CH 7-Overtime Curves

July 21, 2022 | Author: Anonymous | Category: N/A
Share Embed Donate


Short Description

Download CH 7-Overtime Curves...

Description

 

Ch  7

Overtime Curves Rate of  slow down in  Productivity due to  Overtime Fatigue

Overtime Curves Productivit y Rate - 2hr over time load

100%

100% 95% 93%

  y   a    d    /   e    t   a   r   n   o    i    t   c   u    d   o   r    P

91%

89%

87%

85%

80%

83%

81%

80%

79% 79 %

79% 79 %

78%78%

60%

40%

0

2

4

6

8

10

12

14

Days

1

 

Ch  7

Overtime Curves Productivity Rate Rate - 4hr over time lo load ad 100%

100% 95% 93%

91%

88% 86% 83%

  y   a    d    /   e    t   a    R   n   o    i    t   c   u    d   o   r    P

81%

80%

78%

76% 73%

72% 70%

68%

60%

40% 0

2

4

6

Days

8

10

12

14

Overtime Curves

2

 

Ch  7

Overtime Curves Duration curve to reach  zero added production  in a 2hr O. O.T T work    

x=0

y= b=

ax + b 125

x=14

out of

125

0.8

y=

100

14a= x= at 2 HR

y=

‐25

 

‐1.8

 

‐1.8

 

x +

125

At y=

100

1.8

x

=

25

x

=

14.0

Overtime Curves Duration curve to reach  zero added production  in a 2 hr O.T O.T work y‐axis 150% 125%

y = 100% 100%

y =   125%  ‐ 1.8 x

50%

Prod   day

(0,0)

2

4

6

8

10

12

14

16

18 18

20

x‐axis

3

 

Ch  7

Overtime Curves Duration curve to reach  zero added production for 2hr O. O.T T work

Calculated  days for zero additional production

 

x =

14.0

The average extra daily production 

125 + 0

/2

days 12.5 %

Overtime Curves Duration curve to reach  zero added production for 2hr O. O.T T work To impose a net additional production of  20%

 

120

Av y

At day 1

125

Max Y

Select

115

Min Y

Find x =

5.6

days

Calculate the days for this scenario

4

 

Ch  7

Overtime Curves Duration curve to reach  zero added production  in a 2hr O. O.T T work Decisions to be made

A

add few laborers,  or

B

make OT shifts per each alternating crew, or

C

let all laborers  work OT  before they reach zero additional Production

Overtime Curves  –  – Plaster Example Given

 

Forecasted  quantities of  plaster  Existing crews

4 crews x

62,000.00  ms 6 laborer

Average rate

3.00  $/hr

Normal working time

8.00  hr/day

To date total production

Required

24.00  Lab

42,000.00  ms

Number  months incurred

4.00  mth

Av production rate / laborer /hr

1.95  ms/hr

Av Prod / mth 1‐GM asks for an increase  of  40%  production for the next coming   month (4 weeks)

10,500.0 ms/mth 14,700.0

2‐ Extra OT cost rate is 1.25 3‐ avoid working times more than 2 hrs a day

5

 

Ch  7

Overtime Curves  –  – Plaster Example Scenario A

 

1‐   Use additional 12 laborer

Prod factor=

12 24.0

 

percent increase

50.00 %

deduct crowding   impact  8%

Net Increase

42.00 %

2‐   No Overtime  usage crews  No 3‐   NO over Time factor

36.0 0%

Total percent  increase 

42.00 %

Total new Prod /lab/hr

2.77 ms

Total new Prod /mth/crews

14,910.0  ms

Remaining  Production Needed

210  ms

Overtime Curves ‐  Plaster Example Cost A

 

Add laborer cost 

day

rate/ hr

28 x 12

336

OT. OT. cost 

day

OT.rate/ hr

add/1 lab

NA

NA 

3.00 

Add.Cost 8,064.00  Add.Cost

add/ x lab

Total Add Cost

8,064.00 

6

 

Ch  7

Overtime Curves ‐  Plaster Example Scenario B

 

1‐   Use additional  4 laborers

Prod factor=

4 24.0

percent  increase

16.67 %

2‐   Split the crew  into 2 groups  and use weekly alternating OT shifts

crews  No

28.0

3‐   Use the curve  of  y = ‐1.8x + 125

x=7 y=

113 %

Av production

118.8 %

percent  increase  / week 

18.8 %

percent  increase  / week /crew

9.4 % 

Total percent  increase 

26.0 %

Total new Prod /lab/hr

2.46 ms

Total new Prod /mth/crews

13,234.4 ms

Remaining Production Needed

‐1,466  ms

 

Overtime Curves ‐  Plaster Example Cost B

 

Add laborer cost 

day

rate/ hr

28 x 4

112

3

OT OT.. cost 

day

OT.rate/ hr

Add.Cost 2,688.00  Add.Cost

28

0.75 

add/1 lab

1

3.75 

7.50 

add/ 14 lab x 28 d

14

2.00 

2,940.00 

Total Add Cost

5,628.00 

7

 

Ch  7

Overtime Curves ‐  Plaster Example Scenario C

 

1‐   Use the 0 laborers

Prod factor=

0 24

 

percent increase 0.00 2‐   Split the crew  into 2 groups and use  2 days OT shifts alternating OT shifts crew  No 24 3‐   Use the curve of  y = ‐1.8x + 125 x=2 y= 121 Av production 123.2 percent  increase  / week  23.2 percent  increase  / week /crew 11.6 Total percent   increase   11.6 Total new Prod /lab/hr

%

% % % % %

2.18  ms

Total new Prod /mth/crews Remaining  Production Needed

11,718.8  ms ‐2,981  ms

 

Overtime Curves ‐  Plaster Example Cost C

 

Add laborer cost 

OT. OT. cost 

day

rate/ hr

Add.Cost

0

3

NA

day

OT.rate/ hr

Add.Cost

28

0.75 

add/1 lab

1

3.75 

7.50 

add/ 12 lab x 28 d

12 12

2.00 

2,520.00 

Total Add Cost

2,520.00 

8

 

Ch  7

Overtime Curves Decisions to be made Still you can come up with other scenarios and assess the  optimal production increase  rate and its cost impact. Note that sometimes  GMs prefers to pay a penalty that is  cheaper than involving additional OT rates and OT staff  fees.

Overtime Curves Decisions to be made Scenario

% recovery

Total Add Cost

A ‐ Plaster

42

%

8,064.00 

B ‐ Plaster

26

%

5,628.00 

C ‐  Plaster

12

%

2,520.00 

D ‐ Plaster (pay Penalty)

0

%

7,500.00 

A ‐ Tiles

25

%

4,704.00 

B ‐ Tiles

35

%

9,408.00 

C ‐  Tiles

11

%

1,680.00 

D‐ Tiles (pay Penalty)

0

%

5,000.00 

9

 

Ch  7

Overtime Curves Decisions to be made YOU YO U  ARE  THE ONE  TO MAKE  A  PROPER  DECISION,  AND NOT  ANY  COMPUTER  SYSTEM

10

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF