BoostLi Energy Storage Module ESM-48100U2

User Manual Issue

01

Date

2020-06-30

HUAWEI TECHNOLOGIES CO., LTD.

 

  Copyright © Huawei Technologies Co., Ltd. 2020. All rights reserved. No part of this document may be reproduced or transmitted transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd.  

Trademarks and Permissions  and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd. All other trademarks and trade names mentioned in this document are the property of their respective holders.  

Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specied specied in  in the contract, all statements, information, and recommendations in this document are provided "AS IS" without warranties, guarantees or representations of any kind, either express or implied. The information in this document is subject to change without notice. Every efort efort has  has been made in the preparation prepar ation of this document to ensure accuracy of the contents, but all statements, information, and recommendationss in this document do not constitute a warranty of any kind, express or implied. recommendation  

Huawei Technologies Co., Ltd. Address:

Huawei Industrial Base Bantian, Longgang Shenzhen 518129 People's Republic of China

Website:

https://e.huawei.com

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

i

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

About This Document

 About This Document Document Overview This document describes the BoostLi series lithium-ion energy storage module ESM-48100U2 (ESM for short) in terms of its overview, application scenarios, external ports, working principles, installation, and commissioning. Figures provided in this document are for reference only.

Intended Audience This document is intended for: ●

Maintenance eng engineers



Sales engineers



Techn echnic ical al supp suppor ortt engi engine neer erss

Symbol Conventions The symbols that may be found in this document are dened dened as  as follows: Symbol

Description Indicates an imminently hazardous situation which, if not avoided, will result in death or serious injury. Indicates a potentially hazardous situation which, if not avoided, could result in death or serious injury Indicates a potentially hazardous situation which, if not avoided, may result in minor mi nor or moderate injury. Indicates a potentially hazardous situation which, if not avoided, could result in equipment damage, data loss, performance deterioration, or unanticipated results. NOTICE is used to address practices not related to personal injury.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

ii

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

Symbol

About This Document

Description Calls attention to important information, best practices and tips. NOTE is used to address information not related to personal injury, equipment damage, and environment deterioration.

 

Change History Changes between document issues are cumulative. The latest document issue contains all the changes made in earlier issues.

Issue 01 (2020-06-30) This issue is the rst rst  ocial ocial release.  release.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

iii

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

Contents

Contents  About This Document............. ....................... ....................... ...................... ...................... ...................... ...................... ...................... ...................... ..................... .......... ii This Document.. 1 Product Description.. Description............. ...................... ...................... ...................... ...................... ....................... ....................... ...................... ...................... ......................1 ...........1 1.1 Product Overview......... Overview.................... ..................... .................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... .................... ..................... ..................... ................... ......... 1 1.2 Application Application

Scenario...............................................................................................................................................................2

1.3 Appearance Appearance and Ports............................................................................................................................................................3 1.3.1 Appearan Appearance.......... ce.................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... .................... ..................... ..................... ..................... ..................... ..................... ................ ..... 3 1.3.2 Panel and and

Ports.....................................................................................................................................................................3

1.3.3 Activation Activation and Startup.... Startup.............. ..................... ..................... ..................... ..................... ..................... ..................... .................... ..................... ..................... ..................... ..................... ..................... ..................... ............ 7

2 Application Application Description... Description.............. ...................... ...................... ...................... ...................... ...................... ...................... ...................... ...................... ...............9 ....9 2.1 Parallel Connection Mode....... Mode.................. ..................... ..................... ..................... .................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ............... ..... 9 2.2 Online Expansion...... Expansion................ ..................... ..................... .................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... .................... ..................... ..................... .......... 10 2.3 Application Application in Class B Environm Environments ents with Direct Ventilation.................... Ventilation............................... ..................... ..................... ..................... ..................... .................. .......10 10 2.4 Low-Temperature Low-Temperature

Application...........................................................................................................................................10

2.5 Storage with Low SOC (≤ 5%)...... 5%)................ ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... .................... ..................... ..................... ................ ...... 11

3 Transportation Transportation and Storag Storage.......... e..................... ...................... ...................... ...................... ...................... ...................... ...................... .................... .........12 12 3.1 Transportation Transportation Requirement Requirements........... s...................... ..................... .................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... .................... ............. ... 12 3.2 Storage and Recharging.. Recharging............ ..................... ..................... .................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... .................... ..................... ............. 12 3.2.1 Storage Storage

Requirements......................................................................................................................................................12

3.2.2 Conditions Conditions for Judging Overdue Storage... Storage............. ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... .................... ................. ....... 13 3.2.3 Processing Before Recharge... Recharge............. ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... .................... ..................... ..................... ..................... ...........14 14 3.2.4 Recharge Recharge Solution...... Solution................ ..................... ..................... .................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... .................... ..................... ................ ..... 14 3.2.5 Quali Qualication cation  Standards for Recharge.. Recharge............ ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... .................... ..................... .............. ... 15

4 Installation Installation and Commissio Commissioning...... ning................. ...................... ...................... ...................... ...................... ...................... ....................... ................ .... 16 4.1 Tools................ Tools........................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... .................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ............... 17 4.2 Installation Installation an ESM....... ESM.................. ..................... ..................... ..................... ..................... ..................... .................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ............... .... 18 4.3 Cable Connections Connections (Huawei Power System)...... System)................ .................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ............ 19 4.4 Cable Connections (Third-P (Third-Party arty Power System)...... System)................. ..................... .................... ..................... ..................... ..................... ..................... ..................... ..................... .............. .... 23 4.5 Power-On Power-On Commissioning..... Commissioning............... .................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... .................... ..................... ..................... ............... ..... 26 4.5.1 Power Power-On -On (Huawei Power System)...... System)................ ..................... ..................... ..................... ..................... ..................... ..................... .................... ..................... ..................... ..................... .............. ... 26 4.5.2 Power Power-On -On (Third-P (Third-Party arty Power System)..... System)............... ..................... ..................... .................... ..................... ..................... ..................... ..................... ..................... ..................... .................. ........ 27 4.5.3 Power System Parameter Settings (Huawei Power System)..............................................................................27 4.5.4 Power System Parameter Settings (Third-Party Power System).......................................................................29 Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

iv

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

Contents

Criteria................. ..................... ..................... ..................... .................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... .................... ................ ...... 30 4.6 Acceptance Criteria......

5 Maintenanc Maintenance e Guide...... Guide................. ...................... ...................... ...................... ...................... ...................... ...................... ...................... ...................... .................31 ......31 5.1 Maintenance Method...... Method................. ..................... ..................... ..................... ..................... ..................... ..................... ..................... .................... ..................... ..................... ..................... ..................... ..................... ............. 31 5.2 Replacing an ESM........ ESM.................. ..................... ..................... ..................... ..................... .................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ..................... ................. ....... 33 5.3 Tr Troubleshoo oubleshooting....... ting..................... ............................ ............................ ............................ ............................. ............................. ............................ ............................ ............................ ............................ ............................ ................. ... 35

6 Deactivating of the Antitheft Function of the ESM..... ESM................ ...................... ...................... ...................... ................37 .....37  A Common Criteria... Criteria.............. ...................... ...................... ....................... ....................... ...................... ...................... ...................... ...................... ...................... ............. 39 B Warr Warranty anty Rules....... Rules.................. ...................... ...................... ...................... ...................... ...................... ...................... ...................... ....................... ....................... ........... 41 C Technical Specications Specications........... ...................... ...................... ...................... ...................... ...................... ...................... ...................... ...................... ............... ....43 43 D Acron Acronyms yms and Abbrevi Abbreviations........ ations................... ...................... ...................... ...................... ...................... ...................... ...................... ................... ........ 45

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

v

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

1 Product Description

1

 Product Description

1.1 Product Overview Overview The ESM is an energy storage unit composed of lithium batteries. It features better charge and discharge performance, longer service life, and less self-discharge loss than ordinary batteries. An ESM consists of electrochemical cells, an energy storage management unit (ESMU), power and signal terminals, and mechanical parts. It can be used as an independent 48 V unit, supports the mixed use of old and new batteries as well as lithium and lead-acid batteries, and can c an collaborate with third-party power systems. Table 1-1 Nominal 1-1 Nominal ESM voltage and capacity Product Model

Nominal Voltage

Rated Capacity

ESM-48100U2

48 V

100 Ah

 

Features ●

Parall Parallel el connec connectio tion n for for power power expan expansio sion: n: Th The e maximu maximum m power power (P) (P) of N ESMs ESMs connected in parallel can reach 24 kW k W. For details, see 2.1 Parallel Connection Mode. Mode.



Applic Applicatio ation n in class class B envir environm onment entss with with direct direct venti ventilat lation ion:: The ESM ESM can be used in indoor environments where the ambient temperature and humidity are not controlled or outdoor environments (with simple shielding measures such as awnings) where the humidity can reach 100%.



Suppor Supportt for third third-pa -party rty power power system systems: s: The ES ESM M impleme implements nts li lithi thium um batter battery y self-management so that it can be used with third-party power systems.



Mainte Maintenan nancece-fr free: ee: The The mainten maintenanc ance-f e-fre ree e fea featur ture e in the use use of the the ESM reduces the costs of battery O&M and the frequency of site visits



Long Lon g service service life life:: The ESM ESM service service life life of is is two to (SOH) tthr hree ee times tim esstate the the lif life e of com common mon lead-acid batteries. The battery state health and of charge

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

1

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

1 Product Description

(SOC) can be monitored online in real time. These features improve the reliability of site power backup. ●

Function

EMC: –

CE CE:: E EN N 550 55032 32/C /CIS ISPR PR32 32,, Cla Class ss A



RE RE:: E EN N 550 55032 32/C /CIS ISPR PR32 32,, Cla Class ss B



Status Status monitori monitoring: ng: monitors monitors the the electrochemi electrochemical cal cell voltage voltage and temperatur temperature e as well as the ESM voltage and current.



Alarm Alarm manage managemen ment: t: gener generate atess alarms alarms when when overvo overvolta ltage, ge, unde undervo rvolta ltage, ge, overcurrent, overtemperature, or undertemperature occurs.



Protec Protectio tion n against against except exception ions: s: protec protects ts against against overv overvolt oltage age,, undervol undervoltag tage, e, overcurrent, short circuits, ci rcuits, overtemperature, undertemperatur undertemperature, e, electrochemical cell faults, and hardware faults.



Information Information reporting: reporting: provides provides a northbo northbound und CAN/RS485 CAN/RS485 port through through which alarms and status data are reported.



Parall Parallel el conne connectio ction: n: Mu Multip ltiple le ESMs ESMs can can be conne connecte cted d in para paralle llel. l. CAN CAN communication supports parallel connection of up to 32 ESMs, and RS485 communication supports parallel connection of up to 16 ESMs.

● ●

Balanc Balance: e: supp support ortss realreal-time time electr electroch ochemi emical cal ccell ell bal balanc ancing ing.. E-label: identies identies the  the ESM using an electronic label.



Antith Antitheft: eft: provi provides des the the softwar software-b e-base ased d anti antithe theft ft functi function on when when being being us used ed with specied specied Huawei  Huawei power systems.



Forcib Forcible le discon disconnec nectio tion: n: Users Users can disc disconn onnect ect the the externa externall power power supply supply to tthe he PWR port and hold down the MANUAL ON/OFF button for 5s to power of  the ESM forcibly.



Mainte Maintenan nance ce mode: mode: used used for for ESM ESM repla replacem cement ent.. Users Users ca can n hold hold down down the the MANUAL ON/OFF button for 15s to enter the maintenance mode so that the ESM can be replaced safely and reliably.



Activat Activation ion:: The ESM ESM can can be activ activate ated d throug through h the PWR PWR port, port, power power port, port, and the MANUAL ON/OFF button.

1.2 Application Scenario The ESM provides backup power for a power system. It can be used alone or used with lead-acid batteries to back up power. power. Inside an ESM, an energy storage management unit (ESMU) monitors the status of temperature, current, and voltage, provides protection against overvoltage, undervoltage, overcurrent, short circuit, ci rcuit, overtemperature, and undertemperature, and reports the ESM running status and alarm information through a communications port that supports both the CAN and RS485 protocol.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

2

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

1 Product Description

Figure 1-1 Typical 1-1 Typical ESM application scenario

1.3 Appearance and Ports 1.3.1 Appearance Figure 1-2 ESM 1-2 ESM exterior

1.3.2 Panel and Ports Figure 1-3 ESM 1-3 ESM panel and ports

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

3

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

1 Product Description

Table 1-2 Port 1-2 Port pin denitions No.

Silk Screen

Item

Description

1

GND

Protective ground

M6 screw

2

DO 1

ESM dry contact output

Alarm output dry contact; congurable congurable (if  (if the dry contact is closed, an alarm is reported by default). 1-4.. For details, see Table 1-4 1. Used for information reporting and communication cascading.

DO2 3

COM_ IN

Communications port

4

COM_ OUT

Communications port

5

RUN

Run indicator

For the diagram, see Figure 1-5. 1-5.

ALM

Alarm indicator

For details about functions, see Table 1-5. 1-5.

CHG

Charge indicator

DCHG

Discharge indicator

SOC

SOC indicator

6

MANUAL ON/OFF

Button for manual power-on/of 

A contact button used for manual power-on/of  and maintenance. For details, see 1.3.3 Activation and Startup. Startup.

7

PWR

ESMU port for connecting to an external power source

The ESM can be activated if the PWR port is supplied with a voltage of 43.2–58 43 .2–58 V. For details, see 1.3.3 Activation and Startup Startup..

8

+

ESM positive positive terminal terminal

-

ESM negative terminal

Positive Positive and and negative negative ports of the the ESM. ESM. Secured Secured by M6 screws. Appropriate OT terminals should be used. The required torque is 4.5-5.5 N·m and the recommended cable size is 25 mm2. If the ESM is used at a temperature below 45°C, the cable c able size

2. Use RJ45 RJ45 terminals terminals and provi provide de the the 1000 A surge protection capability. For details, see Table 1-3. 1-3.

can be smaller but should be at least 16 mm2.   Figure 1-4 RJ45 1-4 RJ45 pins

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

4

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

1 Product Description

Table 1-3 Pin 1-3 Pin denitions denitions of  of communications ports RJ45 Pin

Signal

Description

Remark

1

RS485 T+

RS485 transmission +

2

RS485 T-

RS485 transmission –

● Four-wire RS485 communications, complying with the Modbus protocol.

3

NC

Reserved

4

RS485 R+

RS485 reception +

5

RS485 R-

RS485 reception –

6

NC

Reserved

-

7

CANH

Positive terminal for CAN communications

8

CANL

Negative terminal for CAN communications

Used to report alarms to a monitoring unit and exchange data between ESMs connected in parallel.

● Ba Baud ud ra rate te:: 9600 9600 b bit it/s /s..

 

DO1 and DO2 Ports Table 1-4 DO1 1-4 DO1 and DO2 port denitions Silk Screen

Denition

Description

Alarm Status

DO1

Fault, major alarm

If the ESM raises one of the following alarms, the dry contact supplies an alarm signal:

Congurable (If the dry contact is closed, an alarm is reported by default.)

Cell voltage sampling fault, cell temperature temperature sampling fault, charge converter output short-circuit, relay coil short-circuit, charge low temperature temperature protection, discharge low temperature protection, charge high temperature protection, discharge high temperature temperature protection, power module internal overtemperature protection, discharge converter output short circuit, input reverse connection, BMU anti-theft lock, overload lockout due to component failure, serial number conict, conict, input/output  input/output discharge overvoltage lockout, discharge overcurrent lockout, discharge overcurrent protection, and cell 1–N fault alarm DO2

Overload warning, overdischarge protection

If the ESM raises one of the following alarms, the dry contact supplies an alarm signal: Discharge undervoltage alarm, discharge undervoltage protection, discharge due to single-ESM cell low voltage disconnection, and heavy load warning

 

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

5

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

1 Product Description

LED Indicator Figure 1-5 LED 1-5 LED indicator

Table 1-5 LED 1-5 LED indicator description Silk Screen

Item

Color

Description

RUN

Run indicator

Green

Steady on: Communication is normal (including board startup, self-check, software loading, and board power-on when not loaded; excluding sleep when the power port or PWR port is energized). Of: The Of:  The ESM is in sleep mode. Blinking at long intervals: The LUI is querying data. Blinking at short intervals: Communication is interrupted.

ALM

Fault indicator

Red

Steady on: There is a fault or major alarm. Of: There Of:  There is no fault or major alarm.

CHG

Charge indicator

Green

Steady on: The ESM is being charged. Of: The Of:  The ESM is open-circuited or discharging.

DCHG

Discharge indicator

Issue 01 (2020-06-30)

Green

Steady on: The ESM is discharging. Of: The ESM is open-circuited or being Of: The charged.

Copyright © Huawei Technologies Co., Ltd.

6

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

1 Product Description

Silk Screen

Item

Color

Description

SOC

SOC indicators

Green

1. 0–24% capacity 25% indicator: blinking Other SOC indicators: of  2. 25%–49% capacity 25% indicator: steady on 50% indicator: blinking Other SOC indicators: of  3. 50%–74% capacity 25% indicator: steady on 50% indicator: steady on 75% indicator: blinking Other SOC indicators: of  4. 75%–99% capacity 25% indicator: steady on 50% indicator: steady on 75% indicator: steady on 100% indicator: blinking 5. 100% capacity The four SOC indicators are steady on.

Notes: ● Major alarm: alarm: The ESM needs needs to be maintained maintained immediat immediately ely.. ● Minor alarm: alarm: The ESM does does not require require maintenan maintenance, ce, but sends sends a reminder reminder to remote maintenance personnel. ● Blinking Blinking at long intervals: intervals: on for for 1s and then then of  for  for 1s ● Blinking Blinking at short short interva intervals: ls: on for 0.125s 0.125s and and then of  for  for 0.125s ● SOC SOC in indi dica cato torr of  and  and other indicators blinking at short intervals: The ESM has entered the maintenance mode. ● ESM in in sleep sleep mode: mode: The The fault fault indi indicat cator or is of  except  except for reverse-connection protection. ● In standb standby y mode, mode, the CHG and and DCHG DCHG indicators indicators are of  and  and the ESM is open-circuited.  

1.3.3 Activation and Startup An ESM can be activated in three modes. After being activated, the ESM switches from the sleep mode to disconnected mode. ●

Activat Activation ion thr throug ough h the PWR PWR termi terminal: nal: supp supply ly 43.2–5 43.2–58 8 V DC powe powerr to the the PWR terminal on the ESM panel for at least 5s.



Activat Activation ion thr throug ough h the MANU MANUAL AL ON/OF ON/OFF F button button:: hold hold down down the MANUAL MANUAL ON/OFF button on the ESM panel for at least 5s and less than 15s.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

7

 

BoostLi Energy Storage Module ESM-48100U2 User Manual



1 Product Description

Activat Activation ion thr throug ough h the pow power er port: port: suppl supply y a DC volta voltage ge of 43.2– 43.2–58 58 V to the the power terminal on the front panel for at least 5s.

1. The MANU MANUAL AL ON/OFF ON/OFF button is a cont contact act butt button. on. The interval interval for for pressing pressing the button should be greater than 0.5s; otherwise, the operation is inefective. 2. If y you ou ha have ve fforc orcibl ibly y pow power ered ed of  the  the battery that is in charging, discharging, d ischarging, or disconnected mode by pressing the MANUAL ON/OFF button, the ESM can be only reactivated by pressing and holding this button.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

8

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

2 Application Description

2

 Application Description

2.1 Parallel Connection Mode

ESMs can be connected in parallel to increase the backup time or backup power. power. Table 2-1 Power 2-1 Power derating coecients coecients for  for parallel connection Number of  Parallel ESMs (N)

2

3

4

5

6

7

8

9

......

16

Derating Coefcient

0.70

0.60

0.55

0.50

0.50

0.45

0.40

0.40

......

0.40

 

Maximum current of N  ESMs  ESMs connected in parallel = N  x  x Derating coecient coecient x  x Imax, where Imax is the maximum allowed ESM current. For example, if four ESMs are connected in parallel, the maximum current is 4 x 0.55 x 100 A = 220 A.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

9

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

2 Application Description

2.2 Online Expansion In the maintenance mode of the ESM, the system capacity or power can be expanded without disconnecting the battery supply so that the site will not break down in case of a mains power failure during capacity expansion.

2.3 Application in Class B Environments with Direct  Ventilation  V entilation The ESM can be used in class A or B environments with direct ventilation but cannot be used separately in class C or D environments. If the ESM needs to be used in class C or D environments, cabinets with air conditioners and a high IP rating (IP55 or higher) must be deployed. Environments subject to atmospheric corrosion can be classied classied into  into four categories: ●

Class A environ environment ment (controll (controlled ed environmen environment): t): refer refer tto o indoor indoor environmen environments ts where the ambient temperature and humidity are controlled (including rooms where people live) and the relative humidity of air is ccontrolled ontrolled below 65%.



Class Class B envir environm onment ent (unc (uncont ontro rolle lled d env envir ironm onment ent): ): refe referr to ind indoor oor environments where the ambient temperature and humidity are not controlled or outdoor environments (with simple shielding measures) where the humidity can reach 100%.



Class C enviro environment nment (harsh (harsh enviro environment nment): ): refer refer to o outdoo utdoorr land land envir environmen onments ts (with simple shielding measures) near seas or pollution sources. If a site is near a sea, it is 0.5–3.7 km away from the sea. If a site is near a pollution source, it is at most 3.7 km away from salt lakes, 3 km away from heavy pollution sources such as smelteries, coal mines, and thermal power plants, 2 km away from medium pollution sources such as chemical, rubber rubber,, and galvanization industries, or 1 km away from light pollution sources such as packing houses, tanneries, and boiler rooms.



Class envir environmen onment t (sea (sea environmen environment): t): refer ref er tto o outdoo o utdoor r land land envir onments ts (with D simple shielding measures) at most 500 m away from theenvironmen seashore or environments on the sea.

2.4 LowLow-T Temperature Ap Applicat plication ion ●

Low-te Low-tempe mpera ratur ture e chargin charging: g: The The ESM does does not not suppo support rt batte battery ry charg charging ing at at a temperature below 0°C. When the battery temperature is below 0°C, the ESM will shut down the charging loop to disable charging. When the ESM is used in an environment below 0°C, a heater needs to be added in the cabinet, and batteries can be charged after the battery temperature rises to 3°C or above.



Low-temper Low-temperatur ature e dischar discharging: ging: The ESM does not support support battery battery dischar discharging ging at aESM temperature –20°C. When theloop battery temperature is below –20°C, the will shut below down the discharging to disable discharging.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

10

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

2 Application Description

When the ESM is used in an environment below –20°C, a heater needs to be added in the cabinet, and batteries can be discharged after the battery temperature rises to –17°C or above.

2.5 Storage with Low SOC (≤ 5%) The ESM has application ESMU staticscenarios, power consumption and powerof. In of.  In actual avoid storing anself-discharge ESM with lowloss SOCafter (≤ 5%). If  unavoidable, limit the storage duration to 30 days at 25°C or 15 days at 45°C. Promptly recharge the ESM after the storage. Otherwise, the ESM may be damaged due to overdischarge, which requires replacing the ESM. The following situations may cause storage of ESMs in discharge state: 1.

After the site site power power suppl supply y is discon disconnected nected due to to a mains mains outage outage,, the power power supply is not recovered for a long time because the faults (such as cable faults) cannot be rectied rectied in  in a timely manner.

2.

After installation installation and commissioni commissioning ng are complete, complete, the mains power power is switched of  directly  directly without powering of  the  the ESM. The ESM can enter the low power mode only after being completely c ompletely discharged, and the interval for onsite acceptance check is long.

3.

Other Other reaso reasons ns resu result lt in that that the the ESM canno cannott enter enter the the low powe powerr mode mode normally.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

11

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

3 Transportation and Storage

3

 Transportation and Storage

3.1 Transportation Requirements The product passes the certications certications of  of the UN38.3 (UN38.3: Section 38.3 of the sixth Revised Edition of the Recommendations on the Transport Transport of Dangerous Goods, Manual Tests Criteria) SN/T 0370.2-2009 (Part 2: Performance Test of the Rulesoffor the and Inspection ofand Packaging for Exporting Dangerous Goods). This product belongs to class 9 dangerous goods. The product can be delivered to the site directly and transported by land and water.. The packing case must be secured for transportation, compliant with water related national standards, and printed with marks such as anti-collision anti- collision and moisture prevention. Dispose of waste ESMs in strict accordance ac cordance with local laws and regulations. Protect the packing case with the product from the following situations: ●

Being Being damp dampene ened db by y rain rains, s, sno snows, ws, or fallin falling g into into water water



Falli alling ng or mech mechan anic ical al im impa pact ct



Be Bein ing g ups upsid idee-do down wn or tilt tilted ed

3.2 Storage and Recharging 3.2.1 Storage Requirements 1.

Place ESMs according according to the the signs signs on the p packing acking case during during storage. storage. Do Do not put ESMs upside down or sidelong.

2.

Stack ESM packing packing cases cases by by complyin complying g with with the the stacking stacking require requirements ments on the the external package.

3.

The stor storage age envir environm onment ent requ requir ireme ements nts a are re as foll follows ows::

Issue 01 (2020-06-30)



Ambien Ambientt tem temper peratu ature re:: 0–40°C; 0–40°C; recom recommen mended ded stor storage age tempe tempera ratur ture: e: 20– 30°C



Relative hu humidity: ty: ≤ 95% Copyright © Huawei Technologies Co., Ltd.

12

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

3 Transportation and Storage



In a dry dry cle clean an place place with with prop proper er vent ventil ilat atio ion n



In a place place that that is is aw away ay from from corr corrosi osive ve an and d organ organic ic subst substanc ances es (incl (includi uding ng gas)



In a pla place ce fr free ee fr from om dir direct ect sun sunli ligh ghtt



At leas leastt 2 meters meters away away fro from m heat heat source sourcess (suc (such h as as a heater heater))

4.

The wareh warehouse ouse keeper keeper should should collect collect ESM ESM stora storage ge inform information ation every month and periodically report the ESM inventory information to the planning department. The ESMs that have been stored overdue should be recharged in a timely manner.

5.

Regional oces oces or  or organizations should not store ESMs or communication equipment congured congured with  with ESMs. Prior approval should be obtained for any requirement on ESM storage.

6.

ESMs ESMs sho shoul uld d be deli delive vere red d base based d on th the e "rst "rst in,  in, rst rst out"  out" rule.

7.

Install Install ESMs ESMs in a dry, dry, clean, clean, an and d ventilate ventilated d environ environment ment that is free free from from sources of strong infrared radiation, organic solvents, and corrosive gases. Do not expose the ESMs to sunlight or water and keep them far away from sources of ignition.

3.2.2 Conditions for Judging Overdue Storage It is recommended that the ESM not be stored for a long period. It should be used soon after being deployed onsite. Table 3-1 Storage 3-1 Storage requirements Required Storage Temperature 0–40°C

Recharge Interval

Remarks

0°C ≤ T ≤ 30°C

12 months

30°C < T ≤ 40°C

8 months

Not reaching the time for recharge: Use the ESM as soon as possible.

 Actual Storage Temperature

Reaching the time for recharge: Recharge the ESM. The total storage duration should not exceed the warranty period.

 

1. If ESMs have been stored overdue, overdue, promptl promptly y report the event to the department leader leader.. 2. Dispose of bulging bulging ESMs directly directly ir irresp respective ective of how long long they have have been stored. stored. 3. The storage storage duration duration (t) sta starts rts from from the latest latest charge charge time on the ESM package. package. The latest charge time is updated after every charge. 4. If an ESM ESM is is qualied qualied after  after charge, mark the latest charge time and the next recharge time on the ESM packing packi ng case. The next recharge time is 8 months (stored above 30°C) or 12 months (stored below 30°C) later than the latest charge time. The total storage duration should not exceed the warranty period.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

13

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

3 Transportation and Storage

3.2.3 Processing Before Recharge ●

Chec Check k th the E ESM SM appe appear aran ance ce..



Di Disp spos ose e of bul bulgi ging ng ESM ESMss dir directl ectly y.



Dispo Dispose se of of dama damage ged d or miss missha hape pen n ESMs ESMs dir direct ectly ly..



Di Disp spos ose e of lea leaki king ng ESM ESMss dir directl ectly y.



Polish Polish ESM termin terminals als using using sand sandpap paper er if if they they are are corro corroded ded..

3.2.4 Recharge Solution Recharge ESMs that pass tests using either of the following solutions based on site requirements. Recharge ESMs using a power system: 1.

Identify qualied qualied ESMs  ESMs that can be recharged.

2.

Install Install the the ESM ESMss and connect connect cables cables to to the ESMs by refer referring ring to the the quick quick installation guide of the related power system.

3.

Us Use e the the powe powerr syst system em to to rech rechar arge ge the the E ESM SMs. s. Table 3-2 Recharge 3-2 Recharge parameter settings Recharge Parameter

Setting Value

Charge voltage

53.5 V.

Charge current

Use the default charge current limit coecient. coecient. The  The maximum charge current is 100 A.

Termination condition

The charge duration is greater than 10 minutes and the charge current is less than 0.02 C (2 A), or the ESM is protected.

  4.

Hold Hold down down the MANU MANUAL AL ON/OF ON/OFF F button button for for at least least 5s and and less less than than 15s. 15s. Wait all indicators on the front panel turn of  and  and then remove the cables. Place the ESM in the original packing case. Modify the latest charge time and the next recharge time marked on the original packing case.

Recharge the ESMs of a purchased or borrowed DC regulated power supply that supports 48 V charge by performing the following operation: 1.

Connect Connect the the positive positive and n negativ egative e poles poles of an ES ESM M to the o output utput positive positive and and negative terminals on a DC regulated power supply respectively respectively.. Figure 3-1 Connecting 3-1 Connecting cables between an ESM and DC regulated power supply equipment

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

14

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

3 Transportation and Storage

2.

Set charge charge parameter parameterss for for the DC regula regulated ted power power supply supply equipment. equipment. For details, see Table 3-2. 3-2.

3.

Hold Hold down down the MANU MANUAL AL ON/OF ON/OFF F button button for for at least least 5s and and less less than than 15s. 15s. Wait all indicators on the front panel turn of  and  and then remove the cables. Place the ESM in the original packing case. Modify the latest charge time and the next recharge time marked on the original packing case.

● Batte Batteries ries can can be activated activated throug through h power power cables. cables. ● Do not per perform form operat operations ions with with power on on when connectin connecting g the recharge recharge cables.

3.2.5 Qualication Qualication Standards  Standards for Recharge Table 3-3  3-3 Qualication Qualication standards  standards for recharge Requ Re quir ired ed Rech Rechar arge ge End End Vol Volttage age

Requ Requir ire ed Vol Volta tage ge Afte Afterr O Ope penn-Ci Cirrcu cuit it for 8 Hours

≥ 51 V

≥ 48 V

 

1. For the ESM that that meets the the standa standard rd afte afterr recharge, recharge, hold hold down the MANUAL MANUAL ON/OFF ON/OFF button for at least 5s and less than 15s. Wait all indicators on the front panel turn of  and then remove the cables. Place the ESM in the original packing case. Mark the latest charge time and the next recharge time (the next recharge time is 8 months (stored above 30°C) or 12 months (stored below 30°C) later than the latest charge time) on the packing case. Packed ESMs should be used as soon as possible. 2. If tthe he ESM ESM iiss not not qualied qualied after  after recharge, recharge it again. If the ESM is still not qualied, dispose qualied,  dispose of it.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

15

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

4

 Installation and Commissioning

Prerequisites The recommended ESMs come from one batch of one manufacturer and are of  the same model. The installation and commissioning comply with the regulations and warnings issued by ESM manufacturers. Before installing ESMs, ensure that battery circuit breakers in the power system are OFF or that battery fuses are removed.

● Smoki Smoking ng and and sparks sparks are are proh prohibited ibited near ESMs ESMs.. ● Use inst installatio allation n tools with with insulated insulated handles handles.. Otherwise, Otherwise, the ESMs ESMs may be burned and injury may be caused. ● Befo Before re operating operating ESMs, ESMs, wear goggles, goggles, rubber rubber gloves, gloves, and protectiv protective e clothes. clothes. Remove any conductive objects, such as watches, bracelets, bangles, and rings. ● Do not us use e metal to simultan simultaneousl eously y touch two or more more terminal terminalss of the ESM. ESM. Do not use metal to touch both an ESM terminal and a grounded object such as a battery cabinet. Otherwise, a short circuit will occur oc cur,, which may produce sparks. ● It is rrecomme ecommended nded that that the power power and and battery battery systems systems be equipped equipped with with qualied  reghting qualied reghting facilities  facilities onsite, such as reghting reghting sand  sand and dry powder extinguishers. ● Do not pl place ace installatio installation n tools on the the ESM during during installat installation. ion. After After the installation, do not place foreign matters on or around the ESM. ● Segr Segregate egate the install installation ation place, place, arrange arrange dedicated dedicated guardians guardians,, and place warning signs of "danger" and "high voltage" above the ESM and separators. ● Wear ant anti-high i-high-volt -voltage age clothing clothing (including (including gloves gloves and shoes) shoes) accordin according g to the high voltage and safety requirements, and wear ESD gloves and wrist straps. ● Use dedi dedicated cated insulati insulation on tools. tools. Metal tools tools such as as torque torque wrenches wrenches mu must st be insulated before they are used. Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

16

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

4.1 Tools Required tools and materials are available.

NO TI E

● Use iinsu nsulat lated ed tools tools.. The foll followi owing ng gure gure is  is for reference only. ● After in install stalling ing power power terminals, terminals, periodicall periodically y check whether whether they are tightened tightened,, and whether rust, corrosion, or other foreign objects exist. If necessary, clean the terminals and tighten the bolts. If the battery bolts are loosely connected, the voltage drop may be too high, or the battery may be burnt when the current is large.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

17

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

4.2 Installation an ESM Procedure Step 1 Install an ESM according to the quick installation guide and check whether oating nuts oating  nuts are installed on both sides of the rack. If not installed, install the oating nuts oating  nuts delivered with the cabinet on both sides of the rack. Step 2 Push the ESM into the cabinet c abinet and fasten the ESM. Figure 4-1 Installing 4-1 Installing an ESM

NO TI E

● The we weight ight of an an ESM-48100U2 ESM-48100U2 is about about 43 kg. kg. Check the the load-bearing load-bearing capability of the rack tray before installation. ● ESM-4 ESM-48100U2 8100U2 is 396 mm mm deep deep.. Check the the rack rack depth depth before before install installation. ation. ● The ESM ca can n be installed installed in a 19-inch 19-inch rack with with guide guide rails and and a tray. tray. Check Check whether the load-bearing capability meets requirements. requirements. ● If multip multiple le ESMs are are installed, installed, clearances clearances should should be reserved. reserved. The averag average e space for each ESM should be at least 3 U. It is not supported to stack ESMs or make an ESM land on its back panel. ● Inst Install all ESMs fr from om bottom bottom to top. You You are advised advised to install install ESMs on three three layers.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

18

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

Figure 4-2 Correct 4-2 Correct installation diagram

----End

4.3 Cable Connections (Huawei Pow Power er System) Prerequisite The ESM has been correctly installed. The protective gloves, socket wrench, and cabinet door key are available.

Procedure Step 1 Wear the protective gloves. Step 2 Install the ESM ground cable.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

19

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

Figure 4-3 Installing 4-3 Installing the ESM ground cable

(1) Ground bar

Step 3 Install the ESM communications cables.

After the ESM communications cables are installed, connect a build-out resistor to the COM_OUT port of the last ESM.

Figure 4-4 Installing 4-4 Installing the ESM communications cables (Method 1)

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

20

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

Figure 4-5 Installing 4-5 Installing the ESM communications cables (Method 2)

Step 4 Install the PWR activation cables of the ESM.

Activation cables are required for Huawei power systems (except the 5G power system). Perform the following steps to install the activation cables. 1.

Locate Locate the the ESM ESM activ activatio ation n cable cable and and cable cable termin terminals als in in the the tting tting bag.  bag.

2.

Instal Installl tthe he activa activatio tion n cabl cable e at at the the termin terminals als..

3.

Instal Installl one end of of the activ activatio ation n cable cable at a PWR PWR port port of the the ESM. ESM.

4.

Install Install the the oth other er end end of the activati activation on cable cable at a load route route (BLVD (BLVD route route recommended, the recommended circuit breaker capacity of the activation act ivation cable ranges from 6 A to 32 A) and the corresponding RTN+ busbar in the power system.

Activation cables of two, four, six, and eight groups of ESMs can be cascaded to one BLVD circuit breaker.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

21

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

Figure 4-6 Installing 4-6 Installing the PWR activation cables for the ESM

Step 5 Assemble an OT terminal with the ESM power cable. Figure 4-7 Preparing 4-7 Preparing an OT terminal

(1) Cable

(2) OT terminal

(4) Hydraulic pliers

(5) Heat gun

(3) Heat shrink tubing

Step 6 Install negative and positive power cables of the ESM.

● When in install stalling ing the ESM ESM power cable, cable, ensure ensure that that the protrud protruding ing part part of the OT terminal on the cable faces outward. ● Do not con connect nect two or more more cables cables to the positive positive and and negative negative power ports ports of  the ESM in parallel.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

22

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

Figure 4-8 Connection 4-8 Connection of ESM power cables

Figure 4-9 Installing 4-9 Installing negative and positive power cables c ables for the ESM

Step 7 Remove the protective gloves and pack up all tools. ----End

4.4 Cable Connections (Third-Party Power System) Prerequisite The ESM has been correctly installed. The protective gloves, socket wrench, and cabinet door key are available.

Procedure Step 1 Wear the protective gloves. Step 2 Install the ESM ground cable.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

23

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

Figure 4-10 Installing 4-10 Installing the ESM ground cable

(1) Ground bar

Step 3 Install the ESM communications cables.

After the ESM communications cables are installed, i nstalled, connect a build-out resistor to the COM_OUT port of the last ESM.

Figure 4-11 Installing 4-11 Installing the ESM communications cables

Step 4 Assemble an OT terminal with the ESM power cable. Figure 4-12 Preparing 4-12 Preparing an OT terminal

(1) Cable

(2) OT terminal

(4) Hydraulic pliers

(5) Heat gun

(3) Heat shrink tubing

Step 5 Install negative and positive power cables of the ESM. Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

24

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

● When in install stalling ing the ESM ESM power cable, cable, ensure ensure that that the protrud protruding ing part part of the OT terminal on the cable faces outward. ● Do not con connect nect two or more more cables cables to the positive positive and and negative negative power ports ports of  the ESM in parallel.

Figure 4-13 Connection 4-13 Connection of ESM power cables

Figure 4-14 Installing 4-14 Installing negative and positive power cables of the ESM

Step 6 Remove the protective gloves and pack up all tools. ----End

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

25

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

4.5 Power-On Commissioning NO TI E

● Perf Performing orming the the power-on power-on procedure procedure provided provided in this this section may result result in power failure or alarms. Inform the alarm center before and after the procedure. ● The pow power er-on -on procedur procedure e involves involves various various technologies technologies and and should be performed by trained personnel according to the power-on power-on instructions. ● Durin During g operations operations,, stand on dry dry insulating insulating material material and and do not wear any any conductors such as jewelry or watches. Use insulated tools during power-on. ● Do not e establ stablish ish contact contact between between electrica electricall points points that have have diferent diferent electric  electric currents. ● When you ar are e performing performing operat operations ions and do not want want other otherss to operate, operate, attach attach the label "Currently being serviced. Do not switch on." to the power distribution equipment. ● Durin During g the power-on power-on procedur procedure, e, shut down down the system immediate immediately ly if any fault is detected. Rectify the fault and proceed with the procedure. ● Conn Connect ect the lithium lithium battery battery supply supply when when the AC power power supply supply is norm normal. al.

4.5.1 Power-On (Huawei Power System) Step 1 Switch on the battery circuit breakers and the circuit c ircuit breaker connected to activation cables in the power system.

NO TI E

If the Huawei power monitoring module is connected to the ESM for the rst time, the monitoring module will restart automatically as battery management parameters need to be switched to the ESM. Step 2 When multiple ESMs connected in parallel are powered on, observe the RUN indicator on each ESM panel. Communication is normal if the indicator is steady on and is not established if it blinks at short intervals. Check the communications cables between ESMs and rectify the fault. Step 3 When the ESMs are communicating with the monitoring module, check whether the communication is normal. If the RUN indicator on an ESM is steady on, the ESM communicates properly with the monitoring module. If the indicator is blinking at short intervals, the communication is interrupted. In this case, check that the communications cable is i s properly connected. Step 4 Observe the ESMs for 15 minutes. Ensure that they are working properly (the ALM indicator is of  and  and the RUN indicator is steady on). ----End Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

26

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

4.5.2 Power-On (Third-Party Power System) Procedure Step 1 Switch on the ESM circuit breakers. Step 2 Check whether the ESMs are activated. If the RUN indicator on an ESM is on, the ESM is activated. If it is of, of, the  the ESM is not activated. If so, check that the cables are properly connected. Step 3 Observe the ESMs for 15 minutes. The ESMs are running properly if the ALM indicators are of. ----End

4.5.3 Power System Parameter Settings (Huawei Power System) Set parameters as follows for the ESM used in a power system. sy stem. Huawei power system automatically identies identies ESMs  ESMs and sets battery parameters. There is no need to set the parameters onsite. To To check the ESM running status or change the charge current limit coecient, coecient, log  log in to the Web user interface (UI) or LCD of Huawei power system and perform the following operations.

NO TI E

● Requ Required ired Huawei Huawei power power monitori monitoring ng module: module: SMU02C ● Requ Required ired software software version: version: SMU SMU V500R003C10 V500R003C10 or later later

Procedure Table 4-1 Setting 4-1 Setting battery parameters on the LCD Main Menu

Level-2 Menu

Level-3 Menu

Level-4 Menu

Setting Value

Scope

Setting parameters

Battery

Basic parameters

Charge current limit coecient

Set based on the site requirements

0.05 C10–1.0 C10

  To check the ESM running status or change the charge current limit coecient coecient on  on the Web UI, perform the following operations: Step 1 Set the PC IP address in the same network segment as the SMU IP address, enter https://local IP address  of  of the SMU (for SMU (for example, https://192.168.0.10) in the address box of Internet Explorer, and press Enter Enter.. The login page is displayed.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

27

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

Figure 4-15 Login 4-15 Login page

Step 2 On the login page, choose Monitoring choose Monitoring > DC Power > Power > Lithium Battery Group > Group > Running Parameter > Parameter > Charge Parameters to Parameters to modify the charge current limit coecient and coecient  and set the value range to 0.05 C10 to 1.0 C10. Figure 4-16 Setting 4-16 Setting the charge current limit coecient

Step 3 On the login page, choose Monitoring >DC Power > Power > Lithium Battery Group > Group > Running Information to Information to view the ESM running status.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

28

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

Figure 4-17 Viewing 4-17 Viewing the ESM status

----End

4.5.4 Power System Parameter Settings (Third-Party Power System) NO TI E

When the lithium battery is connected to a third-party power system, set the battery capacity based on the congured congured lithium  lithium battery capacity. capacit y.

Table 4-2 Parameter 4-2 Parameter settings No.

Parameter

Standard Value

1

Capacity

N (ESM quantity) x 100 Ah

2

Charge current limit coecient

0.15C10

3

Equalized charge voltage

53.5 V

4

Float charge voltage

51 V

5

Low voltage alarm

47 V

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

29

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

4 Installation and Commissioning

No.

Parameter

Standard Value

6

Load lo low vo voltage di disconnection (L (LLVD) threshold

46 V

7

Battery low voltage disconnection (BLVD) threshold

44 V

 

4.6 Acceptance Criteria Install and accept the ESM to ensure that the ESM can work properly. No.

Item

Acceptance Criteria

1

Indicator status

The indicator status is normal (the RUN indicator is steady on and no indicator is red).

2

Working status

The ESM works properly (check by simulating a mains outage or mains recovery).

3

Current

The current ESM curdeviation rent is nois rmwithin al. Acc±2 ordA. ing to system settings, the

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

30

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

5 Maintenance Guide

5

 Maintenance Guide

Skilled personnel are required to perform maintenance operations. Skilled personnel should also be protected against unintentional contact or exposure to energy sources capable of causing injury. Skilled personnel refer to personnel who: ● ●

Have Have traini training ng or exper experien ience ce in th the e equipme equipment nt techno technolog logy y, particu particular larly ly in knowing the various energies and energy magnitudes used in the equipment. Are expected expected to to us use e their their ttrain raining ing and and experie experience nce to recogn recognize ize energ energy y source sourcess capable of causing pain or injury and to take action for protection from injury from those energies.

NO TI E

The ESM software can be upgraded only when the AC input is normal.

5.1 Maintenance Method Table 5-1 Maintenance 5-1 Maintenance method Main Ma inte tena nanc nce e Obje Object ct

Maint Mainten enan ance ce Met Metho hod d

ESM

Check the ESM indicators for its running status. Table 4 describes the indicators.

Moni Mo nito tori ring ng (LCD (LCD))

1. View View the the ESM ESM run runni ning ng st stat atus us on the the LCD LCD of H Hua uawe weii powe powerr moni monito tori ring ng module (SMU02B or SMU02C): LCD menu path: Main Menu > Menu > Running Information > Information > Lithium Battery > Battery > Lithium Battery Group 2. Check th the e active alarms alarms for ESM fault fault alarms. alarms. LCD menu menu path: Main Menu > Menu  > Active  Active Alarm. Alarm. If there is any fault alarm, handle it by referring to Troubleshooting.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

31

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

5 Maintenance Guide

Main Ma inte tena nanc nce e Obje Object ct

Maint Mainten enan ance ce Met Metho hod d

Monito Mon itorin ring g ((Web WebUI) UI)

1. Check Check the ESM runnin running g stat status us on the WebUI WebUI of the Hua Huawei wei power power monitoring module (SMU02B or SMU02C). WebUI menu path: Monitoring > DC Power > Power > Lithium Battery Group > Group > Running  Running Information

2. Check th the e active alarms alarms for ESM ESM fault alarms. alarms. WebUI WebUI menu menu path: Home > Home  > Active  Active Alarm. Alarm. If there is any fault alarm, handle it by referring to Troubleshooting.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

32

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

5 Maintenance Guide

Main Ma inte tena nanc nce e Obje Object ct

Maint Mainten enan ance ce Met Metho hod d

Network management system

1. Check th the e ESM running running status status on the Huawei power power syste system m network management system NetEco (NetEco V600R008C20 or later). NetEco menu path: Monitor Monitor >  > Site Name  >  > Lithium Battery Group > Group > Data

2. Check th the e active alarms alarms for ESM ESM fault alarms. alarms. NetEco NetEco menu menu path: Monitor > Monitor  > Site Name   > > Lithium Battery Group > Group > Alarm  Alarm.. If there is any fault alarm, handle it by referring to Troubleshooting. Troubleshooting.

 

5.2 Replacing an ESM Prerequisites ●

The protective protective gloves, gloves, Phillip Phillipss sc screw rewdriver driver and socket socket wren wrench ch are are available. available.



You have conrmed conrmed the  the model of the ESM to be replaced and prepared a new ESM.



You are are autho authoriz rized ed to ente enterr the the site site with with the the key key..

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

33

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

5 Maintenance Guide

Context ESM replacement may cause a system power failure. To To prevent power failures, ensure that other power sources, such as the mains, diesel generator, generator, or a thirdparty DC power source, provide continuous power supply.

Replacement Requirements Conditions for the ESM to enter and exit the maintenance mode: 1.

In the the non-maint non-maintenanc enance e modes, modes, hold hold down down the the Manual Manual ON/OF ON/OFF F button button for for at least 15s to enter the maintenance mode.

2.

In the the maintenan maintenance ce mode, mode, hold hold down down the the Manual Manual ON/OFF ON/OFF button button for for at least 15s to exit the maintenance mode.

Before replacing an ESM in an actual maintenance scenario, hold down the Manual ON/OFF button for the ESM to power of. of. After  After the ESM is replaced, hold down the Manual ON/OFF button for at least 15s on the new ESM to exit the maintenance mode.

Removing the Old ESM Step 1 Wear the protective gloves. Step 2 Switch the BAT– BAT– battery circuit breaker on the power sy system stem to OFF or remove the battery fuse. Step 3 Use the Manual ON/OFF button on the ESM to turn of  the  the battery output. Step 4 Disconnect the cables from the old ESM. Insulate each cable and label it immediately after disconnecting it. Step 5 Loosen the screws on the panel and remove the ESM. ----End

Installing the New ESM Step 1 Install the new ESM and tighten the screws. Step 2 Hold down the Manual ON/OFF button for 15s for the ESM to enter the maintenance mode. In this mode, all indicators blink, the ESM board is activated, but the ESM will not be charged or discharged. Step 3 Connect the cables to the new ESM based on the cable labels. Step 4 Switch the BAT– BAT– battery circuit breaker in the power system to ON or reinstall the battery fuse using a fuse extracting unit. Step 5 Hold down the Manual ON/OFF button for 15s for the ESM to exit the maintenance mode. The ESM is automatically activated and connects to the power system. Step 6 Remove the protective gloves and pack up all tools. ----End Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

34

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

5 Maintenance Guide

Follow-up Operations ●

Put the the rremo emoved ved comp compone onent nt into into the the ESD ESD box or bag bag and then then place place the the ESD box or bag into the carton box with foams or the bag of the new component.



Fill Fill in the ffaul aultt card card with with the info informa rmation tion abou aboutt the remo removed ved compo componen nent. t.



Con Contact tact yo you ur loc local al Huaw Huawei ei oce oce to  to handle the faulty component.

5.3 Troubleshooting Troubleshooting Fault Type

Fault Generation Condition

Possible Causes

Troubleshooting

BMS fault

1. The electrochemical cell voltage sampling circuit is faulty.

1. The weldin welding g point point for for electrochemical cell voltage sampling is loose or disconnected.

Replace the ESM.

2. The electr electroch ochemi emical cal cell temperature

2. The voltag voltage e samp samplin ling g terminal is disconnected.

sampling circuit is faulty.

3. The fuse fuse in the vol voltag tage e sampling circuit is blown. 4. The elec electr troch ochemi emical cal ccell ell temperature sensor has failed.

Cell fault

The voltage of the electrochemical cell is low or unbalanced.

1. Due to larg large e self-dis self-discha charg rge, e, the electrochemical cell overdischarges to below 2.0 V after long-term storage.

Replace the ESM.

2. The electr electroch ochemi emical cal ce cell ll is damaged by external factors, and short circuits, pinpricks, or crushing occurs. Overvoltage protection

1. The busbar busbar voltag voltage e is greater than 59.4 V in charging state. 2. The The max maxim imum um electrochemical cell voltage is greater than 3.8 V. 3. The The ESM ESM volt voltag age e is greater than 55 V.

Issue 01 (2020-06-30)

1. The busb busbar ar input input voltag voltage e exceeds the normal value. 2. Cells Cells are are not consi consiste stent. nt. The The capacity of some electrochemical cells deteriorates too fast or the internal resistance of some electrochemical cells is too high.

Copyright © Huawei Technologies Co., Ltd.

If the ESM cannot be recovered due to protection against abnormality, contact local Huawei engineers to rectify the fault.

35

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

5 Maintenance Guide

Fault Type

Fault Generation Condition

Possible Causes

Undervoltage protection

1. The The ESM ESM volt voltag age e is less than 44 V.

1. The main mainss power power fa failu ilure re has has lasted for a long time.

2. The The min minim imum um electrochemical cell voltage is less than 2.5 V.

2. Cells Cells are are not consi consiste stent. nt. The The capacity of some electrochemical cells deteriorates too fast or the internal resistance of some electrochemical cells is too high.

Charge high temperature protection

The maximum electrochemical cell temperature is greater than 60°C.

1. The The ESM ESM am ambi bien entt temperature is too high.

Discharge high temperature protection

The maximum electrochemical cell temperature is greater than 65°C.

Charge low temperature protection

The minimum electrochemical cell temperature is less than 0°C.

Discharge low temperature protection

The minimum electrochemical cell temperature is less than –20°C.

Issue 01 (2020-06-30)

Troubleshooting

2. There There are are abno abnorma rmall heat heat sources around the ESM.

1. The The ESM ESM am ambi bien entt temperature is too low. 2. The heat heater er fail failss to work. work.

Copyright © Huawei Technologies Co., Ltd.

36

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

6 Deactivating of the Antitheft Function of the ESM

6

 Deactivating of the Antitheft Function of the ESM

Scenario Before NetEco replacement or a cross-R-version cross-R-version upgrade of the monitoring module, deactivate the antitheft function of the ESM.

Procedure Step 1 Log in to the NetEco WebUI and choose System System >  > License Management. Management. Figure 6-1 NetEco 6-1 NetEco WebUI

Step 2 Select the ESM and click Deactivate Deactivate..

After the antitheft function of the ESM is deactivated, the ESM status is displayed as Inactive.. Inactive

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

37

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

6 Deactivating of the Antitheft Function of the ESM

Figure 6-2 Deactivating 6-2 Deactivating the antitheft function of the ESM

----End

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

38

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

A Common Criteria

 A

 Common Criteria

Safety Precautions ●

Avoi Avoid d skin skin cont contac actt with with elec electr trol olyte yte overow. overow. Before  Before installing or maintaining batteries, wear goggles, rubber gloves, and protective clothing.



Keep Keep the ESM loop loop disc disconn onnecte ected d durin during g ins instal tallat lation ion and and maint maintena enance nce..



Secu Securre E ESM SM cabl cables es to th the e tor torqu que e specied specied in  in the ESM documentation. Loose connections will result in excessive voltage drops or cause ESMs to burn out when the current increases.



Protec Protectt your your skin and and eyes eyes from from ESM ESM electr electrolyt olyte e leakag leakage. e. If your your bo body dy comes comes in contact with electrolyte leakage, wash with clean water immediately and visit a doctor.



Avoi Avoid d inge ingest stio ion n of ESM ESM comp compon onen ents ts..



Protect Protect the the E ESMs SMs from mechanical mechanical vibration, vibration, collision, collision, punctures punctures,, and and strong strong impact. Otherwise, the ESMs may catch re.



Do not throw ESMs in re re because  because this may cause the ESMs to ignite.



Do not not imme immerse rse ESMs ESMs iin n wate waterr or expose expose the them m to ra rain. in.



Replaci Replacing ng an ESM with with an an incorr incorrect ect mode modell may caus cause e cross cross ccurr urrent ent and and bias bias current, which will trigger ESM protection. Long-time operation with an incorrect model will result in cell or board faults, which may cause risks such as re.



If the the ESM loop loop is shor short-ci t-circ rcuit uited, ed, E ESM SM prote protectio ction n will will be tri trigge ggere red d and the the ESM cannot be charged or discharged. Long-time frequent short circuiting can result in cell or board faults, which may cause risks such as re.



An ESM ESM commun communicat ication ion fail failur ure e ala alarm rm cause caused d by rreas easons ons such such as loose loose communications cable connection should be handled within 72 hours (default value, congurable congurable in  in the range of 1 minute to 720 hours). Otherwise, the ESM will be internally locked, which may afect afect the  the ESM power backup.



Dispose Dispose of of waste waste ESMs ESMs in stri strict ct accor accordan dance ce with with local local laws laws and regu regulat lation ions. s.

Misoperations The following lists some misoperations that should be avoided.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

39

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

A Common Criteria

Miso Mi sope perrat atio ions ns

Prot ote ectio ction n Desc Descri ript ptio ion n

Reverse connection

If terminals are connected with reverse polarity, the ESM will not start and will stay in sleep mode. If you hold down the MANUAL ON/OFF button to activate the ESM, it will report a protection alarm and the ALM indicator will be lit.

External short circuit

If the ESM loop is short-circuited, ESM protection will be triggered and the ESM cannot be charged or discharged. Long-time frequent short circuiting can result in cell or board faults, which may cause risks such as re.

Series connection

ESMs cannot be connected in series. If ESMs are connected in series forcibly, ESM protection will be triggered. Operations outside the protection range will result in board or battery damage and battery protection failure, which may cause risks such as re.

 

Gas Composition The ESM is an enclosed battery system and will not release any gases under normal operations. If the ESM is severely misused, for example, being burned or thunderstruck, the ESM may be damaged, resulting in electrolyte elec trolyte leakage. Because the electrolyte is of organic carbonate nature, it may produce CO 2, CO, and N2 after being burned.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

40

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

B Warranty Rules

B ●



 Warranty Rules

Huawei Huawei will will not not be liab liable le ffor or any any damage damage to to Huawei Huawei ESMs ESMs caused caused by by forc force e majeure events. –

Natur Natural al disast disasters ers such such as earthq earthquak uakes, es, volca volcanic nic erupt eruption ions, s, and land landsli slides des



Fires



Wars



Lightning strikes

Huawei Huawei will will not not be liab liable le ffor or any any damage damage to to Huawei Huawei ESMs ESMs caused caused by the the following events: –

Damage Damage such such as br break eakage age and leakag leakage e is cau caused sed to the the ESMs ESMs due to misoperations or incorrect connections during the ESM transportation and installation performed by the customer. customer.



The cust custome omerr does does not not rech recharg arge e the the ESMs ESMs iin n tim time e and and the the ESMs ESMs a are re stored more than six months longer than the storage term, which causes capacity loss or irreversible damage to the ESMs.



After After tthe he ESMs ESMs are are instal installed led and connec connected ted to the the syste system, m, tthe he custo customer mer does not power on the ESMs in time, which causes the ESMs to be overdischarged and further causes damage to the ESMs.



Damage Damage is is caused caused to ESMs ESMs becaus because e they they are are not not accept accepted ed in time time due due to customer reasons.



Damage Damage is caus caused ed to to ESMs ESMs beca because use the opera operatin ting g en envir vironm onment ent or external power parameters do not meet operating environment requirements. For example, the ambient temperature is poor, power outage frequently occurs in the power grid, the ESMs are frequently overdischarged due to the customer's improper maintenance, the capacity of a customer site is expanded, and the ESMs are not fully charged for a long period.



The cust custome omerr chang changes es the the ESM ESM use use sscen cenari arios os with without out notifyi notifying ng H Huaw uawei. ei.



Damage Damage to to ESMs ESMs is cause caused d by the the custom customer er or a thir third d party party,, for for exampl example, e, the customer relocates or reinstalls ESMs without notifying Huawei.



The custom customer er does does not corre correctl ctly y set set ESM ESM oper operatin ating g manag manageme ement nt parameters including but not limited to ESM capacity, capaci ty, number of ESMs, equalized charging voltage, oat oat charging  charging voltage, charge current limit, and disconnection voltage.

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

41

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

B Warranty Rules



The cust custome omerr does does not service service ESMs ESMs base based d on th the e approp appropria riate te oper operati ation on guide. For example, the customer does not periodically check whether ESM terminal screws are tightened.



The The cus custo tome merr con conne nects cts ex extr tra a loa loads ds to ESMs ESMs..



The cust custome omerr mixes mixes Huawe Huaweii ESMs ESMs with with othe otherr ESMs, ESMs, which which cause causess th the e acceleration of capacity deterioration. For example, the customer uses Huawei ESMs together with the ESMs of other brands or rated capacities, or with old ESMs.

Issue 01 (2020-06-30)



ESMs are stolen.



Th The e ESM ESM warr arranty anty exp expir ires es..

Copyright © Huawei Technologies Co., Ltd.

42

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

C Technical Specications

C

 Technical Specications

Table C-1 Technical C-1 Technical specications Item

 

Dimen Dim ensi sion onss ((W W x D x H)

Specications ● 442 mm x 396 396 mm x 130 130 mm (exc (exclu ludi ding ng moun mounti ting ng ears ears)) ● 482 mm x 396 mm mm x 130 130 mm (inclu (including ding mounting mounting ears) ears)

Weight

43 kg

Nominal voltage

48 V DC

Equalized charging voltage

53.5 V DC

Float charging voltage

51 V DC

Max. charging/ discharging current limit

100 A/100 A@35℃

Max. charging/ discharging power

4800 W

Oper Op erat atin ing g Tem Tempe pera ratu ture re

Ch Char argi ging ng:: 0°C–5 0°C–55°C 5°C;; Disch Dischar argi ging ng:: –20°C –20°C to to 55° 55°C C

Relative Humidity

5%–95%

Atmospheric

61 kPa~113 kPa

Installation mode

Installed in a 19-inch rack

Maintenance mode

Maintained from the front

Altitude

0–4000 m (When the altitude ranges from 2000 m to 4000 m, the highest operating temperature decreases by 1°C for each additional 200 m.)

Ripple and noise

≤ 200 mV

IP rating

IP20

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

43

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

Item

 

Other requirements

C Technical Specications

Specications Indoor scenario: ● There There is no conductiv conductive e dust, corros corrosive ive gas, gas, or explosion explosion hazard. hazard. ● Dust, corros corrosive ive substanc substances, es, pests, pests, mol molds, ds, and other other indicato indicators rs should be controlled in accordance with class 3.1 requirements in ETSI EN 300 019-1-3 (V2.3.2 or a later version). Outdoor scenario: ● There There is no conductiv conductive e dust, corros corrosive ive gas, gas, or explosion explosion hazard. hazard. ● Dust, corros corrosive ive substanc substances, es, pests, pests, mol molds, ds, and other other indicato indicators rs should be controlled in accordance with class 4.1 requirements in ETSI EN 300 019-1-4 (V2.2.1).

Issue 01 (2020-06-30)

Copyright © Huawei Technologies Co., Ltd.

44

 

BoostLi Energy Storage Module ESM-48100U2 User Manual

D Acronyms and Abbreviations

D

 Acronyms and Abbreviations

E ESM

energy storage module

ESMU

energy storage management unit

L LUI

LCD user interface

S SOC

Issue 01 (2020-06-30)

state of charge

Copyright © Huawei Technologies Co., Ltd.