Answer Chapter 8 Standard Costing & Variance Analysis

October 11, 2017 | Author: ErikaPalinlinTaguba | Category: N/A
Share Embed Donate


Short Description

ms...

Description

CHAPTER 8 STANDARD COSTING & VARIANCE ANALYIS Exercise 1 1. Determine the material purchase price and quantity variances. Material price variance: 100,000 × P2.50 = 100,000 × P2.60 = Material quantity variance: 95,625 × P2.60 = 89,250 × P2.60 =

P250,000 260,000 P 10,000 F P248,625 232,050 P 16,575 U

2. Determine the labor rate and efficiency variances. Labor rate variance: 122,400 × P8.35 = P1,022,040 122,400 × P8.50 = 1,040,400 P 18,360 F Labor efficiency variance: 122,400 × P8.50 = P1,040,400 127,500 × P8.50 = 1,083,750 P 43,350 F Exercise 2 1. Two variance method Actual (P6,400 + P17,500) Budget Variance: BFOH (8,900 × P1.90) VOH (1,800 × 5 × P.75) Volume Variance: Applied OH: (1,800 × 5 × P2.65)

2. Three variance method Actual Spending Variance: Flexible Budget Based on Actual Input BFOH P16,910 VOH (8,900 × P.75) Efficiency Variance: Flexible Budget Based on Standard DLHs BFOH P16,910 VOH (1,800 × 5 × P.75) Volume Variance: Applied OH: (1,800 × 5 × P2.65)

P23,900 P240 U P16,910 6,750

P23,660 P190 F

P23,850

P23,900 P315 U

6,675

P23,585 P75 F

6,750

P23,660 P190 F

P23,850

3. Four variance method Actual VOH Variable Spending Variance: Flex. Bud. Based on Actual Input Hours (8,900 × P.75) Variable Efficiency Variance: Applied VOH (1,800 × 5 × P.75) Actual FOH FOH Spending Variance: BUDGETED FOH P16,910 FOH Volume Variance: Applied FOH (1,800 × 5 × P1.90)

Exercise 3 a.

P6,400 P275 F P6,675 P75 F P6,750 P17,500 P590 U

P190 F P17,100

actual material cost actual pieces at standard cost (80,000 × P4) material purchase price variance

b.

3,900 units × 20 pieces per unit = 78,000 standard quantity allowed

c.

total standard cost of material (78,000 × P4) P312,000

d.

standard cost of actual material used P312,000 + P6,400 U quantity variance P318,400  P4 = 79,600 actual pieces used

P314,000 320,000 P 6,000 F

P318,400

e.

actual labor cost 5,900 actual direct labor hours × P6 labor rate variance

P40,120 35,400 P 4,720 U

f.

3,900 units × 1.5 standard hours per unit

g.

5,850 Std Hours Allowed × P6

P35,100

h.

actual hours × standard rate (from e) standard cost of labor allowed (from g) labor efficiency variance

P35,400 35,100 P 300 U

i.

actual machine hours × standard VOH rate (18,900 × P2.50) VOH spending variance actual VOH

P47,250 50 U P47,300

j.

3,900 units × 4.8 standard hours per unit = 18,720 MH allowed

k.

standard hours allowed (from j) × standard VOH rate (18,720 × P2.50) actual machine hours × standard rate (from i) (18,900 × P2.50) variable overhead efficiency variance

5,850 SHA

P46,800 47,250 P 450 U

l.

19,000 machine hours × P3

P57,000

m.

3,900 units × 4.8 hours per unit × P3.00

P56,160

n.

actual fixed overhead budgeted fixed overhead (from l) fixed overhead spending variance

P60,000 57,000 P 3,000 U

o.

budgeted fixed overhead (from l) applied fixed overhead (from m) volume variance

P57,000 56,160 P 840 U

p.

total actual overhead [P60,000 + P47,300 (from i)] total applied overhead (18,720 SHA × P5.50) Total overhead variance

P107,300 102,960 P 4,340 U

Exercise 4 a. Total direct material cost variance. = Actual direct material cost – Standard direct material cost = (1,900 lbs x P41) – (8,000 x 0.25 x P40) ; = P77,900 - P80,000 ; = P2,100 favorable b.

Direct material price variance. = (AP – SP) x AQ ; = (P41 - P40) x 1,900 lbs

=

P1,900 unfavorable

c.

Direct material quantity variance. = (AQ – SQ) x SP; = [1,900 lbs - (8,000 x 0.25)] x P40 = P4,000 favorable

d.

Total direct labor cost variance. = Actual direct labor cost – Standard direct labor cost = (250 x P18.25) – (8,000 x 0.03 x P18) ; = P4,562.50 - P4,320.00

e.

f.

Direct labor rate variance. = (AR – SR) x AH ; = (P18.25 - P18.00) x 250

Sales volume (in units) Sales revenues Flexible (variable) costs Contribution margin Capacity-related (fixed) costs Operating profit b.

= P62.50 unfavorable

Direct labor efficiency variance. = (AH – SH) x SR ; = [250 - (8,000 x 0.03)] x P18

Exercise 5 a.

Master Budget 30,000 P3,600,000 2,160,000 1,440,000 900,000 P 540,000

= P242.50 unfavorable

= P180.00 unfavorable

Flexible Budget 25,000 P3,000,000 P1,800,000 P1,200,000 P 900,000 P 300,000

Determine the flexible (variable) cost variance. = Actual cost – Flexible budget cost ; = P1,930,000 - P1,800,000 = P130,000 unfavorable

Actual Results 25,000 P3,000,000 1,930,000 1,070,000 970,000 P 100,000

c.

Determine the flexible (variable) planning variance. = Flexible budget cost – Master budget cost ; = P1,800,000 – P2,160,000 = P360,000 less than planned

d. As these results suggest, the manager should not be congratulated for keeping costs under control. Flexible (variable) costs were P130,000 over budget for actual output and capacity-related (fixed) costs were also P70,000 over budget. These variances from the flexible budget highlight the amounts that are different than planned. Since variances simply signal a deviation from what was planned, these differences need to be investigated before corrective actions can be taken.

Exercise 6 MATERIAL QUANTITY VARIANCE A B C

(181,000 – 172,200) × P0.06 = (33,000 – 28,700) × P0.12 = (6,000 – 4,100) × P0.25 =

P 528 UNF 516 UNF 475 UNF P1,519

Act Q x Act Mix x Std P Std Mix x Std P A 181,000 × P0.06 = B 33,000 × P0.12 = C 6,000 × P0.25 =

MIX VARIANCE = YIELD VARIANCE = Total

P10,860 3,960 1,500 P16,320

Act Q x Std Mix x Std P

184,800 × P0.06 = 30,800 × P0.12 = 4,400 × P0.25 =

P11,076 3,696 1,100 P15,872

Act Q x

172,200 × P0.06 = 28,700 × P0.12 = 4,100 × P0.25 =

P10,332 3,444 1,025 P14,801

P 436 UNF P1,083 UNF P1,519 UNF

Exercise 7 (AH x AM X SR) x MIX VARIANCE A B C D

5,400 × P4 = 3,200 × P6 = 1,300 × P8 = 100 × P10 =

MIX VARIANCE YIELD VARIANCE RATE VARIANCE

(AH x SM x SR )

x (SH x SM x SR ) YIELD VARIANCE

P21,600 6,000 × P4 = P24,000 19,200 3,000 × P6 = 18,000 10,400 1,000 × P8 = 8,000 1,000 P50,000 P52,200 = P2,200 UNF = P1,000 UNF = P 800 UNF (P53,000 – P52,200)

5,880 × P4 = 2,940 × P6 = 980 × P8 =

P23,520 17,640 7,840 P49,000

Exercise 8 TOTAL COST EQUATION = P80,000 FIXED + a.

P20,000 / 10,000 = P2 variable per dlh

120% = P80,000 + (12,000 × P2) = P104,000 100% = P80,000 + (10,000 × P2) = P100,000 80% = P80,000 + ( 8,000 × P2) = P 96,000 60% = P80,000 + ( 6,000 × P2) = P 92,000 APPLICATION RATE =

P100,000 / 10,000 dlh = P10 per dlh

Volume variance = fixed oh rate x difference in normal or planned and actual units produced. P80,000 / 10,000 = P8 per dlh = (12,000 – 10,000 = 2,000 × P8) = P16,000 = (10,000 – 10,000 = 0 × P8) = P0 = ( 8,000 – 10,000 = -2,000 × P8) = - P 16,000 =( 6,000 – 10,000 = - 4,000 × P8) = - P 32,000

.

120% 100% 80% 60%

b.

BUDGET VARIANCE = ACTUAL FOH – BUDGETED FOH P9,000 FAV = P87,000 – P96,000

Exercise 9 1.

Applied rate = P6/dlh Total Overhead Cost = P50,000 + P1/dlh Std Overhead (A) (B) Std Hrs.

2.

5,000 × 2 = 10,000 5,000 × 4 = 20,000

5,000 × 2 = 10,000

a.

1. (P7.20 – P7.00) × 12,000 = 2. (P3.90 – P4.00) × 20,000 =

b.

1. (10,500 – 10,000) × P7.00 = 2. (19,800 – 20,000) × P4.00 =

c.

P79,380 – (9,800 × P8) = P980 U

d.

(9,800 – 10,000) × P8 = P1600 F

e.

(10,000 – 10,000) × P5 = 0

f.

(9,800 – 10,000) × P1 = P200 F

g.

Fix Spd P48,100 – P50,000 = P1,900 F Var Spd P21,000 – (9,800 × P1) = P11,200 U

P2,400 U 2,000 F P 400 U P3,500 U 800 F P2,700 U

Exercise 10 STD Q A B C

120,000 1,000 120 120

× 3 = 360 × 6 = 720 × 9 = 1,080

ACT HRS ACT MIX STD P

ACT HRS STD MIX STD P

MIX VARIANCE A B C

390 × P4.50 = 980 × P4.00 = 970 × P3.00 =

STD HRS STD MIX STD P

YIELD VARIANCE

P1,755 390 × P4.50 = P1,755 P3,920 780 × P4.00 = P3,120 P2,910 1,170 × P3.00 = P3,510 P8,585 P8,385 P200 UNF P645 UNF

360 × P4.50 = 720 × P4.00 = 1,080 × P3.00 =

Test I MULTIPLE CHOICE

1 2 3 4 5 6 7 8 9 10 11 12

D B D A D C B A C C B A

13 14 15 16 17 18 19 20 21 22 23 24

C A B B C C A B A D B C

25 26 27 28 29 30 31 32 33 34 35 36

C B A C B A D A C A B A

Test II MULTIPLE CHOICE

1 2 3 4 5 6 7 8 9 10 11 12

A D C D D D A B A C C D

13 14 15 16 17 18 19 20 21 22 23 24

D B C D D C B C B D C A

25 26 27 28 29 30 31

B D D B D D C

37 38 39 40 41 42

A B A A B D

P1,620 P2,880 P3,240 P7,740

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF