Air Absorbent Dryer Hangzhou Jialong Operation and maintenance manuals...
THE JLAH TEPEFACTION REGENERATION ADSORPTION TYPE DRYER Operation and maintenance manuals
HANGZHOU JIALONG AIR EQUIPMENT CO., LTD. 2014
Catalogue
1. Introduction........................................................................................................1 2. Overview of working principle.......................................................................... 2 3.Technologic Flow................................................................................................. 3 4. Technical Parameter...........................................................................................4 5.Control System.................................................................................................... 5 6.System Disposition..............................................................................................6 7.Operation.............................................................................................................7 8.Breakdown and Settlement................................................................................9 9.Main parts and wearing parts list.................................................................... 11 10. Preventive maintenance and project list......................................................13
Hangzhou Jialong Air Equipment Co., Ltd
1. Introduction Hangzhou Jialong Air Equipment Co., Ltd. is specialized in the production of compressed air dryer manufacturers, pivotal in the air purification industry, also enjoys a high reputation in the majority of users. In order to further expand the market, to meet user requirements, my company to absorb advanced technology to digest foreign nineties adsorption dryer, fully draw on the experience of the development of the domestic like product launched the JLAH-type micro-thermal regeneration sucking machine to the majority of users. The JLAH-type micro heat regenerative dryers has been in hot pursuit of international advanced technology, continue to provide customers with higher technological content, the better the product. In October 2002, Jialong company signed a long-term cooperation agreement with Japan's largest compressed air after-treatment equipment manufacturers (Ocean NPS Giken Co., Ltd.), The Japan Ocean Giken Co., Ltd. was established in 1974, with strong technical strength and advanced manufacturing level, Jialong company backed by the Japanese Ocean Giken powerful technology strength , product quality and technology has reached advanced domestic level, and increasingly close and reached the international advanced level. The main content of this manual is to guide users how to properly use the equipment and do general maintenance work. Aims to extend the useful life of equipment, reduce equipment failures, in order to ensure the quality of compressed air. Read this manual before using the equipment must be in accordance with the instructions, operation and maintenance, and avoid equipment failure.
User if not in this manual operation and do general maintenance, and the Company makes no warranty liability.
1 / 15
Please consider the environment before printing this document
Hangzhou Jialong Air Equipment Co., Ltd
2. Overview of working principle It conducts absorption drying of compressed air through self-heating and slight-heating regeneration method under principle of temperature-pressure swing adsorption. It has Heating-less regeneration (PSA) adsorption type dryer structure is simple, high degree of automation a, Less air consumption than hot regeneration (TSA )dryer,, the depth of the advantage of desorption. To avoid Heating-less regeneration (PSA) adsorption type dryer big air consumption, frequent switching and hot regeneration (TSA )dryer structure is complex、 the power consumption of the big weakness, the comprehensive index has obvious advantages. The double-tower structure is used in The JLAH Adsorption Type Dryer: one tower absorbs moisture in the air at air inlet pressure and low temperature, part of the dry air in another tower regenerate the absorbent in the absorbing tower in the condition of low pressure and high temperature. After a set time, the two towers exchange to ensure the continuous supplying of the dry compressed air. The actual running procedure of each tower is divided into 3 stages: absorb – regenerate— re-pressurize(include heat and cool regenerate). The function of user’s manual is to guide the users how to used this equipment correctly and make daily maintenance. Users should read this manual fluently before using.
2 / 15
Please consider the environment before printing this document
Hangzhou Jialong Air Equipment Co., Ltd
3.Technologic Flow The JLAH-Type dryers process flow diagram,Shown in the following diagram. The compressed air enters into Tower A through IA, then the air is desiccated. The desiccated air goes to the outlet from CA, and part of the air is separated as the regenerating air before going to the outlet, after the flow control by RV, then it goes to B from OB after heated by H. There is moisture absorbed in the last half period in B. The regenerating air .brings all these moisture and eliminated by RB and MF. It is the heat reg The JLAH-Type dryers process flow diagram,Shown in the following diagram eneration stage. After a set time, H cut, then the regenerating air cool Tower B for the next half-period. It is the cool regeneration stage. Then, RB closes, Tower B begins to raise the pressure till the pressure of two towers is balanced. It needs time to raise the pressure to ensure the balance of pressure of two towers. Otherwise, it would cause the pressure undulating in the outlet. After half recycling period, IA closes and IB opens. Concerning the time of the procedure that the valve need, RA open again after 6 seconds. Now Tower B begins to dry air, and the Tower A enters the regeneration status, thus an exchange has been finished. After half period working, the Tower B returns to the regeneration status. This period is a recycling time. In a recycling period, each absorbing tower passed 3 stages: absorb – regenerate (include heat and cool regenerate) — re-pressurize. The procedure is controlled by Siemens LOGO!PLC. Air outlet
Air outlet
Air inlet A tower drying, B tower regenerating
Air inlet B tower drying, A tower regenerating
3 / 15
Please consider the environment before printing this document
Hangzhou Jialong Air Equipment Co., Ltd
4. Technical Parameter Table 1
Basic technical parameters
(The actual project drawings shall prevail) 型
号
JLAH1050 34
3
Normal inlet flow (Nm /min) Inlet presurre Bar Inlet temperature (℃) Consumption of regenerated ai Presure loss Bar Dew-point of gas in the exit (℃) Regenerating way Working way Operating way Power supply Heater power (kW)
7 ≤45
≤4-8 Inlet air flow ≤0.3-0.4 ≤-20~-45
Heat regeneration 2 towers exchange and continue working, the exchange cycle is 120min Fully-automatic PLC program control 380V / 50Hz /3PH 8
Weight ( kg)
Outside size (mm) Length×Width×Height
~1000 长L
2062
宽W
950
高H
2370
Air inlet/outlet connection
DN80 Flange
Note: 1.Intake air flow rate is defined as the intake pressure of 7Bar, the temperature was 38 ° C, the inlet air relative humidity is 100% of the import condition saturated compressed air is converted to an absolute pressure of 1 Bar, the temperature was 20 ° C of the predetermined conditionsdryer into the volume of air flow, the same below 2.The regeneration gas consumption varies according to the size of the inlet air pressure, high pressure, gas consumption is small; pressure is low, the gas consumption of large 3.Inlet / Outlet flange welded flange sudden panel equipped with metric pipe, flange standard for the Ministry of Chemical Industry Standard HG20592 4.Dimensions are subject to change without notice 5.The table pressure If not specified, all refer to gauge pressure, the same below
4 / 15
Please consider the environment before printing this document
Hangzhou Jialong Air Equipment Co., Ltd
5.Control System The system program is reached by PLC. The system work Periodic Table are shown in Table 2. The entire system of electrical wiring diagram see attached page. Table 2 Periodic Table Working period Time Tower A Tower B
1/2 period (60 min) 6s
I 29min54s
28min30s
1/2 period (60 min) II 1min30s
Dry Time Heat Cool delay regenerate regenerate
III IV 6s 29min54s 28min30s 1min30s Time Heat Cool Pressur delay regenerate regenerate e filling
Pressur e filling
Dry
Control system
Photos are for reference only, specific in kind prevail
5 / 15
Please consider the environment before printing this document
Hangzhou Jialong Air Equipment Co., Ltd
6.System Disposition In order to ensure the quality of compressed air after the treatment by the dryer and to prolong the lifetime of dryer, the following items should be concerned in the installation: 1) Pre-filter should be installed in the entrance of the dryer to deal with the liquid water, solid particle and oil aerosols. If the liquid water enters directly into the absorbing tower, it would badly damage the running condition of the dryer to greatly raise the dew point in the outlet and even make failure operation of the dryer. And the oil aerosols will extremely pollute the absorbent: not only raise the dew point, but also shorten the life time of the absorbent. To lengthen the service life of the filter, it is recommended that the user from coarse to fine filtering and summarized the way to filter configuration. Recommended configuration the Company production of Grade 9 filter as a coarse filter, After the filtered with a filter, compressed air content of solid and liquid particles 3μm, the oil mist residual content 5ppm. At level Grade 9 filter after , the recommended configuration the company produces the Grade 5 filter as oil filter After the filtered with a filter ,compressed air content of solid and liquid particles 0.01 u m, oil mist residual content of 0.01 PPM. 2).The rubbing of the absorbent will bring some dust. To ensure the clean of the air, normally we should install post-filter. According to the different requirement of the quality degree of the compressed air, users could dispose different post-filter. For the higher using requirement, you could add other filters behind this filter. We recommend you JHF7-grade filter. After the filtered with a filter, compressed air content of solid and liquid particles 1 μm, the oil mist residual content 1ppm. 3). User should put in by-pass valve, closing valve and releasing valve in the system disposition to ensure the successive gas supplying in the lower reaches when it is in the maintenance. 4). Reliable ground-connection set is necessary to be put in this equipment. Figure II System Configuration Diagram
6 / 15
Please consider the environment before printing this document
Hangzhou Jialong Air Equipment Co., Ltd
7.Operation 7.1 Open the equipment 7.1.1 Close the air exit valve, releasing valve set by the user and open the by-pass valve, slowly open the air inlet valve set by the user in order to raise the pressure of the dryer to working level; adjust the pressure regulator valve in the front of pneumatic valve to regulate the pressure around 2 Bar and lock. 7.1.2 Open the switch in the panel of controller to power on the dryer. 7.1.3 Slowly open the air outlet valve after several minutes normal running of the dryer. 7.1.4 Close the by-pass valve of the dryer. 7.2 Shut the equipment 7.2.1 Close the switch in the panel of controller to power off the dryer. 7.2.2 Disconnect the circuit breaker in the electrical box, The dryer LED off
is powered off. Power
7.2.3 Close the air inlet and outlet valve of the dryer. 7.2.4 Slowly open the releasing valve till the pressure of the two towers is zero. 7.3 Maintenance 7.3.1 Filter regulator outlet pressure is not in the normal range, the Pressure regulating knob need to adjust the filter regulator adjustment method: pull up the upper part of the filter regulator knob clockwise rotation pressure, counterclockwise rotation decompression, and so reach the desired pressure reduction knob lock(0.4Mpa). Users should regularly is cleaning the filter regulator filter body, in order to ensure the quality of the air cleaning method: rotate and pull down the lower body of the bayonet cup, with a neutral detergent solution to clean the filter and cups. Filter regulator for automatic drainage way, users should install drainage pipes to the appropriate location. (Filter regulator is usually placed in the electrical box below.) 7.3.2 Regeneration gas is too big or too small, need to adjust gas regulating valve. Adjust when a time turning a twice regulate dryer running two cycles and then as the case may be adjusted. The regeneration gas control valve is usually located in the top of the device. (JLAH-10, and the following models of micro gas regulating valve.) 7.3.3 Regeneration gas heating temperature is too high or too low, the need to adjust the heating temperature setting upper and lower limits. The lower limit adjustment: temperature controller (tipping the electrical box door) panel switch switch to the lower limit position (when the lower limit set value), with a small screwdriver to rotate the lower limit regulation switch will be located set temperature to normal, clockwise to increase the temperature on the contrary reduce, adjust the switch reversal measurement file upon completion the ceiling set adjustment: Refer to the lower limit of the adjustment. Temperature setting: the lower limit of 80 ° C, the upper limit of 7 / 15
Please consider the environment before printing this document
Hangzhou Jialong Air Equipment Co., Ltd
120 ° C. 7.3.4 While the dryer is in work, the pressure of the regenerating tower should not surpass 0.2 Bar. If it surpasses this value, the valves maybe no have malfunction, or the muffler jam. The muffle should be taken apart immediately to clean the clog. If it is badly jammed and not capable to clean, the muffler should be changed. 7.3.5 Dryer after running for some time, the dry bed sink slightly to check and supplement or replace the desiccants. Desiccants should be screened prior to loading, remove the dust and make it uniform particles. 7 3 6 Regularly check the work of each valve and seal state. 7.3.7 Regularly check the electrical components are in good contact, often clear the inside and outside of the dust distribution box. 7 3 8 Runtime muffler sometimes a small amount of drainage, which is a normal phenomenon, such as the massive drainage please refer to the failure and exclusion
8 / 15
Please consider the environment before printing this document
Hangzhou Jialong Air Equipment Co., Ltd
8.Breakdown and Settlement No.
Appearance of breakdown
Analysis of Reason
Settlement
No current input.
1
Check the voltage.
Power switch malfunction. Turn the Switch, the dryer doesn’t work. Breaker isn’t open. Electrical fault.
equipment
Air flow surpasses maximum.
Change the switch. Change the breaker. is Check connection or change the electrical equipment
the Change the dryer with more capacity.
Absorbent is out of date. 2
The dew-point is too Absorbent is polluted. high.
Change the absorbent. Change the absorbent after checking of the pre-filter.
The pressure of air is too Raise the air pressure or low or the temperature is lower the temperature. too high.
3
Working pressure has not reached the working level while pressure filling.
The regeneration valve is Check and repair not closed tightly. regeneration valve.
The dried compressed air is Reduce the output of the too much. dried compressed air. The muffle is jammed.
4
the
The pressure of the The regeneration valve has regeneration tower is not been open totally. higher than 0.2 Bar. The sealing of the check valve is not good.
Clean or change the muffler. Check and repair regeneration valve.
the
Check and repair check valve.
Exhaust valveRA\RB fault Repair or replacement can not open
5
Controlling the Run when the two valve of towers were pressure electromagnetic (not switch) failure
exhaust the Replace the solenoid valve valve
The controller does not Replacement or output the program does manufacturers not or hardware problem 9 / 15
Please consider the environment before printing this document
contact
Hangzhou Jialong Air Equipment Co., Ltd
Pressure relief pressure too
valve
Switching valve fault
Adjust the pressure Replacing valve
the
switching
Control intake valve IA, IB Replace the solenoid valve solenoid valve fault 6
The controller does not Run time muffler output the program does Replacement or manufacturers exhaust is big not or hardware problem
contact
Foreign body stuck check Repair or replacement valve or fault
7
8
Get angry too big
Off small and then angry valves
Pre-filter drainage poor
Shimizu drain or replace
The muffler when Regeneration gas is too Increase renewable gas running a large small number of drainage Regeneration temperature Increase the regeneration is too low temperature Clogging of the Equipment runtime element pressure drop Equipment leak
filter Replace the filter Eliminate leak
10 / 15
Please consider the environment before printing this document
Hangzhou Jialong Air Equipment Co., Ltd
9.Main parts and wearing parts list 压缩空气干燥机零件清单 Compressed air dryer parts list 项目 Project No.
零件名称 Part Name
零件图号(规格) Drawing No. (Specifications)
单位 Unit
数量 Qty
1
Y 过滤球阀 Y type filtering ball valve
JAL23D991
只 pcs
3
2
自动排水器 Automatic drainer
JAL21D200
只 pcs
3
JAL55E981D
只 pcs
2
JAL25E711D
只 pcs
2
JA35E876D
只 pcs
2
JAL31A091
Kg
700
3 4 5
6
前置过滤器 JLF9F1050 滤芯 Pre filter 除油滤芯 JLF5F1050 Oil element filter 除尘滤芯 JLF7F1050 Dust element filter 超强专用吸附剂 Super special adsorbent
备注 Remarks 易损件 Wearing parts 易损件 Wearing parts 消耗件 Consumable parts 消耗件 Consumable parts 消耗件 Consumable parts 消耗件 Consumable parts(Using 8000-16000 hours to check & replacement) 易损件 Wearing parts 易损件 Wearing parts(When replacing adsorbent)
7
消声器
Silencer
JAL29A758
只 pcs
2
8
扩散器 Diffuser
JAL27A327
只 pcs
4
9
进气气动程控阀门 Pneumatic control valve (IN)
JAL37A132
只 pcs
2
预备件 Preparation parts
10
排气气动程控阀门 Pneumatic control valve (OUT)
JAL39A889
只 pcs
2
预备件 Preparation parts
11
电磁阀 Electromagnetic valve
JAL27D873
只 pcs
4
预备件 Preparation parts
12
过滤减压阀 Filter pressure reducing valve
JAL33D632
只 pcs
1
预备件 Preparation parts
JAL32A661
只 pcs
2
JAL32A789
只 pcs
2
JAL28D307
只 pcs
2
JAL24C879
块 pcs
1
JAL24C709
块 pcs
1
13 14 15 16
17
排气止回阀 Exhaust gas check valve 再生止回阀 Regeneration of check valve 空气压力表 Air pressure gauge PLC 程序控制器(含程序)The PLC program controller (Containing procedures) PLC 扩展模块(含程序)The PLC expansion modules (Containing procedures)
18
温度探头 Temperature probe
JHL30M
支 pcs
1
19
转换开关 Changeover switch
JHL30MZHKG
只 pcs
1
20
指示灯(红绿黄)Indicator lamp (red green yellow)
JHL30MZSD
只 pcs
3
JHL30
件 pcs
1
JAL22C110
只 pcs
1
21 22
电加热器芯 Electric heater core 温度控制器 The temperature controller
11 / 15
Please consider the environment before printing this document
Hangzhou Jialong Air Equipment Co., Ltd Remark: In order to ensure the long-term and stable operation of the equipment, please prepare some spare parts, such as: Y type filtering ball valve、Automatic drainer、Pre filter、Oil element
filter、Dust element
filter、
Super special adsorbent、Silencer、Diffuser 备注: 为保证设备的长期稳定运行,请准备部分备件,如: Y 过滤球阀、自动排水器、主管道滤芯、除油 滤芯、除尘滤芯、超强专用吸附剂、消声器、扩散器
12 / 15
Please consider the environment before printing this document
Hangzhou Jialong Air Equipment Co., Ltd
10. Preventive maintenance and project list 部件名称 Commodity Specifications
检修周期 Maintenance cycle time
1.
Y 型过滤球阀 Y type filter ball valve
每天检查一次 Daily check
2.
浮球自动排水器 floating ball automatic drainage device
每天检查一次 Daily check
3.
空气过滤器 Air filter
4.
吸附剂 adsorbent
4000-8000H 一次 Check once per 4000-8000H 8000H 一次 Check once per 8000H
5.
气流扩散器 Air diffuser
8000H 一次 Check once per 8000H
6.
过滤减压阀 Filter relief pressure valve
每周一次 Once a week
7.
加热器温度 Heater temperature
每周一次 Once a week
序号 No.
8.
9.
设备外部的清洁 Cleaning the appearance of equipment 电器箱内的清洁 Cleaning the Electrical box
主要工作 The main work content 排水是否通畅,必要清洗滤网 Confirm if the drainage is unobstructed, cleaning strainer if necessary 排水是否通畅,必要清洗滤网(建议在自 动排水器前安装手动排水旁通管路) Confirm if the drainage is unobstructed, cleaning strainer if necessary (suggest installation manual drainage bypass pipeline in front of the automatic drainage device) 更换一次空气过滤器滤芯 Replace filter element of air filter once 检查吸附剂,必要时候更换 Check the adsorbent, replace if necessary 每次更换吸附剂的同时更换扩散器 Each replacement of adsorbent should replace the diffuser meanwhile 检查压力设定,调整到 0.4Mpa Check the pressure setting, adjust to 0.4Mpa 检查加热器温度设定限值,一般工况最 低下限 80℃,最高上限 150℃ Check the heater temperature setting limits, minimum general conditions is 80 ℃, 150 ℃ is maximum
每天一次 Once a week
擦扫设备外部的灰尘和油污 Wipe the dust and oil outside the equipment
每周一次 Once a week
吹扫电器箱底部和电器元件上的灰尘 Blowing the dust on the electrical box bottom and electric component
10.
13 / 15
Please consider the environment before printing this document
Hangzhou Jialong Air Equipment Co., Ltd
Compressed air dryer performance guarantees: 1、 Running Reliability Assurance: The company not only has senior technical staff, but also has a strong ability to develop actual experienced technical team, in the production of a set of the complete work process card and corporate standards. 2、the assurance of the ability to adapt to the Variable Work Condition The Company dryer is designed according to the actual situation of our climate. 2、 This product uses standard: JB/T 10532-2005 《 Adsorption compressed air dryers for general use》;Q / HJL 002-2012Enterprise standard. Thank you for using the dryer for the production. The quality of the products will give your company a very good value for money and a good product. Addition to provide the best after-sales service, the company also continued to study the development of compressed air purification products; such as: efficient compressed air-cooler, the air tank, efficient oil removal and efficient level filter, main production pressure swing adsorption nitrogen, oxygen plant, if necessary, please contact the company. If you are in the installation, use the company's products, If you have any questions or unknown place, please call the communication links, we will be the fastest and best way to serve you!
14 / 15
Please consider the environment before printing this document
Hangzhou Jialong Air Equipment Co., Ltd
Quality Assurance book 1.
2.
3.
Hereby warrant dryer manufactured by the Company in Miho period, under normal circumstances, such adverse circumstances, be borne by the company responsible for the free repair, but your organization must be in accordance with the provisions of the Company Manual, to do regular maintenance. Dryer conditions, must be in compliance with the request of the Company, subject to change, notify our service personnel to come forward to discuss treatment, in order to maintain the efficiency and life of the machine. The company will provide you with the relevant technical information, for you to make the most perfect after-sales service to ensure your satisfaction.
15 / 15
Please consider the environment before printing this document
We always strive to provide users with more clean compressed air 我们始终努力为用户提供更加清洁的压缩空气
HANGZHOU JIALONG AIR EQUIPMENT CO.,LTD Address: NO.168,Wuxing village,Qiaosi Street, Yuhang District, Hangzhou, China Tel: 0571-85365111 Fax: 0571-85365000 Server:400-103-8600 Post code: 310001 E-Mail:
[email protected] http://www.jialongequip.com.cn
Compressed Air F ilter Operation and maintenance manuals
HANGZHOU JIALONG AIR EQUIPMENT CO., LTD. 2014
Hangzhou Jialong Air Equipment Co., Ltd 1.Product Briefing For the compressed air filters, all the filtration cores refer to the original‐state products by the world‐famous Hangzhou Jialong Company and the shells of the filters are designed according to the prototype of Jialong Company, including five grades of Grade 9, Grade 7, Grade 5, Grade 3 and Grade 1, etc. by different degrees of filtration precision. The compressed air runs into the filter and removes effectively the contaminants such as moisture, dust and oil fume, etc. in the compressed air, thus the compressed air is made clean and dry to improve the reliability of the pneumatic equipment and the quality of the product. As the filtration cores of HANKISON Company are constructed with multi‐layer filter bed, their extremely high dust containing capacity, high effectiveness and long lifespan have been unanimously recognized in the world compressed air purification equipment domain. The filters made by our company are simple in structure, easy for filter cores to be mounted and dismantled and secured in operation performance. We provide the following 5 grades of filters for your selection. 2. Filter specification HF 9 (JLF9)Grade Main Pipeline Filter Element Removable stainless steel mesh core, Separation of 10μ or more solid and liquid particles by centrifugal force Replaceable glass fiber filter 3μ or more solid and liquid particles completely, The gravity action brings the water at the bottom of the filter and discharge the water. 1ppm oil mist residual content HF 7(JLF7)Grade Main Pipeline Filter Element Corrosion protection for inner and outer layer of filter element Multilayer glass fiber filters solid and liquid particles which is more than 1μ Epoxy laminated glass polyester layer protection fiber coalescence of oil mist and filtration of solid particles HF 5(JLF5)Grade Main Pipeline Filter Element Filter element inner and outer layer of corrosion protection Multilayer glass fiber and micro fiber, Large particle filter, for the next phase of the pre filtering composite fiber layer further coalescence micro oil mist layer tightly attached sponge net Remove 0.01 or more solid and liquid particles, remove 99.99+% micro oil mist, oil mist residual content is 0.01ppm
1 / 3 Please consider the environment before printing this document
Compressed air dryer operation instructions
3. Installation and deployment
1.1 For the convenience of operation and replacement for maintenance, the filter should be installed according to the pipeline indicated in the chart on the right: 1.2 The deployment of the filter can refer to the pattern indicated in the following chart
2 / 3 Please consider the environment before printing this document
Compressed air dryer operation instructions
4.Model and maintenance
3.1The filters made by our company are the equipment that takes the compressed air as the medium. It is strictly forbidden to run other media directly into the filter. Pay special care not to exceed the specified maximum work. Take special care not to exceed the specified maximum work condition at use. 3.2The filtration precision of the compressed air filter is determined under certain condition. The inlet air quality has obvious influence over the operation effect of the precision filter cores. When necessary the proper prep0sitive filter should be added to make the pretreatment of the inlet air quality. The filter deployment and installation should follow the JLF9 – JLF7 – JLF5 – JLF3 – JLF1 sequence. Otherwise the filtration effect will not be reached and the lifespan of the filter cores will be reduced by big margin. 3.3The filter core is the principal part of the filter. The pressure drop at the filter inlet and outlet should be checked regularly at work. When pressure drop reaches higher than 0.7 Bar, then the work lifespan of the filter core is nearly at the end and the filter or the filter core must be replaced in time (The initial pressure drop of a single filter core is about (0.1‐0.2)Bar. 3.4Should be resistant to chemical causticity. Generally the compressed air does not contain any contaminants harmful to filter cores. However, some hydrocarbon species, acid species, alkali species and some special chemical substances may enter into the filter through compressor under the special circumstances. 3.5Filter must raise or reduce pressure slowly at operation and dismantling of the filter should be performed under the pressure‐free condition. 3.6Replacement of filter cores: Should take care during dismantling or mounting the filter core. Should not hold the filter core barrel with hand to avoid the surface filter material of the filter core from being damaged. 3.7For the filters equipped with manual sewerage, should not open the sewerage under the pressure situation (The filter mounted with automatic sewerage will automatically discharge the accumulated water in the filter barrel). 3.8Should not select filter by the diameter of the fitting pipe, while the air treatment capacity and the usage pressure should be taken for selecting a filter. 3.9By strictly following the above conditions, the use lifespan of the HF9, HF7, HF5, and Hf3 types of filter cores in this series can reach over 8000 hours and that of HF1 type of filter cores will be 2500 hours (It is taken to be the work lifespan limit when the work pressure drop of a single filter core reaches 0.7 Bar).
The operating pressure is 0.7‐1.0MPa, belong to special operating pressure. Alarm: 1、 Please don’t change the drain time that was setted. 2、Please attention drain direction when install organ of catch water, for fear the high‐pressure air to harm people if draining. 3、Suggest use of 4000 hours to replace the filter element.
3 / 3 Please consider the environment before printing this document
HANGZHOU JIALONG AIR EQUIPMENT CO.,LTD Address: NO.168,Wuxing village,Qiaosi Street, YuhangDistrict, Hangzhou, China Tel: 0571‐85365111 Fax: 0571‐85365000 Server:400‐103‐8600 Post code: 310001 E‐Mail:
[email protected] http://www.jialongequip.com.cn