

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF