Commissioning Request and Check List (Form 9180)
Short Description
Commissioning of Chillers Checklist...
Description
Dunham-Bush Industries Sdn Bhd (166302-K) Lot 5755-6, Kidamai Industrial Park Bukit Angkat, 43000 Kajang Selangor Darul Ehsan, Malaysia T: +603 89249000 W: www.dunham-bush.com
COMMISSIONING REQUEST AND PRE-START-UP CHECK LIST Request for start-up and commissioning of Dunham-Bush Air and Water Cooled Chillers Job Name : Address & Location :
Unit Model Unit Serial Number of Units
Kindly complete, officially stamp, sign and return this form to Dunham-Bush (DB) should you require DB to dispatch technicians or supervision to jobsite. Failure to complete and check all the below items may result in additional charges to your company. Additional charges will result if the start-up and commissioning exercise is delayed, or additional days are required due to site delays/problems, or if there is in-complete preparations on your scope of work.
A. Dunham-Bush Unit 1.
Essential electrical power to the Chiller is available Measured Voltage: L1-L2:
L1-L3:
L2-L3:
1.
Erected on foundation
2.
Spring isolators or Neoprene Rubber pads installed and adjusted to level unit
3.
Cooler / Chiller vessel insulated
4.
Chiller leveled within ± 1/16” per foot
5.
Visually check for leaks (oil dripping etc.)
6.
Standing Pressure of each refrigerant circuit Refrigerant
7.
Inspect chillers or condensing units for damage
8.
Check for enough clearance for proper airflow and servicing of unit
Page 1 of 5
DBI/WS/SCPC/17 Rev.1 07/15
B. Air Handling Unit/ Fan Coil / Process System 1.
All units tested, commissioned and operating without problem
2.
All process system ready and completed for Operation
C. Piping 1.
Cleaned , flushed and pressure tested for leaks
2.
Properly supported – vibration eliminators installed
3.
Air vents, thermometers and pressure gauges installed
4.
All water balancing and isolating valves installed and tested
5.
All chilled and condenser water flow switches installed, tested and calibrated
6.
All modulating valves and flow controls checked and calibrated
7.
All modulating valves and flows set at design flow requirement
8.
Water piping system properly purged of air and no air lock in system
D. Units with Cooling Tower 1.
Cleaned, tested and operational
2.
Tower fan tested and balanced
3.
Tower water flow balanced
4.
Water treatment services performed, auto chemical Feed has flow interlock
E. Water Pump 1.
All condenser and chilled water pump tested operational and balanced Condenser Pump FLA : Pump Running Amp: Chilled Water Pump FLA :
2.
Pump Running Amp:
All pumps properly primed and no air lock in pumping system
Page 2 of 5
DBI/WS/SCPC/17 Rev.1 07/15
3.
Adequate and constant water supply available
4.
Required flow ratio must be maintained prior to start-up the chillers (Follow water flow curve on I.O.M.)
F. Electrical Wiring 1.
Adequate and constant power supply available
2.
All power wiring and control completed to all of the system components
3.
All circuit breakers and overload relays properly sized and installed
4.
All wiring and grounding conforms to National Electrical Codes
5.
All automatic control devices checked, tested and operational
6.
All field supplied main electrical boards, switch boards, starter boards and controls checked, tested and operational.
7.
Customer interlocks only as indicated on wiring diagram (shielded cable as required )
8.
Energize crank case heater for 24 hours prior to start-up of the compressors
G. Units with Remote Refrigerant Condenser Piping 1.
Required amount of refrigerant for system charging at job site
2.
Entire system properly dehydrated – must hold vacuum at 700 microns for a minimum half an hour.
3.
All fan cycling, damper control systems checked and operational
4.
All control wiring installed
H. Remote Evaporator Systems 1.
Liquid line solenoid interlocked with Dunham-Bush unit control panel
2.
Entire system properly dehydrated – must hold vacuum at 700 microns microns for a minimum half an hour. Page 3 of 5
DBI/WS/SCPC/17 Rev.1 07/15
3.
All expansion valves properly sized and properly installed
4.
All refrigerant piping installed in accordance With standard good practice and design criteria
5.
All terminal equipment properly sized and properly installed
6.
All automatic control devices checked and operational
I. Condition 1.
Essential electrical power to the equipment is available as designed
2.
Essential water supply for city usage and conditions is available
3.
Full load available for proper test and balance of Dunham-Bush equipment
Services To Be Rendered Dunham-Bush engineers, supervisors, technicians and service representative will check, test, start-up and commission the chiller and condensing units in accordance to standard Dunham-Bush procedures and re-commendation and standard commercial good practices. Dunham-Bush Rendered Services Above Do Not Include Any Responsibility For The Following:1. Installation and operating of the temperature control system external to the chillers or condensing units - Other wise agreed upon by both parties prior to performance of works. a. Balancing of the air distributor side of this system. b. Balancing of the water side of the system other than the chillers or condensing units c. Balancing of refrigerant systems. 2. Electrical wiring performed by others. We (the dealer/contractor) request the present of Dunham-Bush personnel at the job site on or about (date) to check, test start-up and commission the equipment / system as required. On receipt of this form, Dunham-Bush will schedule their service personnel to this job within seven to fourteen days (7-14 days) of the requested date.
Page 4 of 5
DBI/WS/SCPC/17 Rev.1 07/15
It is understood that Dunham-Bush personnel will be at site to perform start- up and commissioning exercise for a period not exceeding normal working days. We the undersigned agree that we will pay a free for such time that is spent on this over the specific normal working days agreed upon, due to delays and in-complete preparations on our part and scope of works/responsibilities. To cover this contingency, our contingency Purchase Order No. be issued with the assurance that if no addition time is required, this purchase order will be cancelled. An overtime charge will be rendered for work executed on Saturday, Sunday and Public Holidays Dealer / Contractor: Address:
Authorized Signatory:
Full Name :
Company Stamp: Position:
Page 5 of 5
DBI/WS/SCPC/17 Rev.1 07/15
View more...
Comments