Analysis Of Rates Providing and laying PCC 1:4:8 Materials Stone Aggregate 40 mm
0.69
Cu m
Stone Aggregate 20 mm Coarse Sand Cement
0.28 0.5 1.7
Cu m Cu m Q
Labour Foreman Beldar/ Coolie Mason Waterman
0.1 1.3 0.15 0.13
Each Each Each Each
Total cost Add for T&P and hire charges of machine etc. @ 10 %
Add overhead cost and contractors profit @ 20 %
Analysis Of Rates Providing and laying RCC M 25 Materials Stone Aggregate 20 mm Coarse Sand Cement
0.83 0.42 4.19
Cu m Cu m Q
Labour Foreman Beldar/ Coolie Mason Waterman
0.1 1.5 0.2 0.35
Each Each Each Each
Total cost Add for T&P and hire charges of machine etc. @ 10 %
Add overhead cost and contractors profit @ 20 %
Analysis Of Rates Brick work in foundation and plinth in 1:6 mortar Materials Bricks & wastage Coarse Sand Cement Labour Foreman Beldar/ Coolie Mason Waterman
500 0.27 0.63
Nos. Cu m Q
0.1 1.4 0.6 0.2
Each Each Each Each
Total cost Add for T&P etc. @ 5 %
Add overhead cost and contractors profit @ 20 %
Analysis Of Rates Brick work in foundation and plinth in 1:6 mortar Materials Bricks & wastage Coarse Sand Cement Labour Foreman Beldar/ Coolie Mason Waterman
Total cost Add for T&P and scaffolding @ 10 %
Add overhead cost and contractors profit @ 20 %
500 0.27 0.63
Nos. Cu m Q
0.1 1.8 0.9 0.3
Each Each Each Each
Analysis Of Rates 12 - 15 mm cement plaster in 1:6 mortar For 100 sq m Materials Fine Sand Cement
1.81 430
Cu m Q
1 18 10 3
Each Each Each Each
Labour Foreman Beldar/ Coolie Mason Waterman
Total cost Add for T&P and scaffolding @ 5 %
Add overhead cost and contractors profit @ 20 %
Rate per sq m
Analysis Of Rates 40 mm thick IPS flooring For 10 sq m Materials Stone Aggregate 20 mm Coarse Sand Cement Labour Foreman Beldar/ Coolie Mason Waterman
0.38 0.19 1.5
Cu m Cu m Q
0.1 3 1.5 0.3
Each Each Each Each
Total cost Add for T&P and hire charges of machine etc. @ 10 %
Add overhead cost and contractors profit @ 20 %
Rate per sq m
Analysis Of Rates TMT Reinforcement work For 1 MT Materials TMT Bars Binding Wire Labour Foreman Helper Bar binder
0 10
0.4 5 5
MT Kg
Each Each Each
Total cost Add for T&P etc. @ 5 %
Add overhead cost and contractors profit @ 20 %
Analysis Of Rates 40 mm thick mossaic flooring with 10 mm thick top layer For 10 sq m Materials Marble chips White cement Marble dust Stone Aggregate 20 mm Coarse Sand Cement Labour Foreman Beldar/ Coolie Mason Polisher Waterman
180 100 60 1.88 0.94 13.05
Kg Kg Kg Cu m Cu m Q
1 20 20 80 2
Each Each Each Each Each
Total cost Add for T&P grinding machine and polishing material etc. @20 %
Add overhead cost and contractors profit @ 20 % Rate per sq m
Analysis Of Rates Centring and shuttering in slab for RCC work For 20 sq m ( 4m X 5m) Materials Timber i/c battens rafters wedges etc. !2 mm shuttering plywood Props (Balli) Total cost Assuming 10 repetitions cost per20 sqm Labour Foreman Beldar/ Coolie Carpenter
0.63 23.84 24
0.5 3 2
Kg Kg Kg
Each Each Each
Total cost Add for T&P nail shuttering oil etc @20 %
Add overhead cost and contractors profit @ 20 % Rate per sq m
Analysis Of Rates Brick work in s/s 115 thick wall in 1:4 mortar For 10 sq m Materials Bricks & wastage Coarse Sand Cement Labour Foreman Beldar/ Coolie Mason Waterman Bar binder Total cost Add for T&P etc. @ 5 %
565 0.3 1.43
Nos. Cu m Q
0.1 1.4 1.3 0.3 0.05
Each Each Each Each Each
Add overhead cost and contractors profit @ 20 % Rate per Sq m
As Per Actual Rates Rate amount 670.96 462.96 670.96 688.62 500.00
Thank you for interesting in our services. We are a non-profit group that run this website to share documents. We need your help to maintenance this website.