Upstream network 63kV Short-circuit power 2000 MVA
T2
T1
G1
15 MVA
20 MVA
Usc Us c =1 =10% 0%
Usc Us c =1 =10% 0%
CB1
15 MVA
G
CB2
Usc Su Usc Sub b =1 =15% 5% Usc Tra Trans= ns= 20% 20%
CB3 10KV 10K V bu busb sbar ar
10KV 10 KV bu busb sbar ar
Subs Su bsta tati tion on A
CB4
CB5
T4
T5
CB6
15 MVA
15 15MVA MVA
Usc=10%
Usc=10% Usc=10%
CB18
CB7 In each each subst substation ation 1 single transformer in operation
11 km km Su Subs bstat tation ion Subst Su bstat ation ion B B
CB19
0.5 0.5 km km Subs Su bsta tatio tion nC Subst Su bstat ation ion C
CB10
CB11
T8 5 MVA
3KV
CB8
5 MVA
Usc=8%
CB9
T6
T9
T7
Usc=8%
CB16
10 MVA
10 MVA
Usc=8%
Usc=8%
CB17
3KV CB12
CB13
3KV MV network design & devices selection
Answ An swer er Bo Book ok – Oc Octt 20 2008 08
11
Choice of cables for substations B and C (detailed method cont’d.)
Exercise 6 Substation A
Single-pole AI – PR cables, buried directly in dry, calcareous ground, temperature 20°C, continuous operation,
10KV busbar
CB6
Substation B :
Operational current Ir: 577 A 10 MVA 10 kV 3 2 cables in // imposed Installation mode factor = 1 column 1 Temperature factor = 1 Proximity factor = 0.75 Ground factor = 1
11 km km Substation SubstationB B CB9 T7
CB8 T6
10 MVA Usc=8%
10 MVA Usc=8%
Chosen theoretical currents:
CB13
CB12
577 : 0.75 = 770 A i.e. 385 A per cable column 1: 1852 = 380A 2402 = 440A
3KV 2
cables to substation B: 2 x 240 mm per phase (14% remaining for possible extension)
Substation A
10KV busbar
Substation C Operational current Ir: 288 A Installation mode factor Temperature factor Proximity factor Ground factor
5 MVA 10 kV
= = = =
CB7
3
1 1 1 1
0.5 0.5 km km Substation Substation C C CB11
CB10
Chosen theoretical currents:
T9 5 MVA
T8 5 MVA
288 : 1 = 288 A
Usc=8%
Usc=8%
column 1 952 = 260 A 1202 = 300 A cables to substation C: 1 x 120 mm2 per phase
CB17
CB16 3KV
MV network design & devices selection
Answer Book – Oct 2008
21
Verification of short-circuit current withstand of cables
Exercise 6
Upstream protection circuit breaker tripping time: 0.4 sec. Permissible temperature rise in cables: 160°(+90°=25 0°) Isc S> k t S>
with k = 94
23689 0.4
= 159.45 mm 2
94
The cable planned for Substation C (120 mm2 ) would not withstand the short-circuit currents. It should have a cross-section of 185 mm2 ●
Calculation of short-circuit currents in substations B and C
●
Impedance of the 2 cables of substation B 1000 m of 2 x 240 mm2 R=ρ
L 3 1000 = 36.10− • = 0..15Ω S 240
i.e. for the two cables in parallel R = 0.075 Ω - Calculation of reactance x = 0.15 Ω /km i.e. for the two cables in parallel X = 0.075 Ω - Calculation of impedance:
Z = ●
0. 075 2 + 0 .075 2 = 0.1060 Ω
Impedance of the cable of substation C
500 m of 1 x 185 mm2 − 3 500 L = = 0 . 0973 Ω A single cable R = ρ 36 . 10 . 185 S Calculsations to be done according to verification of results.
X = 0 .15 Ω / km = MV network design & devices selection
Thank you for interesting in our services. We are a non-profit group that run this website to share documents. We need your help to maintenance this website.