Areva-1

November 29, 2017 | Author: Jyoti Prakash Prusty | Category: Transformer, Relay, Switch, Valve, Manufactured Goods
Share Embed Donate


Short Description

erection and commissioning of 56.25 mva transformer...

Description

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 1 of 205

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR

TRANSFORMERS

AREVA T&D India Limited, P.O. NAINI, ALLAHABAD – 211008 (U.P.) INDIA

℡ : +91 (532) 2697422 ~ 24 : +91 (532) 2697447 / 48 : +91 (532) 2697601 ~ 03 : +91 (532) 2697604/ 606

8

: +91 (532) 2696784

E-mail : [email protected] ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 2 of 205

CONTENTS Section

ISSUE/ REVISION DATE

Description

Page

1

General

3

2

Transport, Packing & Despatch

18

3

Storage

26

4

Installation

34

5

Insulation Dryout at Site

57

6

Commissioning

59

7

Erection Checklists

64

8

Commissioning Checklists

68

9

Operation

79

10

Maintenance

81

11

Trouble Shooting

89

12

Reference Standards

102

13

Transformer Accessories:

114

20/10/05

(a)

Temperature Indicator

115

(b)

Gas & Oil Operated Relays

124

(c)

Condenser Type OIP Bushings

140

(d)

Silica Gel Breather

152

(e)

Oil Level Indicator

156

(f)

Pressure Relief Valve

161

(g)

Exhaust Fan

167

(h)

Flow Indicators

171

(i)

Transformer Oil Pump

184

(j)

Flexible Separator

192

(k)

Thermosiphon Filter

197

(l)

Oil to Water Heat Exchanger

200

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 3 of 205

MUST READ THE FOLLOWING CLAUSES IN THIS MANUAL ARE OF UTMOST IMPORTANCE AS REGARDS SAFETY AND HEALTH OF THE PERSONNEL AND EQUIPMENT ARE CONCERNED. HENCE, EVERY ONE INVOLVED IN THE ERECTION,

COMMISSIONING, OPERATION OR MAINTENANCE OF THE EQUIPMENT SHOULD STUDY THE CONTENTS OF THESE CLAUSES CAREFULLY BEFORE TAKING UP ANY OF THE SAID ACTIVITIES. Caluse1.2 on Pages 10 ~ 13

: (Health & Safety matters)

Clause 1.3 on Pages 14 ~ 17

: (Do’s & Don’ts)

Clause 2.3 on Page 20

: (Lifting & Jacking)

Clause 3.0 on Pages 26 ~ 33

: (Receipt & Storage)

Clause 4.2 on Pages 38 ~ 39

: (Oil sampling & Filtering)

Clauses 4.5 ~ 4.8 on Pages 40 ~ 44

: (Erection Precuations)

Clause 4.2 on Page 56

: (Mixing of Transformer Oil)

Clause 6.0 on Page 51

: (Commissioning)

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

1.0

PTRM : 0708 Page 4 of 205

GENERAL • Transformer is a static equipment, which converts electrical energy from one voltage to another. As the system voltage goes up, the techniques to be used for the Design, Construction, Installation, Operation and Maintenance also become more and more critical.

• If proper care is exercised in the installation, operation, maintenance and condition monitoring of the transformer, it can give the user trouble free service throughout the expected life of equipment which is of the order of 25~35 years. Hence, it is very essential that the personnel associated with the installation, operation or maintenance of the transformer are thorough with the instructions provided by the manufacturer.

• This Manual contains general descriptions about Transformers & specific details about the particular contract against which the Transformer is supplied. Also, it contains instructions regarding the safety aspects, erection, commissioning, operation, maintenance & trouble shooting of large capacity Power Transformers.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

1.1

PTRM : 0708 Page 5 of 205

TRANSFORMER CONSTRUCTION • The techniques used in the design and construction of high voltage transformers varies from manufacturer to manufacturer.

• The active parts of the transformers consist of core and windings. 1.1.1

CORE • Core is manufactured from lamination of Cold Rolled Grain Oriented Silicon Steel, which gives very low specific loss at operating flux densities. Joints of the laminations are designed such that the electromagnetic flux is always in the direction of grain orientation. The core clamping structure is designed such that it takes care of all the forces produced in the windings in the event of any short circuit.

1.1.2

WINDINGS • Windings are made from paper insulated copper conductors which are transposed at regular intervals throughout the winding for ensuring equal flux linkage and current distribution between strands.

• Interleaved or shielded construction is adopted for the high voltage windings to ensure uniform distribution of impulse voltages. Insulation spacers in the winding are arranged such that oil is directed through the entire windings for ensuring proper cooling.

1.1.3

COOLING • For ONAN/ONAF cooling, oil flows through the winding and external cooler unit attached to the tank by thermo-syphonic effect.

• For OF AF/OD AF/ OF WF cooling, the oil is directed through the winding by oil pumps provided in the external cooler unit.

• External cooler unit/units consists of pressed steel sheet radiators mounted directly on the tank or separate cooler banks for air-cooled transformers and oil to water heat exchangers for water cooled transformers.

1.1.4

TANK & COVER • Tank and Cover are manufactured by welding steel plates and are suitable for withstanding full vacuum and positive pressure test as per CBIP Manual. For large capacity power transformers, the tank will be of bell type construction. This is to avoid lifting of heavy core and windings, which requires very large capacity crane at site. The weight of upper tank will be much less in comparison with that of core & windings and can be lifted by using a small capacity crane.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 6 of 205

• Construction of the tank and cover are such that pockets for water collection is avoided.

• The tank and cover are designed such that these can be transported by railways/road/water as per customer specification.

Note: Transformer tank is provided with two earthing terminals. While earthing the cable box, busduct etc., it should be ensured that no closed loop is formed because of multiple earthing connections.

1.1.5

CONSERVATOR • Conservator is provided to take care of the expansion and contraction of transformer oil, which takes place during normal operation of the transformer.

• Wherever specified flexible separators or air cell if provided in the conservator can prevent direct contact of air with the transformer oil.

• A smaller oil expansion vessel is provided for the On Load Tap Changer.

• Magnetic oil level gauge is fitted on the main conservator which can give alarm / trip in the event of the oil level falling below the pre-set levels due to any reason.

1.1.6

PRESSURE RELIEF DEVICE • A device for avoiding high oil pressure build up inside the transformer during fault conditions is fitted on top of the tank. The pressure relief device allows rapid release of excessive pressure that may be generated in the event of a serious fault. This device is fitted with an alarm/trip switch.

• The pressure relief device has a spring-loaded diaphragm, which provides rapid amplification of its actuating force and will reset automatically, as soon as the pressure inside the tank drops down to the pre-set pressure.

• A bright colour coded mechanical indicator pin in the cover moves with the valve disc during the operation of the pressure relief device and is held in position by an 'O' ring in the pin bushing. This pin is clearly visible from ground level, which gives an indication that the device has operated.

• The indicator pin may be reset manually by pushing it downward until it rests on the valve disc. The relief device is provided with a shielded weatherproof alarm / trip and is operated by the movement of valve disc. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 7 of 205

• For Small Capacity transformers, an explosion vent is provided with a diaphragm, which will break in the event of abnormal increase in internal pressure. Some times the explosion vent is provided with double diaphragm such that the outer one remains intact even after the inner one is ruptured. Rupturing of inside diaphragm can be checked by viewing through the oil level gauge provided in between the diaphragms.

1.1.7

GAS & OIL ACTUATED (BUCHHOLZ) RELAY • Gas and oil actuated relay is fitted in the feed pipe from the transformer tank to the expansion vessel for collection of gas, if generated in the oil. The relay operates on the fact that almost every type of fault in an oil immersed transformer gives rise to generation of gas. This gas is collected in the body of the relay, and is used to close the alarm switch. In the event of any severe fault, the sudden increase in oil pressure causes an oil surge towards the expansion vessel and this is used to close the trip contacts. This oil surge will impinge on the flap fitted to the trip element causing it to rotate about its axis and thus bringing the mercury switch to the closed circuit position, which in turn operates the tripping device.

• In the event of serious oil loss from the transformer, both alarm and trip elements operate in turn in the manner previously described for gas collection.

• Two brass petcocks are fitted at the top of the relay body, the outlets of which are threaded to take a bleed pipe if required for collection of gas samples.

• In the pipe connection between On Load Tap Changer and its oil expansion vessel a single float Oil Surge Relay is fitted. This relay operates on the principle of oil surge impinging on a flap causing operation of the mercury switch connected to the trip circuit. Gas actuated alarm switch is eliminated because the gas generated during normal tap changing operation will give unnecessary alarm.

1.1.8

SILICAGEL BREATHER • Expansion and contraction of oil cause breathing action. The silicageldehydrating breather absorbs any humidity in the air breathed. An oil seal in the air intake prevents external moisture being absorbed when no breathing occurs.

• The breather container is filled with silicagel crystals. It is arranged such that the air breathed must pass through it. The desiccant contains blue and white crystals. When the silicagel is fully active, the blue crystals will have a deep blue colour and changes to pink as it absorbs ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 8 of 205

moisture. When saturated with moisture and the charge contained should be replaced. The gel removed from the breather may be arranged for regeneration and preserved for future use.

• The size of the breather is chosen such that it can operate effectively over a period of six months approximately. The factors, which influence the selection of size of the silicagel breather required for a particular transformer, depend on many factors like, the oil quantity in the transformer, the adsorption capacity of silicagel, the loading pattern and the atmospheric conditions prevailing at site. The loading pattern and the site conditions are difficult for the transformer manufacturer to assess. Hence, the selection of breather is based on certain assumptions and it is difficult to fix up a time schedule for the regeneration of silicagel. It is advisable to have a periodic inspection (say monthly) of the indicator so that the gel can be regenerated or replaced as soon it is saturated with moisture.

1.1.9

WINDING TEMPERATURE INDICATORS • The winding temperature relay indicates the winding temperature of the transformer and operates the alarm, trip and cooler control contacts. This instrument operates on the principle of thermal imaging and it is not an actual measurement. • Winding temperature indicator consists of a sensor bulb placed in oil filled pocket in the transformer tank cover. The bulb is connected to the instrument housing by means of two flexible capillary tubes. One capillary is connected to the measuring bellow of the instrument and the other to a compensation bellow. The measuring system is filled with a liquid, which changes its volume with rising temperature. Inside the instrument is fitted with a heating resistance which is fed by a current proportionate to the current flowing through the transformer winding. • The instrument is provided with a maximum temperature indicator. The heating resistance is fed by a current transformer associated to the loaded winding of the transformer. (The heating resistance is made out of the same material as that of the winding) The increase in the temperature of the resistance is proportionate to that of the winding. The sensor bulb of the instrument is located in the hottest oil of the transformer, therefore, the winding temperature indicates a temperature of hottest oil plus the winding temperature rise above hot oil i.e. the hot spot temperature.

1.1.10

OIL TEMPERATURE INDICATOR • The oil temperature indicator consists of a sensor bulb, capillary tube and a dial thermometer, the sensor bulb is fitted at the location of hottest oil. The sensor bulb and capillary tube are fitted with an

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 9 of 205

evaporation liquid. The vapour pressure varies with temperature and is transmitted to a bourden tube inside the dial thermometer, which moves in accordance with the changes in pressure, which is proportional to the temperature.

1.1.11

BUSHINGS • The high voltage connections pass from the windings to terminal bushings. Terminal bushings upto 36 kV class, 3150 Amps, are normally of plain porcelain and oil communicating type. Higher current rated bushings and bushings of 52 kV class and above will be of oil impregnated paper condenser type. The oil inside the condenser bushings will not be communicating with the oil inside the transformer. Oil level gauge is provided on the expansion chambers of the condenser bushings. • Oil in the condenser bushing is hermetically sealed and it should not be disturbed in normal operation. Oil level may be checked regularly and any oil leakage should be reported to the bushing manufacturer for immediate attention. • While connecting the overhead transmission line conductor to the bushing terminal, ensure that the line pull is limited to the cantilever strength of the bushing. The cantilever strength of bushings as per IS: 2099 for various types of bushings are as shown below. Rated Voltage (kV) ≤ 52 72.5 & 123 145 & 245 420

1.1.12

≤ 800 (Amps) 102 102 127 254

Cantilever Strength (kg.) 1000 ~ 1600 2000 ~ 2500 (Amps) (Amps) 127 204 127 204 163 254 254 320

≥ 3150 (Amps) 320 408 408 510

TAP CHANGER • Tap changers of power transformer are specifically of two types1. 2.

On Load Tap changer Off Circuit Tap changer

• In the case of off circuit tap changer, the tap changing takes place only when the transformer is de-energised, but in the case of on load tap changers the tap changing takes place when the transformer is in operation. The tap changer can be designed for changing the taps. a. Manually b. Automatically & c. From remote

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 10 of 205

• The On load tap changer will be a self-contained unit housed in the main transformer tank. Since some amount of arcing takes place during the switching operations from one tap to the other, the oil inside the tap selector will deteriorate faster. Hence, this oil cannot be allowed to mix with the oil in the main transformer. On load tap changer is provided with a separate conservator and oil surge relay. • For details of construction and maintenance, please refer to the OLTC supplier's manual attached with Specific Instructions at the end of this manual.

1.1.13

CONTROL & MONITORING SYSTEM • Local control and monitoring of the cooler, tap changer and alarm and trip indicators is carried out at the marshalling kiosk. Automatic control of the tap changer is carried out at the remote control panel.

1.1.14

FIRE DETECTION & FIRE FIGHTING SYSTEM • It is recommended to always install suitable fire detection and fighting system with all transformers. CBIP Manual prescribes guidelines for the selection and installation of Fire Protection System. • “Automatic Mulsifyre System” or “Drain and Stir System” with nitrogen injection inside the transformer are more prominent among the fire fighting systems for large capacity Power Transformers. In the Drain and Stir System, oil is partially drained from the transformer and nitrogen gas is bubbled through the oil in the transformer tank to stir and create a blanket of inert gas above the oil to quench the fire. • Owner of the Transformer has to ensure provision of requisite Contacts/ Relays in his control panel as per requirement specified in the Fire System Instruction Manual for connecting the Fire Detection and Fire Fighting System.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

1.2

PTRM : 0708 Page 11 of 205

HEALTH & SAFETY MATTERS Even though the manufacturer of the transformer has put every effort to comply with the rules and regulations applicable to the safe operation of the transformer, the equipment described in this manual is safe to use provided that: — It is installed in a location suitable for its designed purpose. The installation is done by qualified and competent persons. The installed equipment is operated and maintained in accordance with the manufacturer's instructions by qualified and competent persons familiar with the type of equipment involved and its working environment. All work is done competently and in accordance with good engineering practices and in a manner, which is not hazardous either to personnel or to equipment. The recommended pre-commissioning checks are done before energising the transformer. The operation of protective systems and devices for the transformer are checked regularly. Neglect or deliberate overriding of protection system or device could allow a minor problem to develop into a major problem resulting in total loss of the transformer, damage to other equipment and injury to personnel. Prolonged operation under over load, over voltage or over excitation condition can have a seriously detrimental effect on the life of equipment. The pressure relief devices are designed to eject liquid, which is likely to be very hot in the event of a fault developing within the transformer. Equipment such as pressure relief devices incorporates heavy springs in compression. If the equipment is dismantled without due safeguard, damage and /or injury may result. The internal atmosphere of a transformer tank, if N2 filled, is replaced by breathable dry air of dew point less than –400 C for a minimum period of twenty four hours.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

1.2.1

PTRM : 0708 Page 12 of 205

ELECTRICAL SAFETY The following hazards are commonly associated with the installation, operation and maintenance of electrical equipment ♦

Existence of AC and DC voltage.



Possible existence of toxic hazards associated with material used in the construction of electronic components, cleaning agent and solvents.



Electric shock due to incorrect earthing, moisture on insulation, bad engineering or working practices.



Fire or burn out due to incorrect setting or over load or protective devices, incorrect cables or fuses, insufficient ventilation or incorrect operating voltage.



Short circuit flash over due to dust or moisture on insulation or short circuit on live conductors.



No work should be done to transformer or its associated equipment unless it is disconnected from supply and all terminals have been solidly earthed.



If the secondary of a current transformer is disconnected, a dangerously high voltage can be induced in the circuit. If the secondary circuit of a current transformer is to be disconnected it must be shorted by a link capable of carrying the rated current.



Do not apply any voltage or even high voltage megger when the equipment is under vacuum.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

1.2.2

HAZARDOUS SUBSTANCES

1.2.2.1

TRANSFORMER OIL

PTRM : 0708 Page 13 of 205

Normally, transformer oil presents no hazard to health. However, serious neglect may affect the skin and cause irritation. Oil is a hydrocarbon and will burn. Carbon dioxide, dry chemical, foam or water fog is the extinguishants.

1.2.2.2

MERCURY Mercury switches or thermometers containing mercury should be handled carefully. Mercury vapour can be hazardous over a period of time, especially in poorly ventilated room.

1.2.3

ENVIRONMENTAL HAZARDS DUE TO OIL SPILLAGE & FIRE CONSEQUENT TO FAILURE OF TRANSFORMER AT SITE Oil spillage from Transformer tank, bushing, pipe joints etc. may cause the source of major fires. It is recommended that Transformer shall be inspected daily for the oil spillage. The general CBIP recommendations for the Transformer installation are: a. Soak pits b. Drain pits c. Barrier walls d. Fire detection system e. Fire hydrant system f. Fire mulsifyre system

1.2.3.1

CONTROL OF OIL SPILLAGE Responsibility: Respective operator of Sub station • Keep a track of the maintenance schedule of Transformer & ensure that the required routine & preventive maintenance are done as per the schedule • On noticing any leakages from the Transformer immediately place a tray /container to collect the spillage and inform the maintenance

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

• •

1.2.3.2

PTRM : 0708 Page 14 of 205

department for immediate corrective action (for example replacement of gasket etc.). Oil shall not be allowed to fall on to ground. In case any leakage to ground take place, remove the same with cotton/cloth/ saw dust. In case large scale spillage immediately inform the shift in charge & start collecting the spilled oil to suitable container and assess the risk of continuous operation of the Transformer

CONTROL OF FIRE It is necessary to check the healthiness of the Transformer fire protection system regularly so that the fire risk can be minimized • There shall not be any oil leakage. • During hot oil circulation in the Transformer keep fire extinguisher ready near the Transformer, all the combustible materials shall be kept at a safe distance. • Terminal connector, Fuses shall be checked against spark. • Condition of Transformer oil shall be checked regularly • Proper Housekeeping near Transformer may help to reduce the risk of fire. • Proper fire fighting system as per CBIP recommendation shall be installed near Transformer. Regular inspection & maintenance to be done on the Fire fighting system.

1.2.3.3

PRECAUTIONS AGAINST FIRE

ISSUE/ REVISION DATE



Welding on oil filled Transformer shall be carried out if unavoidable, as per the instructions of the Manufacturer.



Hot oil circulation shall be carried out only under the round the clock supervision to prevent chances of fire on lagging materials etc.

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

1.3

PTRM : 0708 Page 15 of 205

DO'S AND DON'TS FOR SAFETY MEASURES / PRECAUTIONS Safety measures / precautions should be given top most priority during inspection / erection / maintenance work. Any mishap during the process will result in delay in erection, endangering human life, endangering equipment life etc.

1.3.1

DO'S Insulating oil and insulation of windings and connections are inflammable. Watch for fire hazards. Before entering inside the Transformer, replace Nitrogen gas completely with air if it was transported with nitrogen gas inside. Make sure that nothing is kept inside the pockets before one enters inside the main unit. Also take off the wristwatches and shoes. List up all the tools and materials to be taken inside and check it after coming out to make sure that no tools are left inside. There must be a protective guard for lamp to be taken inside. Keep inspection covers open for supply of fresh air when some one is working inside. When one person is working inside, second person must be available out side for emergency help. Use rings spanners and tie them to the wrist of the person or some where outside the tank. Be careful during connections where bolted joints are involved so that nut, washers etc. are not dropped inside the tank. If it is required to weld some lugs or brackets etc., these should be welded to tank stiffeners taking all precautions to avoid fire hazards. De-energise the unit by circuit breakers and line switches while working on energised unit. Check the diaphragm of explosion vent and replace it if cracked.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 16 of 205

Attach the caution tags "DO NOT OPERATE THE SWITCHES" while working on units, which are energised. Make sure that the fire fighting equipment is available at the oil treatment equipment as well as workplace and adjacent to the transformer. Fire fighting equipment should be checked regularly and should have sufficient quantity of extinguishant. Transformer tank, control cabinets etc. as well as oil treatment equipment shall be connected with permanent earthing system of the station. Check and thoroughly investigate the transformer whenever any alarm or protective device is operated. Check air cell in conservator. Attend leakage on the bushings. Examine the bushings for dirt deposits and clean them periodically. Check the oil in transformer and OLTC for dielectric strength and moisture content and take suitable action for restoring quality. Check the oil level in oil cup and ensure air passages are free in breather. If oil is less make up the oil. If inspection covers are removed or any gasket joint is to be tightened, then tighten the bolts evenly to avoid uneven pressure. Check and clean the relay and alarm contacts. Check also their operation and accuracy and if required change the setting. Check the protection circuits periodically. Check the pointers of all gauges for their free movement. Clean the oil conservator thoroughly before erecting. Check the OTI and WTI pockets and replenish the oil if required. Gas filled storage of transformer at site should be limited to a maximum of 3 months.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 17 of 205

Check the door seal of the Marshalling box. Change the rubber lining if required. Ensure proper tightness of top terminal of condenser bushings to avoid entry of rainwater. Check oil level in condenser bushing, any discrepancy should be reported immediately to the manufacturer. Do jacking only at jacking pad.

1.3.2

ISSUE/ REVISION DATE

DON'TS ⌧

Do not take any fibrous material such as cotton waste inside while repairing.



Do not drop any tools / material in side.



Do not stand on leads / cleats.



Do not weld, braze or solder inside the tank.



Do not weld any thing to the tank wall from outside.



Do not weld any thing to the conservator vessel if Air cell bag is inside.



Do not smoke near the transformer.



Do not use fibrous material for cleaning as it can deteriorate the oil when mixed with it.



Do not energise without thorough investigation of the transformer whenever any alarm of protection has operated.



Do not re-energise the transformer unless the Buchholz gas is analysed.



Do not re-energise the transformer without conducting all precommissioning checks. The results must be compared with factory test results.



Do not handle the off circuit tap switch when the transformer is energised.



Do not energise the transformer unless the off circuit tap switch handle is in locked position.



Do not leave off circuit tap switch handle unlocked.

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

ISSUE/ REVISION DATE

PTRM : 0708 Page 18 of 205



Do not use low capacity lifting jacks / slings on transformer for jacking / slinging.



Do not change the setting of WTI and OTI alarm and trip frequently. Setting should be done as per manufacturer's instructions.



Do not leave any connection loose.



Do not meddle with the protection circuits.



Do not leave marshalling box doors open, they must be locked.



Do not switch off the heater in marshalling box except to be periodically cleaned.



Do not allow unauthorised entry near the transformer.



Do not close any valve in pump circuit for taking stand by pump and motor into circuit.



Do not allow water pressure to exceed the oil pressure in oil to water heat exchangers.



Do not mix transformer oils of different make/ base, unless oil is new and conforms fully to IS: 335.



Do not continue with pink (wet) silica gel, this should immediately be changed or reactivated.



Do not store transformer in gas filled condition for more than three months after reaching site. If storage is required for longer duration, the main body should be filled up with oil.



Do not leave tertiary terminals unprotected outside the tank.



Do not allow WTI / OTI temperature to exceed 70°C during dry out of transformer and filter machine temperature beyond 75°C



Do not parallel transformers, which do not fulfil the conditions for paralleling.



Do not over load the transformers beyond limit specified in IS: 6600.



Do not leave secondary terminals of any CT open.



Do not measure insulation resistance by using megger when the transformer is under vacuum.



Do not stand on any vessel, which is under vacuum.

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

2.0

TRANSPORT, PACKING & DESPATCH

2.1

GENERAL

PTRM : 0708 Page 19 of 205

• Depending on the restriction imposed by the weight and transport dimensions, the transformer will be despatched either in oil filled or nitrogen gas filled condition.

• In case of transformer despatched without oil, the transformer will be pressurised with dry nitrogen gas to minimise the likelihood of condensation or moisture entering the tank.

• Transformers are supplied, fitted with nitrogen gas cylinder to maintain positive pressure during transportation and storage before erection.

• While transformers are in transit, gas pressure must be checked on daily basis and any loss of pressure must be made up by feeding gas from the cylinder. For allowable range of pressure at various ambient temperatures, please refer to Fig. 2.I. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 20 of 205

• Accessories and cooler are despatched separately. All oil pipes and chambers are despatched in sealed condition to avoid entry of water during transportation and storage.

2.2

PACKING • When any internal part like tap changer, CT's etc. are removed from the main body for transportation, they shall be despatched in tanks filled with oil or dry nitrogen gas or suitable measures are taken so that they do not absorb moisture.

• All fragile parts such as temperature indicators, oil level gauges etc. shall be carefully packed to avoid breakage in transit.

• Air cell type conservator shall be despatched with air cell mounted inside the conservator and inflated with air at a slightly positive pressure so that it remains fully tight inside the conservator. This is to avoid relative movement of air cell inside the conservator during transit and to avoid damages to air cell during handling.

• All blanking plates, valves guards etc., which are used exclusively for transportation are painted with a different colour shade than the transformer (normally post office red) and shall be preserved for future use.

2.3

RAIL TRANSPORT • Large capacity transformers are normally transported by rail due to considerations of safety and economy. Depending on the weight and dimension of the main body suitable wagons are selected for transport. It should be ensured that the dimensions of the main body when it is loaded on the particular wagon do not project beyond the limiting dimensions specified by the Railways.

• Movement sanction should be obtained form all the Railways through which the transformer has to be transported to site from the factory.

• Detached parts are packed and normally despatched along with the main body so that all parts are received at site along with the main unit.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

2.3.1

PTRM : 0708 Page 21 of 205

LIFTING & JACKING • Transformers should be lifted only by using the lifting bollards provided on the main body for the purpose. All the lifting bollards should be used simultaneously. Care should be taken to use the correct size of sling for lifting and the lifting angle should not exceed 600.

• Safe loads of wire ropes and the multiplying factor to be used corresponding to the lifting angles are shown in Fig. 2.2

Lifting Angle

Slinging Angle

MULTIPLYING FACTOR FOR DIFFERENT LIFTING ANGLES Lifting Multiplying Angle Factor

0 20 40 60

Fig. 2.2 Correct method of slinging

2.3.2

1.000 1.015 1.065 1.155

SAFE LOAD OF WIRE ROPES Dia. of Safe Wire Load Rope mm kg.

6 12 16 20 24 28 32 36 40 44 56 64 70

600 1,300 2,300 3,500 5,000 7,000 9,000 11,000 14,000 17,000 24,500 33,500 40,000

JACKING • For the purpose of jacking, only the jacking pads provided on the tank are to be used. Capacity of Jacks should be at least 1.5 times the weight of transformer. Put sufficient wooden/steel packing below the jack to support the weight. Do not lift more than 30 mm at a time. Use all jacks simultaneously. Jacks should not be left in the loaded position for long time. Transformer should be handled only in the normal upright position.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 2.3.3

PTRM : 0708 Page 22 of 205

LASHING • The transformer is lashed on all four sides by wire ropes or chain of adequate size and is tightened using turnbuckles with locking facility. After the movement of the consignment for a short distance the tightness should be checked.

2.4

ROAD TRANSPORT • Generally road transport is resorted to in case of smaller units and of • • • • •

2.5

site where rail link is not available or where well developed road system exists. Multi-axle tractors driven low-platform trailers are used for transport. Prior to taking decision to transport the heavy consignment by road a route survey has to be conducted to confirm strength of bridges and the road worthiness and to identify constraints if any enroute. Weak bridges if any should be strengthened with the help of, Highways department. A pilot vehicle with all-necessary tools and tackles and trained staff should be run in front of the vehicle. Red flags and danger lamps should be exhibited on the consignment. Tightness of lashing should be verified at frequent intervals during movement.

WATER TRANSPORT • Special cares to be taken during manufacture, packing and despatch of transformers which are to be shipped through high seas. Even if it is not specified by the purchaser the transformer should be applied with anti corrosive coating and packaging should be strong enough for possible rough handling enroute. Accessories should have polythene covering and should contain silicagel or any other suitable moisture absorbent.

2.6

SHIPMENT OF ACCESSORIES • Accessories are packed and despatched separately. Items, which are detached from the main body for transportation, are listed on the outline drawing. These will be transported in suitable crates. • Crates containing fragile items should be marked 'FRAGILE' and handled carefully during loading on vehicle, shipment and unloading at site. • Crates containing accessories, which should not be kept upside down like condenser bushings, control panel etc. should marked 'THIS SIDE UP' and should be handled as per manufacturer's instruction only.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 23 of 205

• Caution symbols for handling are painted on the packing cases.

FIG. – 2.3 2.7

SHIPMENT OF OIL • Transformer oil is despatched to site in sealed steel drums or • •

• •

tankers. When oil is filled in drums, there should be sufficient air space to allow for expansion and contraction of oil due to variations in temperature. Drums should be stacked only in horizontal position with the oil. This will avoid collection of water on top of the drum, which may be sucked in by the vacuum created inside the drum due to the expansion and contraction of oil owing to changes in ambient temperature. Due to any reason, if the drums are kept in vertical position, drums should be covered with polythene or tarpaulin sheet to avoid risk of water getting collected on top and eventually leaking into the drums. Filter holes and air release holes shall be in one horizontal line. This will avoid breathing in of moist air. If there is any leakage of oil it can

FIG. - 2.4 ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 24 of 205

easily be identified. • When oil is transported in tankers, there should be storage tanks of sufficient capacity available at site. Such tanks should be fitted with dehydrating breathers.

2.8

IMPACT RECORDERS • Impact recorders are attached to the main body of the transformer during transportation to monitor the shock, which the transformer may be subjected to, during transportation. Impact Recorders are of two types, viz. Mechanical analogue type and electronic digital type. Both types of shock recorders have ability to record shock and impact from all directions.

2.8.1

MECHANICAL TYPE IMPACT RECORDERS • The Mechanical type recorder used is of Impact-O-graph Impact Recorder Model M1 supplied by "Impact-O-Graph, Division of Chatsworth Data Corporation, 20710 Lassen Street, Chatsworth, California, U.S.A. The record will be in the form of chart, which will show the total number of impacts that have occurred, the magnitude, the direction and the time at which they occurred. Impact is recorded in both magnitude and direction through three independently operating mechanisms, which record – i. Lateral shock ('x' axis) ii. Longitudinal shock ('y' axis) iii. Vertical shock ('z' axis) Typical sensitivity (rating) values of impact recorders are as follows: i.

Trucks trailer

-

Smooth road

2g

ii.

Truck trailers

-

Rough road

6g

iii.

Railway wagons -

6g

Movement of the graph paper is powered by battery operated clock mechanism. The battery has a normal life of 6 months. At the time of despatch of the transformer from the factory, the recorders should be switched 'ON' and the time set. The cover may be locked or sealed to avoid possibility of tampering with the chart on the way.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 25 of 205

Procedure for analysing impact recorder chart results: (i)

Determine the numbers of days between switching ON the impact recorder and switching OFF and check that all the number of days has been recorded on the chart.

(ii)

For each stylus measure the length of the trace from centre line in one direction to the end of the arc that extends farthest from the centre line.

(iii)

Use the table below to find equivalent 'g' levels in the designated column (X column for 'x' axis shocks etc.) Direction

2.8.2

X

Y

Z

mm

space

2g

6g

6g

2g

6g

3

1

0.4

1.7

1.4

0.4

1.2

6

2

0.8

3.3

2.8

0.8

2.5

9

3

1.3

5.0

4.2

1.3

3.7

12

4

1.7

6.3

5.5

1.7

5.0

15

5

2.1

8.2

6.9

2.1

6.2

ELECTRONIC DIGITAL TYPE IMPACT RECORDERS • The Impact Recorder is of “Sensorex Minishock” supplied by : • M/s. International Business Park – Archamps, 74165 Saint Julien, En, Genevois, France.

• The Minishock is a recorder designed for the simple instrumentation of the conditions of transport. With three accelerometers, the 128 highest shocks are measured, dated and memorised in each X, Y and Z-axes. Provisions for recording temperature and humidity are optional in this type of instrument.

• The Minishock is a self contained reorder designed for use in the transport and packaging sectors. This instrument will measure and date shock, temperature and humidity (optional).

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 26 of 205

• Shocks are recorded when the acceleration passes a predetermined threshold in each of the X, Y and Z-axes. Only the 128 shocks of greatest intensity are memorised, thus reducing the data overload.

• Before the mission, the threshold limits above which the shocks are to be recorded are determined and the Minishock is activated. During the mission, the acceleration is measured continuously and recorded together with the date and time, whenever the threshold is exceeded. After the mission, the data is downloaded via a RS 232 link and visualised using the Logishock software. The data can be visualised graphically or in the form of tables. The Sensor characteristics are as follows: i. Range

: ± 10 g

ii. Resolution

: 0.1 g

iii. Accuracy (250 C)

: ± 0.2 g

iv. Threshold

: from 1.5g ~ 10 g

v. Band width

: 25/ 50/ 100/ 200 Hz

vi. Sampling periods

: 1 minute to 4 hours.

vii. Power source

: Works with a standard lithium battery

• In case the transformer suffers serious shock during shipment, the core and coil will have to be subjected to through inspection before erection and commissioning.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 27 of 205

3.0

STORAGE

3.1

RECEIVING MAIN UNIT AND ACCESSORIES • When a transformer arrives at site a careful external inspection must be made of the unit, its cooling system and all sealed components, referring to the general arrangement drawing and the shipping list.

• Inspect all packing cases and loose components for damage or missing items.

• Check whether the transformer has arrived at site with a positive gas pressure in case of despatch without oil. In case of despatch of main body in oil filled condition, the oil level should be checked. One transport oil level gauge is welded near the top of the tank for indicating the level of oil in the tank.

• Should the transformer arrive at site without pressure (owing to gas leakage) it must be assumed that moisture has entered the tank and that the moisture will have to be driven out. In such cases the manufacturer’s advice must be sought.

• Confirm that case numbers match with the packing list. Check their contents tally with the packing list if the packing case is damaged.

IMPORTANT: • If any scratches or damage to the paint is noticed on receipt of Main body or Accessories, touchup painting should be done immediately over the damaged area. For procedures of touchup painting, refer to “ Clause 4.22: Touchup Painting at site”.

3.1.1

REPORT OF DAMAGE PARTS ETC. • If any damage is noticed, claim must be lodged with the insurance agency and the matter must be reported promptly to the manufacturer. The report should contain sufficient details of damaged parts and extent of damage so that the cost of replacement /rectification can be worked out.

3.1.2

INSPECTION OF MAIN UNIT GAS FILLED • After receipt of consignment at site, gas pressure inside the tank and the temperature at the time of measurement should be recorded. The value obtained should be compared with the gas pressure versus temperature chart furnished in the instruction manual. (Refer fig.– 2.1 of chapter 2)

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

3.1.3

PTRM : 0708 Page 28 of 205

INSPECTION OF MAIN UNIT OIL FILLED • Upon arrival at site, check oil level inside the tank. If a transparent oil level gauge is not provided, the oil level can be measured by connecting a transparent hose between the bottom and top sampling valves.

• Check for damages to valves etc. • A sample of oil should be taken from the bottom of the tank and tested for BDV and moisture content. If the values do not meet the relevant standards the matter should be taken up with the manufacturer.

3.2.1

UNLOADING OF MAIN UNIT • In cases where the substations are having adequate crane facility; the transformer is unloaded by crane. Alternatively, mobile cranes are used. Where no crane facility is available a trench is dug to a depth equal to height of the trailer platform and the transformer is slid to position. If this also is not possible the transformer is unloaded into a sleeper platform and gradually lowered to plinth level (Refer Figure 3.1 for guidance). The sleeper platform level is to be at a slightly higher level to allow for the increase in height of the trailer while the load is released due to the springs getting relaxed. Winches are to be used for putting the transformer into position.

Fig. 3.1

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 29 of 205

• Lift the main body of the transformer with a mobile crane and wire ropes. The crane capacity must be at least 10% higher than the weight of consignment. Lifting angle of ropes should be limited to 30 deg. to vertical. • Unloading must be done with maximum care, avoiding any jerking movements or dropping. • Use only the lifting bollards/hooks for slinging while lifting. • For lifting with hydraulic jacks, the transformers are provided with jacking pads dimensioned for lifting the complete transformer filled with oil. • If the foundation of the transformer is not ready and if the transformers are to be unloaded temporarily, it should be done on leveled hard surface. Under base of the transformer should not rest on the ground as it will lead to rusting of the transformer. • Place at least 300 to 400 mm wooden sleepers to facilitate jacking.

3.2.2

PLACING IN POSITION •



ISSUE/ REVISION DATE

If foundation is ready and if rail link between unloading point/storage place is available, then the main body of the transformer must be moved on its own rollers to the foundation where the transformer is to be erected finally. If the transformer is not provided with rollers and if it is to be erected on its skid base, the transformer must be slid to its final position using greased steel plates to protect the plinth surface and make movement easier. The plates should form a continuous surface and it must clear the final jacking areas.

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS



• •

3.2.3

PTRM : 0708 Page 30 of 205

The transformer must be pulled by using slings and winches as shown in Fig. - 3.2. Use only the specified haulage lugs for pulling. Pulling capacity of winches should be more than (Main body weight x 0.15/4) tons. Pulleys should have a capacity of (Main body weight x 0.15/2) tons. When jacking (e.g. to remove steel plates), position the jacks under specified jacking pads only. When jacking, ensure that all four jacks are operated simultaneously. Before lowering, clean all grease dirt etc. from the under base of the transformer.

UNPACKING AND INSPECTION OF ACCESSORIES • Crates / packages are to be opened carefully so that the tools used for opening do not cause damage to the contents.

• Drums containing transformer oil, which have been despatched separately, shall be examined carefully for leakage.

• In case of Condenser Bushings, oil level shall be checked. Porcelain should be checked thoroughly for any crack or chipping. Any oil leakage or damage to porcelain must immediately be reported.

• Fragile instruments like oil level gauges, temperature indicators etc. are to be inspected for breakage or other damages.

• Any damage or short shipment should be reported to the manufacturer.

3.3

STORAGE OF MAIN BODY

3.3.1

GENERAL • It is preferable to erect the transformer immediately on receipt at site and fill with transformer oil. However, if it is not possible, the following precautions should be taken for storing the main body and accessories for longer duration:

• The storage area should be adequate and should be easily accessible for inspection.

• The surface on which it should be stored is strong and levelled. • Surrounding area of storage is not polluted and water does not accumulate in the storage area.

• Sufficient space is provided underneath for free flow of air and also for lifting, jacking etc. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 3.4

PTRM : 0708 Page 31 of 205

GAS FILLED STORAGE • It is recommended to keep the transformer oil filled immediately after receipt. If oil can not be filled immediately after receipt of main body, it must be retained with dry nitrogen gas filled at a positive pressure of 0.2 kg/ cm2 at about 20OC. (Please ref. Fig.– 1 of Chapter 2 for Pressure Vs Temperature Chart).

• The duration of gas filled storage should be limited to 3 months from the receipt of main body at site.

• If the pressure of gas inside drops due to leakage, the leakage point may be detected by using soap water. The matter shall be reported to the manufacturer for immediate corrective action.

1. Cylinder Key. 2. Top sampling valve of transformer. 3. Gauge for reading gas pressure inside the transformer 4. Adapter. 5. Gauge to indicate gas pressure in the cylinder 6. Gas pressure regulator. 7. Gauge to indicate gas pressure from the regulator 8. Pneumatic pressure hose. 9. Hose clip. 10. Nitrogen cylinder.

FIG. — 3.3 • Should it not be possible to rectify the leak immediately, the transformer must be covered by putting a tarpaulin sheet over the whole tank until remedial measures can be carried out.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 32 of 205

• Gasket must not be tightened indiscriminately as this could result in • •

• • 3.5

OIL FILLED STORAGE • If the gas pressure on arrival at site is found satisfactory, it can be • • • •

• • • 3.6

loss of gasket property due to over compression. The arrangement for gas filled storage is shown in fig. - 3.1 Pressure inside the transformer should be monitored on daily basis and any pressure drop should be made up by opening the cylinder and operating the pressure regulator. The cylinder should be kept closed. Before deciding on loss of pressure, the pressure versus temperature chart (Fig. –2.1) shall be referred to. If the storage period of transformer at site is expected to be beyond 3 months, it is recommended to keep it filled with transformer oil.

assumed that there is no leakage. Before filling oil, all the valves, which were detached during transport, should be fitted back and blanked. If possible, the main body shall be fitted with its own rollers and supported on rails and locked in position. Assemble conservator, pipe work and fix silicagel breather. Oil shall be filled upto the conservator corresponding to the ambient temperature. If the transformer foundation is not ready, it may be stored in any convenient location. In that case, oil shall be filled upto the level so as to immerse all the insulation parts in oil and the space above should filled with dry gas. Fix silicagel breather at any convenient point on the cover. If the main unit is received at site filled with oil, fit a silicagel breather on any opening on cover with a suitable pipe. Before filling oil inside the transformer, its BDV and moisture content should be measured. If values are not within limit specified, the oil should be filtered.

STORAGE OF OIL • If the oil is received at site in tankers, it is necessary to provide an oil storage tank of enough capacity to hold the oil for one transformer.

• The oil storage tank should be equipped with valves for oil filling, draining, sampling and filtration, oil level gauge, silicagel breather and a manhole on top cover. The inside of the tank should be painted with oil resistant paint / varnish. Before filling oil, the inside of the tank should be cleaned thoroughly.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 33 of 205

• If the oil is received at site in sealed drums it may be stored in horizontal position as shown in Fig 3.2 and covered with tarpaulin sheet. Filter holes and air release holes shall be in one horizontal line. This will avoid breathing in of moist air. If there is any leakage of oil it can easily be identified.

• The storage area should be free from fire hazards.

Fig. 3.4 3.7

STORAGE OF ACCESSORIES • The following points may be taken care of in order to keep accessories in good condition without damage, rust and dust.

• Check and confirm that all packing cases as per packing list are received in good condition.

• If erection work is not likely to commence immediately the boxes, which are opened for inspection, should be repacked and the packing list retained for future reference and records.

• All packing cases should be kept above ground on suitable support so as to allow free circulation of air underneath. Water should not collect in the storage area. There should be sufficient space for inspection, handling and transport.

• All fragile items and instruments should be stored indoors. • All crates should be kept as per the markings provided on the crates by manufacturer. As a general rule, all control boxes such as RTCC Panel, Marshalling Box, Drive Mechanism etc. should be kept indoors in vertical position. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 34 of 205

• Crates should not be stacked one over the other. • Strictly adhere to the specific storage instruction provided by the manufacturer for specific items.

• Table - 1 may be referred to for further guidelines for storage and periodical inspection of transformer accessories. Table- 1 Sr.

Accessories Storage

No.

Position

Position

Precautions

Location

Special

Inspection

Instructions

check

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 35 of 205

4.0

INSTALLATION

4.1

TOOLS AND EQUIPMENT REQUIRED AT SITE FOR ASSEMBLY: Sr. No.

ISSUE/ REVISION DATE

Tool/ Equipment

Qty.

Specifications

1

Oil Storage Tank

1 No.

Mild Steel Tank of sufficient capacity to store the complete oil in the transformer. The tank shall be fitted with inlet and outlet valves of 50 mm diameter. Inside of the tank shall be thoroughly cleaned and coated with hot oil resistant varnish/ paint.

2

Oil Purifier

1 No.

Oil purification plant shall have at least 6 kiloliters/ hr. capacity and vacuum dehydrator, oil heater and filtering device.

3

Vacuum Pump

1 Set

Vacuum Pump should have capacity to evacuate the tank mentioned above and having a maximum leak rate of 0.5 torr. in one hour to an ultimate vacuum of 0.1 torr. in 2 hours.

4

Flexible Oil Hoses:

20/10/05

(of 3 m length)

5 Nos.

(of 10 m length)

2 Nos.

(of 10 m length)

2 Nos.

28/01/07

Flexible oil hoses of 50 mm dia. with flanges on either end. These hoses shall be capable of withstanding vacuum of 0.1 torr. 50 mm dia. with flanged ends and capable of O withstanding 120 C

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 36 of 205

Sr. No.

Tool/ Equipment

Qty.

Specifications

5

Flexible Vacuum Hoses of 10 m length

2 Nos.

Flexible vacuum hoses of 75 mm diameter with flanged ends. The hoses shall be capable of withstanding full vacuum.

6

Oil testing equipment

1 Set

Oil testing equipment shall be capable of checking break down voltage of transformer oil across 2.5 mm sphere gap 60 kV (min.).

7

Vacuum Gauge

2 Nos.

Vacuum gauge of Mc Leod type capable of measuring vacuum less than 0.01 torr

8

Compound Gauge

1 No.

Compound gauge for a pressure range of -760 to +760 mm of mercury

9

a)

Megger

1 No.

Megger of 5 kV with motor operation is preferable.

b)



1 No.

Megger of 2 kV.

c)



1 No.

Megger of 500 Volts.

10

Multi meter

1 No.

11

a)

3 Nos.

0 ~ 300 V AC range.

3 Nos.

0 ~ 75 V AC range.

2 Nos.

100 W Lamp of 100 V or less with sufficient length of flexible cable and bulb protector.

Voltmeter

b) 12

ISSUE/ REVISION DATE

20/10/05



Electric Hand Lamp

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

Sr. No. 13

Tool/ Equipment Mobile Crane

Qty. 1 No.

PTRM : 0708 Page 37 of 205

Specifications Mobile crane of 5 or 10 Tonnes capacity with a maximum lift of 20 meters.

14

Slings and Shackles

Sufficient Nos. Slings and shackles of sufficient length to handle weight up to 25 tonnes.

15

Water Proof Sheets

40 m2

For temporary exposed parts

16

Vinyl Hose

30 meters

Transparent vinyl hose of 12 mm dia to be used as oil level gauges.

17

Hose Nipple

2 Nos.

12 mm hose nipples

covering of

with flanges on one side to match valve flanges.

ISSUE/ REVISION DATE

18

Methyl Ethyl Ketone / 10 litres For cleaning purpose. Carbon tetra chloride

19

Rag Cotton cloths

20

Unstarched Mill Cloth

10 m.

For cleaning internal Parts.

21

Knife

2 Nos.

For cutting insulation parts.

22

Spanners

2 Sets

All standard sizes for both metric sizes up to 42 mm and BS ½ to 1½.

23

Screw Driver

2 Nos.

6" Screw driver (-).

24

Painting Brushes

6 Nos. each

15 mm, 25 mm & 75 mm

20/10/05

28/01/07

20 kgs. For cleaning purpose.

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

Sr. No.

Tool/ Equipment

25

Qty.

PTRM : 0708 Page 38 of 205

Specifications

a) 3 Phase, 440 Volts, 50 Hz. Electric Power Supply for Operating the vacuum pump and filter machine b) Water Supply if Purifier is water cooled.

ISSUE/ REVISION DATE

26

Pulling winches/ Pulleys

2 Sets each

Please refer section 4.3.

27

Hydraulic/Mechanical Screw Jacks with Locking facility

4 Nos.

50% of total weight of main body with oil.

28

Measuring Tapes

2 Nos.

10 meter long.

29

Spirit Level/Level tube (Plastic)

1 No.

30

Dry Air Generator (For Transformers of 400 kV class and above)

1 No.

20/10/05

28/01/07

Capacity; 4~5 m3/hr. Dew Point –40O C Temperature 25 ± 5OC, Outlet pressure 200 Aq.

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

4.2

PTRM : 0708 Page 39 of 205

OIL SAMPLING AND FILTERING • Oil should not be filled in the transformer directly from the drums or transport container as there is a chance of precipitated water or sediments may also be pumped into the transformer along with the oil. • Oil from the drums or transport container should be filled into the oil storage tank and oil parameters should be tested before it is filled into the transformer. • If oil is received in drums, samples should be taken for testing from as many drums as shown in the Table -1 at random. Table -1 Selection of Samples from drums No. of Drums in a Batch

No. of Drums from which Samples to be taken

2 to 5

2

6 to 20

3

21 to 50

4

61 to 100

7

101 to 200

10

201 to 400

15

401 and more

20

• Samples should be collected from the bottom of the drums as shown in fig.–4.2 for testing.

FIG. – 4.2 ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 40 of 205

• If oil is received in containers, oil sample shall be collected through the sampling valve at the tank outlet or by means of thief dipper as suggested for sampling of oil from drums. The container should be allowed to stand for atleast one hour before drawing the sample. • Conduct the following tests for ascertaining the quality of oil. ♦ Breakdown Voltage test ♦ Moisture content test ♦ Tan delta ♦ Resistivity

• If oil does not meet the specified criteria, oil should be filtered and stored in the oil storage tank before filling in to the transformer.

• While pumping oil from the barrels, the barrels may be tilted suitably to ensure that complete oil is taken out from each barrel.

FIG. – 4.3

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

4.5

PTRM : 0708 Page 41 of 205

ERECTION PRECAUTIONS NOTE: PRECAUTIONS MUST BE TAKEN TO ENSURE THAT ALL GAS PRESSURE IN THE TRANSFORMER IS RELEASED BEFORE ANY ATTEMPT IS MADE TO REMOVE A COVER AND DRYNESS (DEW POINT) OF GAS IS CHECKED BEFORE A GAS CYLINDER IS USED.

• During erection it is advisable that only one hand hole cover is opened at a time in order to minimise the ingress of moisture. The hand hole cover should be replaced as soon as the operation is completed.

• Dry air of dew point –40OC or better must be fed through the inside of tank when covers are removed in case of 400 kV and higher class of transformers to avoid direct contact of winding insulation with moist air outside.

• It is essential that the transformer be filled with oil immediately on completion of work. The exposure should not be allowed more than 16 hours at stretch.

• Insulation resistance between core frame and tank must be checked before oil filling with a 2 kV megger, the insulation resistance must be compared with the factory test results.

• Measure the insulation resistance between: I. II. III. IV.

ISSUE/ REVISION DATE

HV – Earth (Tank) LV/ IV – Earth (Tank) HV – LV/ IV Core Frame – Earth (Tank)

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

4.6

PTRM : 0708 Page 42 of 205

ERECTION PROCEDURE The following flow chart shows the installation procedure generally followed at site. PREPARATION FOR INSTALLATION . INSTALLATION OF MAIN BODY ON FOUNDATION . RECEIVING INSPECTION AND STORAGE . OIL RECEIVING AND FILTERING . REPLACING DRY GAS WITH OIL . ASSEMBLE BUSHING TURRET . ASSEMBLE LV BUSHING AND CABLE DUCT . ASSEMBLE COOLERS . ASSEMBLE CONSERVATOR . ASSEMBLE PRESSURE RELIEF DEVICE . ASSEMBLE HV BUSHINGS . ASSEMBLE ACCESSORIES . INTERNAL LEAD CONNECTIONS . CONTROL WIRING OIL LEAKAGE TEST . OIL FILLING UNDER VACUUM . PAINTING (Ref. Cl. 4.22) .

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

4.7

PTRM : 0708 Page 43 of 205

REPLACE DRY GAS WITH OIL • After installing the transformer on the foundation dry gas in the transformer should be replaced with treated oil.

• Oil should be tested for breakdown voltage and it should be above 55 kV / 2.5mm gap.

• Make sure that the hose and pipe interiors are cleaned in advance. • Connect the oil pipes to the lower filter valve. Ref. fig.– 4.4 Transformer

Oil Storage Tank

Dry Gas Filter Press

Transparent Vinyl Hose (For oil level Indication)

FIG. – 4.4 • Attach a transparent vinyl hose to indicate the level of oil being filled in the transformer.

• Open the top filter valve or any other bolted covers on topmost point on the transformer for releasing dry gas at the time of oil filling.

• Open the bottom filter valve on the transformer and top air release valve on the oil storage tank.

• Oil should be filled upto a level above the top insulation of transformer winding.

• A small gas space (approx. 5~10%) should be left above oil for expansion of oil.

• During oil filling, if the filter press stops due to any reason, the top filter valve and any other opening on the top of the transformer should be closed immediately to prevent air getting into the transformer. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 44 of 205

• Oil level shall be continuously monitored during oil filling. • While filling oil directly from the barrels, the barrels shall be tilted suitably to ensure that complete oil is taken from the barrels.

• After filling oil, if the storage is expected to be for a long period, dry gas should be filled above the oil at a pressure of 0.1 ~ 0.2 kg/cm2.

• Assembling work should start from the bottom of the tank so that after initial oil filling, oil need not be drained again for assembling work.

4.8

PRECAUTION TO MAINTAIN QUALITY • As a precautionary measure to restrict absorption of moisture, the transformer should not be exposed to atmosphere for more than 8 hours continuously and erection work should be scheduled accordingly.

• Following each day’s work, transformer should be kept oil filled. • For high voltage jobs of 400 kV and above, dry air having dew point below -400C should be purged inside the tank during internal assembling work.

• Transformer should be tested for B.D.V. before filling and it should be more than 55kV at 2.5 mm gap.

• Extreme care shall be taken against any foreign objects falling inside the transformer tank during inside working.

• Keep only one man hole open at a time and close it as soon as possible.

• Avoid inside working on rainy days. • Earthwork near the transformer should be avoided when internal assembly is in progress to avoid ingress of dust.

• While scraping the gasket surfaces of bushing bases, inspection covers etc., keep a cloth below to avoid the scraped material falling into the transformer.

• Any tools taken inside should be tied by string or cotton tape to the person who is using the same.

• No. of tools shall be counted and recorded before and after each days work in order to ensure that no tools are left inside.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 45 of 205

• Gaskets used are of synthetic rubber bonded cork material. These are to be compressed to 50 ~ 60% of its original thickness. Over tightening and under tightening of gaskets should be avoided as these may cause oil leakage and shortening of gasket life.

• Tightness of all inside connection should be checked and proper locking shall be provided.

• Persons working inside the transformer or top of the transformer should not wear wristwatches, pen, coins etc.

4.9

ERECTION OF PIPE WORK • All items of pipe work are match marked. • All joints are to be assembled with gasket only and without joining compounds or grease.

• Joints must be fully tightened only when the transformer has been fully erected; by that stage the pipes can be centralised.

• No pre determined torque values are applicable. • No joint must be under excessive assembled load as subsequent expansion or contraction could cause leaks.

• Ensure that all accessories belong to the same unit. Indent No., Unit No. and Serial numbers of each item are marked on each item. This is to avoid mismatching at site. E.g.:

670700002 / 4 / 209 shows: Sale Order No.: 670700002, Unit No.: 4 and Serial No. of item : 209

• Serial numbers of all items, which are dismantled from the main body and sent separately, are shown in "PART MARKING AND CABLE WIRING" drawing.

4.10

ERECTION OF COOLER BANK • Generally for oil forced cooled transformers radiators will be mounted in a separate cooler bank.

• Cooler headers supporting ‘A’ frame are mounted on separate foundations. Refer "FOUNDATION DRAWING" for details.

• Since cooler headers are provided with butter fly type shut off valve, oil from main body need not be drained for assembling cooler. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 46 of 205

• Cooler Assembly should be carried out referring to "GENERAL ARRANGEMENT" and "PART MARKING DRAWING" of the transformer.

• Check and ensure that level of all the foundations for cooler support are in same level as that of the top surface of rails. Level difference should be compensated by putting shims if the level is lower and chipping the concrete foundation if the level is higher.

• Fix cooler header mounting frames as per dimensions shown in General arrangement and Foundation Plan drawing.

• Mount cooler headers loosely. Final tightening to be done only after proper alignment.

• Top and bottom butterfly valves of all radiators should be in the vertical line. This should be confirmed by a plumb.

• Remove blanking plates from the butterfly valves. • Tighten the cooler frame foundation bolt, and clamping bolts of cooler headers and pipe connections.

• While mounting the oil pump and oil flow indicators, care should be taken to ensure the arrows indicating the oil flow direction are towards the transformer tank.

• While mounting radiators care should be taken to ensure that the weight is balanced.

• Ensure that a fresh gasket is used while mounting the radiators. • In case of separately mounted coolers, the oil pipes are provided with expansion joints. Tack welded bars on expansion joints should be removed.

• Fix the fan mounting frames and fans as indicated in the general arrangement drawing.

• Fan & mounting frame shall be connected to the earth grid. 4.11

CONSERVATOR • Mount the conservator as shown in G.A. Drawing. • Very often the small conservator for on load tap changer is attached to the main conservator.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 47 of 205

• Usually the main conservator is provided with Magnetic Oil level Gauge having low oil level alarm contacts and OLTC conservator is provided with oil sight window.

• Magnetic oil level gauge shall be mounted after attaching the float to the gauge. Check and confirm free movement of float arm and proper locking of float to the float arm.

• Mount all valves as shown in GA drawing on the conservator. • Mount the connecting pipe with Buchholz relay from the main tank to the conservator. Ensure direction of Buchholz Relay by the direction of arrow on Buchholz Relay towards conservator.

• Mount connecting pipe with oil surge relay from OLTC to the conservator.

• Mount breather connecting pipes and silica gel breathers for the main tank and OLTC conservators.

METHOD OF MOUNTING FLEXI SEPARATOR (AIR CELL) INSIDE THE CONSERVATOR

PROCEDURE - I (OIL FILLING WITHOUT VACUUM)

• Set up the air cell in side the conservator. Care should be taken to see that the hooks on air cell are properly engaged in the brackets provided in side the conservator.

• Inflate the air cell at a pressure as shown in the instruction plate (DO NOT APPLY EXCESS PRESSURE AS IT MAY DAMAGE THE AIR ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 48 of 205

CELL) through the breather connection pipe. Follow the instructions given in the Instruction Plate fixed on the transformer.

• Ensure that there is no leakage. • The conservator with Air Cell is pressure tested and despatched from the factory at a slightly positive pressure. Confirm that there is no oil leakage.

• Fix three numbers air release valves on the conservator. • Keep air release valves open. Fix air filling adapter on breather pipe and inflate the air cell at an air pressure indicated on the INSTRUCTION PLATE affixed on the transformer and hold air pressure.

• Open the air release valves and start oil filling from the bottom filter valve of the transformer.

• Observe the air release valves and as soon as oil starts overflowing, close the air release valves one by one. Stop oil filling when all air release valves are closed.

• Remove the air filling adapter. • Continue oil filling and observe the Magnetic Oil Level Gauge (MOLG)

• Stop the filling when the needle of MOLG shows the level corresponding to the ambient temperature at the time of filling.

• Fix silica gel breather. CAUTION: Do not open any of the air release valves after completion of oil filling. If air release valve is opened, air will enter and oil level will drop. The plain oil level gauge on the end cover of the conservator should indicate full oil level always. If air enters the conservator, it can be seen by a fall in the oil level in plain oil level gauge. The plain oil level gauge should be monitored on regular basis. FILLING PROCEDURE UNDER VACUUM IN CONSERVATOR The conservator, with its separator, being set up and plugged in above the transformer, is connected to its oil filling reserve by a pipe in its lower part.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 49 of 205

Proceed as follows: • Create a vacuum in separator. • With the same source of vacuum, create a vacuum in the conservator.

• Open the oil filling valve of the transformer. Because of the vacuum in the conservator, the oil level rises automatically.

• Stop the oil filling once the required volume in the conservator is attained.

• While maintaining the conservator under vacuum, allow Dry Air or Nitrogen gas to enter into the internal part of the separator. Then, the separator inflates by itself, and takes all the free space due to the fact that the conservator was not completely full. In particular, during the operation, the oil is going to rise to the top of the conservator.

• Inflate the separator at a maximum as shown in the INSTRUCTION PLATE.

• Check on the vent-holes, and confirm that there is no more air in the conservator or, if necessary, adjust the level. CAUTION: The above mentioned CAUTION regarding the opening of air release valves after completion of oil filling is applicable for this case also.

4.12

PRESSURE RELIEF DEVICE • Mount PRD as per manufacturers leaflet and also the G.A. drawing of Transformer.

• Check operation of alarm/trip contacts.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 4.13

PTRM : 0708 Page 50 of 205

ERECTION OF HV TURRETS AND BUSHINGS

FIG.— 4.5 METHOD OF LIFTING CONDENSER BUSHINGS FROM PACKING CASE AND MOUNTING ON THE TRANSFORMER AT AN ANGLE

• Before starting the erection work of Condenser Bushing, lift the Bushing from its crate and keep it vertical and check the oil level. Confirm that oil level is up to the centre of oil sight window of Bushing.

• Part numbers of Bushing turrets are indicated in the part marking drawing.

• If oil is drained from the tank a continuous supply of dry air should be ensured while removing the blanking plates and fixing the bushing turrets and bushings.

• Dry air shall have a dew point of -40OC or better. • Total exposure time should not exceed 8 hrs. • At the end of each day’s work, blank off all openings and pressurise with dry air.

• If weather is bad (rain, snow or fog) the tank should not be opened unless adequate shelter is provided. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 51 of 205

• For details of connections from winding to the bushing please refer to the specific drawing and suppliers catalogue given in the instruction manual.

• Ensure that a fresh gasket is used while mounting the bushing. • Ensure that the air release pipe connections are oriented towards the correct directions, as shown in the GA and part marking drawings.

• Check for match markings on the mating flanges. • Bushing shall be mounted in the order of B, A, C or B, C, A. • While mounting the bushings, ensure that the oil level gauge is oriented away from the transformer.

• While lowering draw lead type condenser bushing the cable shall be held tightly by using strong steel/plastic rope. Remember that dropping of cable can cause injury to the personnel and damage to the transformer.

• Check and ensure that secondary terminal of turret mounted C.T. if any are connected to the proper terminals on the terminal board.

• Check and ensure that secondary leads of C.T's. mounted inside the transformer are connected to the proper terminals in the terminal board.

• If holes are not provided in the CT terminal box for fixing cable glands, suitable holes shall be drilled and cable glands assembled.

• Fix all air release pipes between bushing turrets and Buchholz relay connecting pipe. Please refer to the part marking drawing for respective part numbers of air release pipes.

4.14

TEMPERATURE INDICATORS • Sensing elements of oil and winding temperature indicators are to be fitted on to the thermometer pockets welded on the top cover of the transformer.

• Before mounting the thermal sensing bulbs, inside of the pocket should be cleaned thoroughly and filled with transformer oil upto a depth of half the pocket.

• Care should be taken not to damage the capillary tubing. Capillary tubes should be clamped properly.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 52 of 205

• RTD (if provided and shown in GA drawing) sensor element and heater coil are fitted on the cover.

• Fill oil in the pocket after cleaning. • CT leads shall be connected on one side and sensor leads are taken from the other side.

• RTD instruments are mounted on the remote panel in the control room.

4.15

OLTC DRIVE MECHANISM • In case of on load tap changing transformer, the OLTC driving mechanism has to be mounted on the transformer. Please refer to the OLTC instruction manual supplied by the OLTC manufacturer.

• Check for mechanical stops at extreme positions by manually operating with the handle.

• Bring the tap position in DM to the tap position 1. • Connect 3-phase supply with correct phase sequence. • Check raise/lower operations. If direction is correct, check electrical end stops at extreme positions.

• Bring back the DM to the tap position 1. • Different manufacturers of OLTC adopt different designs for the DM. Some manufacturers adopt dry type gear box for the motor and some manufacturers adopt oil filled gear box. Oil, if required, shall be filled as per the manufacturer's instructions.

• Coupling up of drive mechanism and OLTC bevel gear shall be done only after ensuring that both are at the same tap position. Normally the transformer is despatched from the factory at rated Tap position.

• Operate the DM manually from rated tap to tap no. 1 and then to the other extreme tap position and bring back to rated tap.

• Operate DM electrically. Check and confirm that for each impulse given in both raise and lower directions, diverter switch operation sound is heard before the motor stops. After hearing the sound, the travel of the tap position indicating disc upto the green band shall be equal in both forward and backward crank operation.

• Verify the ratios on all taps using ratio meter or digital voltmeter.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

4.16

PTRM : 0708 Page 53 of 205

CABLE BOX ASSEMBLY • If cable box is provided, the assembly shall be carried out referring to the cable box assembly drawing provided in the Instruction Manual.

• Cable sealing ends shall be fitted on to the end of the cable before it is inserted and bolted on to the cable box.

• Cable box assembly may be bolted to the disconnecting chamber on the transformer tank.

• Flexible connections shall be made between bushings and cable box bus bars through the Inspection Cover.

4.17

INSTRUCTIONS REGARDING USAGE OF GASKETS • Gasket materials used are either Synthetic Rubber Bonded Cork (SRBC) sheet or nitrile rubber.

• SRBC material conforms to RC-70C of IS : 4253(Part II); thickness used are 6.0 mm and 10.0 mm.

• Gaskets should be stored in stress free condition and must be protected from moisture, oil and grease.

• Synthetic rubber bonded cork sheets once used should not be used again.

• Gasket seating surfaces should be smooth and free from scratches, oil, grease, dirt etc.

• Gasket should be properly located before tightening. • Gasket joints are designed with 40~50% compression. • Gasket joints should be tightened evenly with a diametrically opposite sequence.

• Full compression should not be achieved in one go. • Over tightening will cause the gasket material to loose its properties and under tightening may not prevent oil leakage.

4.18

CHECKING LEAK RATE UNDER VACUUM • Drain oil & create vacuum of 200 torr inside the tank, close the valve between vacuum pump and tank and stop the pump and hold the vacuum. There should be no appreciable loss of vacuum over one minute.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 54 of 205

• If there is leak, find out the leak and rectify. • Start the pump and open the valves and continue till a vacuum of 10 torr is achieved.

• Close vacuums valve and stop the pump. • There should not be an increase of pressure of more than 1 torr over half an hour.

• IF the rise in pressure is more, find out leak and rectify. • If results are satisfactory, restart the vacuum pump open the valves and continue pumping to obtain a vacuum of 1 torr or better and maintain this vacuum for more than 24 hrs. before and during subsequent oil filling operations.

4.19

INSULATION OF CORE AND FRAME TO TANK • If the internal body earthing lead is brought out through low voltage bushings, the megger values shall be measured using 2 kV megger and the values recorded.

4.20

OIL LEAKAGE TEST • Oil leakage test is done after attaching the oil pipes, bushing, radiators, conservator, relief device and all the instruments.

• Remove the breathers and connect dry gas cylinder with pressure gauge to the connecting pipes if conservator is not provided with air cell. If conservator is fitted with air cell, pressure shall be applied after connecting an equaliser pipe between the air release valve and breather connection pipe. Otherwise the air cell may get damaged.

• Remove PRD and explosion vent if provided and blank the opening. • Open all valves between conservator, main tank and OLTC. • Fill oil in the transformer upto 1/3 rd of the conservator through oil filter.

• Apply a gas pressure above the oil such that the pressure at the base of the tank is between 0.7 kg/cm² to 1.0 kg/cm².

• Check for oil leakage at all bolted and welded joints by keeping the pressure for 12 Hrs.

• If any leakage is noticed, rectify the leak and continue the test. • Break pressure and reassemble breathers, PRD, explosion vent etc. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 4.21

PTRM : 0708 Page 55 of 205

VACUUM OIL INJECTION • Oil injection shall be made under full vacuum (1.0 torr or better) for transformers above 66kV. 380 mm Hg or better vacuum is required for transformers rated for 66kV and below. The vacuum shall preferably be measured by using McLeod Vacuum Gauge.

• After draining the oil completely from the transformer, vacuum should be pulled from the oil filling hole on main conservator. If the conservator is fitted with air cell, pressure equalising connection is required to avoid damage to the air cell.

• For facilitating evacuation of main transformer and diverter switch compartment of OLTC simultaneously, an equaliser pipe (Refer GA drawing for item number & location) is supplied. This is to be fitted during evacuation and removed after vacuum oil filling.

• Before starting vacuum, all bolted connections shall be checked. • Radiator valves shall be kept open. • A transparent vinyl hose shall be connected to the bottom sampling valve (Refer Fig. – 4.4) for indicating the oil level.

• If explosion vent is provided, the pressure shall be equalised on either side of the diaphragm to avoid damage to the diaphragm.

• Vacuum shall be maintained for 6 hours. • Oil may be injected through the bottom filter valve until the level reaches 35OC marking on the Magnetic Oil Level Gauge of the conservator.

• Initial oil filling shall be done at a slow rate. Rise in oil level per hour inside the transformer shall be limited to 300 mm.

• Natural rubber hose shall not be used as sulphur in the rubber may react with oil.

• Oil inlet valve shall be closed and after one hour the vacuum shall be broken.

• Oil level indicating vinyl hose can be removed by closing the bottom sampling valve.

• Vacuum gauges may be detached and breathers assembled in its position.

• Pressure equalising connection provided for explosion vent diaphragm and OLTC diverter chamber shall be removed. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 4.22

PTRM : 0708 Page 56 of 205

TOUCH UP PAINTING AT SITE • Any damage to the painting of the transformer and accessories shall be made good after erection work is completed.

• If a welding has been done on the transformer at site, the paint film burnt by the welding shall be removed by wire brush or metal spatula.

• Remove the rust by wire brush and emery paper #80 / #100. • Wash away the oil, grease, dirt and dust by using suitable solvent and dry it up.

• Polish the surface to be painted by using emery paper #80 /#100 and then clean the surface.

• After cleaning, stir the ready mixed rust resistant primer paint 'Yellow Zinchromate' or 'Red Oxide' primer paint. Before applying the paint, confirm the correct viscosity.

• Apply the paint uniformly by using a brush. drying time for the paint is normally 4 hours.

• After the first coat of paint is dried up, mix and stir the finish coat paint to the desired viscosity and apply by brush uniformly. Drying time of finish coat paint is normally 6 hours.

• Inspect the repainted surface and do re-painting if the painting is not uniform and unpainted surface is visible. Recommended viscosities for painting : (i) For brushing : 50 ~ 55 sec. (ii) For spraying : 20 ~ 25 sec. (iii) Pressure for spraying : 55 ~ 60 psi. (iv) Time gap between two coatings : 24 Hours. (v) Total dry film thickness after final coating: as per data sheet (80 ~ 100 microns if not specified)

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

4.23

PTRM : 0708 Page 57 of 205

MIXING OF TRANSFORMER OIL • Some times a need arises at site to top up a transformer with oil of a different make.

• New oil can be mixed with each other irrespective of the source or degree of refinement if both the oils meet the same standard specification.

• Inhibited oils can be mixed only if the inhibitor used is same in either oils or the other one is uninhibited.

• At any point of time, the percentage of new oil topped up shall be limited to 10% of the total oil quantity.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

5.0

INSULATION DRY OUT AT SITE

5.1

HOT OIL CIRCULATION

PTRM : 0708 Page 58 of 205

• Connect bottom filter valve of tank to inlet point of filter machine. • Connect top filter valve of tank to outlet of vacuum filter machine and start oil circulation.

• The filter outlet temperature should be limited to 60 ~ 70OC. • Continue filtration for 4 cycles. • Oil circuit should include a vacuum chamber in which oil drawn from the transformer is sprayed and the moisture and gases are released from the oil are extracted by the vacuum pump.

• Oil drawn from transformer is passed through a filter press before being admitted to the vacuum chamber to remove impurities

• A minimum capacity of 6000 litres per hour is recommended for the circulation equipment.

• Cooler connection at inlet shall be kept closed to minimise loss of temperature during circulation. Outlet valve shall be kept open to allow expansion of oil inside the cooler.

• Coolers also shall be included in the hot oil circulation towards the end of the process.

• Drain the oil by simultaneously admitting dry air or nitrogen gas from the top. This is to avoid winding insulation coming in contact with moisture.

• Apply vacuum of 1.0 torr or better and maintain for 6 Hrs. • Inject oil under vacuum upto a level of approximately half of the conservator.

• Start hot oil circulation again as explained earlier and continue for 4 cycles. Maintain temperature of 60 ~ 700 C.

• Drain oil by feeding dry air or nitrogen gas as explained. • Apply vacuum as explained • Repeat vacuum/hot oil circulation cycle till required dryness is obtained.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 59 of 205

• Normally 3 or 4 cycles of hot oil circulation and evacuation will be sufficient to obtain the required dryness for the insulation.

FIG.— 5.1 Variation of Insulation Resistance with Temperature • Dryness of insulation is determined by measuring insulation resistance of transformer winding.

• Insulation resistance between each pair of windings and also between windings and earth shall be measured by using a 5 kV megger. Readings shall be comparable with the factory test results.

• Direct heating of transformer is not recommended for dry out at site. • Oil samples shall be tested for moisture content, (Below 20/15/10 for 145/220/400 kV class respectively). Break down voltage (More than 60 kV at 2.5 mm gap). Resistivity ( ≥1012 ohm meter) before final oil filling.

• Do not measure insulation resistance when the transformer in under vacuum. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 60 of 205

6.0

COMMISSIONING

6.1

POST ERECTION CHECKS

6.1.1

INSPECTION AND MAINTENANCE LOG SHEET • It is important that an inspection and maintenance log sheet be kept regularly. The original of this log sheet should be kept along with the Instruction Manual for future reference and record.

• The log should include dates and details of all inspections and maintenance carried out.

• Results of oil tests and insulation resistance together with the temperatures at the time of measurement should also be recorded in the log sheet.

• Before commencing the test it should be ensured that the secondary terminals of all current transformers are kept short-circuited. After test these shorting connections shall be removed.

6.1.2

PHYSICAL CHECKS • Check oil levels in the level gauges of all condenser bushings. • All air release plugs shall be loosened and closed after releasing trapped air if any.

• Check and confirm tightness of all fasteners. • Check and confirm that valves are either open or closed as indicated the valve schedule plate.

• Check all bolted gasket joints and confirm that there is no oil leak. • All blanking plates and spares including spare gasket should be stored carefully for future use.

• Check all cable terminations and ensure that cables are properly connected and cable numbering ferrules are provided.

• Check and ensure that all protective covers like valve guards, LV bushing protection covers etc. are removed.

• Check and confirm that all bushing porcelain are cleaned thoroughly and are without damage.

• Check & confirm that the test tap caps of all Condenser type Bushings are tightened.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 61 of 205

• Remove the cap provided at the bottom of silicagel breather for the transportation purpose.

• Arcing horns if provided are set to the specified gap • All earthing connections are tightened properly. • Anti condensation heaters are functioning correctly. • Rating and connection diagram plates and other marking labels are fitted properly.

• All isolating switches are set at ON position. • Cooler control switch is set to AUTO. • All alarm circuits are reset. • OLTC to Transformer equalising pipe shall be removed after oil filling under vacuum and the opening shall be coverd by blanking plate supplied with the transformer.

6.2

INSULATION RESISTANCE CHECK • Check and record insulation resistance between pair of windings and windings and earth using 5 kV Motorised megger megger and record the values at 15, 60 & 600 seconds.

• Calculate the ratios of insulation resistances IR 600/ IR 60 (Polarisation Index.) and IR 60/ IR 15

• Compare the values with factory test results. • Check insulation resistance between core and frame to ground if the earthing connection is brought out through bushings.

• Do not apply any voltage or even high voltage megger when the equipment is under vacuum.

6.3

RATIO TESTS • Connect 3-phase 415 volts supply between HV terminals and measure the voltage ratios at all taps and record.

• Earth connections from star point shall be removed during measurement and reconnected after tests.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

6.4

PTRM : 0708 Page 62 of 205

VECTOR GROUP TESTS • Connect 415 V, 3-phase supply to HV winding terminals. The transformer shall be at rated tap.

• Connect one HV terminal to one LV terminal and measure voltage between each HV terminal to each LV terminal in turn. Compare the values with factory test results. E.g. for Ynyno: Measure voltage between 1u -1V, 1u - 1W , 1V2 - 1W, 1u -2V, 1u - 2W, 2V2 - 2W, 1u -2V, 1W - 1W, 1W2 - 2W,

6.5

MAGNETIC BALANCE TEST • Single-phase 240 volts is applied across any HV winding and voltage induced across the other phases are measured and compared with the factory test results. CAUTION: If there is a residual magnetism in the core, it can give erratic readings.

6.6

SHORT CIRCUIT IMPEDENCE • LV terminals are shorted by using suitable cables. • 3 phase 415 volts supply is connected to HV winding and HV exciting current of all the phases and LV circulating currents of all the phases are measured and recorded.

• Percentage impedance = Rated current x Applied voltage x 100 Measured current x Rated voltage

• Compare the results with factory test results. 6.8

WINDING RESISTANCE MEASUREMENT • Note down the oil/winding temperature. If the measurements are done after hot oil circulation; the oil/winding temperature may be different from the ambient temperature.

• Measure the resistance of all windings using a Whetstone Bridge or Kelvin bridge.

• Convert the resistances to 75OC. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 63 of 205

For copper windings:

• R (75)

= R (measured) x (234.5 + 75) (234.5 + Oil temperature at the time of measurement)

• Compare the values with factory test results. 6.9

TAN DELTA AND CAPACITANCE • Measure tan delta and capacitance of Condenser bushings of 52 kV and above and compare with the factory test results (Refer to "INSTRUCTIONS FOR INSTALLATION AND MAINTENANCE OF OIP CONDENSER BUSHINGS" provided elsewhwhere in this Manual).

• Compare the values with factory test results. 6.10

6.11

OPERATION CHECKS •

Check direction of rotation of pumps and fans.



Check and confirm that flow indicators are mounted correctly.



Check signalling circuits for pump fail/fans fail etc., and reset.



Check setting of over load relays and reset.

BUCHHOLZ RELAY OPERATION • Check inclination of Buchholz relay pipe. The slope should be in upward direction, between 3 ~ 9O to horizontal towards the conservator.

• Connect a compressed air line (Pressure 4 kg/cm2) or a nitrogen cylinder to the petcock on top of the Buchholz relay.

• Open the petcock slowly and allow air to enter into the Buchholz relay.

• Check the continuity of alarm contacts by using a multimeter. • Record the volume of air in the Buchholz Relay at which the alarm switch contact closes.

• Close the air supply and release all the air by opening the other petcock on the Buchholz relay.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 64 of 205

• Open the petcock quickly and allow air full flow with surge. Record the minimum pressure required to operate the surge contacts.

• Release all the air trapped in the Buchholz relay. 6.12

WINDING TEMPERATURE INDICATOR CALIBRATION • Rotate the indicator pointer slowly and confirm that the alarm signal is received at the set temperature.

• Rotate the pointer slowly and confirm that the trip signal is received at the set temperature.

• For set values of alarm and trip contacts, please refer to the instruction manual.

• Repeat the test for all winding temperature indicators if more than one indicator is provided.

• Remove the thermal sensing bulb from the transformer cover and insert in hot oil bath.

• Check the readings with clinical thermometer. • Replace the sensing element in transformer pocket and check the readings or remote winding temperatures if provided.

• For any adjustment if needed please refer to the instrument supplier's catalogue.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 65 of 205

APPENDIX – A

ERECTION CHECK LIST TRANSFORMER ERECTION CHECK LIST This checklist is intended for use at site by Site Engineers. It outlines the minimum on site checks expected to be carried out during the erection activity. CUSTOMER

: ……………………………………………………………

EQUIPMENT DETAILS: …………………………………………………………… SITE

SL. No. 1

: ……………………………………………………………

CHECK POINT

O.K.

NOT O.K.

REMARKS

AVAILABILITY OF DOCUMENTATION Erection drawings including OGA Erection / Maintenance Manual Transport packing list

2

RECEIPT OF TRANSFORMER Externally inspected damage (if any) Gas pressure on receipt (Where applicable) Oil level (in case of oil filled transformer) Unit correctly positioned

3

RECEIPT OF ACCESSORIES All materials stored correctly Packing Cases inspected, damage if any Marshalling box inspected, damage if any Control panels (RTCC)inspected damage if any

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

SL. No.

CHECK NPOINT

O.K

PTRM : 0708 Page 66 of 205 NOT O.K.

REMARKS

Materials received corresponded to Advise note Any shortages / wrong supply Materials comply with shipping specification Remark (if any) 4

ERECTION Transport rollers mounted Conservator mounted Buchholz relay and oil surge relay mounted (arrow marked should be towards conservator) Breather mounted and duly charged HV Bushings mounted LV Bushing mounted Tertiary Bushing mounted (if applicable) HV neutral Bushing mounted LV Neutral Bushing mounted Bushing installed at correct angles Diaphragm checked MOLG mounted Radiator mounted Fans mounted Pressure Relief valves mounted Alignment of all pipe work OLTC Conservator mounted Heat Exchangers assembled with pipe work Topping up of transformer oil Leakage observed after 24 hrs.(if any) Rating Diagram and identification plate fitted

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 67 of 205

Marshalling box aligned Control panel (RTCC) aligned Control panel (OLTC) aligned

5

OIL FILLING All bushing oil level Tap changer selector oil level Diverter switch oil level Auxiliary unit oil level Radiator, Headers oil filled Transformer / OLTC Conservator oil tight Complete transformer oil tight All air release plug vented Valves in service position All drain / filter valves blanked

6

MULTICORE CABLE All tray work adequately secured All cables adequately tied/clipped back to tray Cables glanded correctly WTIs and OTIs satisfactorily installed

7

BREATHERS Transformer silica gel breather satisfactory Tap changer silica gel breather satisfactory Drycol breather correctly installed

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 8

PTRM : 0708 Page 68 of 205

FANS Fans rotate freely & quickly Pumps installed for correct flow Flow indication visible

9

CONTROL PANELS Cable termination Cable glanding Control cabinet clean & tidy Heater supplied Locking arrangement

10

CLEANING & TOUCH UP PAINTING OF COMPLETE TRANSFORMER

Date: Signature: ----------------------------------

----------------------------------

Name:

----------------------------------

----------------------------------

(FOR AREVA)

ISSUE/ REVISION DATE

(FOR CUSTOMER)

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 69 of 205

APPENDIX -B PRE-COMMISSIONING CHECKS & TEST RESULTS Customer: ______________________

Site:______________________________

EQUIPMENT DETAILS: (Rating, Ratio, Maker's Ref., Sl. No., Year etc.) ___________________________________________________________________ Vector Group: -------------------------- Amps. (H/I/L) ---------------------------------------------Tapping Range: --------------------%

Impedance at Normal tap ---------------------------

Temperature Rise: Oil -----------------------

Wdg. ---------------------------

GENERAL CHECKS: STATUS

CHECK POINTS

OK 1

Direction & mounting angle of O.S.R. & Buchholz relay

2

Dryness of silica gel, seal removal & oil level in bottom cup

3

Oil level in Main conservator.

4

Oil level in OLTC conservator.

5

Oil filled in OTI / WTI pockets.

6

Earthing of Main tank, cooler bank, neutral, fans, pumps, etc

7

Absence of oil seepages / leakages.

8

Bushing -their oil levels & test cap covering.

9

Explosion vent & rupture pin setting.

10

Touch up painting & washing.

11

Overall clearances.

12

Atmoseal commissioned (top gauge glass to show full oil )

13

Sagging of radiator / pipes

14

Tightness of bushing top seal

15

Distortion in expansion bellows / removal of transit support

ISSUE/ REVISION DATE

20/10/05

28/01/07

REMARKS

NOT OK

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 70 of 205

A. MARSHALLING BOX (Sl. No. & Rating : _____________________________) STATUS CHECK POINTS OK 1

REMARKS

NOT OK

W.T.I. (Sl.No., Make & Model) a. Transit lock release. b. Switch settings & operation. c. Connections. d. Ambient reading. e. Heater shunt shorting link. f. Matching with repeaters. g. Power supply & current converter

2

O.T.I (Sl. No., Make & Model) a. Transit lock release b. Switch setting & operation. c. Connections. d. Ambient reading. e. Matching with repeaters.

3

Space heater & Thermostat settings.

4

Cabling, Glanding, Termination etc.

5

Earthing & Touch up painting.

6

Stand by supply change over operation

7

Timer settings.

8

Closure of openings & tidiness.

B. FANS: (Model, RPM, KW / HP ) ____________________________________ 1

Glanding & Earthing.

2

Mounting & Terminal cover condition.

3

Direction & Smoothness of operation : a. Manual -Local.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 71 of 205

b. Manual – Remote c. Auto & Stand by operation 4

Overload setting

5

Starting current

6

Running current

7

Megger values

C. O.L.T.C. (Sl No. , Make & Type) ____________________________________ STATUS CHECK POINTS

OK

1

Alignment of all shafts & Drive Mechanism

2

Oil fill in gear box (Where reqd.)

3

Mechanical end limits of D.M.

4

Coupling Position & rotation lag.

5

Manual operation.

6

Local electrical operation.

7

Electrical end limit operation.

8

Remote electrical operation.

9

Tightness of external shaft coupling

10

Bending of lock washer.

11

Fitment of window & shaft covers.

12

Cabling, Termination, Glanding etc.

13

Space heater & thermostat setting.

14

Continuity check during transition by voltage application.

15

Earthing.

16

TPI counter reading

17

CCU for TPI

ISSUE/ REVISION DATE

20/10/05

28/01/07

REMARKS

NOT OK

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 72 of 205

D. R.T.C.C.: (Sl. No. & Rating): _________________________________________ 1

Installation & Earthing.

2

Cabling, Glanding, Termination etc.

3

Setting of Timers.

4

Functioning of Indication Lamps.

5

Functioning of Hooter / Buzzers.

6

Annunciation / Relay Checks: a. b. c. d. e. f. g. Make & Model

7

Tap position indicator.

8

W.T.I. Repeater.

9

O.T.I. Repeater.

10

O.L.T.C. Operations : a. Individual : b. As Master : c. As Follower :

11

Emergency Trip.

12

Out of step & MP Timer operation.

13

Operation of A.V.R. & L.D.C.

E. Operation of Pumps, NRV, Flow Indicators: 1

Direction of pump operation.

2

Manual operation.

3

Auto operation.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

4

Stand-by changeover.

6

Non Return Valve operation.

7

Overload setting

8

Starting current

9

Running current

10

Stability of alarm & trip contacts of Buchholz relay during oil pump starting by manual / Auto mode

11

Megger value (500 V / 1000 V Megger )

ISSUE/ REVISION DATE

20/10/05

28/01/07

PTRM : 0708 Page 73 of 205

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 74 of 205

PART – 2 S I T E T E S T R E S U L T S: NOTE: Instruments provided by Customer will normally he used for the tests after ascertaining their operation in the applicable ranges. A. Insulation Resistance: Range, Make, kV rating & Type of tester: _________________________________ 1

Top oil Temperature:

2

Megger Values: 60 Sec. H.V. to L.V.:

600 Sec.

60 Sec.

H.V. to T.V.:

H.V. To Earth T.V. To Earth

L.V. to T.V.:

L.V. To Earth

600 Sec.

CORE to TANK ( By 1000 V Megger ) CORE to FRAME ( By 1000 V Megger ) B. Current Transformers: C. TAN DELTA & CAPACITANCE TEST OF BUSHINGS: C. T. DETAILS

CHECK POINT Continuity Approx. Ratio Polarity (Only for REF / DIFFL. C.T) Saturation check only for PS class C.T's

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 75 of 205

C. TAN DELTA & CAPACITANCE TEST OF BUSHINGS: a. Atmospheric condition & temperature: b. Equipment used for test: c. Bushing position on test: Bushing Sl. No.

Make

Rating A / V

Tan delta

Capacitance Megger value

NOTE: Please ensure that the bushings are absolutely clean. Atmosphere should be dry & bushing should be in vertical or mounted on transformer during testing. Test O

tap should be cleaned with CTC & dried out using a hot air dryer (60 C) if need be. Short the terminals of other bushings & connect to earth. Arcing horns & line terminals to be removed. D. SHORT CIRCUIT TEST ON TRANSFORMER: Method of testing: Tap Position

Current in Amps HV

LV

IV

NEUTRAL

FIRST NORMAL LAST REMARKS: Value of short circuit current should be observed on other taps for any abnormality & abnormalities if any may be recorded. E. PHASING CHECK ON MULTI-RUN OF CABLES (HV & LV): Ensure absence of cross connections by physical inspection, and continuity check. PHASING CHECK BEFORE PARALLELING: ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 76 of 205

Ensure absence of cross connections by physical inspection and by measurement of voltage across corresponding phases on the LV By applying low voltage on HV. Approximate Voltage Ratio: Apply single phase 240 or 440 volts on each HV line lead and ‘N’ or pair of HV line leads and Measure LV voltage on all taps in all phases.

F.

Tap No.

HV Volts (applied) 1U-1V 1U1N

1V1W

LV1 Volts

1W-1U 2U-2V

1V-1N 1W-1N

2U2N

2V2W

LV2 / Tertiary

2W-2U

3U-3V

3V-3W

3W-3U

2V-2N 2W-2N

3W-3N

3V-3N

3W-3N

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 77 of 205

G. MAGNETIC BALANCE: (For star winding only) AT NORMAL TAP POSITION VOLTAGE ACROSS

1U-1N

1V-1N

1W-1N

2U-2N

2V-2N

2W-2N

TAP No.

H. EXCITATION WITH REDUCED VOLTAGE: 1. For LV winding of up to 1.1 KV class, apply single phase, 2 wire, 415 volts from HV side (Keeping neutrals isolated) on each leg. 2. For L.V. winding of class higher than 1.1 KV, apply single phase, 2 wire, 415 volts from LV side (Keeping neutrals isolated) on each leg. Applied Volts ( V ) Measured current (A) Tap No 1U-1V

1V-1W

1W-1U

1U

1V

1W

I. OIL BREAKDOWN VALUES: (Average of six readings with 2.5 mm gap) (a) Main tank top oil sample : ______________________________ (b) Main tank bottom oil sample : ______________________________ (c) O.L.T. C. oil sample: ______________________________ J. VECTOR GROUP CHECK: Short terminals 1U to 2U and apply 3 phase, 3 wire 415 volts supply across 1U-1V-1W and measure voltage across terminals and confirm the group STAR -STAR CONNECTION

STAR -DELTA CONNECTION

1V -2V : 1V -2W : 1W -2W : 1W -2V :

1V -2V : 1V -2W : 1W -2W : 1W -2V : 1U -1V : 1V -1W : 1W -1U : (Signature & Name): _____________ (Signature & Name): _______________ AREVA ENGINEER ISSUE/ REVISION DATE

20/10/05

28/01/07

CUSTOMER'S ENGINEER 01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 78 of 205

PART – 3 PRE-COMMISSIONING CHECKS – To be carried out after transformer is connected to lines & before energisation CHECK POINTS 1 2 3 4

5

6.

STATUS O.K. NOT OK

REMARK S

Clearances in air (refer O.G.A.) Arcing horn gap set (refer O.G.A.) Tightness of bushing lugs, cable / line connections, terminals, etc. Simulation of Alarm & Trip circuits (verify breaker / Master trip operation by initiating operating contacts of) a. Buchholtz relay b. Winding temperature indicator c. Oil temperature indicator d Oil surge relay e. Pressure relief device / vent switch f. M.O.L.G. g. Oil / Water flow indicators / D.P.G. h. Sudden pressure relay I. Over current relay j. Earth fault relay k. Differential relay l. Inter tripping relay m. Others Air venting from: a. Bushings b. Radiators, headers, couplings c. Buchholtz relay d. O.L.T.C. cover / head e. Main tank cover / Thermosyphon f. Disconnecting chamber a. H.V. Lightening Arrester counter reading b. L.V. Lightening Arrester counter reading

Transformer successfully energised on __________ at _______ Hrs on Tap No. ___ Load & is operating satisfactorily. Transformer put on _______ Amps. / MVA load on _______ at _______ Hrs and is operating satisfactorily. Signature : ____________________ Signature: _________________ (AREVA ENGINEER) (CUSTOMER'S ENGINEER) Name : _________________ Name: _____________________ Designation: __________________ Designation: _________________

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 79 of 205

DATA REGARDING ACCESSORIES: 1

H.V.BUSHINGS: Make: Rating: Sl. No.:

2

L.V.BUSHINGS: Make: Rating: Sl. No.:

3

O.L.T.C. DETAILS: Make: Type: Sl. No.:

4

FACIA DETAILS: Make: Sl. No.: Model: No. of windows : Voltage:

5

PRESSURE RELIEF DEVICE: Make: Sl.No: Pressure Setting:

Name of Service Engineer: Signature: Date:

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

7.0

PTRM : 0708 Page 80 of 205

OPERATION • After the inspection and pre-commissioning tests are successfully completed the transformer can be energised at no load.

• Oil soaking/ settling duration of 2 days for transformers up to 245 kV class and 3 days for 400 kV and above class are recommended after completion of hot oil circulation and before energising.

• Excessive vibration if any on any part of the transformer shall be located and rectified.

• Transformer shall be observed for any abnormality. • If any gas is collected inside the Buchholz relay, it shall be analysed for its combustibility. If gas is not combustible, it indicates air trapped inside the transformer.

• All instruments should be checked for any abnormal indication. • Check winding temperature and oil temperature readings at least once in every shift.

• Check and confirm that tap position indicators is same in local and remote indicators.

• Check and confirm that none of the alarms are indicated. • Ensure that cooler power supply isolator is ON. • Ensure that cooler control is in AUTO. • Ensure that pumps and fans are running smoothly as temperature dictates. If the temperature is below the ON setting neither the pump nor fan should be running.

• After watching the operation of the transformer at no load for 24 hours and confirming that everything is normal, the transformer shall be taken on load.

• Observe the rise in temperature of oil and winding temperature indicators.

• While temperature is rising, confirm that fans and pumps are switched on automatically at the preset temperatures.

• While temperature is falling, observe that the pumps and fans are switched off at preset temperature.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 7.1

PTRM : 0708 Page 81 of 205

ROUTINE / PERIODIC INSPECTION SCHEDULE FOR POWER TRANSFORMER

S. No.

Items to be inspected

Frequency

1

Load current

Hourly

2

Terminal Voltage

Hourly

3

Ambient Temperature

Hourly

4

Winding Temperature

Hourly

5

Oil Temperature

Hourly

6

Tap position

Daily

7

Air cell conservator

Daily

8

Oil level in Conservator

Daily

9

Oil level in Bushings

Daily

10

Oil level in OLTC Conservator

Daily

11

Oil level in breather cup

Daily

12

Connections

Monthly

13

Dust deposits & physical damages to bushings

Monthly

14

Air passage & colour of silica gel in breather

Quarterly

15

Cable boxes, gasket joints, gauges etc.

Quarterly

16

Dielectric strength of transformer oil

Half yearly

17

Moisture content of transformer oil

Half yearly

18

Dissolved gas analysis of transformer oil

Half yearly

19

Resistivity of transformer oil

Half yearly

20

Insulation resistance of windings

Yearly

21

Tan delta & Capacitance of condenser bushings

Yearly

22

Operation of relays and their circuit

Yearly

23

Surface paint

2 ~ 3 Years**

Note: ** Duration of surface repainting depends on the level of pollution prevailing at site. If pollution level is high, a frequent repainting schedule may have to be worked out. •

Lifting of core and windings are not recommended as a routine inspection.



Core and coils are to be inspected only if such an inspection is warranted by test results of dissolved gas analysis, any abnormality in performance or for suspected internal damages due to external short circuit.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

8.0

PTRM : 0708 Page 82 of 205

MAINTENANCE Maintenance Schedule Periodicity

Preventive Maintenance Procedures 3 Replacement / Regeneration of Silica gel Breather

8.1

Months 6

12

Scheduled outage

4

Dissolved Gas Analysis

4

Oil Sampling

4

Buchholz Relay Functional Tests

4

Tan Delta & Capacitance Measurement of Condenser Bushings

4

OTI/ WTI Tests

4

Tap changer operation

4

Insulation Resistance of Windings

4

Oil Filtration

4

Surface Painting

4

Oil Sampling Oil sample should be tested for the following and results recorded: -

8.1.1

Electric Strength • If the dielectric strength of oil in transformer is less than 55 kV at 2.5 mm gap, the oil must be filtered to improve the characteristics. • For line end OLTC diverter chamber, oil filtration is recommended when the BDV is ≤ 40 kV at 2.5 mm gap. • For neutral end OLTC diverter chamber, oil filtration is recommended when the BDV is less than ≤ 30 kV at 2.5 mm gap.

8.1.2

Moisture Content • For transformers of 400 kV and above class, if the moisture content is found to have increased beyond 20 ppm oil should be filtered. • For transformers of voltage class up to 245 kV, if the moisture content is found to have increased beyond 25 ppm oil should be filtered.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 8.1.3

PTRM : 0708 Page 83 of 205

Acidity • It the acidity is increased beyond 0.5 mg KOH/g, than the oil needs filtration. • After draining the oil completely from the transformer, core, winding, insulation and interior of tank should be washed by hot oil jet. The oil being used for washing of internal body also must be drained completely. • Refilling of oil in transformer should be done under vacuum.

8.2

Sampling procedure • Special care in oil sampling is required for Delta connected transformer and autotransformers.

8.2.1

Tools required • • • • • • • •

8.2.2

Spanner set Thermometer Steel sampling bottles with polyethylene cone caps. Silicon rubber tubing 10 mm bore - 1 m long. Clean synthetic sponge. Polyethylene sheet - 1 m square Clean cloths Self adhesive labels

Procedure • The sampling bottles shall be labelled and marked with information like • • • • • •

source of sample, date and time & sample temperature. Sample bottle shall not be opened before it is needed for testing. Sampling point should be cleaned by using sponge. Blanking plate of sampling valve shall be removed by using spanner. Clean the silicon rubber tubing thoroughly and fit to sampling point nipple. Rinse the bottle in oil stream and reduce the rate of oil flow to 1 litre/minute. Put the end of rubber tubing to sampling bottle and fill the bottle from bottom.

• No air bubble shall be introduced into the bottle. • The bottle is allowed to overflow before it is closed. • Measure and record the temperature of oil sample as soon as it is taken. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 84 of 205

• Put back and tighten the blanking plate. • Remove all tools, excess oil container and oil sample from the area. • Arrange for testing oil sample at laboratory. 8.3

WINDING TEMPERATURE INDICATOR TESTS

8.3.1

Tools and materials • • • • •

8.3.2

Hot oil bath (with heating facility) Secondary injection test set Multimeter Clinical thermometer Keys of marshalling box.

Procedures • The purpose of this check is to confirm that the winding temperatures Indicators are functioning accurately. • The transformer shall be isolated and earthed. • Rotate the indicator pointers slowly to the alarm set value and confirm from the control room that the alarm signal has been received. • Rotate the pointer still further and confirm from the control room that trip signal is received.

8.3.3

Calibration • Remove the thermal sensing bulbs from the transformer and insert it into the hot oil bath. • Check the winding temperature readings up and down the scale at intervals of 5 °C. • Confirm from control room that remote temperature readings are tallying with the local readings. • Replace the sensing element into the transformer pocket. For any adjustment, see the manufacturer's catalogue.

8.3.4

SECONDARY INJECTION TESTS

8.3.5

ONAN Rating • Set the cooler supply isolator of OFF position. • Connect the secondary injection test set across the heater coil terminals. • Inject current and check the resultant gradient for ONAN rating.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

8.3.6

OFAF Rating • • • • • • •

8.4

PTRM : 0708 Page 85 of 205

In order to carry out these tests the pump must be running. Set the cooler isolator to ON position. Set the cooler switch to fans and pumps. Check and confirm that the pump is running. Inject current in the heater coil and check the gradient for OFAF rating. Disconnect. Set the cooler control switch to AUTO.

BUCHHOLZ RELAY FUNCTIONAL TEST Tools and Materials Required. • Multimeter • Nitrogen cylinder with regulator and pressure gauge or air supply (4 kg/cm²) • Bucket • 10 mm polythene tube, 10 meters.

8.4.1

Procedure • The purpose of this test is to ensure correct operation of Buchholz • • • • • • • • • • • • •

ISSUE/ REVISION DATE

relay. Transformer shall be isolated and earthed. Connect nitrogen cylinder to the top petcock of Buchholz relay. Open the other petcock. Allow gas to enter the relay. Check and confirm from control room that alarm signal is received. Check continuity of alarm contact by using multimeter. Close petcock on gas supply side and release all gases trapped in relay casing. Increase the gas pressure to approx. 2 kg/cm² (30 psi) Open the test petcock and allow full surge of gas to enter the relay casing. Check and confirm from control room that trip signal has been received. Check continuity of trip contacts by using multimeter. Close Buchholz relay test cocks. If relay has not operated, increase gas pressure and repeat the test.

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 86 of 205

• If the relay is found faculty replace it with a new one. • Open conservator shut off valve and release all gases trapped. 8.5

TAPCHANGER OPERATION • Regular inspection of tap changing equipment is not required because • • • • • • • • • • • •

8.6

mechanical operation of tap changer does not involve significant contact wear. It is sufficient to operate the tap changer through the whole range of tap selector positions twice a year. The purpose of this check is to ensure correct mechanical operation of tap changer. Transformer shall be isolated and earthed. Note the tap position. Operate the tap changer through operating handle through entire range of tap positions. Return to the original tap position. Set the local selector switch to LOCAL. Press RAISE button and release. Check and confirm the tap position indication has changed and that limit switch stops the tap changing at preset tap. Repeat. Press the LOWER button and release. Check and confirm that limit switch has operated and tap position indication has changed. Repeat till the tap position has returned to the original value. Set the local selector switch to REMOTE.

OIL FILTRATION • Purpose of this maintenance is to improve the unsatisfactory condition of oil found during sampling. • Transformer shall be isolated and earthed.

8.6.1

Tools and Materials • • • •

8.6.2

Oil conditioning plant (Filter Machine) 50 mm flexible hoses of sufficient length for oil inlet and outlet. Hose adapters to match the flanges of top and bottom filter valves. Cleaning cloths

Procedure • Remove the blanking plate from filter valves and connect the oil inlet hose to top filter valve and oil outlet hose to the bottom filter valve.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 87 of 205

• Open the filter valves and start circulation of hot oil. Oil temperature shall be 55°C to 70°C. • Circulate the oil for 4 full passes. • Re sample and arrange to test. • Continue until oil condition is acceptable.

8.7

CORRECTIVE MAINTENANCE • All flange gaskets must be renewed wherever joints are dismantled. • Cleanliness of gasket surfaces and correct compression (40 % ~ 50% approx.) of gasket must be ensured during reassembling.

8.8

REMOVING AND REFIXING OF PUMPS

8.8.1

Tools and materials • • • •

8.8.2

Jib crane or chain pulley block to handle the weight of pumps. Oil drip tray Blanking plates New gaskets.

Procedure • • • • • • • • • • • •

Transformer is isolated and earthed. Close the isolating valves on either side of pump Disconnect the motor supply wires Remove the drain plug of the pump and drain oil from the pump. Remove the clamping bolts and remove the pump Blank off the isolating valve. For re-fixing the pump, remove the blanking plates. Fix new gaskets. Replace and tighten the clamping bolts. Open the isolating valves on cooler side. Open air release plug and close when oil starts flowing out. Open the isolating valve on transformer tank side.

8.9

REMOVING AND RE FITTING RADIATOR

8.9.1

Tools and Materials • • • •

ISSUE/ REVISION DATE

Jib crane to handle the weight of radiator. Oil container (capacity approx. 1000 litres) Oil drain hose 50 mm bore Hose adapter to match flanges of fitter valve. 20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 88 of 205

• Oil filter machine • New gaskets. 8.9.2

Procedure • Transformer shall be isolated and earthed. • Set the cooler supply isolator of OFF. • Close the inlet and outlet valves if radiator is mounted on a separate • • • • • • • • • • • • • • •

• • • •

cooler tank. Close the top and bottom isolating valves of radiator. Open the top air release plug. Remove the bottom drain plug and drain the oil to oil container under gravity. Sling the radiator with jib crane. Remove the radiator clamping bolts. Remove radiator. Blank off the radiator and header openings. Close the air release and drain plugs. For Re fitting the Radiator. Remove the blanking plates. Fix new gaskets. Assemble the radiator and tighten the clamping bolts. Open the top header air release plug. Open the bottom radiator isolating valve. If the radiator is on a separate cooler bank, oil shall be filled into the radiator bank through the bottom header valve by using the filter machine. If the radiator is tank mounted, the oil from the oil tank should be pumped into the tank by using the filter machine. Close the air release plug on top as soon as oil starts flowing through the air release plug. Shut down the oil filter machine Open top header isolating valve. In case of separate cooler banks, air should be released through the top common header air release plugs.

8.10

REMOVING AND RE FITTING FAN & MOTOR

8.10.1

Tools and materials • Forklift truck to take weight of fan and motor assembly.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 8.10.2

Procedure • • • • • •

8.10.3

PTRM : 0708 Page 89 of 205

The transformer is to be isolated and earthed. Set cooler supply isolator to OFF and lock the marshalling box. Disconnect the fan motor supply wires. Support the weight of fan and motor assembly by using fork lift truck. Unbolt fan and motor form fan mounting frame. Lower the fan from the fan-mounting frame.

Re fitting Fan and Motor • Assemble the fan and motor in position and tighten clamping bolts. • Re connect the power supply wires. • Unlock marshalling box and set cooler supply isolator to ON.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

9.0

PTRM : 0708 Page 90 of 205

TROUBLE SHOOTING Following table shows some of the symptoms, possible causes and remedies in case of abnormal situations: – If the abnormality is of a major nature, the manufacturer should be contacted at the address given else where in this Manual. When the matter is referred to the manufacturer it shall contain the following: • Transformer Rating. • Voltage Rating. • Manufacturers Indent No. / Serial No. • Year of Manufacture. • Date / Time of failure. • Brief description of the problem. • Checks done and their results.

9.1

ABNORMAL OPERATING CONDITIONS

TROUBLE High Winding/ Oil Temperature

Electrical Troubles/ Winding Failure

ISSUE/ REVISION DATE

20/10/05

CAUSE

REMEDY

Over voltage

Change the circuit voltage or transformer connections to avoid over excitation.

Over current

If possible, reduce load. Heating can be reduced by improving power factor of load. Check parallel circuits for circulating currents, which may be caused by improper ratios or impedances.

High ambient temperature

Either improve ventilation or relocate transformer in lower ambient temperature.

Insufficient cooling

If unit is artificially cooled, make sure cooling is adequate.

Low oil level

Top up oil to proper level.

Deterioration/

Use filter press to wash off core and coils.

sludge formation of oil.

Filter oil to remove sludge.

Short circuited core

Test for exciting current and no load loss. If high inspect core and repair. See Electrical Troubles, below.

Lightning, short circuit, Overload Oil of low dielectric strength.

Usually, when a transformer winding fails, the transformer is automatically disconnected from the circuit by the circuit breaker.

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 91 of 205

9.2 DIAGNOSIS OF INTERNAL FAULTS • •

When the operation of a protective device does not clearly indicate an internal fault, it is desirable to conduct the preliminary measurements and analysis before dismantling the transformer. Conditions before and after the development of fault should be taken into consideration in arriving at a conclusion. No

CHECK POINT

DESCRIPTION

CRIETERIA

1

Measurement of Insulation Resistance of Windings

Measurement must be taken after isolating the transformer from the circuit and cleaning the surface of insulators. Insulation failures can be detected by this measurement.

2

Measurement of winding resistance

When measurement is made in one circuit, other circuit must be kept open circuited. This measurement can detect winding faults.

3

Measurement of Transformer Ratio.

This can be conducted by applying 230 volts, which can be readily available at site. For three phase jobs, measure ratios phase by phase.

4

Measurement of No Load Current

Measurement can be made by applying 230 volts under normal conditions by making use of locally available power source. This measurement can detect fault in windings and core.

If values obtained are higher compared to factory test results, it indicates faulty condition.

5

Testing of oil

Measure Break Down Voltage, moisture content, tan delta & check for sludge formation, discoloration and unusual smell.

Judgment to be made with reference to tables 9.1, 9.2, 9.3, 9.4 & 9.5

6

Measurement of Tan delta of Windings

Abnormal increase means deterioration of insulation.

Comparison with factory test result

7

Analysis of gas collected in Buchholtz Relay

When gas is accumulated in Buchholz relay. It should be analysed by gas chromatograph to check presence of combustible gases.

Manufacturer may be contacted for advice

8

Dissolved Gas Analysis

Development of internal incipient fault can be judged from the results. Increase in gas composition to be monitored at periodic interval.

Refer to tables 9.6, 9.7 & 9.8 Contact manufacturer for advice.

ISSUE/ REVISION DATE

20/10/05

28/01/07

Comparison with factory test results.

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 9.3

PROTECTIVE DEVICES No. 1

2

3

4

5

6

9.4

PTRM : 0708 Page 92 of 205

DETECTIVE DEVICE

DESCRIPTION

Pressure Relief Device

When the internal pressure increases beyond the preset value of PRD it operates. This may also happen if the breather connection is choked. Judgment based on the inspection of other protective relays is essential Differential Relay This relay detects the internal defects by comparing the input current and the output current of the transformer. If it functions simultaneously it indicates internal fault. Please note that this relay sometimes operates due to in rush current when transformer is energised and this is not an internal fault. This thermometer gives Alarm when the temperature Oil Temperature Indicator/ Winding rises beyond the set value. Over loading, insufficient cooling because of contamination of fan impellers, Temperature stoppage of fans/pumps etc. are to be checked. Indicator Alarm Over Current These are intended for detecting faults in power system Relay/ Earth Fault associated with the transformer. A fault in the Relay transformer results in operation of these relays. This is accompanied by actuation of protective devices of the transformer. Identification of fault should therefore be made on the basis of a thorough analysis of these functions. Voltmeter/ If a sudden change in voltage or current is noted when Ammeter there is no abnormality in the power system or an unbalance of voltage or current is noted between phases, the reasons should be investigated. Human Sense Human sense can play an important role in detection of faults. a) Discoloration or odour of insulating oil. If pieces of insulating materials or copper are found in oil, an internal fault can be suspected. b) Abnormal noise or vibration.

VALVES, GASKETS, WELD JOINTS SYMPTOM Oil Leak

Valve can’t be opened

ISSUE/ REVISION DATE

20/10/05

POSSIBLE CAUSE Loose joint Welding joint Gland packing not fitted correctly. Valve spindle bent. Seating for valve plug corroded

28/01/07

REMEDY Tighten the joint evenly. If the leak does not stop, renew the gasket. Take the help from manufacturer. Renew the gland packing and adjust gland packing nuts evenly. Fit new valve spindle. Dismantle valve, free valve plug or fit new valve.

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 9.5

PUMPS SYMPTOM Pump Motor over heats

POSSIBLE CAUSE Impeller binding

Pump motor vibrating

Pump running; but output low.

Insulation failure of Motor Winding Two phase operation Motor bearings worn Impeller damaged Pump bearing bushes or rings worn. Valve not fully open Impeller damaged or worn Speed too low

9.6

REMEDY Remove the pump and investigate the problem. Remove the pump and investigate the problem. Check power supply. Remove pump and investigate the reason Remove pump and investigate the reason Remove pump and investigate the reason Open the valve fully. Remove pump and investigate the reason Check electric supply.

FANS SYMPTOM

9.7

PTRM : 0708 Page 93 of 205

POSSIBLE CAUSE

REMEDY

Fan motor overheats

Motor bearing worn

Remove the fan and investigate reason.

Two phase operation

Check electric supply

Fan vibrating

Fan blades out of balance and noisy

Balance the fan or replace

Mounting bolts loose

Check and tighten fasteners.

BUCHHOLZ RELAY SYMPTOM

POSSIBLE CAUSE

Rate of gas evolution

Electrical response of relay

NONE

None Trip mechanism operated by oil surge

ISSUE/ REVISION DATE

20/10/05

28/01/07

Identity Class of fault of gas

REMEDY Inference

Oil surge

Faulty operation of oil pump

Sudden vaporisation of oil at 260~400OC

Large masses of metal heated Eg.: Earth fault, short circuit not causing insulation failure.

Boiling of water in exceptional cases

Simultaneous occurrence of a heat producing fault and entry of water into the tank.

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS RAPID

MEDIUM

Alarm operates and repeats after releasing gas

Air or inert gas

Major leak due to mechanical fault

Fracture of tank, pipe, or Buchholtz relay casing or faulty oil circulating pump.

Trip and alarm mechanism operates

Hydrogen

Thermal decomposition of oil above 400OC

Hydrogen and carbon monoxide

Thermal decomposition of oil and insulation

Air or inert gas

Air leaks or leakage due to mechanical fault. Thermal decomposition of oil above 400OC

Local, very high current, hot spot not involving insulation, arc over between metal parts of Terminal gear or terminal to tank. Local hot spots due to very high current faults in contact with solid insulation. Eg. Insulation failure followed by arc between insulated conductors and earth, short circuited turn etc. Fracture of tank pipe or Buchholz relay casing or faulty oil circulating pumps Local hot spots not involving insulation, faulty joint/ contacts, core faults causing burning, an incipient fault not involving solid insulation Eg. Core not properly earthed Local hotspots in contact with solid insulation. Low power arc between insulated conductors and earth, core faults. Faulty joints/ contact. Any incipient fault involving solid insulation Release of entrapped air during early life of transformer of

Alarm operates and repeats within minutes or hours after each release of gas

Hydrogen

Hydrogen and carbon monoxide

Alarm operates

SLOW

ISSUE/ REVISION DATE

20/10/05

PTRM : 0708 Page 94 of 205

28/01/07

Air or inert gas

Thermal decomposition of oil and solid insulation.

Presence of air due to mechanical

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

Hydrogen

Hydrogen and carbon monoxide

No gas pressure in Buchholtz relay

ISSUE/ REVISION DATE

20/10/05

Alarm operated

28/01/07

N. A.

PTRM : 0708 Page 95 of 205

fault or physical absorption Decomposition of oil only

transformer, crack in tank, pipe or relay casing, faulty oil pump. Low current arcing not involving solid insulation, gassing caused by high electrical stress, corona discharge Decomposition Low energy arcing of oil and solid involving insulation decomposition of solid insulation, creepage through solid insulation, oxidation of insulation Low oil level Oil level falling below the level of Buchholtz relay due to oil leakage

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 96 of 205

Table 9.1: DIELECTRIC STRENGTH OF INSULATING OIL (12.5 mm dia. Spheres, 2.5 mm gap) No.

Nominal Voltage Of Transformer Dielectric Strength of Insulating Oil (kV)

1

145 kV class and above

More than 50

2

72.5 kV class to less than 145 kV

More than 40

3

Less than 72.5 kV class

More than 30

Table 9.2: ACID CONTENT OF INSULATING OIL (BY NEUTRALISATION) No.

Judgment

Acid Content of Oil (mg KOH/g)

1

Good

Less than 0.2

2

Replace or do filtration

0.3 ~ 0.5

3

Replace immediately

Above 0.5

Table 9.3: RESISTIVITY OF INSULATING OIL No.

Judgment

1

Good

2

Fair

1x1011 to 0.1x1012

3

Poor

Less than 0.1x1011

Resistivity of Oil at 90OC ( -cm) More than 0.1x1012

Table 9.4: WATER CONTENT No. Nominal Voltage of Transformer

Water Content (ppm)

1

400 kV Class & above

Less than 20.

2

Upto 245 kV Class

Less than 25.

Table 9.5: DIELECTRIC DISSIPATION FACTOR No. Nominal Voltage of Transformer

At 90OC, 40 ~ 60 Hz

1

145 kV Class & above

0.2 Max.

2

Below 145 kV Class

1.0 Max

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

9.8

PTRM : 0708 Page 97 of 205

DISSOLVED GAS ANALYSIS O2

(Oxygen)

N2

(Nitrogen)

CO2

(Carbon dioxide)

CO

(Carbon monoxide)

H2

(Hydrogen)

CH4

(Methane)

C2H2

(Acetylene)

C2H4

(Ethylene)

C2H6

(Ethane)

C3H6

(Propylene)

C3H8

(Propane)

Table 9.6 "Normal" Values of Dissolved Key Gas Concentration Limits in oil of Power Transformers in Service [Parts per Million – ppm]. (Ref. FIST 3-30ττ : October 2000) CH4 C2H2 C2H4 C2H6 CO CO2* TDCG** Status H2 Condition 1 100 120 35 50 65 350 2500 720 Condition 2 101~ 121~ 36~ 51~ 66~ 351~ 2500~ 721~ 700 400 50 100 100 570 4000 1920 Condition 3 701~ 401~ 51~ 101~ 101~ 571~ 4001~ 1921~ 1800 1000 80 200 150 1400 10000 4630 Condition 4 >1800 >1000 >80 >200 >150 >1400 >10000 >4630 ττ

Ref.: FIST 3-30 (Transformer Maintenance; Facilities, Instructions, Standards and Techniques by United States Department of the Interior Bureau of Reclamation, Denver, Colorado).

*

CO2 is not considered in the calculations for TDCG, because it is not a combustible gas

**

TDCG means Total Dissolved Combustible Gas.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 98 of 205

Condition - 1 Total Dissolved Combustible Gas (TDCG) and any individual combustible gas below this level indicate normal operation of the transformer. If any gas exceeds the specified level, it needs investigation.

Condition - 2 TDCG and any individual combustible gas in this range indicate greater than normal combustible gas level. A fault may be present. Further monitoring is required. Refer Table 9.7 for recommended sampling frequency and actions.

Condition - 3 TDCG and any individual combustible gas in this range indicate a high level of decomposition of cellulose insulation and / or oil. Refer Table 9.7 for recommended sampling frequency and actions.

Condition - 4 TDCG and any individual combustible gas in this range indicate excessive decomposition of cellulose insulation and / or oil. Continued operation could result in failure of the transformer. Refer Table 9.7 for recommended sampling frequency and actions.

Note: A sudden increase in key gases and the rate of gas generation are more important in evaluating a transformer than the amount of gas.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 99 of 205

Table 9.7 Action based on Dissolved Combustible Gas concentration. Conditions

Condition 1

TDCG Level or Highest Individual Gas (Ref. Table 9.5)

TDCG Generation Rates (ppm / day)

720 ppm of TDCG or highest condition based on individual gas from Table 9.5

Condition 2

Condition 3

Condition 4

ISSUE/ REVISION DATE

20/10/05

28/01/07

Sampling Intervals and Operating Actions for Gas Generation Rates Sampling Interval

< 10

Annually/ 6 Monthly for EHV Trf.

10 ~ 30

Quarterly

> 30

Monthly

< 10

Quarterly

10 ~ 30

Monthly

> 30

Monthly

< 10

Monthly

10 ~ 30

Weekly

> 30

Weekly

< 10

Weekly

10 ~ 30

Daily

> 30

Daily

Operating Procedures Continue normal operation

Exercise caution. Analyse individual gases to find cause. Determine load dependence. Exercise caution. Analyse individual gases to find cause. Determine load dependence. Exercise caution. Analyse individual gases to find cause. Plan outage. Contact manufacturer for advice. Exercise caution. Analyse individual gases to find cause. Plan outage. Contact manufacturer for advice. Consider removal from service. Contact manufacturer for advice

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 100 of 205

Table –9.8 Transformer Fault Types and the gases they produce. Key Gases H2, possible trace of CH4 and C2H6, possible CO

Possible Faults Partial discharge (Corona)

Possible Findings Weakened insulation from ageing and electrical stress.

H2, CH4 (CO if discharges involve paper insulation). Possible trace of C2H6.

Low energy discharges (sparking)

Pinhole puncture in paper insulation with carbon and carbon tracking. Possible carbon particles in oil. Loose grounding of metal objects.

H2, CH4, C2H6, C2H4 and C2H2 present in large amounts. If C2H2 is being generated, it indicates continuance of arcing. CO will be present if paper is being heated.

High energy discharges (arcing).

Metal fusion, (poor contacts in tap changer or lead connections). Weakened insulation, from ageing and electrical stress. Carbonised oil. Paper over heating/ destruction if it is in the arc path.

H2, CO.

Thermal faults less than 3000C in an area close to paper insulation (Paper is being heated)

Discoloration of paper insulation. Overloading or cooling problem. Bad connections. Stray current path and/or stray magnetic flux.

H2, CO, CH4, C2H6 and C2H4

Thermal fault between 3000 C and 7000 C

Paper insulation destroyed. Oil heavily carbonised.

All the above gases and acetylene in large amounts.

High energy electrical arcing 7000 C and above.

Same as above with metal discoloration. Arcing may have caused a thermal fault.

Note: Transformers are so complex that it is impossible to put all causes into a chart. Several other reasons like high current surges due to faults down stream, static electric discharges, multiple core earthing, sustained operation under over load, over/under voltage etc. may also be seen. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 101 of 205

Dissolved Gas Analysis using Key-gas Ratios (Ref. CIGRE Report 15.01.01: October 1999) Key ratio No. 1: (INDICATION: DISCHARGE) C2H2 (acetylene /ethane) : >1 indicates fault C2H6 Key ratio No. 2: (INDICATION: PARTIAL DISCHARGE) H2 (hydrogen /methane) : >10 indicates problem CH4 Key ratio No. 3: (INDICATION: THERMAL FAULT) C2H4 (ethylene /ethane) : >1 indicates thermal fault C2H6 Key ratio No. 4: (INDICATION: CELLULOSE DEGRADATION) CO2 (carbon dioxide /carbon monoxide) : >10 indicates thermal CO over heating >3 indicates electrical fault Key ratio No. 5: (INDICATION: INTANK TAPCHANGER) C2H2 (acetylene /hydrogen) : >2 & C2H2 >30 ppm indicates possibility H2 of tap changer oil leaking into main tank Note: Ratios are to be calculated only if the concentrations of both the gases are above the detection levels.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 102 of 205

FLOW CHART FOR FAILURE INVESTIGATION Ref.: IEEE Std. C 57. 125 - 1991 SELECTED TESTS

TRANSFORMER TRIPPED OR MALFUNCTIONED

ROUTINE TESTS SHOW DEVIATION FROM PAST

ANALYSIS OF DATA

DATA GATHERING TABLES 2 AND 3

MONITOR

YES

NO PROBLEM

YES

CANDIDATE FOR REPAIR

YES

NO

DAMAGE IS OBVIOUS

RETURN TO SERVICE

TESTING TABLE 4 AND TABLE 5

FOCUSED TESTS SELECTED FROM TABLE 4 AND TAB LE 5

SELECTED TESTS

NO ANALYZE TEST RESULTS APPENDIX A

SCRAP

INTERNAL INSPECTION TABLE 8 ANALYZE-SECTION 6

YES

PROBLEM FOUND

TESTING TABLE 4 AND TABLE 5

NO

NO

PERFORM CORRECTIVE ACTION

FURTHER TESTING

YES

YES

FIELD REPAIR

NO

NO

FACTORY REPAIR DECISION

YES TEARDOWN-TABLE 10 ANALYZE-SECTION 6

FIG. — 9 NOTE: For further details please refer to IEEE Std. C. 57. 125 - 1991 ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

10.0

PTRM : 0708 Page 103 of 205

NATIONAL AND INTERNATIONAL STANDARDS APPLICABLE TO POWER TRANSFORMER AND ALLIED PRODUCTS.

10.1

INDIAN NATIONAL STANDARDS.

10.1.1

POWER TRANSFORMERS: IS 1866

: 2000 Code of Practice for Maintenance and Supervision of Insulating Oil in Equipment.

IS 1885 (Part 38) : 1993 Electrical Vocabulary - Transformers and Reactors. IS 2026 ( Part 1) : 1977 Power Transformers - General. IS 2026 (Part 2 ) : 1977 Power Transformers - Temperature rise IS 2026 (Part 3 ) : 1981 Power Transformers - Insulation level and dielectric tests. IS 2026 (Part4)

: 1977 Power Transformer - Terminal marking, Tapping & Connections

IS 2026 ( Part5)

: 1994 Transformer / Reactor bushing minimum external clearance in air

IS 6600

: 1972 Guide

for

loading

of

oil

immersed

transformers. IS 10561

: 1983 Application guide for power transformers.

IS 11171

: 1985 Dry type transformers.

IS 10028(Part1)

: 1985 Code of practice for selection installation & maintenance of transformers- Selection

ISSUE/ REVISION DATE

IS 10028 (Part 2) : 1981 "

"

-

Installation

IS 10028 (Part 3) : 1981 "

"

-

Maintenance

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

10.1.2

PTRM : 0708 Page 104 of 205

MATERIALS, FITTINGS AND ACCESSORIES OF POWER TRANSFORMERS. IS 1747

: 1972 Nitrogen.

IS 1576

: 1992 Solid Press board for electrical purposes.

IS 2312

: 1967 Propeller type AC ventilating fans.

IS 3024

: 1997 Grain Oriented Electrical steel sheet and strips.

IS 3070 (Part3)

: 1993 Lightning arresters for alternating current System; Metal oxide lightning arresters without gaps.

IS 3151

: 1982 Earthing transformers.

IS 3231 (Parts 0~3)

Electrical relays for power System Protection

IS 1367 (Part13) : 1983 Hot dip galvanised coating on threaded fasteners. IS 1363 (Part 1)

: 2002 Hexagonal head bolts, screws, and nuts of product grade

C, Hexagonal head bolts

(M5 to M64) IS 1363 (Part 2)

: 2002 Hexagonal head bolts, screws, and nuts of product grade C, Hexagonal head screws (M5 to M64)

IS 1363 (Part 3)

: 1992 Hexagonal head bolts, screws, and nuts of product grade

C, Hexagonal head nuts

(M5 to M64)

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

IS 8603 (Part 1)

: 1977 Dimensions bushings

PTRM : 0708 Page 105 of 205

for

for

porcelain

use

in

transformer

heavily

polluted

atmosphere 12/17.5 kV Bushings. IS 8603 (Part 2)

: 1977 Dimensions bushings

for

for

porcelain

use

in

transformer

heavily

polluted

atmosphere 24 kV Bushings. IS 8603 (Part 3)

: 1977 Dimensions bushings

for

for

porcelain

use

in

transformer

heavily

polluted

atmosphere 36 kV Bushings. IS 8603 (Part 4)

: 2003



IS 12676

: 1989 Dimensions

52 kV Bushing. for

oil

impregnated

paper

insulated condenser bushings. IS 13305

: 1992 Permissible limits of visual defects for insulating porcelains for electrical circuits.

IS 13312

: 1992 Dimensions of porcelain oil filed transformer bushings (rated 52 kV) in medium polluted atmospheres.

IS 15137

: 2002 Metal Connecting Lugs for Porcelain Transformer Bushings - Specification

IS 1573

: 1986

Electroplated coatings of zinc on iron & steel

IS 2629

: 1985 Recommended

practice

for

hot

dip

galvanising of iron and steel. IS 2633

: 1986 Methods for testing uniformity of coating of zinc coated articles.

IS 4759 ISSUE/ REVISION DATE

20/10/05

: 1996 Hot dip zinc coating on structural steel. 28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 106 of 205

IS 3401

: 1992 Silica gel

IS 3588

: 1987 Electric Axial flow fans.

IS 3637

: 1966 Gas operated relays.

IS 3639

: 1966 Fittings & accessories for power Transformers

IS 4253 (Part1)

: 1980 Cork Composition Sheet - Plain cork

IS 4253(Part2)

: 1980 Cork Composition Sheet - Cork & Rubber.

IS 5561

: 1970 Electric power connectors.

IS 6088

: 1988 Oil

to

water

heat

exchanger

for

transformers. IS 1666

: 1961 Paper

Covered

Rectangular

Copper

Conductors for transformer winding. IS 8468

: 1977 On load tap Changers.

IS 8478

: 1977 Application guide for on load tap Changers.

IS 104

: 1979

Ready mixed paint, brushing, zinc chrome, priming.

IS 2074

: 1992 Ready mixed paint, air drying, red oxide zinc chrome, priming.

IS 2932

: 1993 Enamel, synthetic, exterior (a)

undercoating,

(b)

finishing.

IS 13213

: 1991 Polyurethane full gloss enamel.

IS 13238

: 1991 Epoxy based zinc phosphate primer (two pack).

IS 1554 (Part 1)

: 1988 PVC insulated (heavy duty) electric cables for working voltages upto and including 1100 V.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 107 of 205

IS 1554 (Part 2)

: 1988 " from 3.3 kV upto and including 11 kV

IS 9147

: 1979 Cable sealing boxes for oil immersed transformers; 12 kV ~ 36 kV.

1S 9700

: 1991 Activated alumina.

IS 12943

: 1990 Brass Glands for PVC Cables.

IS 13947 (Parts 1~5):

Low voltage Switch Gear and Control Gear General rules.

IS 4257 (Part 1)

: 1981 Dimensions

for

clamping

arrangements

porcelain transformer bushings for 12 kV to 36 kV bushings.

10.1.3

INSTRUMENT TRANSFORMERS IS 1885 (Part28) : 1993 Electro Technical Vocabulary Instrument Transformers. IS 2705 (Part1)

: 1992 Current Transformers - General.

IS 2705 (Part2)

: 1992 Current Transformers - Measuring.

IS 2705 (Part3)

: 1992 Current Transformers - Protective.

IS 2705 (Part4)

: 1992 Current Transformers – Protective Current transformers for special purpose application.

IS 3156 (Part1)

: 1992 Voltage transformer - General.

IS 3156 (Part2)

: 1992 Measuring Voltage transformers.

IS 3156 (Part3)

: 1992 Protective Voltage transformers.

IS 3156 (Part4)

: 1992 Capacitive Voltage transformers.

IS 4146

: 1983 Application guide for Voltage transformers.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

IS 4201

PTRM : 0708 Page 108 of 205

: 1983 Application guide for Current transformers.

IS: 5547

: 1983 Application guide for Capacitive Voltage transformers.

10.1.4

TRANSFORMER BUSHING IS 1885 (Part54) : 1993 Electro Technical Vocabulary - Insulators. IS 2099

: 1986 Bushings for alternating Voltages above 1000 V.

IS 3347(Part 1to8)

Dimension

for

porcelain

transformer

bushings. IS 4257 (Part 1)

: 1981 Dimension for Clamping arrangements for bushing 12 kV to 36 kV.

IS 5621

: 1980 Hollow porcelains for use in electrical equipment.

IS 8263

: 1976 Methods for radio interference test on high Voltage insulators.

IS 8603 (Part1~3): 1977

Dimension

for

porcelain

transformer

bushings for heavily polluted atmospheres 12, 24 & 36 kV. IS 8603 (Part 4)

: 2003



52 kV Bushing

IS 8704

: 1995 Artificial pollution tests on high Voltage insulators to be used on AC Systems.

IS 12676

: 1989 Dimensions

for

oil

impregnated

paper

insulated Condenser bushings. IS 13134

: 1992 Guide

for

Selection

of

insulators

respect of pollution Conditions. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

in

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

IS 13305

PTRM : 0708 Page 109 of 205

: 1992 Permissible limits for Visual defects

for

insulating porcelains for electrical circuits. IS 13312

: 1992 Dimensions

of

porcelain

oil

filled

transformer bushing (rated 52 kV) for medium polluted atmosphere. IS 15137

: 2002 Metal Connecting Lugs for Porcelain Transformer Bushings - Specification

10.1.5

REACTORS IS 5553 (Part 1)

: 1989 Reactors - General.

IS 5553 (Part 2)

: 1990 Shunt Reactors.

IS 5553 (Part 3)

: 1990 Current

limiting

reactors

and

neutral

earthing reactors. IS 5553( Part 6) : 1990 Earthing transformers (Neutral Couplers) IS 5553( Par 8)

10.1.6

: 1990 Smoothing Reactors

TRANSFORMER OIL AND OIL TESTING IS 335

: 1993

New insulating oils.

IS 1448 (Part 10) : 1970 Method for test for petroleum and its products cloud point and pour point. IS 1448 (Part 16) : 1990 Density of crude petroleum and liquid petroleum products by Hydrometer method. IS 1448 (Part 21) : 1992 Petroleum and its Products - Flash point by Pensky Martens Apparatus. IS 1448(Part 25) : 1976 Determination of Kinematic and Dynamic Viscosity. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

IS 1866

PTRM : 0708 Page 110 of 205

: 2000 Code of practice for maintenance and

supervision

of

insulating

oils

in

equipment. IS 2362

: 1993 Determination of water by Karl Fisher method.

IS 6103

: 1971 Method of test for specific resistance (resistivity) of electrical insulating liquids.

IS 6104

: 1971 Method of test for interfacial tension

of

oil against water by ring method. IS 6262

: 1971 Method of test for power factor and dielectric constant of electrical

insulating

liquids. IS 6792

: 1992 Method of determination of electric strength of insulating oils.

IS 6855

: 2003 Method of sampling for liquid dielectrics.

IS 9434

: 1992 Guide for sampling and analysis of free and dissolved gases and oil from oil filled electrical equipment.

IS 10593

: 1992 Methods of evaluating the analysis of gases in oil filled electrical equipment.

IS 12177

: 1987 Methods of test for oxidative ageing of electrical insulating petroleum oils by open beaker method.

IS 13567

: 1992 Determination of water in insulating liquids and in oil impregnated paper & press board

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

by

automatic

PTRM : 0708 Page 111 of 205

Coulometric

Karl

Fisher

Titration - Method of Test. IS 13631

: 1993 Method of test for detection & determination of antioxidant additives in insulating oils.

IS 12463

10.1.7

: 1988 Inhibited Mineral Insulating oils.

INSULATION CO ORDINATION AND HIGH VOLTAGE TESTING IS 1876

: 1961 Method

for

voltage

means IS 2071 (Part1)

measurement

by

of sphere gaps.

: 1993 High voltage test techniques;

General

definitions and test requirements. IS 2071 (Part 2)

: 1974





Test procedures.

IS 2071 (Part3)

: 1976





Measuring devices.

IS 2165 (Part1)

: 1977 Phase to earth insulation co-ordination principals and rule.

IS 2165 (Part2)

: 1983 Phase to phase insulation co-ordination principles and rules.

IS 3716

: 1978 Application

guide

for

insulation

for

partial

co-

ordination. IS 6209

: 1982 Methods

discharge

measurements. IS 8690

: 1977 Application guide for measuring devices for high voltage testing.

ISSUE/ REVISION DATE

IS 2551

: 1982 Danger notice plates.

IS 8923

: 1978 warning symbol for dangerous voltages.

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

IS 12776

: 2002 Galvanised

strand

PTRM : 0708 Page 112 of 205 for

earthing

-

Specification.

10.2

IEC STANDARDS IEC 60071-1 (2006)

Insulation co-ordination; Definitions, principles and rules.

IEC 60071-2 (1996)

Insulation co-ordination; Application guide.

IEC 60076–1 (2000)

Power transformers; General.

IEC 60076–2 (1993)

Power transformers; Temperature rise.

IEC 60076–3 (2000)

Power

transformers;

Insulation

levels,

dielectric tests and external clearances in air. IEC 60076–4 (2002)

Power transformers; Guide to the lightning impulse and switching impulse testing.

IEC 60076–5 (2006)

Power transformers; Ability to withstand short circuit.

IEC 60076–7 (2005)

Power transformers; Loading guide for oil immersed power transformers.

IEC 60076–8 (1997)

Power transformers; Application guide.

IEC 60076–10 (2005)

Power

transformers;

Determination

of

sound levels – Application Guide. IEC 60076–10-1 (2005)

Power

transformers;

Determination

of

sound levels. IEC 60076–11 (2004)

Power transformers; Dry type transformers.

IEC 60076–14 (2004)

Power transformers; Design & Application of liquid immersed power transformers using high temperature insulation materials.

IEC 60137 (2003)

Insulating bushings for alternating voltages above 1000 V

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

IEC 60156 (1995)

PTRM : 0708 Page 113 of 205

Method for determination of the electric strength for insulating oils.

IEC 60044-1 (2003)

Current Transformers.

IEC 60044-2 (2003)

Inductive Voltage Transformers.

IEC 60044-5 (2004)

Capacitor Voltage Transformers.

IEC 60044- 6 (1992)

Protective Current Transformer for transient performance.

IEC 60214-1 (2003)

Tap changers; Performance requirements and test methods

IEC 60214-2 (2004)

Tap changers; Application Guide

IEC 60168 (2001)

Tests on indoor and outdoor post insulators greater than 1000 volts.

IEC 60270 (2000)

High

Voltage

Test

techniques:

Partial

discharge measurements. IEC 60289 (1988)

Reactors.

IEC 60296 (2003)

Fluids for electro-technical applications unused

mineral

insulating

oils

for

transformer and switch gear. IEC 60310 (2004)

Railway

applications

-

Traction

Transformers and inductors. IEC 60422 (2005)

Mineral insulating oil in electrical equipment - Supervision and maintenance guide.

IEC 60445 (2006)

Identification of equipment terminals and termination of certain designated conductors including general rules for an alpha numeric system.

IEC 60475 (1974)

ISSUE/ REVISION DATE

20/10/05

28/01/07

Method of sampling liquid dielectric.

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

IEC 60529 (2001)

PTRM : 0708 Page 114 of 205

Degrees of protection provided by enclosures (IP Codes).

IEC 60554 (Part 1 ~ 3)

Specification for cellulosic papers for electrical purposes.

IEC 60567 (2005)

Guide for the sampling of gases and of oil from oil filled electrical equipment and for the analysis of free and dissolved Gases.

IEC 60599 (1999)

Guide to the interpretation of dissolved and free

gases

in

mineral

oil-impregnated

electrical equipment in service. IEC 60616 (1978)

Terminal and tapping marking for power transformers.

IEC 60628 (1985)

Gassing of insulating liquids under electrical stresses and ionisation.

IEC 60905 (1987)

Loading

guide

for

dry

type

Power

Transformer. IEC 60947 (Part 1 to 7)

Low voltage switchgear and control gear.

IEC 61378-1 (1997)

Converter Transformer for industrial application.

IEC 61378-2 (2001)

Converter Transformer for HV DC application.

IEC 61639 (1996)

Direct

Connection

transformer

and

gas

between insulated

power metal

enclosed switchgear for rated voltages of 72.5kV and above. ********************

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 115 of 205

TRANSFORMER ACCESSORIES

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 116 of 205

TEMPERATURE INDICATOR

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 117 of 205

INSTALLATION AND MAINTENANCE INSTRUCTIONS 1.

APPLICATION The Temperature indicator is used as an Oil Temperature Indicator (OTI) or as Winding Temperature Indicator (WTI) for the protection of liquid immersed power transformer. In the case of dry type transformers it is used as Temperature Indicator (T.I.) to monitor the temperature of the windings.

2.

SCOPE OF SUPPLY OTI & TI: Instrument with specified Range, Number of control switches, length of capillary and sensing bulb. WTI: Same as 2.1 but fitted with specified thermal image device. TRANSMITTER (OPTIONAL): A precision potentiometer is mounted inside the case of OTI or WTI (2.1 or 2.2) to transmit the measured temperature to remote point(s). REPEATER (OPTIONAL): Analogue indicator supplied separately for remote indication of the temperature measured by OTI or WTI (2.1 or 2.2)

3.

OPERATION The instrument operates as OTI when its sensing bulb is mounted in an oil filled pocket located in the hottest oil of an oil immersed transformer. The instrument operates as TI when its sensing bulb is exposed to the medium adjacent to the windings of a dry type transformer. When a proportionate load current of the transformer is passed through the thermal image device, the instrument operates as a WTI integrating the simulated temperature rise of the thermal image device and the top oil temperature measured by the sensing bulb. Remote indication of the temperature measured by the OTI or WTI is provided by connecting the transmitter to the repeater either directly or through a resistance transducer (resistance to current converter).

4.

CONSTRUCTION LIQUID-FILLED SYSTEM (Refer Fig. 1): A sensing bulb (25), a measuring bellows (2) and a small bore capillary tube (24) connecting the two, form the measuring system. A second bellows (16-compensating bellows)

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 118 of 205

connected with a second capillary (24) running parallel to the first capillary and terminated at the head of the bulb from the temperature compensating system. Both the systems are completely filled with the same liquid (other than mercury). The two bellows are linked to a compensating lever (15) in such a manner that the effect of ambient temperature changes on the capillary line and measuring bellows is compensated. The movement of the measuring bellows is related only to the temperature being measured by the sensing bulb. This movement is amplified by the link and lever mechanism (6), which directly drives the rotating disc (21) carrying the control switches. The same mechanism moves, through rack and pinion a separately mounted indicating pointer (Fig. 2, 11) over a calibrated dial. Head compensation is provided by sealing both the systems under initial pressure, which is greater than the possible head pressure due to differences in the elevation between the bulb and indicator. MAXIMUM POINTER (RED COLOURED) located on the indicator lid, is resettable from outside the case by a screw driver blade. Unscrew and remove black cap to reach the screw driver-slot. CAUTION: Never use the switch testing knob for setting the maximum pointer. If used, the switch contacts will close and initiate the external control circuits when the instrument is in operation. SWITCH TESTING KNOB: It is fitted on the indicator lid to check mercury switches setting and potentiometer operation. This knob when rotated moves the indicating pointer, switch mechanism and potentiometer wiper together and facilitates testing these circuits without opening the lid. Rotate the knob slowly and steadily for an accurate check. Never allow the knob to spring back suddenly or quickly, as this will cause damage. THERMAL IMAGE DEVICE (Refer Fig. 1): A heater coil (3-Bellows Heater) is fitted around the measuring bellow (2) and supplied from a current transformer in the load circuit of transformer. The heater coil simulates hotspot temperature of the winding over top oil temperature for a given load. The measuring bellows reacts to this simulated temperature rise in addition to the top oil temperature measured by the sensing bulb and the instrument functions as a WTI displaying the hottest spot temperature of the winding. An adjustable shunt resistor (17-calibrating shunt) is provided for shunting portion of the current through the heater coil to obtain precise thermal image.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 119 of 205

FIG. 1 INDICATOR (LID & DIAL REMOVED)

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 120 of 205

REMOTE INDICATION (OPTIONAL): Refer Fig. 1, A precision potentiometer (20) is mounted inside the indicator to function as a transmitter for remote indication of the temperature measured by the OTI/WTI. Technical Data of the transmitter and repeater along with details of adjustments are given in the relevant data sheet supplied with each indicator. ELECTRICAL CONNECTION: All internal electrical connection are wired to the terminal block (Fig. 1, 14) mounted inside the indicator case. A wiring diagram is fixed inside the case of each indicator. Switches are identified by markings S1, S2, S3 and S4 on them. Terminal Nos. wired to each circuit are detailed below.

TERMINAL Nos.

WIRED TO

1,2 Switch 3,4 5,6 7,8 9,10,11 12,13,14

5.

S1 — Alarm S2 — Trip S3 — Cooler Control – 1 S4 — Cooler Control – 2 Bellows, Heater & Shunt Potentiometer-Min., Wiper, Max

PRE-INSTALLATION TESTING EQUIPMENT: 1. Controlled constant temperature bath with continuously stirred liquid. 2. Certified Standard Thermometer. 3. A continuity test circuit. 4. High voltage breakdown tester. 5. A constant current source. Note: Calibration baths are generally suitable for use only in workshop. If required for use in the field, they should be used under cover and in a non hazardous environment.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 121 of 205

PRE-CONDITIONING: Before commencing any tests check the following: 1. The instrument is as per purchaser specification. 2. The instrument is not damaged in any way and any such damage is rectified before testing. 3. The instrument is mounted correctly. (Refer 6.1) 3. The shipping stop (22 - Fig. 1) is removed.

OTI CALIBRATION: Place the sensing bulb of the temperature indicator under test in the well-stirred constant temperature bath. Allow 5 minutes settling time before taking readings. Check the reading near to but not less than minimum value of the indicator scale. For increasing values of temperature, repeat the procedure to obtain at least two further readings the highest value being near to but not greater than the maximum scale value of the indicator. The readings should agree with the standard thermometer within ± 1.5% f.s.d. (Maximum scale value). Otherwise following adjustments should be made.

ZERO ADJUSTMENT: Use this adjustment for correcting readings near minimum scale value. Referring to Fig. 1, firmly hold the tongue adjuster (50 by a 2BA spanner and slacken the lock nut (4) with a second 2BA spanner. To move the indicting pointer (19) up or down the scale, turn the tongue adjuster (5) by a small amount anticlockwise or clockwise respectively. Retighten the lock nut holding firmly the tongue adjuster. Do not twist the measuring bellows while carrying out this adjustment as this may cause damage to the linkage/bellows.

SPAN ADJUSTMENT: Use this adjustment for correcting reading near the maximum scale value. Referring to Fig. 1, slacken the shoulder screw (7) half a turn but do not remove the same. Turn the range adjuster screw (8) anticlockwise or clockwise to increase or decrease respectively the sweep of the pointer. Make the adjustment in small increments and carefully. Half a turn in either direction may correspond to approximately 0.5° reading. After adjustment, retighten the shoulder screw.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 122 of 205

Ensure that the lock nut (4) and shoulder screw (7) are properly tightened after the above adjustments. Repeat the tests in cold and hot bath until the accuracy limit of ± 1.5% f. s. d. is achieved.

WTI CALIBRATION: During Calibration, keep the instrument lid fixed in position. Place the sensing bulb in the continuously stirred oil bath, the temperature of which is maintained at the specified value. Allow 5 minutes setting time and apply the specified current to the bellows heater and calibrating shunt network. The current must remain switched on at specified value for at least 40 minutes before taking reading. To achieve the readings within the accuracy limits or to reset the temperature rise to a different value, the following adjustments should be made.

GRADIENT ADJUSTMENT: After opening the instrument lid, carefully remove the dial. Withdraw the calibrating shunt (17-Fig. 1) after removing the nut and retaining washer. One adjustable centre band and two fixed bands at the ends are provided in the shunt. One supply lead is connected to the centre band and the other lead to the lower band on the shunt. Slacken the screw in the retaining clip of the centre band. To reduce the temperature rise, move the centre band nearer to the lower band, to increase the temperature rise reverse the procedure. Retighten the screw on the centre band after adjustment. Replace the shunt, dial and lid. Repeat the calibration, check after adjustments until the accuracy limits achieved. SWITCH SETTING: The switch settings are adjustable as indicated below: Indicator Scale Range Switch setting adjustable Switch differential (close to to close between open) adjustable between 0 - 120° C

40° C and 120° C

6° C and 80° C

20 - 120° C

50° C and 120° C

6° C and 90° C

30 - 120° C

50° C and 120° C

6° C and 100° C

0 - 150° C

45° C and 150° C

7.5° C and 105° C

0 - 240° C

80° C and 240° C

12° C and 160° C

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 123 of 205

NOTE: Unless specified otherwise, the instruments are supplied with minimum switch differential. Connect across the switch contacts the continuity test circuit and check the correct operation of the switches at their set points to make (close) and break (open) contacts. The switches should operate at set point within ± 2.5% of switch setting arm pointer (10-Fig. 1) indication, otherwise the following adjustment should be made. SWITCH ADJUSTMENTS: Referring to Fig. 1 slacken switch setting screw (11) on each switch setting arm (10). Move the left hand arm pointer over the switch scale (9) to the required temperature for making (closing) contact and right hand arm pointer to the required temperature for breaking (opening) contact. Retighten both switch setting screws. By closing the left hand arm pointer to the right hand arm pointer minimum differential is obtained. A builtin stop automatically sets the minimum differential. While slackening and tightening the setting screw, steady the disc with the other hand to prevent undue strain on the mechanism. The indicating pointer can be moved with a finger in a clockwise direction to check the operation of the switches at set points. By moving the pointer slowly and steadily, an accurate check is obtained. Never allow the pointer to spring back suddenly or quickly and also force the pointer in an anticlockwise direction. By doing so the measuring bellows is likely to be damaged. An alternative procedure is to check the switch operation while calibrating the instruments for temperature readings.

INSTALLATION MOUNTING: Mount the instrument in a vertical position. Otherwise errors, particularly in the horizontal plane, will upset the zero setting of the mercury switches. Place a sprit level on the top of the indicator case to ensure correct positioning and operation of the mercury switches. If vibration exists at the mounting position, mount the indicator on a nonvibrating structure. Suitable anti-vibration mountings are supplied. Do not use these mountings during transport. CAPILLARY LINE: Do not stretch hard twist or bend the capillary to a radius less than 75 mm. Continuously support the capillary by suitable clips at intervals of 300 to 450 mm. Allow necessary slack at the bulb and for

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 124 of 205

mounting and removing the bulb without sharp bend at the joint. Wind in spiral (minimum dia. 150 mm) the possible excess length of capillary close to the indicator or the bulb.

7.

HANDLING AND STORAGE Handle the instrument with utmost care. Do not twist the capillary while unpacking, storage or installation. Avoid sharp bends especially where the capillary joins the indicator and bulb. Allow minimum 75 mm radius of bend. Never lift or carry the instrument by holding the capillary only. Before storing or transporting, pack the instrument in the paper board box supplied. Before lowering the instrument into the box, fix the shipping stop (22) and wind the capillary in spiral close to the indicator (minimum, spiral dia 150 mm) locate all the cushions before closing and sealing the box. Where necessary, provide additional wooden packing case for transport. IMPORTANT: When Anti-Vibration mountings are supplied, do not use these during transport.

8.

MAINTENANCE Normally no maintenance is required for the temperature indicator. However, adjustment or replacement of switches and resetting of the maximum pointer may become necessary.

9.

REPAIRS If a mercury switch is damaged in anyway, it may be unclipped from the switch carrier and the leads removed with a hot soldering iron. After resoldering the leads to a new switch and locating back the switch in the clip, the switch should be re-balanced. This is done by making the switch to topple in its carrier at the instant when the mercury flows toward or away from the electrodes. By sliding the switch a little in the appropriate direction in the clip, correct topping is achieved. After correctly balancing the switch, check the operation at preset temperature. If necessary re-zero the switch scale by slackening the switch zeroing screw (12-Fig. 1) at the top of the switch scale and rotating the scale to required position. Retighten the screw after adjustment. If the bellows, bulb or capillary are damaged, repairs can be done only at the manufacturer's factory.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 125 of 205

GAS & OIL OPERATED (BUCHHOLZ) RELAYS

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 126 of 205

CONTENTS I.

General

2.

Applications

3.

Advantages

4.

Construction

5.

Functional Test

6.

Electrical Connection

7.

Installation and Maintenance

8.

Basic Characteristics

9.

Function

10.

Operating Characteristics

11.

Relays for use in areas of Seismic Disturbances

12.

Specifications of Relays

13.

Overall Dimensional drawing

14.

Dimensions and ratings

PREFACE The ever increasing demand for electrical energy goes together with the demand for more and more efficient and reliable "protection devices'' for power, distribution and supply facilities. In the field of power supply, transformers represent key installations that demand effective protection to ensure the constant availability of electrical energy. One of the most essential devices to protect a transformer is a Buchholz relay. For more than 20 years, Buchholz relays have been manufactured in India. They are made by an experienced staff of skilled workers, highly qualified technicians and engineers ensuring a high degree of precision and quality. A wide range of type corresponding to the BIS & International Standards are available to meet the many requirements of manufacturers and users of transformers. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

1.

PTRM : 0708 Page 127 of 205

GENERAL Power Transformers are considered to be a highly reliable type of equipment, yet, in order to ensure the continuity of service that modern conditions demand, protective devices are required. The purpose of such devices is to disconnect faulty apparatus before large-scale damage is caused by ‘a’ fault to the apparatus or to other connected apparatus. Such devices generally respond to a change in the current or pressure arising from the faults and are used for either signalling or tripping the circuits. Protective devices in the ideal case must be sensitive to all faults, simple in operation, robust for service and economically feasible. Considering liquid immersed transformers, a near-ideal 'protective device' is available in the form of Gas and Oil relay described here. The relay operates on the well-known fact that almost every type of electric fault in a `liquid immersed transformer' gives rise to gas. This gas is collected in the body of the relay and is used in some way or other to close the alarm or the tripping circuit The principle of the Gas and Oil relay was first successfully demonstrated and utilised by 'Buchholz' many years back. In a series of experiments carried out extensively in Germany it was proved that the Relay is capable of bringing to light incipient fault thereby preventing further spreading of the fault and extensive damage and thus saving expensive and protracted repairs. So successful is the principle of this Relay that despite the continued search for better protective devices in other electrical fields the Gas-and-Oil Relay is still on its own in providing protection against a variety of faults.

2.

APPLICATIONS Double element relays can be used in detecting minor faults in a transformer. The alarm element will operate, after a specified volume of gas has collected to give an alarm indication. Examples of incipient faults are a)

Broken-down core bolt insulation

b) Shorted laminations c) Bad contacts ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 128 of 205

d) Overheating of part of windings. The alarm element will also operate in the event of oil leakage, or if air gets into the oil system. The trip element will be operated by an oil surge in the event of more serious fault such as a)

Earth faults

b)

Winding short circuits

c)

Puncture of bushings

d)

Short circuit between phases

The trip element will also be operated if a rapid loss of oil occurs. Single element relays can be used to detect either incipient or major faults in oil filled potential transformers, reactors, capacitors etc. A special single element relay is available for the protection of on load tap-change equipment.

3.

ADVANTAGES a)

Castings treated against porosity through a special process.

b)

Unique internal design of 'housing' prevents false air traps on top of the relay.

c)

Well-designed internal layout gives clear view of colour of gas inside the relay through glass window for fault analysis.

d)

Bucket type float design with inherent ability to withstand vacuum treatment of transformers.

e)

Built in test facility for checking continuity of both Alarm and Trip circuits.

f)

Antivibration custom-built mercury switches give high stability against mechanical shocks and vibrations.

g)

ISSUE/ REVISION DATE

ISI Mark of quality on every relay

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

ISSUE/ REVISION DATE

20/10/05

28/01/07

PTRM : 0708 Page 129 of 205

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

4.

PTRM : 0708 Page 130 of 205

CONSTRUCTION The Buchholz relay essentially consists of enclosure 1 i.e. an oil tight container and an inserted assembly 2 comprising of two pivoted elements fitted with switches (Refer fig. above). The enclosure is provided with inlet 1.1 and outlet 1.2 for the liquid. To allow connection of pipes, the enclosure openings can be designed with pipe thread or flange. The front inspection glass is provided with a graduation (100 to 300 cm³) to allow readings the accumulated volume of gas and observe colour of gas for fault analysis. For checking the function of the inserted assembly a Test Key (1.3) is provided. There is also a visual indication on the scale (1.4) of service and Test/Locking position, in the form of movement of red indicator on the reading scale. This allows the testing of the alarm and Trip circuits before installation and even when the transformer is in service. Just above the inspection glass an arrow shows the specified direction of flow of the insulation liquid to the conservator. Enclosure 1 and its inserted Assembly cover are made out of Cast Iron.

5.

FUNCTIONAL TEST

5.1

Testing the relay Function with the test key. A test system is provided in the Buchholz relay that allows the functional test of the upper and lower switching system. To test the relay function loosen the nut (1.5) on the Test Key (1.3) and rotate the key with a screwdriver in the Anticlockwise direction till the SLOT on the TEST. Key points towards the T/L position. Both the alarm (upper switching system) and Trip (lower switching system) will show continuity. On bringing the SLOT on the Test Key to S (service) position by rotating the

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 131 of 205

'key' clockwise the Alarm and Trip circuits will not show continuity. The circuits will be actuated to 'ON' position only when there will be a fault in the transformer. Repeat the functional test each time a relay is started or maintenance completed. 5.2

Testing the relay Function with the Test Pump. Screw the test pump/Air bottle to the test cock. Open the test cock and pump air gently into the Buchholz relay until the upper switching system operates. For operating the lower switching system air has to be pumped suddenly with a jerk which will in turn operated the lower switching system.

6.

ELECTRICAL CONNECTION To allow installation of the 'signal wire' open the terminal box cover comprising of the nameplate and the instruction sticker on the backside. Then pass the wire through one of the two-conduit screwings (1.6) into the terminal box. By using either one or the other openings, facility is given for the cable to enter the terminal box from the left or right. The upper two studs are terminals for the Alarm switching circuit and are denoted by A. Likewise the lower two studs are terminals or the Trip switching circuit and are denoted by T.

7.

INSTALLATION

7.1

Installation in to pipeline. For installing the relay into pipeline proceed as follows: -

See that the Buchholz relay is positioned with the arrow pointing towards the conservator, the connection box is in the Y plane (vertical) and to Test cock. (1.7) and air vent cock (1.8) are at the top.

-

Mount the Buchholz relay as close as possible to the tank in the pipeline between transformer and conservator.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 132 of 205

-

Keep pipe bends as wide as possible between transformer and conservator.

-

Make sure pipe ascends to the conservator at angle between three degree to seven degrees.

-

See that the relay enclosure is not subjected to stress. If necessary, use expansion compensators.

-

Ensure that he slot on the Test Key remains in the T/L (Test/Locking) position during storage or loose transportation of the relay.

- Ensure that the slot on the Test Key remains in the 'S' (Service) position and the Test Key Bolt is Tightened just before commissioning of the relay. 7.2

Filling with insulation Liquid To fill the Buchholz relay, proceed as described below:

7.3

-

Remove the protective acorn nut (1.9) from the air vent cock.

-

Open the air vent cock to let air escape until insulation liquid emerges.

-

Shut the air vent cock.

-

Check liquid level in conservator.

Maintenance The Buchholz relays are not sensitive to external influences. No servicing is needed during operation. On routine inspections of the protection equipment, test the function of the Buchholz relay as described earlier and check the alarm and trip devices connected to them.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

8.

PTRM : 0708 Page 133 of 205

Basic Characteristics The Gas and Oil relay provide protection against a number of internal faults but it also is able to indicate in several cases the type of fault. This is possible because the gas collected in relay can, from its colour, odour and composition, indicate where the fault may be and what its nature is. By examining the gases collected it is possible to infer the nature of fault. Thus : a. If the gas is colourless and odourless or with only a faint odour of oil, the gas is air trapped in the oil or the insulation. b.

If the gas is Greyish White with sharp and penetrating odour and noninflammable it is due to overheated or faulty insulation (fuller board etc.)

c.

If the gas is yellowish in colour and inflammable it may be due to surface leakage on material like wood.

d. lf the gas is dark Grey and inflammable it may be due to a flashover in oil or due to excessive overheating of the oil caused by a fault in the winding or the core. On the operation of the alarm if investigation of the collected gas does not indicate a serious fault it is possible to leave the transformer in service till it is convenient to carry out a through inspection. This occurrence is possible on a newly commissioned transformer due to air trapped in the oil or the insulation. On repeated and frequent alarm signals the transformer should be taken out of service for thorough check up.

9.

FUNCTION The function of a double element relay will be described here. During normal operation of a transformer the Buchholz relay is completely filled with oil. Buoyancy and the moment due to counter weights keep the floats in their original top positions.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 134 of 205

In the event some fault in the interior of the transformer tank gas bubbles are produced and accumulate in the Buchholz relay on the way to the conservator. In consequence, the oil level in the relay enclosure drops which in turn lowers the upper bucket. This causes the mercury switch/Reed switch to operate an alarm signal. The lower bucket does not change its position, because when the gas reaches the upper inside wall of the pipe it can escape into the conservator. Hence, minor fault in the transformer tank will not trigger the lower switching assembly and will not trip the transformer. In case the liquid continues to drop due to loss of oil, the lower also goes down. In consequence lower switching system operates if the level of oil goes below the bottom level of the pipe connected to the relay. The lower bucket, does not change its position, because when the gas reaches the upper inside wall of the pipe it can escape into the conservator. Hence, minor fault in the transformer tank will not trigger the lower switching assembly and will not trip the transformer. In case the liquid continues to drop due to loss of oil, the lower also goes down. In consequence lower switching system operates if the level of oil goes below the bottom level of the pipe connected to the relay. Alternately in the event the liquid flow exceeds a specific value (which is continuously adjustable, by means of a flap) the lower bucket is forced down, thus triggering the lower switching system to operate. As the liquid flow rate decreases or the level of the liquid rises the bucket returns to its original position. The single element relay has only one operating element and it responds to either gas collection or oil surges. The method of operation is similar to that described for double element relay. Single element relays are suitable for the protection of oil filled reactors, capacitors and potential transformers. The single element oil Surge relay has been specifically designed for use with on load tap change equipment and it will bypass normal amounts of gas which are generated by tap change operations and will only respond to oil surges and loss of oil. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

10.

PTRM : 0708 Page 135 of 205

OPERATING CHARACTERISTICS Relays of the double element type are made in three sizes. The sizes are distinguished by the numerical prefix 1, 2 or 3. This refers to the diameter of the bore of the oil pipe connecting the transformer to the conservator tank. They are referred to as Type GOR 1, GOR 2 and GOR 3, where the Alphabets indicate 'Gas and Oil Operated Relay' and the number refers to the pipe bore diameter as 25, 50 and 80 mm. respectively. The implications of the various Type Nos. and their operating conditions can be listed as follows: TYPE NO.

SPECIAL OPERATING CONDITIONS.

GOR 1 GOR 2

Double element Mercury switch type Buchholz Relays Normally open type.

GOR 3 SR 1

25 mm. Single element Mercury switch type Surge relay suitable for OLTC

SR 1/V

25 mm. Single element Mercury switch type for Gas volume Alarm suitable for reactors, capacitors, potential and distribution transformers.

GOR 1E

Double element Mercury Switch type Buchholz relays.

GOR 2E

Made as per UNEL-UTE-DIN-BS standards normally open type.

The symbol /VO following their type markings indicate that the relays contain Reed switches and normally open type

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 136 of 205

The symbol /S following their type markings of all relays mentioned indicate that the relays are suitable for Silicon Oil normally used in Electro static precipitator transformers. All relays mentioned above are normally open types. Normally closed type relays can also be supplied on request.

11.

Relays for use in Areas of Seismic Disturbance When transformers are required for use in areas subject to earthquakes or for traction applications, we can supply special relays, which use magnetically operated Reed Switches instead of mercury switches.

The outward appearance of these relays are exactly the same as those with mercury switches but they are distinguished from them by the symbol /VO following their type marking. The latter V (for vibration) indicates that the relay contains reed switches and the latter O that the contacts are normally open. Thus a Type GOR 2/VO signifies a 50 mm. (pipe size). Double float relay with normally open Reed Switches. OPERATION In the double element relay, collection of gas causes the oil level within the relay to fall. This in turn causes the upper element to rotate on its pivots, bringing the magnet it carries into a position where it operates the Alarm Switch. An oil surge through the relay will cause the lower element to rotate about its pivots and its magnet into a position so as to operate the tripping switch. CONNECTIONS The terminal box and the terminals are the same as that of mercury switch type relays. In the reed switch relays, each reed switch is protected by, an inductor in series. These inductors are intended to protect the reed switch contacts from the effects of capacitive loads, such as are imposed by long leads or pilot cables, and must not be removed from relays in service.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 137 of 205

Protection of reed switch contacts against the effects of inductive loads, such as those imposed by contactors and Electro-Magnetic relays, is achieved by means of a diode wired across each load. This diode must be rated with forward current at least as high as the steady load current and connected observing polarity so as to absorb the back e.m.f.. These diodes are not provided with the relay. The Mounting position and Testing on site procedure are same as that of 'Mercury Switch type' Buchholz relay. OPERATING CHARACTERISTICS All double element relays are adjusted so that their performances lie within the limits given in table 14. In addition the Reed Switch Relay is capable of withstanding shocks of up to 4g. Such shocks will not of themselves cause the relay to operate.

SWITCH DATA: TYPE ---------------------------------------------------------- Normally Open CONTACT RATlNG ------------------------ 250VA A.C. (r.m.s.) or D.C. max. SWITCHING CURRENT --------------------------------- 5A A C or D.C. max. SWITCHING VOLTAGE --------------------------------------- 300 V D.C. max. ----------------------------- 240 Volts A.C. (r.m.s.) max. BREAKDOWN VOLTAGE --------------------------------- 650 Volts D.C. min. INITIAL CONTACT RESISTANCE ------------------------- 70 milli-ohms max. RESONANT FREQUENCY ------------------------------- greater then 700 Hz. ACTUATING TIME (Including Bounce) -------------- 2 milli-seconds (Typical) THESE SWITCHES HAVE RHODIUM CONTACT, LOCATED MIDWAY ALONG THE LENGTH OF THEIR GLASS TUBES, THE TUBES CONTAIN AN ATMOSPHERE OF NITROGEN. PROTECTION OF REED SWITCH CONTACTS:

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 138 of 205

THE EFFECTS OF CAPACTIVE LOADS SUCH AS ARE IMPOSED BY LONG LEADS, ARE SUPPRESSED BY MEANS OF SMALL INDUCTORS MOUNTED WITHIN THE RELAY AND WIRED ONE IN SERIES WITH EACH SWITCH. THE EFFECTS OF INDUCTIVE LOADS SUCH AS ARE IMPOSED BY CONTACTORS AND E.M. RELAYS ARE SUPPRESSED BY MEANS OF A DIODE WIRED ACROSS EACH LOAD. DIODE TO BE RATED WITH FORWARD CURRENT AT LEAST AS HIGH AS STEADY LOAD CURRENT AND CONNECTED SO AS TO ABSORB BACK e.m.f.. ARRANGEMENT OF TERMINALS AND MEANS OF PROTECTION FOR REED SWITCH CONTACT.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

12.

PTRM : 0708 Page 139 of 205

SPECIFICATION OF RELAYS Parameter

Rating

Tolerance

Contact System

Mercury switch

Type of contact

Make Contact

Optional make or break

Switching voltage

220V AC/DC

12 V to 250V AC/DC

Switching Current

5 Amp AC/2 Amp DC

0.05 to 5 Amp

Switching Capacity

1000 W/VA

1 W/VA to 1000 W/VA

Frequency

50 HZ

0 to 60 HZ

Limiting temp of insulation liquid

+ 120° C

140° C for two hrs.

Gas volume alarm

100 cm³ to 300 cm³

Insulating liquid flow

65 cm/sec to 160 cm./sec. (depending on size)

Relay casing tested at

8 KG/cm² for 1 minute

Max. Permissible flow rate of insulating liquid

400 cm/sec.

Vibration sensitivity

0.01 inches peak to peak at frequency of 100 cycle/sec.

Continuously adjustable

Assembled relays are pressure tested with transformer oil at 3kg/cm² for 60 minutes. Electrical circuits are tested at 2000 volts R.M.S. for one minute. Insulation resistance measured at 500 volts is not less than 10 Megaohms in air.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 140 of 205

IMPORTANT The various part of a relay including the body, form one complete calibrated unit and must not be inter changed with those of other relays. We strongly recommend that relay should not be taken apart, and under no circumstances should any alteration be made to the angle of the flap on the trip element. This has been correctly adjusted during manufacturing.

RELAY TYPE GOR 1

RELAY TYPE SR1

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 141 of 205

OIP CONDENSER TYPE BUSHINGS

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 142 of 205

CONTENTS

1.

Design and construction

2.

Packing and storage

3.

Unpacking and handling

4.

Checks before installation

5.

Installation

6.

Checks after installation

7.

Periodical check and maintenance

8.

Unmounting and packing

9.

Safety

These instructions are crucial for the proper handling, installation, operation & maintenance of Oil Impregnated Paper Condenser Bushings and these should be in the possession of those who are responsible for the above activities.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 143 of 205

INSTRUCTIONS FOR INSTALLATION, OPERATION AND MAINTENANCE OF OIP CONDENSER BUSHINGS 1.

DESIGN AND CONSTRUCTION The general constructional details of the bushing, intended for oil-air application are shown in Fig. 1. The active part of the bushing consists of an Oil Impregnated Paper (OIP) core (1) manufactured from superior grade Kraft insulating paper with condenser graded layers for field control, wound under tension on central tube / conductor (2). The innermost condenser layer is electrically connected to the central tube / conductor (2) and the outermost layer is electrically connected to the fixing flange (3) through a test tap (11). The core is dried under heat and vacuum and then impregnated with superior grade of insulating oil. Porcelain insulators (4&5) on the upper and lower sides of the bushing, oil resistant high quality rubber gaskets & ‘O’ rings (6) are held together with the central tube by means of a set of powerful springs (7). The fixing flange (3) is provided with a test tap (11) for the measurement of Capacitance and Tan delta, air releasing screw (10) to release the air trapped in the transformer during topping up of oil or can be connected to Buchholz relay, name plate giving the product details, handle / eyebolt for lifting and space for ring type CT's on the oil end of the bushing. At the oil end, an epoxy coated stress shield or base plate (15) is provided to control the high stresses in oil inside the transformer. A detachable bottom arc shield is provided for bushing rated 245 kV and above. The intervening space between the core and the porcelain insulators is filled with specially treated mineral oil under vacuum. A Prismatic (upto 300kV) or magnetic (upto 400 kV) Oil sight glass (14) is provided on the expansion bowl (8). A top terminal (12) is provided to connect to the over head line. Arcing horns (16, 17) are provided on request. (Ref. Fig. 3). Test Tap: - (Refer Fig. 2) The test tap (11) is provided for the measurement of Capacitance, Tan delta and Insulation Resistance (IR) values of the bushing. It is connected with a copper lead to the last condenser foil of the core directly. During normal service this test tap is electrically connected to the mounting flange through test tap cover. The threaded test tap cover must be fixed properly (Fig 2a) before putting into service.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

ISSUE/ REVISION DATE

20/10/05

28/01/07

PTRM : 0708 Page 144 of 205

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 2.

PTRM : 0708 Page 145 of 205

PACKING AND STORAGE: Please refer to Fig. 4 To prevent physical damage to the bushings, generally only one bushing is packed in wooden packing case. At times, more than one bushing is also packed in the case of bushings of lower voltage rating. The bushing is placed in the packing case at an angle of 68 degrees to horizontal. Accessories like arcing horns, terminals etc. are also packed in the same packing case. The bushing may be stored either in the same case or removed and placed vertically or placed at an angle of 6-8 degrees from horizontal. This is to ensure the core remains immersed in oil. When the packed bushings are stored outdoors, they should be kept horizontal and covered with tarpaulin for protection from rain and other atmospheric contaminants.

3.

HANDLING AND UNPACKING: Please refer to Fig. 5, 6 & 7 The unpacking should be done at the time of installation. During unpacking, mechanical stresses or jerks are to be avoided on the bushings. On receipt, carefully

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 146 of 205

open the top cover of the wooden case and inspect the bushings thoroughly for any transit damage. Ensure all the accessories are received in good condition and report, in case found to be missing. Note: Any damage or shortages should be reported immediately. Bushing should be handled only with mechanical lifting arrangements, such as the illustrated in Fig. 5. When bushings are taken out of the packing case, they must not be allowed to rest on the lower part of the bushing. The operation is best carried out two lifting gears and two ropes as shown in Fig. 6. One rope is slung around the lower end of the metallic flange and let directly to the hook of the first crane and the other passed around the shell, between two sheds and then led to the hook of the second crane. The bushing is raised sufficiently in the same inclination angle as in the packing case with hoists and then lowered at the flange end. When positioning the bushing upright (Fig. 7), care should be taken to avoid any shocks, jerks or scratch to the oil end porcelain and bottom stress shield. On no account the bushing should be balanced on rope, passed around the porcelain at it’s centre of gravity.

4.

CHECKS BEFORE INSTALLATION: i)

Mount the bushing vertically on a suitable stand and clean the surface thoroughly with a dry cloth, particularly the oil end. Inspect the bushing physically for any leakage or damage on the porcelains. The oil end and inner portion of the central tube should be further cleaned with transformer oil. Care should be taken to prevent scratching of the painted surface of the bottom stress shield / base plate.

ii)

Check oil level of the bushing in vertical position. The oil level should be such that the oil level is clearly visible through the oil sight glass provided on the bushing. The oil level is filled in the factory upto the mid point of the sight glass, which is considered to be the normal oil level. The oil in the prismatic type sight glass can be identified by the highlighting of the red colour reflector at any position mounted from vertical upto a maximum of 30 degrees.

iii)

Ensure the top terminal is tightened firmly with its gasket provided to avoid water / moisture entry into the transformer.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

iv)

PTRM : 0708 Page 147 of 205

Measure and record the IR values of the bushing with a 2.5 kV meggar. The recommended values are:



4000 Meg ohms (Min) between oil end terminal or top and test tap.



1500 Meg ohms (Min) between test tap and flange with 1 kV meggar. The IR values may vary due to the atmospheric condition (humidity), surface cleanliness of the porcelains, dryness of test tap etc. In such cases, preheating of porcelains, terminals test tap etc., with hot air is recommended. This is only an indicative test, however, the healthiness of the bushings can be known only after measurement of Tan delta & capacitance values. v) Capacitance and Tan delta values of the bushing should be measured between the top terminal and test tap at 2 kV to 10 kV (Maximum). The measurement should be preferably carried out indoors with RH not exceeding 60% and at ambient temperature, with the facilities and procedure as described as described below:



Schering Bridge



Standard loss free capacitor



High voltage supply



Necessary screened connecting leads. Place the bushing vertically on suitable stand. Remove the threaded test tap cover. Insert a plug / clip into the central stud of the test tap and connect to the Schering Bridge through a screened cable. The flange body should be grounded. Connect the high voltage supply to the top terminal. Measure the capacitance & tan delta value of bushing upto a maximum of 10 kV. Note:



The voltage applied on the bushing should be limited to 10 kV, when the bottom end is not immersed in oil. Utmost care should be taken to avoid any contact with the bushing during testing as this may result in fatal injury to the personnel.



The test tap should be dry, free from any moisture condensation and dirt deposition. The threaded test tap cover should be fixed back to the test tap, immediately after the test.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 148 of 205

Factory test values of tan delta and capacitance are indicated in the test report of individual bushing at working voltages. However, site values may vary, as they do not resemble factory test conditions. The site values recorded at the time of commissioning should be taken as the reference values for comparison with future measurements. The bushing can be commissioned, if tan delta value measured is less than or equal to 0.007, and capacitance value as per the factory test value with maximum variation of 10%. If higher values are obtained, please contact ALSTOM, Customer Service Department giving full details of testing arrangement, for further advice. Note: The bushing should be kept vertical or mounted on transformer for a minimum period of 24 hours before application of voltage.

5.

INSTALLATION: Please refer to Fig. 8 The bushing is suitable for installation for a maximum angle of 30 degrees from vertical. During the lowering of the bushing into the transformer, extreme care should be taken to prevent the lower porcelain hitting the wall of the tank. The bushing should be so mounted on the transformer that the oil sight glass is visible from the ground level. Ensure the visibility of the oil level to the naked eye. Maximum stress experienced by the bushing is at the bottom stress shield during testing. Hence sufficient care should be taken to avoid any flashover from the stress shield to the wall of the turret. The flashover voltage depends on the clearance maintained in oil between the stress shield and turret, oil

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 149 of 205

quality, surface smoothness, presence of barriers, shape of the stress shield and turret etc. The recommended size of the turret to be maintained for various voltage class of bushings is given in the manufacturer’s booklet / respective drawings. BUSHING WITH DRAW LEAD CONNECTION: Please refer to Fig. 9. Each bushing is supplied with a top terminal (12), cable bolt (9), cable bolt pin and a gasket placed separately in the packing case. Drill a hole of suitable diameter based on the size of the flexible transformer cable at the bottom end of the cable bolt and braze the cable into it. Insert an M8 bolt at the upper end of the cable bolt and tie a wire or a fish cord on to it. Clean the gasket seating surface on top face of the transformer and place the gasket in position. Lift the bushing above the transformer turret and clean the bottom end of the bushing. Lower the bushing slowly into the transformer, simultaneously pull the transformer cable brazed with cable bolt through the central tube with the help of the fish cord. Secure the cable bolt to the central tube with the cable bolt pin. Remove the fish cord. Bolt the bushing into position taking care to correctly position the gasket joint. Ensure the threads on the terminal and the cable bolt are clean. Tighten the terminal to the cable bolt ensuring full thread engagement for proper current transfer. Sometimes the cable bolt is supplied along with the brazed flexible lead upto the flange seat with a half connector at bottom end. In such cases the flexible lead from the transformer winding should be brazed to the other half connector and should be fastened with the draw lead connector of the bushing using bolts and nuts.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 150 of 205

BUSHING WITH DRAW-ROD CONNECTIONS: Please refer to Fig. 10 Bushings of higher current ratings are provided with draw rod type arrangement with a half overlap bolted joint at the flange seat. Remove the draw rod through the bushing tube or take it out from the packing case. Clean the outer surface and braze the transformer cable to the lower half connector. Clamp the upper and lower half connectors together with bolts and nuts. Follow the installation instructions as described for draw lead type of bushing. BUSHING WITH SOLID STEM: Refer to Fig.11 In solid stem type of bushings, the central conductor forms the current carrying part. Mount the bushing on the turret and connections should be made to the top and bottom terminals individually. The transformer cable termination should be connected to the bottom terminal with bolts & nuts, through the viewing port of the transformer. The top terminal should be fixed directly to the central conductor.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

6.

PTRM : 0708 Page 151 of 205

CHECKS AFTER INSTALLATION: i) After installation, clean the bushing thoroughly with a dry cloth and carry out physical inspection for any damage on the porcelain / leakage that might have occurred during installation. ii) Check the oil level of the bushing. iii) Ensure the top terminal is fixed tightly with the gasket provided to avoid entry of moisture in to the transformer. iv) Measure and record the capacitance and tan delta values of the bushing. Here again the values may differ from the previous ones. Note:



The threaded test tap cover should be fixed back to the test tap immediately after the test.



The bushing should be kept vertical mounted on the transformer for a minimum of 24 hours before energisation.

CAUTION: THE TEST TAP WILL ALWAYS BE EARTHED AS LONG AS THE THREADED CAP IS FIXED (Fig. 2a). HENCE THE CAP SHOULD NEVER BE KEPT OPEN.

7.

PERIODICAL CHECKS AND MAINTENANCE: As the bushing is a self contained unit, as such there is no specific maintenance to be carried out. However, a periodical check of the oil level and cleaning of the porcelain will normally suffice. In order to determine the healthiness of the bushing, measurement of capacitance and tan delta may be carried out during annual maintenance. These values are to be compared with the pre-commissioning test results. Tan delta value more than 0.007 and increase in capacitance by more than 10% or more, if observed, should immediately informed to ALSTOM for further advice.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

8.

PTRM : 0708 Page 152 of 205

UNMOUNTING AND PACKING: Whenever bushings are to be further transported, they have to be dismantled from the transformer and handled in the same way as explained under PACKING. The bushing should be repacked in the same wooden packing case or in a similar packing case suitable for transportation.

9.

SAFETY: Understanding the procedures and instructions are a must while handling bushings. Also, all applicable safety procedures such as regional or local safety rules and regulations must be followed. Safe working practices and good judgement are essential by the personnel while installing, testing, maintaining or disposing the bushings. CAUTION: FAILURE TO FOLLOW THE INSTRUCTIONS MIGHT RESULT IN FATAL INJURY TO PERSONNEL OR DAMAGES TO PROPERTY INCLUDING TRANSFORMER AND ITS ALLIED EQUIPMENT.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 153 of 205

SILICAGEL BREATHER

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 154 of 205

SILICAGEL DEHYDRATING BREATHER FOR TRANSFORMER A dehydrating breather is used to dry the air that enters a transformer as the volume of oil decreases because of fall in temperature. Air entering the breather is first drawn through an oil seal and passes upwards through the silicagel crystals to the connecting pipe at the top. During this upward passage of air, any moisture present is absorbed by the dry silicagel. The oil seal ensures that the gel absorbs moisture only when the transformer is breathing. INSTALLATION The breather is usually detached from the tank and shipped separately; the silicagel charge is shipped in at the top with a plug. To install, it is necessary to: 1. Remove top cover by unscrewing cap nut and fill with silicagel. 2. Remove the plug. 3. Pipe up to the tank or conservator. 4. Fill the oil cup with transformer oil to the indicated level.

MAINTENANCE Inspect the breather on monthly basis; more frequently, if found necessary by experience (eg. highly humid atmosphere). When the breather is first installed, the crystals have a blue tint, and after a period of operation, the colour of the tinted crystals gradually changes to pink; this is an indication that the silicagel is becoming saturated and losing its absorbent properties. When there is a preponderance of pink crystals the geI should be changed or reactivated. Silicagel may be reactivated by heating in a shallow pan at a temperature of 150° C to 200° C for two to three hours when the crystals should have regained their original blue tint. Before filling the container with silicagel, clean and dry all parts of the breather. Verify that the oil Level in the oil cup is correct when reassembling. Ensure that the breather is not choked and is free for passage of air.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 155 of 205

SECTIONAL VIEW OF BREATHER

TYPE 1

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 156 of 205

SILICAGEL BREATHER

TYPE 2

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 157 of 205

OIL LEVEL INDICATOR

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 158 of 205

OIL LEVEL INDICATOR

SIDE VIEW

FRONT VIEW

PARTS LIST FOR FIG. 1 Sr. No. DESCRIPTION 1. 2. 3. 4. 5. 6.

MATL.

Float 50 p x 100 Terminal Box Cover for T. B. Dial Body with switch housing Mercury switch Nut for Switch Adj.

Brass Cast Al. Cast Al. Cast Al. Glass Brass

Sr. No. 7. 8. 9. 10. 11. 12.

DESCRIPTION

MATL.

Bolts 'B'-6 Nos.- M6 Base with Mtg. Holes Limit stoppers Gear with lever Float Arm 9.5 p tube Check Nut

M.S. Cast. Al. Brass Brass Brass Brass

Fig. 1 ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

ISSUE/ REVISION DATE

20/10/05

28/01/07

PTRM : 0708 Page 159 of 205

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 160 of 205

OIL LEVEL INDICATOR MODEL SO-HE-10 APPLICATION This model of indicator is manufactured considering Transformer application. It can also be used as Content Gauge on other tanks where level of liquid inside the tank is required to be indicated continuously on a dial.

CONSTRUCTION, WORKING & FEATURES A float is used as sensor of liquid level inside the conservator (tank). Swing of hinged float due to change in liquid level is utilised to indicate level on a calibrated dial and to operate a switch for external alarm unit. Use of magnetic coupling in the indicator achieves complete sealing off of liquid inside the conservator from surrounding atmosphere. This results in avoiding any leakage of costly oil and avoiding contamination of insulating oil due to seepage of surrounding air in the conservator. The glass mercury switch is nylon encapsulated to avoid breakage and spilling of mercury. Switch is accessible for servicing while indicator is mounted on the conservator without any necessity of draining the oil.

CALIBRATION The standard calibration of dial is Empty, 1/4, 1/2, 3/4, Full. Calibration of marks Empty & Full is done after leaving 65 mm from bottom and top of conservator to avoid striking of float to conservator wall. Different calibrations are done to suit customer's needs.

MOUNTING In fig. 2, indicator is shown mounted by keeping dial and mounting pad in vertical position. However, indicator can be mounted in titled position towards ground (max 30°) for easy viewing by fixing mounting pad at desired angle. The position of indicator on the conservator can be selected to suit site condition. Float mechanism passes through the hole in pad (see Fig. 2).

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 161 of 205

ALARM SWITCH & CONNECTIONS One mercury switch is provided for Low Level Alarm. The Normally Open switch closes when oil level drops to 10 mm above Empty level i.e. 75 mm from bottom of conservator. Leads from mercury switch are brought into a terminal box positioned at the bottom of indicator. (see Fig. 4B), A two-way terminal strip is provided which is accessible for connection after removing cover of terminal box. A hole with 3/4” B.S.P. is provided for cable gland. Wiring should be done as per Fig. 4B.

SPECIFICATIONS 1.

Operating Liquid

:

Transformer Oil to IS: 335

2.

Working Temperature

:

0 to 100° C of Oil

3.

Working Pressure

:

0 to 4 kg/cm²

4.

Environment

:

For Indoor & Outdoor use

5.

Size

:

See Fig. 2 & 3

6.

Weight

:

6.6 Kg. with Float & Float-arm

7.

Mounting Specifications

:

See Fig. 2 & 3

8.

Float Travel

:

Float moves in right angle plane to seating face (See Fig.2)

9.

Electrical witch

:

One SPST Mercury Switch

10.

Contact Rating

:

5 Amps 240 V.AC. 50 Hz. 1.2 Amps 240 V.DC.

11.

Switch Setting

:

Normally Open Closes when oil level drops to Empty level. Switch opens automatically when oil level rises.

12.

Dial Size

:

250 mm dia.

13.

Dial Position

:

Vertical or Inclined

14.

Conservator dia

:

Available for use in range of 600 to 1500 mm dia.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 162 of 205

PRESSURE RELIEF VALVE

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 163 of 205

GLOSSARY OF TERMS PRV : Pressure Relief Valve Tank : Tank in which transformer winding & oil etc. are housed. Figures : Figures in brackets in write-up refer to part list of Drg. CD-601-R-3

1.

APPLICATION: This PRV is designed to be used on Power Transformer. When pressure in the tank rises above predetermined safe limit this valve operates and performs following functions. λ Allows the pressure to drop by instantaneously opening a port of about 150 mm diameter. λ Gives visual indication of valve operation by rising a flag. λ Operates a micro switch. This switch has 1 NO and 1 NC contacts (Four terminals). Hence switch can be effectively used in control circuit.

2.

SPECIFlCATIONS: See Drg. No. CS-601-R-3.

3.

TESTS: Tests are carried out as per test certificate attached to this leaflet.

4.

CONSTRUCTION & WORKING: (Refer Drg. CS-601-R-3) This PRV has an integral flange with six holes for mounting. The valve can be mounted vertically or horizontally on the tank. The PRV has got a port of about 150 mm dia. This port is sealed by a stainless steel diaphragm. The diaphragm rests on an 'O' ring (3) and is kept pressed by two heavy-duty springs, thereby keeping the port closed. The other side of the diaphragm is exposed to tank pressure. Whenever the pressure in the tank rises due to any reason, the same pressure acts on the diaphragm from inside. When pressure rises above predetermined safe limit the diaphragm gets lifted from its seat. This lifting is instantaneous and allows vapours, gases or liquid to come out of tank depending upon the position of valve on tank.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 164 of 205

The diaphragm restores its position as soon as pressure in the tank drops below set limit. The lift of the diaphragm is utilised to operate flag ( 10) and micro switch ( 11) with the help of rod (8). The flag and switch remain operated until they are reset manually.

5.

CHECK FOR VALVE: The PRV is generally packed in a corrugated box. The method of packing may vary. The PRV should be checked as follows before it is installed. Remove the valve from packing and keep it on a table. Remove all packing, strings fixed to valve. Check that no parts are damaged in transit. If any damage is found refer to faults and remedies in this leaflet. Remove the cover of switch box (13). By lifting the operating rod (8) check operations of switch as stated in Test 4 in test certificate with the help of an AVO meter. After checking, reset the switch by pressing knob (12). Replace the cover. The flag operation should be checked manually by lifting the rod (8) as per test 1.2 in the test certificate. Reset the flag by turning it down. Handling of flag should be done very carefully. The product label indicates the suitability of valve for synthetic liquid or for transformer oil. A proper valve should be selected. Normally Red product label is used for synthetic liquid and Black label for transformer oil. A Gasket (2) for base is supplied with each valve. It should be noted for general guidance that Red gasket (silicone) is provided for synthetic liquid and Black for transformer oil. Each PRV is tested at our works as per test certificate. However, customer is advised to check the valve by stimulating pressure conditions before it is actually installed on Transformer. While conducting such Tests at your end care should be taken that small Particles do not have a passage through the port opening. Such particles are likely to be trapped between diaphragm and gasket, which will affect functioning of Valve.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

ISSUE/ REVISION DATE

20/10/05

28/01/07

PTRM : 0708 Page 165 of 205

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

6.

PTRM : 0708 Page 166 of 205

CHECK FOR INSTALLATION: The following checks should be observed before installation of PRV on Transformer. Check that the orientation of pad is properly done. Check that the proper bolts, M12x40 with thick washers are taken for installation. Bolts other than this size should not be used. Any other gasket than supplied with the valve should not be used. Provide cable gland of "3/4" BS conduit with suitable bush for cable to be used. After all above check the PRV is ready for installation.

7.

INSTALLATION Each valve should be cleaned from inside (tank side) with compressed air jet. All particles should be removed from tank side. While cleaning, care should be taken that the jet does not attack the switch and the flag mechanism. The PRV should be installed considering the following aspects. The indicating flag (10) is easily seen from distance, The valve is accessible for manual resetting and for routine manual checking. While installing remove dirt and clean the mounting surface, remove all traces of oil, grease. The rubber gasket supplied with the valve should be properly cleaned & be located properly in the recess carefully. All the bolts should be tightened evenly so that equal pressure is exerted on gasket and base. Connect control circuits to terminal plate provided in the switch box through cable gland (14). As per wiring diagram (ref. fig. 1 drg. CS-601-R-3), check the operation of flag and switch by lifting operating rod (8) and confirm that both controls operate as required. The PRV can be put to service.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 8.

PTRM : 0708 Page 167 of 205

FAULTS AND REMEDIES: The valve has rugged construction and it is not likely to get damaged easily. However, the indicating flag (10) is delicate item. Hence if is likely to get damage. The indicating flag can be replaced by either making similar flag at your end or by asking for replacement. You can repair with the help of good instrument mechanic minor faults occurring in working of switch or flag mechanisms. However for breakage or damage to major parts like diaphragm, base, valve cover. Send the PRV back to us. In any case the Sr. No. of PRV must be informed so that sending correct replacement is possible. This will also save lot of communication.

9.

GENERAL NOTES: Store the valve on its base duly packed in polythene bag to ensure that dirt or other solid particles do not enter the valve port from tank side. Do not remove the protection cover on flag box and switch box when it is stored. Keep the flat gasket (2) duly tied to the valve. Remove it only when it is to be installed. This gasket should be kept dry. After installation of valve on transformer, test periodically the functioning of switch operation and flag operation by lifting the operating rod manually. This will ensure the switch operation and flag operation when valve opens due to rise in pressure inside the tank. It is not possible to change the operating pressure at site. The valve gaskets are of entirely different nature for synthetic liquid and transformer oil. Hence use proper valve for liquid as described on product label.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 168 of 205

EXHAUST FAN

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 169 of 205

COOLING FANS GENERAL Exhaust type cooling fans used on transformers are designed to operate outdoors in all weather conditions. Generally the following sizes of fans are used.

SIZE

(mm)

450

610

610

915

915

SPEED

(r.p.m.)

1400

700

900

550

700

INPUT

(watts)

410

240

500

700

1200

PHASE

3

3

3

3

3

VOLTAGE (volts) FREQUENCY (Hz)

415 50

415 50

415 50

415 50

415 50

CURRENT

0.9

0.5

0.9

1.5

2.5

(amps.)

The fans are designed to operate outdoors in all weather conditions.

MOTORS The fans are powered by totally enclosed, squirrel cage induction motors. The motors are adequately rated to give reliable service for many years.

IMPELLER The impeller is designed to give maximum volume at minimum noise level with minimum power consumption. For reducing vibrations, special shoes made of rubber are provided at fixing points of fan lugs.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 170 of 205

MOUNTING 1.

The arm is secured by the resilient mounting caps, which are placed over the rubber sockets and secured to the diaphragm with 8 screws, nuts and washers provided. The lock washers should be fitted under the heads of the screws.

2.

Rubber sockets fitted to arms. To be fitted so that flat side will come in contact with the diaphragm.

3.

Arms to be secured to motor by the 4 screws in motor carton. NOTE: Lock washers are supplied and should be fitted.

4.

ISSUE/ REVISION DATE

Setscrew in blade should engage in dimple nearest the end of the shaft. After blade is fitted, see that split pin 5 is replaced in end of shaft.

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 171 of 205

CONSTRUCTIONAL DETAILS

No. 1 2 3 4 5 6 7 8 9 10 11 12 13

ISSUE/ REVISION DATE

PART NAME TERMINAL BLOCK BALL BEARING STATOR WINDING EARTH SCREW ROTOR STAMPING STATOR STAMPING RESILIENT CAP RUBBER SLEEVE BACK COVER FIXING SCREW BACK COVER FAN FIXING BOLT WING CH. HD. SCREW

20/10/05

28/01/07

No. 14 15 16 17 18 19 20 21 22 23 24 25

PART NAME WING FIXING BOLT SPLIT PIN SHAFT HUB FIXING BOLT HUB BALL BEARING LUBRICATOR SCREW MOUNTING ARM MOTOR FIXING BOLT DIE CAST AL. ROTOR CH. HD. SCREW DIAPHRAGM

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 172 of 205

FLOW INDICATORS

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 173 of 205

FLOW INDICATORS FUNCTION Flow indicators included in this catalogue are mainly designed as a safety device looking to the need of an electrical signal on failure of forced circulation of liquid in pipeline. They perform following functions: 1.

Indicate the rate of full flow in proper direction in specified pipe.

2.

Operate one or two mercury switches when rate of flow drops near to 70% of specified full flow. These switches can be used to initiate precautionary systems or safety devices.

APPLICATION Consider the case of furnace transformer in which one Flow Indicator can be mounted on suitable member of oil circulating pipe and one on water circulating pipe of heat exchanger. The pointer of respective Flow Indictor will indicate whether desired rate of flow is maintained or not and switch will operate if the flow drops near to 70% to initiate precautionary system. For similar purpose it can be used on liquid circulating pipes in chemical processes, heavy-duty bearings, compressors, etc.

MOUNTING To introduce these Flow Indicators in a pipe line a `T-Mounting’ is necessary. In this catalogue we have tabulated dimensions of 'T-Mounting' for range of size from 40 mm (1.5") to 250 mm (10") N.B. Pipes. But customer can always specify if his requirement is different than the tables on page 8.

CONSTRUCTION & WORKING A suspended vane is used as sensor. Its surface is kept at right angle to direction of flow. When liquid starts flowing through pipe, the vane gets deflected along with vane shaft. This deflection is used to indicate flow inside the pipe and to operate mercury switch or switches as follows: A pair of permanent magnets is used as gland-less coupling. The driving magnet is connected with vane, therefore it rotates with vane and remains in liquid. The follower magnet, separated by a non-magnetic wall, is kept outside in air and acquires position corresponding to driving magnet. The follower magnet carries a

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 174 of 205

pointer and a cam. The pointer is set to read the specified rate of full flow and the cam is set to operate one or two mercury switches when flow drops near to 70%. A return spring is used which acts in the opposite direction of flow. Hence any steady position of pointer is the result of equilibrium of force due to impinging liquid on vane, spring tension & weight of vane. The pointer does not remain steady for unsteady flows. The size and shape of vane and tension on return spring is adjusted to suit specified full flow. The vane occupies very small area out of full cross section of pipe at NO-FLOW position. At full flow it becomes almost parallel to flow. Hence there is practically no head-loss across Flow Indicator.

DIAL MARKING The spread of flow indicating portion of dial is only about 70°. Hence it is not possible to print more markings. Usually PUMP ON-PUMP OFF or FULL FLOW-NO FLOW type of limit markings is printed. Intermediate markings such as ALARM. TRIP is also printed if required. Besides, specifications such as value of full flow, liquid, pipe size and direction of flow are also printed. The background of dial is white. Direction indicating arrow is in red colour and all other markings in black colour.

SWITCHES One or two mercury switches of SPST type are provided. The contact position can be set to No or NC at full flow. If required, switch can be changed from NO to NC or vice versa at site. In case of single switch, it is set to operate near 70% when flow is falling. In case of two switches, both are mounted on same plate. Hence both operate at same rate of flow. But in order to satisfy design requirements, one switch can be set to operate near 80% and the other near 70% or one near 70% and the other near 60%. It is not possible to set a switch to operate at lower value than 60%. Even when both switches are set to operate at lower value than 60%. Even when both switches are set to operate at same rate of flow, some switching differentiate is observed due to use of mercury as switching element, We can modify setting suitably if switching requirements are clearly specified.

WIRING Leads from mercury switch/switches are brought into a terminal box positioned at the bottom of indicator. A two-way or four-way terminal strip is provided. Terminals are accessible for wiring after removing cover. A hole with conduit threads is ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 175 of 205

provided for fixing cable gland to box. Terminals are marked. Wiring should be done as per respective wiring diagrams.

SETTING Full Flow- Each indicator is set in water-flowing condition. Pipe size, pipe position, direction of flow is maintained. By adjusting a valve in pipeline, the specified rate of full flow is established, then the pointer is set to read the full flow mark. This method of setting gives very accurate results as it is based on equilibrium of vane at full flow. In case of liquids other than water, proportional rate of flow of water is maintained for setting. Switch - After setting of pointer at full flow, switches are set in the sequence ordered by customer. Flow is reduced to check operation of switch & increased to check automatic resetting. The rate of flow at which switching occurs is approximate. The switch position is kept adjustable to compensate difference in pipe gradient at site.

TESTING Static Pressure: At 7 kg/cm². Flow: Indicator is mounted on pipe. Water is allowed to flow in specified direction. Rate of flow is checked when pointer reads full flow. For Liquids other than water proportional rate of flow of water is checked. Switch: Switch operation is checked by reducing and increasing flow in pipeline. Contact rating: Switches are tested in laboratory at 5A.24OV.AC Dielectric strength: Live terminals are checked at 2 kV with body. A test Certificate is provided with each instrument.

DESIGN FEATURES 1.

Switch contacts are not affected by dust, humidity or corrosive atmosphere.

2.

Switches can be serviced without need of stopping flow.

3.

Causes negligible head-loss.

4.

Low maintenance cost.

5.

Robust construction & trouble free service.

6.

Does not get damaged due to excess flow or reverse flow.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

Fig. 1

PTRM : 0708 Page 176 of 205

SCHEMATIC Item Description 1 2 3 4 5 6 7 8 9 10 -

Fig. 2

Pointer & Dial Mercury Switch Switch Operating Cam Return Spring Vane Shaft Vane Main Pipe Driving Magnet Non-magnetic Wall Follower Magnet

WORKING POSITIONS Item Description 1 2 3 4 5

-

Main Pipe T - Mounting Connecting Flanges Flow Indicator Flange of indicator

Horizontal Pipe Vertical Pipe

NOTES: I.

Flow indicators are not interchangeable for different liquids, pipe dia., direction of flow or rate of full flow. Hence they should be ordered separately.

2.

The rate of full flow is not adjustable.

3.

The switch operation point is not adjustable.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 177 of 205

(Actual Supply may not be exactly same)

Fig. 3 Wiring Diagram For Series 4021.

Fig. 4

Dimension Drawings for Series 4021

Hardware for indicator (Supplied at extra cost) M 12 x 65 Bolts, Nuts - Nos. Washer & Suitable gasket.

Accessories (Supplied at extra cost if agreed) T-Mounting, Weldable connection, Flanges, hardware.

Part List No. Description 1 2 3 4 5 6 7 8 9 10

– – – – – – – – – –

Cover for terminal box Base with mounting holes Vane shaft Vane Product label Cable entry Terminals Mercury switch Nut for adjusting switch Cover for switch box

Weight - 3.8 kg.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 178 of 205

Flow Indicators Series 4021 & 4022 It may noted that mounting specifications, flow sensing mechanism, vane orientation and size of dial is same in both series. Basic difference between two series is that in Series 4021 only one mercury switch is provided. Whereas in Series 4022 two mercury switches are provided. Proportionately, number of terminals, size of switchbox and size of terminal box differ, After suitable series is selected, requirement should be specified as per 'How to Order' column on Page 3 of this catalogue. Because each indicator is set to suit requirement specified by customer. Common specifications of Series 4021 & 4022 working: Principal of working, switch operation and other details as explained on page 2 & 3 of this catalogue.

Operating specifications (in ranges) Liquid Pipe Switch

— — —

Environment Working temperature Working pressure

— — —

Water, oils 37 to 250 NB (1.5" to 10”) One or two SPST mercury switches depending on series. Indoor or Outdoor 0° to 100° C of liquid in pipe 0 to 4 Kg/cm²

Material of Construction Wetted Parts Vane shaft, return spring St. Steel Vane, spring housing, screws Brass Base Aluminium (G. M. on Order) Magnet Alnico. Note: All Brass Parts chrome plated and Aluminium Parts anodised. Other Parts Dial Body, switch housing, terminal box, covers Aluminium Dial shield Tough glass Terminals Brass Mercury switch Hg in hard glass

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 179 of 205

Fig. 5 Details of vane orientation common to Series 4021 & 4022

Details of symbols used in Fig. 5 Direction of flow liquid in pipe as seen from dial side of indicator. Force due to return impinging liquid Force due to return spring Vane at no-flow Vane at full-flow Pipe Fig. 5 above shows vane positions at no-flow as seen from dial side of indictor. Indicators are set for any one direction out of four illustrated in Fig. 5. T figure also shows direction of forces acting on vane due to impinging liquid and return spring (gravitational force not shown).

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 180 of 205

Fig. 6 Wiring Diagram For Series 4022

Fig. 7 Dimension Drawings For Series 4022 Hardware for indicator (Supplied at extra cost) M 12 x 65 Bolts, Nuts - Nos. Washer & Suitable gasket.

Accessories (Supplied at extra cost if agreed) T-Mounting, Weldable connection, flanges, hardware.

Part List No. Description 1 2 3 4 5 6 7 8 9 10

– – – – – – – – – –

Cover for terminal box Base with mounting holes Vane shaft Vane Product label Cable entry Terminals Mercury switch Nut for adjusting switch Cover for switch box

Weight - 4.0 kg.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 181 of 205

(Actual Supply may not be exactly same)

Fig. 8

Wiring Diagram For Series 4031

Fig. 9

Dimension Drawings For Series 4031

Hardware for indicator (Supplied at extra cost) M 12 x 65 Bolts, Nuts - Nos. Washer & Suitable gasket.

Accessories (Supplied at extra cost if agreed) T-Mounting, Weldable connection, flanges, hardware.

Part List No. Description 1 2 3 4 5 6 7 8 9 10

– – – – – – – – – –

Cover for terminal box Base with mounting holes Vane shaft Vane Product label Cable entry Terminals Mercury switch Nut for adjusting switch Cover for switch box

Weight - 4.3 kg.

Flow Indicators Series 4031 & 4032 ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 182 of 205

It may noted that mounting specifications, flow sensing mechanism, vane orientation and size of dial is same in both series. Basic difference between two series is that in Series 4021 only one mercury switch is provided. Whereas in Series 4022 two mercury switches are provided. Proportionately, number of terminals, size of switchbox and size of terminal box differ, After suitable series is selected, requirement should be specified as per 'How to Order' column on Page 3 of this catalogue. Because each indicator is set to suit requirement specified by customer. Common specifications of Series 4031 & 4032 working: Principal of working, switch operation and other details as explained on page 2 & 3 of this catalogue.

Operating specifications (in ranges) Liquid Pipe Switch

— — —

Environment Working temperature Working pressure

— — —

Water, oils 37 to 250 NB ( 6" to 10" ) One or two SPST mercury switches depending on series. Indoor or Outdoor 0° to 100° C of liquid in pipe 0 to 4 kg/cm²

Material of Construction Wetted Parts Vane shaft, return spring St. Steel Vane, spring housing, screws Brass Base Aluminium (G. M. on Order) Magnet Alnico. Note : All Brass Parts chrome plated and Aluminium Parts anodised. Other Parts Dial Body, switch housing, terminal box, covers Aluminium Dial shield Tough glass Terminals Brass Mercury switch Hg in hard glass

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 183 of 205

Fig. 10 Details of vane orientation common to Series 4031 & 4032

Details of symbols used in Fig. 10 Direction of flow liquid in pipe as seen from dial side of indicator. Force due to return impinging liquid Force due to return spring Vane at no-flow Vane at full-flow Pipe

Fig. 10 above shows vane positions at no-flow as seen from dial side of indictor. Indicators are set for any one direction out of four illustrated in Fig. 5. T figure also shows direction of forces acting on vane due to impinging liquid and return spring (gravitational force not shown).

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 184 of 205

(Actual Supply may not be exactly same)

Fig. 11

Wiring Diagram For Series 4032

Fig. 12 Dimension Drawings For Series 4032 Hardware for indicator (Supplied at extra cost) M 12 x 65 Bolts, Nuts - Nos. Washer & Suitable gasket.

Accessories (Supplied at extra cost if agreed) T-Mounting, Weldable connection, flanges, hardware.

Part List No. Description 1 2 3 4 5 6 7 8 9 10

– – – – – – – – – –

Cover for terminal box Base with mounting holes Vane shaft Vane Product label Cable entry Terminals Mercury switch Nut for adjusting switch Cover for switch box

Weight - 4.8 kg.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 185 of 205

TRANSFORMER OIL PUMP

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 186 of 205

IN LINE TRANSFORMER OIL PUMP INSTALLATION, OPERATION & MAINTENANCE INSTRUCTIONS GENERAL CONSTRUCTION PUMP The pump set is a single stage axial flow gland-less type, integral with the drive motor. It has been specifically designed for forced circulation of oil through the cooling system of large transformer & allows thermo syphonic flow. It is designed for flange mounting directly to the pipe circuit of transformers in either horizontal or vertical position. All the moving parts are completely enclosed and gasket thus permitting open air installation, without any need for protective cover. It is compact in design. The Nameplate gives details of pump and motor output along with respective connecting pipe size. MOTOR The motor is of squirrel cage induction type suitable for 3 PHASE A.C. Power supply. It is coaxial with the pump and is designed to operate in hot transformer oil. The bearings are lubricated by transformer oil. PRECAUTIONS 1.

Store the unit in clean and dry place.

2.

Do not remove the M. S. end covers till the pump set is to be installed in pipe circuit. These are meant to protect the internal components against dirt and dust during transit and storage.

3.

It is important that all pipe work must be supported independently so that it imposes no under strain in bending or torsion on the pump flanges.

4.

The bearings are lubricated by the transformer oil and hence the pump should not run dry, to avoid damage to bearings.

5.

Keep the entire pipe circuit perfectly clean and free from moisture and foreign material.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 187 of 205

6.

Ensure that the electrical supply available is suitable for data given on the pump rating plate.

7.

Care should be taken that the valves are in the 'open' position, when the pump set is operated, because the pump works correctly only when all valves are fully opened. The oil filled pump will produce Pressure even with the valves closed, but there is no circulation, there will be oil churning inside the pump set and the pump motor might also get overheated.

INSTALLATION Before mounting on pipeline check the following: 1.

Remove the terminal box cover (8), and check the insulation resistance of the set with a meggar to ensure minimum resistance of 10 meg-ohms.

2.

Remove end covers and check for free rotation of the rotor. Ensure that Impeller (5) and locking screw (19) with washer are in their proper position.

3.

Connect the supply terminals and ensure rotation of impeller as per 'Arrow Mark' on the Impeller Housing i.e. anti-clockwise rotation when looking through the impeller housing opening.

NOTE: In case of wrong direction of rotation of impeller, there will be no discharge. OPERATION After installation on the pipe circuit, start filling the system with clean transformer oil until it completely fills the pump unit, Release all air by the air vent plug initial continuous air free oil seeps out. It is important that no air is trapped in the pump. It is always a good practice to allow the pump to run for about 30 minutes before energising the transformer, to ensure that any air not removed by venting has been pumped out. MAINTENANCE Check periodically the behaviour regarding leakage, vibration, noise, and current/power consumption of the pump set. In case the pump is to be removed, allow the unit to cool and drain the oil completely from the set and replace the end covers. Store as prior installation. Dismantling of Pump and Motor may be carried out as detailed on Page 201. TROUBLE SHOOTING Trouble

Checks

1) Reduced or No delivery

:

a) Casing Suction Pipe not filled with liquid b) Discharge head too high. c) Wrong direction of rotation. d) Air not vented out.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

2) Low Pressure

:

PTRM : 0708 Page 188 of 205

a) Wrong direction of rotation. b) No oil in the pump.

3) More Power Consumption

:

a) Shaft bent. b) No free movement of rotating element.

4) Pump is noisy

:

a) Hydraulic Noise: Cavitation, wrong direction of rotation b) Mechanical Noise : Bearing worn-out.

5) Motor Does not Start

:

a) Supply failure. b) Defective Phase. c) Loose Contacts. d) Rotor Mechanically locked.

6) Fuse blows out while starting :

a) Winding burnt. b) Interphase shorts.

DISMANTLING OF PUMP AND MOTOR Please refer Exploded view: 1. Remove Allen Cap Head Screw (19) and Washer (12). 2. Remove Impeller (5) by gently wrenching outwards with preferably a screw driver. 3. Remove Key (20) 4. Remove End shield fixing screws (21). 5. Lightly tap end shield (2) & (5) with a wooden/nylon mallet until it dismantles from bearing housing. 6. Remove Pre-loading washer (18). 7. Remove shaft with rotor (4). 8. Remove bearings (11) using a bearing puller. 9. In case required, the terminal arrangement, oil flow indicator (7) and plugs (13) may be dismantled in the same order as shown. For re-assembly follow reverse procedure.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 189 of 205

EXPLODED VIEW OF INLINE OIL PUMP

No.

DESCRIPTION

QTY. No.

DESCRIPTION

QTY. No.

DESCRIPTION

QTY.

1

STATOR CASE WITH WINDING

1

12

IMPELLER WASHER

1

23

LOCK WASHER

16

2

ENDSHIELD (ODE)

1

13

AIR VENT PLUG & DRAIN PLUG

2

24

ENDSHIELD FIXING NUT

16

3

ENDSHIELD (DE)

1

14

AIR VENT & DRAIN PLUG WASHE

2

25

TERMINAL BOARD FIXING SCREW

4

4

SHAFT WITH ROTOR

1

15

TERMINAL BOX GASKET

2

26

TERMINAL BOX FIXING SCREW

4

5

I MPELLER

1

16

TERMINAL COVER GASKET

1

27

TERMINAL COVER FIXING SCREW

4

6

TERMINAL BOX

1

17

OIL FLOW INDICATOR WASHER

1

28

PLAIN WASHER

4

7

OIL FLOW INDICATOR

1

18

PRE LOADING WASHER

1

29

NUT FOR TERMINAL STUD

6

8

TERMINAL COVER

1

19

HEX SOCKET HEAD CAP SCREW

1

30

LOCK WASHER

6

9

TERMINAL BOARD

1

20

PARALLEL KEY (OER)

1

31

PLAIN WASHER

12

10

SQUARE RING

1

21

ENDSHIELD FIXING SCREW

16

11

BALL BEARING SKF 6306

1

22

PLAIN WASHER

32

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 190 of 205

CONSTRUCTIONAL FEATURES

TYPE OF PUMP

P

D

T

L

E

A

B

M

S

Wt. kg.

IL - 5A

345 200

25

502

380

240

270

295

23

65.0

IL - 3A

285

20

425

305

210

240

240

23

41.0

ISSUE/ REVISION DATE

20/10/05

150

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 191 of 205

RADIAL FLOW (CENTRIFUGAL) OIL PUMPS The pump set is a single stage radial flow gland-less type, integral with a squirrel cage type induction motor suitable for three phase AC Power supply. The pump and motor are coaxial and suitable for operation in hot transformer oil. A well balanced impeller is co-axially mounted on the motor shaft through a key and positively locked in position. A cast iron volute casing mounted on the stator case through a spigot joint and sealing ring houses the impeller and imparts direction to the flow of oil as indicated by an arrow cast on it. Centrifugal type transformer oil pumps are used for circulating transformer oil through windings and heat exchanger of oil immersed transformer. These type of oil pumps are not suitable for natural cooling of transformer and hence these are used only in association with oil to water heat exchanger where natural cooling is not applicable. Normally oil to water heat exchangers are used on transformers where water is available in plenty like hydroelectric stations or on transformers used for furnace applications.

SPECIFICATIONS MOTOR

:

4.3 HP and 7.5 HP

STATOR

:

3 Phase, 50 Hz, Induction Type

ROTOR

:

Squirrel Cage Type

BEARING

:

Ball Type, Lubricated by transformer oil itself.

COOLING

:

By circulating transformer oil itself.

PERFORMANCE

:

To IS: 325-1996; 3 Phase Induction Motor

PUMPS CASING

: Cast Iron

IMPELLER

: Cast Aluminium/Bronzed keyed to the shaft

SEALING RINGS

: Neoprene rubber

FRAME

: Cast Iron totally enclosed integral part of the pump

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 192 of 205

PARTICULARS OF DUTY AND DIMENSIONS 4.3 HP

7.5 HP

DISCHARGE

(l.p.m.)

:

1190

1880

TOTAL HEAD

(m)

:

11.00

11.00

PIPE SIZE Inlet/Outlet

(mm)

:

100/100

150/150

Pump Ref.

Dis. Flange P1 d1

M1

S1

Suc. Flange LA1 N

P2

d2

M2

S2

Overall LA2 L

G

D

HB

Wt.(kg.) HC HD Net Gross

EL4.3R

220 100 180 18

18

4

220 100 180 18

18

460 220 125 290 195 360 71

111

EL7.5R

285 150 240 23

20

8

285 150 240 23

20

525 227 152 360 210 410 91

131

Fig.

Over all dimensions of 4.3 HP & 7.5 HP Centrifugal Pumps

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 193 of 205

FLEXIBLE SEPARATOR (AIR CELL)

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 194 of 205

FLEXIBLE SEPARATOR 1.

INTRODUCTION Flexible separator (Air Cell) is provided inside the conservator of power transformers for avoiding direct contact of air with the transformer oil. Air Cell provides a permanent, flexible and non porous barrier between the atmosphere and the transformer oil without affecting the operational function of the system. The basic construction of the separator is a highly resistant fabric coated externally to resist transformer oil and internally to Ozone and weather resistant. Flexible separators offer the following advantages :-

• Avoids contact between air and oil and consequently of condensation or oxidation inside the transformer.

• Protection against water vapour and gases. • Suppression of any gas bubble formation in oil. • Compensation of large volume changes. 2.

DESCRIPTION Flexible separator is fitted inside a cylindrical conservator. Oil being outside, the separator is in direct contact with atmosphere. This type of mounting makes it possible to compensate for the oil volume displacements due to temperature variations.

3.

CHARACTERISTICS OF MATERIAL Flexible separators are made from coated fabric consisting of :



Textile reinforcement i.e. highly resistant polyamide fabric.



External coating chemically resistant to transformer oils



Inner coating resistant to Ozone and all weather conditions.

Major characteristics of materials are listed below: Mass



1400 ± 140 g/m²

Coating



Poly acrylonitrile butadiene

Textile reinforcement



Polyamide

Breaking Strength before immersion in oil



> 300 daN / 5 cm.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

4.

PTRM : 0708 Page 195 of 205

INSTALLATION PROCEDURE 1 Connection to the inside of Air Cell 2 Connection to the inside of Conservator 3 Magnetic Oil Level Gauge

Mounting Of Air Cell And Oil Level Gauge In Conservator

Fig. 1

Details Of Fixing Air Cell

Details Of Hook On

On Conservator

On Conservator And Handle On Air Cell

Fig. 2

ISSUE/ REVISION DATE

20/10/05

Fig. 3

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 5.

PTRM : 0708 Page 196 of 205

FILLING PROCEDURE WITHOUT VACUUM IN CONSERVATOR • The conservator with Air Cell is pressure tested and despatched from the

factory at a slightly positive pressure. Confirm that there is no oil leakage.



Fix three numbers air release valves on the conservator.

• Keep air release valves open. Fix air filling adapter on breather pipe and inflate the air cell at an air pressure indicated on the INSTRUCTION PLATE affixed on the transformer and hold air pressure.

DO NOT APPLY EXCESS AIR PRESSURE AS IT MAY DAMAGE THE AIR CELL. • Open air release valves and start oil filling from the bottom of the conservator.

• Observe the air release valves and as soon as oil starts overflowing, close the air release valves one by one. Stop oil filling when all air release valves are closed.

• Remove the air filling adapter. • Continue oil filling and observe the Magnetic Oil Level Gauge (MOLG) • Stop the filling when the needle of MOLG shows the level corresponding to the ambient temperature at the time of filling.

• Fix silica gel breather.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 197 of 205

CAUTION: Do not open any of the air release valves after completion of oil filling. If air release valve is opened, air will enter and oil level will drop. The plain oil level gauge on the end cover of the conservator should indicate full oil level always. If air enters the conservator, it can be seen by a fall in the oil level in plain oil level gauge. The plain oil level gauge should be monitored on regular basis.

6. FILLING PROCEDURE UNDER VACUUM IN CONSERVATOR The conservator, with its separator, being set up and plugged in above the transformer, is connected to its oil filling reserve by a pipe in its lower part.

Proceed as follows: •

Create a vacuum in separator.



With the same source of vacuum, create a vacuum in the conservator.



Open the oil filling valve of the transformer.



Because of the vacuum in the conservator, the oil level rises automatically.



Stop the oil filling once the required volume in the conservator is attained.



While maintaining the conservator under vacuum, allow Dry Air or Nitrogen gas to enter into the internal part of the separator. Then, the separator inflates by itself, and takes all the free space due to the fact that the conservator was not completely full. In particular, during the operation, the oil is going to rise to the top of the conservator.



Inflate the separator at a maximum as shown in the INSTRUCTION PLATE.



Check on the vent-holes, and confirm that there is no more air in the conservator or, if necessary, adjust the level.

The above mentioned CAUTION regarding the opening of air release valve after completion of oil filling, remains valid for this case also. ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 198 of 205

THERMOSIPHON FILTER

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 199 of 205

THERMO SIPHON FILTER FOR

POWER TRANSFORMERS 1.

INTRODUCTION Thermosiphon filter is provided on large capacity, oil filled Power Transformers for keeping the moisture level of insulating oil at a very low level. At the time of initial erection and commissioning of transformer, most of the moisture present in the oil is removed by hot oil circulation. The moisture absorption of oil is eliminated by directing the air breathed in by the transformer during its operation through silica gel desiccant. Air cell in conservator avoids direct contact of oil with air and thereby eliminating the chance of moisture absorption. However, it is a well known fact that water is released to the oil from the paper insulation due to ageing process. Thermosiphon filter helps in removing this moisture from oil. When the transformer is on load, the thermosiphonic action of liquid causes circulation of oil through the filter. The adsorbent filled in the Thermosiphon filter adsorbs moisture and keeps the oil dry.

2.

CONSTRUCTION

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 200 of 205

Typical arrangement of the Thermosiphon filter is as shown in the figure. Thermosiphon filters are provided with isolating valves at top and bottom to enable its removal for maintenance purposes.

3.

MAINTENANCE Thermosiphon filters do not require any routine maintenance. Oil samples shall be tested periodically and the values of resistivity and tan delta shall be compared with the values given in the “Operation & Maintenance Manual”. If the results are within the limits, reactivation of the adsorbent needs to be done only as part of the annual maintenance. If there is a rapid deterioration in the values, reactivation of the adsorbent should be done immediately.

4.

MONITORING The periodicity of oil testing and acceptance criteria is explained in the Instruction Manual of the Transformer. However, the same is reproduced here for your ready reference. a) b) c)

5.

Periodicity of measurement(Resistivity & Tandelta) : Quarterly Resistivity at 90OC : ≥ 0.1x 1012 Ω cm O Tandelta at 90 C :≤1% (Ref. IS - 1866: 2000)

REGENERATION OF ADSORBANT Regeneration of adsorbent can be done by circulation of hot gas at a temperature of 180 to 250O C. To confirm proper regeneration, the dew point of the purged gas may be measured and it should be less than –70O C. For regeneration of adsorbent, dry nitrogen gas is preferred. A continuous stream of gas is to be maintained during heating and gas pressure is not important.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 201 of 205

OIL TO WATER HEAT EXCHANGER

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 202 of 205

DOUBLE TUBE HEAT EXCHANGER

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS

PTRM : 0708 Page 203 of 205

OPERATION AND MAINTENANCE INSTRUCTIONS FOR OIL TO WATER HEAT EXCHANGERS (SHELL & TUBE TYPE) 1.

INTRODUCTION: In transformer oil cooler, the hot oil from the transformer is passed through the shell, which comes in contact with the external surface of the tubes, which is constantly cooled by the incoming cooling water flowing inside the tubes. Heat transfer takes place due to temperature difference between the oil and cooling water flowing through tubes resulting in cooling of the oil.

2.

DESCRIPTION: The transformer oil cooler is a shell and tube type oil cooler. It is also known as lantern ring type oil cooler. The hot oil passes through the shell, and cooling water passes through tubes, tubes are secured to the tube sheet by expansion. Baffle plates have been provided to support the tube. The baffles are held in position by tie rod and spacers. Baffles have thermal significance in that the shell side fluid is made to flow to and fro across the bundle from one end of the exchanger to the other end. The flow induced vibration is avoided by proper spacing of the baffles. Separation of shell and tube side fluids at the floating head is obtained by means of packing rings (‘o’ rings) installed between outside of the floating tube sheet and recesses in the rear head flanges. The shell and tube fluids have their own packing rings (‘o’ rings), which are separated, by a lantern ring provided with weep holes for leak detection. Leakage at the packing will not cause mixing of the shell side and tube side fluids within the exchanger itself. Channel side has been provided with pass partition arrangement so as to have the flow of cooling water inside the tubes in each section. The inside surface of channel except tube sheet have been coated with epoxy paint to prevent corrosion of carbon steel material. Zinc anodes are provided to reduce the galvanic corrosion.

3.

HYDRO TESTING: The equipment shall be subjected to hot oil test on shell side and hydro test on tube side to a pressure of 1½ times of the design pressure to check for leaks. Before conducting hydraulic test for new unit or one that has been out of service for sometime or for unit that has been opened, carry out a thorough internal and external inspection to ensure: • •

ISSUE/ REVISION DATE

All foreign materials have been removed Pressure gauges have been correctly calibrated 20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS •

4.

PTRM : 0708 Page 204 of 205

Vent on high point of unit (air vent) if installed is left open

OPERATING INSTRUCTIONS: Inspect the transformer oil cooler and ensure that the external surfaces and channels are free of dirt and ensure the readiness of cooling water supply on the tube side.

5.

START UP PROCEDURE: The start up of the oil cooler in a system consists of putting into service various equipment in a definite logical operating sequence. ‹ Open the vent and drain valve on the channel side of the oil cooler. ‹ Establish cooling water flow through channel and tubes ‹ When water flows through the vent and drain close the same. ‹ Open the oil side vent & drain and adopt the same procedure as that of tube side ‹ Temperature of oil shall be raised gradually with specified flow rate.

6.

PERFORMANCE OF THE OIL COOLER. Use proper strainers on shell side and tube side. • • • •

7.

Do not operate the cooler beyond the specified working pressure indicated in the nameplate. Operate the cooler at the specified flow rate to obtain maximum efficiency. The oil should not have any contamination as the performance of cooler get reduced. Periodic cleaning of the cooler on shell side and tube side shall be carried out for better performance.

SHUT DOWN PROCEDURE: The oil flow should be completely stopped before stopping the water flow.

8.

CLEANING METHODS: •

The bundle assembly is taken out and the internal and external surface of the tubes are cleaned by smooth wire mesh or cleaning agent.



After cleaning, the bundle is inserted and the gasket and ‘o’ ring are replaced with new ones and the equipment is tested hydraulically before setting the unit under operation.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

ERECTION, COMMISSIONING, OPERATION AND MAINTENANCE MANUAL FOR POWER TRANSFORMERS 9.

PTRM : 0708 Page 205 of 205

PRESERVATION

9.1



When the transformer oil cooler is out of service, preservation by proper methods is essential to prevent corrosion.



It is recommended that during short duration of operational interruptions as a preventive measure against stand still corrosion, a continuous flow of cooling water through tubes is to be maintained. If this is not possible then it is necessary to clean the tubes to remove dirt, impurities etc. And fill with suitable clean water to retain in same condition.



In case of longer shut down, the shell side of the oil cooler is to be drained and rinsed with oil. Dry all internal surfaces of oil cooler by using hot air. Blank all open nozzles to avoid ingress of dust. Clean the tube side to remove dirt, impurities etc., and fill with suitable clean water and retain in that condition.

TYPES OF PRESERVATION PROCESS:

9.1.1 WET PRESERVATION: The wet preservation is used in case of short term shutdowns. In case of wet preservation of plants/systems or components, it is to be observed that the filling water is mixed with sufficient quantity of suitable corrosion inhibitors. The preservative fluid should be circulated once in a week and analysed periodically. The consumed chemicals are to be substituted. 9.1.2 DRY PRESERVATION: • •

The dry preservation is used in case of long term shut downs. In case dry preservation, it is important that the plants/systems or components are completely dried before passing nitrogen or dry air. The preservative air, which is to be blown through plants/systems or components to be maintained dry, shall be dust free, oil free and free from aggressive ingredients. The relative humidity of the out coming O



preservative air should be less than 20% with reference to 20 C. The effectiveness of the measure taken is to be checked at regular intervals.

P.S.: The above instructions are applicable for single tube Heat Exchangers.

ISSUE/ REVISION DATE

20/10/05

28/01/07

01/08/07

AREVA Confidential Information. Must not be disclosed, copied or used for Manufacturing, Tendering or for any other purpose without prior written permission.

.A

Easun - MR Tap changers (P) Ltd., Chennai, India

ON-LOAD TAP CHANGER TYPE M Operating Manual

---.,Ea .,-:su-n.,-·--;Mc;R;;-:;: Ta'"'p--;C,-h-,-an,-,~-,-er-,s "(J?""l' ILt"' d-. , 761"'2"12"'3"'2)',7M,..,.T"'.H".-;R:-:o-,-ad;-,"'li""ru__,n.,..in--,ra_vu_r,.., , C"'h,....e-,-nn,-,a.'· ".-:60"'2"""'02~4.

EMR

India Phone : 91 • 44 • 26390863 (lluntmg) , l'ax : 91 • 44 • 26390881 , e-mail : helpdesk @easunmr.com

On Load Tap Changer Type M Operating Manual

1. General 1.1 Operational principal of the on-load changer (fig.1) A tap-change operation begins with the tap selector preselecting the desired tap on the transformer winding.

The diverter switch transfers the current from the tap in service to the preselected tap. During this quick change-over, ohmic resistors are inserted in the circuit to ensure no-break transfer of the current.

2

On Load Tap Changer Type M Operating Manual

1.2 Designation of an-load tap changer models (fig.2) Every type of tap changer is available in a number of different models. These design vary according to: number at poles, max rated through current, insulation to ground, tap sector size, and basic circuit diagram. The designation incorporates all these characteristics and permits easy identification of the tap changer. The basic circuit diagram code in the model designation identifies: number of operating positions, number of mid-positions, and type of changeover selector.

ON-LOAD TAP CHANGER M

I

501 -

123 /

B-

10 19 1W

Type

Basic Circuit diagram

Number of Poles

Tap selector size

Max. rated through. current in amperes and additonal indication of model Highes voltage for equipment Um Insulation go ground

Example in Fig.2: On-load tap changer type M single-pole, max rated throughcurrent 500A, insulation to ground according to Um = 123 kV, tap selector size B, basic circuit diagram code 10 19 1 W meaning: 10 contacts, 19 operating positions, with one midposition, change-over selector used as reversing switch

BASIC CIRCUIT DIAGRAM 10

Pitch of tap selector contact circle

19

Max. number of service positions

1.3 Principal parts of the onload tap changer (fig. 3)

- the diverter switch compartment and

oil

without 10 12 14 16 18

10 12 14 16 18

with 09 11 13 15 17

W

Mid-positions 1 0 1 3

Change-over selector

The principal parts of the unload tap changer are - the tap changer nead

1

19 23 27 31 35

Change-over selector

coarse tap selector

Reversing switch

G

W

*) No designation without change-over selector

- the tap selector Diverter switch unit & Top drive unit on tap head are subject to inspection

Fig.2 Designation of Tap Changer model and basic circuit diagram

3

On Load Tap Changer Type M Operating Manual

Principal parts of the on-load tap changer

Principal parts of the on-load tap changer 13

Tap changer head gasket

14

Position Indicator

15

lnspection glass

16

Drive shaft for position Indicator

21 22

Tap changer head Cover bolt

23 24 25 26 27 28

Head cover gasket Tap changer head cover Upper gear unit with drive shaft 25a Pipe connection R for protective relay Pipe connection S for suction pipe Pipe connection Q for return pipe (with oil filter unit only)

29a 29b 29c

Bleeder valve of tap changer head cover Bleeder facility for transformer oil Bleeder screw for suction pipe

31

Diverter switch oil compartment

32

Bottom of oil compartment

33

Grading rings

34

Terminal of diverter switch oil compartment

35

Suction pipe

41 42 43 44 45

Tap selector support Tap selector gear Fine tap selector Change-over selector Tap selector terminal

51

Diverter switch unit

52

Support cylinder

53

Support plate

54

Fixing screw

55

Lifting lug

56

Transition resistors

Fig. 3 Centric Upper Gear Unit 4

On Load Tap Changer Type M Operating Manual 1.4 Inspection intervals IMPORTANT : We recommend inspection of the tap changer equipment at regular intervals to maintain a high level of operating reliability. In general, the inspection can be carried out within one day by EMR qualified and trained personnel provided it is well prepared and organized. We strongly recommend to have in-spections performed by our Technical Service. This Guarantees a professional performance including all the latest updating of specific components to the latest operation state. Inquire for spare parts when preparing an Inspection which shall not be carried out by E-MR personnel (please indicate tap changer number and number of operations). The number of tap change operations determining the Inspection intervals indicated in Table 1 are figures based on experience with use of usual oil qualities. Regardless of the number of operations we recommend inspection after 6 to 7 years of service, or after 4 years of service, if the tap changer operating voltage is > 220 kV. The tap selectors of our on-load tap changers are generally main-tenance-free. However, special care should be taken with special applications. This applies e.g. to industrial transformers where high numbers of tap change operations are to be expected. Here we recorr-mend to contact our Technical Service afterabout 1,000,000 operations. The divertor switch unit of the tap changer has to be replaced by a new one after about 800,000

operalion latest. If the number of operations per year Is 15,000 or higher, we recommended the use of our oil filter plant type 51 manufactured by our principal MR Germany.

Filtering of switching oil allows to extend the inspection and oil change intervals. Continuous filtering also increases the mechanical life of the diverter switch by

Standard values for tap changer oil testing according to CIGRE report 12-13 (1982) apply to Transformer oil at servIce temperature: Use of Tap Changer

Water content’) Dielectric strength”)

For use at the neutral point of windings For use at a position other than the neutral point of winding

30 kV/2,5 mm

40 kV/2,5 mm

*) measured accorclng to IS 13567/1992 **) measured according to 156792/I 972 On-load tap changer

Transformer rated current

Number of tap change operations

M III 350



350 A

100 000

M Ill 500

≤ ≤

350 A 500 A

100 000 80 000

MIII 600

≤ ≤

350 A 600 A

100 000 80 000

M1 351



350 A

100 000

M1 501



500 A

100 000

M1 601



600 A

100 000

M1 802

≤ ≤

500 A 800 A

100 000 80 000

M1 1200

≤ ≤

800 A 1200 A

80 000 70 000

M1 1500

≤ ≤

1200 A 1500 A

70 000 60 000

M1 1800

≤ ≤

1500 A 1800 A

60 000 50 000

Table I Inspection Intervals Note: 1. If Um >245 kV at the tapchanger the indicated numbers of tapchange operation must be halved & 2. regardless of the number of tap change operations listed in Table 1, inspection must becained out after 6 to 7 years 3. Regulation at the line end of the transformer with Um > 245 the first inspection must becanied out after 20,000 operations or after 2 years of seniice respectively, which ever comes first 5

On Load Tap Changer Type M Operating Manual ImmediateIy removing most of abrasive particles responsible for mechanical wear. The user should regularly monitor the transformer insulating oil in the transformer according to the ralevant standards. If inspection is not carried out by E-MR personnel, please give us your report to supplement our in-spection data, incase of need recommendation for the next in-spection can be given. WARNING : Inspections of the tap changer equipment are obligatory. Disregarding the Inspection intervals can affect the trouble-free operation of tap changer and transformer. 1.5 Summary of inspection work A typical inspection includes the following work: — Withdrawing arid reinstalling the diverter switch unit — Cleaning the diverter switch oil compartment and diverter switch unit and, where necessary, the tap changer oil conservator tank. — Changing the switching oil — Checking the diverter switch oil compartment and diverter switch unit — Determining the contact wear — Measuring the transition resistors — Checking the protective relay, drive shaft, motor drive unit and, where present; the oil filter unit and voltage regulator. The diverter switch unit should not be exposed to air longer than necessary (at max. for 10 hours). Inspection work should not be inter-rupted. Care and cleanliness should be observed.

WARNING: inspection must be carried out by qualified, skilled personnel only. The instructions should be followed strictly. Damage which is found during inspection needs immediate contact with E-MR for assistance. Do not put the tap changer in service until the damage has been corrected. Do not alter or modify the tap changer equipment without prior consulting E-MR. Improper or incomplete work carried out during inspection can aflect the trouble-free operation of tap changer and transformer. Under certain circumstances this can cause property damage andlor per-sonal injury. 2. Preparation 2.1 Necessary equipment — empty vessels for dirty oil, the necessary quantity of new transformer oil for cleaning and oil change; kV 36 72.5 123 170 245 Litres 125 130 150 170 190 Table II Oil filling quantity in litres — an oil pump for draining and refilling; — a drip pan; — miscellaneous brushes and absorbent, non-fuzzing rags for cleaning; — a work table; — a lifting device: — weight of diverter switch unit max. 80 kg. required lifting force is mdx. 1300 N; kV 36 37.5 123 170 245 m m 830 870 1000 113 1230 Table Ill Withdrawal height in mm — inspection tool — spare parts

Please note: Lock tabs, self lock-ing screws and nuts should never be used twice and should be replaced during reassembly. CAUTION: Always use E-MR authorized replacement parts. Parts of other origin can affect the trouble-free operation of tap changer and transformer. 2.2 Safety precautions WARNING: The user of the plant should perform the following safety measures. The transformer must be switched off, isolated and secured against reclosing. All terminals must be grounded visibly (by means of ground cables or ground switches). The working area should be marked clearly. Start with inspection only after all these safety precautions have been carried out. Dis-regarding them endangers lives 2.3 Operating position when withdrawing the diverter switch unit The diverter switch unit can be withdrawn in any operating posi-tion. Take note of the operating position when withdrawing the unit. However, we recommend on prin-ciple to withdraw the diverter switch in the adjustment position which is marked by an arrow on the position indicating disc of the motor drive unit.

6

On Load Tap Changer Type M Operating Manual

CAUTION: Do not operate the motor drive unit while the tap changer is uncoupled, either manually or electrically. To prevent electrical operation by remote control, it is good safety practice to isolate the motor drive unit by trIpping the motor protective switch. 3.

Withdrawal of the Diverter Switch Unit (FIg.4)

Lowering the oil level: Shut the stop valve between oil conservator and tap changer head.

Lower the oil level in the tap changer head. To do this, open the bleeder valve in the head cover (remove screw cap M30/wrench size 36, lift valve tappet by means of a screwdriver) and the drain valve. WARNING: The switching oil ol the tap changer should always be handled as a I lam-mable liquid. Moreover, explosive gases can accumulate under the tap changer head cover, in the switching oil or in the oil com-partment. Therefore, strictly avoid open fire. Use a pump-ing equipment suitable for flammable liquids.

4

In case of an oil filter plant: open the return pipe sample valve and operate the filter unit, drain about 10 litres of oil from the tap changer head so that the support plate is out of the oil (check through the in-spection glass in the head cover). Uncoupling the drive shaft of the upper gear unit: Unscrew 6 screws M6 (w.s.1 0) from the coupling. Take care not to lose coupling baits, nuts and lock tabs. Normally the drive shaft can be moved to one side for clearance. It not, remove the other coupling on the bevel gear from the square tube (screws, nuts and lock labs as above) until the horizontal drive shaft can be removed. Take off the tap changer head cover (fig. 5) Unscrew the cover bolts Ml 0. Take care not to lose spring washers. Remove the cover, take care not to damage the Oring gasket of the head cover.

5 Fig . 4 Tap Changer head

1. Drive shaft ( square tube ) 2. Coupling brackets and bolt 3. Upper gear unit (centric arrangement) 4. Tap Changer head cover 5. Bleeder Screw of head cover 6. Pipe connection R for protective relay 7. Pipe connection S with bleeder screw for suction pipe

Dimantle In the following order Remove the position indicator disc (fig.6). Remove the clip from the shaft end. The coupling pin allows assembly in the correct position only.

7

On Load Tap Changer Type M Operating Manual

Fig. 10 Diverter Switch Unit

Take note of the marks on the tap changer head and the support plate In the adjustment position the key in the diverter switch drive shaft

matches with the triangle mark on the support plate. Undo the screws fixing the support plate. Standard design: 4 screws MB x

20 (Fig. 7). Special design for bell-type transformer cover. 5 studs MB with nuts (Fig.8). In both cases take care of bolts or nuts and washers. Carefully lift out the diverter switch unit using the lifting lugs (FIg.9) and put it on a flat, clean place. 4. Cleaning the Oil Compartment, the Oil Conservator and the Diverter Switch Unit Oil compartment, oil conservator Drain the oil compartment completely. Open the stop valve between tap changer head and oil conservator. Drain oil from the conservator until clean oil flows. If necessary, flush the oil conservator tank with clean transformer oil. Drain the oil compartment, flush with clean oil, and drain again completely. Diverter Switch Unit Carryout the visual inspection of divertor swithc external. Clean the diverter switch unit by flushing with clean transformer oil. 5. Inspection of the Dlverter Switch Unit 5.1 Withdrawal position Before starting the inspection take note of the switched position of the diverter switch (=withdrawal position). Note the position of the trip lever of the spring energy accumulator unit (Fig. 10) in order to regain this position after reassembly of the diverter switch unit. 5.2 Measuring the transition resistor (Fig. 11) Measures the value of each transition resistor. The values are in the order of 0.3 ... 30 ohms. Measure at the open side of the diverter switch sector between the stationary main switching contacts 8

On Load Tap Changer Type M Operating Manual

Fig.11 Measurement of transition resistor on distinct points of the contact shells.

and transition contacts above and below. For this purpose set the diverter switch to the opposite position by means of the operating

key Then measure again (Fig. 11). Compare the measured values against the indications on the nameplate. A 10 percent difference is pefmissibie. Detach the support cylinder. Undo 8 screws M8.20 (w.s.1 3) each with a self-locking nut, at the 4 fish-plates of the spring energy accumulator. When removing the screws take not to drop the parts into the diverter switch. Take off the support cylinder. Take off the in outling drive shaft clean the support cylinder inside and outside with a brush and

transformer oil. Finally flush with transformer oil and dry. 5.3 Removing the contact shells Remove and reinstall contact shells consecutively on one diverter switch sector after the other. To remove the contact shells the diverter switch must be set to its mid-position where the transition contacts are closed: Release the spring energy accumulator and turn the drive shaft by means of the operating key until the wind-up sledge and the cocking sledge have reached a stable position just about in the middle (fig. 12,13, 14). Undo the fixing screws of the contact shells of one diverter switch sector: first the 4 other screws, then the 4 inner screws, in total 8 screws M6 x 20 (w.s. 10), see fig. 15,16,17. 5.4 Removing the arc chutes Withdraw the arc chutes The outer arc chutes have split sidewalls and must be refitted in exactly their initial position.

12

9

On Load Tap Changer Type M Operating Manual

Fig.21 Drive Shaft

5.7

5.5

Cleaning the diverter switch unit The contact shell with transition resistors and stationary contact system must be cleaned thoroughly with transformer oil. Special care should be taken when cleaning insulating parts. Flush all parts with clean oil. Since the contact shells and transi-tion resistors are to be disassembled and reassembled one sector before the next perform cleaning of the diverter switch between these procedures.

5.6

Cleaning the diverter switch Insulating drive shaft: To remove the insulating drive shaft, the support cylinder with support plate have to be detached from the energy accumulator case. CAUTION : Take care not to drop any parts Into the diverter switch. Otherwise the diverter switch can block and cause severe damage to the tap changer and transformer. There-fore, make sure that the number its is complete when disassembling and reassem-bling) count them to be sure.

Contact wear of main switching contacts and transition contact The admissible contact wear of the diverter switch contacts is determined by: a. The contact volume (see tig.22). The max. admissible contact wear of the individual contact is 4 mm. Contacts should be replaced if this value is reached or expected to be reached before the next inspection. b. the mechanical tap change operation sequence (see section 1.1), shunt contact (A, B), main switching contacts (a, b), transition contacts (al, bl). If the difference between main switching and transition contacts could become greater than certain given limits, the correct mechanical switching sequence of the diverter switch is no longer ensured. Unfavourable operating conditions can cause increased contact wear on transition contacts. 10

On Load Tap Changer Type M Operating Manual

switching and transition contacts by vernier gauge. Determine the contact wear by comparing the difference between new contact and measured value. 6. Replacement of the Diverter Arcing Contacts and Contact Braids 6.1 Diverter switch arcing contacts Each diverter switch sector is fitted with two main switching contacts (a, b) and two transition contacts (a1, b1). Each of these contacts exists as stationary and a movable contact. Each stationary and movable contact consists of two contact tips. Replacement of the contact tips of the stationary and movable contact system is simple (attachment : 1 screw M6 for each element). Note the following details: Stationary contact (see tig.23, 24) Each contact tip is fixed by one hexagon socket screw M6 x 16 (w.s. 4 or 5), max. torque 9 Nm, locked by centre punching the groove of the screw head. Movable contacts (see fig. 25, 26, 27) Each contact element is fixed by one hex head screw M6 x 16 (w.s. 10), 2 dished washers, max. torque 9 Nm, locked by lock tab. WARNING: Continued operation of the diverter switch with greatly differing contact layer thickness on arcing contacts can lead to severe damage of tap changer and transformer.

reached or is expected to be reached before the next inspection, the contacts shall be replaced or matched to the other contacts by interchanging or milling.

The max. permissible difference of contact layer thickness between main switching and transition contact is 2.5 ... 2.6 mm. If this dif-ference has been

5.8

Determination of contact wear Measure and note the thickness ot the contact layers on the stationary and movable main

OLTC M III 350 M I 351: Before undoing contact tips remove the contact braids on top and bottom (see section 6.2). Note: In case of through-current exceeding 200 A contacts of tungsten

11

On Load Tap Changer Type M Operating Manual

contact system to the slide contact (= output terminal) of the diverter switch sector. These braids are fixed by a screw, washer and self-locking nut (fig. 28, 29). As a precaution, the contact braids should be replaced after 250,000 operations regardless of replacement of diverter switch contacts. Please note: OLTC 111350, M 1351 (see fig. 30) There are 8 sets of contact braids, two sets each on top and bottom as well as two sets of two in the middle of a sector. The contact braids of the main switching contacts and transition contacts are joined together at the output terminal. 2 sets ot contact braids (on top and bottom) Each fixed to the output terminal by one bolt M6 x 28 (w.s.10) with self-locking nut and washer, max. torque 9 Nm. Attachment to the main switching contact (double braid) by one bolt M6 x 18L, attachment to the transi-tion contact (single braid) by one bolt M6 x 16. copper are used tor tne transition contacts (a1, b1). OLTC M III 500, M III 600, M I 501, M l 601, M I 802, M I 1200, M I 1500, M I 1800.

All bolts with self-locking nut and washer, max. torque 9 Nm. 4 sets of double contact braids (in the middle) Attachment to the output terminal:

Before undoing the contact tips remove the contact braids on top (see section 6.2).

each by one bolt M5 x 22 (w.s.8) with self-locking nut and washer, max. torque 5 Nm.

6.2

Each fixed to the main switching contact by one bolt M6 x 1 BL (w.s.1 0) with selt-locking nut and washer, max. torque 9 Nm.

Contact braids

The contact braids connect the main switching contacts and transition contact of the movable

12

On Load Tap Changer Type M Operating Manual

Attachment to the main switching contact and transition contact: each by one bolt M6 x 16 (w.s. 10) with self-looking nut and washer. max. torque 9 Nm. Always use new self-locking nuts. 7. Reattachment of the contact shells Reattach the contact shell in reverse order to removal. The diverter switch is in the midposi-tion. Insert a chucking wedge between epoxy segment and contact carder to hold back the movable contact system of the diverter switch. This counters the pressure of the movable contact system (fig. 32. 33) and makes attachment of the contact shell easier. Refit the arc chutes and make sure that they are properly seated. Attachment of each contact shell by 8 screws M6 x 20 (w.s. 10), max. torque 5 Nm, with look tabs (fig.34). Use new self-locking screws and lock tabs. After tightening the screws, remove the chucking wedge in upward direction (fig.35). When all contact shells have been reinstalled, the spring energy accumulator must be set from the mid-position into a switched position of the diverter switch and locked-in. OLTC M III 500, M III 600, M I 501, M I 601, M I 802, M I 1200, M I 1500 M I 1800 (sec fig. 31) There are two sets of contact braids on top only, connected to main switching and transition contacts.

The contact braid of the main switching contacts and transition contacts are joined together at the output terminal.

Insert a screwdriver between wind-up sledge and cooking sledge of the energy accumulator (fig. 36).

Attachment to the output terminal by one bolt M6 x 28 (w.s. 10) with self-locking nut and washer, max. torque 9 Nm.

13

On Load Tap Changer Type M Operating Manual

Actuate the eccentric by means of the operating key until the pawl locks-in (see fig. 37, 38). Operate the diverter switch several times to check its mechanical function. Finally check again the transition resistors as described in section 5.2. Set the diverter switch to its withdrawal position (see section 5.1). The diverter switch unit is now ready to be reinstalled.

8. Reattach the support cylinder with support plate: 8 bolts M8 x 20 (w.s.13), each with 2 washers, max. torque 22 Nm. En-sure alignment of triangle marks on bottom at the spring energy accumulator housing and on top at the support plate (fig. 39, 40). Operate the diverter switch several times to check its mechanical function (fig. 41). Final ly check again the transition resistors as described in section 5.2.

14

On Load Tap Changer Type M Operating Manual

Fill up the oil conservator with new oil to its original level. CAUTION: The transformer should be energised not earlier than 1 hour after the oil filling. 11. Motor Drive The on-load tap changer type M is operated by motor drive unit MA2 mounted outside the transformer tank, with maximum operating posi. tion of 35. Set the dlverter switch to Its withdrawal position (see section 5.1) The diverter switch unit is now ready to be reinstalled.

9. Reinstallatlon ol the diverter switch unit Remove the tap changer head cover. Lift the diverter switch unit over the open tap changer head. Lower it down into the oil compartment slowly and carefully. When remounting the diverter switch unit turn, if necessary, the insulating shaft slightly until the coupling engages. Ensure alignment of marks on the support plate of diverter switch unit and in the tap changer head. Fix the diverter switch unit by the screws of the support plate. Standard design: 4 screws MB x 20 (w.s. 13). Special design for bell-type tank installation: 5 nuts M8 (w.s. 13). Both types secured by spring washers, max. torque 22 Nm. Reinstall the position indicating disc (put on clip to shaft end).

10. Oil Filling CAUTION: The tap changer oil compartment arid the associate oil conservator must only be filled with new mineral insuIating oil for transformers as per IEC 296 (1982). The use of other oil can affect the trouble-free operation of tap changer and transformer. Fill new oil into the diverter switch oil compartment up to the level of the support plate. Put the cover on the tap changer head making sure that the gasket fits property; if necessary replace the O-ring. The head cover is attached by 24 bolts M10 (w.s. 17), max. torque 34 Nm, secured by spring washers. Open the stop valve between protective relay and oil conser-vator. Vent the tap changer head through the bleeder valve in the tap changer head cover (remove screw cap M30 I w.s. 36 and lift valve tappet by means of a screwdriver). Vent the suction pipe (screw cap M161w.s 22. bleeder screw M6 with chees head, max. torque 2 Nm). see fig. 42. Units with stationary oil filter unit: operate the oil fitter unit and bleed.

The drive shaft is the mechanical connection between motor drive and tap changer head. The bevel gear connects the vertical and horizontal parts of the drive shaft. The vertical part has to be mounted between motor drive unit and bevel gear, and the horizontal part be-tween bevel gear and tap changer head.The drive shaft couplings are the same for both parts. Both ends of the square shaft are connected to the respective implement by two coupling brackets and one coupling pin. Square shaft have to be trimmed to the required lengths when they are mounted on the transformer. 11.1 Coupling instructions When mounting observe the following instructions: 1. Check the shaft length between the two shaft ends. 2. Attach the coupling brackets to the shaft by “6” screws M6 (wrench size 10) add flat washer (m6) and lock washer (m6). Slide the coupling brackets on the square shaft as far as possible, tighten the M6 nuts. (maximum torque 9Nm). 3. Lubricate “O” ring and coupling pin.

15

On Load Tap Changer Type M Operating Manual

4. Place the coupling pin into the trunion and slide the square shaft together with the coupling. 5. Provide the opposite trunion with coupling bracket and coupling pin. Fit in the square shaft. Place second coupling bracket and tighten the “6” bolts (M6) with flat washer, lock washer and (M6) nuts. 6. Make sure that there is an axial clearance of 2mm between coupling pin and coupling brackets. 7. Finally tighten the coupling brackets (max. torque 9Nm) placed on both side of the bevel gear and next to the tap changer head. Note: The screws of coupling brackets next to motor drive unit must be tightened and locked when the rotation lag of motor drive has been equalized. 11.2 RotatIonal lag adjustment of the tap changer and motor drive For the following procedure the tap changer and motor drive must be the same tap position. The motor drive has to be set to the same position as found in the tap changer. Motor drive and tap changer cans however, finally be coupled only when the rotation lag (if there is

any) has been balanced. For this purpose proceed as follows: 11.2.1Turn the hand crank clock-wise towards “Lower” until the energy accumulator of the tap changer is released. 11.2.2Continue cranking and count the revolutions necessary br releasing the spring unit of the motor ‘drive, till a “click’ which can be distinctly heard (about 3 to 5 revolutions). 11.2.3Turn the hand crank counter clockwise towards “Raise” until the energy accumulator of the lap changer is released. 11.2.4Continue cranking and count the revolutions, as in 11.2.1. 11.2.5Balancing the rotation lag is necessary if the number of clock-wise revolutions does not equal that of the counter clockwise revolu-tions. In this case the vertical part of the driving shaft is uncoupled. The hand crank is then turned in the rotation sense which required more revolutions to be effected. The number of the balancing revolutions amounts to half the difference between the clockwise and counter clockwise revolutions. Example (see Fig.43)

Turn the crank clockwise (e.g. from position 6 to 5) rotation lag deter mined 3 revolutions (Fig.43). Turn the crank counter clockwise (e.g. from position 5 to 6) rotation rag determined: 5 revolutions. Uncouple. Equalize by truning the crank for half the difference: 1/2 (5-3) = 1 revolution counter clockwise. Recouple. Checking the result: Cranking clockwise (e.g. towards position 5) and then counter clock-wise (e.g. towards position 6) results in both oases in the same number of revolutions constituting the rotation lag (Ref. Fig.43).

EMR/OI/M/0010 16

Part-No.

Designation

009 859 1) 009 859 2) 010 236 1) 011 586 1) 012 5982) 0125992) 012 600 017 3552) 046 942 047 020 047 640 047 652 048 053 049 039 049 113 049 823 051 873 2) 052 206 052 866 056 932 2) 073 284 085 253 090 982 092 120 092 121 260 930 262 331 1) 264 020 400 004 401 044 401 045 401 471 450 330 450 335 450 361 450 500 451 076 451 087 451 325 452 356 453 255 453 977 453 981 550 666 550 711 1) 550 719 560 031 .

Contact tip (tungsten-copper) Contact tip (tungsten ~copper) for transition contact (> 200 A) Flexible current strip Flexible current strip Flexible current strip Flexible current strip Connecting lead Contact tip for main switching contact (> 200 A, for furnace/electrolysis transformer operation) Contact holder Flexible current strip M 111500, M 1501, M 1802, M 11200: stationary main contact Pressure plate Washer Pressure plate Tubular spacer Spring socket Contact tip (copper) Counterpiece Washer Stationary main contact, instead of 047 640, if needed Washer M Ill 600, M I 601, M 11500, M 11800: stationary main contact Stationary main contact, instead of 085 253, if needed Connecting lead Connecting lead Contact shell Contact holder (main contact) Contact holder (transition contact) Washer Hex. head screw M5 x 10 Hex. head screw M5 x 16, instead of 401 044, if needed Hex. head screw M6 x 20, self-locking Hex. head screw M5 x 8 Hex. head screw M5 x 20 Hex. head screw M6 x 25 Hex. head screw M6 x 22 Slotted socket screw MS x 16, recess head Slotted socket screw M6 x 16, recess head Washer Dished washer Hex. head screw M5 x 16 Hex. nut MS, self-locking Hex. nut M5, self-locking Helical spring, compression type Helical spring, compression type Helical spring, compression type Molded insulator

Note:

1

ForM 111500, M 111600, M 1501, M 1601, M 1802, M 11200, M 11500, M 11800; delete in case of MS 111300 ... M 1351

2l

ForMS Ill 300, MIll 350, MS I 300, M 1351 ; delete in case of M 111500 ... M 11800

l

Easun- M R Ta p C han gers Ltd., C hcnn ai

On-load tap changer type M Parts of diverter switch unit (stationary contact system)

Parts designation for 1 894 389:4E

450335

~

262331

047640 500 A [ (056 932) 600 A [ 085 253 (090982)

~

451325

011586

" 453977

-----

452356

-------

\

401044 (401 045)

Easun -MR Tap Changers Ltd., C hcnna i

On-load tap changer type M Parts of diverter switch unit (stationary contact system)

894 389:4E

Part-No.

Designation

009 859 011 105 012 770 012 801 015 991 015 992 017 355 022 417 022 419 026 157 046 956 046 957 046 970 046 987 047 409 047 412 047 738 048 400 048 633 048 869 049 209 050 101 050 102 050 103 050 319 050 387 050 504 050 535 051 873 053 155 053 667 056 919 057 801 057 802 070 941 093 326 264 013 450 043 450 062 450 101 450 109 450 355 450 356 451 086 451 323 451 325 452 063 452 220 452 350 452 997 452 998 453 447 453 977 453 978 453 979 453 981 550 292 550 293 550 294 550 295 550 665 550 668 560 163

Contact tip (tungsten-copper) for transition contact (> 200 A) Epoxy segment Braided contact lead Braided contact lead Current strip Current strip Contact tip for main switching contact (> 200 A, for furnace/electrolysis transformer operation) Washer Washer, instead of 022 417, if needed Washer Tubular drive shaft Drive star Take-off bar Pressure plate Tubular spacer Contact holder, main switching contact Tubular spacer Sliced spacing ring Roller Sliced spacer Sectorial connection Tubular spacer Tubular spacer Roller Centering sliced spacer Tubular spacer Tubular spacer Contact holder, transition contact Contact tip (copper) Threaded clamping stud Washer Screen cap Contact holder Contact holder Lock tab Braided contact lead Epoxy guide plate Hex. head screw M5 x 22 Hex. head screw M6 x 28 Hex. head screw M8 x 125 Hex. head screw M8 x 160 Hex. head screw M6 x 16 Hex. head screw M6 x 18 L Slotted socket screw M6 x 20, recess head Washer Washer Ball bearing Circlip lock ring Dished washer Feather Feather Flat head screw M6 x 30 Hex. nut M6, self-locking Hex. nut M8, self-locking Hex. nut M 10, self-locking Hex. nut M5, self-locking Insulating tube Tubular spacer Tubular spacer Tubular spacer Tubular spacer Helical spring compression type Current take-off housing

Easun -MR Tap C hangers Ltd., C hennai

On-load tap changer type M Parts of diverter switch unit M 350 (movable contact system MS Ill 300 ... M I 351))

Parts designation for dwg.

890 476:6E

453977

049209

453 977 1451325

~

~ 450 355

·~

..

~

453979

i

\

451325 I 050319 I 450 062 "--

....--- · - ~

453447 -~

451 323

450101 -----

----264013

453977

452 452220

On-load tap changer type M Eas un -MR Tap C hangers Ltd., C henna i

Parts of diverter switch unit M 350 (movable contact system MS 111300 ... M 1351)

890 476:6E

~

Part-No. 009 859 010 725 010 736 011 1OS 015991 015 992 022 013 022 417 022 419 026 157 046 956 046 957 046 970 046 987 046 988 047 409 047 738 048 397 048 400 048 403 048 441 048 633 048 869 048 870 049 209 050 101 050 102 050 103 050 319 050 535 053 155 053 667 056 919 057 801 057 802 070 941 085 252 093 325 264 013 450 062 450 101 450 109 450 334 450 355 450 361 451 086 451 237 451 325 452 063 452 220 452 350 452 997 452 998 453 447 453 977 453 978 453 979 550 292 550 293 550 294 550 295 550 665 550 668 560 163

Designation Contact tip (tungsten copper)

M Ill 500, M I 501 , M I 802, M I 1200: movable main contact Triangular switching lever Epoxy segment Current strip Current strip Washer Washer Washer, instead of 022 417 if needed Washer Tubular drive shaft Drive star Take-off bar Pressure plate Lock tab Tubular spacer Tubular spacer Tubular spacer Sliced spacing ring Bearing sleeve Intermediate plate Roller Sliced spacer Tubular spacer Sectorial connection Tubular spacer Tubular spacer Roller Centering sliced spacer Contact holder Threaded clamping stud M 10 x 290 Washer Screen cap Contact holder Contact holder Lock tab M 111600, M 1601, M 11500, M 11800: movable main contact Braided contact lead Epoxy guide plate Hex. head screw M6 x 28 Hex. head. screw M8 x 125 Hex. head screw M8 x 160 Hex. head screw M5 x 18 Hex. head screw M6 x 16 Hex. head screw M6 x 25 Slotted socket screw M6 x 20, recess head Hex. nut M5 Washer Ball bearing Circlip lock ring Cup spring Feather Feather Flat head screw M6 x 30 Hex. nut M6, self-locking Hex. nut M8, self-locking Hex. nut M1 0, self-locking Tubular spacer Tubular spacer Tubular spacer Tubular spacer Helical spring compression type Helical spring compression type Take -off contact case

Easun -MR Tap C hangers Ltd ., C hcnna i

On-load tap changer type M Parts of diverter switch unit M 500/600 (movable contact system M Ill 500 ... M I 1800)

Parts designation for dwg. 894 388:5E

45397R ~t

453977

I

..

049209

453977JlJ-

046970

264013 453 447

,--- --~

~

r:::--~~

451237046988048441-

500A: 010725 ~~~~~; 600 A: 085 252 048441--

026157--~,;J

048 869-- -..~---~:::Ciiii>~~~~ 047 409 ---~~;;:(;_
View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF