COILED TUBING COMPLETION SPOOLABLE™ INSTALLATION SEQUENCE
CONFIDENTIALITY This manual section is a confidential document which must not be copied in whole or in part or discussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion – Surface Equipment • Surface equipment rig-up comprises coiled tubing and pressure control equipment generally used for conventional coiled tubing service operations
Injector head
Lubricator
Coiled tubing BOP Gate valve Coiled tubing hanger Casing hanger
Fig. 1. Surface equipment rig-up.
CONFIDENTIALITY This manual section is a confidential document which must not be copied in whole or in part or discussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion – Well Preparation • Set bottom-hole seal assembly in existing tubing nipple • Flapper valve (closed) provides a pressure barrier – opens when locator seal is stung-in • Back-pressure valve installed in tubing hanger • Nipple down tree
Coiled tubing hanger Casing hanger
Sub-surface safety valve (closed)
Nipple in production tubing Seal bore Flapper valve (closed) Production packer
Fig. 2. Well preparation.
CONFIDENTIALITY This manual section is a confidential document which must not be copied in whole or in part or discussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion – BHA Preparation • Locator seal assembly (LSA) made-up to coiled tubing with an external connector • Pump-through pump-off check valve installed on LSA • LSA is long enough to allow required tubing movement
Coiled tubing hanger Casing hanger
Coiled tubing inside production tubing
Sub-surface safety valve (open) Locator/external connector Locator seal assembly with pump-out plug
Lock with PBR Flapper valve (closed)
Fig. 3. BHA preparation.
CONFIDENTIALITY This manual section is a confidential document which must not be copied in whole or in part or discussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion – Testing Components • Run required length of coiled tubing until the first GLM and valve are about to leave the spool • Make up a test pump and gauge to the valve port and test the valve opening pressure • Repeat as required by completion design
Testing GLV
Fig. 4. Testing a gas lift valve.
CONFIDENTIALITY This manual section is a confidential document which must not be copied in whole or in part or discussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion – Spacing Out • With locator engaged in the seal assembly the flapper valve will be held open • Find neutral point and test downhole seals • Prepare to set coiled tubing hanger
Valve Coiled tubing hanger Casing hanger
SPOOLABLE safety valve
Sub-surface safety valve (open)
SPOOLABLE gas lift valve SPOOLABLE gas lift valve
Locator in place Flapper valve (open)
Fig. 5. Sting-in space out.
CONFIDENTIALITY This manual section is a confidential document which must not be copied in whole or in part or discussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion – Setting the CT Hanger • Tighten the coiled tubing hanger slips and pack-off to the set position • Function and pressure test the hanger
, ,,,,,,,,,,, , , , , , , , , , , , ,,,,,,,,,,,,,,,,,,,,, ,,,,,,,,,
• Cut the coiled tubing and control line and rig down the coiled tubing equipment
Control line hanger
Slip actuators
Pack-off
,,,,,, , ,,,,,
,,,,, ,,,, ,
Side-port
Production tubing hanger
Fig. 6. Setting the coiled tubing hanger.
CONFIDENTIALITY This manual section is a confidential document which must not be copied in whole or in part or discussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion – Control Line Hanger • Control line cut above CT • Control line is fed through the hanger and hanger is placed on the CT • Hanger housing is placed over the hanger and made-up to the coiled tubing hanger • Top of assembly is plugged and tested
Plug profile Control line port Control line shear ram
Guides
Coiled tubing
,, ,, ,, ,, ,, , ,, , ,, , ,, , ,, , ,, , ,, , ,, , ,, ,, ,,,,
Fig. 7. Setting the control line hanger.
CONFIDENTIALITY This manual section is a confidential document which must not be copied in whole or in part or discussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion – Completion Configuration • With the test plug in place rig down the CT equipment and nipple up the tree • Retrieve the test plug with slick-line and prepare to turn well to production
Valve Control line hanger Coiled tubing hanger Casing hanger
SPOOLABLE safety valve
Sub-surface safety valve (open)
SPOOLABLE gas lift valve SPOOLABLE gas lift valve
Locator in place Flapper valve (open)
Fig. 8. Completion in place.