Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

May 3, 2017 | Author: Penjejak Awan | Category: N/A
Share Embed Donate


Short Description

Download Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Constructio...

Description

Guidelines on the Estimation Procedures for Traffic Management during Construction

7.0m

5.0m

Roads Branch Public Works Department Malaysia Jalan Sultan Salahuddin 50582 Kuala Lumpur

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

TABLE OF CONTENTS 1. INTRODUCTION 2. OBJECTIVE 3. PRACTICES IN ESTIMATING BQ FOR TRAFFIC MANAGEMENT 3.1 PREVIOUS PRACTICE 3.2 CURRENT PRACTICE 4. ESTIMATION PROCEDURES 4.1 Case 1: Construction On Both Sides On Existing 2 Lane Single Carriageway To 4 Lane Dual Carriageway (Urban Roads) 4.2 Case 2: Construction On Both Sides On Existing 2 Lane Single Carriageway To 4 Lane Dual Carriageway (Rural Roads) 5. CONCLUSION APPENDIX A - STANDARD BQ FOR TRAFFIC MANAGEMENT DURING CONSTRUCTION APPENDIX B - BQ FOR THE ESTIMATION QUANTITIES FOR TRAFFIC MANAGEMENT DURING CONSTRUCTION APPENDIX B1 - CASE 1 : EXPANSION FOR URBAN ROAD FROM 2 LANE TO 4 LANE DUAL CARRIAGEWAY APPENDIX B2 - CASE 2 : EXPANSION FOR RURAL ROAD FROM 2 LANE TO 4 LANE DUAL CARRIAGEWAY APPENDIX C -DRAWINGS ON TYPICAL APPLICATION OF STANDARD TEMPORARY SIGNS APPENDIX D -NEW TEMPORARY SIGNBOARDS

JKR 20400-0681-03 NOTA TEKNIK (JALAN) 23/03 Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 1

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

1.0 INTRODUCTION Traffic Management during construction has been a great concern lately on all JKR road projects that are being constructed. The quality of the Traffic Management varies from project to project depending on the amount allocated for the Traffic Management, method of construction and the implementation of the Traffic Management. The inadequate amount allocated for the Traffic Management are due to the non-standardized estimation procedures for different category of roads and the difficulty in estimating Traffic Management during project costing due to the lack of information on method of construction. The methods of construction usually are not specified in the tender documents. This will later affect the Traffic Management for the projects when it is constructed on the ground. If the method of construction can be specified before the construction commences, the Traffic Management can then be planned properly so that the construction site is safe and give less disruption to the road users. This will also be easier for the implementation of the Traffic Management to the site officer.

2.0 OBJECTIVE The objective of this guideline is to provide a standard Bill of Quantities (BQ) for Traffic Management during construction. This guideline will also give examples on the estimation procedures in estimating the quantities for the items specified in the standard BQ for Traffic Management during construction. This standard BQ and the estimation procedures will be a basis for the engineers coordinating the design process to estimate the costs of the Traffic Management so that adequate funds can be allocated to give proper traffic management during construction.

Cawangan Jalan, Ibu Pejabat JKR, K.L

3.0 PRACTICES IN ESTIMATING BQ FOR TRAFFIC MANAGEMENT 3.1 PREVIOUS PRACTICE Previously, the Traffic Management cost was priced as a Lump Sum in Preliminaries item in the BQ. It was found that the problems faced later during construction with this procedure were: Inadequate funds allocated for Traffic Management Details for Traffic Management items were not specified in the BQ Materials to be used were not specified Since the Traffic Management costs was part of the Preliminaries BQ, the costs allocated was quite limited since it will increase the overall cost of the Preliminaries. The total Preliminaries cost usually has a maximum percentage to the Builders Works. Therefore, the amount needed for the Traffic Management sometimes was not priced adequately by the contractor. Through this procedure, the details for the Traffic Management items and materials to be used and the quantities were not specified. The supervision officers on site will then have problems in implementing and enforcing the traffic management since they do not have guidelines to what items, quantities and the right materials to be used. 3.2 CURRENT PRACTICE Due to the many problems faced and the poor quality provided by the contractors on Traffic Management through the previous procedure, the Traffic Management items has now been taken out from the Preliminaries bill as a separate bill on its own. All the quantities for the items specified in the bill will be Provisional Quantities except for the provision of the Traffic Management plan and safety Page 2

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

report that will be priced as Lump Sum. Through this procedure, the detailed items, materials and quantities to be provided on site are specified in the bill. In order to ensure that the standard items and devices needed for Traffic Management will be provided for all the projects, the Roads Branch has prepared a Standard BQ for Traffic Management during construction to be used for all new projects. This standard BQ consists of basic items usually used in Traffic Management. Extra special items needed to be used for certain projects can be added to the Standard BQ. The standard BQ is as in Appendix A.

KPKR/J/R/STD/AM 204 in the Standard Drawings for Road Construction. Examples on the estimation procedures for the quantities of Traffic Management are shown in 4.1 and 4.2. The estimations procedures are calculated for the Urban and Rural expansion from 2 lane single carriageway to 4 lane dual carriageway. The BQ for the estimation quantities are in Appendix B1 for Case 1: Construction On Both Sides On Existing 2 Lane Single Carriageway To 4 Lane Dual Carriageway (Urban Roads) and Appendix B2 for Case 2: Construction On Both Sides On Existing 2 Lane Single Carriageway To 4 Lane Dual Carriageway (Rural Roads).

4.0 ESTIMATION PROCEDURES For the estimation of the quantities for devices used in Traffic Management during construction, the typical standard application drawings for specific works during construction can be used as a basis. The existing 'Application of Standard Temporary Signs 1 - 4' numbered as KPKR/J/R/STD/AM 206 - 209' in the Standard Drawings for Road Construction has been revised. The revised application drawings will supersede the existing drawings in the Standard Drawings for Road Construction documents and also the application drawings incorporated in the existing Arahan Teknik (Jalan) 2C/85. Apart from the existing typical application drawings, there is some additional typical application drawings added for other s pecific works. The revised and new typical application drawings are as shown in Appendix C. During the revision process for the existing typical application drawings, there is a need for new temporary signboards to be added. The new temporary signboards added are as shown in Appendix D. These new sign boards will be added to the existing Standard Temporary Signboards numbered Cawangan Jalan, Ibu Pejabat JKR, K.L

The estimations are based on the typical application for Works on Shoulder and Typical Application On A 2-Lane Highway Where The Entire Roadway Is Closed And A Bypass Detour Is Provided (temporary road diversion). The drawings for both the applications are as in Appendix C drawing number KPKR/J/R/STD/AM 208A and KPKR/J/R/STD/AM 207A, respectively. 4.1 Case 1: Construction On Both Sides On Existing 2 Lane Single Carriageway To 4 Lane Dual Carriageway (Urban Roads) 4.1.1

Assumptions:-

i. There is no street lighting in the contract area. ii. 5 km length of construction areas. iii. The construction area shall be segregated from the traffic way from commencement of work to completion time to prevent uncontrolled disruption to the traffic movements. Continuous barriers shall be used to segregate the working areas from the traffic way. iv. The excavation area (work site) shall be Page 3

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

carried out at 200m length at one time at 4 locations along the 5 km.

To be placed along the road side continuously and at the centre of the two way traffic.

v. There will be 1 traffic diversion at every 5km. The length of temporary traffic diversion is assumed to be 30m length.

Therefore the numbers of barriers needed :-

vi. The traffic diversion costs exclude the earthworks and pavement costs. It com prises cost for traffic signs, devices for traffic management and road markings.

Length of construction area less the length of 4 work site @ 200m at each work site and less the length for the temporary road diversion @30m (30 x 2 - for both side of the road ).

vii. For estimation purposes, the signboard quantities are based on per work site applications. For example, if the total work site is 4 locations, the quantities installed for one work site is multiplied by 4.

= (5000 x 2 ) - (200 x 4 ) - 60 = 9140 nos.

viii.The quantities do not take into consideration the percentage of losses and damages. 4.1.2 Estimation on BQ Items i. Item 1. 1. 1 : Movable Reinforced Concrete Barrier (NJB) or equivalent To be used where excavation on the road side is 1m deep or more. Since each work site is 200m length, therefore the number of concrete barriers needed for each work site is 200 nos. For 4 locations =200*4 = 800 nos. This set (800 nos.) can be use repeatedly throughout the construction area.

a.

Along the construction area.

Along the median less 30m for the temporary road diversion = 5000 - 30 = 4970 nos. b. For temporary traffic diversion 10 nos. of barrier is assumed (as shown in the typical application drawing for temporary diversion in Appendix C). Total = 14120 nos. iii. Item1.1.4. : Warning Lamp / Blinkers. To be placed on the barriers at 30m interval along the construction area (excluding the work site area and temporary road diversion). To be placed at 10m interval along the excavation work site and at signboards as shown in the typical application drawing in Appendix C.

Total = 800 nos. The number of warning light needed:ii. Item1.1.2 : Light Weight Movable Barrier (Plastic Barrier) To be used where excavation on road side is less than 1m deep. To replace movable barricade at transition area, buffer area and termination area. Cawangan Jalan, Ibu Pejabat JKR, K.L

a. At the construction area = (15000 - (200 x 4 ) - 90)/ 30 = 470.3 = 471 nos. b. Along the work site area = (20 nos. x 4 site) + (11 (at signboards ) x4) = 124 nos Page 4

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

c. Along the temporary traffic diversion construction site = 28 nos Total =

623 nos.

vi. Item1.1.8. : Flashing Arrow. To be placed at traffic diversion in construction area.

iv. Item1.1.5. : Beacon Light.

The number of flashing arrows needed.:-

To be placed at the start and end of a specific work site.

a.

At the work sites = 2 nos. x 4 sites = 8 nos.

The number of beacon light needed.:-

b.

Along the temporary road diversion site = 2 nos

a. At the specific work site = 2 nos. * 4 site = 8 nos

c.

Total =

b. Along the temporary traffic diversion construction site = 2 nos Total =

10 nos.

10 nos.

vii. Item 1. 1. 10. : Guardrails Used at temporary road diversion approximately 50 m

v. Item 1.1.7. : Barrier Delineators

Total = 50 m

To be pasted on each barrier on one side. For median barrier, pasted on both side. Alternative to the string delineators.

viii. Item1.1. 11. : Temporary Lighting. To be placed at the start and end of a specific work site.

Numbers needed :The number of temporary lighting needed.:a.

Based on Item 1. 1. 1

No. of delineators =800 nos b.

Based on Item 1. 1. 2

No. of delineators for barriers along the construction area = 9140 nos

a. At the specific work site = 2 nos. * 4 site = 8 nos b. Along the temporary road diversion site = 2 nos Total =

10 nos.

xi. Item1.2. : Temporary Signs No. of delineators for median barriers = 4970 * 2 = 9940 nos c. No. of barriers along temporary traffic diversion = 10 nos. Total number of barrier delineators = 19890 nos.

a.

At the work site = 7 * 4 sites = 28 nos Along the temp. road diversion work area = 22 nos. Total = 50 nos b.

Cawangan Jalan, Ibu Pejabat JKR, K.L

Not exceeding 1 sq. m

Exceeding 1 sq. m but not exceeding 2 sq. m

Page 5

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

At the work excavation site = 4 * 4 sites = 16 nos

the earthworks and pavement costs. It comprises cost for traffic signs, devices for traffic management and road markings.

Along the temp. road diversion work area = 4 nos. Along the construction area = 4 nos. Total = 24 nos xii. Item 1.5. : Road Markings For temporaray road diversions - 30 m a.

b.

vii. For estimation purposes, the signboard quantities are based on per work site applications. For example, if the total work site is 4 locations, the quantities installed for one work site is multiplied by 4.

Edge lines = 30 * 2 = 60 m

viii.The quantities do not take into considerations the percentage of losses and damages.

Total = 60 m

4.2.1

Centre lines = 30 m

i. Item 1.1.1 : Movable Reinforced concrete Barriers (NJB) or equivalent

Estimation on BQ items

Total = 30 m 4.2 Case 2: Construction On Both Sides On Existing 2 Lane Single Carriageway To 4 Lane Dual Carriageway (Rural Roads) 4.2.1

To be used where excavation on the road side is 1m deep or more. Since each work site is 200m length, therefore the number of concrete barriers needed for each work site is 200 nos.

Assumptions:-

i. There is no street lighting in the contract area.

For 4 locations =200*4 = 800 nos. This set (800 nos.) can be use repeatedly throughout the construction area.

ii. 5 km length of construction areas.

Total = 800 nos.

iii. The excavation work area shall be carried out at 200m length at one time at 4 locations along the 5 km (assuming 2 locations on each side of the road).

ii. Item 1.1.2 Light Weight Movable Barriers (Plastic Barrier)

iv. Paving works shall be done after the road base works has been completed for the whole 5 km. Therefore, the NJB plastic barriers shall be installed along the 5 km at spacing of 4 m apart.

To be used where excavation on road side is less than 1m deep. To replace movable barricade at transition area, buffer area and termination area. To be placed along the road side at interval until the constructed area are paved. Therefore the numbers of barriers needed :-

v. There will be 1 traffic diversion at every 5 km. The length of temporary traffic diversion is assumed to be 30m length. vi. The traffic diversion costs exclude the Cawangan Jalan, Ibu Pejabat JKR, K.L

a.

Along the construction area.

Say the plastic barrier is placed at 4m interval. Page 6

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

Length of construction area = 5000 x 2 = 10000 Length of work site = 200 x 4 = 800 Length of temp. road diversion = 30 x 2 sides= 60

b. Along the temporary traffic diversion construction site = 2 nos

No. of barriers needed = (10000 - 800 - 60)/4 = 2285 nos.

To be pasted on each barrier on one side. Alternative to the string delineators.

b.

Numbers needed :-

For temporary traffic diversion 10 nos of barrier is assumed.

Total =

v. Item 1.1.7 : Barrier Delineators

a. Total =

10 nos.

Based on Item 1. 1. 1

2295 nos. No. of delineators =800 nos.

iii. Item 1.1.4. : Warning Lamps/ Blinkers b. To be placed on the barriers at 30m interval along the construction area (excluding the work site area and temporary road diversion). To be placed at 10m interval along the excavation work site and at signboards as shown in the typical application drawing in Appendix C.

Based on Item 1. 1. 2

No. of delineators for barriers along the construction area = 2285 nos. c. No. of barriers along temporary traffic diversion = 10 nos. Total number of barrier delineators = 3095 nos.

The number of warning light needed.:vi.Item1.1.8. : Flashing Arrow. a. At the construction area = (10000 - 800 - 60)/30 = 304.7 = 305 nos. b. Along the work site area = (20 nos. x 4 site) + (11 (at signboards ) x4) = 124 nos

To be placed at traffic diversion in construction area. The number of flashing arrows needed.:a.

At the work sites = 2 nos. x 4 sites = 8 nos. Along the temporary road diversion site = 2 nos

c. Along the temporary traffic diversion construction site = 28 nos

b.

Total = 457 nos.

c.

Total =

iv. Item1.1.5. : Beacon Light.

vii.

Item 1. 1. 10. : Guardrails

To be placed at the starting and end of a specific work site.

Used at temporary road diversion approximately 50 m

The number of beacon light needed.:-

Total = 50 m

10 nos.

a. At the specific work site = 2 nos. * 4 site = 8 nos Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 7

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

viii. Item1.1. 11. : Temporary Lighting.

5.0

To be placed at the start and end of a specific work site.

Due to the inconsistencies in the quality of Traffic Management for road construction projects, there is a need for a standard detailed itemized BQ and estimation procedures. This standard BQ and estimation procedures will be used as a guide for the engineers involved in the design procedures to estimate the Traffic Management costs for a project. It is also a guide for the supervision officer on site to ensure that a proper Traffic Management with enough items and devices be installed on site during construction.

The number of temporary lighting needed.:a. At the specific work site = 2 nos. * 4 site = 8 nos b. Along the temporary road diversion site = 2 nos Total =

10 nos.

CONCLUSION

xi. Item1.2. : Temporary Signs a.

Not exceeding 1 sq. m

At the work site = 7 * 4 sites = 28 nos Along the temp. road diversion work area = 22 nos. Total = 50 nos b.

Exceeding 1 sq. m but not exceeding 2 sq. m

At the work excavation site = 4 * 4 sites = 16 nos Along the temp. road diversion work area = 4 nos. Along the construction area = 4 nos. Total = 24 nos xii. Item 1.5. : Road Markings For temporaray road diversions - 30 m a.

Edge lines = 30 * 2 = 60 m Total = 60 m

b.

Centre lines = 30 m Total = 30 m

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 8

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

APPENDIX A STANDARD BQ FOR TRAFFIC MANAGEMENT DURING CONSTRUCTION

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 9

Guidelines On The Estimation Procedures For Traffic Management During Construction

FOR INTERNAL USE ONLY

STANDARD BQ FOR TRAFFIC MANAGEMENT DURING CONSTRUCTION BIL NO.1-TRAFFIC MANAGEMENT Item No 1.0

Description of work

Quantity

Unit

Rate

Amount

TRAFFIC MANAGEMENT TEAM ManProvide for the appointment of a full time traffic diversion and safety officer as specified. Months Traffic management team 1. Traffic Safety Officer (……..Persons) 2. Supervision/foreman (……..Persons) 3. Traffic Controller (……persons)

1.1 TEMPORARY ROAD FURNITURES 1.1.1 Precast Movable Reinforced Concrete Nos Barriers or equivalent Supply precast reinforced concrete movable, "New Jersey Barriers" as shown on the Drawings and /or as directed by the S.O. and as specified installation at the first position as shown on the drawings and storage, maintenance and replacement during construction period including moving from point to point, and removal at the completion of the roadworks. 1.1.2 Light Weight Movable Barriers Nos Supply light weight movable "New Jersey Barriers" as shown on the Drawings and/or as directed by the S.O. including installing in the first position as shown on the drawing and storage, maintenance and replacement during Construction Period including moving from point to point removal on completion of the roadworks. 1.1.3 Light Weight Movable Traffic Guidance Nos Cones Supply movable cones as shown on the Drawings and/or as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during the construction period and removal on completion of road works. To Collection Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 10

Guidelines On The Estimation Procedures For Traffic Management During Construction

FOR INTERNAL USE ONLY

BIL NO.1-TRAFFIC MANAGEMENT Item Description of work Quantity No 1.1.4 Blinkers Nos Supply warning lamp/blinker with batteries as shown in the drawing and/or as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during construction period including removal from site at the end of each stage and at the completion of the road works.

Unit

Rate

Amount

1.1.5 Beacon Light Nos Supply beacon light with batteries as shown in the drawing and/or as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during construction period including removal from site at the end of each stage and at the completion of the road works. 1.1.6 String Delineators Lin.m Supply double sided reflective string delineators as shown on the drawings and or /as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works. 1.1.7 Barrier Delineators Nos Supply barrier delineators to be attached at each barrier as shown in the drawing and/or as directed by the S.O. and as specified including installing, maintenance and replacement during construction period. 1.1.8 Flashing Arrow Nos Supply flashing arrow as shown on the drawing and so/as directed by the S.O. and as specified including installing in the first position as shown on the drawing and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works. To Collection Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 11

Guidelines On The Estimation Procedures For Traffic Management During Construction

FOR INTERNAL USE ONLY

BIL NO.1-TRAFFIC MANAGEMENT Item Description of work Quantity No 1.1.9 Sand Bag Cu.m Supply sand bag as directed by the S.O. and as specified including installing in the first position and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works.

Unit

Rate

Amount

1.1.10 Temporary Guardrails Lin.m Supply temporary guardrails with reflectors as shown on the drawings and/or as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works. 1.1.11 Temporary Lighting Nos Supply temporary flood light as shown on the drawings and or /as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works. 1.2

TEMPORARY SIGNS Supply and install in position all temporary traffic signs of fluorescent orange prismatic retro-reflective sheeting including all posts brackets, painting and everything complete as shown on the Drawing and/or as directed by the S.O. including removal from site at the end of each stage and at the completion of the road works.. i. Not exceeding 1 sq. m ii. Exceeding 1 sq. m but not exceeding 2 sq.m iii Exceeding 2 sq. m but not exceeding 3 sq.m iv.Exceeding 3 sq. m but not exceeding 4 sq.m v. Exceeding 4 sq. m

Nos Nos Nos Nos Nos

To Collection

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 12

Guidelines On The Estimation Procedures For Traffic Management During Construction

FOR INTERNAL USE ONLY

BIL NO.1-TRAFFIC MANAGEMENT Item Description of work No 1.3 TEMPORARY ROAD DIVERSION 1.3.1 Earthwork Supply all labour, plants, materials, transports etc for the proposed work in accordance with the Specifications and Drawings

Quantity

Unit

Rate

Amount

1.3.1.1 Excavate unsuitabe material at temporary road Cu.m diversion Cu.m 1.3.1.2 Provide, place spread, level and compact in layers suitable fill materials at temporary road diversion from contractor's own source 1.3.1.3 Excavate earth drain at temporary road

Cu.m

1.3.1.4 Provide close turfing on slopes

Cu.m

1.3.2 Pavement 1.3.2.1 Preparation of formation as specified and as directed by the S.O for receiving temporary road pavement

sq.m

1.3.2.2 Supply, spread and compact crushed aggregate sq.m base course to a minimum compacted thickness of ….. mm 1.3.2.3 Prime coat to crusher run road base using cut- sq.m back bituminous material (MC 70 OR SS-1) spraying rate shall be 0.5 to 1.0 liter per sq.m. sq.m 1.3.2.4 Supply, lay and compact asphaltic concrete binder course to a minimum compacted thickness of 60 mm 1.3.3 Road Markings Install temporary road marking as shown on the drawings and or/as directed by the S.O. and as specified during the construction period. i. Edges lines ii. Centre lines iii. Blackening existing road marking

Lin.m Lin.m Lin.m

To Collection

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 13

Guidelines On The Estimation Procedures For Traffic Management During Construction

FOR INTERNAL USE ONLY

Item Description of work Quantity No 1.4 REPORT & TRAFFIC MANAGEMENT PLAN 1.4.1 Allow for the preparation submission of traffic L.S management plan and method of statement for approval when and where as requested by the S.O. 1.4.2 Submission of 6 sets Traffic Management Safety Report once in every 3 months 1.5 Removal of temporary road diversion and structures upon completion of project

Unit

Rate

Amount

L.S

L.S

To Collection

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 14

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

APPENDIX B STANDARD ESTIMATION QUANTITIES FOR TRAFFIC MANAGEMENT DURING CONSTRUCTION

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 15

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

APPENDIX B1 CASE 1: EXPANSION FOR URBAN ROAD FROM 2 LANE TO 4 LANE DUAL CARRIAGEWAY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 16

Guidelines On The Estimation Procedures For Traffic Management During Construction

FOR INTERNAL USE ONLY

CASE 1: EXPANSION FOR URBAN ROAD 2 LANE TO 4 LANE DUAL CARRIAGEWAY-BASED ON 5 KM LENGTH BIL NO.1-TRAFFIC MANAGEMENT Item No 1.0

Description of work

Quantity

Unit

Rate

Amount

TRAFFIC MANAGEMENT TEAM Provide for the appointment of a full time Mantraffic diversion and safety officer as specified. Months Traffic management team 1. Traffic Safety Officer (……..Persons) 2. Supervision/foreman (……..Persons) 3. Traffic Controller (……persons)

1.1 TEMPORARY ROAD FURNITURES 1.1.1 Precast Movable Reinforced Concrete Nos Barriers or equivalent Supply precast reinforced concrete movable, "New Jersey Barriers" as shown on the Drawings and /or as directed by the S.O. and as specified installation at the first position as shown on the drawings and storage, maintenance and replacement during construction period including moving from point to point, and removal at the completion of the roadworks. 1.1.2 Light Weight Movable Barriers Nos Supply light weight movable "New Jersey Barriers" as shown on the Drawings and/or as directed by the S.O. including installing in the first position as shown on the drawing and storage, maintenance and replacement during Construction Period including moving from point to point removal on completion of the roadworks.

800

14120

1.1.3 Light Weight Movable Traffic Guidance Nos Cones Supply movable cones as shown on the Drawings and/or as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during the construction period and removal on completion of road works. To Collection Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 17

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

BIL NO.1-TRAFFIC MANAGEMENT Item Description of work Quantity No 1.1.4 Blinkers Nos Supply warning lamp/blinker with batteries as shown in the drawing and/or as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during construction period including removal from site at the end of each stage and at the completion of the road works. 1.1.5 Beacon Light Nos Supply beacon light with batteries as shown in the drawing and/or as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during construction period including removal from site at the end of each stage and at the completion of the road works. 1.1.6 String Delineators Supply double sided reflective string delineators as shown on the drawings and or /as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works.

Unit

Amount

623

10

Lin.m

1.1.7 Barrier Delineators Nos Supply barrier delineators to be attached at each barrier as shown in the drawing and/or as directed by the S.O. and as specified including installing, maintenance and replacement during construction period.

19890

1.1.8 Flashing Arrow Nos Supply flashing arrow as shown on the drawing and so/as directed by the S.O. and as specified including installing in the first position as shown on the drawing and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works. To Collection

10

Cawangan Jalan, Ibu Pejabat JKR, K.L

Rate

Page 18

Guidelines On The Estimation Procedures For Traffic Management During Construction

FOR INTERNAL USE ONLY

BIL NO.1-TRAFFIC MANAGEMENT Item Description of work Quantity No 1.1.9 Sand Bag Cu.m Supply sand bag as directed by the S.O. and as specified including installing in the first position and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works.

Unit

1.1.10 Temporary Guardrails Lin.m Supply temporary guardrails with reflectors as shown on the drawings and/or as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works.

50

1.1.11 Temporary Lighting Nos Supply temporary flood light as shown on the drawings and or /as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works.

10

1.2

TEMPORARY SIGNS Supply and install in position all temporary traffic signs of fluorescent orange prismatic retro-reflective sheeting including all posts brackets, painting and everything complete as shown on the Drawing and/or as directed by the S.O. including removal from site at the end of each stage and at the completion of the road works.. i. Not exceeding 1 sq. m ii. Exceeding 1 sq. m but not exceeding 2 sq.m iii Exceeding 2 sq. m but not exceeding 3 sq.m iv.Exceeding 3 sq. m but not exceeding 4 sq.m v. Exceeding 4 sq. m

Nos Nos Nos Nos Nos

Rate

Amount

50 24

To Collection

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 19

Guidelines On The Estimation Procedures For Traffic Management During Construction

FOR INTERNAL USE ONLY

BIL NO.1-TRAFFIC MANAGEMENT Item Description of work No 1.3 TEMPORARY ROAD DIVERSION 1.3.1 Earthwork Supply all labour, plants, materials, transports etc for the proposed work in accordance with the Specifications and Drawings

Quantity

Unit

Rate

Amount

1.3.1.1 Excavate unsuitabe material at temporary road Cu.m diversion Cu.m 1.3.1.2 Provide, place spread, level and compact in layers suitable fill materials at temporary road diversion from contractor's own source 1.3.1.3 Excavate earth drain at temporary road

Cu.m

1.3.1.4 Provide close turfing on slopes

Cu.m

1.3.2 Pavement 1.3.2.1 Preparation of formation as specified and as directed by the S.O for receiving temporary road pavement

sq.m

1.3.2.2 Supply, spread and compact crushed aggregate sq.m base course to a minimum compacted thickness of ….. mm 1.3.2.3 Prime coat to crusher run road base using cut- sq.m back bituminous material (MC 70 OR SS-1) spraying rate shall be 0.5 to 1.0 liter per sq.m. sq.m 1.3.2.4 Supply, lay and compact asphaltic concrete binder course to a minimum compacted thickness of 60 mm 1.3.3 Road Markings Install temporary road marking as shown on the drawings and or/as directed by the S.O. and as specified during the construction period. i. Edges lines ii. Centre lines iii. Blackening existing road marking

Lin.m Lin.m Lin.m

60 30

To Collection

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 20

Guidelines On The Estimation Procedures For Traffic Management During Construction

FOR INTERNAL USE ONLY

BIL NO.1-TRAFFIC MANAGEMENT Item Description of work Quantity No 1.4 REPORT & TRAFFIC MANAGEMENT PLAN 1.4.1 Allow for the preparation submission of traffic L.S management plan and method of statement for approval when and where as requested by the S.O. 1.4.2 Submission of 6 sets Traffic Management Safety Report once in every 3 months 1.5 Removal of temporary road diversion and structures upon completion of project

Unit

Rate

Amount

L.S

L.S

To Collection

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 21

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

APPENDIX B2 CASE 2: EXPANSION FOR RURAL ROAD FROM 2 LANE TO 4 LANE DUAL CARRIAGEWAY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 22

Guidelines On The Estimation Procedures For Traffic Management During Construction

FOR INTERNAL USE ONLY

CASE 2: EXPANSION FOR RURAL ROAD 2 LANE TO 4 LANE DUAL CARRIAGEWAY-BASED ON 5 KM LENGTH BIL NO.1-TRAFFIC MANAGEMENT Item No 1.0

Description of work

Quantity

Unit

Rate

Amount

TRAFFIC MANAGEMENT TEAM ManProvide for the appointment of a full time traffic diversion and safety officer as specified. Months Traffic management team 1. Traffic Safety Officer (……..Persons) 2. Supervision/foreman (……..Persons) 3. Traffic Controller (……persons)

1.1 TEMPORARY ROAD FURNITURES 1.1.1 Precast Movable Reinforced Concrete Nos Barriers or equivalent Supply precast reinforced concrete movable, "New Jersey Barriers" as shown on the Drawings and /or as directed by the S.O. and as specified installation at the first position as shown on the drawings and storage, maintenance and replacement during construction period including moving from point to point, and removal at the completion of the roadworks. 1.1.2 Light Weight Movable Barriers Nos Supply light weight movable "New Jersey Barriers" as shown on the Drawings and/or as directed by the S.O. including installing in the first position as shown on the drawing and storage, maintenance and replacement during Construction Period including moving from point to point removal on completion of the roadworks.

800

2295

1.1.3 Light Weight Movable Traffic Guidance Nos Cones Supply movable cones as shown on the Drawings and/or as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during the construction period and removal on completion of road works. To Collection Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 23

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

BIL NO.1-TRAFFIC MANAGEMENT Item Description of work Quantity No 1.1.4 Blinkers Nos Supply warning lamp/blinker with batteries as shown in the drawing and/or as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during construction period including removal from site at the end of each stage and at the completion of the road works. 1.1.5 Beacon Light Nos Supply beacon light with batteries as shown in the drawing and/or as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during construction period including removal from site at the end of each stage and at the completion of the road works. 1.1.6 String Delineators Supply double sided reflective string delineators as shown on the drawings and or/as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works.

Unit

Amount

457

10

Lin.m

1.1.7 Barrier Delineators Nos Supply barrier delineators to be attached at each barrier as shown in the drawing and/or as directed by the S.O. and as specified including installing, maintenance and replacement during construction period.

3095

1.1.8 Flashing Arrow Nos Supply flashing arrow as shown on the drawing and so/as directed by the S.O. and as specified including installing in the first position as shown on the drawing and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works. To Collection

10

Cawangan Jalan, Ibu Pejabat JKR, K.L

Rate

Page 24

Guidelines On The Estimation Procedures For Traffic Management During Construction

FOR INTERNAL USE ONLY

BIL NO.1-TRAFFIC MANAGEMENT Item Description of work Quantity No 1.1.9 Sand Bag Cu.m Supply sand bag as directed by the S.O. and as specified including installing in the first position and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works.

Unit

1.1.10 Temporary Guardrails Lin.m Supply temporary guardrails with reflectors as shown on the drawings and/or as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works.

50

1.1.11 Temporary Lighting Nos Supply temporary flood light as shown on the drawings and or /as directed by the S.O. and as specified including installing in the first position as shown on the drawings and storage, maintenance and replacement during the construction period including removal from site at the end of each stage and at the completion of the road works.

10

1.2

TEMPORARY SIGNS Supply and install in position all temporary traffic signs of fluorescent orange prismatic retro-reflective sheeting including all posts brackets, painting and everything complete as shown on the Drawing and/or as directed by the S.O. including removal from site at the end of each stage and at the completion of the road works.. i. Not exceeding 1 sq. m ii. Exceeding 1 sq. m but not exceeding 2 sq.m iii Exceeding 2 sq. m but not exceeding 3 sq.m iv.Exceeding 3 sq. m but not exceeding 4 sq.m v. Exceeding 4 sq. m

Nos Nos Nos Nos Nos

Rate

Amount

50 24

To Collection

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 25

Guidelines On The Estimation Procedures For Traffic Management During Construction

FOR INTERNAL USE ONLY

BIL NO.1-TRAFFIC MANAGEMENT Item Description of work No 1.3 TEMPORARY ROAD DIVERSION 1.3.1 Earthwork Supply all labour, plants, materials, transports etc for the proposed work in accordance with the Specifications and Drawings

Quantity

Unit

Rate

Amount

1.3.1.1 Excavate unsuitabe material at temporary road Cu.m diversion Cu.m 1.3.1.2 Provide, place spread, level and compact in layers suitable fill materials at temporary road diversion from contractor's own source 1.3.1.3 Excavate earth drain at temporary road

Cu.m

1.3.1.4 Provide close turfing on slopes

Cu.m

1.3.2 Pavement 1.3.2.1 Preparation of formation as specified and as directed by the S.O for receiving temporary road pavement

sq.m

1.3.2.2 Supply, spread and compact crushed aggregate sq.m base course to a minimum compacted thickness of ….. mm 1.3.2.3 Prime coat to crusher run road base using cut- sq.m back bituminous material (MC 70 OR SS-1) spraying rate shall be 0.5 to 1.0 liter per sq.m. sq.m 1.3.2.4 Supply, lay and compact asphaltic concrete binder course to a minimum compacted thickness of 60 mm 1.3.3 Road Markings Install temporary road marking as shown on the drawings and or/as directed by the S.O. and as specified during the construction period. i. Edges lines ii. Centre lines iii. Blackening existing road marking

Lin.m Lin.m Lin.m

60 30

To Collection

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 26

Guidelines On The Estimation Procedures For Traffic Management During Construction

FOR INTERNAL USE ONLY

BIL NO.1-TRAFFIC MANAGEMENT Item Description of work Quantity No 1.4 REPORT & TRAFFIC MANAGEMENT PLAN 1.4.1 Allow for the preparation submission of traffic L.S management plan and method of statement for approval when and where as requested by the S.O. 1.4.2 Submission of 6 sets Traffic Management Safety Report once in every 3 months 1.5 Removal of temporary road diversion and structures upon completion of project

Unit

Rate

Amount

L.S

L.S

To Collection

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 27

FOR INTERNAL USE ONLY

Guidelines On The Estimation Procedures For Traffic Management During Construction

APPENDIX C DRAWING ON TYPICAL APPLICATION OF STANDARD TEMPORARY SIGN

Cawangan Jalan, Ibu Pejabat JKR, K.L

Page 28

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 29

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 30

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 31

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 32

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 33

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 34

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 35

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 36

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 37

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 38

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 39

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 40

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 41

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 42

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 43

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 44

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 45

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 46

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 47

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 48

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 49

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 50

FOR INTERNAL USE ONLY

Cawangan Jalan, Ibu Pejabat JKR, K.L

Guidelines On The Estimation Procedures For Traffic Management During Construction

Page 51

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF