ARAHAN TEKNIK 16 03 Pin 2008.pdf
Short Description
Download ARAHAN TEKNIK 16 03 Pin 2008.pdf...
Description
Arahan Teknik (Jalan) 16/03; (Pindaan 2008) JKR 21300-0002-09
JABATAN KERJA RAYA
A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS
Cawangan Kejuruteraan Jalan & Geoteknik Ibu Pejabat JKR Malaysia Peti Surat 18 & 19, Menara Tun Razak Jalan Raja Laut 50350 Kuala Lumpur
GREEN MISSION Being the key implementing agency for governments‟ projects, Jabatan Kerja Raya (JKR) is committed and dedicated to steer the organization and safeguard the environment by adopting the following principles:
Natural resources protection and enhancement Resource efficiency Sustainable consumption Sustainable construction Adherence to relevant laws and regulations
In doing so, Jabatan Kerja Raya (JKR) is guided by their environmental management system (ISO 14001 EMS) particularly during the construction stage to minimize and mitigate impacts to the environment through controlled site clearing, protection and maintenance of slopes, waste minimization and management and compliance to legal requirements. In moving forward, JKR is committed in ensuring that all projects are developed in a sustainable manner, focus shall be given at planning stage in order to take into account the need to identify and mitigate environmental impacts for developments in Environmentally Sensitive Areas (ESAs) or within its vicinity. Protection of ESA is one of the key steps towards protecting our country‟s natural resources.
i
PREFACE In line with the MS: ISO 14001 requirement, a continual improvement of the system must be done to ensure success and effectiveness of environmentally sustainable approach in construction. To produce a clear and comprehensive tender document, revision of JKR Tender Documents on environment protection and enhancements has been done by itemising the environmental works into the Bill of Quantities to allow contractors to tender a realistic price. Arahan Teknik (Jalan) 16/03, produced in 2004, provided changes to the items in the Tender Document with regards to the Condition of Contracts, Instruction to Tenderers, Specification to Environmental Protection and Enhancements, Preamble to Bill of Quantities, Need Statement, Bill of Quantities and Drawings.
In 2006, a committee comprising multi-disciplinary personnel was set up to revise the Arahan Teknik (Jalan) 16/03. Changes have been made in accordance to problems encountered and inadequacies of the previous Arahan Teknik. The overall improvement is aimed to ensure contractors understand the application of the environment protection works that they have tendered in the Bill of Quantities. Notwithstanding the importance of other technical agencies requirements to protect the environment, some parts have been added such as the preparation of Erosion and Sediment Control Plan (ESCP) and management of disposal site for surplus material as part of the latest EIA requirements. Drawings of mitigation works have been revised and amended. The revised Arahan Teknik (Jalan) 16/03 is made applicable, not only to road projects, but to all projects in JKR. It is important that all parties involved in the construction industry, be made aware of the latest government requirements in environment protection to ensure our nation has the capacity to be sustainable in the long term future.
ii
ACKNOWLEDGEMENT This revised Arahan Teknik (Jalan) 16/03 was prepared by a sub-committee comprising thirty-seven (37) multi-disciplinary personnel as listed below:-
(1)
Ir. Cheong Pui Keng
(2) (3)
Dato‟ Ir. Dr. Hj. Roslan bin Md Taha Ir. Hj. Abu Harith bin Shamsuddin
(4)
Ar. Cik Lee Bee Chew
(5) (6)
En. Meor Mohamed Haris bin Meor Hussein En. Muhamad Rahimi b Abdullah
(7) (8)
Pn. Hjh. Sujatiah binti Tamrin Pn. Hjh. Faridah binti Abdul Rashid
(9) Tn. Hj. Abdul Rahman bin Idris (10) Pn. Nor Shahrene binti Mohd Ibrahim (11) En. Amran bin Majid (12) Pn Emmy Sherina binti Ismail Hashim (13) En. Nasrollah bin Mohamad (14) En. Hamizan bin Husain (15) En. Mohd Nor Rashidi bin Abd Jalil (16) En. Mohd Aznan Shukri b Mohamed Safian (17) Pn. Nurazaini binti Mokhtar (18) YM Raja Nur Ashikin binti Raja Zainal (19) Pn. Geetha P. Kumaran (20) En. Romzi bin Mat Zainul (21) En. Shamsul Azhar bin Ismail (22) En. Mohd Zikri bin Azmi (23) En. Mohd. Khusairi b. Mohd. Isa (24) Cik Siti Nor bt. Othman (25) Pn. Siti Noor Aiza bt. Abd. Aziz (26) Cik Nurazura bt. Ali (27) En. Azizul b. Hashim (28) Pn. Hawa Liza bt. Zahari (29) En. Khairol Nazri b. Abdul Khaiyom iii
Pengarah, JKR Cawangan Alam Sekitar dan Tenaga (CAST) Pengarah, JKR Negeri Sembilan KPPK, JKR Cawangan Kejuruteraan Senggara Retired, (formerly Pengarah, JKR Cawangan Alam Sekitar dan Tenaga. KPP, JKR Perak (Jalan). KPPK, Cawangan Kej. Jalan & Geoteknik PPK, Cawangan Jalan KPP, Kementerian Kewangan (formerly JKR Cawangan Kontrak dan Ukur Bahan) KPP, JKR WPKL KPP (Arkitek). JKR Cawangan Pengurusan Korporat Juruukur Bahan, Cawangan Kejuruteraan Ukur Bahan Jurutera Senggara, JKR Daerah Kuala Terengganu PP, (ECER) PP, Cawangan Kej Mekanikal PP, Cawangan Pengurusan Korporat Jurutera Bangunan, JKR Hilir Perak PPK, Jabatan Pengairan dan Saliran ERE Consulting Group Sdn. Bhd. Europasia Eng. Services Sdn. Bhd. & ENSEARCH ATZ Consult Sdn. Bhd. (formerly HSSI S/B) Wiranda (M) Sdn. Bhd. Wiranda (M) Sdn. Bhd. KPP, CAST PP, CAST PP, CAST PP, CAST PP, CAST PP, CAST PP, CAST
(30) En. Mohd. Fauzie b. Ismail (31) Cik Aida Elyana bt. Jamil (32) En. Khairul Amir b. Isahak (33) En. Mohd. Amir b. Hashim (34) Pn. Noor Azizah bt. Majid (35) En. Mohd. Eikmal b. Ahmad (36) Pn. Zuraiha bt. Zainuddin@Abd Aziz (37) Pn. Izmazurin bt. Ramli
PP, CAST PP, CAST PP, CAST PP, CAST PP, CAST PP, CAST PP, CAST PP, CAST
Finally, the publisher wishes to express its gratitude to the above committee members for their valuable contributions and preparation of this guide. Published by:-
Unit Standard & Spesifikasi Bahagian Penyelarasan & Khidmat Sokongan Cawangan Kejuruteraan Jalan & Geoteknik Ibu Pejabat JKR Malaysia Tingkat 14, Menara Tun Razak Jalan Raja Laut 50350 Kuala Lumpur
Reproduction of any part from this publication may be made subject to due acknowledgement of the source. However, the publisher does not accept any responsibility for any consequences arising from the use of the information within this guide.
iv
A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS
CONTENTS
PAGE
CHAPTERS 1.0
Introduction
1
2.0
Environmental Requirements
5
3.0
Contractual Requirements
14
4.0
Specifications
16
5.0
Method of Measurement
35
6.0
Bill of Quantities
71
7.0
Best Management Practices
82
8.0
Standard Drawings and Figures
91
REFERENCES
104
APPENDIX 1
105
Standard Specifications for Building Works (2005 Edition):SECTION A: PRELIMINARIES AND GENERAL CONDITIONS AND SECTION C: EXCAVATIONS AND EARTHWORKS
APPENDIX 2:
Government Requirements (Need Statement)
111
(Term of Reference) (For Design and Build Projects Only)
APPENDIX 3:
Standard Report Format for :-
(i)
Environment Management Plan (EMP)
(ii)
Environment Quality Report (EQR)
(iii)
Environment Management Audit Report (EMAR)
(iv)
Closure Audit Report (CAR)
v
120
CHAPTER 1 INTRODUCTION
1
CHAPTER 1.0:
1.0
INTRODUCTION
Introduction
Environmental protection and conservation is gaining more significance in the long term national development plan. In this regards, Malaysia as a country, has reaffirmed its commitments towards the protection and conservation of its environment as stated in the National Policy on Environment, National Physical Plan (NPP) and prevailing Malaysia Plans. In summary, the National Policy on Environment aims for continuous economic, social and cultural progress and enhancement of the quality of life of Malaysians, through environmentally sound and sustainable development. The main goal of the NPP is to create an efficient, equitable and sustainable national framework that will guide future development of the country. It is an important piece of document as it provides the spatial element in development planning as well as spells out policies that determine the direction of physical development and conservation areas within Peninsular Malaysia. It also identifies areas that need to be conserved and protected via a ranking system. These areas are called Environmentally Sensitive Areas (ESA). Such identification will greatly assist any project proponent (government or private sector) in evaluating and determining the feasibility of some projects at macro or national level. In line with the nation‟s aspirations in protecting the environment, JKR has formulated and implemented the “JKR Green Mission” and has an Accredited MS ISO 14001 since 5th November 2002. The main objective of the document is to protect and enhance the environment by ensuring that projects are being implemented in a sustainable manner and with the least impacts to the environment.
1.1
Objectives
This Revised Arahan Teknik shall aim to attain the following objectives:
To ensure that the “JKR EMS ISO 14001” requirements in terms of environmental protection measures are properly incorporated in the preparation of the tender document and subsequently implemented during the planning, construction and operational stages of the project.
To guide users on the requirements pertaining to environmental protection, mitigation and enhancement measures in the preparation of tender document.
1.2
Method of Procurement
This document is applicable for both conventional and design and build contracts. A typical example of the process flow for both types of contracts can be referred to in the JKR‟s Quality Management System (QMS).
2
1.3
Limitation
This document may have limited use for costing and environmental protection measures purposes in the preparation of Bill of Quantities (BQ) for Projects that are subjected to the following:
Detailed Environmental Impact Assessment Study (particularly for projects that involve reclamation; Marine-related projects such as jetties, marina, coastal protection structures or any structure that extends out into the sea; and Projects located within areas identified as Environmentally Sensitive Areas (ESAs) such as wildlife sanctuary, wetlands, marine parks and national parks.
For projects identified above, more specific environmental protection measures may be required in order to minimize impacts to the environment.
1.4
Format of Document
This Revised Arahan Teknik (Jalan) 16/03 has been divided into eight chapters addressing the various components which form part and parcel of the tender document preparation process. In addition to the introductory material in this section, the document contains:Chapter 2.0
Environmental Requirements – in which environmental requirements at various project development stages will be described. Relevant guidelines are also tabulated for reference purposes.
Chapter 3.0
Contractual Requirements – in which environmental requirements pertaining to different methods of procurement will be presented.
Chapter 4.0
Specifications – in which environmental protection works are elaborated to assist users in preparing tender document as well as ensuring compliance to the relevant legislations and regulations.
Chapter 5.0
Method of Measurement (MOM) – in which elaboration of methods of measurement for items stated in the BQ will be measured. It describes the items, unit and measurement for payment.
Chapter 6.0
Bill of Quantities (BQ) – in which environmental protection works will be itemized in terms of unit, quantity, rate and cost. It will cover both non-physical works and physical works.
Chapter 7.0
Best Management Practices (BMP) – in which samples of mitigating measures that have been implemented successfully at site are shown.
Chapter 8.0
Standard Drawings and Figures – in which preliminary drawings and figures of mitigating measures such as silt trap, sediment basins, check dams and fuel storage skid tanks are shown. 3
APPENDIX 1 Standard Specifications For Building Works (2005 Edition):- SECTION A : PRELIMINARIES AND GENERAL CONDITIONS AND SECTION C : EXCAVATIONS AND EARTHWORKS
Appendix 2
Government Requirements (Need Statement) (Term of Reference) (For Design and Build Projects Only)
Appendix 3
Standard Report Format for Environmental Management Plan (EMP), Environmental Quality Report (EQR), Environmental Monitoring and Audit Report (EMAR) and Closure Audit Report (CAR)
4
CHAPTER 2 ENVIRONMENTAL REQUIREMENTS
5
CHAPTER 2:
ENVIRONMENTAL REQUIREMENTS
The legislation that is related to the prevention, abatement, control of pollution and enhancement of the environment in Malaysia is stipulated in the Environmental Quality Act 1974 (Amendment) 2007. To date, 40 sets of Regulations and Orders have been introduced and enforced. Under this Act, an Environmental Impact Assessment (EIA) is required for activities prescribed under the Environmental Quality (Prescribed Activities (Environmental Impact Assessment) Order 1987. Those activities that are not subject to the mandatory EIA requirement are nevertheless subject to various other regulations under the Act. The standard regulations require evaluation for project siting, pollution control, monitoring and self regulation via the audit process. For the states of Sabah and Sarawak, the environmental requirements are clearly stipulated in the Environment Protection (Amendment) Enactment 2004 and Natural Resources and Environment Ordinance respectively. Apart from compliance with the Environmental Quality Act (EQA) 1974 (Act 127) and other related environmental legislations, the following Acts are also applicable based on its relevancy to the planning, design, construction, equipping and commissioning of any project. (a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k)
National Land Code (Act 56 of 1965) Town and Country Planning Act 1976, (Act 172) Street, Drainage and Building Act, 1974: Act 133 and Amendment, 1978 Protection of Wildlife Act, 1972 (Act 76) Forestry Act 1984 (Act 313) Land Conservation Act 1960 (Act 385) Occupational Safety and Health Act 1994 (Act 514) Solid Waste and Public Cleansing Management Act 2007 (Act 672) Federal Territory (Planning) Act 1982 (Act 267) Workers Minimum Amenities Act 1990 (Act 446) Local Government Act 1976 (Act 171)
6
2.1
Planning/Design Stage
Environmental requirement during planning or design stage is clear whereby if the said project has been classified as a “prescribed activity” according to the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 1987 and Section 34A of the Environmental Quality (Prescribed Activities)(Environmental Impact Assessment) Order 1987, an Environmental Impact Assessment (EIA) study needs to be carried out and submitted to Department of Environment for approval prior to project implementation. Under the Act, there are a total of nineteen (19) categories of prescribed activities which include agriculture, airport, drainage and irrigation, land reclamation, fisheries, forestry, housing, industry, railways, transportation, resort and recreation development, waste treatment and disposal, and water supply projects. Additionally, a Detailed Environmental Impact Assessment (DEIA) study is required for thirteen (13) different types of projects which include steel mill, pulp and paper mill, cement plant, coal-fired power plant, dams (hydroelectric and water supply), coastal land reclamation, incinerators (scheduled wastes and solid wastes, solid wastes disposal sites, projects involving land clearance where more than 50% of the area has slope>250) and logging (>500 hectares). It is to be noted that for projects in Sabah and Sarawak, specific local legislations pertaining to EIA requirements need to be adhered to. For the state of Sabah, lists of prescribed activities are contained in First Schedule and Second Schedule of the Environment Protection (Prescribed Activities) (Environment Impact Assessment) Order 2005. For projects in Sabah, an environmental impact assessment report is required for any prescribed activities specified in the Second Schedule of the Environment Protection (Prescribed Activities) (Environment Impact Assessment) Order 2005. In addition, a proposal for mitigation measures is required for any prescribed activities specified in the First Schedule. For projects in Sarawak, an environmental impact assessment report is required for any prescribed activities specified in the First Schedule of the Natural Resources and Environment (Prescribed Activities) Order 1994. Apart from the legislative requirement, EIA may be prepared taking into consideration the sensitivity of the project in terms of its location, site conditions and magnitude of impacts. In some cases, preparation of EIA study is required by the local authorities or form part of the contractual requirement of a project. Findings from the study are intended to provide input in the planning of the Project, particularly in minimizing environmental impacts during the construction and operational stages. An EIA is considered as a planning tool to assist the Project Initiator in anticipating impacts of the development, both beneficial and adverse, with an aim to maximize the beneficial impacts and minimize the adverse impacts on the environment. For better understanding of the EIA process and procedures, an EIA flow chart for both Preliminary EIA and Detailed EIA are shown in Figures 1 and 2. Similarly, a simple EIA flow chart for Sarawak and Sabah are shown in Figures 3 and 4.
7
Figure 1: Flowchart for Preliminary EIA Process in Malaysia
Source: Department of Environment, Malaysia
8
Figure 2: Flowchart for Detailed EIA Process in Malaysia
Source: Department of Environment, Malaysia
9
Figure 3: Flowchart for EIA Process in Sarawak
Source: Natural Resources and Environment Board, Sarawak
10
Figure 4: Flowchart for Preliminary EIA Process in Sabah
Source: Environment Protection Department, Sabah
11
2.2
Implementation/ Construction Stage
In order to monitor Project‟s compliance with the general requirements of the Client‟s needs and relevant environmental legislation, an Environmental Management Plan (EMP) shall be prepared as detailed herein. The EMP shall be prepared in accordance to the format or guidelines recommended by the Department of Environment (DOE) and/or other relevant government departments‟ requirements. These guidelines shall provide the framework for the preparation of the environmental management and mitigation measures to mitigate on-site impacts to acceptable limits as stipulated by the DOE. The EMP is not intended as a rigid planning document but an active document that shall be revised and improved, as and when required, throughout the implementation stage. Proper execution of the EMP is expected to result in minimal adverse impacts on the surrounding environment and its natural resources. The plan shall outline the responsibilities of the various parties involved in the Project, the environmental requirements for the Project and specifies mitigation measures and environmental monitoring and audit that must be implemented during construction stage. The EMP shall be prepared and implemented to ensure compliance to the JKR EMS ISO 14001. Integral to EMP is the establishment of a monitoring program that serves as a quantitative feedback mechanism on the effectiveness of the mitigation measures. Essentially, the monitoring program is a set of procedures targeted towards periodical measurement of environmental indicators that provides a platform to evaluate environmental performance through comparisons against baseline and compliance levels. Selection of environmental components to monitor, their locations, parameters and frequency of monitoring are governed by the EIA approval conditions or by a Registered Environmental Consultant (if no EIA was carried out for the project). As a norm, monitoring is centered on the issues of water, noise and air qualities likely to be impacted upon by the Project. The auditing procedure and schedule shall be detailed out in the EMP. The audit shall focus on the implementation of the EMP and/or other environmental management elements. The environmental auditor shall have the necessary expertise and experience to execute the tasks diligently and professionally in accordance with the requirements of JKR EMS: MS ISO 14001 and shall undertake the following tasks:(a)
To carry out environmental compliance audits quarterly and closure audit on completion of the project;
(b)
To evaluate monitoring data for water, air, noise qualities and if applicable vibration qualities;
(c)
To verify implementation of corrective and preventive action findings on adequacy of compliance to the EMP and/or JKR EMS ISO 14001;
(d)
To prepare a comprehensive environmental auditing report in compliance to elements as stated in the EMP and/or JKR EMS ISO 14001;
12
2.3
Operational/Post Construction Stage
Upon submission and acceptance of the closing audit at the end of the construction period, monitoring of operational activities in compliance to the necessary laws and regulations is encouraged to be continued during the post construction stage in order to ensure that the operational stage of the project does not cause any environmental damage. The impact of generated wastewater has been deemed to be the more significant residual impact that requires further monitoring. The quality of any wastewater discharged must comply with the limits as stipulated by the Environmental Quality (Sewage) Regulations 2009. 2.4
Applicable Guidelines
The use of the relevant Guidelines in the planning/design stage of the project is deemed necessary in order to ensure the project activities do not violate any applicable laws and regulations. The guidelines need to be used in respect to the project site specific conditions. The General guidelines applicable are as follows:Area to be developed
Applicable Guidelines
General Sites
Hill slope and Sensitive Sites
Coastal Sites
Guidelines for the Environmental Impact Assessment of Highway/Road Projects, JKR Malaysia Environmental Impact Assessment Guidelines for Housing and New Township Development Project, DOE 2003 Urban Storm Water Management Manual for Malaysia (Manual Saliran Mesra Alam Malaysia), JPS 2000 Guidelines for Prevention and Control of Soil Erosion and Siltation in Malaysia, DOE 1996 Environmental Audit Guidance Manual, DOE 2009 Submission checklist for stormwater management in Malaysia, DID 2008 Cabinet Committee Guidelines on Hill slope development; KPKT Guidelines for Development of Hilly Areas, JPBD 2009; JKR Manual on Slope Maintenance JPS Guidelines 1/97 Erosion Control for Coastal Development Area, 1997; Planning Standards for Coastal Areas, JPBD Planning Standards for the Physical Development of Islands, JPBD
Note: The above guidelines are not exhaustive.
13
CHAPTER 3 CONTRACTUAL REQUIREMENTS
14
CHAPTER 3:
CONTRACTUAL REQUIREMENTS
Environmental protection and enhancement works for conventional contract projects are to be specified in the Instructions to Tenderer (ITT) and Conditions of Contracts. These shall form part of the pre bid document to be prepared for Conventional Contract projects.
3.1
Instructions to Tenderer (ITT)
As stated in the Contract Specification issued by JKR on behalf of the Government of Malaysia, the Contractor shall comply with all legal duties and obligations regarding the protection of the environment as laid down in the Environmental Quality Act 1974 (Act 127). Before the commencement of works Contractor shall submit to the Superintendent Officer (S.O.), an Environmental Management Plan (EMP), detailing the Contractor‟s proposed arrangement for the abatement and mitigation measures for environmental protection, environmental monitoring, testing programmed and reporting, and his organisation chart.
3.2
Conditions of Contract
Within forty-five (45) days from the Letter of Acceptance, the successful tendered shall submit for the S.O.‟s approval an Environmental Management Plan (EMP) as specified. In the event if the contractor fail to submit such plan, then the government deserves the right to prepare such plan and the cost incurred shall be deducted from the contract sum. The cost of preparing the EMP shall include the cost involved in obtaining the services of a Registered Environmental Consultant and is deemed to be borne by the Contractor. The Environmental Impact Assessment (EIA) report and the Conditions of Approval given by the Department of Environment (DOE), where possible, will be made available by the Government to assist the Contractor and the environmental consultant in preparing the EMP.
3.3
Design and Build Contract
For design and build contract, reference shall be made to the need statement pertaining to environmental protection and enhancement requirements. The need statement is as appended in appendix 2 of this document.
15
CHAPTER 4 SPECIFICATIONS
16
CHAPTER 4:
SPECIFICATIONS
This section contains the specification relating to environmental matters in the execution of JKR projects in line with JKR EMS: MS ISO 14001 and shall be read in conjunction with the Standard Specification for Buildings, Road Works and JKR Green Mission. However where these matters appear also in other sections of the Contract Document, this specification shall take precedence.
4.1
Legislation and Regulations
The Contractor shall at all times adhere to all existing statutes regarding the protection of the Environment. Prior to the execution of the project, the Contractor shall comply with the Environmental Quality Act (EQA) 1974 (Act 127) and other related environmental legislation including, but not limited to:
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k)
National Land Code (Act 56 of 1965) Town and Country Planning Act 1976, (Act 172) Street, Drainage and Building Act, 1974: Act 133 and Amendment, 1978 Protection of Wildlife Act, 1972 (Act 76) Forestry Act 1984 (Act 313) Land Conservation Act 1960 (Act 385) Occupational Safety and Health Act 1994 (Act 514) Solid Waste and Public Cleansing Management Act 2007 (Act 672) Federal Territory (Planning) Act 1982 (Act 267) Workers Minimum Amenities Act 1990 (Act 446) Local Government Act 1976 (Act 171)
The Contractor shall be liable for and shall indemnify the Government against any damages, expenses, liability, losses, claims, prosecution, proceedings, fines and penalties caused by any non-compliances or contraventions of the above legislation and regulations.
4.2
Environmental Impact Assessment (EIA)
In line with EQA 1974, Act 127, Section 34A (1-8), the Contractor shall submit a report on project‟s impact on the environment if the project is listed as prescribed activities in the Environmental Quality (Prescribed Activities) (EIA) Order, 1987. The report should be prepared in accordance with the requirements as per the latest “A Handbook of EIA Guidelines” by the Department Of Environment.
17
4.3
Environmental Management Plan (EMP) & Applicable Elements 4.3.1
Objectives The main objective of the Environmental Management Plan (EMP) is to set out a comprehensive programmed which will form the basis for implementing environmental mitigation measures, environmental monitoring and environmental auditing of the construction works by the Contractor as listed below:(i)
To set out various environmental protection / conservation measures that conform to the environmental conditions stipulated in the Specifications, EIA report and by other relevant authorities (e.g. the Department of Environment (DOE);
(ii)
To ensure that the Contractor comply with all applicable environmental standards and guidelines, legislative requirements and other relevant conditions related to the environment;
(iii) To specify a detailed environmental monitoring and auditing programmed to ensure that the Contractor and all his Sub-contractors comply with all stipulated requirements throughout the duration of the project; and (iv) To streamline the different functions of various sections and authorities related to the environmental matters during construction.
4.3.2
Preparation of the EMP The Contractor shall submit an EMP prepared by a registered environmental consultant and approved prior to commencement of any works on site. The EMP shall be submitted to the S.O. for endorsement within 45 days from the date of Letter of Acceptance in compliance with the Conditions of Contract and/or in compliance with the requirements of the conditions of approval of the EIA report by the Department of Environment. For design and build projects, the need statement shall prevail. The EMP shall make reference to the following but not limited to:(a) (b) (c) (d)
DOE Format for the Preparation of EMPs JKR Environmental Management System (EMS) The approved EIA report EIA Approval Conditions from DOE (attached if any).
It should be clearly noted the EMP is a document for practical use on site by nominated personnel and thus should be concise, up to date and site specific.
18
The execution of the EMP is a joint responsibility of the Contractor, consultant and appointed Environmental officer (EO) for the project. The EO‟s primary responsibility is to ensure the implementation of the EMP and JKR‟s EMS and to monitor and report on the site compliance on a daily basis. 4.3.3
Scope of EMP Scope of EMP is as per DOE Guidelines on Preparation of EMP.
4.3.4
Deliverables The following documents shall be submitted by the Contractor:-
Table 1: Deliverables to be submitted by the Contractor to the S.O./P.D. Documents No. of Reporting Frequency Timing Copies Environmental Management Plan (EMP)
5
Once only (However, EMP should be updated when necessary)
Within 45 days from the date of the Letter of Acceptance and/or as compliance to the conditions of approval of the EIA report
Environmental Quality Report (EQR)
5
Monthly
4 weeks after monitoring
Environmental Monitoring and Audit Report (EMAR)
5
Quarterly
2 weeks after audit
Closure Audit Report (CAR)
5
Once Only
2 weeks prior to issuance of Certificate of Practical Completion (CPC)
Note: To ensure consistency, a standard reporting format for EMP, EQR, EMAR and CAR is provided in Appendix 3.
19
4.4
Site Office and Facilities 4.4.1
4.4.2
Site office, workshop, canteen and store (a)
The Contractor shall provide and maintain on site, suitable and sufficient offices for the S.O., his representatives and the Contractor own use.
(b)
The Contractor shall also provide and maintain on site suitable workshops and stores with impervious flooring including grease traps.
(c)
The Contractor is prohibited from discharging oil and grease to any watercourses. Any spilled oil and grease shall be promptly removed and this contaminated waste shall be kept in proper containers. Used oil and grease shall be kept in separate containers for recycling. All containers shall be stored in secured areas prior to disposal by a licensed contractor as per the Environmental Quality (Scheduled Wastes) Regulations 2005.
Accommodation for Workmen (a)
The Contractor shall provide and maintain on site, suitable and sufficient accommodation and camps for his workmen and supervisory staff as required in the Contract.
(b)
The location of the workmen‟s accommodation shall be agreed beforehand with the S.O. and shall be such as to avoid obstruction and nuisance to the Works and public and shall be laid out in an approved and orderly manner.
(c)
The construction and habitation of the accommodation shall comply with the requirements of all government and local authorities.
(d)
All accommodation for workmen shall be properly ventilated and lighted with sufficient toilet and bathing facilities and waste and refuse collection bins/disposal. Cooking is prohibited in sleeping quarters.
(e)
The Contractor shall also provide adequate supply of water for canteen usage and allowable cooking areas.
(f)
The Contractor shall be wholly responsible for the workmen at the accommodation provided. Activities such as hunting/ trapping of wildlife should be strictly forbidden and fines/ penalties shall be imposed on the Contractor by the relevant Government Departments.
20
4.4.3
Utilities (a)
Water Supply (i)
The Contractor shall provide and maintain a potable water supply system to all facilities required in the construction area. The supply shall be taken from sources approved by the S.O.
(ii)
The Contractor shall submit his plans for the water supply and reticulation system, including filtration, chlorination and other proposed treatment where required, to the S.O. for approval, not less than thirty (30) days prior to the provision of water supply.
(iii) Potable water shall comply with the requirements of Ministry of Health Standards. (b)
Sanitation (i)
The Contractor shall provide and maintain sufficient toilets at appropriate locations on site as approved by the S.O. Toilets shall be complete with adequate water closets, urinals and handbasins, and proper sanitary system.
(ii)
The Contractor shall maintain all toilets in a clean and sanitary condition and shall comply with requirements of the Ministry of Health.
(iii) All wastewater must be treated such that its discharged effluent meets the requirements of all existing legislation and regulations. (c)
Solid waste disposal (i)
The Contractor shall undertake the collection and disposal of solid waste such as litter, kitchen and canteen refuse, nonhazardous solid waste including office, workshop and accommodation waste. Solid waste collection shall be made at least twice a week or as and when directed by the S.O.
(ii)
Solid waste shall be stored in proper bins and containers, collected and disposed off at designated site(s) approved by the S.O. or to a locally available landfill by a licensed contractor.
(iii) A waste management schedule shall be set up to ensure that licensed contractors carry out the collection and disposal of waste materials at regular intervals. Proper facilities for the temporary collection of solid waste shall be established at the site office for construction debris and solid waste.
21
(iv) The Contractor should adopt ways to minimize waste such as reduce, reuse and recycle of waste. Example of waste minimizations is to reduce the amount of waste from concrete usage, first is by ordering the correct quantity and batch or by using concrete panels. Excess concrete can then be recycled as concrete blocks and bench or reused as hardcore materials.
4.5
Site Clearing and Earthworks No site clearing and earthworks shall be carried out prior to EMP approval by relevant parties/authorities. 4.5.1
Site Clearing (a)
Site clearing shall be done in stages and within construction limit. No burning of cleared vegetation and debris shall be allowed unless prior approval has been obtained from the Director General of the Department of Environment.
(b)
Erosion mitigating measures shall be installed or constructed before commencement of site clearing and earthworks. This includes planning for „work in stages‟ and also plans for diverting as much as possible surface runoff from the work areas.
(c)
For road projects, site clearing should be from the centre of the road outwards towards the construction limit to enable escape of wildlife into neighbouring jungles.
(d)
Cleared vegetation and debris should be disposed off to approve designated spoil tips. The Contractor shall be responsible for identifying these disposal areas (unless stated otherwise). The approved disposal areas shall be prepared before any site clearing is allowed to commence.
(e)
Cleared vegetation, debris and spoils should on no account be deposited or pushed into water-courses, streams and rivers.
(f)
Trees and vegetation identified for conservation must be protected by the Contractor at all costs.
(g)
Other clearing activities such as access road construction, site office and work-camp construction, etc shall be carried out with minimal cutting of trees and site clearing. The intended area shall be marked out for the S.O.‟s inspection and approval prior to any site clearing works.
22
4.5.2
(h)
Holes and cavities resulting from clearing, grubbing, de-stumping and de-rooting shall be backfilled with acceptable materials and compacted to approximate densities of adjacent areas.
(i)
The Contractor shall provide all necessary temporary drainage for keeping the site and other areas free of standing water. Efforts must be made to channel the surface runoff as much as possible away from the work areas.
(j)
If due to unforeseen circumstances turfing cannot be carried out immediately to the slope exposed areas, temporary protection/cover (e.g. plastic sheet or equivalent) shall be applied over exposed surfaces by the Contractor at his own cost.
(k)
Should the Contractor fail to ensure compliance with any of the above, the S.O. without prejudice to any other rights or remedies available to the Government under this Contract may employ and pay other persons to execute the work and all costs incurred in connection with such employment shall be recoverable from the Contractor as stipulated in the Conditions of Contract.
Earthworks (a)
All silt traps, sedimentation basins, erosion control measures and drainage system as shown in drawings must be constructed in stages and maintained by the Contractor. The location of these mitigating measures shall be detailed and shown on plan in the EMP for the approval of the S.O
(b)
The Contractor shall provide all necessary temporary drainage for keeping the site and other areas free of standing water before the commencement of any earthworks. Effort must be made to channel the surface runoff as much as possible away from the work areas.
(c)
All temporary drainage, mitigation measures (e.g. silt traps and silt fence) must be constructed before the commencement of any earthworks and shall be maintained throughout the construction period to ensure their effectiveness.
(d)
Unsuitable materials and surplus earth shall be disposed off in designated spoil tips, within the site or off site. Unless otherwise stated, the Contractor shall be responsible for identifying these disposal areas. The dump site/ disposal areas shall be identified and approved by the S.O. before commencement of any earthworks. In the event additional disposal areas (spoil tips) are required, the Contractor shall also be responsible for identifying these disposal areas which shall be approved by the S.O.
(e)
The method of depositing the unsuitable materials and surplus earth to the spoil tips must be properly engineered designed and must be 23
sufficiently graded, leveled, compacted, properly drained, revegetated and approved by the S.O. End-tipping shall not be allowed.
4.6
(f)
The Contractor shall schedule for earthworks to be carried out as much as possible during dry weather periods. This is to ensure that the earthwork activities being carried out are done in a systematic/orderly manner in order to minimise earth surfaces from being exposed for long periods during wet weather periods. Turfing or hydro seeding must be carried out immediately after earthworks and before work on other beam/lift commences. If due to unforeseen circumstances turfing cannot be carried out immediately, temporary protection/cover (e.g. plastic sheets or equivalent) shall be applied to the exposed slopes.
(g)
Should the Contractor fail to ensure compliance with any of the above, the S.O. without prejudice to any other rights or remedies available to the Government under this Contract may employ and pay other persons to execute the work and all costs incurred in connection with such employment shall be recoverable from the Contractor as stipulated in the Conditions of Contract.
Access Roads and Existing Road (a)
All access roads to the site shall be built away from the existing watercourses, streams and rivers with proper drainage system and be paved for a distance of at least 10 meters from where these access roads join existing roads.
(b)
The Contractor shall maintain all access roads including the drainage system throughout the construction period to the satisfaction of the S.O.
(c)
Where the Contractor uses existing/private roads as his access, he shall be responsible for any damage to the existing roads, bridges, drains, culverts, roadside furniture, and all other appurtenances and services on such roads caused by any work carried out by him throughout the construction period. The Contractor shall repair any damages and reinstate the same to their original condition to the satisfaction of the S.O.
(d)
All temporary diversion affecting public/private roads must be approved by the Government, private landowner and the S.O. All such diversions must be equipped with temporary diversion signs and comply with the requirements of Arahan Teknik (Jalan) 2C/85 of JKR. Adequate workmen for controlling traffic diversion must be provided.
24
4.7
Pollution Control 4.7.1
4.7.2
Water quality (a)
All silt fence, silt traps, sedimentation basins and other erosion and sediment control measures as shown in drawings must be constructed and maintained by the Contractor.
(b)
Water quality standards and monitoring schedule from the silt traps/ sedimentation basin/rivers/stream/water bodies shall comply as specified in Table 2 or as directed by the S.O. Silt traps and sediment basin discharges shall be monitored monthly and shall be collected within 30 minutes after a rainfall event of more than 20mm depth or more.
(c)
The Contractor is prohibited from discharging oil and grease to any watercourse. Any spilled oil and grease shall be promptly removed by the Contractor. The Contractor shall collect, keep in proper containers, label and store all used oil and grease and other scheduled wastes according to Environmental Quality (Scheduled Wastes) Regulations, 2005.
(d)
The Contractor shall carry out water quality monitoring at locations on existing water bodies as indicated in the EMP. Parameters to be tested are as specified in Table 2.
Noise Control (a)
All work shall be carried out with least disturbance and noise. The Contractor shall ensure all his equipments and machineries are in proper working condition so as to minimize the amount of noise generated. The S.O. may require the Contractor to replace any machinery that to his discretion is emitting excessive noise.
(b)
The Contractor shall comply with the general recommendations set out in DOE Interim Planning Guidelines for Construction Noise together with any specific requirements described in the Contract.
(c)
The Contractor shall indemnify and keep indemnified the Government, S.O. and the S.O.‟s Representatives against any liability for damages on account of noise or other disturbances created while or in carrying out of the works and from and against all claims, demands, proceedings, damages, costs charges and expenses whatever in regard or in relation to such liability.
25
4.7.3
4.7.4
Air Quality (a)
Open burning of cleared vegetation, debris and construction waste etc, shall not be allowed unless prior approval is obtained from the Director General of the Department of Environment.
(b)
The Contractor shall provide suitable spraying equipment for regular spraying of water over the existing roads, tracks and access roads, near settlements, completed as well as incomplete road and other barren areas of the site used by the contractor especially during the dry season or as and when directed by the S.O.
(c)
When the Contractor‟s trucks or equipment utilizes public or private roadways, all dirt and materials shall be removed from the trucks/ equipments by hosing, lorry wash-trough, etc. before leaving the site.
(d)
The Contractor shall provide for the prompt removal of all dirt and other materials spilled from his or his sub-contractor‟s vehicles on public or private roadways.
(e)
For Contractor‟s trucks carrying sand, aggregates, earth and other loose construction materials liable to spillage, tarpaulin must be used to cover such open trucks when passing through villages and settlements or on all roadways.
(f)
The Contractor shall also ensure dust control at quarry / batching plant (if any) complies with environmental requirement as stipulated in the Environmental Quality (Clean Air) Regulations, 1978.
Vibration control (a)
All works shall be carried out with least vibration disturbance. The Contractor shall ensure that at any time, the vibration levels resulting from his works at or across real property boundary should not exceed the Recommended Limit as Specified in Table 2 of this document. No person unless duly authorized by law or carrying our legitimate duties shall use explosives or results in explosions which create a vibration disturbance across a real property boundary or on a public space or right of way.
(b)
The Contractor shall comply with the general recommendations set out in DOE Interim Planning Guidelines for Vibration Limits and Control in the Environment together with any specific requirements described in the Contract.
26
(c)
The Contractor shall indemnify and keep indemnified the Government, S.O. and the S.O.‟s Representatives against any liability for damages on account of vibration disturbance created while or in carrying out of the works and from and against all claims, demands, proceedings, damages, costs charges and expenses whatever in regard or in relation to such liability.
27
Table 2: Environmental Quality Standards to be complied with by the Contractor Environment Quality (Sewage) Regulations, 2009 Aspects
Parameter
Soil loss
Soil
Turbidity
Water 1,2
JKR EMS Set Target
Standard A
Minimum earthwork Phase construction 6 berms/bench es for slopes ( 6m per berm) Reuse topsoil ≤ 200 NTU
-
Standard B
National Water Quality Standards (NWQS)
Class IIA
Class IIB
-
≤ 50 NTU
≤ 50 NTU
Suspended Solid
≤ 100 mg/l
≤ 50 mg/l
≤ 100 mg/l
≤ 50 mg/l
≤ 50 mg/l
Biochemical Oxygen Demand 5 @ 20°C (BOD)5
≤ 50 mg/l
≤ 20 mg/l
≤ 50 mg/l
≤ 3 mg/l
≤ 3 mg/l
Chemical Oxygen Demand (COD)
≤ 100 mg/l
≤ 120 mg/l
≤ 200 mg/l
≤ 25 mg/l
≤ 25 mg/l
pH
5.5 – 9
6–9
5.5 – 9
6-9
6-9
E-Coli
≤ 400 counts / 100 ml
-
-
≤ 100 counts / 100ml
≤ 400 counts / 100ml
Dissolved Oxygen (DO)
≥ 4 mg/l
-
-
5-7 mg/l
5-7 mg/l
Oil and Grease
≤ 10 mg/l
≤ 5 mg/l
≤ 10 mg/l
≤ 40 µg/l, N
≤ 40 µg/l, N
-
≤ 10 mg/l
≤ 20 mg/l
≤ 0.3 mg/l
≤ 0.3 mg/l
Ammoniacal Nitrogen
(river) Total Suspended Particulate (TSP) (24hr)
≤260 µg/m3/day
Particulate Matter (PM10) (24hr)
≤150 µg/m3/day
Air3
28
Receiving Land Use (residential) Equivalent Noise Level (Leq), L10, L90
Day time (7.00 am – 7.00 pm ) L90 ≤ 60 dBA; L10 ≤75 dBA; Lmax ≤ 90 dBA; Evening (7.00 pm – 10.00 pm) L90 ≤55 dBA; L10 ≤70 dBA; Lmax ≤ 85 dBA;
Noise4
Night time (10.00 pm – 7.00 am) Noise Sensitive Areas : LAeq ≤40 dBA Suburban Areas : LAeq ≤ 45 dBA Urban Areas : LAeq ≤ 50 dBA Vibration5
Vertical Vibration Peak Velocity (mm/s)
Not more than 3 mm/s at receiver location or across real property boundary.
Reference: (1)
2nd Schedule (Regulation 7), Environmental Quality (Sewage) Regulations 2009, Environmental Quality Act 1974. Standard A: Standard B:
(2)
For location with downstream water intake For location with no downstream water intake
National Water Quality Standards for Malaysia Class IIA: Class IIB:
Water Supply II – conventional treatment required Fishery II – sensitive aquatic species Recreational use with body contact
(3)
Recommended Malaysian Guidelines on Ambient Air Quality
(4)
Schedule 1 & Schedule 6, Planning Guidelines for Environmental Noise Limits & Control, (Department of Environment, 2004)
(5)
Planning Guidelines for Vibration Limits and Control of the Environment (Department of Environment, 2004)
Note: N – No visible floatable materials or debris or no objectionable odour, or no objectionable taste.
29
4.8
Preservation of Flora and Fauna 4.8.1
Flora (a)
Prior to site clearing, the forester and/or botanist engaged by JKR or Contractor shall assist the surveyor to identify any trees of rare, endemic or endangered species which need to be conserved or relocated. Trees which are classified as rare, endemic and endangered shall be conserved and marked (crossed) red. Similarly, trees having girth of 800mm and above shall be conserved and marked (crossed) red. Trees which are rare, endemic or endangered and required to be relocated shall be marked (crossed) white. Should relocation be required, trees shall have girth of 300mm and below.
(b)
The Contractor shall be responsible for the transportation of trees to nearby sites, arboretum or other alternatives, as advised by the forester. The Contractor shall ensure all relocated trees are well kept.
(c)
The botanist/ forester shall produce a report on the effectiveness of the tree conservation, preservation and action plan as proposed in the EMP as directed by the S.O. The report shall also cover aspects of new findings not covered during the earlier investigation and proposal of any rectification plan required. The felling of trees shall be confined within the construction limit.
(d)
4.8.2
(e)
The Contractor shall prohibit all his and his sub-contractor‟s employees from destroying, removing or clearing trees, timber, shrub and other flora to any extent greater than that approved by the S.O. as being necessary for the execution of the contract.
(f)
The Contractor is prohibited from disposing waste materials amongst vegetation within or outside the work site.
Fauna (Wildlife) (a)
The Contractor and his employees are prohibited from the following:(i)
Hunting, disturbing, capturing, endangering or destroying such wildlife by any means (e.g. poison, baits, bird line or net) as may be protected by relevant statutes including removing or damaging bird nests and eggs.
(ii)
Housing, confining or breeding any wildlife
30
4.9
4.10
Requirements In Relation To Waterways (a)
The Contractor and/or JKR shall seek approval from Jabatan Pengaliran & Saliran (JPS) for any works related to natural waterways including diversions, modifications replacements and/or relocation of rivers, watercourses and related structures during execution of the works.
(b)
The Contractor shall coordinate all operations and make adjustments to his programmed resulting from JPS requirements pertaining to changes made to the natural waterways.
(c)
The Contractor shall ensure that temporary diversions of rivers and/or waterways shall be capable of sustaining flows throughout the year as specified by the JPS.
Erosion and Sediment Control (Temporary works) 4.10.1 Erosion Control (a)
Natural (I).
Bioengineering Vetiver The plant, Vetiver Zizanioodes (Rumput Wangi) shall be non-seeding types tillers derived from tissue culture or micro propagation method. The plantlets to be supplied shall be at least an aggregate of 5 plantlets with roots at least 3 cm long. The Contractor shall plant Vetiver Zizanioodes in rows as specified in the drawings or as directed by the S.O. In difficult soil types, borrowed topsoil may be required to refill trenches for planting the vetiver. The Contractor shall ensure and maintain the growth of the vetiver. Creepers The Contractor shall plant creepers either through seeds or saplings. Commonly used creepers are of the species Centrusemo pubscens, Ficus pumila and Parthenocissus himalayana. Ficus pumila and Parthenocissus himalayana are suitable on concrete/gunited slopes and rock surfaces. Creepers shall be planted into a planter bed previously prepared with drainage layer/weep holes and topsoil. Creepers should be planted individually immediately at the toe of wall/slopes at approximately 0.3m centre to centre. 31
(II)
Mulching Mulch is a protective cover placed over the soil to protect soil from rain, preserve moisture and slows runoff velocity. A variety of materials can be used as mulch such as grass clippings, leaves, hay, straw, shredded bark, sawdust, wood chips, shredded newspaper, cardboard and wool.
(b)
Proprietary products The Contractor may also use proprietary or any man-made products available in the market to control erosion on slopes, subject to JKR‟s approval. The suitability of the products used shall follow the manufacturer‟s specifications including method of installation and maintenance. Examples of propriety products are geotubes, ENKA mat, geocells/geoweb, fibromat and coir logs.
4.10.2 Sediment Control The specification as described under this Section shall be read together with other related sections of the Standard Specification for Road Works or Standard Specification for Buildings and the drawings shall refer to the Chapter 8 - Standard Drawings of this document. (a)
Silt Fence Silt fence shall consist of geotextile supported by poles at regular interval. The geotextile shall be made of non-woven material with minimum properties of 200 g/m² or tensile strength 15 kN/m. shall be constructed as close as possible, parallel to the contours of the site with a setback of at least 0.9 m (3 ft0 from the toe of the slope. The silt fence The fence shall be inspected after every rain. The silt accumulated behind the fence shall be removed when it has reached 2/3 of the fence filter height and disposed at designated site. The geotextile shall be checked for rips, tears and other types of deterioration and replaced as needed.
(b)
Silt Trap/Sediment Basin Silt trap/sediment basin comprises rocks in gabions, shall be constructed in respective catchment area to collect and store sediment prior to entering natural waterways. The silt traps/sediment basins shall be inspected regularly especially after heavy rain and any damages shall be rectified. The sediment
32
accumulated in the silt traps/sediment basins shall be removed when it has reached 2/3 of its depth and disposed at designated site. (c)
Gabion Wall A gabion wall which comprises rocks in gabions but of smaller nature compared to silt trap, shall be constructed in difficult terrains such as on slopes and narrow valleys for the purpose of collecting and storing sediment prior to entering natural waterways.
(d)
Check Dam A check dam which is a small, temporary or permanent dam shall be constructed across a drainage ditch, swale or channel for the purpose of lowering the speed of concentrated flows. The check dams shall be inspected regularly especially after heavy rain and any damages shall be rectified. The sediment accumulated behind the check dams shall be removed when it has reached 2/3 of its height and disposed at designated site. The height of the check dam shall be maintained to be the same at all time.
(e)
Silt Curtain Silt curtain shall be used to mitigate sediments by confining sediments and prevent dispersal and contamination of the water body especially in lakes and riverbanks. Silt curtain shall also be used as a divider to prevent sediment laden-water from migrating to the rest of the water body. Silt curtain shall be checked for rips, tears and other types of deterioration and replaced as needed. The suspended sediments trapped behind silt curtain shall be allowed to settle for a minimum of 24 hours, prior to removal of the silt curtain.
(f)
Sand bag barrier A sandbag barrier is a series of sand-filled bags placed on a level contour to intercept sheet flows. Sandbag barriers pond sheet flow runoff, allowing sediment to settle out. Sandbag barriers are suitable as a linear sediment control measure which includes below the toe of slopes and erodible slopes, as sediment traps at culvert/pipe outlets, down slope of exposed soil areas, around temporary stockpiles and spoil areas, as check dams across mildly sloped construction roads and parallel to a roadway to keep sediment off paved areas. Sand bag barrier shall be checked daily before and after rain events, In addition, sandbags exposed to sunlight will cause degradation 33
and need to be replaced immediately. Sediment should be removed when the sediment accumulation reaches one-third of the barrier height and disposed at designated site. NOTES: Other items not specified above shall be referred to the Standard Specification for Road Works JKR/SPJ/1988 of Section 1 – General, Section 2 – Earthworks and Section 3 – Drainage Works REFER TO APPENDIX 1 : Standard Specifications For Building Works (2005 Edition):- SECTION A : PRELIMINARIES AND GENERAL CONDITIONS AND SECTION C : EXCAVATIONS AND EARTHWORKS
4.11
Permanent Works 4.11.1 Noise Barrier (a)
Noise barrier shall be provided in sensitive areas such as housing, schools and hospitals situated beside busy roads or highways.
(b)
The type of noise barrier used shall be either absorptive, reflective, dispersive or mixed depending upon the noise level survey conducted or recommendations made by the relevant Consultant.
(c)
The Contractor shall supply and install noise barrier including maintenance until the expiry of the defects liability period.
(d)
For concrete noise barrier, creepers shall be planted and maintained to cover the said noise barrier until the expiry of the defects liability period.
34
CHAPTER 5 METHOD OF MEASUREMENT
35
CHAPTER 5:
METHOD OF MEASUREMENT
Non-Physical Work
5.1
Environmental Impact Assessment (EIA) (If Applicable) 5.1.1
EIA Report Unit The unit of measurement for preparation of EIA Report shall be Lump Sum (sum). Measurement The measurement for payment shall be the preparation and approval of the EIA report in accordance to the format in the Guidelines for EIA of Highway/Road Projects and A Handbook of EIA Guidelines prepared by Department of Environment (DOE). Pricing Factors The item for preparation of the EIA Report shall be in accordance with the Preambles to Bill of Quantities:-
5.2
(a)
Cost of any study required, literatures, references, consultation in the production of the EIA Report;
(b)
Cost for the engagement of a registered environmental consultant required for carrying out the respective study and preparation of the said report;
(c)
Submission of twenty one (21) hard copies and one (1) digital copy of the approved and accepted report to S.O. The copyright of the said documents shall be transferred and become the absolute property of the Government.
Environmental Management Plan (EMP) 5.2.1
Preparation and acceptance of EMP Unit The unit of measurement for preparation and acceptance of EMP shall be Lump Sum (sum) and include: (a)
Erosion and Sediment Control Plan (ESCP)
36
Pricing Factor The item for preparation of ESCP shall be in accordance with the Preambles to Bill of Quantities:(a)
all cost associated in the preparation of a complete report on drainage system, erosion control plan and course of action to be taken;
(b)
additional cost for the engagement of a professional engineer required for the preparation of the ESCP;
(c)
Submission of five (5) copies of ESCP for endorsement by the S.O.
(d)
Flora Management Plan for tree conservation including method of preservation and course of action to be taken
(e)
Wildlife Management Plan for translocation animal to approved location by Jabatan Perhilitan.
Measurement The measurement for payment shall be made upon submission and acceptance of the EMP prepared in accordance to the format as stipulated in the DOE General Checklist for Preparing EMP as follows:(a)
60% upon submission of draft EMP to S.O.;
(b)
40% upon approval of EMP by DOE/JKR
Pricing Factor The item for preparation of EMP including updating and revision shall be in accordance with the Preambles to Bill of Quantities:(a)
Cost of literatures, references, consultation and all that is required and specified for the production of the EMP;
(b)
cost for the engagement of the registered environmental consultant required for the preparation of the EMP including its updating and revision;
(c)
Submission of five (5) copies and one (1) digital copy of the approved and accepted EMP for endorsement by the S.O. The copyright of the said documents shall be transferred and become the absolute property of the Government.
37
5.3
Environmental Officer (E.O.) 5.3.1
Environmental Officer Unit The unit of measurement for provision of E.O. shall be Lump Sum (sum). Measurement The measurement for payment shall be made in each interim payment in proportion of the total period lapsed to the Contract Period (excluding Defects Liability Period). The measurement for payment shall be the man-month basis throughout the contract period (excluding Defects Liability Period). Pricing Factors The item for provision of E.O., assigned to be responsible for environmental management works only, shall be in accordance with the Preambles to Bill of Quantities:(a)
The wages and other emoluments paid to the E.O.;
(b)
Working outside the Contractor‟s normal working hours if so required by the S.O.;
(c)
The Contractor, with the approval of the S.O., shall employ a competent E.O. (A Graduate in science and/or engineering field with a minimum of one year experience in the environmental sector);
(d)
Costs and expenses incurred consequent upon the employment or hiring of a competent full time E.O. throughout the contract period including payment of Employee Provident Fund, insurance, medical and hospitalization;
(e)
Costs and expenses incurred for the training/awareness briefing by the E.O. to site personnel whose activities have impact on the environment;
(f)
Replacement of incompetent E.O. to the equivalent level or higher to the approval of the S.O.;
(g)
Any substitution when the appointed E.O. is absent or on leave for more than three (3) consecutive days.
38
5.4
Environmental Monitoring, Audit And Training 5.4.1
Environmental Monitoring 5.4.1 (i) 5.4.1 (ii) 5.4.1 (iii) 5.4.1 (iv)
Water Quality Monitoring Air Quality Monitoring Noise Monitoring Vibration Monitoring
Unit The unit for measurement to conduct the above monitoring shall be Lump Sum (sum) for the whole duration of the contract. Measurement The measurement for payment shall be the number of samples taken for monitoring, tested and accepted by the S.O. Pricing Factor The item to conduct environmental monitoring (water, air, noise and vibration) shall be in accordance with the Preambles to Bill of Quantities:(a)
Provision of all necessary equipments as specified;
(b)
Carrying out calibration of all necessary equipments prior to use;
(c)
Taking samples according to the intervals, parameters and for the duration specified at approved sampling locations by trained laboratory personnel;
(d)
Recording and noting of specified data;
(e)
Sending samples collected, testing and analysis at approved independent accredited laboratory. The analysis report shall be signed by a registered chemist;
(f)
Submission of analysed results for purpose of reporting (preparation of monitoring report is measured separately).
5.4.1 (v)
Environmental Quality Report
Unit The unit of measurement for the preparation of submission of the Environmental Quality Report shall be Lump Sum (sum) for the whole duration of the contract. 39
Measurement The measurement for payment shall be the number of reports prepared based on monitoring carried out and accepted by the S.O. Pricing Factor The item for preparation of the monitoring report shall be in accordance with the Preambles to Bill of Quantities:-
5.4.2
(a)
Cost associated in the preparation of a comprehensive report;
(b)
Submission of five (5) copies of report to S.O.
Environmental Audit and Closure Audit Unit The unit of measurement to conduct environmental audit and preparation of environmental monitoring and audit report shall be Lump Sum (sum) for the whole duration of the contract. Measurement The measurement for payment shall be the number of reports prepared based on audits carried out and accepted by the S.O. Pricing Factor The item to conduct environmental audit and preparation of report including the Closure Audit Report shall be in accordance with the Preambles to Bill of Quantities:(a)
Cost and expenses incurred consequent upon the engagement of a competent, independent environmental auditor, registered with DOE and/or have attended courses on ISO 14001 auditing with a minimum of auditing experience for at least 3 sites;
(b)
Cost of carrying out quarterly audits or at any other intervals deemed necessary due to the nature of works on site, evaluation of monitoring data and verifying implementation of corrective and preventive actions;
(c)
Cost associated in the preparation of a comprehensive report including recommendations for improvement in accordance with the Standard Report Format as specified in Appendix 2 of this Document;
40
(d)
5.4.3
Submission of five (5) copies of report (per audit) with colour photographs to S.O.
Training Unit The unit of measurement for training shall be in number (no). Measurement The measurement for payment shall be the number of training sessions carried out for the duration of the contract. Pricing Factor The item for training JKR personnel shall be in accordance with the Preambles to Bill of Quantities:(a)
Cost associated in organizing and conducting training of JKR personnel locally pertaining to Environmental Management, EIA, Safety and Health, Environmental related legal and other requirements.
Physical Work 5.5
Dust and Mud Control 5.5.1
Water Bowser Truck Unit The unit of measurement for provision, operation and maintenance of water bowser truck shall be in number (no). Measurement The measurement for payment shall be the number of water bowser truck provided on site and shall be made as follows:(a)
60% on complete provision of vehicle and equipment to the satisfaction of the S.O.;
(b)
40% for operation and maintenance which shall be made in each interim payment in proportion of the total period lapsed to the Contract Period (excluding Defects Liability Period).
41
Pricing Factor The item for provision, operation and maintenance of bowser truck shall be in accordance with the Preambles to Bill of Quantities:-
5.5.2
(a)
All cost associated with the provision and operation of trucks including operators, water supply, pumping of water, water tank and all other necessary equipments needed to carryout water spraying;
(b)
Carrying out water spraying minimum 3 times a day along haul/access roads, existing road and nearby settlement zone or other affected areas or as directed by S.O.;
(c)
Maintenance in a roadworthy condition of trucks and associated equipments;
(d)
Provision of suitable replacement including equipment when the regular truck is not available or unserviceable for more than 24 hours;
(e)
Removal of truck and equipment from site on completion of the works.
Tyre Washing Facilities 5.5.2 (i)
Portable Water Jet
Unit The unit of measurement for provision, operation and maintenance of portable water jet shall be in number (no). Measurement The measurement for payment shall be the number of portable water jet provided on site and shall be made as follows:(a)
60% on complete construction of structure, platform, provision and installation of all equipments to the satisfaction of the S.O.;
(b)
40% for operation and maintenance which shall be made in each interim payment in proportion of the total period lapsed to the Contract Period (excluding Defects Liability Period).
Pricing Factor The item for provision, operation and maintenance of portable water jet shall be in accordance with the Preambles to Bill of Quantities:-
42
(a)
cost of construction and maintenance of the structure for the elevated water tank and the supply of the water tank;
(b)
cost for the construction of the tyre washing concrete platform;
(c)
provision of portable water jet including operator and other necessary equipment deemed required for the successful washing operation;
(d)
carrying out cleaning of all vehicle tyres at various exits of worksites;
(e)
maintenance of all cleaning facilities and associated equipments;
(f)
provision of replacement when the regular equipment is not available or unserviceable for more than 24 hours;
(g)
demolition, and disposal of all rubbish, debris and surplus material including removal of all equipment from site on completion of the works to the satisfaction of the S.O. including reinstatement of the site.
5.5.2 (ii)
Wash Trough
Unit The unit of measurement for construction and maintenance of wash trough shall be in number (no). Measurement The measurement for payment shall be the number of wash trough constructed on site as shown in Drawing and shall be made as follows:(a)
80% on complete construction to the satisfaction of the S.O.;
(b)
20% for maintenance which shall be made in each interim payment in proportion of the total period lapsed to the Contract Period (excluding Defects Liability Period).
Pricing Factor The item for construction and maintenance of wash trough shall be in accordance with the Preambles to Bill of Quantities:(a)
Preparation of site and approaches including excavation and disposal of surplus excavated material; 43
5.5.3
(b)
Construction of wash trough including concrete, formwork, reinforcement, hardcore complete as shown in Drawing;
(c)
Filling and regular maintaining of water during the course of the works;
(d)
Maintenance of wash trough and surrounding areas clean including desalting and disposal of material;
(e)
Demolition and disposal of all rubbish, debris and surplus material from the site to the satisfaction of the S.O. including reinstatement of the site.
Water Sprinkler Unit The unit of measurement for provision and maintenance of water sprinkler shall be in number (no) Measurement The measurement for payment shall be the number of water sprinkler installed at quarry/batching plant and shall be made as follows:(a)
40% on complete installation;
(b)
60% for operation and maintenance which shall be made in each interim payment in proportion of the total period lapsed to the Contract Period (excluding Defects Liability Period).
Pricing Factor The item for provision and maintenance of water sprinkler shall be in accordance with the Preambles to Bill of Quantities:(a)
Supply and installation of water sprinkler system including all other necessary equipments and facilities;
(b)
Maintenance of water sprinkler system and associated equipments;
(c)
Removal of all installation on site to the satisfaction of the S.O.
44
5.6
Erosion Control 5.6.1
Creepers Unit The unit of measurement for planting and maintenance of creepers shall be square metre (m²). Measurement The measurement for payment shall be made of the plan area placed to the lines, level grades and dimensions shown in Drawing or as directed by the S.O. Pricing Factor The item for planting and maintenance of creepers shall be in accordance with the Preambles to Bill of Quantities:(a)
Removal of debris from the surfaces of earthwork to be turfed;
(b)
The preparation of the areas to be turfed including if appropriates the amount of topsoil to be used and its method of application;
(c)
The details and results of investigations to determine which types of grass and legume are compatible with the soil in the areas to be turfed;
(d)
The types of grass and legume (if any) and strains of seed to be used, and the function, root and growth characteristics of each type;
(e)
The rates of application of the grass and legume seeds;
(f)
The type of mulch to be used and its method and rate of application;
(g)
The amount of lime or other chemicals (if any) to be applied to improve the soil before, during and after turfing;
(h)
The equipment and methods to be used in preparing and placing the turf mix and other materials;
(i)
The cultivation and after – care of the turfed areas, including rates and frequencies of watering, fertilising, grass cutting and general maintenance for 1 year after turfing;
(j)
An estimate of the time required after turfing for establishment of a permanent dense growth of grass which will require minimal maintenance.
45
5.6.2
Artificial Erosion Control Items Unit The unit of measurement for installation and maintenance of artificial erosion control items shall be square metre (m²). Measurement The measurement for payment shall be made of the plan area placed to the lines, level grades and dimensions shown in Drawing or as directed by the S.O. Pricing Factor The item for installation and maintenance of artificial erosion control items shall be in accordance with the Preambles to Bill of Quantities:-
5.7
(a)
Removal of debris from the surfaces of earthwork to be artificially controlled;
(b)
The preparation of the areas to be artificially controlled including (if any) the amount of topsoil to be used and its method of application;
(c)
The details and results of investigations to determine which types artificial erosion control items used are compatible with the soil in the areas to be artificially controlled;
(d)
The types of artificial erosion control items (if any) and strains of artificial erosion control items to be used, and the function, root and growth characteristics of each type;
(e)
The type of artificial erosion control items to be used and its method and rate of application including equipments and maintenance required.
Sediment Control 5.7.1
(i)
Construction of Silt Fence Unit The unit of measurement for construction of silt fence shall be linear metre (m). Measurement The measurement for payment shall be the length of complete fence constructed as shown in Drawing and shall be made as follows:-
46
(a)
80% on complete construction to the satisfaction of the S.O.
(b)
20% on removal
Pricing Factor The item for construction of silt fence shall be in accordance with the Preambles to Bill of Quantities:-
5.7.1
(ii)
(a)
Clearing of site for base preparation;
(b)
Construction of silt fence complete as shown in drawing;
(c)
Removal and disposal of all rubbish, debris and surplus material from the site
(d)
To the satisfaction of the S.O. including reinstatement of the site
Maintenance of Silt Fence Unit The unit of measurement for maintenance of silt fence shall be linear metre (m). Measurement The measurement for payment shall be made in each interim payment in proportion of the total period lapsed to the Contract Period (excluding Defects Liability Period). Pricing Factor The item for maintenance of silt fence shall be in accordance with the Preambles to Bill of Quantities:(a)
Inspection at regular interval and after heavy rain of geotextile and other components for rips, tears and other types of deterioration and replacement if required;
(b)
Removal of silt and sediment accumulated to approximate 2/3 of filter height including its disposal.
47
5.7.2
Sand bag barrier 5.7.2
(i)
Installation of sand bag barrier Unit The unit of measurement for Installation of sand bag barrier shall be in number (no).
Measurement The measurement for payment shall be the number of sand bag barrier constructed as shown in Drawing and approved by the S.O. and made as follows:(a)
80% on complete construction to the satisfaction of the S.O.;
(b)
20% on removal
Pricing Factor The item for construction of installation of sand bag barrier shall be in accordance with the Preambles to Bill of Quantities:(a) 5.7.2
(ii)
Labour required for installation purposes;
Maintenance of sand bag barrier Unit The units of measurement for maintenance of sand bag barrier shall be in number (no). Measurement The measurement for payment shall be maintenance of the completed sand bag barrier and shall be made in each interim payment in proportion of the total period lapsed to the Contract Period (excluding Defects Liability Period). Pricing Factor The item for maintenance of sand bag barrier shall be in accordance with the Preambles to Bill of Quantities:-
48
5.7.3
(a)
Sand bag barrier shall be checked daily before and after rain events, weekly during the rainy season, and at two-week intervals during the non-rainy season.
(b)
Sediment should be removed when the sediment accumulation reaches to approximate 1/3 of the barrier height and it has to be incorporated into earthwork on the site or disposed at an appropriate location.
Silt Trap & Sediment Basin 5.7.3
(i)
Gabion Unit The unit of measurement for construction of gabion units in silt traps or sediment basins shall be in number (no) Measurement The measurement for payment shall be the number of specified size gabion unit constructed as shown in Drawing and approved by the S.O. and made as follows:(a)
80% on complete construction to the satisfaction of the S.O.;
(b)
20% on removal
Pricing Factor The item for construction of gabion units in silt traps and sediment basins shall be in accordance with the Preambles to Bill of Quantities:(a)
Excavation for preparation of the silt trap and disposal of surplus excavated material;
(b)
Construction of gabion overflow including cage, geotextile and rock fill complete as shown in Drawing;
(c)
Assembling, tying and staking for the positioning of the gabion units. ;
(d)
Removal and disposal of all rubbish, debris and surplus material from the site to the satisfaction of the S.O. including reinstatement of the site
49
5.7.3
(ii)
Sand Bedding Unit The unit of measurement for sand bedding in silt traps or sediment basins shall be in cubic meter (m3). Measurement The measurement for payment shall be the volume of sand bedding constructed as shown in Drawing and approved by the S.O. and made as follows:(a)
80% on complete construction to the satisfaction of the S.O.;
(b)
20% on removal
Pricing Factor The item for construction of sand bedding in silt traps and sediment basins shall be in accordance with the Preambles to Bill of Quantities:-
5.7.3
(iii)
(a)
Excavation for construction of the sand bedding and disposal of surplus excavated material;
(b)
Maintenance of the sand bedding to effectively control siltation and sedimentation.
Stone Filling Unit The unit of measurement for construction of stone filling in silt traps or sediment basins shall be in cubic meter (m3). Measurement The measurement for payment shall be the volume of stone filling constructed as shown in Drawing and approved by the S.O. and made as follows:(a)
80% on complete construction to the satisfaction of the S.O.;
(b)
20% on removal
50
Pricing Factor The item for construction of stone filling in silt traps and sediment basins shall be in accordance with the Preambles to Bill of Quantities:-
5.7.3
(iv)
(a)
Excavation for construction of stone filling and disposal of surplus excavated material;
(b)
Maintenance of the stone filling to effectively control siltation and sedimentation.
Mortared Rip Rap Unit The unit of measurement for construction of mortared rip rap in silt traps or sediment basins shall be in cubic meter (m3). Measurement The measurement for payment shall be the volume of mortared rip rap constructed as shown in Drawing and approved by the S.O. and made as follows:(a)
80% on complete construction to the satisfaction of the S.O.;
(b)
20% on removal
Pricing Factor The item for construction of mortared rip rap in silt traps and sediment basins shall be in accordance with the Preambles to Bill of Quantities:-
5.7.3
(v)
(a)
Excavation for construction of the mortared rip rap and disposal of surplus excavated material;
(b)
Maintenance of the mortared rip rap to effectively control siltation and sedimentation.
Excavation for silt trap construction Unit The unit of measurement for excavation of earth for silt traps or sediment basin shall be in cubic meter (m3). 51
Measurement The measurement for payment shall be the volume of earth excavated as shown in Drawing and approved by the S.O. and made as follows:(a) (b)
80% on complete construction to the satisfaction of the S.O.; 20% on removal
Pricing Factor The item for excavation of earth for silt traps or sediment basin shall be in accordance with the Preambles to Bill of Quantities:(a)
5.7.3
(vi)
Excavation for preparation of the silt trap and disposal of surplus excavated material;
Maintenance of Silt Trap or Sediment Basin Unit The units of measurement for maintenance of silt trap or sediment basin shall be lump sum (sum). Measurement The measurement for payment shall be maintenance of the completed silt trap or sediment basin and shall be made in each interim payment in proportion of the total period lapsed to the Contract Period (excluding Defects Liability Period). Pricing Factor The item for maintenance of silt trap or sediment basin shall be in accordance with the Preambles to Bill of Quantities:(a)
Regular inspection and maintenance throughout the construction period as directed by the S.O. and make good and replace any damaged component;
(b)
Removal of silt and sediment accumulated to approximate 2/3 of filter height including disposal;
(c)
Inspection at regular interval and after heavy rain for damage and other types of deterioration and replacement if required
52
5.7.3
(vii)
Temporary Drainage Unit The unit of measurement for provision and maintenance of temporary earth drain shall be cubic metre (m3).
Measurement The measurement shall be the volume of the void formed from the surface of the ground after clearing and excavation of top soils to the lines, levels, grades and dimensions as shown in Drawings or as directed by the S.O. Pricing Factor The item for provision and maintenance of temporary earth drain shall be in accordance with the Preambles to Bill of Quantities:-
5.7.4
(a)
Preparation of site, excavation, leveling, trimming, shaping and compacting surface of excavation to the required lines, levels, grade and dimensions and disposal of surplus excavated material;
(b)
Reinstatement of site on completion of the work, to the satisfaction of the S.O.
(c)
Inspection at regular interval and after heavy rain to check for clogs and sediment-laden;
(d)
Removal of accumulated sediment to disposal site and reshaping of temporary drainage;
Gabion Wall 5.7.4
(i)
Construction of Gabion Wall Unit The unit of measurement for construction of gabion wall shall be in number (no). Measurement The measurement for payment shall be the number of specified size gabion constructed as shown in Drawing and approved by the S.O. and made as follows:-
53
(a)
80% on complete construction to the satisfaction of the S.O.;
(b)
20% on removal
Pricing Factor The item for construction of gabion wall shall be in accordance with the Preambles to Bill of Quantities:(a) (b)
5.7.4
(ii)
Excavation for preparation of bed and disposal of surplus excavated material; Construction of gabion overflow including cage, geotextile and rockfill complete as shown in Drawing;
(c)
Assembling, tying and staking for the positioning of the gabion units;
(d)
Removal and disposal of all rubbish, debris and surplus material from the site to the satisfaction of the S.O. including reinstatement of the site.
Maintenance of Gabion Wall Unit The unit of measurement for maintenance of gabion shall be in number (no). Measurement The measurement for payment shall make in each interim payment in proportion of the total period lapsed to the Contract Period (excluding Defects Liability Period). Pricing Factor The item for maintenance of gabion wall shall be in accordance with the Preambles to Bill of Quantities:(a)
Regular inspection and maintenance throughout the construction period as directed by the S.O. and make good and replace any damaged component;
(b)
Removal of accumulated silt and sediment when full including disposal.
54
5.7.5
Check Dam 5.7.5
(i)
Construction of Check Dam Unit The unit of measurement for construction of check dam shall be cubic metre (m3). Measurement The measurement for payment shall be the volume of rock constructed as shown in drawing and approved by the S.O. and made as follows:(a) 80% on complete construction to the satisfaction of the S.O.; (b)
20% on removal.
Pricing Factor The item for construction of check dam shall be in accordance with the Preambles to Bill of Quantities:-
5.7.5
(ii)
(a)
Excavation for preparation of bed and disposal of surplus excavated material;
(b)
Construction of rock check dam including overflow complete as shown in Drawing;
(c)
Removal and disposal of check dam, all rubbish, S.O. including reinstatement of the site.
Maintenance of Check Dam Unit The unit of measurement for maintenance of check dam shall be cubic metre (m3). Measurement The measurement for payment shall be maintenance of the completed check dam and shall be made in each interim payment in proportion of the total period lapsed to the Contract Period (excluding Defects Liability Period).
55
Pricing Factor The item for maintenance of check dam shall be in accordance with the Preambles to Bill of Quantities:-
5.7.6
(a)
Regular inspection and maintenance throughout the construction period as directed by the S.O. and make good and replace any damaged component;
(b)
Removal of silt and sediment accumulated to approximate 2/3 of filter height including disposal.
Silt Curtain 5.7.6
(i)
Installation of Silt Curtain Unit The unit of measurement for installation of silt curtain shall be square metre (m2). Measurement The measurement for payment shall be the area of curtain constructed as shown in drawing and approved by the S.O. and made as follows:(a)
80% on complete installation to the satisfaction of the S.O.;
(b)
20% on removal
Pricing Factor The item for installation of silt curtain shall be in accordance with the Preambles to Bill of Quantities:-
5.7.6
(ii)
(a)
Installation of silt curtain complete as shown in drawing;
(b)
Removal including of all rubbish, debris and surplus material from the site to the satisfaction of the S.O.
Maintenance of Silt Curtain Unit The unit of measurement for maintenance of silt curtain shall be square metre (m2). 56
Measurement The measurement for payment shall be maintenance of the completed silt curtain and shall be made in each interim payment in proportion of the total period lapsed to the Contract Period (excluding Defects Liability Period). Pricing Factor The item for maintenance of silt curtain shall be in accordance with the Preambles to Bill of Quantities:(a)
5.8
Inspection at regular interval and after heavy rain for rips tears and other types of deterioration and replacement if required.
Topsoil and Finished Slope Temporary Protection 5.8.1
Plastic Sheeting Unit The unit of measurement for plastic sheeting to temporarily cover topsoil and finished slope shall be square metre (m2). Measurement The measurement for payment shall be the area of sheeting laid (laps shall not be measured for payment) as approved by the S.O. and made as follows:(a)
90% on complete installation to the satisfaction of the S.O.;
(b)
10% on maintenance and removal
Pricing Factor The item for installation of plastic sheeting shall be in accordance with the Preambles to Bill of Quantities:(a)
5.8.2
Supply and placing of sheeting to cover topsoil stockpile.
Silt Fence Unit The unit of measurement for construction of silt fence shall be linear metre (m). 57
Measurement The measurement for payment shall be the length of complete fence constructed as shown in drawing and shall be made as follows:(a)
80% on complete construction to the satisfaction of the S.O.
(b)
20% on removal
Pricing Factor The item for construction of silt fence shall be in accordance with the Preambles to Bill of Quantities:-
5.9
(a)
Clearing of site for base preparation;
(b)
Construction of silt fence complete as shown in drawing;
(c)
Removal and disposal of all rubbish, debris and surplus material from the site
(d)
To the satisfaction of the S.O. including reinstatement of the site
Fuel Spillage Management 5.9.1
Containment Bund for Bulk Fuel Tank Unit The unit of measurement for skid tank bund shall be in number (no). Measurement The measurement for payment shall be the number constructed as shown in drawing and approved by the S.O. and made as follows:(a)
70% on complete construction to the satisfaction of the S.O.;
(b)
20% on maintenance;
(c)
10% on removal.
Pricing Factor The item for construction of containment bund shall be in accordance with the Preambles to Bill of Quantities:(a)
Excavation for preparation of base and disposal of surplus excavated material; 58
5.10
(b)
Construction of concrete base, brick wall including grease trap with oil and grease separator overflow complete as shown in Drawing;
(c)
Regular cleaning and maintenance of grease trap, bund and surrounding areas to prevent surface corrosion;
(d)
Installation of proper drainage to bund and surrounding area;
(e)
Demolition, removal and disposal of bund and all rubbish, debris and surplus material from the site to the satisfaction of the S.O. including reinstatement of the site.
Waste Management 5.10.1 Scheduled Waste Disposal 5.10.1 (i)
Storage Shed Unit The unit of measurement for construction of storage shed shall be Lump Sum (sum) Measurement The measurement for payment shall be the shed constructed as shown in Drawing and approved by the S.O. and made as follows:(a)
90% on complete construction to the satisfaction of the S.O.;
(b)
10% on maintenance and removal
Pricing Factor The item for construction of containment bund shall be in accordance with the Preambles to Bill of Quantities:(a)
5.10.1 (ii)
All cost associated with the construction, maintenance and removal of suitable storage shed for the purpose of housing scheduled wastes
Scheduled Wastes Unit The unit of measurement for disposal of scheduled waste shall be Lump Sum (sum). 59
Measurement The measurement for payment shall be the number of consignment of scheduled waste disposed from the project site. Pricing Factor The item for disposal of scheduled waste shall be in accordance with the Preambles to Bill of Quantities:(a)
Identifying the category of scheduled waste generated from the project site as per the 1st Schedule;
(b)
Treating and recovering of scheduled waste generated on site according to the regulations and specification;
(c)
Storing and labeling of scheduled waste as per regulations;
(d)
Delivering of scheduled waste by licensed contractor to prescribed premises for treatment;
(e)
Training of all relevant employees involved in identification, handling, transportation, storage and response to spillage or release of scheduled wastes.
5.10.2 Grease Trap Unit The unit of measurement for grease trap shall be in number (no). Measurement The measurement for payment shall be the number of grease trap constructed as shown in drawing. Pricing Factor The item for construction of grease trap shall be in accordance with the Preambles to Bill of Quantities:(a)
Construction and maintenance of grease trap at kitchen areas, sharing and workshop;
60
5.11
(b)
Skimming of oil and grease from the trap for disposal as scheduled waste;
(c)
Removal of grease traps to the satisfaction of S.O.
Management of Disposal Site for Surplus Material 5.11.1 Earthworks 5.11.1 (i)
Close Turfing Refer to Earthworks Method of Measurement
5.11.1 (ii)
Hydroseeding with fibromat or equivalent Refer to Earthworks Method of Measurement
5.11.1 (iii)
Vertiver Z
Unit The unit of measurement for planting and maintenance of vertiver Z shall be square metre (m²). Measurement The measurement for payment shall be made of the plan area placed to the lines, level grades and dimensions shown in Drawing or as directed by the S.O. Pricing Factor The item for planting and maintenance of vertizer Z shall be in accordance with the Preambles to Bill of Quantities:(a)
Removal of debris from the surfaces of earthwork to be turfed;
(b)
The preparation of the areas to be turfed including if appropriates the amount of topsoil to be used and its method of application;
(c)
The details and results of investigations to determine which types of grass and legume are compatible with the soil in the areas to be turfed;
61
(d)
The types of grass and legume (if any) and strains of seed to be used, and the function, root and growth characteristics of each type;
(e)
The rates of application of the grass and legume seeds;
(f)
The type of mulch to be used and its method and rate of application;
(g)
The amounts of lime or other chemicals (if any) to be applied to improve the soil before, during and after turfing;
(h)
The equipment and methods to be used in preparing and placing the turf mix and other materials;
(i)
The cultivation and after – care of the turfed areas, including rates and frequencies of watering, fertilising, grass cutting and general maintenance for 1 year after turfing;
(j)
An estimate of the time required after turfing for establishment of a permanent dense growth of grass which will require minimal maintenance;
5.11.1 (iv)
Creepers
Unit The unit of measurement for planting and maintenance of creepers shall be square metre (m²). Measurement The measurement for payment shall be made of the plan area placed to the lines, level grades and dimensions shown in Drawing or as directed by the S.O. Pricing Factor The item for planting and maintenance of creepers shall be in accordance with the Preambles to Bill of Quantities:(a)
Removal of debris from the surfaces of earthwork to be turfed;
(b)
The preparation of the areas to be turfed including if appropriates the amount of topsoil to be used and its method of application;
62
5.11.2
(c)
The details and results of investigations to determine which types of grass and legume are compatible with the soil in the areas to be turfed;
(d)
The types of grass and legume (if any) and strains of seed to be used, and the function, root and growth characteristics of each type;
(e)
The rates of application of the grass and legume seeds;
(f)
The type of mulch to be used and its method and rate of application;
(g)
The amount of lime or other chemicals (if any) to be applied to improve the soil before, during and after turfing;
(h)
The equipment and methods to be used in preparing and placing the turf mix and other materials;
(i)
The cultivation and after – care of the turfed areas, including rates and frequencies of watering, fertilising, grass cutting and general maintenance for 1 year after turfing;
(j)
An estimate of the time required after turfing for establishment of a permanent dense growth of grass which will require minimal maintenance;
Drainage Taken from Drainage Works Method of Measurement:4.8
Surface Drain
Unit The unit of measurement for surface drain shall be linear metre (m). Measurement The measurement for payment shall be length measured along the centre line of the drain as shown on the drawings or as directed by the S.O between any of the following: (a)
The external faces of manholes, sump, chambers, and like the like;
(b)
The external faces of headwalls, inlet and outlet structures and the like;
(c)
The intersections of the centre at drain/pipe junctions; 63
(d)
The position of terminations as shown on the drawings; and
(e)
The point of change of stage depth.
In the case of cascade drains, the length shall be measured along the centre line of the projected horizontal plane. No allowance shall be made foe laps. The depth of drains shall be the vertical measurement between the invert and the lowest of the following: (a)
Lower existing ground level at sides;
(b)
Lower formations level at sides;
(c)
At slopes, for the lower finished earthwork level at sides prior to top soiling measured perpendicular to the invert;
(d)
Lower finished earthworks level at sides
The average depth to invert shall be calculated arithmetic means of the depths taken at intervals of 10 metres along the drains starting from the outfall end. For terminal lengths of drains less than 10 metres long, the measurement of depths shall be taken at their ends. Where the depth of drains are not stated, the Contractor shall establish the depth of excavation required from the information provided in the Contract and allow their costs in the rates. Item Coverage The item for the drain shall be in accordance with the Preambles to the Bill of Quantities General Directions and shall include: (a)
Locating existing drains;
(b)
Breaking into existing drains, chambers and the like, dealing with existing flow and making connections unless otherwise measured separately;
(c)
Hand or machine excavation in any material except rock, dewatering upholding the sides, keeping the excavation free of water, backfilling with approved material from any source and compaction;
(d)
Taking precautions to avoid damage to existing works including providing temporary supports;
(e)
Excavation and filling of soft spot with granular backfilling material and compaction; 64
4.10
(f)
Brickworks (including rendering), stonework, filter materials, pipes and fittings including cutting, laying, stepping and jointing;
(g)
Building in drains to sumps, chambers, headwalls and the like;
(h)
Blinding and bedding;
(i)
Concrete bedding hunching and surround and cement mortar;
(j)
Formwork and reinforcement;
(k)
Trimming of sides‟ slopes and inverts, leveling and compaction;
(l)
Stepping of inverts;
(m)
Double handling and disposal of material to dumping site off site provided by the Contractor;
(n)
Movement joints to concrete beds surrounds and the like;
(o)
Reinstatement of surfaces;
(p)
Taking precautions to prevent siltation and desalting prior to handling over;
(q)
Checking and cleaning;
(r)
R.C struts for blocks to drain with brick sides, precast concrete covers (where specified, mild steel gratings, frame and bedding);
(s)
Additional excavation the contractor may require for working space and its subsequent backfilling; and
(t)
Transport, unload, storage and multiple handling of precast concrete drain sections.
Sumps Unit The unit of measurement for sump shall be number (no).
65
Measurement The measurement shall be the number of the completed sump (walls and base) as shown on the Drawing or as directed by the S.O. The depth shall be the distance between the top surface or the structure and the invert if the main channel or upper most surface of the base slab. Item Coverage The item of the sump shall be accordance with the Preambles to the Bill of Quantities General Directions and shall include: (a)
Excavation in any material except rock, upholding the sides, keeping excavation free of water, backfilling with approved material from any source and compaction, double handling and disposal of material;
(b)
Taking precautions to avoid damage to existing works including providing temporary supports;
(c)
Trimming of side slopes and inverts, leveling and compaction;
(d)
Excavation and filling of soft spots with granular backfilling material and compaction;
(e)
Blinding and bedding, hunching and surround material;
(f)
Concrete, formwork and reinforcement;
(g)
Brickworks and rendering for brick sumps;
(h)
Channels, fittings, benching and building, in drains and pipes;
(i)
Steps iron, safety chains, ladders, handholds, anchor irons, bearers support and the like;
(j)
Mild steel grating to suit including frame;
(k)
Reinstatement of surfaces;
(l)
Cleaning and desalting prior to handing over;
(m)
Additional excavation for working space and its subsequent backfilling;
(n)
Movement joints;
66
(o)
5.11.3
Joint filler, sealant and water stops.
Retaining Wall Unit The unit of measurement for construction and maintenance of retaining wall shall be in number (no). Measurement The measurement for payment shall be the number of specified size of the retaining wall as shown in drawing and approved by the S.O. and made as follows:(a)
60% on complete construction to the satisfaction of the S.O.;
(b)
30% for maintenance
(c)
10% on removal
Pricing Factor The item for construction and maintenance of retaining wall shall be in accordance with the Preambles to Bill of Quantities:(a)
Excavation for preparation of bed and disposal of surplus excavated material;
(b)
Construction of gabion overflow including cage, geotextile and rockfill complete as shown in Drawing;
(c)
Assembling, tying and staking for the positioning of the gabion units;
(d)
Removal and disposal of all rubbish, debris and surplus material from the site to the satisfaction of the S.O. including reinstatement of the site.
(e)
Regular inspection and maintenance throughout the construction period as directed by the S.O. and make good and replace any damaged component; Removal of accumulated silt and sediment when full including disposal.
(f)
67
5.12
Flora Management 5.12.1 Flora Survey Unit The unit of measurement to conduct Flora Survey shall be Lump Sum (sum). Measurement The measurement for payment shall be the submission and acceptance of the report by the S.O. Pricing Factor The item for conducting flora survey shall be in accordance with the Preambles to Bill of Quantities:(a)
The costs of literatures, references and consultation in the production of the floral survey report.
5.12.2 Relocation, Transportation and Maintenance of Trees Unit The unit of measurement for relocation, transportation and maintenance of trees with conservation value shall be in number (no). Measurement The measurement for payment shall be upon the completion of the relocation process and acceptance by the S.O. Pricing Factor The item for relocation, transportation and maintenance of trees shall be in accordance with the Preambles to Bill of Quantities:(a)
Trees relocation to approved site and/or arboretum as required by Jabatan Perhutanan;
(b)
Handling, storing and maintaining packages of salvaged trees in well kept condition including safety during relocation and transportation;
(c)
Watering;
(d)
Fertiliser required and nurturing until the flora is established at the temporary nursery and at the final place of relocation. 68
5.13
Wildlife Management 15.13.1 Fauna survey Unit The unit of measurement to conduct fauna survey shall be Lump Sum (sum). Measurement The measurement for payment shall be based on the number of surveys scheduled for the project. Pricing Factor The item to conduct fauna survey shall be in accordance with the Preambles to Bill of Quantities:(a)
Fauna survey prior to site clearing, during middle and end of construction period;
(b)
Preparation and submission of fauna status report.
5.13.2 Wildlife Translocation Unit Allow as provisional sum.
5.14
Noise Control (For permanent works only) 5.12.1 Noise Barrier Unit Allow as provisional sum. The unit of measurement shall be square metre (m²). Measurement The measurement for payment shall be the exposed plain surface area on the traffic side of noise barrier installed according to the specification and approved by the S.O.
69
Pricing Factor The item for construction of noise barrier shall be in accordance with the Preambles to Bill of Quantities:(a)
Site clearing and base preparation;
(b)
Supply and driving of poles;
(c)
Replacement of defective materials and components
70
CHAPTER 6 BILL OF QUANTITIES
71
PROJECT: BILL NO 10: ENVIRONMENTAL PROTECTION WORKS ITEM NO
10.1 10.1.1
10.2 10.2.1
10.3 10.3.1
10.4 10.4.1
DESCRIPTION OF WORKS
UNIT
QTY
RATE
AMOUNT (RM)
NON - PHYSICAL WORKS ENVIRONMENTAL IMPACT ASSESSMENT (EIA) Preparation, submission and approval of EIA Report by environmental consultant registered with Department Of Environment (DOE) ENVIRONMENTAL MANAGEMENT PLAN (EMP) Preparation, submission and approval of EMP by environmental consultant registered with DOE including :(i) Erosion and Sediment Control Plan (ii) Flora Management Plan * (iii) Wildlife Management Plan * ENVIRONMENTAL OFFICER (E.O.) Provision of a full time E.O. for environmental management works only, throughout the contract period for the implementation of EMP and/or JKR EMS : MS ISO 14001 ENVIRONMENTAL MONITORING, AUDIT AND TRAINING Environmental Monitoring i) Water Quality Monitoring a) Conduct monthly river/stream/other water bodies* water quality monitoring as specified and as shown on drawing for the following parameters or as directed by the S.O./P.D.* through out the contract period :1. Turbidity; 2. pH; 3. Total Suspended Solids (TSS); 4. Biochemical Oxygen Demand (BOD); 5. Chemical Oxygen Demand (COD); 6. Dissolved Oxygen (DO); 7. Oil & Grease; 8. E. Coli; 9. Ammoniacal Nitrogen (NH3-N) Carried to Collection 72
sum
sum
sum
sum
SEN
ITEM NO
DESCRIPTION OF WORKS
UNIT
QTY
RATE
AMOUNT (RM)
10.4
NON – PHYSICAL WORKS (cont’d) ENVIRONMENTAL MONITORING, AUDIT AND TRAINING (cont‟d)
10.4.1
Environmental Monitoring (cont‟d) i) Water Quality Monitoring (cont‟d) sum b) Conduct monthly water quality monitoring of the effluent discharge at accommodation, workshop and canteen area as specified for the following parameters or as directed by the S.O./P.D.* through out the contract period :1. Turbidity; 2. pH; 3. Total Suspended Solids (TSS); 4. Biochemical Oxygen Demand (BOD); 5. Chemical Oxygen Demand (COD); 6. Dissolved Oxygen (DO); 7. Oil & Grease; 8. E. Coli; 9. Ammoniacal Nitrogen (NH3-N) c) Conduct monthly water quality monitoring at discharge outlet of silt trap, sediment pond, sediment basin as specified for Total Suspended Solid (TSS) or as directed by the S.O./P.D.* through out the contract period. ii) Air Quality Monitoring Conduct quarterly air quality monitoring for Total Suspended Particulates (TSP) for 24-hour period including wind velocity and direction as specified or as directed by the S.O./P.D.* through out the contract period. iii) Noise Monitoring Conduct quarterly noise monitoring (12 hours average) including Leq, L10 and L90 as specified or as directed by the S.O. /P.D.* throughout the contract period. iv) Vibration Monitoring Conduct vibration monitoring as specified or as directed by the S.O. /P.D.* through out the contract period. Carried to Collection
73
sum
sum
sum
sum
SEN
ITEM NO
10.4 10.4.1
DESCRIPTION OF WORKS
UNIT
QTY
NON – PHYSICAL WORKS (cont’d) ENVIRONMENTAL MONITORING, AUDIT AND TRAINING (cont'd) Environmental Monitoring (cont'd)
a) Monthly environmental quality report
10.4.3
AMOUNT (RM)
v) Environmental Quality Report Preparation of five (5) copies (per month) of the following report through out the contract period :-
10.4.2
RATE
sum
Environmental Audit i) Conduct quarterly audit as specified including preparation of five (5) copies of Environmental Monitoring and Audit Report (per audit) throughout the contract period
sum
ii) Conduct closure audit prior to issuance of certificate of practical completion including preparation of five (5) copies of the report
no
Training i) Local Training Conduct environmental training on site for JKR personnel once a year.
no
PHYSICAL WORKS 10.5
DUST AND MUD CONTROL
10.5.1
Water Bowser Truck Provision, operation and maintenance of bowser truck including operator, pumping of water, water tank and other necessary equipments as specified for carrying out water spraying along haul/access roads, existing roads and near settlements or as directed by the S.O./P.D
Carried to Collection
74
no
1
SEN
ITEM NO
DESCRIPTION OF WORKS
UNIT
RATE
AMOUNT (RM)
PHYSICAL WORK (cont’d) 10.5
DUST AND MUD CONTROL (cont‟d)
10.5.2
Tyre Washing Facilities i) Portable Water Jet Provision, operation and maintenance of portable water jet including operator, water tank and other necessary equipments as specified for carrying out cleaning of vehicle tyres at various exits of the worksites or as directed by the S.O./P.D ii) Wash Trough Construction and maintenance of wash trough including excavation, backfill and disposal of surplus materials, formwork, reinforcement, hardcore and placement of aggregate layer as specified and shown in the drawing or as directed by the S.O./P.D.*
10.5.3
QTY
no
no
Water Sprinkler Provision and maintenance of water sprinkler for controlling dust at quarry/ batching plant as directed by S.O./P.D.*
10.6
EROSION CONTROL
10.6.1
Natural Control
no
Creepers Planting and maintenance of creepers until fully established as specified or as directed by the S.O./P.D.* I) Centrusemo Pubscens II) Ficus Pumila III) Parthenocissus Himalayana IV) ……………… (any other suitable species)
Carried to Collection
75
m2 m2 m2 m2
SEN
ITEM NO
DESCRIPTION OF WORKS
UNIT
10.7
SEDIMENT CONTROL
10.7.1
Silt Fence i) Construction of 1.0m high silt fence including nonwoven geotextile and wooden post with dimension as specified and shown in the drawing or as directed by the S.O./P.D.* ii) Maintenance of silt fence as specified or as directed by the S.O./P.D.*
10.7.3
RATE
AMOUNT (RM)
PHYSICAL WORK (cont'd)
10.7.2
QTY
m
m
Sand Bags i) Supply and lay gunny sack (or equivalent) filled with sand as specified and shown in the drawing or as directed by the S.O./P.D.*
no
ii) Maintenance of sand bags as specified or as directed by the S.O./P.D.*
no
Silt Trap and Sediment Basin i) Gabion cage with rock fill and geotextile including excavation, jointing, backfilling and disposal of surplus materials as specified and shown in the drawing or as directed by the S.O./P.D.* a) 1.0m x 1.0m x 1.0m gabion b) 2.0m x 1.0m x 1.0m gabion c) 2.0m x 1.0m x 0.5m gabion d) 2.0m x 1.0m x 0.3m gabion
no no no no
ii) Sand bedding for silt traps iii) Stone filling at outlet iv) 300 mm thick mortared rip-rap v) Excavation to form silt trap
m3 m3 m2 m3
Carried to Collection
76
SEN
ITEM NO
DESCRIPTION OF WORKS
UNIT
Gabion Wall i) Construction of 1.0m x 1.0m x1.0m gabion cage with rock fill, sand bed and geotextile including excavation, jointing, backfilling and disposal of surplus materials as specified and shown in the drawing and as directed by the S.O./P.D.* ii) Maintenance of gabion wall as specified or as directed by the S.O./P.D.*
10.7.5
sum sum m3
no
no
Check Dam i) Construction of check dam using rocks as specified and as shown in the drawing or as directed by the S.O. ii) Maintenance of check dam as specified or as directed by the S.O./P.D.*
10.7.6
RATE
AMOUNT (RM)
PHYSICAL WORK (cont'd) SEDIMENT CONTROL (cont‟d) vi) Maintenance as specified or as directed by the S.O. a) silt trap b) sedimentation basin vii) Provision and maintenance of temporary earth drain 10.7.4
QTY
m3
no
Silt Curtain i) Installation of silt curtain including non-woven geotextile and floats as specified and as shown in the drawing or as directed by the S.O./P.D.* ii) Maintenance of silt curtain as specified or as directed by the S.O./P.D.*
m2
10.8
TOPSOIL PROTECTION
10.8.1
Provision and maintenance of plastic sheeting to immediately cover topsoil stockpile for turfing and landscaping
m2
10.8.2
Construction of 1.0m high silt fence including nonwoven geotextile and wooden post with dimension as specified and shown in the drawing or as directed by the S.O./P.D.* Carried to Collection
m
77
SEN
ITEM NO 10.9 10.9.1
10.10
DESCRIPTION OF WORKS
UNIT
RATE
AMOUNT (RM)
PHYSICAL WORK (cont'd) FUEL SPILLAGE MANAGEMENT Containment Bund for Bulk Fuel Tank Construct impervious concrete base as per drawing to contain 110% volume of stored fuel including grease trap
no
WASTE MANAGEMENT
10.10.1 Scheduled Wastes Disposal i) Construction of storage shed to temporary house scheduled wastes as specified and as shown in the drawing ii) Disposal of scheduled waste to designated and approved premises
sum
sum
10.10.2 Grease Trap Provision and maintenance of grease traps at kitchen areas, sharing and workshop 10.11
QTY
MANAGEMENT OF DISPOSAL SURPLUS MATERIAL
SITE
no
FOR
10.11.1 Earthworks Protective Vegetation for Erosion Control Plant and maintain until fully establish as specified or as directed by the S.O./P.D.* i) Closed turfing ii) Hydroseeding with fibromat or equivalent iii) Vertiver Z iv) Creepers 10.11.2 Drainage i) Embankment Sump Outlet Reinforced concrete class 25/20 embankment sump outlet including excavation, concrete, reinforcement, leveling, blinding, formworks, RCP, backfilling and all incidentals necessary as shown in drawings or as directed by the S.O./P.D.* Carried to Collection
78
m2 m2 m m2
SEN
ITEM NO
DESCRIPTION OF WORKS
UNIT
QTY
RATE
AMOUNT (RM)
PHYSICAL WORK (cont’d) MANAGEMENT OF DISPOSAL SURPLUS MATERIAL (cont‟d)
SITE
FOR
a) Sump Type S3 internal size 400mm x 600mm x 700mm depth b) …………………………………………
no no
ii) Drains Reinforced insitu concrete class 25/20 in drains at any inclination including excavation, junction, reinforcement, formworks where necessary, joints, stepping, backfilling and disposal of surplus material and all incidental necessary as specified and as shown in Drawings or as directed by the S.O./P.D.* a) Toe Drain Along Toe of Embankment - 450mm invert width, 450mm deep - 600mm invert width, 600mm deep
m m
b) Berm Drain Along Berm of Embankment - 400mm deep
m
c) Embankment Shoulder Block Drain - 300mm half round concrete drain
m
d) Slope Drain Down Embankment (Spillway) - 600mm invert width, 500mm deep
Slope m
10.11.3 Gabion Retaining Wall Construction and maintenance of gabion retaining wall inclusive of geotextile filter and sand drainage blanket and necessary works as specified and as shown in drawings or as directed by S.O./P.D.* i) 2.0m x 1.0m x 1.0m gabion
no
ii) 2.0m x 1.0m x 0.5m gabion
no
iii) 2.0m x 1.0m x 0.3m gabion
no
Carried to Collection
79
SEN
ITEM NO
DESCRIPTION OF WORKS
UNIT
QTY
FLORA MANAGEMENT
10.12.1 Conduct Flora Survey as specified.
no
10.12.2 Relocate, transport and maintain trees with conservation value of girth 300mm and above : i) to nearby sites approved by forester or botanist
no
ii) to arboretum 10.13
AMOUNT (RM)
PHYSICAL WORK (cont'd) 10.12
RATE
2
no
WILDLIFE MANAGEMENT
10.13.1 Conduct Fauna Survey as specified.
no
10.14 NOISE CONTROL (Permanent Works) 10.14.1 Noise Barrier Supply and install noise barrier type as approved by SO/PD* at specified locations as directed by the S.O./P.D.*
Carried to Collection
80
m2
2
SEN
ITEM NO
DESCRIPTION OF WORKS
UNIT
RATE
AMOUNT (RM)
PHYSICAL WORK (cont'd) 10.15 EROSION CONTROL (cont‟d) 10.15.1 Artificial Control Proprietary Products Allow a Provisional Sum of Ringgit ______________________ for the supply, installation and maintenance of proprietary products to be used and expended as directed by the S.O./P.D.* in part or whole or entirely omitted
10.16
QTY
PS
WILDLIFE MANAGEMENT
10.16.1 Allow a Provisional Sum of Ringgit ___________________ to translocation wildlife to sites approved by Jabatan Perhilitan to be used and expended as directed by the S.O./P.D.* in part or whole or entirely omitted
Carried to Collection
81
PS
SEN
CHAPTER 7 BEST MANAGEMENT PRACTICES
82
CHAPTER 7:
BEST MANAGEMENT PRACTICES
Soil Erosion and Sedimentation Control Measures Silt Traps
Courtesy of: Pn.Geetha (Europasia Eng. Services)
Sediment Basins
83
Sediment Basins Outlets
Silt Marker & Desilting Works
Source : Projek Lebuhraya Pantai Timur Fasa 2, Pakej 2
Sand Bag & Grease Trap
84
Silt Fence
Source ::Projek Lebuhraya Pantai Timur Fasa 2, Pakej 2
Silt Curtain
Courtesy of: Wiranda (M) Sdn. Bhd
Gabion Wall
Courtesy of: Pn.Geetha (Europasia Eng. Services)
85
Turfing
Z
Hydroseeding
Sources: Projek Membina dan Menyiapkan Jalan Pos Betau Lembah Bertam, Pahang
86
SCHEDULED WASTE MANAGEMENT
Courtesy of: Pn.Geetha (Europasia Eng. Services)
87
FLORA AND FAUNA MANAGEMENT EXAMPLES OF ANIMAL VIADUCT
Courtesy: Wiranda (M) Sdn Bhd. – Projek Simpang Pulai Lojing – Gua Musang
FLORA SALVAGING
Protected endemic species Rafflesia, found only in Hutan Simpan Belum, Endau Rompin and Taman Kinabalu
88
EXAMPLES OF ENVIRONMENTAL MONITORING 1. Examples of Water / Effluent Quality Monitoring
Source: Projek Trans-Eastern Kedah Interland Highway
89
2. Examples of Air Quality Monitoring
Source: Projek Trans-Eastern Kedah Interland Highway
3. Example of Noise Monitoring
Source: Projek Trans-Eastern Kedah Interland Highway
90
CHAPTER 8 STANDARD DRAWINGS AND FIGURES
91
92
93
Drawing 1: Containment Bund For Skid Tank
94
Drawing 2: Silt Traps
95
Drawing 3: Wash Trough For Construction Site At Urban Area
96
Drawing 4: Wash Trough For Construction Site At Rural Area
97
Drawing 5: Silt Fence
98
Drawing 6: Check Dam
99
Drawing 7: Scheduled Waste Storage Shed
100
Drawing 8: Disposal of Suitable Cut Materials
101
WATER LEVEL JOINT TO SUIT SITE CONDITION GEOTEXTILE SEPARATOR
CONCRETE ANCHORAGE EVERY 6000mm CURTAIN
WIRE ROPE
HARD WOOD PICKET
TYPICAL CONCRETE ANCHOR
CURTAIN ARRANGEMENT
NOTES : ALL DIMENSION ARE IN MILIMETRE UNLESS OTHERWISE STATED
Drawing 9: Silt Curtain
102
Drawing 10: Unsuitable Material Disposal Embankment
103
REFERENCES (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16) (17)
(18) (19) (20) (21) (22) (23) (24) (25) (26) (27) (28) (29)
Environmental Quality Act 1974 (Act 127) & Subsidiary Legislations Department of Environment, 2007: A Handbook of Environmental Impact Assessment Guidelines (4th Edition) Environmental Impact Assessment Guidelines for Highway/Road Project Canter, L.W. (1996). Environmental Impact Assessment. McGraw Hill, Boston. Protection of Wild Life Act 1972 (Act 76). National Forestry Act 1984 (Act 313). Fisheries Act 1985 (Act 317) Town and Country Planning Act 1976 (Act 172) Occupational Safety and Health Act 1994 (Act 514) Street, Drainage and Building Act 1974 (Act 133) Jabatan Kerja Raya EMS ISO 140001 Environmental Manual and Procedure Nota Teknik (Jalan) 22/01 : A Practical Guide to Prepare Bill of Quantities for Environmental Protection and Enhancement Cawangan Jalan, Ibu Pejabat JKR, 50582 Kuala Lumpur, Standard Specification for Road Works : JKR/SPJ/1988 Manual Mesra Alam Malaysia, Jabatan Pengairan dan Saliran Malaysia, 2000 Department of Environment, 1986 : Water quality Criteria and Standards for Malaysia. Ministry of Science, Technology and the Environment, Malaysia Flood Estimation for Urban Areas in Peninsular Malaysia (Hydrological Procedure No. 16), 1976, JPS Malaysia Planning guidelines for the Preservation of Natural Topography in Physical Planning and Development in Accordance with the Town and country Planning Act 1976 (Act 172), the Federal Department of Town and country Planning, Malaysia EIA Guidelines for Forestry, Department of Environment, 2000 EIA Guidelines for Housing and New Township Development Project, Department of Environment, 2003 Department of Environment Guidelines for Soil Erosion and Siltation Malaysia, 1996 Guidelines of Slope Maintenance in Malaysia Morgan, R.P.C., 1987. Soil Erosion and conservation Ed. D.A. Davidson. Longman UK. Corner, E.J. H., 1988. The Wayside Trees of Malaya, 3rd Edition (2 vols). Malayan Nature Society, Kuala Lumpur. David T.J.,1993. Flora of Malaysia. Illustrated. Oxford University Press, Singapore. Giles, R.H. (ed),1969. Wildlife Management Techniques, 3rd Edition. The wildlife Society Washington Henderson, Murry & R, 1974. Malayan Wild Flowers (2 vols). Malayan Nature Society, Kuala Lumpur IUCN, 1994. IUCN Red List Categories. IUCN Special Survival Commission, IUCN Gland John, B. 1993. A Birdwatchers Guide to Malaysia. Wymark Publ. Junaide, P. C.M. Francis & K. Phillips, 1985. A Field Guide to the Mammals of Borneo. The Sabah Society and WWF Malaysia
104
APPENDIX 1 Taken From Section 2.2.8 – Protective Vegetation for Erosion Control of Standard Specification for Roadworks JKR/ SPJ/1988:Standard Specifications For Building Works (2005 Edition):- SECTION A : PRELIMINARIES AND GENERAL CONDITIONS AND SECTION C : EXCAVATIONS AND EARTHWORKS
105
Hydroseeding/Turfing Taken from From Section 2.2.8 – Protective Vegetation for Erosion Control of Standard Specification for Roadworks JKR/ SPJ/1988:Topsoil Topsoil stockpiled for the Works in accordance with SubSections 2.1.1.3 and 2.1.2.3 (of Section 2.2.8 – Protective Vegetation for Erosion Control of Standard Specification for Roadworks JKR/ SPJ/1988) shall be spread and lightly compacted to an even thickness of 50 mm as directed by the S.O. in areas to be turfed and/or seeded, or used as the S.O. shall otherwise direct for tree planting and other purposes. Turfing (i)
Turfing shall be carried out as soon as practicable on all earth slopes and other areas as shown on the Drawings and/or where directed by the S.O.
(ii)
The type of turf shall be as indicated on the Drawings or other alternative type as approved by the S.O. and shall be free of „lalang‟ and essentially free of weeds.
(iii)
Turf shall be obtained in unbroken sods with a substantial amount of topsoil and shall be approximately 250 mm x 250 mm in size and 100 mm thick, from an approved source, and shall be placed in position as soon as practicable after cutting.
(iv)
Turf sods shall be stacked and watered when they cannot be laid immediately after cutting. The surfaces to be turfed shall be trimmed and thoroughly wetted. The turf shall then be carefully laid to form a complete and uniform cover as shown on the Drawings.
(v)
Turf lay on slopes steeper than 1 (vertical) and 3 (horizontal) shall be pegged down with bamboo stakes approximately 250 mm in length.
(vi)
Approved fertiliser shall be applied after lacing of turf at suitable times and at rates of application approved by the S.O. All turf shall be regularly watered and fertilised to the satisfaction of the S.O. until the vegetation is satisfactorily established.
106
(vii)
Any dead turf shall be replaced with new turf at the Contractor's own expense.
Seeding Seeding or hydroseeding shall be carried out as soon as practicable on slopes and other areas as shown on the drawings and/or directed by the S.O. The contractor shall submit to the S.O. for his consideration and approval, at least four (4) weeks in advance of the proposed work, full details of his proposed method of seeding or hydroseeding. The information submitted shall include, but not necessarily be limited to, a full description of the following aspects of the work:(i)
The preparation of the areas to be seeded or hydroseeded, including if appropriate the amount of top soil to be used and its method of application;
(ii)
The details and results of investigations to determine which types of grass and legume are compatible with the soil in the areas to be seeded;
(iii)
The types of grass and legume (if any) and strains of seed to be used, and the function, root and growth characteristics of each type;
(iv)
The rates of application of the grass and legume seeds;
(v)
The composition of fertiliser to be used at the time of seeding and its rate of application;
(vi)
The composition of fertiliser to be used after seeding, the times of application after seeding, and the rates of application;
(vii)
The type of mulch to be used and its method and rate of application;
(viii) The amounts of lime or other chemicals (if any) to be applied to improve the soil before, during and/or after seeding; (ix)
The type and amounts of binding agent to be applied with the seeds, mulch, fertiliser, etc., as appropriate;
(x)
The proportions and methods of preparation of the seeding mix;
107
(xi)
The equipment and methods to be used in preparing and placing the seeding mix and other materials;
(xii)
The cultivation and after-care of the seeded areas, including rates and frequencies of watering, fertilising, grass cutting and general maintenance for at least 1 year after seeding;
(xiii) The time after seeding required for establishing permanent, dense growth of grasses, which will require minimal maintenance; (xiv)
Guarantees of the success of the seeding work. All grass shall be regularly watered until the vegetation is satisfactorily established to the satisfaction of the S.O. Any dead grass shall be replaced at the Contractor's own expense.
SECTION A – Preliminaries and General Conditions 22.
Drainage of Site and Erosion Control 22.1
The Contractor shall make proper provision for the drainage of surface water from the work site including rainwater from surrounding areas which drain on to the Site.
22.2
The Contractor shall at his own cost, provide, form, fix and maintain such pumps, chutes, walls, drains, bunds and other temporary works necessary for the proper drainage of the Site so that no flooding or other damage or disturbance is caused to areas surrounding the Works or to the Works throughout the duration of the Contract.
22.3
Silt trap shall be constructed as shown in the Drawings. The silt trap shall be maintained regularly throughout the contract period, including desalting when full or as directed by the S.O and making good of any damaged portions during the course of the works. The desalted material shall be transported to disposal site approved by the S.O.
22.4
The Contractor shall, if and where directed by the S.O, install silt fences as shown in the drawings for trapping silt and sediment from disturbed area during construction. The silt fence shall be constructed of a vertical barrier of geotextile supported by poles at regular intervals. The geotextile shall be made of 108
non-woven material with minimum weight of 200g/m2 and tensile strength 15 kN/m. The fence shall be inspected after every rain and when a sediment accumulation of approximately two third (⅔) of the fence height is observed; the silt shall be removed and disposed of properly. The geotextile shall be checked for rips, tears and other types of deterioration and replaced as needed. 22.5
The Contractor shall, if and where directed by the S.O, construct gabion walls which shall consist of layers of gabion as shown in the Drawings for trapping sediments in catchment area.
22.6
The Contractor shall, if and where directed by the S.O, construct sediment pond or basin as shown in the Drawings for collecting and trapping sediments before the water leaves the Site. The sediment basin shall be maintained such that the silt shall be removed when a sediment accumulation of approximately one third (⅓) the basin depths is observed.
SECTION C – Excavations and Earthworks; 16.
Temporary Drainage Channels and Bunds 16.1
17.
Clearing of Existing Ditches, Drains, Rivers, etc. 17.1
18.
As earthwork progresses, the Contractor shall provide and maintain efficient drainage of the Site as specified under SECTION A: PRELIMINARIES AND GENERAL CONDITIONS, until such time as the permanent surface water drainage is installed.
During the execution of the earthwork, the Contractor shall take all necessary precautions to prevent blockage or obstruction, and to ensure freeflow of existing drains, ditches, streams and the like.
Protection and Maintenance of Earthworks 18.1
The Contractor shall provide all necessary protection and maintenance of earthwork, particularly from the damaging effects of water entering the works from rainfall, runoff, springs, rivers or streams. Damage to finished or partly completed work arising from the lack of such protection and maintenance work, shall
109
be made good by the Contractor at his own cost and expense. 18.2
Where turfing is required for slope protection, they shall be planted immediately after the embankment is formed.
18.3
If due to unforeseen circumstances turfing cannot be carried out immediately, temporary protection/cover (e.g. plastic sheets or equivalent) shall be laid on exposed slopes by the Contractor.
110
APPENDIX 2 GOVERNMENT REQUIREMENTS (NEED STATEMENT) (TERM OF REFERENCE) (FOR DESIGN AND BUILD PROJECTS ONLY)
111
(Please insert this document into the prebid document)
GOVERNMENT REQUIREMENTS (NEED STATEMENT) (TERM OF REFERENCE) ENVIRONMENTAL PROTECTION AND ENHANCEMENT REQUIREMENTS (FOR DESIGN AND BUILD PROJECTS ONLY)
112
Fill in Name of Project
ENVIRONMENTAL PROTECTION AND ENHANCEMENT REQUIREMENTS
CONTENTS GENERAL 1.0
Scope of Works
2.0
Special Requirements
3.0
Legal Requirements 3.1
Compliance with the Legal Requirements
3.2
Environmental Impact Assessment (EIA)
3.3
Environmental Protection Works
4.0
Safety and Health Requirements
5.0
Waste Management and Disposal System
6.0
Stormwater Management
7.0
Environmental Management Plan 7.1
8.0
Erosion and Sediment Control Plan (ESCP)
Environmental Monitoring, Auditing and Training 8.1
Monitoring
8.2
Auditing
8.3
Reports
8.4
Training
113
GENERAL 1.0
2.0
3.0
Scope of Works 1.1
The works shall cover planning, design, construction, monitoring, auditing, reporting, training and maintenance of environmental protection and enhancement works.
1.2
The Contractor is deemed to have visited the site to familiarize himself with site and local conditions that pertain to the necessary programme, design and execution of this work. The Contractor shall take all necessary action and precaution during construction and maintenance works so as not to affect the surrounding environment.
Special Requirements 2.1
Forty five (45) days prior to site possession, the Contractor shall submit for the P.D/S.O approval a detailed EMP based on the Arahan Teknik (Jalan) 16/03 – Pindaan 2008. For projects subjected to EIA requirements, the EMP shall be submitted 45 days after the approval of the EIA. No site clearing and earthworks shall be carried out prior to EMP approval by relevant parties/authorities.
2.2
The Contractor shall need to include the environmental activities in the program (CPM) to be submitted to the P.D/S.O. These activities shall contain all the necessary actions and interactions in detail.
2.3
The onus of obtaining timely approval from each relevant Local Approving Authority on environment shall be the Contractor‟s responsibility. Untimely receipt of approvals which may affect the Contractor‟s design/construction program shall not in any way be a basis/cause for consideration of time extension or variation to the contract.
2.4
The Contractor must take serious and urgent actions on all findings and recommendations toward protecting the environment as in the report or/and as instructed by the P.D/S.O.. Failure to do so, the P.D/S.O shall appoint other party and all cost will be borne by the contractor.
2.5
The Contractor shall provide turbidity measuring equipment to determine direct in-situ measurement on water quality for immediate rectification should pollution occur.
Legal Requirements 3.1
Compliance with the Legal Requirements Prior to the execution of the project, the Contractor shall comply with the Environmental Quality Act 1974, Act 127 and other related environmental legislations including, but not limited to:
114
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) 3.2
National Land Code (Act 56 of 1965) Town and Country Planning Act 1976, (Act 172) Street, Drainage and Building Act, 1974: Act 133 and Amendment, 1978 Protection of Wildlife Act, 1972 (Act 76) Forestry Act 1984 (Act 313) Land Conservation Act 1960 (Act 385) Occupational Safety and Health Act 1994 (Act 514) Solid Waste and Public Cleansing Management Act 2007 (Act 672) Environmental Quality Act 1974 (Act 127 & Subsidiary Legislation) Federal Territory (Planning) Act 1982 (Act 267) Workers Minimum Amenities Act 1990 (Act 446) Local Government Act 1976 (Act 171)
Environmental Impact Assessment (EIA) Where EIA is required by the said Act, the Contractor shall prepare, submit and obtain approval from the Department of Environment (DOE). The Contractor shall incorporate in his Works all the abatement and mitigation measures for environmental protection and enhancement including monitoring and auditing.
3.3
Environmental Protection Works The Contractor shall identify the significant environmental aspects and impacts of the projects and execute all mitigating measures proposed in the Conditions of Approval by the Approving Authority and in the EMP. Reference shall be made to the Arahan Teknik (Jalan) 16/03 – Pindaan 2008 for a more comprehensive understanding of the scope of works. The contractor shall also observe / carry out the following: (i)
Limit and control site clearing works to construction areas only. Existing trees of 80cm diameter at breast height are to be retained as much as possible and only minimum tree cutting is allowed unless they impose danger to the public and traffic after completion of the project.
(ii)
Transport and stockpile topsoil to designated areas approved by the P.D./S.O for reuse during turfing, hydroseeding and landscaping.
(iii)
Turf or hydroseed slopes immediately upon reaching their formation levels. For cut slopes, hydroseeding shall be carried out together with supportive materials. Landscaping works shall commence early as directed by the P.D. /S.O.
(iv)
Take necessary precautions to prevent deposition of debris, rubbish, silt, waste materials, polluted water, chemicals, etc. during execution of the works from entering existing streams/waterways.
115
4.0
(v)
Construct berm/bench drains, interceptor drains and other related drainage works to slopes which have reached the required formation levels. Provide temporary cover, for example, polythene or plastic sheet to exposed slopes.
(vi)
Provide and maintain sediment control measures namely silt fences, silt traps, sediment basins, gabion walls, check dams, silt curtains, etc. Upon completion, reinstate site including landscaping where sediment basins were located and remove other measures which are not required as directed by the P.D. /S.O.
(vii)
Take necessary precautions to ensure that tyres of all vehicles leaving the site are free of mud.
(viii)
Not to carry out open burning on site unless with written approval from the DOE.
(x)
Supply and lay immediately at least to binder course layer on roads which have reached the required formation levels including the required drainage system.
(xi)
Preserve mangrove areas on site unless deemed necessary for construction. However, the clearing of mangroves shall be limited to construction infrastructural area only and with approval from P.D. /S.O.
(xii)
Bakau piles are not allowed to be used.
Safety and Health Requirements The Contractor shall provide and maintain suitable accommodations for workmen by carrying out the following: (i) (ii) (iii) (iv) (v) (vi)
5.0
Locate suitable workmen's accommodation to be agreed by the P.D./S.O. Provide sufficient toilet facilities to the satisfaction of the P.D./S.O. Provide proper disposal for waste and refuse. Provide adequate supply of water for washing, cooking and drinking. Maintain site in a clean and sanitary condition and that complies with all requirements of Government, Health and Sanitary Authorities. Prohibit activities such as hunting/trapping of wildlife. Fines/penalties imposed by the relevant Government Departments due to such activities shall be borne by the Contractor.
Waste Management and Disposal System 5.1
All types of waste i.e. Solid waste, Liquid waste, Domestic waste (nonhazardous) and Scheduled wastes are to be segregated, stored and disposed in accordance with the Ministry of Health requirements , the DOE requirements and other approving Authority requirements (e.g. the Local Authority). 116
6.0
5.2
Wastes with sharp edges are to be stored in specially designed containers and specially manufactured for that purpose.
5.3
Scheduled waste shall be kept in labeled containers/ drums and stored in storage shed which shall both be maintained and removed in accordance with the DOE requirements. Schedule waste shall be disposed by a licensed contractor to approved prescribed premises for treatment.
5.4
The disposal of Liquid or Solid waste and scheduled wastes must be properly designed and programmed to abide with the Authorities‟ Requirements.
Stormwater Management Stormwater management design and construction works shall conform with the requirements of Jabatan Kerja Raya „Drainage System‟, „Erosion and Sedimentation Control Plan (ESCP), Jabatan Pengairan dan Saliran „Urban Stormwater Management Manual (MSMA) and Local Authorities requirement. Stormwater drainage shall be designed for least maintenance cost, effective initial cost and serves its function. There shall be no flooding, ponding/silting up and erosion during construction and after completion of the works.
7.0
Environmental Management Plan (EMP) The Contractor shall submit for prior approval by the government, an environmental consultant registered with DOE, for preparation of a site specific EMP. The EMP shall be submitted to the S.O. for endorsement 45 days prior to site possession in compliance with the Conditions of Contract and/or in compliance with the requirements of the conditions of approval of the EIA report by the Department of Environment. The EMP shall make reference to the following but not limited to: (a) DOE Format for the Preparation of EMPs. (b) JKR Environmental Management System (EMS). (c) The approved EIA report. (d) EIA Approval Conditions from DOE (attached if any). It should be clearly noted the EMP is a document for practical use on site by nominated personnel and thus should be concise, up to date and site specific. The Contractor shall engage the following qualified personnel (degree holder in related fields) on site: (i) (ii) (iii) (iv)
Environmental Officer (Full Time). Safety and Health Officer (Full Time). Horticulturist / Plant / Tree Expert (Part Time), if required. Fauna Expert (Part Time), if required.
117
7.1
Erosion and Sediment Control Plan (ESCP) The Contractor shall prepare an ESCP. This document which is to be prepared and certified by a Professional Engineer shall be submitted to the P.D. / S.O and Environment Branch, JKR Malaysia 30 days prior to commencement of any earthwork activity at project site. The P.D. / S.O shall then submit the ESCP document to the Drainage and Irrigation Department (D.I.D) for approval upon document review by the Environment Branch, of JKR Malaysia. The following items apply to an ESCP document: (a) (b)
(c)
(d)
8.0
The document shall be prepared in accordance with the Storm water Management Manual (MSMA) published by D.I.D. It must be amended whenever a change in the design, construction, operation or maintenance at the construction site has a significant effect on the discharge of pollutants to the waters at project site not previously addressed in the document It must be amended if discharges are causing water-quality “exceedances” or the Best Management Practice (BMP) are ineffective in minimizing pollutants in storm water discharging from the construction site. The document must be revised within 7 calendar days following an inspection when additions and/or modifications to BMPs are necessary to correct observed problems.
Environmental Monitoring, Auditing and Training 8.1
Monitoring The Contractor shall monitor water and air quality, noise and vibration, if required. All samples taken must be tested by an accredited laboratory. The Contractor shall produce and submit monthly and quarterly environmental quality reports consisting in-situ and laboratory results, sampling photographs with weather charts and analyses of the monitoring data in terms of environmental performance. Reference to the contents of the reports can be made to the Standard Report Format attached in Appendix 2.
8.2
Auditing The Contractor shall engage a registered Environmental Auditor to audit all activities on site as per JKR EMS: MS ISO 14001 requirements. The tasks of the Auditor among others are: (i) (ii) (iii)
To carry out environmental compliance of JKR EMS: MS ISO 14001 audits quarterly. To interpret monitoring data in terms of environmental performance. To verify effectiveness of corrective and preventive action implemented. 118
(iv) (v)
To recommend requirement and improvement of mitigating measures. To produce and submit a comprehensive environmental auditing report.
8.3
Reports The Contractor shall submit environmental quality and audit reports to JKR Environment Branch and Portfolio Branch, DOE HQ/State and P.D./S.O. Contents of the report must be in accordance with the Standard Report Format as attached in Appendix 2 of this document.
8.4
Training The contractor shall provide training for relevant JKR personnel in the field of environment. This training shall include Environmental Conservation, Post EIA and Environmental Monitoring, Environmental Management System in Project Construction, Safety and Health Courses, and Technical visits. The training shall be conducted and given by an established organization with reputable track records in environmental protection during project management and construction with opportunity for transfer of technology in enhancing such development. The Contractor‟s EO shall also provide training/awareness briefing for site personnel involved in works that have impact on the environment.
119
APPENDIX 3 STANDARD REPORT FORMAT FOR EMP, EQR, EMAR AND CAR
120
TITLE OF DOCUMENT: ENVIRONMENTAL MANAGEMENT PLAN (EMP) STANDARD REPORT FORMAT FOR JKR PROJECTS
1.0
Definition of EMP An EMP is basically a documentation of administrative environmental management and coordination procedures for onside management in order to ensure that all development activities complies with the EIA approval conditions as stipulated by DOE. It must show the commitment of the project proponent in terms of accountability and availability of resources. An EMP should be improved and adapted throughout the life of the project to reflect changing conditions. It must also be subjected to periodic review to ensure it‟s continues relevance and validity.
2.0
Objectives of EMP The main objectives of the Environmental Management Plan (EMP) is to set out a comprehensive programme which will form the basis for implementing environmental mitigation measures, environmental monitoring and environmental auditing of the construction works by the Contractor as listed below:
3.0
(a)
To set out various environmental protection / conservation measures that conform to the environmental conditions stipulated in the Specifications, EIA report and by other relevant authorities (e.g. the Department of Environment (DOE);
(b)
To ensure that the Contractor comply with all applicable environmental standards and guidelines, legislative requirements and other relevant conditions related to the environment;
(c)
To specify a detailed environmental monitoring and auditing programme to ensure that the Contractor and all his Sub-contractors comply with all stipulated requirements throughout the duration of the project; and
(d)
To streamline the different functions of various sections and authorities related to the environmental matters during the construction.
General Information about the Project The following details are needed to help commence the preparation of the EMP:(i) (ii) (iii) (iv) (v)
Project Contractor Project Title Condition of Contract Project Cost Duration of Contract
121
4.0
Information on EMP The type of EMP that is being prepared can be divided into:(i) (ii)
5.0
Compliance to EQA 1974 Compliance to JKR MS ISO 14001
Cover Page Information The cover has to include the following information:(i) (ii) (iii) (iv) (v) (vi)
6.0
Project & Document Title JKR Logo Contractor‟s Logo Contractor‟s Registration DOE Approval Reference (if applicable); Insertion page for document verification
Executive Summary The executive summary must manage to summarise the key elements of the project:(i) (ii) (iii) (iv) (v)
7.0
Site Features Project Description Identified Impacts Proposed Mitigation Conclusion
Chapter 1:
Introduction
Key information needed to be detailed in Chapter 1 is:(i) (ii) (iii)
Project Title Details of Project Proponent Site Description Topography Drainage Flora Fauna Land use Geology & Soils Socio Economy
122
(iv)
8.0
Project Description Concept Components Activities Scheduling
Chapter 2:
Environmental Requirement
This chapter has to outline the need for the EMP and has to detail the following:(i) (ii)
9.0
Listing of all Environmental Requirements including any approval obtained for the ESCP, MASMA, disposal site etc. EIA approval conditions (if applicable)
Chapter 3:
Environmental Policy
Chapter 3 has to state in the Policy in relation to Environment of the Project Proponent and elaborate on the objectives of the EMP:(i) (ii)
10.0
Objectives of the EMP Environmental Policy of the PP
Chapter 4:
Organisation Chart and Budget
Chapter 4 has to detail the aspects related to the Environmental Management Unit (EMU) and the allocations provided for Environmental Protection:(i) (ii) (iii) (iv) (v)
11.0
Organisation chart of EMU Contact details of EMU Job description of EMU Training proposed Budget for EMP implementation
Chapter 5:
Monitoring Program
Detailing of the environmental monitoring proposal for the project:(i)
Baseline information Monitoring locations and justification of locations Validity of data Verification of data Frequency of monitoring Sampling methodology and Accreditation of laboratory
123
(ii)
Proposed monitoring programme
12.0
Chapter 6:
Monitoring locations and justification of locations Frequency of monitoring Accreditation of laboratory to be used for sampling Report to be submitted
Auditing Programme
This chapter has to detail the auditing programme for the project:(i) (ii) (iii) (iv) (v) (vi)
13.0
Audit elements Frequency of audit Reports to be submitted Types of forms used Registration details of auditor Follow up action on audit
Chapter 7: Measures
Identification of Aspect, Impact and Recommended Mitigation
This chapter has to detail the identified significant aspects, impacts and their corresponding site specific mitigation measures:(i) (ii) (iii) (iv) (v)
Site Cleaning and Biomass Management Wildlife Protection Plan Social Acceptance Plan Earthworks Description ESCP Description Elements Staging Plans Implementation Schedule
(vi) (vii) (viii) (ix) (x) (xi) (xii)
Stockpile Management Slope Protection Drainage Logistics Site Facilities Solid Waste Management Scheduled Wastes Management Type of waste generated Estimated volume Storage, Collection and Disposal Plan (xiii) Safety (xiv) Traffic Control (xv) Site Abandonment/Closing Plan 124
14.0
Chapter 8:
Environmental Contingency Plan
This chapter has to detail the contingencies related to the project:-
15.0
(i)
Issued identified Flooding Landslide Fire Medical Emergencies Spillages
(ii) (iii)
Action Plan and Line of Communication Contact Numbers of relevant Agencies
Chapter 9:
Performance Evaluation and Project Review
This chapter has to detail the analysis used to determine performance of the environmental Protection Measures and the recommendations for improvement:(i) (ii) (iii)
16.0
Description of Analytical Methodology Used Forms Used Recommendations for Improvement
Chapter 10:
Conclusion
This chapter has to conclude the findings of the EMP:(i)
17.0
Concluding Statements on site related issues and their corresponding mitigation measures.
Appendices Items to include in the appendix are:(i) (ii) (iii) (iv) (v) (vi)
Data sources Consultations held Approvals obtained References Calculations Plans
125
18.0
Figures The following figures are mandatory to be included in the EMP:(i) (ii) (iii) (iv) (v) (vi)
Location plan Layout of site and facilities Organisation chart of EMU Location of water, air and noise monitoring stations (baseline) Location of water, air and noise monitoring stations (proposed) ESCP Earth drain network Diversion channels Silt traps/sediment basins locations Final discharge outlets Silt fence Gabions Check dams
(vii)
Overall Mitigation Plan Location of solid waste storage Location of scheduled wastes storage Toilets Stockpile area Boundary of site clearing Septic tanks Grease traps Wash trough
(viii) Emergency Response chart for any Non-compliances observed/identified
126
REPORT:
ENVIRONMENTAL QUALITY REPORT (EQR)
TABLE OF CONTENTS EXECUTIVE SUMMARY 1.0
INTRODUCTION 1.1 1.2 1.3
2.0
WATER QUALITY MONITORING 2.1 2.2 2.3 2.4 2.5 2.6
3.0
Introduction to Project Progress of works to date Monitoring Period
Sampling and analysis procedures Results Comparison with baseline quality and Previous results Discussion on water quality results Conclusion of findings on water quality Photos
SILT TRAP/SEDIMENT BASIN MONITORING 3.1 3.2 3.3 3.4 3.5 3.6
Sampling and analysis procedures Results Comparison with previous results Discussion on results Conclusion of findings on discharge quality Photos
4.0
SITE OBSERVATION DETAILS Photos to verify site observations
5.0
NON-CONFORMANCE REPORTS 5.1
6.0
Details
CONCLUSION
APPENDIX: Certified Monitoring Results
127
REPORT: (EMAR)
ENVIRONMENTAL
MONITORING
AND
TABLE OF CONTENTS EXECUTIVE SUMMARY 1.0
INTRODUCTION 1.1 1.2 1.3 1.4 1.5
2.0
SCOPE OF MONITORING WORKS 2.1 2.2 2.3 2.4
2.5
2.6
3.0
Introduction to Project Project Development Concept Project Environmental Management Unit Progress of works to date Auditing Period
Summary of Monitoring Programme Sampling Methodology Water Quality Results Silt trap/Sediment Discharge Results 2.4.1 Comparison with Baseline/Previous Results 2.4.2 Findings/Observations Air Quality Results 2.5.1 Comparison with Baseline/Previous Results 2.5.2 Findings/Observations Noise Quality Results 2.6.1 Comparison with Baseline/Previous Results 2.6.2 Findings/Observations
STATUS OF COMPLIANCE 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 3.11
Regulation of Earthworks Drainage and Surface runoff control Slope Protection Air Pollution Control Noise Pollution control Biomass Management Sewage Management Solid Waste Management Scheduled Wastes management Contingency and Emergency Response Plan Housekeeping
128
AUDIT
REPORT
4.0
RECOMMENDATIONS 4.1 4.2 4.3
5.0
NCR Issued/Closed Out Action Plan for Rectification/Improvement works Recommendations for Identified/Predicted Issues
CONCLUSION
APPENDIX:
PROJECT PHOTOGRAPHS
ENVIRONMENTAL PROTECTION AND ENHANCEMENT MONITORING CHECKLIST DURING CONSTRUCTION: Ref: ER/4.5.2/1/1
CERTIFIED LABORATORY RESULTS
129
REPORT:
CLOSURE AUDIT REPORT (CAR)
TABLE OF CONTENTS EXECUTIVE SUMMARY 1.0
INTRODUCTION 1.1 1.2 1.3 1.4 1.5
2.0
EVALUATION OF PROJECT PERFORMANCE 2.1 2.2 2.3 2.4
3.0
Background details of Project Project Description Any changes to Project Activities throughout duration of Contract Summary of Monitoring Program Summary of Audit Program
Description and evaluation of environmental monitoring results Description and evaluation of mitigating measures Achievement of environmental performance as compared to JKR Corporate Objectives Achievement of environmental performance compared against JKR ISO 14001 EMS, the EMP and other environmental requirements
LESSONS LEARNED AND RECOMMENDATIONS 3.1 Detailing of any problems encountered on-site 3.2 Suggestions for improvement
APPENDIX:
PROJECT PHOTOGRAPHS
HANDING OVER AUDITING CHECKLIST: Ref: ER/4.5.5/1/9
130
View more...
Comments