Ch13 Solutions to Book Examples
Short Description
Download Ch13 Solutions to Book Examples...
Description
CH13 Exercises 1. In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project. CV = EV – AC = 2,100 – 2,000 = +100 SV = EV – PV = 2,100 – 2,400 = -300 2. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51? CV = EV – AC = 600 – 650 = -50 SV = EV – PV = 600 – 560 = +40 CPI = EV / AC = 600 / 650 = .92 3. Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8. From the data you have collected and computed for periods 4 and 8, what information are you prepared to tell the customer about the status of the project at the end of period 8? The project appears to be doing nicely. In both periods 4 and 8 the cost variance is positive—+$300 and +$400, respectively. This suggests a pattern of good cost variance that is under budget. The schedule variance is also positive—+$300 and +$400 for period 4 and period 8. Since Task D is already 25% complete, Task B must have been completed at least one period early.
2
End of Period 4 Actual % Task Complete A Finished B 50% C 33% D 0% E 0% Cumulative Totals
EV $ 400 1200 500 0 0 $2100
AC $ 300 1000 500 0 0 $1800
PV $ 400 800 600 0 0 $1800
CV $ +100 +200 0 0 0 $+300
SV $ 0 +400 -100 0 0 $+300
End of Period 8 Actual % Task Complete A Finished B Finished C Finished
EV $ 400 2400 1500
AC $ 300 2200 1500
PV $ 400 2400 1500
CV $ +100 +200 0
SV $ 0 0 0
PROJECT MANAGEMENT: THE MANAGERIAL PROCESS
D 25% E 33% F 0% Cumulative Totals
400 300 0 $5000
300 300 0 $4600
0 300 0 $4600
+100 0 0 $+400
+400 0 0 $+400
Note: Completion of the answer sheet requires constant reference to the baseline figure.
Chapter 13 Progress and Performance Measurement and Evaluation
3
4. Given the following project network, baseline, and status information, develop status reports for periods 1-4 and complete the project summary graph (or a similar one). Report the final SV, CV, CPI and PCIB. Based on your data, what is your assessment of the current status of the project? At completion? After 4 time periods the project is roughly 77% (PCIB) complete and is current getting only 83 cents worth of work for each dollar spent. The project is currently $10,000 over budget. There is $3,000 worth of work on critical Activity 5 that has not been completed as planned so the project is behind schedule. Since so much of the project has been completed the project is expected to come in over budget. The forecast cost at completion is $78,000 which is $13,000 over budget. Whether the project will be completed on schedule will depend upon whether Activity 5 can make up for lost time.
E x e c ri se 13 4 -a
0 1 1
1 2 1 2 3
2 1 3
0 0 0
2
3 0 3
3 0 3
5
0 0 0
3
2 0 2
2 0 2
6
3
2
4 2
4 1 5
5 0 2 5
3
5 0 5
5 0 5
7
6 0 1 6
LEGEND ES SL
I D
EF SL
LS DUR LF
4
PROJECT MANAGEMENT: THE MANAGERIAL PROCESS
Status Report: Ending Period 1 Task % Complete EV 1 50% 6 2 40% 6 3 25% 2 Cumulative Totals 14
AC 6 8 3 17
PV 4 3 4 11
CV 0 -2 -1 -3
($000) SV +2 +3 -2 +3
Status Report: Ending Period 2 Task % Complete EV 1 Finished 12 2 80% 12 3 75% 6 Cumulative Totals 30
AC 13 14 8 35
PV 12 10 8 30
CV -1 -2 -2 -5
($000) SV 0 +2 -2 0
Chapter 13 Progress and Performance Measurement and Evaluation
5
6
Status Report: Ending Period 3 Task % Complete EV 1 Finished 12 2 80% 12 3 Finished 8 4 50% 3 5 0% 0 6 33.3% 3 Cumulative Totals 38
AC 13 15 10 4 0 4 46
PV 12 15 8 3 0 3 41
CV -1 -3 -2 -1 0 -1 -8
($000) SV 0 -3 0 0 0 0 -3
Status Report: Ending Period 4 Task % Complete EV 1 Finished 12 2 Finished 15 3 Finished 8 4 Finished 6 5 30% 3 6 66.7% 6 7 0% 0 Cumulative Totals 50
AC 13 18 10 8 3 8 0 60
PV 12 15 8 6 6 6 0 53
CV -1 -3 -2 -2 0 -2 0 -10
($000) SV 0 0 0 0 -3 0 0 -3
PROJECT MANAGEMENT: THE MANAGERIAL PROCESS
5. The following labor hours data have been collected for a nanotechnology project for periods 1 through 6. Compute the SV, CV, SPI, and CPI for each period. Plot the EV and the AC on the summary graph provided (or a similar one). Plot the SPI, CPI and PCIB on the index graph provided (or a similar one). What is your assessment of the project at the end of period 6? After 6 time periods the project is roughly 66% complete and so far work on the project has taken 1,600 hours less work than planned. There is 400 hours worth of work on Activity 4 which was suppose to have been done that has not done. Since Activity 4 is on the critical path, the project is behind schedule. If schedule is the number priority, the project manager may want to consider investing some of the savings on accelerating critical activities.
Chapter 13 Progress and Performance Measurement and Evaluation
7
8
Status Report: Ending Period 1 Task % Complete EV 1 50% 1000 Cumulative Totals 1000
AC 500 500
PV 1000 1000
CV +500 +500
SV 0 0
Status Report: Ending Period 2 Task % Complete EV 1 Finished 2000 Cumulative Totals 2000
AC 1500 1500
PV 2000 2000
CV +500 +500
SV 0 0
Status Report: Ending Period 3 Task % Complete EV 1 Finished 2000 2 0% 0 3 10% 300 4 20% 500 Cumulative Totals 2800
AC 1500 0 200 500 2200
PV 2000 1600 500 1000 5100
CV +500 0 +100 0 +600
SV 0 -1600 -200 -500 -2300
PROJECT MANAGEMENT: THE MANAGERIAL PROCESS
Status Report: Ending Period 4 Task % Complete EV 1 Finished 2000 2 50% 1200 3 30% 900 4 40% 1000 Cumulative Totals 5100
AC 1500 1000 800 1500 4800
PV 2000 2400 1000 2000 7400
CV +500 +200 +100 -500 -300
SV 0 -1200 -100 -1000 -2300
Status Report: Ending Period 5 Task % Complete EV 1 Finished 2000 2 Finished 2400 3 50% 1500 4 60% 1500 5 25% 400 Cumulative Totals 7800
AC 1500 2000 800 1500 400 6200
PV 2000 2400 2000 2200 400 9000
CV +500 +400 +700 0 0 +1600
SV 0 0 -500 -700 0 -1200
Status Report: Ending Period 6 Task % Complete EV 1 Finished 2000 2 Finished 2400 3 80% 2400 4 80% 2000 5 50% 800 Cumulative Totals 9600
AC 1500 2000 2100 1800 600 8000
PV 2000 2400 2300 2400 800 9900
CV +500 +400 +300 +200 +200 +1600
SV 0 0 +100 -400 0 -300
Indexes Period 1 2 3 4 5 6
SPI 1.00 1.00 .55 .69 .87 .96
CPI 2.00 1.33 1.27 1.06 1.26 1.20
PCIB .07 .14 .19 .35 .54 .66
SPI = EV / PV CPI = EV / AC PCIB = EV / BAC
Chapter 13 Progress and Performance Measurement and Evaluation
9
10
PROJECT MANAGEMENT: THE MANAGERIAL PROCESS
6. The following data have been collected for a British health care IT project for two-week reporting periods 2 through 12. Compute the SV, CV, SPI, and CPI for each period. Plot the EV and the AC on the summary graph provided. Plot the SPI, CPI and PCIB on the index graph provided. (You may use your own graphs.) What is your assessment of the project at the end of period 12?
Chapter 13 Progress and Performance Measurement and Evaluation
11
Status Report: Ending Period 2 Task % Complete EV 1 50% 4 Cumulative Totals 4
PV 4 4
CV 0 0
Status Report: Ending Period 4 Task % Complete EV 1 Finished 8 Cumulative Totals 8
AC 10 10
PV 8 8
CV -2 -2
($00) SV 0 0
Status Report: Ending Period 6 Task % Complete EV 1 Finished 8 2 25% 10 3 33% 10 4 0% 0 Cumulative Totals 28
AC 10 15 12 0 37
PV 8 10 10 10 38
CV -2 -5 -2 0 -9
($00) SV 0 0 0 -10 -10
CV -2 -8 -7 0 -17
($00) SV 0 -8 -7 -20 -35
CV -2 -6 -10 -10 0 -6 -34
($00) SV 0 -6 0 -10 0 -2 -18
CV -2 -10 -10 -20 -10 -10 -62
($00) SV 0 0 0 0 0 -10 -10
Status Report: Ending Period 8 Task % Complete EV 1 Finished 8 2 30% 12 3 60% 18 4 0% 0 Cumulative Totals 38 Status Report: Ending Period 10 Task % Complete EV 1 Finished 8 2 60% 24 3 Finished 30 4 50% 10 5 0% 0 6 30% 18 Cumulative Totals 90 Status Report: Ending Period 12 Task % Complete EV 1 Finished 8 2 Finished 40 3 Finished 30 4 Finished 20 5 50% 20 6 50% 30 Cumulative Totals 148
12
AC 4 4
($00) SV 0 0
AC 10 20 25 0 55 AC 10 30 40 20 0 24 124 AC 10 50 40 40 30 40 210
PV 8 20 25 20 73 PV 8 30 30 20 0 20 108 PV 8 40 30 20 20 40 158
PROJECT MANAGEMENT: THE MANAGERIAL PROCESS
Indexes Period 2 4 6 8 10 12
SPI 4/4 = 1.0 8/8 = 1.0 28/38 = .74 38/73 = .52 90/108 = .83 148/158 = .94
CPI 4/4 = 1.0 8/10 = .80 28/37 = .76 38/55 = .69 90/124 = .73 148/210 = .70
PCIB 4/248 = .02 8/248 = .03 28/248 = .11 38/248 = .15 90/248 = .36 148/248 = .60
SPI = EV / PV CPI = EV / AC PCIB = EV / BAC
After 12 time periods the project is roughly 60 percent and the project is only getting 70 cents worth of work for each dollar spent. The project is current $6,200 over budget. There is $1,000 worth of work that supposed to have been done that has not been completed according to plan. However, this work involved a noncritical activity and the project is on schedule with regards to the critical path.
Chapter 13 Progress and Performance Measurement and Evaluation
13
PCIB = .60
Appendix problems not bothered with, as we will not use the 50/50 or 1-100% rules in DS856.
14
PROJECT MANAGEMENT: THE MANAGERIAL PROCESS
View more...
Comments