Cable Pulling Methods.pdf

June 30, 2018 | Author: Vasudev Agrawal | Category: Coaxial Cable, Electrical Conductor, Insulator (Electricity), Rope, Duct (Flow)
Share Embed Donate


Short Description

Download Cable Pulling Methods.pdf...

Description

TITLE:

Engineering Specification RECOMMENDED: APPROVED: REV. DATE:

K. McRoberts C. S. Malone P. Eng. 2008-12-03

NO:

GCS0004

1 OF 15

REV:

1

XLPE CABLE INSTALLATION 15kV, 28 kV, 1000V AND 600V CABLES

See Hydro Ottawa’s Web site for the Latest revisions revisions at: www.hydroottawa.com

For Hydro Ottawa Use Only © 2008

GCS0004 Rev.1

Page 1 of 15

REVISION SHEET

Revision

Description

Date

0

Original Document

2002-09-30

km/csm.

1

Sections added / Corrected Table 3-3 metric SWBP RWU table added / 5-2 Ref. to direct buried plant removed

2008-12-03

kh/km/csm

For Hydro Ottawa Use Only © 2008

GCS0004 Rev.1

Initial

Page 2 of 15

TABLE OF CONTENTS

PAGE

1.0

INTRODUCTION........................................................................ ..................................... 4

2.0

REFERENCE................................................... ................................................................. 4

3.0

SCOPE ............................................................................................................................... 4

4.0

CABLE PULLING METHODS ................................................. ..................................... 4

5.0

PREPARATION ............................................................................................................... 5

6.0

LUBRICANT............................................................. ........................................................ 5

7.0

CABLE PULLING....................................................................... ..................................... 6

7.1 7.2 7.3 7.4

ONE WAY PULL IN ................................................... ........................................................ 6 ONE WAY FEED IN ................................................... ........................................................ 8 TWO WAY PULL .............................................................................................................. 9 AFTER THE PULL ............................................................................................................ 10

8.0

CABLE IDENTIFICATION ......................................................................................... 10

9.0

CABLE TRAINING ................................................. ...................................................... 10

10.0

CABLE RACKING .................................................. ...................................................... 11

11.0

SECONDARY SERVICES ............................................... ............................................. 11

APPENDIX A .............................................................................................................................. 12

For Hydro Ottawa Use Only © 2008

GCS0004 Rev.1

Page 3 of 15

1.0

Introduction

This specification covers the installation of primary voltage, 15kV & 28kV XLPE cables ranging from 1/0 AWG aluminum/copper conductor through to 1000 kcmil aluminum conductor and 600V secondary aluminum triplex cables ranging from 1/0 AWG aluminum to 500 kcmil aluminium/copper which comply with Hydro Ottawa Engineering Specification document number GMS0005 and GMS0008. These cables shall be installed in a concrete encased duct and manhole system, or a direct buried duct system. For cable pull in duct, the cable-duct configuration shall be determined/approved by Hydro Ottawa.

2.0

Reference

Hydro Ottawa - ECS0002: 120/240V Underground Residential Meter Socket Hydro Ottawa - GCS0012: Electrical Underground Distribution Plant Identification U/C Hydro Ottawa - GMS0005: Underground Secondary Hydro Ottawa - GMS0008: Underground Primary XLPE Concentric Neutral Cable Hydro Ottawa - UTS0004: Single – Phase Padmount Transformer 2.4kV-16kV – Secondary Wiring Detail Hydro Ottawa - UTS0005: Single – Phase Padmount Transformer 2.4kV – 16kV – Primary Wiring Detail Prysmian – Handling and Installation Excerpt from Prysmian’s Wire and Cable Engineering Guide

3.0

Scope

This specification covers how Hydro Ottawa and its contractors are to install underground cables for Hydro Ottawa as well as maximum pulling tensions and sidewall bearing pressures.

4.0

Cable Pulling Methods

Cable that cannot be pulled in manually shall be installed by means of a cable puller, an electric winch or a winch on a radial boom derrick. In each case, the machine operator shall have access to a means of determining the pulling tensions on the cable (e.g. gauges which indicate direct line pressure or gauges which indicate hydraulic pressure which can be converted to line tension via a conversion table or a dynamometer). Cable pulling with trucks, backhoes or any other method whereby the amount of pulling tension is not measurable, is unacceptable.

For Hydro Ottawa Use Only © 2008

GCS0004 Rev.1

Page 4 of 15

5.0

Preparation

First, establish the direction of the pull based on safe pulling tensions, sidewall bearing pressure calculations and minimum bending radius for a Hydro Ottawa specific cable to be installed; see Appendix A Tables 5-1, 5-2, 5-3, 5-4, 5-5A & 5-5B. Based on the safe pulling tension, determine if the cable pull requires a basket grip or a pulling eye attached to the conductor; see Appendix A Table 5-1. Basket grips or pulling eyes shall be attached to the pulling rope or cable by an appropriate sized swivel head. Rod each duct with an appropriate size brush and mandrel to ensure ducts are properly fitted and they are clean and free of all dirt, stones, scale, water etc. For installation in conduit, place cable guides wherever necessary to avoid abrasion and/or damage to the cable e.g. when guiding the cable from the reel to the duct mouth or trench, when passing through or exiting manholes, when exiting a duct run. Cable guides shall be in the form of large diameter, smooth-surfaced free turning sheaves or rollers. They shall be designed to ensure that cable will not ride off the end of the roller or be pinched into a sheave contour. Guide tubes or chutes may be used provided they have a smooth burr-free working surface, well flared entrances, largest possible bending radius and are securely fastened so that the cable passes smoothly over them. In any case, equipment shall be installed to ensure the minimumbending radius of the cable is not exceeded; see Appendix A Tables 5-5A & 5-5B. Using suitable reel mounting equipment, locate and position the reels such that cable tension at the feeding end is minimized. Select pulling equipment, which can provide smooth speed control at the anticipated tensions. Ensure the pull rope or flat line has the required tensile rating. Avoid the use of elastic materials.

6.0

Lubricant

Pre-lubricate duct runs or setup lubrication points along the duct run (e.g. feed in point, manholes etc to reduce pulling tension and abrasion to the cable jacket). For long heavy pulls, prelubrication of conduit and pull rope is essential to prevent abrasion at the bends, particularly plastic conduit bends, which can become softened due to frictional heating. In the case of long duct lengths or excessive curvatures in the duct the cable may have to be pulled in from two directions. The recommended amount of lubricant is depended on the size and length of the conduit system into which the cable is being pulled. Typically, a ratio of 6.4 liters of lubricant per 100 linear meters of 100 mm PVC duct would be used. Hydro Ottawa will accept water-based Bentonite Clay lubricants. Compounds containing oils or greases are not acceptable since they can adversely affect the cable jacket. The following chart provides a list of pulling lubricants, which are acceptable to Hydro Ottawa. Lubricant not shown on this chart, shall not be used without prior approval by Hydro Ottawa. For Hydro Ottawa Use Only © 2008

GCS0004 Rev.1

Page 5 of 15

TABLE 6-1

Cable Pulling Lubricants

Product Trade Name Polywater J Cable Glide

7.0

Manufacturer American Polywater Corporation CRC Industries

Cable Pulling

Poly rope is not to be used for any mechanical pulling (e.g. conductor/winch line, overhead or underground). Poly rope stretches when subjected to high tension and can create a hazard. Manual pulling (by hand) using poly rope is allowed. When using a mechanical means to complete a pull, (e.g. capstan, collapsible wheel, clutch-able capstan, boom, vehicle), a Samson rope or equivalent, flat line, shall be used, as it does not stretch in the same way that poly rope does, and presents less of a hazard. Provide two-way voice communication and adequate resources at both feeding and pulling ends of the run and at any interim location (e.g. manhole). Apply pulling lubricant liberally during the cable pull. To minimize back reel tension accelerate slowly and smoothly from rest to a constant pulling speed of approximately 30 m/minute. Avoid stopping the pull midway through the installation; the drag due to friction is greatly increased when pulling is restarted. Record dynamometer readings at frequent intervals during each pull.

7.1 One Way Pull In

Position the pulling equipment at the pulling manhole or transformer base. Set up equipment to maintain the minimum-bending radius of cable being pulled. See example in Figure 7-1 and Figure 7-2.

For Hydro Ottawa Use Only © 2008

GCS0004 Rev.1

Page 6 of 15

Figure 7-1

Pull End Setup for XPLE cable – Transformer Base

Figure 7-2

For Hydro Ottawa Use Only © 2008

Pull End Setup for XLPE cable – Manhole

GCS0004 Rev.1

Page 7 of 15

7.2

One Way Feed In

Position the cable reel so that the cable can be handfed into the manhole. When possible the cable shall be pulled off the reel by hand to reduce pulling tensions; see Figure 7-3 and Figure 7-4.

Figure 7-3

Reel End Setup for XPLE cable – Transformer Base

Figure 7-4

Reel End Setup for XLPE cable – Transformer Base

For Hydro Ottawa Use Only © 2008

GCS0004 Rev.1

Page 8 of 15

7.3 Two Way Pull

Position the cable reel near the center of your pull and pull required cable one way according to all tension guidelines and pertinent specifications; see Figure 7-5.

Figure 7-5

Initial Setup for 2-way Pull

Back reel cable length required for pull in other direction on debris free ground or a tarp in a coil formation, large enough to not exceed minimum cable bending radius; see Figure 7-6.

Figure 7-6

Back reel cable in a coil formation

Position puller at pulling end and begin pulling. Maintain slack loop of cable at feed end into duct structure; see Figure 7-7.

For Hydro Ottawa Use Only © 2008

GCS0004 Rev.1

Page 9 of 15

Figure 7-7

Final Setup for 2-way pull

7.4 After the Pull

Seal the ends of the installed cable and the ends of unused cable remaining on the reel, pending splicing or terminating, to prevent ingress of moisture. Observe the minimum-bending radius when training cable into final position. Secure cables to manholes, riser poles, etc., as per Hydro Ottawa Engineering Specifications. Provide suitable mechanical protection during project construction for exposed cables.

8.0

Cable Identification

All cables shall be identified as per Hydro Ottawa specifications GCS0012, UTS0004, UTS0005, and ECS0002.

9.0

Cable Training

At transformer bases and primary pedestals, primary cables shall be trained from the bottom of the base to the elbow insert. Care should be taken in order to install elbow compression connectors with the proper turn to fit the insert, cables are not crossed or tangled with adjacent cables. Freedom of movement for energized switching operations is essential; see Hydro Ottawa Engineering Specification UTS0005. Secondary cables shall be trained from the bottom of the transformer base to the secondary bus of the transformer with care taken to ensure cables are not crossed and do not cause a downward force on the transformer bus bars; see Hydro Ottawa Engineering Specification UTS0004.

For Hydro Ottawa Use Only © 2008

GCS0004 Rev.1

Page 10 of 15

10.0 Cable Racking Hydro Ottawa shall determine the cable racking method and location to be used. Cables in manholes and switchgear bases shall be racked along the wall of the structure using Hydro Ottawa approved tray and support system. The minimum bending radius of cables shall not be exceeded; see Appendix A Table 5-5A & 5-5B.

11.0 Secondary services Secondary cables are to be pre-installed to lot lines staked up to a suitable support (1 m onto private property with a minimum 2 m of cable tail) and their ends sealed with SelfAmalgamating Polyethylene (SAPP) tape to prevent the ingress of moisture.

For Hydro Ottawa Use Only © 2008

GCS0004 Rev.1

Page 11 of 15

   A    X    I    D    N    E    P    P    A

  n   o    i    t   s    l   n   a   o   u   s    i   s    I   n   n   e    E    T    P   g    L   n    X    i  ,    l    l    t   e   u   c    P    k   a   e    l    J    b    C   a    C    V    P  ,   s   m    l   e   u    b   m   a    i   x    C   a   e   g   a    M    t   -    l   o    1   -    V    5   y   e   r   a    l   m    b    i   a   r    T    P

  n   o    i   s   n   e    T   g   n    i    l    l   u    P   m   u   m    i   x   a    M

   *   s    *    l    9   3   7    l   m   a   2    6   0    5   7    9   2   4   5   u   r    6    6    0    9   g    P   o  ,    7   9  ,    6  ,    4  ,    2  ,    1    4    3    5    7    l   r   i   o    t   c   K   u    d   n   s   o    0   0    0   0   0   0    C   d    0   0    0   0    2    9    3    0   n    0    0   e    3    6    1  ,    0  ,    0  ,   u  ,  ,  ,    1  ,    2   e    6   o    2    1    2    8   e   r   P    1    1    1   y   h    E   T   g   n    i   s    l    l    l   u   l    4   2   9   u   m   a    P   P    3   3   5    9   1   2   2   r    6    2    8    8    4  ,    8  ,    7  ,    6  ,   r   g   o   5   3   4   2    1    2    3   o    l    i    t   c   K   u    d   n   o    C  s    0   5   5   0   0   0   0   e   d    l    0   0   0   0   n    4   6   g   u   6    1    0    5  ,  ,  ,    0  ,    0  ,    0  ,    8   n   o   1    1   5    4    6    8    i    P    S   s    *    l    l   m   2    9   6   6   u   a   5   7   6   0    9   2   3   3    P   r    6    6   g   0  ,    7   9   9  ,    6  ,    5  ,    5  ,   r   l   o   1    4    3    4    4   o    i    t   c   K   u    d   n   o   s    C   d    0    0   0   0   0    0   0    0    0    0   e    2    9    3    0   n   e    0    0    3    6    1  ,    0  ,    0  ,   u   r   p  ,  ,  ,  ,    0   0    i   o   2   1   2   0    8   r    h    1    1    1    P    G   T    t   e    k   s   s    l   a   l   u   m    4   2   9    B   P   a    3   3   5    9    1   2   2   r    6    2   8   8   4    8   r   g  ,  ,    7  ,    6  ,    5    3    4   o   o   l    2    1    2    3    t    i   c   u   K    d   n   o    C  s    0   0   0   0   e   d   0    5   5    l    6   0   0   0   0    4   g   n   6    1    0  ,    8  ,    5  ,    0  ,    0  ,    0  ,   n   u   1    i    1    5    4    6    8   o    S   P   e   p   y    T    &   e   z    i    S   r   o    t   c   u    d   n   o    C

  m   m  u   m  m   m   n   u   u   i   u   u   r    i   n   i   n   r   n   n   e   e   i    i   p   m  m  m   u   p   m  m  p   u   u   l   p   l    l    l   u   u   o   o    l    A   A   A    l    i    C   A   A   C    l    i    l    i    l    i   m    G   G   G  m  m  m  c    W    W    W  c   c   c   K    A   A   A   K   K   K   0    0   0   0   0    0    /    0    /    0    /    0   0   5   0    1   1   2   5   5   7   1

   5    1    f   o    2    1   e   g   a    P

   1  .   v   e    R    4    0    0    0    S    C    G

  r   o   r    t   o   c    t   u   c   d   u   n    d   o   n   c   o   c   r   e   r   e   p   p   e   p   y    i   r   e   g   g   n    t   e   i    l    l    k   u   s   a   p    b   1    1   r   r    f   o   o    f   e   r   e   a   r   a   s   s   n   n   i   o   o   s    i   s   n   e   n   e   T    T   * *   *

   8    0    0    2    ©   y    l   n    O   e   s    U   a   w   a    t    t    O   o   r    d   y    H   r   o    F

APPENDIX A (con’d)

Table 5-2 Maximum Cable Pulling Tensions Secondary Voltage Cables, 600V, XLPE Insulation

Conductor Size & Type

1/0 AWG Aluminum URD 3/0 AWG Aluminum URD 250 Kcmil Aluminum URD 500 Kcmil Aluminum URD

Maximum Pulling Tension Basket Grip Pulling Eye Single Cable Pull* Single Cable Pull** Pounds Kilograms Pounds Kilograms 1,690 767 1,690 767 2,000 907 2,684 1,217 2,000 907 4,000 1,814 2,000 907 8,000 3,629

* Tensions are for 1 basket grip per triplexed cable ** Tensions are for 1 pulling eye per conductor

Table 5-3 Maximum Cable Pulling Tensions Secondary Voltage Cables, 1000V RWU

Conductor Size & Type

2 AWG RWU Copper 2/0 AWG RWU Copper 4/0 AWG RWU Copper 350 Kcmil RWU Copper 500 Kcmil RWU Copper

Maximum Pulling Tension Basket Grip Pulling Eye Single Cable Pull* Single Cable Pull** Pounds Kilograms Pounds Kilograms 1458 660 1458 661 2000 907 2928 1328 2000 907 4654 2111 2000 907 7700 3493 2000 907 11000 4990

* Tensions are for 1 basket grip per triplexed cable ** Tensions are for 1 pulling eye per conductor

For Hydro Ottawa Use Only © 2008

GCS0004 Rev.1

Page 13 of 15

Table 5-4 Maximum Sidewall Bearing Pressure Primary Voltage Cables, PVC Jacket, XLPE Insulation Sidewall Bearing Pressure Conductor Size & Type

1/0 AWG Copper 1/0 AWG Aluminum 2/0 AWG Aluminum 500 Kcmil Copper 500 Kcmil Aluminum 750 Kcmil Aluminum 1000 Kcmil Aluminum URD Aluminum RWU Copper

Lbs/Ft of Bend Radius

Kg/m of Bend Radius

1,160 845 1,065 2,000 2,000 2,000 2,000 1200 1200

1726 1258 1585 2976 2976 2976 2976 1786 1786

Table 5-5A Minimum Bending Radius (MBR) During Installation* Primary Voltage Cables, XLPE Insulation Conductor Size & Type

1/0 AWG Copper, 15 kV 1/0 AWG Aluminum, 28 kV 2/0 AWG Aluminum, 28 kV 500 Kcmil Copper, 15 kV 500 Kcmil Aluminum, 28 kV 750 Kcmil Aluminum, 28 kV 1000 Kcmil Aluminum, 28 kV

Minimum Bending Radius Minimum Bending Radius (mm) (inches) 354 14 411 16

433 506 564 634 698

17 20 22 25 27

*Based on 12 x Cable Diameter

For Hydro Ottawa Use Only © 2008

GCS0004 Rev.1

Page 14 of 15

Table 5-5B Minimum Bending Radius (MBR) Permanent* Primary Voltage Cables, XLPE Insulation Conductor Size & Type

1/0 AWG Copper, 15 kV 1/0 AWG Aluminum, 28 kV 2/0 AWG Aluminum, 28 kV 500 Kcmil Copper, 15 kV 500 Kcmil Aluminum, 28 kV 750 Kcmil Aluminum, 28 kV 1000 Kcmil Aluminum, 28 kV

Minimum Bending Radius Minimum Bending Radius (mm) (inches) 236 9

274 289 337 376 423 465

11 11 13 15 17 18

*Based on 8 x Cable Diameter

For Hydro Ottawa Use Only © 2008

GCS0004 Rev.1

Page 15 of 15

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF