HALLAR EL PRESUPUESTO TOTAL DE LA CONSTRUCCION DEL MURO DE CONTENCION CON LAS SIGUIENTES DESCRIPCIONES...

Description

RESOLUCION DE EXAMEN N° 02 3.- HALLAR EL PRESUPUESTO DEL MURO

x=0.15

a) Vol. De Excavacion:

vol=1.8∗1.65∗200=594 m3 vol =1594 m3 b) Vol. de Relleno.

h

Aizq = N.T.N.

( B+b )∗h ( 0.55+0.4 )∗1.05 = 2 2 Aizq =0.49875 m2

Ader =1.05∗0.5=0.525 m2 1.05

Area Total = 1.02375 m2 ⇒ Volumen Total = 1.02375*200

x = 204.75 m3 c) Vol de Eliminación. E=20% C= 1/(1+E)= 0.8333

VE=Vexc ( 1−E ) − Tg ( 8 ° )=

0.5 0.5 ⇒ H= h Tg(8)

Vrell∗( 1+ E ) C

VE=594 ( 0.8 )−204.75∗(1.44)

h=3.56 VE=180.36 m 3 Tg ( 8 ° )=

x ⇒ X =Tg ( 8° )∗1.05 1.05

d) Vol de Concreto:

RESOLUCION DE EXAMEN N° 02

A 1=

( B+ b )∗h ( 0.9+ 0.4 )∗3.56 = 2 2

X1 ≈ 4816 bls de Cemento

A 1=2.3725

A 2=B∗h=1.8∗0.6

o

Agregado fino:

2.3__________ 5.42

A 2=1.08

X2_________690.5

Área Total= 2.3725+1.08 = 3.4525

X= 293.02 m3

⇒ Volumen Total = 3.4525 * 200

Esponjamiento: 15%

= 690.50 m3

X= 293.02*1.15

e) Diseño de mezclas: Proporcion.- 1:2.3:3.6 1 cemento * 0.5 = 0.5 2.3 Ag.. Fino * 0.6 = 1.38 3.6 Ag. Grueso* 0.6= 2.16 6.9 4.04 Agua 0.2*6.9 = 1.38 5.42 m3 de Concreto  HALLANDO LA CANTIDAD DE MATERIALES o Cemento:

X= 336.973 m3 X= 336.973 * 1.07 =360.56 m3 X2 ≈ 361 m3 de Agregado Fino o

Agregado Grueso:

3.6__________ 5.42 X3___________690.5

1__________ 5.42

X= 468.63 m3

X1_________690.5

Esponjamiento: 20%

X= 127.40 m3

X= 468.63*1.15

01 bls = 01 pie3

X= 562.356 m3

01 pie3 = 0.02831

X= 562.356 * 1.07 =601.72 m3

X1= 4500.17 bls.

X2 ≈ 602 m3 de Agregado

X= 4500.17* 1.07 =4815.18 bls

Grueso o

Agua

RESOLUCION DE EXAMEN N° 02 Agua= 20/100 *690.5 Agua= 138.1 m3 Agua ≈ 139 m3 de agua

f) Costo Material: Cemento: 4816 bls * 23.50 = 113,176.00 Agr. Fino= 361 m3 * 32.60 = 11,768.60 Agr. Grueso = 602 m3 * 25.60 = 15,411.20 Agua = 139 m3 * 0.50 = 69.5_________ TOTAL MAT. S/. = 140,425.30 N.S. g) Costo Mano De Obra: Vacia Conc= 690.50 m3 * 15.70 = 10,840.85 Excavacion = 594 m3 * 8.20 = 4,870.80 Relleno = 204.75 m3 *17.3 = 3542.18 Eliminacio = 180.36 m3 * 12.5 =2,254.50___ TOTAL M.O. S/= 21,508.33 h) Costo Total: TOTAL MAT. S/. = 140,425.30 N.S. TOTAL M.O. S/= 21,508.33 N.S.___ COSTO TOTAL = 161,933.63 N.S.