Analysis of Rates

December 19, 2016 | Author: tush197428 | Category: N/A
Share Embed Donate


Short Description

Download Analysis of Rates...

Description

Analysis Of Rates Providing and laying PCC 1:4:8 Materials Stone Aggregate 40 mm

0.69

Cu m

Stone Aggregate 20 mm Coarse Sand Cement

0.28 0.5 1.7

Cu m Cu m Q

Labour Foreman Beldar/ Coolie Mason Waterman

0.1 1.3 0.15 0.13

Each Each Each Each

Total cost Add for T&P and hire charges of machine etc. @ 10 %

Add overhead cost and contractors profit @ 20 %

Analysis Of Rates Providing and laying RCC M 25 Materials Stone Aggregate 20 mm Coarse Sand Cement

0.83 0.42 4.19

Cu m Cu m Q

Labour Foreman Beldar/ Coolie Mason Waterman

0.1 1.5 0.2 0.35

Each Each Each Each

Total cost Add for T&P and hire charges of machine etc. @ 10 %

Add overhead cost and contractors profit @ 20 %

Analysis Of Rates Brick work in foundation and plinth in 1:6 mortar Materials Bricks & wastage Coarse Sand Cement Labour Foreman Beldar/ Coolie Mason Waterman

500 0.27 0.63

Nos. Cu m Q

0.1 1.4 0.6 0.2

Each Each Each Each

Total cost Add for T&P etc. @ 5 %

Add overhead cost and contractors profit @ 20 %

Analysis Of Rates Brick work in foundation and plinth in 1:6 mortar Materials Bricks & wastage Coarse Sand Cement Labour Foreman Beldar/ Coolie Mason Waterman

Total cost Add for T&P and scaffolding @ 10 %

Add overhead cost and contractors profit @ 20 %

500 0.27 0.63

Nos. Cu m Q

0.1 1.8 0.9 0.3

Each Each Each Each

Analysis Of Rates 12 - 15 mm cement plaster in 1:6 mortar For 100 sq m Materials Fine Sand Cement

1.81 430

Cu m Q

1 18 10 3

Each Each Each Each

Labour Foreman Beldar/ Coolie Mason Waterman

Total cost Add for T&P and scaffolding @ 5 %

Add overhead cost and contractors profit @ 20 %

Rate per sq m

Analysis Of Rates 40 mm thick IPS flooring For 10 sq m Materials Stone Aggregate 20 mm Coarse Sand Cement Labour Foreman Beldar/ Coolie Mason Waterman

0.38 0.19 1.5

Cu m Cu m Q

0.1 3 1.5 0.3

Each Each Each Each

Total cost Add for T&P and hire charges of machine etc. @ 10 %

Add overhead cost and contractors profit @ 20 %

Rate per sq m

Analysis Of Rates TMT Reinforcement work For 1 MT Materials TMT Bars Binding Wire Labour Foreman Helper Bar binder

0 10

0.4 5 5

MT Kg

Each Each Each

Total cost Add for T&P etc. @ 5 %

Add overhead cost and contractors profit @ 20 %

Analysis Of Rates 40 mm thick mossaic flooring with 10 mm thick top layer For 10 sq m Materials Marble chips White cement Marble dust Stone Aggregate 20 mm Coarse Sand Cement Labour Foreman Beldar/ Coolie Mason Polisher Waterman

180 100 60 1.88 0.94 13.05

Kg Kg Kg Cu m Cu m Q

1 20 20 80 2

Each Each Each Each Each

Total cost Add for T&P grinding machine and polishing material etc. @20 %

Add overhead cost and contractors profit @ 20 % Rate per sq m

Analysis Of Rates Centring and shuttering in slab for RCC work For 20 sq m ( 4m X 5m) Materials Timber i/c battens rafters wedges etc. !2 mm shuttering plywood Props (Balli) Total cost Assuming 10 repetitions cost per20 sqm Labour Foreman Beldar/ Coolie Carpenter

0.63 23.84 24

0.5 3 2

Kg Kg Kg

Each Each Each

Total cost Add for T&P nail shuttering oil etc @20 %

Add overhead cost and contractors profit @ 20 % Rate per sq m

Analysis Of Rates Brick work in s/s 115 thick wall in 1:4 mortar For 10 sq m Materials Bricks & wastage Coarse Sand Cement Labour Foreman Beldar/ Coolie Mason Waterman Bar binder Total cost Add for T&P etc. @ 5 %

565 0.3 1.43

Nos. Cu m Q

0.1 1.4 1.3 0.3 0.05

Each Each Each Each Each

Add overhead cost and contractors profit @ 20 % Rate per Sq m

As Per Actual Rates Rate amount 670.96 462.96 670.96 688.62 500.00

187.87 344.31 850.00 1845.14

225.00 135.00 225.00 135.00

22.50 175.50 33.75 17.55 249.30 2094.44 209.44 2303.89 460.78 2764.66

As Per Actual Rates Rate amount 670.96 556.90 688.62 289.22 500.00 2095.00 2941.12 225.00 135.00 225.00 135.00

22.50 202.50 45.00 47.25 317.25 3258.37 325.84 3584.20 716.84 4301.04

As Per Actual Rates Rate amount 0.00 0.00 688.62 185.93 500.00 315.00 500.93 225.00 135.00 225.00 135.00

22.50 189.00 135.00 27.00 373.50 874.43 43.72 918.15 183.63 1101.78

As Per Actual Rates Rate amount 0.00 0.00 688.62 185.93 500.00 315.00 500.93 225.00 135.00 225.00 135.00

22.50 243.00 202.50 40.50 508.50 1009.43 100.94 1110.37 222.07 1332.44

As Per Actual Rates Rate amount 688.62 1246.40 500.00 215000.00 216246.40 225.00 135.00 225.00 135.00

225.00 2430.00 2250.00 405.00 5310.00 221556.40 11077.82 232634.22 46526.84 279161.07

te per sq m

2791.61

As Per Actual Rates Rate amount 670.96 254.96 688.62 130.84 500.00 750.00 1135.80 225.00 135.00 225.00 135.00

22.50 405.00 337.50 40.50 805.50 1941.30 194.13 2135.43 427.09 2562.52

256.25

As Per Actual Rates Rate amount 0.00 0.00 60.00 600.00 600.00 225.00 135.00 225.00

90.00 675.00 1125.00 1890.00 2490.00 124.50 2614.50 522.90 3137.40

er As Per Actual Rates Rate amount 2.20 396.00 10.24 1024.00 1.80 108.00 670.96 1261.40 688.62 647.30 0.00 0.00 3436.71 225.00 135.00 225.00 200.00 135.00

225.00 2700.00 4500.00 16000.00 270.00 23695.00 27131.71 2713.17 29844.88

5968.98 35813.85 358.14

As Per Actual Rates Rate amount 15890.00 10010.70 430.00 10251.20 100.00 2400.00 22661.90 2266.19 225.00 135.00 225.00

112.50 405.00 450.00 967.50 3233.69 646.74 3880.43 776.09 4656.51 232.83

As Per Actual Rates Rate amount 0.00 0.00 688.62 206.59 500.00 715.00 921.59 225.00 135.00 225.00 135.00 225.00

22.50 189.00 292.50 40.50 11.25 555.75 1477.34 73.87 1551.20

310.24 1861.44 186.14

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF