BUILT-UP RATE FOR SCREEDING TENDER FILE NO : PROJECT :

LOCATION : SUPPLIER :

SUB-CONTRACTOR : QUOTATION DATE : Material Cost Cement Sand (ex-mining)

10.35 per bags 50kg ( Including Rm 0.25 for unloading ) 250.00 per loads ( 14 cu. yard ) or 23.48 per m3

Cement & Sand ( 1:3 ) Mixed

Material Cost

Cement ( 1440kg/50 ) @ 1 m3 White Lime ( 1 bag / 100 ft2 ) Sand Total cost For 4 m3

29 bags 0 bags 3 m3

@ @ @

Net volume after shrinkage @ 33 1/3%

3.23 per m2 2.20 per m2

Screeding Material cost Wastage @ Total material cost / m2 Labour Cost Plant Cost ( Inclusived ) Tender Cost / m2

5%

300.15 70.45 370.60 2.67 m3

Material cost per m3 Plant cost ( Concrete mixer @ 3.00/m3 ) Total Cost : Labour Cost Base screed Labour Cost

10.35 0.00 23.48

138.90 3.00 141.90

( 0.30 per ft2 ) ( 0.20 per ft2 )

Cost / m2 20mm thk 25mm thk 2.84 3.55 0.14 0.18 2.98 3.72 2.20 2.20 5.18 5.92