MEMBINA JALAN BARU DARI KAMUNTING KE ANAK KURAU, DAERAH LARUT MATANG & SELAMA, PERAK DARUL RIDZUAN (FASA 1) ITEM NO 1 1.1
1.2
DESCRIPTION OF WORKS
UNIT
QTTY
PILING (300mm dia. MICRO-PILES) Allow for mobilization and demobilization of all labour, plants, piling and drilling equipments, etc. on site, for the proposed piling works.
SUM
Drilling of holes through soil a) Drill 300mm dia. Vertical holes through whatever soil strata M
185
M
185
a) Drill 300mm dia. Vertical holes in rock.
M
120
b) Drill 300mm dia. Raked holes in rock.
M
120
permanent casing as shown in the drawing (or equivalent)
M
Rate Only
Steel pipe reinforcement as specified
M
610
Concrete Grade 30 to vertical bored piles
M3
341
Nr
20
Nr
1
Nr
6
Nr
20
other than rock with provision of temporary casing. a) Drill 300mm dia. Raked holes through whatever soil strata other than rock with provision of temporary casing. 1.3
1.4
1.5
1.6
Drilling of holes through rock
To supply and install 300mm diameter & 10mm thick
Cutting off piles head to required length including preparing pile head as shown in drawing.
1.7
Carry out initial maintained load test to twice working load of 1200 kN in accordance with the Specification.
1.8
Carry out pile driver analyser (PDA) in accordance with the Specification.
1.9
Carry out integrity test using sonic logging method in accordance with the specification.