Comparison Between PWD Form 203A and PWD Form Design and Built
January 23, 2017 | Author: Meor Syahmi | Category: N/A
Short Description
Download Comparison Between PWD Form 203A and PWD Form Design and Built...
Description
Abstract
All standard forms of construction contract contain clauses for determination of contracts. For example, PWD 203A forms, PWD Design and Built, PAM 2006 form and etc. It is the same with the PWD 203A form where the PWD 203A (Rev. 10/83) has been replaced by the PWD 203A (Rev. 2007). These are the traditional forms of contract based on drawings and specification (203) or bills of quantities (203A) produced for use in public sector or government projects in both building and civil engineering contracts. Generally it can be said that a majority of the risks have been transferred to the contractor under these standard forms of contract and this remains true with the 2007 version. The standard form is generally used in conjunction with the accompanying standard administrative forms which have been produced specifically for use with the contract forms and in many instances enhance the obligations contained within the conditions of contract. However, based on a preliminary study that had been conducted for the research, it has been found out that both of the employers and contractors may not actually realize their rights, procedures and effects in determining the contractor’s employment under the new forms. Hence, this study will focus on comparison between PWD 203a and PWD Design and Built, procedures and effects as a result of determination of the contractor’s employment under the forms.
1.1 Introduction
A contract is a legally binding agreement between the parties identified in the agreement to fulfill all the terms and conditions outlined in the agreement. A prerequisite requirement for the execution of a contract, amongst other things, is the condition that all the parties to the contract accept the terms of the claimed contract. Construction contracts are basically different from major service contracts. There are various types of construction contract. The choice of contract depends on the basis of pricing and the contract strategy that best meets the project objectives. The various types offer different ways of handling pricing, risk transfer, responsibility for performance, cost certainty, and complexity. The purpose of standard forms of contract is to facilitate the contractual arrangements between actors in a project. Standard forms of contract are readymade terms and conditions when making a contract (Kwakye 1997). The standards vary from country to country and from one type of project to another. These standards are generally used and accepted by different contracting parties. It would be practically impossible to devise a standard form of contract that would take account of all eventualities that might occur in a construction project (Andersson and Gunnarsson, 2002). Standard forms of contracts are often criticized as being a compromise containing some defective aspects. However, the advantage of their adoptions is that with the passage of time, persons using them become familiar withtheir overall content as well as their particular strengths and weaknesses (Kwakye 1997).
1.2 Comparison between PWD (203a) and PWD (D & B)
There are different specialists or parties during the process of building procurement. It leads to the fragmentation process in construction industry (Murdoch and Hughes, 2000). Each project participant has particular aims and objectives and it is rare to find contract structures that encourage harmony among these aims. According to the scale and requirement of the project the parties may differ in types of contract. Figure 2 provides parties’ organization in PWD DB form of contract and figure 3 shows parties relation in PWD 203A form of contract.
Client
Project Director
Turnkey Contractor
Architect
(project management consultant) Joint Venture Contractor
Architect
Project Engineer
Design and Implementation Project Manager
C&S Builders
Validation Team
M&E Engineer
Accreditation Team
Figure 1: Organization chart of PWD DB form of contract
C&S eer
Client
Superintending Officer
Contractor (director)
C&S Engineer
Quantity Surveyor
Assistant of Quantity Surveyor
Architect
Safety Officer
Executive
Nominated Sub-Contractor
Director
M & E Services
Site Supervisor
M&E Engineer
Assistant of Site Supervisor
Figure 2: Organization chart of PWD 203A form of contract
MAIN PARTY Client
ROLES
PWD D & B
PWD 203A
Design Leadership
Project director Advisory group, feasibility consultant End-user, general public, tenant -
Management
-
Design
-
Administration
-
Superintending Officer Advisory group, feasibility consultant End-user, general public, tenant Architect(management function) Consultant team manager Architect(design function) Architect, contract administrator, supervising officer, project administration
Site inspector Overall responsibility
Consultant(architect), main contractor, joint venture contractor, design and build project manager Contract manager, project engineer, supervision team, builders Architect, C & S sub-contractor, M & E sub-contractor, supplier
Representative Advisor Stakeholder
Consultant
Contractor
Constructor’s staff
Partial responsibility
Clerk of work Builder, main contractor, principal contractor, executive director Project manager, site supervisor, builders
C&S sub-contractor, M&E sub-contractor, quantity surveyor, supplier
Table 1: Comparison of PWD DB and PWD 203A form of contract parties
According to table 1; PWD DB. form, there is no consultant party which directly would be employed by the client. In fact, the client employs the contractor to design and build which means the consultant is included in the package of the contractor. Therefore the design leadership, design management, administration team and site inspector roles are under contractor’s responsibilities. The contract management is the method in use in PWD DB. The contract manager controls, monitors and maintains the project since the earliest stage of a project.
One of the benefits for the client is that the client does not have to be so active during the project, because most of the responsibility of the project is allocated to the contractor (Söderberg 1993). Architect (management function), consultant team manager, design manager, architect (design function), engineer, consultant, contract administrator, supervising officer, planning supervisor, project administration, clerk of work are the roles involved in consultant which are the subordinates of contract manager. In PWD DB the contractor is compensated for all costs incurred. Also failing such deductions will be recovered from the performance bond or as a debt from contractor. Identifying and controlling (by avoiding or minimizing) the risks to a project is a vital part of managing it. This includes those risks that have been transferred to the contractor under PWD DB contract. The reason of popularity for using this type of contract is that the client does not take the risk as much as the contractor has.
Hence the contractor consists of a contract manager to control over the cost and time. However in PWD 203A the client employs consultant separately which is directly linked. In this type of contract there is a separation of construction and design. There is a designing team, which is contracted by the client, and they shall provide the contractor with a complete design (Ashworth 1991). The contractor subordinates include executive director who is the person in charge at site for complementation. Any problem happens during project development or any difference between designed and built documents in details, the executive director informs the superior and handles all.
The executive director includes site supervisor, quantity surveyor and safety officer who occupy positions at the site of construction. The quantity surveyor monitors all required materials’ quantities, proper cost and suggests to the client. The site supervisor manages all works, workers, daily reports (site dairy) and the quality of work. Arranging the masonries, material maintenance and all machines’ installation are the site supervisor’s responsibilities. In occurrence of a problem, they refer to the project manager for handling. The different method of organizing and maintaining the project is used in PWD 203A which is project management. The project manager controls and monitors the work through schedule of planning during constructing. The important aspect in PWD 203A is bills of quantities. Therefore the contractor has the responsibility to complete the work according to the requested quantities referred to the contract documents. In PWD 203A the government is entitled to deduct such costs, expenses and on-cost charges or any part from any monies due to the contractor or to recover it from performance bond as debt due from the contractor. That is the reason of being popular for this type of contract for government sector in Malaysia.
1.3 Categories of Comparison
In this report, the comparison will be carried out based on these categories: 1. Parties who involves in payment 2. Type of payment 3. Interim payment stages statement 4. Advance payment 5. Procedure of Interim Payment 6. Schedule of issuing interim certificates 7. Requirement upon issuing interim certificates 8. Contractor’s obligation in applying payment 9. Procedure of payment upon completion 10. Wages of workmen affects the final payment 11. Retention fund/performance bond 12. Payment for liquidated damages 13. Payments upon termination 14. Performance bond 15. Direct payment to the third party 16. Late payment by government/employer
1.4 Comparison between PWD Form 203A and PWD Form Design and Built No
Item
PWD 203A
PWD DB
1
Parties who involves
parties involves
parties involves:
in payment
1. Contractor
1. Contractor
obligation:
2. Superintending Officer(SO),
2. Project Director (PD)
or SO’s representatives
3. Employer
3. Employer 2
Type of payments
Stages
Advance payment and stages
3
Interim payment
Stated in appendix
Stated in appendix
No advance payment
25% of the value of the contract
stages statement 4
Advance payment
sum 5
Procedure of interim
Procedure:
Procedure:
payment
1. Contractor shall complete the
1. Contractor shall submit
work as in Appendix 2. Regarding to the complete work, SO shall make valuation of the complete work in 14 days
interim payment application 2. PD consider and ascertain the amount in 28 days 3. PD issuing the interim payment certificates
3. SO issuing interim certificates 4. Government pays the 4. Government pays the contractor base on interim
contractor base on interim certificates
certificates
6
Schedule of issuing
14 days
28 days
Schedule of interim
Stated in appendix, if it not stated
Stated in appendix, if it not
certificates payment
= 30 days
stated = 30 days
interim certificates 7
8
Contractor’s
To make a works is done and SP
obligation in applying can make a valuation payment
1. The value of works done and properly executed 2. The amount on any valuation of variations or the instructions by the PD (clause 24 3. The amount in regard to the expenditure of provisional sums executed or expended (clause 25) 4. The value of any goods or unfixed materials delivered to or adjacent to the site intended for use or to be incorporated into the works 5. The upervision reports as required by the PD under clause 13.1
9
Procedure of payment 1. Within 3 month after the upon completion
1. Within 3 month after
issuance of the certificate of
issuance of the certificate of
practical completion, the
completion of making good
contractor shall submit
defects or the certificate of
application to enable the final
completion of maintenance
account prepared by the SO.
(if any), Contractor shall
If contractor failed, SO shall
submit to PD a statement of
forthwith make the
the final account showing in
assessment based on available
detail the value
document for the final account
2. Within 3 months after the
2. PD proceed to verify the final
expiry of the defects liability
account based on the
period for the whole of the
document which is given by
works or 3 month after the
contractor
issue of the certificate of
3. If final account is verified,
completion of making good
PD shall issues Final
defects under clause 48
certificate which consists of
hereof, SO shall issue the
balance sum
final certificate that consists
4. Final payment is paid by the
of supported documents, full
government to the contractor.
particulars complete with
Final payment will not be
receipt, vouchers, final
paid unless the contractor
valuation, any amount
satisfied the SO in his
determined in clause 31.1
obligation due to the
3. Final payment is paid by the
workmen
government to the contractor. Final payment will not be paid unless the contractor satisfied the SO in his obligation due to the workmen
10
Wages of workmen
Wages of all the workmen has to
Wages of all the workmen has to
affects the final
be paid and all contributions
be paid and all contributions
payment
under the Employment Act 1955,
under the Employment Act
The Employee;s Social Security
1955, The Employee;s Social
act 1969, The Employee’s
Security act 1969, The
provident Fund Act 1991 and any
Employee’s provident Fund Act
other laws relevant to the
1991 and any other laws relevant
employment of workmen have
to the employment of workmen
been paid.
have been paid.
11
12
Retention fund
No retention fund is applied in
No retention fund is applied in
government standard form.
government standard form.
Payment for
If the contractor fails to complete
If the contractor fails to complete
liquidated damages
the works by the date for
the works by the date for
completion or within any
completion or within any
extended time granted pursuant to extended time granted pursuant clause 43, the SO shall issues a
to clause 49, the PD shall issues
certificate of non completion to
a certificate of non completion to
the contractor and notice the
the contractor and notice the
intention of the Government to
intention of the Government to
impose liquidated and ascertained impose liquidated and damages that stated in appendix.
ascertained damages that stated in appendix.
13
Payment upon
Base on reasonable valuation. If
Base on reasonable valuation. If
termination
contract is terminated under
contract is terminated under
clause 50 and 52, the amount to
clause 50 and 52, the amount to
be paid (in so far as such amounts be paid (in so far as such or items have not already been
amounts or items have not
covered by payments on account
already been covered by
made to the contractor) shall be
payments on account made to the
the following:
contractor) shall be the
a. The value of all work carried
following:
out up to the date of termination
a. The value of all work carried out up to the date of termination
b. The amounts payable in
b. The amounts payable in
respect of any preliminary
respect of any preliminary
items so far as the work of
items so far as the work of
service comprised therein has
service comprised therein
been carried out or performed
has been carried out or
and a proper proportion of
performed and a proper
any such items which have
proportion of any such items
been partially carried out or
which have been partially
performed
carried out or performed
c. The cost of materials or goods
c. The cost of materials or
reasonably ordered for the
goods reasonably ordered for
works which have been
the works which have been
delivered to the contractor or
delivered to the contractor or
of which the contractor is
of which the contractor is
legally liable to accept
legally liable to accept
delivery
delivery
d. A sum being the amount of
d. A sum being the amount of
any expenditure reasonably
any expenditure reasonably
incurred by the contractor in
incurred by the contractor in
the expectation of completing
the expectation of
the whole of the works in so
completing the whole of the
far such expenditure has not
works in so far such
been recovered by any other
expenditure has not been
payments
recovered by any other
e. The reasonable cost of any protection works and removal
payments e. The reasonable cost of any
of equipment and site
protection works and
facilities pursuant to
removal of equipment and
termination as provided under
site facilities pursuant to
the contract.
termination as provided under the contract.
14
Performance bond
If the contractor fails to performs
If the contractor fails to performs
any of his obligations under the
any of his obligations under the
contract and such failure is non
contract and such failure is non
remedied in accordance with this
remedied in accordance with this
contract, the government shall be
contract, the government shall be
entitled to call upon the
entitled to call upon the
performance bond, wholly or
performance bond, wholly or
partially.
partially.
The performance bond may be
The performance bond may be
released or refunded to the
released or refunded to the
contractor upon the completion of contractor upon the completion
15
works.
of works.
Direct Payment to the
Government shall paid the
Applied in direct payment to the
third party
nominated sub
contractor’s consultants. For the
contractor/suppliers according to
purpose of payment to the
interim certificates/final
consultant, the contractor and the
certificates
consultant shall enter an irrevocable Deed of Assignment for the assignment of any money due to the consultant to be paid directly by the government.
16
Late payment by employer/government
No provision
No provision
Conclusion
In conclusion, the main differences in construction contract are the extent to which the client is responsible for the management of the project, risk allocation and the internal responsibilities of the project members. According to the comparison which is given above, the roles link are depended on the type of contract and it would lead the liabilities and risk to the parties. In PWD DB, contractor’s responsibilities vary from PWD 203A. The contractor’s responsibilities in PWD DB are the design leadership, design management, administration team and site inspection roles. The traditional contractual arrangement sets out the legal relationship the parties wish to establish and the rights, obligations and procedures for resolving contractual disputes .There are several factors that affect what type of contract is suitable for a certain project such as the amount of involvement from the client, the location of the project, technical complexity. The project manager controls and monitors the work through schedule of planning during constructing.
The trend of the faster development of the construction industry in Malaysia make Design & Build contract more familiar and efficient because it may avoid the delay in completing the project. The increasingly of complex projects, and the search for quicker and cheaper solutions and achievement of value for money will influence the need for new organisational and management methods. This will have a positive influence in terms of the integration of main project stakeholders and phases, as well as the ultimate success of the entire construction project.
In an initial stage of the design phase, the client has to adopt a suitable contractual arrangement for the project and a corresponding standard form of contract in order to attain the proper management and organization in project.
References Malaysian Construction and Contract Law, Retrieved from http://simplymalaysia.wordpress.com/standard-forms-of-contract/domestic-standard-contractforms/p-w-d-form-of-contract-203-2007/
Determination Of Contractor’s Employment Under PWD 203a (Rev. 2007) And PAM2006 Standard Forms Of Contract Retrieved from http://fab.utm.my/files/2012/07/ThesisUGBQS2010ChenKianMun.pdf
View more...
Comments