Comparisons between LNG Terminals
Short Description
Report III...
Description
Customer: Document Title:
Date of Issue:
The United States Department of Energy National Energy Technology Laboratory
24 April 2003
Report III: Comparisons Between LNG Receiving Conventional, Salt cavern Based, and “Energy Bridge®”
Terminals:
Doc # & Version:
Doc 07 r2.0
Page 1 of 7
Comparisons between LNG Receiving Terminals: Conventional, Salt cavern Based, and “Energy Bridge®”
BY MICHAEL M. MCCALL WILLIAM M. BISHOP D. BRAXTON SCHERZ
r 1.0
For client review
02/09/03
Version
Reason for Issue
Issue Date
Document Title: Comparisons Between LNG Receiving Terminals: Conventional, Salt cavern Based, and “Energy Bridge®”
BS
MM
Orig. Chk. Appr. Chk. Appr. CGI NETL
Review
Document No: CGI/DOE_DOC 07 DE-FC26-02NT41653
Filename: 41653R01
Customer: Document Title:
Date of Issue:
The United States Department of Energy National Energy Technology Laboratory Report III: Comparisons Between LNG Receiving Conventional, Salt cavern Based, and “Energy Bridge®”
24 April 2003 Terminals:
Doc # & Version:
Doc 07 r2.0
Page 2 of 7
TABLE OF CONTENTS
1. EXECUTIVE SUMMARY ..................................................................................................................................3 2. TYPICAL LNG TERMINALS ............................................................................................................................3 3. EL PASO’S ENERGY BRIDGE........................................................................................................................4 4. SUMMARY OF ESTIMATED CAPITAL, OPERATION, AND FUEL COSTS..................................................6
Filename: 41653R01
Customer: Document Title:
Date of Issue:
The United States Department of Energy National Energy Technology Laboratory Report III: Comparisons Between LNG Receiving Conventional, Salt cavern Based, and “Energy Bridge®”
24 April 2003 Terminals:
Doc # & Version:
Doc 07 r2.0
Page 3 of 7
1. EXECUTIVE SUMMARY The technologies in the LNG industry have remained essentially unchanged over the years. “Energy Bridge,” a notable exception developed by El Paso Global LNG Co., combines LNG shipping and regasification on a single ocean-going vessel. Energy Bridge because of its mobility, “zero footprint”, and offloading flexibility may have advantages in markets where spot trades command higher prices. The LNG spot market continues to grow, but long term baseload LNG sales contracts have yet to be eclipsed. Whether or not Energy Bridge realizes its true competitive advantage has yet to be confirmed. Five representative LNG terminals were evaluated to determine an indicative cost of service required to achieve a 15% IRR on each project. A summary review of the findings (Table 4.1) prepared for this Document 07, indicates that the Bishop Process Exchanger LNG terminals generate the lowest terminal fees required to achieve the 15% IRR condition. This is attributable to competitive CAPEX costs, very high sendout rates, excellent fuel efficiencies, and lower operating costs. 2. LNG TERMINALS – FIVE CASES Five generally defined LNG terminals were selected for the basis of this study. There were no attempts to “equalize” the terminals by establishing a base line capacity, or any other common element that might skew the results of the matrix. Rather, each terminal is based upon an actual or proposed LNG project. The Bishop Process Onshore and Offshore terminals in this section are representative also and are not to be confused with the onshore and offshore terminals in Task 2.0. Terminals in Task 2.0 are site specific and estimated costs reflect each terminal location. Terminal send-out is a product of design, and the results of the comparisons have been based on a 100% load factor for each project and unitized on a BTU basis. Regarding El Paso’s Energy Bridge®, there are no provisions for a land based receiving terminal. For cost comparison purposes the estimate for an LNG vessel of 138,000 m3 of membrane tank design was used. An LNG specific cost estimating model using factored analysis was chosen as a basis of the calculated results. LNG receiving terminals have many machinery items in common and the costs for these items remain common throughout the comparison. There are of course major differences in the methods used to store LNG, the design of the marine facility, and the methods used to vaporize LNG. These major differences are reflected in capital costs, fuel cost, and personnel required to staff the terminals. For the first case, an LNG terminal located on the Pacific Coast of the Americas (North or South) was selected. Pacific coast LNG sites typically share several major design similarities including, (1) the requirement for a breakwater and a long approach trestle to protect and access the LNG berth, and (2) large LNG storage tanks to allow for adequate reserve due to the long distances from LNG supplier (Asia in most cases) to the receiving terminal. These requirements generally increase the cost of the terminal as indicated in the following tables. An estimate of an LNG terminal located on the Atlantic coast of North America forms the basis of the second case. This terminal will serve as a baseload LNG receiving facility, and benefits from a good location directly adjacent to deep water. For this reason a short approach trestle connects the dock with the shore facility, and no breakwater is required. Storage can be optimized because there are several LNG supply terminals located within reasonable shipping distances from the receiving facility. Cases three and four reflect LNG receiving terminals based on the use of the Bishop Process Heat Exchanger (BPT) and use salt caverns for storage. A detailed discussion of the Onshore and Offshore BPT terminal is included in Task 2.0 of this study. El Paso’s Energy Bridge® concept represents the fifth case.
Filename: 41653R01
Customer: Document Title:
Date of Issue:
The United States Department of Energy National Energy Technology Laboratory Report III: Comparisons Between LNG Receiving Conventional, Salt cavern Based, and “Energy Bridge®”
24 April 2003 Terminals:
Doc # & Version:
Doc 07 r2.0
Page 4 of 7
3. EL PASO - ENERGY BRIDGE®
Fig. 3.1
The fifth LNG terminal used in the comparison is based on El Paso’s Energy Bridge concept. EL PASO’S ENERGY BRIDGE developed by El Paso Global LNG Co., combines LNG shipping and regasification on a single ocean-going vessel. Proven technologies are employed by Energy Bridge allowing natural gas to be delivered directly to coastal markets. With this new system, scheduled gas delivery from remote regions could take place on a baseload or seasonal basis, using highly reliable offshore moorings and subsea pipelines to shore. Figure 3.1 above is an artist’s rendering of what an EPEB vessel might look like. A new ship design is not required, simply modification of an existing LNG carrier. Shown are some of the major components, such as onboard vaporizers and a view of the turret with the docking buoy attached to the receiving housing. The EPEB inter-connection design uses the APL Submerged Turret Loading (APL) system, with a docking buoy that provides a single-point mooring system with high reliability for offshore LNG-vessel unloading. The APL system has been proven in actual conditions and under very severe conditions in the North Sea off the coast of Norway. Connections with the APL buoy have been made in seastates over 5 meters and operational loading has taken place on seastates over 13 meters. There are currently 19 APL buoys in service, used for traditional oil and gas
Filename: 41653R01
Customer: Document Title:
Date of Issue:
The United States Department of Energy National Energy Technology Laboratory Report III: Comparisons Between LNG Receiving Conventional, Salt cavern Based, and “Energy Bridge®”
24 April 2003 Terminals:
Doc # & Version:
Doc 07 r2.0
Page 5 of 7
production operation. Over 1,000 connections have been made to date in the North Sea with a 100% success rate. El Paso envisions a fleet of specially equipped EPEB vessels bringing LNG to market. Figure 3.2 shows the general system layout. Upon arrival in the terminal area, the EPEB ship connects to a submerged offloading system which moors the vessel and connects it to an offload pipeline. This takes place well offshore and
Fig. 3.2
typically over the horizon. Once connected to the offload pipeline, the ship begins onboard regasification to provide safe LNG conversion to vaporous natural gas at pressures up to 1,400 psi. Referring to Figure 3.2, the gas is sent through the offloading system and riser to a seabed pipeline that leads to an onshore customer’s facility, or a nearby as transmission pipeline. At conclusion of the transfer the ship releases the offloading system to its idle position safely beneath the ocean’s surface where it remains until the next ship arrives. Each 138,000 m3 tanker carries about 3 Bcf of gas and will typically off load in 7 to 10 days. At 100% load factor the vessel can discharge its cargo in about 5.5 days. Figure 3.3 shows how the system will look when gas is being offloaded. The APL system is suitable for water depths of 35 meters to well over 100 meters. Once the ship is connected to the mooring buoy, it freely weathervanes with the wind and the current, thus mitigating much of the stress on the mooring lines and anchors. Once connected send-out to shore can occur in seas of 10 to 11 m, providing for high reliability. The typical offshore gas installation have two offloading buoys and risers to accommodate simultaneous docking and undocking assuring continuous flow.
Filename: 41653R01
Customer: Document Title:
Date of Issue:
The United States Department of Energy National Energy Technology Laboratory Report III: Comparisons Between LNG Receiving Conventional, Salt cavern Based, and “Energy Bridge®”
24 April 2003 Terminals:
Doc # & Version:
Doc 07 r2.0
Page 6 of 7
A detailed review of the marketing aspects of this innovative design is beyond the scope of this study. However, general reactions to Energy Bridge and its comparison to the other four LNG terminal options will be assessed in the matrix of Doc 08 of this study Task.
Fig. 3.3
4. SUMMARY OF LNG TERMINAL ESTIMATED CAPITAL, OPERATION, AND FUEL COSTS LNG terminal estimated Operating and Maintenance costs are based on historical LNG operation and maintenance data. The major engineering firms estimate OPEX costs at 1.5% of the TIC capital cost of the terminal for the first year of operation and 1% thereafter. For the purposes of this study, CGI will use that assumption for all five terminal examples and average costs over a 20 year period. The O&M costs do not include fuel gas or imported power. The estimated fuel consumption of each terminal and fuel efficiencies have been derived from engineering studies listing the power requirements, or from fuel requirements published in existing tariffs. Table 4.1 includes a summary of all critical elements involved in the analysis, and it is understood that the results are indicative rather than actual. As the table indicates, the BPT LNG terminals due to competitive CAPEX costs, excellent fuel efficiencies, and lower operating costs generate the lowest terminal fees required to achieve the 15% IRR condition. The equipment list used to generate the factored analysis and the summary sheet of the financial model for each terminal is included in Doc 07 Attachment I. The following document (Doc 08) includes the matrix used to summarize the advantages and disadvantages of each LNG terminal design.
Filename: 41653R01
(percent of through-put
($/mmBtu)
500 182,500 194,727,500 3.75
67 202,906,294 1.04 2,079,790 6,610,000 0.045 0.85% 0.220
800 292,000 311,564,000 6.00
107 415,827,479 1.33 4,262,232 11,200,000 0.050 1.20% 0.250
0.094
0.33%
0.017
8,500,000
3,013,726
0.43
294,022,086
235
639,000 681,546,250 13.10
1750/3000 peak
Bishop Process/Salt Store
Offshore Terminal
0.090
0.33%
0.016
8,000,000
3,048,409
0.44
0.295
1.00%
0.046
5,600,000
2,944,502
1.54
287,268,472
64
235 297,405,735
175,200 186,938,400 3.60
480
Direct to Gas Pipeline
Energy Bridge
639,000 681,546,250 13.10
1750/3000 peak
Bishop Process/Salt Store
Onshore Process
Report III: Comparisons Between LNG Receiving Conventional, Salt cavern Based, and “Energy Bridge®”
Fee Required to Realize Project Pre-Tax IRR of 15%
Fuel Consumption
($USD/yr)
($/mmBtu)
(TIC $USD)
($USD/yr @ 3.00/mcf)
OPEX (O&M + Fuel) / Plant Capacity
Estimated Fuel Cost
Estimate O & M
TIC per Plant Capacity
Estimated Total Installed Cost
Maximum Cargoes per year
(mmBtu) Million Metric Tonnes per Anum
(m mcf)
(daily full design rate in mmcfd)
Est. Annual Sendout 100% load factor
Sendout
Atlantic North East
Traditional Terminal
Pacific Coast
Traditional Terminal
Document Title:
Cavern Terminals are ship limited
Customer:
The United States Department of Energy National Energy Technology Laboratory Date of Issue:
Terminals:
24 April 2003
Doc 07 r2.0
Doc # & Version:
Page 7 of 7
Table 4.1 – LNG Terminal Cost Comparison
Note : Table 4.1 references LNG terminals representative of geographic locations and as such do not refer specifically to the Pro-Forma estimates for the LNG Onshore and Offshore terminals presented in Task 2.0
Filename: 41653R01
PACIFIC COAST LNG TERMINAL PROFORMA ECONOMICS Project Summary SUMMARY FACILITY ASSUMPTIONS Facility Basis - Firm Service Cargos per Year LNG Discharge per Ship, cubic meters LNG LNG Btu content, Btu/scf Storage Working Gas Volume, Bcf Storage Base Gas Volume, Bcf
Pricing Throughput Fee, $/MmBtu Other Revenue - % of Terminal Throughput Rev. Terminal Energy Use Charge, % of throughput Assumed Henry Hub Index for initial year Gas Storage Net Revenue Realized $MM/year Other Assumptions Base Gas Price (Delivered), $/Mcf Base Gas Source ("Lease" or "Buy") Total Operations Cost, $M/Year - Labor & Maintenance, $M/Yr - Electrical Demand Charge, $M/Yr Management Overhead, $M/Year Property Taxes (assumed amount), $M/Yr Storage Site Lease Fee, $M/yr % Revenue Stream to Inflation Protect, %/yr General Inflation Rate Inflation applied to certain annual costs, %/yr Energy Use for Terminal ops., % of throughput Full storage cavern compression charge rate % of throughput requiring compression at cavern Project & Technology Rights Running Royalty, as % of Henry Hub index Project & License Upfront Payment, $MM
107 138,000 1067 16.00 7.30
0.250 0.0% 0.00% $3.50 $0.0
3.50 buy 2,499 2,299 200 360 4,000 500 100% 3.0% 1.5% 1.20% 0.00% 0%
Facility Costs, $ Marine Port Facilities LNG Vaporization & Process Terminal Utility System Storage Surface Facility Site Specific Misc Header Pipeline Engineering & Const. Mgmt. Project Acquisition & Tech. Rights Owner Costs, Permits, Misc. Financing Fees Contingency Total Facility Cost
FINANCIAL ASSUMPTIONS 50,910,255 74,108,000 28,288,700 166,070,000 31,423,797 0 19,674,248 50,000 7,191,583 21,048,045 56,133,750 454,898,378
LNG Terminal Project Metrics 100% Load Factor (based on 240 cargos/yr max) Reference Annual throughput, mcf/yr 291,076,745 Annual LNG Offloaded, BCF/yr 291 Reference throughput, million mmBtu/yr 310,578,887 Daily equivalent amount (mcf/day) 808,547 Tax Rates Federal, %/YR 35.0% State, %/YR 4.50% Blended Rate, %/Yr. 37.93% Property, %/YR, initial year/capital cost 0.88% Capital Gain Rate for Terminal Value 20% Depreciation Depreciation (Straight-Line or Accel) Straight-Line Depreciable Life, Years 20 Project Life, Years 20
0.00% based on mmBtu throughput 0
Financial Structure Sr. Debt Percent of Capital Jr. Debt Percent of Capital Equity Percent of Capital Senior Debt Term Junior Debt Term Base Gas Lease Carrying Cost, %/YR
% Capital 50.0% 0.0% 50.0% 20 5 6.75%
FINANCIAL RESULTS Cost of Capital Pretax WACC WACC Equity Return (assumed from above)
10.88% 9.60% 15.0%
Project Economics Project NPV@Pretax WACC, $M Project Pretax IRR NPV @ WACC (tax-effected), $M Project IRR (tax-effected)
218,660 15.7% 142,174 12.5%
Yr. 1 EBITDA $M/year Avg. EBITDA, Yrs 1-5, $M/year
$57,241 $61,059
Equity Returns, AFTER-Tax Equity NPV@ Assumed Equity Return, $M
Equity IRR (calculated) Debt Coverage Minimum EBITDA/Interest Coverage Minimum EBITDA/Debt Service
41,816 17.1% Pre-tax
3.7 2.7
Rate 6.75% 0.0% 15.0%
LNG Terminals Cost Comparison Equipment Summary Sheet Bare Equipment
Traditional Land Based Terminal West Coast w/Breakwater Capacity - 0.8 Bcfd Description
Cost ($M)
LNG STORAGE TANK 2 x (160,000 m3) 6.4 Bcf LNG Storage Tank Subtotal
62,000.0
Steel Concrete I/E & Piping Cost ($M) 27,280.0 27280
Installed Direct & Indirect Cost ($M)
Freight Spares Other Cost ($M)
54,684.0 54684
Taxes Duties Insurance Cost ($M)
1,364.0 1364
Contract Engineering (12%) Cost ($M)
Total Cost Cost ($M)
1639.3 1639.28
9835.7 9835.68
94,803 94,803
PROCESS VESSELS Recondenser, 9'ID x 45', 304 SS BOG Compressor Knock Out Drum 70 m3 HP Fuel Gas Knock Out Drum, 3 m3 HP Flare Knock Out Drum, 50 m3 Service Water Storage Tank, 20 m3 Diesel Storage Tank, 50 m3 Foam Tank, 4 m3 Process Vessels Subtotal
142.0 35.6 10.5 28.8 12.2 16.8 6.5 252.4
85.9 25.5 7.5 20.6 8.1 11.1 4.3 162.9
172.2 51.0 15.0 41.3 16.1 22.2 8.6 326.5
15.7 4.1 1.2 3.3 1.4 1.9 0.7 28.3
8.1 2.3 0.7 1.8 0.7 1.0 0.4 15.0
48.0 13.4 4.0 10.9 4.4 6.0 2.3 89.0
472 132 39 107 43 59 23 874.2
VAPORIZERS Open Rack Vaporizers, 170 ton/hr (3 each) Submerged Combustion Vaporizers, 170 Tons/hr (2 each) Shell & Tube Vaporizers Subtotal
5,940 1,736 0 7,676
4,574 1,337 0 5,911
9,168 2,680 0 11,848
703.9 205.7 0.0 910
397.2 116.1 0.0 513
2361.9 690.3 0.0 3,052
23,145 6,764 0 29,909
HEAT EXCHANGERS Standby glycol/fuel gas heater 127 kW HP knockout drum heater 20 kW Gaseous N2 Vaporizer 35 kW Gaseous N2 Vaporizer (Spare) 35 kW Liquid N2 Pressurization vaporizer 35 kW Liquid N2 Vaporizer 35 kW Heat Exchangers Subtotal
6.1 0.8 0.66 0.66 0.66 0.66 9.5
4.03 0.53 0.74 0.74 0.74 0.74 7.5
8.07 1.06 1.48 1.48 1.48 1.48 15.0
0.7 0.1 0.1 0.1 0.1 0.1 1.1
0.4 0.0 0.1 0.1 0.1 0.1 0.6
2.2 0.3 0.3 0.3 0.3 0.3 3.8
21 3 3 3 3 3 37.7
0
0
0
0
0
0
0
Pumps Subtotal
$640 $825 $452 15.00 7.10 17.40 203.70 2,160.20
668.8 862.1 472.3 21.5 10.2 24.9 213 2,273
1340.6 1728.2 946.8 43.0 20.4 49.9 426.7 4,556
84.6 109.1 59.8 2.3 1.1 2.6 26.9 286
53.4 68.8 37.7 1.6 0.8 1.9 17.0 181
317.9 409.8 224.5 9.5 4.5 11.1 101.2 1,079
3,105 4,003 2,193 93 44 108 988 10,534
Compressors Subtotal
800.00 1,000.00 2,200.00 4,000.00
440 550 1155 2,145
882 1102.5 2315.3 4,300
86.0 107.5 233.8 427
42.9 53.7 114.7 211
254.6 318.3 680.4 1,253
2,506 3,132 6,699 12,337
SEAWATER INTAKE SYSTEM (Incl Electrochlorination) Electrochlorination Unit, 12,000 m3/hr Seawater Intake Structure (12,000 m3/hr each) Seawater Outfall Structure (12,000 m3/hr each) Seawater Intake Screens (13,200 m3/hr each) Seawater Rotary Screens (13,200 m3/hr each) Seawater Intake System Subtotal
20 1,100 1,100 400 400 3,020
29 1150 1755 858 1078 4,869
57.33 2304 3517 1720 882 8,480
3.0 145.5 175.7 74.9 85.9 485
2.1 91.7 128.1 59.8 47.4 329
12.7 546.4 764.6 357.3 283.2 1,964
124 5,337 7,440 3,470 2,777 19,148
507
84 2,850 63.3 990.0 165.1 60.1 198.0 4,410.5
167.6 126.8 1,984.5 331.0 120.4 396.9 3,127.1
44.7 142.5 21.6 409.5 32.2 9.2 33.9 693.7
15.5 57.0 8.5 152.2 16.1 5.2 18.1 272.6
90.9 342.1 50.4 896.9 95.5 31.0 107.4 1,614.2
909 3,392 501 8,933 940 304 1,054 16,032.5
0 0 0 0 0
450.0 0.0 1,200.0 0.0 1650
180.0 341.0 480.0 0.0 1001
1080.0 2046.0 2880.0 0.0 6006
10,710 19,437 28,560 0 58707
WASTE HEAT RECOVERY Waste Heat Recovery Subtotal PUMPS First stage sendout pump, 416 m3/hr (intank) Second stage sendout pump, 325 m3/hr Seawater pump, 2187 m3/hr Sub combustion Vap. Overflow pump, 5hp Process Area Sump Pump, 10 hp, 5 m3/hr Service Water Pump, 5 hp, 57 m3/hr Firewater Pumps
COMPRESSORS BOG Compressors Ship Vapor Return Blower Ship Unloading Compressor
UTILITIES HP Flare, 415,000 kg/hr Electrical Switchgear & Power Distrib (5% of FC) Emergency Generator - Diesel Driven, 500 kW Gas Turbine Generator, 4 MW, Centaur 50 Instrument air compressor and drier, 100 scfm N2 Dewar for Terminal, Vac. insul. tank, 42 m3 Firewater Protection System (Foam Sys, dry powder, tanks) Utilities Subtotal MARINE FACILITIES - JETTY Topworks (Road/750 meter Trestle/Pipeway) Cryogenic Piping (I/E, piping w/ insulation) Berth (Mooring, Breasting Dolphins) Dredging Marine Facilities - Jetty Subtotal
230.0 4,500.0 299.8 78.0 300.0 5,914.4
9,000 17,050 24,000 50,050
MARINE FACILITIES - UNLOADING Unloading Arms Marine Facilities - Unloading Subtotal BREAKWATER Breakwater Subtotal
8,650 8,650
963 963
1930.6 1,931
0 0
60,000 60,000
0 0
740.2 740
236.1 236
1385.2 1,385
13,905 13,905
3,000 3,000
1,200 1,200
7,200 7,200
71,400 71,400
70.0 17.5 26.3 113.75
28.0 7.0 10.5 45.5
168.0 42.0 63.0 273
1,666 417 625 2707.25
2,850 2,850
142.5 143
57.0 57
342.1 342
3,392 3,392
12,000 0 $7,981 9000 28,981
600.0 0.0 399.1 450.0 1,449
240.0 0.0 159.6 180.0 580
1440.0 0.0 957.8 1080.0 3,478
14,280 0 9,498 10,710 34,488
NAVIGATIONAL AIDS (lighting and buoys) Navigational Aids Subtotal BUILDINGS Administration Office/Control Center Compressor Building (Included in cost of compressors) Warehouse/Maintenance Building, 10,000 ft2 Buildings Subtotal
1400 350 525 2275
SITE PREPARATION Site Preparation Subtotal BULKS Piping (exclud. trestle) Piling Insulation and Paint Electrical/Instrumentation Bulks Subtotal
3,000 3,000
REAL ESTATE Real Estate Subtotal OSBL INFRASTRUCTURE Includes access roads, bldgs, hospitals, stores, bridges OSBL Infrastructure Subtotal UNADJUSTED GRAND TOTAL CONTINGENCY 12% OF THE TOTAL ADJUSTED GRAND TOTAL
3,000 3,000
0 62,683
195,177
0 89,267
11,291
6,282
37,575
371,275 44,553 415,827
ATLANTIC COAST LNG TERMINAL PROFORMA ECONOMICS Project Summary SUMMARY FACILITY ASSUMPTIONS Facility Basis - Firm Service Cargos per Year LNG Discharge per Ship, cubic meters LNG LNG Btu content, Btu/scf Storage Working Gas Volume, Bcf Storage Base Gas Volume, Bcf
Pricing Throughput Fee, $/MmBtu Other Revenue - % of Terminal Throughput Rev. Terminal Energy Use Charge, % of throughput Assumed Henry Hub Index for initial year Gas Storage Net Revenue Realized $MM/year Other Assumptions Base Gas Price (Delivered), $/Mcf Base Gas Source ("Lease" or "Buy") Total Operations Cost, $M/Year - Labor & Maintenance, $M/Yr - Electrical Demand Charge, $M/Yr Management Overhead, $M/Year Property Taxes (assumed amount), $M/Yr Storage Site Lease Fee, $M/yr % Revenue Stream to Inflation Protect, %/yr General Inflation Rate Inflation applied to certain annual costs, %/yr Energy Use for Terminal ops., % of throughput Full storage cavern compression charge rate % of throughput requiring compression at cavern Project & Technology Rights Running Royalty, as % of Henry Hub index Project & License Upfront Payment, $MM
67 138,000 1067 16.00 7.30
0.220 0.0% 0.00% $3.50 $0.0
3.50 buy 2,499 2,299 200 360 4,000 500 100% 3.0% 1.5% 0.85% 0.00% 0%
Facility Costs, $ Marine Port Facilities LNG Vaporization & Process Terminal Utility System Storage Surface Facility Site Specific Misc Header Pipeline Engineering & Const. Mgmt. Project Acquisition & Tech. Rights Owner Costs, Permits, Misc. Financing Fees Contingency Total Facility Cost
FINANCIAL ASSUMPTIONS 50,910,255 48,250,000 28,288,700 57,000,000 1,116,097 0 11,634,948 50,000 7,191,583 11,133,903 30,142,500 245,717,986
LNG Terminal Project Metrics 100% Load Factor (based on 240 cargos/yr max) Reference Annual throughput, mcf/yr 182,263,008 Annual LNG Offloaded, BCF/yr 182 Reference throughput, million mmBtu/yr 194,474,630 Daily equivalent amount (mcf/day) 506,286 Tax Rates Federal, %/YR 35.0% State, %/YR 4.50% Blended Rate, %/Yr. 37.93% Property, %/YR, initial year/capital cost 1.63% Capital Gain Rate for Terminal Value 20% Depreciation Depreciation (Straight-Line or Accel) Straight-Line Depreciable Life, Years 20 Project Life, Years 20
0.00% based on mmBtu throughput 0
Financial Structure Sr. Debt Percent of Capital Jr. Debt Percent of Capital Equity Percent of Capital Senior Debt Term Junior Debt Term Base Gas Lease Carrying Cost, %/YR
% Capital 50.0% 0.0% 50.0% 20 5 6.75%
FINANCIAL RESULTS Cost of Capital Pretax WACC WACC Equity Return (assumed from above)
10.88% 9.60% 15.0%
Project Economics Project NPV@Pretax WACC, $M Project Pretax IRR NPV @ WACC (tax-effected), $M Project IRR (tax-effected)
108,531 15.3% 69,959 12.2%
Yr. 1 EBITDA $M/year Avg. EBITDA, Yrs 1-5, $M/year
$29,640 $31,751
Equity Returns, AFTER-Tax Equity NPV@ Assumed Equity Return, $M
Equity IRR (calculated) Debt Coverage Minimum EBITDA/Interest Coverage Minimum EBITDA/Debt Service
17,846 16.7% Pre-tax
3.6 2.6
Rate 6.75% 0.0% 15.0%
LNG Terminals Cost Comparison Equipment Summary Sheet Bare Equipment
Traditional Land Based Terminal East Coast no Breakwater reqd. Capacity - 0.5 Bcfd Description
Cost ($M)
LNG STORAGE TANK 2 x (125,000 m3) 5.0 Bcf LNG Storage Tank Subtotal
45,000.0
Steel Concrete I/E & Piping Cost ($M)
Installed Direct & Indirect Cost ($M)
19,800.0 19800
Freight Spares Other Cost ($M)
22,500.0 22500
Taxes Duties Insurance Cost ($M)
Contract Engineering (12%) Cost ($M)
Total Cost Cost ($M)
990.0 990
846.0 846
5076.0 5076
49,212 49,212
PROCESS VESSELS Recondenser, 9'ID x 45', 304 SS BOG Compressor Knock Out Drum 70 m3 HP Fuel Gas Knock Out Drum, 3 m3 HP Flare Knock Out Drum, 50 m3 Service Water Storage Tank, 20 m3 Diesel Storage Tank, 50 m3 Foam Tank, 4 m3 Process Vessels Subtotal
142.0 35.6 10.5 28.8 12.2 16.8 6.5 252.4
85.9 25.5 7.5 20.6 8.1 11.1 4.3 162.9
172.2 51.0 15.0 41.3 16.1 22.2 8.6 326.5
15.7 4.1 1.2 3.3 1.4 1.9 0.7 28.3
8.1 2.3 0.7 1.8 0.7 1.0 0.4 15.0
48.0 13.4 4.0 10.9 4.4 6.0 2.3 89.0
472 132 39 107 43 59 23 874.2
VAPORIZERS Open Rack Vaporizers, 168 ton/hr (3 each) Submerged Combustion Vaporizers, 170 ton/hr (1 each) Shell & Tube Vaporizers Subtotal
0.0 898.0 1,100.0 1,998
0.0 691.5 847.0 1,538
0.0 1,386.1 1,697.9 3,084
0.0 106.4 130.4 237
0.0 60.0 73.6 134
0.0 357.1 437.4 794
0 3,499 4,286 7,785
HEAT EXCHANGERS Standby glycol/fuel gas heater 127 kW HP knockout drum heater 20 kW Gaseous N2 Vaporizer 35 kW Gaseous N2 Vaporizer (Spare) 35 kW Liquid N2 Pressurization vaporizer 35 kW Liquid N2 Vaporizer 35 kW Heat Exchangers Subtotal
$6 $1 $1 $1 $1 $1 9.5
4.03 0.53 0.74 0.74 0.74 0.74 7.5
8.07 1.06 1.48 1.48 1.48 1.48 15.0
0.7 0.1 0.1 0.1 0.1 0.1 1.1
0.4 0.0 0.1 0.1 0.1 0.1 0.6
2.2 0.3 0.3 0.3 0.3 0.3 3.8
21 3 3 3 3 3 37.7
0
0
0
0
0
0
0
Pumps Subtotal
$640 $825 $452 $15 $7 $17 203.70 2,160.20
668.8 862.1 472.3 21.5 10.2 24.9 213 2,273
1340.6 1728.2 946.8 43.0 20.4 49.9 426.7 4,556
84.6 109.1 59.8 2.3 1.1 2.6 26.9 286
53.4 68.8 37.7 1.6 0.8 1.9 17.0 181
317.9 409.8 224.5 9.5 4.5 11.1 101.2 1,079
3,105 4,003 2,193 93 44 108 988 10,534
Compressors Subtotal
800.00 1,000.00 2,200.00 4,000.00
440 550 440 1,430
882 1102.5 2315.3 4,300
86.0 107.5 198.0 392
42.9 53.7 100.4 197
254.6 318.3 594.6 1,168
2,506 3,132 5,848 11,486
SEAWATER INTAKE SYSTEM (Incl Electrochlorination) Electrochlorination Unit, 12,000 m3/hr Seawater Intake Structure (12,000 m3/hr each) Seawater Outfall Structure (12,000 m3/hr each) Seawater Intake Screens (13,200 m3/hr each) Seawater Rotary Screens (13,200 m3/hr each) Seawater Intake System Subtotal
20 1,100 1,100 500 500 3,220
29 1150 1755 1073 1348 5,353
57.33 2304 3517 2150 2701 10,730
3.0 145.5 175.7 93.6 107.4 525
2.1 91.7 128.1 74.7 91.3 388
12.7 546.4 764.6 446.7 545.8 2,316
124 5,337 7,440 4,337 5,293 22,532
506.6
83.6 1,908.1 63.3 0.0 165.1 60.1 165.1 2,445.2
167.6 126.8 0.0 331.0 120.4 331.0 1,076.7
44.7 95.4 21.6 0.0 32.2 9.2 32.3 235.4
15.5 38.2 8.5 0.0 16.1 5.2 16.1 99.6
90.9 229.0 50.4 0.0 95.5 31.0 95.5 592.4
908.8 2,270.6 500.5 0.0 939.7 303.9 940.0 5,863.6
9,000.0 1,915.0 17,000.0 0.0 27,915.0
0.0 0.0 0.0 0.0 0.0
450.0 95.8 850.0 0.0 1,395.8
180.0 38.3 340.0 0.0 558.3
1,080.0 229.8 2,040.0 0.0 3,349.8
10,710.0 2,278.9 20,230.0 0.0 33,218.9
WASTE HEAT RECOVERY Waste Heat Recovery Subtotal PUMPS First stage sendout pump, 416 m3/hr (intank) Second stage sendout pump, 325 m3/hr Seawater pump, 2187 m3/hr Sub combustion Vap. Overflow pump, 5hp Process Area Sump Pump, 10 hp, 5 m3/hr Service Water Pump, 5 hp, 57 m3/hr Firewater Pumps
COMPRESSORS BOG Compressors Ship Vapor Return Blower Ship Unloading Compressor
UTILITIES HP Flare, 415,000 kg/hr Electrical Switchgear & Power Distrib (5% of FC) Emergency Generator - Diesel Driven, 500 kW Gas Turbine Generator Instrument air compressor and drier, 100 scfm N2 Dewar for Terminal, Vac. insul. tank, 42 m3 Firewater Protection System (Foam Sys, dry powder, tanks) Utilities Subtotal MARINE FACILITIES - JETTY Topworks (Road/150 meter Trestle/Pipeway) Cryogenic Piping (I/E, piping w/ insulation) Berth (Mooring, Breasting Dolphins) Dredging Marine Facilities - Jetty Subtotal
230.0 0.0 299.8 78.0 300.0 1,414.4
MARINE FACILITIES - UNLOADING Unloading Arms Marine Facilities - Unloading Subtotal
0.0 0.0
0.0 0.0
1,470.0 1,470.0
0.0 0.0
29.4 29.4
176.4 176.4
1,675.8 1,675.8
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
1,400.0 350.0 525.0 2,275.0
70.0 17.5 26.3 113.8
28.0 7.0 10.5 45.5
168.0 42.0 63.0 273.0
1,666.0 416.5 624.8 2,707.3
Site Preparation Subtotal
2,850.5 2,850.5
142.5 142.5
57.0 57.0
342.1 342.1
3,392.0 3,392.0
Bulks Subtotal
12,000.0 0.0 5,342.7 9,000.0 26,342.7
600.0 0.0 267.1 450.0 1,317.1
240.0 0.0 106.9 180.0 526.9
1,440.0 0.0 641.1 1,080.0 3,161.1
14,280.0 0.0 6,357.8 10,710.0 31,347.8
Real Estate Subtotal
500.0 500.0
500.0 500.0
OSBL INFRASTRUCTURE Includes access roads, bldgs, hospitals, stores, bridges OSBL Infrastructure Subtotal
0.0
0.0
BREAKWATER Breakwater Subtotal NAVIGATIONAL AIDS (lighting and buoys) Navigational Aids Subtotal BUILDINGS Administration Office/Control Center Compressor Building (Included in cost of compressors) Warehouse/Maintenance Building, 10,000 ft2 Buildings Subtotal SITE PREPARATION
BULKS Piping (exclud. trestle) Piling Insulation and Paint Electrical/Instrumentation
REAL ESTATE
UNADJUSTED GRAND TOTAL CONTINGENCY 12% OF THE TOTAL ADJUSTED GRAND TOTAL
35,555
92,892
48,057
5,664
3,078
18,420
181,166 21,740 202,906
LNG ONSHORE TERMINAL WITH CAVERN STORAGE PROFORMA ECONOMICS Project Summary SUMMARY FACILITY ASSUMPTIONS Facility Basis - Firm Service Cargos per Year LNG Discharge per Ship, cubic meters LNG LNG Btu content, Btu/scf Storage Working Gas Volume, Bcf Storage Base Gas Volume, Bcf
Pricing Throughput Fee, $/MmBtu Other Revenue - % of Terminal Throughput Rev. Terminal Energy Use Charge, % of throughput Assumed Henry Hub Index for initial year Gas Storage Net Revenue Realized $MM/year Other Assumptions Base Gas Price (Delivered), $/Mcf Base Gas Source ("Lease" or "Buy") Total Operations Cost, $M/Year - Labor & Maintenance, $M/Yr - Electrical Demand Charge, $M/Yr Management Overhead, $M/Year Property Taxes (assumed amount), $M/Yr Storage Site Lease Fee, $M/yr % Revenue Stream to Inflation Protect, %/yr General Inflation Rate Inflation applied to certain annual costs, %/yr Energy Use for Terminal ops., % of throughput Full storage cavern compression charge rate % of throughput requiring compression at cavern Project & Technology Rights Running Royalty, as % of Henry Hub index Project & License Upfront Payment, $MM
235 138,000 1067 16.00 7.30
0.090 0.0% 0.00% $3.50 $0.0
3.50 lease 4,832 4,632 200 360 4,000 500 100% 3.0% 1.5% 0.35% 0.00% 0%
Facility Costs, $ Marine Port Facilities LNG Process & HP PIpeline Terminal Utility System Storage Surface Facility Site Specific Misc Header Pipeline Engineering & Const. Mgmt. Project Acquisition & Tech. Rights Owner Costs, Permits, Misc. Financing Fees Contingency Total Facility Cost
FINANCIAL ASSUMPTIONS 47,118,345 51,374,800 28,288,700 108,000,000 17,788,105 0 18,630,050 50,000 7,385,958 15,154,197 41,242,500 335,032,655
LNG Terminal Project Metrics 98% Load Factor (based on 240 cargos/yr max) Reference Annual throughput, mcf/yr 639,280,701 Annual LNG Offloaded, BCF/yr 639 Reference throughput, million mmBtu/yr 682,112,508 Daily equivalent amount (mcf/day) 1,775,780 Tax Rates Federal, %/YR 35.0% State, %/YR 4.50% Blended Rate, %/Yr. 37.93% Property, %/YR, initial year/capital cost 1.19% Capital Gain Rate for Terminal Value 20% Depreciation Depreciation (Straight-Line or Accel) Straight-Line Depreciable Life, Years 20 Project Life, Years 20
0.00% based on mmBtu throughput 0
Financial Structure Sr. Debt Percent of Capital Jr. Debt Percent of Capital Equity Percent of Capital Senior Debt Term Junior Debt Term Base Gas Lease Carrying Cost, %/YR
% Capital 50.0% 0.0% 50.0% 20 5 6.75%
FINANCIAL RESULTS Cost of Capital Pretax WACC WACC Equity Return (assumed from above)
10.88% 9.60% 15.0%
Project Economics Project NPV@Pretax WACC, $M Project Pretax IRR NPV @ WACC (tax-effected), $M Project IRR (tax-effected)
162,142 15.7% 106,352 12.5%
Yr. 1 EBITDA $M/year Avg. EBITDA, Yrs 1-5, $M/year
$41,618 $44,576
Equity Returns, AFTER-Tax Equity NPV@ Assumed Equity Return, $M
Equity IRR (calculated) Debt Coverage Minimum EBITDA/Interest Coverage Minimum EBITDA/Debt Service
31,006 17.1% Pre-tax
3.7 2.7
Rate 6.75% 0.0% 15.0%
LNG Terminals Cost Comparison Equipment Summary Sheet LNG On-shore Terminal with Salt Cavern Storage Bishop Process
Bare Equipment
Average capacity 1.75 Bcfd
Cost ($M)
Description
GLNG Storage Caverns: 6 ea x 2 BCF = 12 BCF (608,000 m3)
Process Vessels Subtotal VAPORIZERS Open Rack Vaporizers, 168 ton/hr Submerged Combustion Vaporizers, 168 ton/hr Bishop Process Vaporizers Subtotal HEAT EXCHANGERS Standby glycol/fuel gas heater 127 kW HP knockout drum heater 20 kW Gaseous N2 Vaporizer 35 kW Gaseous N2 Vaporizer (Spare) 35 kW Liquid N2 Pressurization vaporizer 35 kW Liquid N2 Vaporizer 35 kW
Installed Direct & Indirect Cost ($M)
Freight Spares Other Cost ($M)
Taxes Duties Insurance Cost ($M)
60,000 60,000
-
3,000 3,000
142.0 35.6 10.5 28.8 12.2 16.8 3.3 249.2
85.9 25.5 7.5 20.6 8.1 11.1 2.1 160.7
172.2 51.0 15.0 41.3 16.1 22.2 4.3 322.2
15.7 4.1 1.2 3.3 1.4 1.9 0.4 28.0
0 0 6,020 6,020
0 0 3,973 3,973
0 0 7,964 7,964
0.0 0.0 680.3 680
Salt Cavern Storage 2 each at 15 BCF total 30 BCF PROCESS VESSELS Recondenser, 9'ID x 45', 304 SS BOG Compressor Knock Out Drum 70 m3 HP Fuel Gas Knock Out Drum, 3 m3 HP Flare Knock Out Drum, 50 m3 Service Water Storage Tank, 20 m3 Diesel Storage Tank, 50 m3 Foam Tank, 4 m3
Steel Concrete I/E & Piping Cost ($M)
Contract Engineering (12%) Cost ($M)
1,200 1,200
Total Cost Cost ($M)
3,600 3,600
67,800 67,800
8.1 2.3 0.7 1.8 0.7 1.0 0.2 14.8
48 13 4 11 4 6 1 87.9
472 132 39 107 43 59 11 862.7
0.0 0.0 362.8 363
1,077.5 1,077
0 0 20,078 20,078
Heat Exchangers Subtotal
6.1 0.8 0.66 0.66 0.66 0.66 9.5
4.03 0.53 0.74 0.74 0.74 0.74 7.5
8.1 1.1 1.5 1.5 1.5 1.5 15.0
0.7 0.1 0.1 0.1 0.1 0.1 1.1
0.4 0.0 0.1 0.1 0.1 0.1 0.6
2.2 0.3 0.3 0.3 0.3 0.3 3.8
21 3 3 3 3 3 37.7
Waste Heat Recovery Subtotal
0
0
0
0
0
0
0
Pumps Subtotal
0.0 225.0 2,100.0 0.0 0.0 3.6 203.7 2,532.3
0.0 5386.5 2194.5 0.0 0.0 0.0 213 7,794
0.0 1583.6 527.9 0.0 0.0 17.4 426.7 2,556
0.0 287.3 277.7 0.0 0.0 0.3 26.9 592
0.0 144.0 97.7 0.0 0.0 0.4 17.0 259
0.0 431.7 289.3 0.0 0.0 2.5 101.2 825
0 8,058 5,487 0 0 24 988 14,558
Compressors Subtotal
800.0 1,000.0 0.0 1,800.0
264 330 0 594
529.2 661.5 0.0 1,191
77.2 96.5 0.0 174
32.3 40.4 0.0 73
191.2 239.0 0.0 430
1,894 2,367 0 4,261
SEAWATER INTAKE SYSTEM (Incl Electrochlorination) Electrochlorination Unit, 12,000 m3/hr Seawater Intake Structure (12,000 m3/hr each) Seawater Outfall Structure (12,000 m3/hr each) Seawater Intake Screens (13,200 m3/hr each) Seawater Rotary Screens (13,200 m3/hr each) Seawater Intake System Subtotal
20 1,100 1,100 500 500 3,220
29 1150 1755 1073 1348 5,353
57.33 2304 3517 2150 2701 57.33
3.0 145.5 175.7 93.6 107.4 525
2.1 91.7 128.1 74.7 91.3 388
12.7 546.4 764.6 446.7 545.8 2,316
124 5,337 7,440 4,337 5,293 22,532
507
84 3,618 63.3 2,420.0 82.4 60.1 198.0 6,525.1
167.6 126.8 4,851.0 165.3 120.4 396.9 5,827.9
44.7 180.9 21.6 1,001.0 28.1 9.2 33.9 1,319.4
15.5 72.4 8.5 372.0 11.1 5.2 18.1 502.8
90.9 434.1 50.4 2192.5 65.7 31.0 107.4 2,972.1
909 4,305 501 21,837 652 304 1,054 29,561.7
4,500.0 17,000.0 0.0 1,400.0 22,900.0
0.0 0.0 0.0 0.0 0.0
225.0 850.0 0.0 70.0 1,145.0
90.0 340.0 0.0 28.0 458.0
540.0 2,040.0 0.0 168.0 2,748.0
5,355.0 20,230.0 0.0 1,666.0 27,251.0
WASTE HEAT RECOVERY
PUMPS First stage sendout pump, 416 m3/hr (intank) Second stage sendout pump, 28 each @270 m3/hr Seawater pump, 3160 m3/hr Sub combustion Vap. Overflow pump, 5hp Process Area Sump Pump, 10 hp, 5 m3/hr Service Water Pump, 5 hp, 57 m3/hr Firewater Pumps
COMPRESSORS BOG Compressors Ship Vapor Return Unit w/Blower Ship Unloading Compressor
UTILITIES HP Flare, 415,000 kg/hr Electrical Switchgear & Power Distrib (5% of FC) Emergency Generator - Diesel Driven, 500 kW Gas Turbine Generator, 22MW, GE LM2500 (back-up) Instrument air compressor and drier, 100 scfm N2 Dewar for Terminal, Vac. insul. tank, 42 m3 Firewater Protection System (Foam Sys, dry powder, tanks) Utilities Subtotal
MARINE FACILITY - TRADITIONAL WHARF Platform and topworks Berth, walkways and dolphins Dredging Marine Facilities - Jetty Subtotal
230.0 11,000.0 299.8 78.0 300.0 12,414.4
UNLOADING ARMS Arms: Unloading and Vapor Return Marine Facilities - Unloading Subtotal
1,960.0 1,960.0
788.0 788.0
1,930.6 1,930.6
196.2 196.2
94.7 94.7
561.4 561.4
22,500 22,500
Piepline to Caverns 15 miles @ 1.5 mmUSD/mile Pipeline Subtotal
5,531.0 5,531.0 22,500 22,500
NAVIGATIONAL AIDS (lighting and buoys) Navigational Aids Subtotal BUILDINGS Administration Office/Control Center Compressor Building (Included in cost of compressors) Warehouse/Maintenance Building, 10,000 ft2 Buildings Subtotal
850 200 525 1,575
SITE PREPARATION Site Preparation Subtotal BULKS Piping (exclud. trestle) Piling Insulation and Paint Electrical/Instrumentation Bulks Subtotal
Real Estate Subtotal OSBL INFRASTRUCTURE Includes access roads, bldgs, hospitals, stores, bridges OSBL Infrastructure Subtotal
CONTINGENCY 12% OF THE TOTAL ADJUSTED GRAND TOTAL
17.0 4.0 10.5 31.5
102.0 24.0 63.0 189
1,012 238 625 1874.25
2,171 2,171
108.5 109
43.4 43
260.5 260
2,583 2,583
19,853 0 9264.8 9000 38,118
992.7 0.0 463.2 450.0 1,906
397.1 0.0 185.3 180.0 762
2382.4 0.0 1111.8 1080.0 4,574
23,625 0 11,025 10,710 45,360
750 750
REAL ESTATE
UNADJUSTED GRAND TOTAL
42.5 10.0 26.3 78.75
750 750
0 28,205
173,209
0 25,200
9,754
4,191
19,645
265,541 31,865 297,406
LNG OFFSHORE TERMINAL WITH CAVERN STORAGE PROFORMA ECONOMICS Project Summary SUMMARY FACILITY ASSUMPTIONS Facility Basis - Firm Service Cargos per Year LNG Discharge per Ship, cubic meters LNG LNG Btu content, Btu/scf Storage Working Gas Volume, Bcf Storage Base Gas Volume, Bcf
Pricing Throughput Fee, $/MmBtu Other Revenue - % of Terminal Throughput Rev. Terminal Energy Use Charge, % of throughput Assumed Henry Hub Index for initial year Gas Storage Net Revenue Realized $MM/year Other Assumptions Base Gas Price (Delivered), $/Mcf Base Gas Source ("Lease" or "Buy") Total Operations Cost, $M/Year - Labor & Maintenance, $M/Yr - Electrical Demand Charge, $M/Yr Management Overhead, $M/Year Property Taxes (assumed amount), $M/Yr Storage Site Lease Fee, $M/yr % Revenue Stream to Inflation Protect, %/yr General Inflation Rate Inflation applied to certain annual costs, %/yr Energy Use for Terminal ops., % of throughput Full storage cavern compression charge rate % of throughput requiring compression at cavern Project & Technology Rights Running Royalty, as % of Henry Hub index Project & License Upfront Payment, $MM
235 138,000 1067 16.00 7.30
0.095 0.0% 0.00% $3.50 $0.0
3.50 lease 8,039 7,839 200 360 4,000 500 100% 3.0% 1.5% 0.35% 0.00% 0%
Facility Costs, $ Marine Port Facilities LNG Process & HP Pipeline Terminal Utility System Storage Surface Facility Site Specific Misc Header Pipeline Engineering & Const. Mgmt. Project Acquisition & Tech. Rights Owner Costs, Permits, Misc. Financing Fees Contingency Total Facility Cost
FINANCIAL ASSUMPTIONS 127,722,695 51,374,800 28,288,700 55,900,000 -10,670,245 0 15,733,050 50,000 7,653,250 15,156,957 40,814,850 332,024,057
LNG Terminal Project Metrics 98% Load Factor (based on 240 cargos/yr max) Reference Annual throughput, mcf/yr 639,280,701 Annual LNG Offloaded, BCF/yr 639 Reference throughput, million mmBtu/yr 682,112,508 Daily equivalent amount (mcf/day) 1,775,780 Tax Rates Federal, %/YR 35.0% State, %/YR 4.50% Blended Rate, %/Yr. 37.93% Property, %/YR, initial year/capital cost 1.20% Capital Gain Rate for Terminal Value 20% Depreciation Depreciation (Straight-Line or Accel) Straight-Line Depreciable Life, Years 20 Project Life, Years 20
0.00% based on mmBtu throughput 0
Financial Structure Sr. Debt Percent of Capital Jr. Debt Percent of Capital Equity Percent of Capital Senior Debt Term Junior Debt Term Base Gas Lease Carrying Cost, %/YR
% Capital 50.0% 0.0% 50.0% 20 5 6.75%
FINANCIAL RESULTS Cost of Capital Pretax WACC WACC Equity Return (assumed from above)
10.88% 9.60% 15.0%
Project Economics Project NPV@Pretax WACC, $M Project Pretax IRR NPV @ WACC (tax-effected), $M Project IRR (tax-effected)
167,500 15.9% 110,676 12.7%
Yr. 1 EBITDA $M/year Avg. EBITDA, Yrs 1-5, $M/year
$41,821 $44,792
Equity Returns, AFTER-Tax Equity NPV@ Assumed Equity Return, $M
Equity IRR (calculated) Debt Coverage Minimum EBITDA/Interest Coverage Minimum EBITDA/Debt Service
33,937 17.4% Pre-tax
3.7 2.7
Rate 6.75% 0.0% 15.0%
LNG Terminals Cost Comparison Equipment Summary Sheet LNG Offshore Terminal with Salt Cavern Storage Bishop Process Average capacity 1.75 Bcfd
Bare Equipment Cost ($M)
Description
Salt Storage Caverns: 6 x 3.5 BCF = 21 BCF (1,065,000 m3) Salt Cavern Storage 6 each at 3.5 Bcf total 21 bcf
Steel Concrete I/E & Piping Cost ($M)
Installed Direct & Indirect Cost ($M)
Freight Spares Other Cost ($M)
Taxes Duties Insurance Cost ($M)
20,000 20,000
30,000 30,000
1,000 1,000
Contract Engineering (12%) Cost ($M)
1,000 1,000
Total Cost Cost ($M)
6,000 6,000
58,000 58,000
PROCESS VESSELS Recondenser, 9'ID x 45', 304 SS BOG Compressor Knock Out Drum 70 m3 HP Fuel Gas Knock Out Drum, 3 m3 HP Flare Knock Out Drum, 50 m3 Service Water Storage Tank, 20 m3 Diesel Storage Tank, 50 m3 Foam Tank, 4 m3 Process Vessels Subtotal
142.0 35.6 10.5 28.8 12.2 16.8 3.3 249.2
85.9 25.5 7.5 20.6 8.1 11.1 2.1 160.7
172.2 51.0 15.0 41.3 16.1 22.2 4.3 322.2
15.7 4.1 1.2 3.3 1.4 1.9 0.4 28.0
8.1 2.3 0.7 1.8 0.7 1.0 0.2 14.8
48 13 4 11 4 6 1 87.9
472 132 39 107 43 59 11 862.7
VAPORIZERS Open Rack Vaporizers, 168 ton/hr Submerged Combustion Vaporizers, 168 ton/hr Bishop Process Vaporizers Subtotal
0 0 6,020 6,020
0 0 3,973 3,973
0 0 7,964 7,964
0.0 0.0 680.3 680
0.0 0.0 362.8 363
1,077.5 1,077
0 0 20,078 20,078
HEAT EXCHANGERS Standby glycol/fuel gas heater 127 kW HP knockout drum heater 20 kW Gaseous N2 Vaporizer 35 kW Gaseous N2 Vaporizer (Spare) 35 kW Liquid N2 Pressurization vaporizer 35 kW Liquid N2 Vaporizer 35 kW Heat Exchangers Subtotal
6.1 0.8 0.66 0.66 0.66 0.66 9.5
4.03 0.53 0.74 0.74 0.74 0.74 7.5
8.1 1.1 1.5 1.5 1.5 1.5 15.0
0.7 0.1 0.1 0.1 0.1 0.1 1.1
0.4 0.0 0.1 0.1 0.1 0.1 0.6
2.2 0.3 0.3 0.3 0.3 0.3 3.8
21 3 3 3 3 3 37.7
0
0
0
0
0
0
0
Pumps Subtotal
0.0 6,300.0 2,100.0 0.0 0.0 17.4 192.5 8,609.9
0.0 6583.5 2194.5 0.0 0.0 24.9 201 9,004
0.0 13196.9 4399.0 0.0 0.0 49.9 403.2 18,049
0.0 833.2 277.7 0.0 0.0 2.6 25.5 1,139
0.0 525.4 175.1 0.0 0.0 1.9 16.1 718
0.0 1564.8 1043.2 0.0 0.0 11.1 95.6 2,715
0 29,004 10,190 0 0 108 934 40,235
Compressors Subtotal
800.0 1,000.0 0.0 1,800.0
264 330 0 594
529.2 661.5 0.0 1,191
77.2 96.5 0.0 174
32.3 40.4 0.0 73
191.2 239.0 0.0 430
1,894 2,367 0 4,261
SEAWATER INTAKE SYSTEM (Incl Electrochlorination) Electrochlorination Unit, 12,000 m3/hr Seawater Intake Structure (12,000 m3/hr each) Seawater Outfall Structure (12,000 m3/hr each) Seawater Intake Screens (13,200 m3/hr each) Seawater Rotary Screens (13,200 m3/hr each) Seawater Intake System Subtotal
20 0 0 250 250 520
29 0 0 69 69 166
57.33 0 0 56 56 170
3.0 0.0 0.0 23.4 23.4 50
2.1 0.0 0.0 7.7 7.7 17
6.4 0.0 0.0 22.5 22.5 51
117 0 0 429 429 975
507
84 3,001 31.6 2,420.0 82.4 60.1 198.0 5,876.7
167.6 63.4 4,851.0 165.3 120.4 396.9 5,764.5
44.7 150.0 10.8 1,001.0 28.1 9.2 33.9 1,277.8
15.5 60.0 4.3 372.0 11.1 5.2 18.1 486.2
90.9 360.1 25.2 2192.5 65.7 31.0 107.4 2,872.9
909 3,571 250 21,837 652 304 1,054 28,577.5
50,000.0 6,480.0 5,000.0 0.0 61,480.0
0.0 0.0 0.0 0.0 0.0
2,500.0 324.0 250.0 0.0 3,074.0
1,000.0 129.6 100.0 0.0 1,229.6
6,000.0 777.6 600.0 0.0 7,377.6
59,500.0 7,711.2 5,950.0 0.0 73,161.2
WASTE HEAT RECOVERY Waste Heat Recovery Subtotal PUMPS First stage sendout pump, 416 m3/hr (intank) Second stage sendout pump, 28 ea @ 270 m3/hr Seawater pump, 3160 m3/hr Sub combustion Vap. Overflow pump, 5hp Process Area Sump Pump, 10 hp, 5 m3/hr Service Water Pump, 5 hp, 57 m3/hr Firewater Pumps
COMPRESSORS BOG Compressors Ship Vapor Return Unit w/Blower Ship Unloading Compressor
UTILITIES HP Flare, 415,000 kg/hr Electrical Switchgear & Power Distrib (5% of FC) Emergency Generator - Diesel Driven, 500 kW
Gas Turbine Generator, 32MW, GE LM2500+ Instrument air compressor and drier, 100 scfm N2 Dewar for Terminal, Vac. insul. tank, 42 m3 Firewater Protection System (Foam Sys, dry powder, tanks) Utilities Subtotal
MARINE UNLOADING STRUCTURE Platforms and Hex Bridge Cryogenic Piping (2 each 32" dia x L 1800 meters @ 1800 $/m)) Big Sweep Arm Marine Facilities - Subtotal
115.0 11,000.0 299.8 78.0 300.0 12,299.4
MARINE UNLOADING ARMS Arms: Unloading and Vapor Return Marine Facilities - Unloading Subtotal
1,500.0 1,500.0
963.0 963.0
1,930.6 1,930.6
168.2 168.2
88.8 88.8
527.2 527.2
5,177.8 5,177.8
1,120.0 3,500.0 4,620.0
0.0 0.0 0.0
56.0 175.0 231.0
22.4 70.0 92.4
134.4 420.0 554.4
1,332.8 4,165.0 5,497.8
500.0 0.0 0.0 500.0
25.0 0.0 0.0 25.0
10.0 0.0 0.0 10.0
30.0 0.0 0.0 30.0
565.0 0.0 0.0 565.0
Site Preparation Subtotal
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
Bulks Subtotal
9,003 0 4201.4 9000 22,204
180.1 0.0 84.0 180.0 444
540.2 0.0 252.1 540.0 1,332
SUBSEA PIPELINE To Cavern (total 6 = I mile long)
To existing subsea infrastructure (5 miles to tie in) Pipeline Subtotal NAVIGATIONAL AIDS (lighting and buoys) MODULAR STRUCTURES Administration Office/Control Center Compressor Building (Included in cost of compressors) Warehouse/Maintenance Building, 10,000 ft2 Buildings Subtotal SITE PREPARATION
BULKS Piping (exclud. trestle) Piling Insulation and Paint Electrical/Instrumentation
0 0
REAL ESTATE Real Estate Subtotal OSBL INFRASTRUCTURE Includes access roads, bldgs, hospitals, stores, bridges OSBL Infrastructure Subtotal UNADJUSTED GRAND TOTAL CONTINGENCY 12% OF THE TOTAL ADJUSTED GRAND TOTAL
450.1 0.0 210.1 450.0 1,110
0 0
0 31,008
129,550
10,173 0 4,748 10,170 25,091
0 65,406
8,958
4,538
23,060
262,520 31,502 294,022
Energy Bridge® LNG TERMINAL PROFORMA ECONOMICS Project Summary SUMMARY FACILITY ASSUMPTIONS Facility Basis - Firm Service Cargos per Year LNG Discharge per Ship, cubic meters LNG LNG Btu content, Btu/scf Storage Working Gas Volume, Bcf Storage Base Gas Volume, Bcf
Pricing Throughput Fee, $/MmBtu Other Revenue - % of Terminal Throughput Rev. Terminal Energy Use Charge, % of throughput Assumed Henry Hub Index for initial year Gas Storage Net Revenue Realized $MM/year Other Assumptions Base Gas Price (Delivered), $/Mcf Base Gas Source ("Lease" or "Buy") Total Operations Cost, $M/Year - Labor & Maintenance, $M/Yr - Electrical Demand Charge, $M/Yr Management Overhead, $M/Year Property Taxes (assumed amount), $M/Yr Storage Site Lease Fee, $M/yr % Revenue Stream to Inflation Protect, %/yr General Inflation Rate Inflation applied to certain annual costs, %/yr Energy Use for Terminal ops., % of throughput Full storage cavern compression charge rate % of throughput requiring compression at cavern Project & Technology Rights Running Royalty, as % of Henry Hub index Project & License Upfront Payment, $MM
65 138,000 1067 16.00 7.30
0.295 0.0% 0.00% $3.50 $0.0
3.50 lease 8,039 7,839 200 360 4,000 500 100% 3.0% 1.5% 1.00% 0.00% 0%
Facility Costs, $ Marine Port Facilities LNG Vaporization & Process Terminal Utility System Storage Surface Facility Site Specific Misc Header Pipeline Engineering & Const. Mgmt. Project Acquisition & Tech. Rights Owner Costs, Permits, Misc. Financing Fees Contingency Total Facility Cost LNG Terminal Project Metrics Load Factor (based on 65 cargos/yr max) Reference Annual throughput, mcf/yr Annual LNG Offloaded, BCF/yr Reference throughput, million mmBtu/yr Daily equivalent amount (mcf/day) Tax Rates Federal, %/YR State, %/YR Blended Rate, %/Yr. Property, %/YR, initial year/capital cost Capital Gain Rate for Terminal Value Depreciation Depreciation (Straight-Line or Accel) Depreciable Life, Years Project Life, Years
0.00% based on mmBtu throughput 0
FINANCIAL ASSUMPTIONS 25,067,080 19,981,000 175,000,000 0 3,640,466 0 12,001,454 50,000 7,653,250 13,421,313 35,916,000 292,730,563
100% 176,822,322 177 188,669,417 491,173 35.0% 4.50% 37.93% 1.37% 20%
Financial Structure Sr. Debt Percent of Capital Jr. Debt Percent of Capital Equity Percent of Capital Senior Debt Term Junior Debt Term Base Gas Lease Carrying Cost, %/YR
% Capital 50.0% 0.0% 50.0% 20 5 6.75%
FINANCIAL RESULTS Cost of Capital Pretax WACC WACC Equity Return (assumed from above)
10.88% 9.60% 15.0%
Project Economics Project NPV@Pretax WACC, $M Project Pretax IRR NPV @ WACC (tax-effected), $M Project IRR (tax-effected)
121,293 15.1% 77,396 12.1%
Yr. 1 EBITDA $M/year Avg. EBITDA, Yrs 1-5, $M/year
$34,430 $36,944
Equity Returns, AFTER-Tax Straight-Line 20 20
Equity NPV@ Assumed Equity Return, $M
Equity IRR (calculated) Debt Coverage Minimum EBITDA/Interest Coverage Minimum EBITDA/Debt Service
17,392 16.4% Pre-tax
3.5 2.5
Rate 6.75% 0.0% 15.0%
LNG Terminals Cost Comparison Equipment Summary Sheet Energy Bridge Shipboard Regasification
Bare Equipment
Capacity 0.48 Bcfd
Cost ($M)
Description
GLNG Storage Caverns: 2 ea x 3 BCF = 6 BCF (304,400 m3) LNG Storage Tank Subtotal - NA -
Steel Concrete I/E & Piping Cost ($M)
Installed Direct & Indirect Cost ($M)
-
-
Freight Spares Other Cost ($M)
Taxes Duties Insurance Cost ($M)
Contract Engineering (12%) Cost ($M)
Total Cost Cost ($M)
-
-
-
-
NA
PROCESS VESSELS Recondenser, 9'ID x 45', 304 SS BOG Compressor Knock Out Drum 70 m3 HP Fuel Gas Knock Out Drum, 3 m3 HP Flare Knock Out Drum, 50 m3 Service Water Storage Tank, 20 m3 Diesel Storage Tank, 50 m3 Foam Tank, 4 m3 Process Vessels Subtotal
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
0 0 0 0 0 0 0 0.0
VAPORIZERS Shell and TubeVaporizers, 168 ton/hr Submerged Combustion Vaporizers, 168 ton/hr Bishop Process Vaporizers Subtotal
1,200 0 0 1,200
924 0 0 924
1,852 0 0 1,852
142.2 0.0 0.0 142
80.2 0.0 0.0 80
477 477
4,676 0 0 4,676
HEAT EXCHANGERS Standby glycol/fuel gas heater 127 kW HP knockout drum heater 20 kW Gaseous N2 Vaporizer 35 kW Gaseous N2 Vaporizer (Spare) 35 kW Liquid N2 Pressurization vaporizer 35 kW Liquid N2 Vaporizer 35 kW Heat Exchangers Subtotal
0 0 0 0 0 0 0.0
0.00 0.00 0.00 0.00 0.00 0.00 0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0
-
0
0
0
0
0
Pumps Subtotal
0.0 1,800.0 0.0 0.0 0.0 17.4 0.0 1,817.4
0.0 1881.0 0.0 0.0 0.0 24.9 0 1,906
0.0 3770.6 0.0 0.0 0.0 49.9 0.0 3,820
0.0 238.1 0.0 0.0 0.0 2.6 0.0 241
0.0 150.1 0.0 0.0 0.0 1.9 0.0 152
0 0 0 0
0 0 0.0 0
0.0 0.0 0.0 0
0.0 0.0 0.0 0
-
Compressors Subtotal
0.0 0.0 0.0 0.0
SEAWATER INTAKE SYSTEM (Incl Electrochlorination) Electrochlorination Unit, 12,000 m3/hr Seawater Intake Structure (12,000 m3/hr each) Seawater Outfall Structure (12,000 m3/hr each) Seawater Intake Screens (13,200 m3/hr each) Seawater Rotary Screens (13,200 m3/hr each) Seawater Intake System Subtotal
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 57.33
0.0 0.0 0.0 0.0 0.0 0
0.0 0.0 0.0 0.0 0.0 0
-
0
0 429 0.0 0.0 41.2 60.1 0.0 530.0
0.0
0.0 21.4 0.0 0.0 14.1 9.2 0.0 44.7
600.0 115.0 0.0 450.0 1165
0.0
0 0 0 0 0 0 0.0
0
0
WASTE HEAT RECOVERY Waste Heat Recovery Subtotal PUMPS First stage sendout pump, 416 m3/hr (intank) Second stage sendout pump, 325 m3/hr Seawater pump, 2187 m3/hr Sub combustion Vap. Overflow pump, 5hp Process Area Sump Pump, 10 hp, 5 m3/hr Service Water Pump, 5 hp, 57 m3/hr Firewater Pumps
COMPRESSORS BOG Compressors Ship Vapor Return Unit w/Blower Ship Unloading Compressor
UTILITIES HP Flare, 415,000 kg/hr Electrical Switchgear & Power Distrib (5% of FC) Emergency Generator - Diesel Driven, 500 kW Gas Turbine Generator, 22 MW, GE LM2500 Instrument air compressor and drier, 100 scfm N2 Dewar for Terminal, Vac. insul. tank, 42 m3 Firewater Protection System (Foam Sys, dry powder, tanks) Utilities Subtotal
Offshore Platform and APL Subsea Installation APL Buoy Pipeline to Plem 1 mile @ 2.3 mmUSD Plem Turret, riser, moorings, and installation (EP supplied) Marine Facilities - Platform Subtotal
0.0 0.0 149.9 78.0 0.0 227.9
12000 2300 0 9000.0 23300
0.0 0.0 82.6 120.4 0.0 203.0
894.2 11.1 905
0
0 8,734 0 0 0 108 0 8,842
0 0 0 0
0
0 0 0 0 0 0
0.0 8.6 0.0 0.0 5.6 5.2 0.0 19.4
51.4 32.9 31.0 115.3
0 510 0 0 326 304 0 1,140.3
240.0 46.0 0.0 180.0 466
1,440.0 276.0 1,080.0 2796
14,280 2,737 0 10,710 27727.0
MARINE FACILITIES - UNLOADING Arms: Unloading and Vapor Return Marine Facilities - Unloading Subtotal
175,000.0 175,000.0
SUBSEA PIPELINE To Cavern Platform (2 pipes 1 mile) To existing subsea infrastructure (11 miles) Pipeline Subtotal
0.0 0.0
0.0 0.0
14,000.0 14,000.0
3,605.0 3,605.0
10,500.0 10,500.0
203,105.0 203,105.0
0.0 2,000.0 2,000.0
0.0 100.0 100.0
0.0 40.0 40.0
0.0 240.0 240.0
0.0 2,380.0 2,380.0
100 100
5.0 0.0 0.0 5
2.0 0.0 0.0 2
12.0 12
119 0 0 119
NAVIGATIONAL AIDS (lighting and buoys) MODULAR STRUCTURES Administration Office/Control Center Compressor Building (Included in cost of compressors) Warehouse/Maintenance Building, 10,000 ft2 Buildings Subtotal
257 257
12.9 13
5.1 5
30.9 31
306 306
Bulks Subtotal
1,286 0 600.2 5000 6,886
64.3 0.0 30.0 250.0 344
25.7 0.0 12.0 100.0 138
154.3 0.0 72.0 600.0 826
1,531 0 714 5,950 8,195
Real Estate Subtotal
0.0 0
OSBL INFRASTRUCTURE Includes access roads, bldgs, hospitals, stores, bridges OSBL Infrastructure Subtotal
0
SITE PREPARATION Site Preparation Subtotal BULKS Piping (exclud. trestle) Piling
Insulation and Paint Electrical/Instrumentation
REAL ESTATE
UNADJUSTED GRAND TOTAL CONTINGENCY 12% OF THE TOTAL ADJUSTED GRAND TOTAL
178,245
35,904
0 0
0 5,904
16,055
4,507
15,903
256,490 30,779 287,268
Customer: Document Title:
Date of Issue:
The United States Department of Energy National Energy Technology Laboratory
24/04/2003
Task 3 Doc 08: Matrix for Comparison of Five LNG Terminal Designs
Doc # & Version:
Doc 08 r1.0
Page 1 of 4
Matrix for Comparison of Five LNG Terminal Designs
BY MICHAEL M. MCCALL WILLIAM M. BISHOP D. BRAXTON SCHERZ
r 1.0
For client review
02/09/03
Version
Reason for Issue
Issue Date
Document Title: Matrix for Comparison of Five LNG Terminal Designs
BS
MM
Orig. Chk. Appr. Chk. Appr. CGI NETL
Review
Document No: CGI/DOE_DOC 08 DE-FC26-02NT41653
Filename: 41653R01
Customer: Document Title:
The United States Department of Energy National Energy Technology Laboratory Task 3 Doc 08: Matrix for Comparison of Five LNG Terminal Designs
Date of Issue:
24/04/2003 Doc # & Version:
Doc 08 r1.0
Page 2 of 4
TABLE OF CONTENTS
1. MATRIX FOR COMPARISON PURPOSES.....................................................................................................3
Filename: 41653R01
Customer: Document Title:
Date of Issue:
The United States Department of Energy National Energy Technology Laboratory
24/04/2003
Task 3 Doc 08: Matrix for Comparison of Five LNG Terminal Designs
Doc # & Version:
Doc 08 r1.0
Page 3 of 4
1. MATRIX FOR COMPARISON PURPOSES This matrix is based on a five tiered rating system with indicators depicting “Excellent to Acceptable” as follows:
= Excellent = Very Good = Good = Fair = Acceptable The first section of the matrix is based on the quantitative results of the factored analysis (see Doc 07 for Summary Table) discussed in prior sections and other calculated parameters. The quantitative analysis for the five terminals lends itself to a ranking whereby each terminal is uniquely rated “Acceptable through Excellent” unless the numerical results were equivalent. To better interpret the quantitative results of the matrix below, the reader should refer to Table 4.3 in Doc 07 “LNG Terminal Cost Comparison.” All subjective parameters are based on a qualitative analysis and represent the experience of the Study Team and industry polling. Because the rankings in each parameter under the qualitative analysis are subjective, the five terminals may share a common ranking from time to time. Parameter
Pacific Coast
Atlantic Coast
BPT Onshore
BPT Offshore
Energy Bridge
Quantitative Annual Sendout TIC per Capacity OPEX per Capacity Fuel Consumption Service Fee Qualitative Security Capacity Economy Buyer Response Filename: 41653R01
Customer: Document Title:
The United States Department of Energy National Energy Technology Laboratory Task 3 Doc 08: Matrix for Comparison of Five LNG Terminal Designs
Date of Issue:
24/04/2003 Doc # & Version:
Doc 08 r1.0
Page 4 of 4
Netback to Seller Construction Time Permitting Complexity
Filename: 41653R01
View more...
Comments