Concrete Weight Coating

Share Embed Donate


Short Description

ghbnmyu...

Description

PETRONAS CARIGALI SDN BHD 

 

PROVISION OF FRONT END ENGINEERING DESIGN (FEED) AND  ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION &  COMMISSIONING (EPCIC) OF SK316 DEVELOPMENT PROJECT 

 

(CONTRACT NO. CHO/2012/D316/1000)  TABLE OF CONTENT  1 

PROJECT INTRODUCTION ............................................................................................................ 5 

1.1 

SCOPE OF DOCUMENT ....................................................................................................................... 7 

1.2 

DEFINITION ......................................................................................................................................... 7 

1.3 

ABBREVIATION ................................................................................................................................... 7 



REFERENCES ................................................................................................................................ 8 

2.1 

PROJECT DOCUMENTS ....................................................................................................................... 8 

2.2 

COMPANY STANDARDS ...................................................................................................................... 8 

2.3 

CODES AND STANDARDS .................................................................................................................... 8 

2.4 

SYSTEM OF UNITS ............................................................................................................................... 9 



GENERAL REQUIREMENTS ......................................................................................................... 10 



CONCRETE COATING MATERIALS .............................................................................................. 11 

4.1 

CEMENT ............................................................................................................................................ 11 

4.2 

AGGREGATES .................................................................................................................................... 11 

4.3 

WATER .............................................................................................................................................. 12 

4.4 

ADDITIVES ......................................................................................................................................... 12 

4.5 

REINFORCING STEEL ......................................................................................................................... 12 

4.6 

WELDED STEEL WIRE MESH.............................................................................................................. 13 

4.7 

STEEL CAGE TYPE .............................................................................................................................. 13 



RECEIPT, HANDLING AND STORAGE OF BARE PIPES ................................................................... 14 



CONCRETE COATING APPLICATION ........................................................................................... 15 

6.1 

VISUAL AND HOLIDAY INSPECTION OF 3‐LAYER PE COATED PIPES ................................................. 15 

6.2 

PLACEMENT OF REINFORCEMENT STEEL ......................................................................................... 15 



APPLICATION OF COATING MATERIALS ..................................................................................... 16 

7.1 

PREPARATION OF THE CUTBACK AREA ............................................................................................ 16 

7.2 

FINISHING OPERATIONS WITHIN CONCRETE COATING PLANT ........................................................ 16 

7.3 

CURING ............................................................................................................................................. 17 

7.3.1 

WATER CURING ............................................................................................................................... 17 

7.3.2 

STEAM CURING ................................................................................................................................ 18 

7.3.3 

CURING BY SEALING COMPOUNDS ................................................................................................. 18 

Page 2 of 50 

Area  05  File 

 

Loc.  SSPL 

Typ.  SPC 

Disc.  U 

05SSPLSPCU00050.doc 

No.  0005 

Rev.  0 

PETRONAS CARIGALI SDN BHD 

 

PROVISION OF FRONT END ENGINEERING DESIGN (FEED) AND  ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION &  COMMISSIONING (EPCIC) OF SK316 DEVELOPMENT PROJECT 

 

(CONTRACT NO. CHO/2012/D316/1000)  7.3.4 

CURING UNDER POLYETHYLENE WRAPPING ................................................................................... 18 

7.3.5 

FOG CURING .................................................................................................................................... 19 



INSPECTION AND TESTING ........................................................................................................ 20 

8.1 

STACKING OF 3‐LAYER PE COATED PIPES ......................................................................................... 21 

8.2 

CONTROL, IDENTIFICATION AND SEGREGATION OF 3‐LAYER PE COATED PIPES ............................. 22 

8.3 

DELIVERY AND STORAGE OF CONCRETE COATING RAW MATERIALS .............................................. 22 

8.4 

TEST TO BE PERFORMED ON CONCRETE COATING MATERIAL UPON RECEIPT ............................... 23 

8.4.1 

SIEVE ANALYSIS AND CLEANLINESS CONTROL OF AGGREGATES .................................................... 23 

8.4.2 

STEEL REINFORCEMENT WIRES DIMENSIONAL CONTROL .............................................................. 23 

8.4.3 

MIXING WATER CHEMICAL ANALYSIS ............................................................................................. 23 

8.5 

VERIFICATION OF CALIBRATION OF THE TEST INSTRUMENTS ......................................................... 24 

8.5.1 

HOLIDAY DETECTOR ........................................................................................................................ 24 

8.5.2 

PIPE WEIGHING SCALES ................................................................................................................... 24 

8.6 

VISUAL AND HOLIDAY INSPECTION OF THE 3‐LAYER PE COATED PIPES .......................................... 24 

8.7 

CONCRETE COATING MIX CONTROL ................................................................................................ 25 

8.8 

CONCRETE COATING MIX TEMPERATURE MEASUREMENT ............................................................. 25 

8.9 

WATER‐CEMENT RATIO CHECK ........................................................................................................ 25 

8.10 

REINFORCING WIRE POSITION CONTROL ......................................................................................... 26 

8.11 

CONCRETE COATING APPLICATION CONTROL ................................................................................. 26 

8.12 

MEASUREMENT OF EXTERNAL DIAMETER OF APPLIED CONCRETE ................................................. 26 

8.13 

CUTBACK CONTROL .......................................................................................................................... 27 

8.14 

WEIGHING OF FRESHLY CONCRETE COATED PIPE............................................................................ 27 

8.15 

CALCULATION OF NEGATIVE BUOYANCY ......................................................................................... 27 

8.16 

VISUAL INSPECTION OF APPLIED CONCRETE .................................................................................... 28 

8.16.1 

SURFACE FALL‐OUTS (SPALLING) OF FRESHLY CONCRETE COATED PIPES ...................................... 29 

8.16.2 

CONCRETE COATING DAMAGES ON FRESH AND HARDENED CONCRETE ....................................... 29 

8.16.3 

CRACKS ............................................................................................................................................ 29 

8.17 

ELECTRICAL RESISTANCE BETWEEN STEEL REINFORCEMENT AND THE PIPE ................................... 30 

8.18 

CONTROL OF CURING PROCESS ....................................................................................................... 30 

8.19 

CONTROL OF STACKING OF PIPES DURING THE CURING PROCESS .................................................. 30 

Page 3 of 50 

Area  05  File 

 

Loc.  SSPL 

Typ.  SPC 

Disc.  U 

05SSPLSPCU00050.doc 

No.  0005 

Rev.  0 

PETRONAS CARIGALI SDN BHD 

 

PROVISION OF FRONT END ENGINEERING DESIGN (FEED) AND  ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION &  COMMISSIONING (EPCIC) OF SK316 DEVELOPMENT PROJECT 

 

(CONTRACT NO. CHO/2012/D316/1000)  8.20 

CONTROL OF MARKING ON CONCRETE COATED PIPES ................................................................... 30 

8.21 

CONTROL OF MARKING ON CONCRETE COATING REPAIR ............................................................... 31 

8.22 

DETERMINATION  OF  FACTOR  ALPHA  IN  THE  FORMULA  FOR  CALCULATION  OF  NEGATIVE  BUOYANCY ....................................................................................................................................... 31 

8.23 

COMPRESSION STRENGTH TEST CUBES ........................................................................................... 31 

8.24 

COMPRESSION STRENGTH CORE SAMPLES ...................................................................................... 32 

8.25 

DETERMINATION OF THE TIME FOR STACKING OF PIPES IN MORE THAN ONE LAYER ................... 33 

8.26 

WATER ABSORBTION TEST ............................................................................................................... 34 

8.27 

ADHESION BETWEEN THE 3‐LAYER PE COATING AND CONCRETE COATING ................................... 34 

8.28 

IMPACT TESTING .............................................................................................................................. 35 

8.29 

STACKING OF CURED CONCRETE COATED PIPES.............................................................................. 36 

8.30 

LOAD OUT INSPECTIONS .................................................................................................................. 37 



3‐LAYER PE COATING REPAIR .................................................................................................... 38 

10 

CONCRETE COATING REPAIR AND STRIPPING OF CONCRETE COATED PIPES .............................. 40 

11 

PIPE MARKING .......................................................................................................................... 42 

12 

STORAGE, HANDLING AND TRANSPORTATION OF CONCRETE COATED PIPES ............................ 43 

13 

DOCUMENTATION .................................................................................................................... 45 

13.1 

GENERAL REQUIREMENTS ................................................................................................................ 45 

13.2 

TECHNICAL DOCUMENTATION TO BE SUBMITTED DURING THE BIDDING PHASE .......................... 45 

13.3 

TECHNICAL  DOCUMENTS  TO  BE  SUBMITTED  AFTER  AWARD  OF  THE  CONTRACT  TO  SUBCONTRACTOR ............................................................................................................................ 46 

13.4 

FINAL TECHNICAL DOCUMENTATION .............................................................................................. 47 

13.5 

CONTENT OF PARTICULAR TECHNICAL DOCUMENTS ...................................................................... 48 

13.5.1 

CONCRETE COATING APPLICATION PROCEDURE ............................................................................ 48 

13.5.2 

INSPECTION AND TEST PLAN ........................................................................................................... 49 

13.5.3 

DAILY PRODUCTION REPORT ........................................................................................................... 49   

Page 4 of 50 

Area  05  File 

 

Loc.  SSPL 

Typ.  SPC 

Disc.  U 

05SSPLSPCU00050.doc 

No.  0005 

Rev.  0 

PETRONAS CARIGALI SDN BHD 

 

PROVISION OF FRONT END ENGINEERING DESIGN (FEED) AND  ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION &  COMMISSIONING (EPCIC) OF SK316 DEVELOPMENT PROJECT 

 

(CONTRACT NO. CHO/2012/D316/1000) 

1

PROJECT INTRODUCTION 

NC3 and NC8 are gas fields located in Block SK 316, approximately 180km North of Bintulu, Sarawak with  water depth ranging approx. between 70m – 105m. NC8 field is located approximately 7km South East on  NC3 field. The nearby riser facility E11RC is located approximately 80 km South West of NC3. The existing  trunk line connecting E11RC to shore TL 6 is available and provisioned for in this gas field development. The  locations of NC3, NC8 and nearby facilities are illustrated in Figure 1‐1 below. 

  Figure 1‐1 Location of Project  Gas from NC3 and NC8 fields are the main feed gas supplier into the PETRONAS LNG Complex Train 9 near  Bintulu  which  is  expected  to  be  ready  for  start‐up  in  December  2015.The  scope  demarcation  between  upstream and downstream facilities is as described below in Figure 1‐2. 

  Figure 1‐2 Upstream and Downstream Scope Demarcation 

Page 5 of 50 

Area  05  File 

 

Loc.  SSPL 

Typ.  SPC 

Disc.  U 

05SSPLSPCU00050.doc 

No.  0005 

Rev.  0 

PETRONAS CARIGALI SDN BHD 

 

PROVISION OF FRONT END ENGINEERING DESIGN (FEED) AND  ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION &  COMMISSIONING (EPCIC) OF SK316 DEVELOPMENT PROJECT 

 

(CONTRACT NO. CHO/2012/D316/1000)  The development of NC3 and NC8 fields is envisaged to be in complex‐type configuration. NC3 will become  a hub comprising of a Central Processing Platform (CPP) with living quarters and a bridge‐linked Wellhead  Platform (WHP). Another WHP is to be installed at NC8; it will be tied‐back to NC3 via an inter‐field subsea  pipeline.  Though  compression  may  not  be  required  at  the  beginning  of  production,  the  need  for  gas  compression is anticipated after approximately four (4) years. Hence the provision for future compression  facilities and mercury removal facilities shall be considered as part of this FEED work for the NC3 CPP. 

  Figure 1‐3 Overall Development Concept  A  new  subsea  pipeline  connecting  NC3  and  E11RC  will  be  installed  to  deliver  the  processed  gas  and  the  spiked dehydrated condensate. Due to incompatibility of this gas quality with the existing gas supply at the  riser, a dedicated manifold at E11RC may be required to accommodate this tie‐in. This is to ensure that the  gas from NC3 and NC8 fields do not contaminate the entire network to shore. As such, modification will be  required to convert the existing TL 6 to be dedicated for gas from NC3 and NC8.  The future trunk line (TL 7) may be required in the future should TL 6 no longer be fit for service.  The  processed  gas  and  dehydrated  condensate  will  be  separated  at  onshore  receiving  facilities  prior  to  being introduced into LNG Plant Train 9. 

Page 6 of 50 

Area  05  File 

 

Loc.  SSPL 

Typ.  SPC 

Disc.  U 

05SSPLSPCU00050.doc 

No.  0005 

Rev.  0 

PETRONAS CARIGALI SDN BHD 

 

PROVISION OF FRONT END ENGINEERING DESIGN (FEED) AND  ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION &  COMMISSIONING (EPCIC) OF SK316 DEVELOPMENT PROJECT 

 

(CONTRACT NO. CHO/2012/D316/1000) 

1.1 SCOPE OF DOCUMENT  The purpose of this document is to define the minimum requirements for concrete weight coating to be  used for the following offshore rigid pipeline in the SK316 Development Project:     32” Offshore pipeline from NC3 WHP to E11RC Platform   32” Offshore pipeline from E11RC Platform to Onshore Beach Valve Location   20” Offshore pipeline from NC8 WHP to NC3 WHP (Diameter to be confirmed)  1.2 DEFINITION  COMPANY 

PETRONAS Carigali Sdn Bhd 

CONTRACTOR 

SAIPEM 

SUBCONTRACTOR 

Party selected by COMPANY/CONTRACTOR responsible for  application  of  the  concrete  weight  coating  on  PROJECT  pipes  in  accordance  with  this  specification  and  other  contractual documents 

MANUFACTURER 

Supplier  of  the  raw  materials  or  inspection  and  testing  equipment required to perform the work 

PROJECT 

FEED  for  SK316  Facilities  ‐  Development  of  the  NC3  and  NC8 Gas Fields 

1.3

ABBREVIATION 

FBE 

Fusion Bonded Epoxy 

N/A 

Not Applicable 

No. 

Number 

OD 

Outside diameter (external pipe diameter) 

PQT 

Pre‐Qualification Test 

3LPE 

3‐Layer Polyethylene 

3LPP 

3‐Layer Polypropylene 

CWC 

Concrete Weight Coating 

Page 7 of 50 

Area  05  File 

 

Loc.  SSPL 

Typ.  SPC 

Disc.  U 

05SSPLSPCU00050.doc 

No.  0005 

Rev.  0 

PETRONAS CARIGALI SDN BHD 

 

PROVISION OF FRONT END ENGINEERING DESIGN (FEED) AND  ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION &  COMMISSIONING (EPCIC) OF SK316 DEVELOPMENT PROJECT 

 

(CONTRACT NO. CHO/2012/D316/1000) 

2

REFERENCES 

Unless otherwise stated, the latest issue of the below listed PTS COMPANY Specifications, Codes, Standards  and Regulations shall apply. Equivalent alternatives may be offered; these shall be identified and mutually  agreed on.   2.1

PROJECT DOCUMENTS 

DOCUMENT  

NAME 

/1/ 05‐SSPL‐BOD‐U‐0001  

Pipeline And Riser Design Basis 

/2/ TBC 

Input for Pipeline Study 

/3/ 05‐GEN‐BOD‐B‐0001 

Process Design Basis 

/4/ 05‐SSPL‐REP‐U‐0001 

Steady State Pipeline Simulation Report 

/5/ 05‐GEN‐BOD‐Z‐0002 

Corrosion Study Memorandum 

/6/ 05‐SSPL‐REP‐U‐0002 

Pipeline Transient Analysis Report 

/7/ 05‐SSPL‐REP‐U‐0003 

Pipeline Route Selection Report 

  2.2

  COMPANY STANDARDS 

DOCUMENT  

NAME 

/8/ 31.40.00.20  

Pipeline & Riser Engineering 

/9/ 31.40.30.30 

Concrete coating of linepipe 

2.3

CODES AND STANDARDS 

DOCUMENT  

NAME 

/10/ ISO 21809‐1 

Petroleum  and  Natural  Gas  Industries  ‐  External  Coatings for Buried or Submerged Pipelines Used in  Pipeline Transportation Systems ‐ Part 1: Polyolefin  Coatings (3‐Layer PE and 3‐Layer PP). 

/11/ BS EN 10288 

Steel  Tubes  and  Fittings  for  Onshore  and  Offshore  Pipelines  ‐  External  Two  Layer  Extruded  Polyethylene Based Coatings 

/12/ ASTM C 150 

Standard Specification for Portland cement 

/13/  ASTM C 33 

Standard Specification for Concrete Aggregates 

/14/ ASTM A 810‐01 

Standard  Specification  for  Zinc‐Coated  (Galvanized)  Steel Pipe Winding Mesh 

Page 8 of 50 

Area  05  File 

 

Loc.  SSPL 

Typ.  SPC 

Disc.  U 

05SSPLSPCU00050.doc 

No.  0005 

Rev.  0 

PETRONAS CARIGALI SDN BHD 

 

PROVISION OF FRONT END ENGINEERING DESIGN (FEED) AND  ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION &  COMMISSIONING (EPCIC) OF SK316 DEVELOPMENT PROJECT 

 

(CONTRACT NO. CHO/2012/D316/1000) 

/15/ ASTM A 615 M 

Standard  Specification  for  Deformed  and  Plain  Carbon Steel Bars for Concrete Reinforcement 

/16/ ASTM 185‐01 

Standard  Specification  for  Steel  Welded  Wire  Reinforcement, Plain, for Concrete 

/17/ ASTM A 82‐01 

Standard  Specification  for  Steel  Wire,  Plain,  for  Concrete Reinforcement 

/18/ ASTM C 309‐98 A 

Standard  Specification  for  Liquid  Membrane‐ Forming Compounds for Curing Concrete 

/19/ ASTM C 171 

Standard  Specification  for  Sheet  Materials  for  Curing Concrete 

/20/ ASTM C 39/C39 M‐01 

Standard  Test  Method  for  Compressive  Strength  of  Cylindrical Concrete Specimens 

/21/ ASTM C 617‐98 

Standard  Practice  for  Capping  Cylindrical  Concrete  Specimens 

/22/ BS EN 197‐1 

Cement  ‐  Part  1:  Composition,  Specifications  and  Conformity Criteria for Common Cements 

/23/ BS EN 1008 

Mixing  Water  for  Concrete  ‐  Specification  for  Sampling,  Testing  and  Assessing  the  Suitability  of  Water,  Including  Water  Recovered  from  Processes  in  the  Concrete  Industry,  as  Mixing  Water  for  Concrete 

/24/ BS 4482 

Cold  Reduced  Steel  Wire  for  the  Reinforcement  of  Concrete Products‐ Specification 

/25/ BS 4483 

Steel  Fabric  for  the  Reinforcement  of  Concrete  ‐  Specification 

/26/ BS EN 12390‐2 

Testing  Hardened  Concrete  ‐  Part  2:  Making  and  Curing Specimens for Strength Tests 

/27/ BS EN 12390‐3 

Testing  Hardened  Concrete  ‐  Part  3:  Compressive  Strength of test Specimens 

2.4

SYSTEM OF UNITS 

The  International  Unit  System  (SI)  shall  be  utilized  throughout  the  project,  unless  otherwise  highlighted.  Any conversion shall be provided in parenthesis where applicable.     

Page 9 of 50 

Area  05  File 

 

Loc.  SSPL 

Typ.  SPC 

Disc.  U 

05SSPLSPCU00050.doc 

No.  0005 

Rev.  0 

PETRONAS CARIGALI SDN BHD 

 

PROVISION OF FRONT END ENGINEERING DESIGN (FEED) AND  ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION &  COMMISSIONING (EPCIC) OF SK316 DEVELOPMENT PROJECT 

 

(CONTRACT NO. CHO/2012/D316/1000) 

3

GENERAL REQUIREMENTS 

For testing purposes specified in this Specification, the production shift shall be considered of maximum 12  hours  depending  on  the  SUBCONTRACTOR’s  internal  organization.  In  case  SUBCONTRACTOR  intends  to  work more than 12 hours per day, COMPANY/CONTRACTOR shall consider that the work is performed in  more than one shift and the relevant testing frequency shall be respected as per this Specification.  All SUBCONTRACTOR’s documents shall comply with the limitations of this Specification. SUBCONTRACTOR  shall promptly inform COMPANY/CONTRACTOR of any need to make changes to these documents, which  shall have to be specifically accepted by COMPANY, who has the right to require additional testing without  additional costs.  Any  technical  deviations  to  this  Specification  shall  be  obtained  by  SUBCONTRACTOR  only  through  a  concession request format. In any case it is not allowed to insert any deviation from this Specification in  any SUBCONTRACTOR’s document prior that this deviation has not been previously presented separately  to COMPANY/CONTRACTOR and approved in written by COMPANY/CONTRACTOR.  Concession  requests  require  COMPANY’s  review  and  approval  prior  to  implementation  of  the  proposed  changes.  Pipes  coated  by  implementing  the  technical  changes  prior  to  the  COMPANY’s  approval  shall  be  rejected.  Prior to the commencement of the production and during the production, COMPANY shall reserve the right  to perform audits in the SUBCONTRACTOR’s facilities.  COMPANY and COMPANY’s representatives shall be permitted by SUBCONTRACTOR  the unlimited access  to  all  SUBCONTRACTOR’s  facilities  related  to  the  SUBCONTRACTOR’s  scope  of  work  for  the  PROJECT  starting from the moment the work has been awarded to SUBCONTRACTOR  until SUBCONTRACTOR  has  completed all of the obligations related to his scope of work in the PROJECT.  It  is  mandatory  requirement  for  SUBCONTRACTOR’s  coating  facilities  that  all  of  the  inspection  activities  according to the action points specified in inspection and test plans can be performed by inspectors from  all  involved  Parties  in  safe  manner  for  all  personnel  involved  in  these  activities.  In  case  the  inspection  activities  cannot  be  safely  performed  for  all  persons  involved  in  inspection  (CONTRACTOR,  SUBCONTRACTOR’s,  COMPANY’s  and  Third  Party’s  personnel),  SUBCONTRACTOR    shall  stop  all  of  the  activities at that particular inspection point and shall organize the work space in a manner that all activities  can be performed in safe manner. All costs due to such stoppages shall be borne only by SUBCONTRACTOR. 

Page 10 of 50 

Area  05  File 

 

Loc.  SSPL 

Typ.  SPC 

Disc.  U 

05SSPLSPCU00050.doc 

No.  0005 

Rev.  0 

PETRONAS CARIGALI SDN BHD 

 

PROVISION OF FRONT END ENGINEERING DESIGN (FEED) AND  ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION &  COMMISSIONING (EPCIC) OF SK316 DEVELOPMENT PROJECT 

 

(CONTRACT NO. CHO/2012/D316/1000) 

4

CONCRETE COATING MATERIALS 

The concrete coating applied on line pipes shall have the following nominal dry and cured concrete density  of 3044 kg/m3.  4.1 CEMENT  Unless otherwise specified in the Purchase Order, all cement used for the preparation of the concrete shall  be “Portland Cement” conforming to the requirements of one of the following standards depending on the  availability at the location where the concrete coating application shall be carried out:  

ASTM C 150 Type II and V; 



MS 522 standard; 



BS EN 197‐1 standard. 

All  batches  of  cement  shall  be  supplied  to  SUBCONTRACTOR  with  test  certificate  stating  the  compliance  either  with  the  ASTM  C  150  (Type  II  and  V)  or  BS  12  or  EN  197‐1  standard  which  shall  then  SUBCONTRACTOR submit to COMPANY for review prior to its use.  The  certificates  must  be  presented  to  COMPANY’s  review  to  verify  that  also  the  following  mandatory  requirements are met:  

that the content of alkali is 
View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF