CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON”

CONTRACTOR – PTC-LIL

REV. NO.

DESCRIPTION

0

Issued for Information

Document Document Number

PREPARED BY & SIGNATURE

REVIEWED BY & SIGNATURE

Capt. Vu Van Ha Pham Tuan Anh

CLIENT -VSP

APPROVED BY & SIGNATURE

DATE

Alan Roberts

16-Jun-09

CHECKED BY

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

APPROVED BY

DATE

Sheet No.

Page 1 of 50

Issue Date

16-Jun-2009

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

AMENDMENT SHEET

REVISON #

Prepared By

Description

0

VVH

Review for Comment

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 2 of 50

Issue Date

16-Jun-2009

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

TABLE OF CONTENTS    SECTIONS      1      2      3                4                              5          6                             

 

PAGE  INTRODUCTION 

 



SAFETY POLICY 



RESPONSIBILITY 

 

3.1  3.2  3.3  3.4 

8  8  9  11  

Operations  Master of Towing Vessel  Lines of Communications  Routine Communications 

PROJECT OPERATION  4.1  Narrative  4.2  Barge & Tug details  4.3  Bollard pull  4.4  Passage Planning  4.5  Tow Route  4.6  Bunkering 

  13  14  14  15  18  20 

HSE PROCEDURE AND CONTENGENCY PLAN  5.1  Narrative  5.2  General Precautions during normal towing 

  22  22 

TRANSPORATION ANALYSIS  6.1  Narrative  6.2  Stability Analysis  6.3  Stowage Arrangement  6.4  Towing and Ballast Condition  6.5  Design Weight Data  6.6  Intact & Damage Stability Assessment  6.7 Seafastening Design 

28  28  31  33  35  36  37 

ANNEXES  ‐ Annexe 1 ‐ Towing Arrangement  ‐ Annexe 2 ‐ Bollard Pull Calculation  ‐ Annexe 3 ‐ Certificate of Towing Equipment 

    Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 3 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

                                             

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

SECTION 1 

INTRODUCTION 

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 4 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

  1.0         

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

INTRODUCTION    This  Manual  is  prepared  for  the  Sea  Transportation  of  the  Linepipes  and  Miscellaneous  Items on the Flat‐top barge “SYNERGY FALCON” from Vietsovpetro Port, Vung Tau, S. R.  Vietnam  to  Nam  Rong  –  Doi  Moi  Oilfield,  Offshore  Vung  Tau,  S.  R.  Vietnam  during  the  month of June – July 2009. 

     

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 5 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

                                    SECTION 2    SAFETY POLICY         

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 6 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

  2.0     

                       

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

SAFETY POLICY  The Master of the Towing Vessel will ensure that the Safety Policy and Safe Objectives, as being  laid out in the Towing Manual are being implemented and followed by the crew on board the  tug.  This is to ensure safety at sea, prevention of human injury or loss of life, and avoidance of  damage to the environment, in particular, to the marine environment and to property.  The following rules are being implemented, including but not limited to:  ‐  ‐  ‐  ‐  ‐  ‐  ‐ 

International SOLAS Convention  International Regulations for prevention of Collisions at Sea  MARPOL 73/78 Regulations  STCW (2001 edition)  ISPS (2003 edition)  ISM (2002 edition) and revised guidelines on implementation of ISM Code  IMO Guideline for Safe Ocean Towing, MSC Circular 884, 21 December 1998 

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 7 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

                                    SECTION 3    RESPONSIBILITIES       

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 8 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

3.1     

   

OPERATIONS  The Operations Personnel will be responsible for all vessels’ operational activities asscociated  with the project.  These shall include, but not limited to, the co‐ordination with agents, pilots,  customs, port authorities and the tow‐out operation.  During the  voyage the  Operations Personnel  will  keep the  Petechim – Likpin  Consortium /  Vietsovpetro J/V Offshore Construction Division project department fully informed in respect  of the operational progress and technical update. 

  3.2     

     

MASTER OF TOWING VESSEL  The Master on board the Towing Vessel is responsible for the smooth towing operation for  the proposed voyage. He is, as Owner’s and Petechim – Likpin Consortium / Vietsovpetro J/V  Representative, responsible in all respects of a safe transportation, navigation and reporting  of the progress of the tow as from departure Vietsovpetro Port, Vung Tau, S. R. Vietnam to  Nam Rong – Doi Moi Oilfield, Offshore Vung Tau, S. R. Vietnam.  He will co‐ordinate / assist and resolve any emergency situation such as   -

   

       

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

Personal accidents  Fire  Man Overboard  Abandon ship  Towline failures and other material incidents  Collision 

In case of any accident or emergency, the Master of Towing Vessel is to report immediately  to Owner’s Designated Person Ashore (DPA), and thence, if safety of the tow is concerned  / impaired, to Project Managers of Petechim ‐ Likpin Consortium.  The Master of the Towing Vessel will also, as far as his judgement in regards to the safety of  the tow will not be endangered, will reduce speed and deviate as necessary.  The  Master  will  inform  Petechim  ‐  Likpin  Consortium  immediately  in  respect  of  these  deviations and / or speed deviations reductions and will be recorded in Daily Position Report  (DPR) and Deck logbook accordingly. 

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 9 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

3.3                                                                     

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

LINES OF COMMUNICATIONS 

Document Document Number

Tug   “FALCON 17” 

REPORT FOR THE TOW  INCIDENT / ACCIDENTS 

OWNERS 

PETECHIM – LIKPIN  CONSORTIUM 

MWS  VIETNAM ENERGY INSPECTION  CORP. 

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 10 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

3.3                     

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

LINES OF COMMUNICATIONS  Contact Details  Petechim – Likpin Consortium     Mr. Tran Manh Hung  Telephone :      +84 8 39106960    Fax              :       +84 8 39106938    Mobile       :       +84 903822750    Email          :       [email protected]  Vietnam Energy Inspection Corporation (MWS) 

              Mr. Nguyen Van Que   

Telephone :       +84 8‐39118565  Fax              :       +84 8‐39118567  Mobile       :       +84 90‐3388523 (Mr Que)                                                   Email          :       [email protected]                                                                        Mobile       :       +84 90‐9328378 (Mr Luyen)                                                                        Email          :       [email protected]                                                                        Mobile       :       +84 91‐3533515 (Mr Tien)                                                                        Email          :   [email protected]     

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 11 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

  3.4         

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

ROUTINE COMMUNICATION  Daily Position Report  The Following format of the daily report will be submitted to Petechim – Likpin Consortium  by the Master of Towing Vessel “FALCON 17” 

   

   

¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾  

Document Document Number

Report Time and Date  Latitude (XX° XX.XX’ N / E) / Longitude (XX° XX.XX’ W / E)  Distance last 24 hours (XXX.X NM)  Course (XXX°)  Present Speed (XX.X Knots)  Speed 24 hours (XX.X Knots)  General Average Speed (XX.X Knots)  Total Running hours  Distance Covered (XXX.X NM)  ETA  Deviation (NM)  Hours at reduced speed  Wind Direction (XX°) / Speed (XX Knots)  Sea (XX Metres)  Swell Direction / Height (Metres)  Weather Outlook  Fuel consumption 24 hours (XX m3)  Lub Oil (LO) Consumption 24 hours (XX ltrs)  Fuel R.O.B. (XX m3)  Luboil (LO) R.O.B. (XX ltrs)  Potable water R.O.B. (XX m3)  RPM setting  Mean Exhaust Temperature  Towing wire length  Towing wire tension (min/max)  Roll / Period (Towed Unit)  Pitch / Period (Towed Unit)  Remarks :  Tow Progress :  Tow Outlook : 

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 12 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

                                    SECTION 4    PROJECT OPERATION                       

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 13 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

4.1     

   

   

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

NARRATIVE   The towage contractor shall provide the tug (fully fuelled, manned and operational) and will  execute the towage operation of the towage of the Flat‐Top Barge “FALCON 17” loaded with  Linepipes  and  Miscellaneous  Items,  actual  hook  up  and  the  tow  from  Vietsovpetro  Port,  Vung Tau, S. R. Vietnam to location Nam Rong – Doi Moi Oilfield, Offshore Vung Tau, S. R.  Vietnam.  The tug Master will inspect and supervise the connection of the tug’s towing gear and the  towing  gear  of  the  barge  “FALCON  17”,  consisting  of  main  and  emergency  bridle  configuration, including valid certification.  Anticipated date of departure for the proposed tow from Vietsovpetro Port, Vung Tau, S. R.  Vietnam is expected to be during the 2nd week of June 2009. The place of departure must  always be Safe and Accessible. 

  4.2  BARGE & TUG DETAILS    4.2.1  Barge “SYNERGY FALCON”      The unit, which was originally constructed in 1990 in Fujian, P.R. of China, was converted/rebuilt in  2007 by Falcon Shipping  at Ba Son Shipyard, Ho Chi  Minh City, S. R. Vietnam.  The unit  is  a non  propelled rectangular flat‐top cargo barge manufactured in steel with a round bow and flat stern. 

       

         

 

Skegs are fitted for directional stability whilst under tow.  The hull is divided by two (2) longitudinal and eight (8) transverse watertight bulkheads so forming  twenty‐six (26) spaces, with two (2) additional fresh water tanks and two (2) chain lockers within  these spaces  The  unit  is  Classed  by  Vietnam  Registry  (VR)  with  the  Notation  *  VRH1  –  1  Restricted  area  of  navigation. 

Particulars  Length  Breadth  Depth  Summer Freeboard  GRT / NRT  Maximum Deck Loading 

Document Document Number

 

:  :  :  :  :    : 

82.87 metres  21.40 metres    4.90 metres    3.70 metres  2,110 / 633  9 tonnes (80 KN) per m2 

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 14 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

4.2  BARGE & TUG DETAILS    4.2.2  Towing Vessel “FALCON 17”      The unit is a 23 metres steel hull coast tug built in 1977 with the accommodation /superstructure is  located  at  midship  a  top  of  which  is  the  all  round  view  navigation  bridge.  The  machinery  space  is  below  the  superstructure  and  towing  arrangement  is  on  the  aft  deck.  The  vessel  is  Classed  by  Vietnam Registry (VR) with the Notation * VRH II Tug boat, * VRM. 

   

Particulars 

 

 

  4.3     

   

  Owners / Managers  Length  Breadth  Depth  Gross / Net Tonnage  Horse Power  Built in  Year of build  Bollard Pull  Speed (Free running)  Fuel Capacity  Fuel Consumption per 24 hours   

:  :  :  :  :  :  :  :  :  :  :  : 

Falcon Shipping JSC, Ho Chi Minh City, S.R. Vietnam  23.04 metres    7.45 metres    3.90 metres  157/47  2 x 1,060 BHP, total 2,120 BHP  Courseulles, France  1977  (22 Tonnes) Certified by V.R., dated 15 July 2008.  10 knots  80 m3  7‐8 m3 

BOLLARD PULL  For  the  voyage  from  Vietsovpetro  Port,  Vung  Tau,  S.  R.  Vietnam  to  Nam  Rong  –  Doi  Moi  Oilfield,  Offshore  Vung  Tau,  S.  R.  Vietnam,  during  the  month  of  June  –  July  2009,  extreme  weather condition is expected to occur along the tow route of South part of South China Sea.  The weather during the month of June‐July is generally Southwestly  and with average force 4  to  5  Beaufort  scale,  but  can  go  up  to  force  6‐7  or  more  south  part  of  South  China  Sea,  significant wave height is between 2 to 3 metres.  A  minimum  19  tonnes  bollard  pull  would  be  adequate  for  the  proposed  tow  (See  Annexe  –  Bollard Pull Calculation). 

 

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 15 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

  4.4         

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

PASSAGE PLANNING  The  towing  route  selection  has  to  be  made  to  ensure  the  best  navigational  aids  and  environmental advantages, such as sea / wind and current particulars.  Routeing Charts for South China Sea will be referred to ascertain the best recommended route  to be undertaken for the proposed voyage. 

    The towing vessel Master will deviate if necessary in view of deteriorating weather conditions.    4.4.1  Nautical Charts and Publications      Following nautical charts and publications are required for the proposed voyage on board the  towing vessel and will be corrected up to the latest received Notice to Mariners.      British Admiralty Charts : 1016, 1261, 3986      Admiralty Sailing Directions : NP 30      Admiralty List of Lights : Volume F (NP 79)      Admiralty List of Radio Signals : Volume 6 (4)      Admiralty Tide Tables : Volume 3 (NP 203) or Vietnam Tide Table Volume 2      Mariners Handbook : NP 100      Ocean Passages for the World NP 136      Guide to Port Entry    4.4.2  Weather Routing Services      The  Tug  will  receive  daily  weather  forecasts  via  Radio  Weather  Stations  and  via  Navtex  messages  along  the  tow  route.  Climatological  data  and  weather  routine  provided  by  Meteorological Office are useful information that must be referred to during the passage.      Weather forecast will be provided by Offshore Weather Services Pty Ltd (OWS).            Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 16 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

  4.4.3  Weather / Meteorological Agency      For this proposed  voyage from Vietsovpetro Port, Vung Tau to Nam Rong ‐ Doi Moi Oilfield,  Offshore S.R Vietnam during the month of June ‐ July, the extremes of wind and wave are most  likely to occur in South China Sea.       The Meteorological  Office  will supply  weather forecasting,  and  during  deteriorating weather  conditions, the meteorological agency will discuss for support and advice accordingly for any  alternative route.    4.4.4  Limiting Weather Condition For Transportation      The limiting weather condition for the proposed transportation will be as follows:      ‐   Significant Wave Height (Hs)  :  3.20 metres    ‐  Mean Period :        6 sec    ‐  Current :        1 m/sec    ‐  Wind Speed :        26 m/sec   

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 17 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

  4.4  PASSAGE PLANNING    4.4.4  Procedures when Manoeuvrability is being restricted and all areas during day / night when  visibility is hampered by fog or other meteorological conditions.      During transit, the towing vessel will announce the following message on VHF channel 16, if  required for safe navigation.      Message,  Message,  Message  this  is  vessel  “FALCON  17”  towing  barge  “SYNERGY  FALCON”,  loaded with Line pipes and Miscellaneous Items, please listen for my information broadcast on  channel 13.      On working channel 16      Message  (3x),  this  is  tug  “FALCON  17”  towing  barge  “SYNERGY  FALCON”  loaded  with  Line  pipes and Miscellaneous.      Our present position : Latitude / Longitude    Our present course : ‐‐‐‐‐‐‐‐ degrees    Our present speed   : ‐‐‐‐‐‐‐‐‐ knots    Total length of the transport ‐‐‐‐‐‐‐‐ metres      “FALCON17” is standing by on VHF channel 16 & 13.    A wide berth is requested, end of message.     

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 18 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

  4.5  TOW ROUTE    4.5.1  Departure Port      The  berth  is  at  Vietsovpetro  Port,  Vung  Tau,  S.  R.  Vietnam  at  approximate  Geographical  Position Latitude 10 degrees 23.20 minutes North, Longitude 107 degrees 05.22 minutes East.      The area is benign and is considered as safe and accessible for the proposed tug and where the  tug is permitted to commence the towage in accordance with local rules and Port Authority of  Vung Tau instructions. However, weather and sea conditions will be closely monitored for the  hook‐up  of  the  tow  line  of  the  towing  vessel  to  the  main  bridle  of  the  barge  “SYNERGY  FALCON”.      The hook‐up will take place in daylight hours and with a favourable weather outlook for the  next 72 hours.      N.B. For any and all vessels that may be requested to use or assist at this berth, it is essential  that Owners inspect the facility and agree in writing that it is safe and that these operations  will be the responsibility of the tug’s Master. 

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 19 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

4.5  TOW ROUTE    4.5.2  Route  from  Vietsovpetro  Port,  Vung  Tau,  S.R  Vietnam  to  Nam  Rong‐Doi  Moi  Oil  Field,  Offshore Vung Tau S.R Vietnam.         

       

   

  Planning on the Tow Route is the responsibility of the Tug Master and the Owners.      Route.  The  tow  route  would  be  proceeding  west  from  Vietsovpetro  Port  then  Southwest/  South  in the  traffic channel  of Vung Tau Port,  thence  Southeastly direction  toward the  Nam  Rong‐Doi Moi Field.  Distance.  Distance  from  Vietsovpetro  Port  to  Nam  Rong‐Doi  Moi  Field  is  approximately  95  nautical miles and with an average speed of 2.5 knots maintaining throughout the voyage, the  tow would take approximately 1.6 days. 

        Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 20 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

  4.5     

   

TOW ROUTE  Weather.  Along  this  tow  route,  the  sea  and  swell  directions  and  heights  are  determined  entirely  by the circulation  of  the  SW Monsoon  from April to  September.  The  wind expected  along the tow route is generally southerly to southwesterly wind force of 5 to 6 Beaufort scale  and could go up to 7 or more, with the significant wave height can go between 4 metres to 5  metres. Tropical storm may occur along the tow route although the frequency is not as high as  during the month of June ‐ July. However, actual sail‐away will be decided upon the condition  meeting  the  limiting  weather  condition  defined  earlier  in  this  document  and  the  suitable  weather forecast.  Sheltered Area: Vung Tau port is a nearest port on the tow‐route and destination too. Apart  for destination itself, Nam Rong – Doi Moi Oilfield, on the tow‐route there no natural port or  places  considered  suitable  as  a  port  of  refuge.  However,  designated  Holding  Areas  may  be  established  en‐route.  The  tow  spread  is  designed  to  survive  an  adverse  weather  condition  given that sufficient sea room to allow a controlled drifting situation is maintained. If deemed  required due to unfavourable weather conditions, the tow will against the weather and allow a  controlled  drifting  situation  (maintain  sufficient  power  for  steering)  and  also  use  sufficient  length of towline to avoid shock loads on the towline. 

  4.6         

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

BUNKERING  Bunkering en‐route will take place. The proposed Towing Vessel utilised for the proposed tow  will have sufficient fuel plus 25% of reserve for the each leg of the proposed voyage.  The tug “FALCON 17” has a fuel capacity of 80.0 m3, and with a maximum consumption of 8.0  m3, the  tug  would  have  a  range  of  10.0  days,  this  would  be  sufficient for  the entire  voyage  from Vietsovpetro Port, Vung Tau to Nam Rong – Doi Moi Field, Offshore Vung Tau.    

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 21 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

                                                SECTION 5    HSE PROCEDURES AND CONTINGENCY PLAN       

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 22 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

5.1     

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

NARRATIVE  In respect to HSE procedures and contingency planning, the Owner’s SMS procedures should be  followed, as well as Petechim ‐ Likpin HSE Manual if any should be consulted. 

  5.2  GENERAL PRECAUTIONS DURING NORMAL TOWING OPERATION    5.2.1  Tow line‐shortening      In  areas  of  shallow  water,  water  depths  less  than  35  to  50  metres,  the  Master  of                  “FALCON 17” will shorten the towline and adjust speed accordingly. Crossing over lesser water  depths being limited, in view of the catenary of the towing line and the maximum draft of the  barge “SYNERGY FALCON”.      The  tow  line  length  will  be  determined  during  the  voyage  by  the  Towing  Vessel  Master  accordingly to weather and sea conditions.    5.2.2  Additional Precautions and Contingency Planning      In an emergency, when the tow presents a direct danger to navigation, offshore structures or  coastlines  through  breaking  adrift  or  for  some  other  causes,  the  Master  of                  “FALCON  17”  is  bound  by  SOLAS  regulation  V/2  to  communicate  the  information  by  all  the  means at his disposal to ships and Authorities in the vicinity.      The  Owners  will inform  Petechim  ‐  Likpin  and  MWS  accordingly and  will  keep all  parties  fully  informed.  Owners  and  or  Petechim  ‐  Likpin  should  give  the  Master  of  the  Towing  Vessel  a  detailed Emergency Response Plan prior to departure Vietsovpetro Port, Vung Tau, S.R Vietnam.    5.2.3  Towline Failure      The “FALCON 17” is equipped with two tow ropes, PP Superdan 8  Strans 80mm diameter of 200  metres length each  with  certified MBL of 95  MT,  giving a  minimum  breaking strength ratio  of  4.32 : 1 to the bollard pull of the tug. The spare tow rope is available  onboard and  stowed in  such that the rope can be quickly and safe transfer to the towing hook in an emergency.      When a towline failure takes place in confined waters where heavy shipping traffic exits, the Tug  Master will decide to make an emergency connection with the aid of the emergency towing gear  of the barge “SYNERGY FALCON”.      However,  this  will  only  be  used  when  there  is  no  space  and  time  readily  available  for  the  re‐ connection operation to the main towing bridle.      The towing vessel should be sufficiently stored with spare shackles and towing chains in order to  establish a new towing connection.  Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 23 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

5.2.3  Towline Failure Cont’d …      In all cases, the arrangements for recovering the tow, should it break adrift, will be made by the  tug’s  crew  in  accordance  with  good  seamanship,  bearing  in  mind  the  seasonal  conditions  and  the area of operation.    5.2.4  Retrieving Towing Gear On Board “SYNERGY FALCON”      On  board  the  barge  “SYNERGY  FALCON”,  a  towing  bridle  retrieval  arrangement  will  be  fitted.  The crew of the tug will assist in retrieving the towing bridle and reconnection the towline  as  agreed with the tug Master of “FALCON 17” prior to departure.    5.2.5  Tug Failure      The “FALCON 17” has sufficient redundancy, i.e. two main engines and double steering gear and  sufficient spare parts on board, enabling the crew to perform the normal and basic repairs.      During the towage operation, the crew on board the tug will ensure that there will be a 24 hour  engine room duty according the SOLAS Rules and Company’s Instructions.    5.2.6  Propulsion failure      Whenever the “FALCON 17” has a failure on one of the propulsion systems, this will be reported  immediately to Petechim ‐ Likpin and the Owners by the Master together with an indication of  the time required for the repairs.      If  the  tug  has  a  black‐out,  the  Master  will  alter  course  in  order  to  avoid  the                  “FALCON 17” to collide with the towed unit.      The crew on board of the “FALCON 17” will be warned immediately by the General Alarm and  must be standby for possible alternation of towing rope or release of the towing connection.      ‐  The Master will inform immediately to Owner’s and Petechim ‐ Likpin by Single Side Band  (SSB) Radio or VHF with date / time and position as well as time required for repair and / or if  substitution of tug is required.      ‐  If a replacement tug is required, Owners and Petechim ‐ Likpin will immediately commence  necessary  action  as  required,  and  will  also  arrange  for  another  towing  vessel  to  tow  the  disabled tug to a safe haven, if required.      ‐  Final Incident Report to be drawn up and being send to Owners and Petechim ‐ Likpin office  will inform the Principals’ and Marine Warranty Surveyor accordingly. 

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 24 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

5.2  GENERAL PRECAUTIONS DURING NORMAL TOWING OPERATION    5.2.7  Deteriorating Weather conditions      During  the  month  of  June‐July,  the  Southwest  Monsoon  is  at  its  beginning  stage  in  the  South  China Sea, which may results in periods with bad weather and / or heavy seas / swell.      When the tow encounters deteriorating weather conditions, which have not been predicted in  the  daily  weather  forecasts,  the  Master  of  “FALCON  17”  will  inform  Owner’s  and  Petechim  ‐  Likpin immediately.      Petechim ‐ Likpin will request for weather update from the designated Meteorological Agency, a  copy of this request will be forwarded to the tug.      Additional weather update request must also include    ‐  Expected Weather conditions    ‐  Extra Weather outlook services.      Upon  receipt  of  these  new  updates,  the  Master  of  “FALCON  17”  will  decide  if  alteration  of  course / speed is required for the proposed voyage.    5.2.8  Contingency Plan for Typhoon      The tug “FALCON 17” will receive at least daily weather reports and forecast via several Radio  Weather  Stations  and  via  Navtex  messages  along  the  tow  route.  Whenever  the  area  is  being  affected  by  a  tropical  depression,  storm  or  typhoon,  metrological  support  will  be  received  by  Meteo Consultant, via Petechim ‐ Likpin and or Owners when deemed necessary.      Whenever  there  is  a  tropical  depression  activity  along  the  tow  route,  weather  reports  and  forecast will be monitored in every 6 hours and tropical depression track be plotted. Frequent  reading  of  barometer  should  be  made.  If  the  barometer  reading  should  fall  5mb/hPa  below  normal  or  if  the  wind  should  increase  to  force  6,  there  is  little  doubt  that  a  storm  is  in  the  vicinity.      If the tropical depression turns into a storm or typhoon, all systems such as but not limited to  EGC and Navtex are submitting cyclone safety messages. When the cyclone track is intending to  cross the tow route, Owners and Petechim ‐ Likpin will obtain from separate sources additional  / specific cyclone data, in order to advise or assist the Master as much as possible to determine  the actions to be taken.      When the typhoon approaches the tow route, the Tug Master should or will reduce speed and  or deviate when necessary.        Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 25 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

   

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

Typhoon occurs all year round in the south part of South China Sea with peak period normally  occurs during the months of October to December, however there can be also quite a number  of typhoons developed during the month of July to August. 

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 26 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

5.2  GENERAL PRECAUTIONS DURING NORMAL TOWING OPERATION    5.2.9  Possible of beaching due to bad weather conditions      In a case of tow line failure and or in severe weather conditions with the possibility of beaching,  in  order  to  prevent  loss  of  barge  and  cargo,  the  Master  of  “FALCON  17”  will  prepare  as  necessary and to select an area suitable to beach the tug, bearing in mind the safety of the tug  and crew on board. 

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 27 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

                                SECTION 6    TRANSPORTATION ANALYSIS       

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 28 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

6.1     

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

NARRATIVE  This  section  is  intended  to  present  the  design  criteria  and  procedure  regarding  the  transportation analysis of the barge and cargoes. The criteria and procedure contained herein  is  to  be  utilized  to  verify  stability  analysis,  dynamic  seaforce  calculation,  barge  global  force  check and bollard pull estimation, etc. 

  6.2  STABILITY ANALYSIS    6.2.2  General      A  cargo‐barge  integrated  system  shall  have  positive  stability  in  calm  water  equilibrium  position.    In  addition,  the  system  shall  have  sufficient  dynamic  stability  (righting  ability)  to  withstand the overturning effect of the force produced by a steady wind from any horizontal  direction.  In order to examine the stability of the system, the following criteria were applied.    6.2.3  Wind Condition      The stability of cargo‐barge integrated system was evaluated using the following design wind  conditions  which  are  specified  in  DNV  Rules  (Stability  And  Watertight  Integrity  ‐  January  2001).      Wind  force  shall  be  considered  from  any  direction  relative  to  the  unit  and  the  value  of  the  wind velocity shall be as follows      Intact Stability : V =  51.5 m/sec (100 knots)      The unit should have sufficient reserve stability in a damaged condition to withstand the wind  heeling  moment  based  on  a  wind  velocity  of  25.8  m/s  (50  knots)  superimposed  from  any  direction.      Damaged Stability : V = 25.8 m/sec (50 knots)    6.2.4  Wind Force Calculation      Based on the maximum design wind speed, the wind force acting on the cargo‐barge system  can be computed in terms of the following equation.      Fw  =  0.0623V2ChCsA (kg)      Where    Cs  =  the shape co‐efficient: The derrick shape factor (=1.3) shall be used for cargo  wind load calculation. The hull shape factor (=1.0) shall be used for the barge  wind load calculation  Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 29 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

          6.2.5 

Ch    V  A 

=    =  = 

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

the height co‐efficient varied upon the height of  the structure on which the wind force acts.  design wind speed (m/sec)  projected area of the exposed surface (m2) 

Stability Ratio 

 

 

In order to examine the dynamic stability of floating structure, American Bureau of Shipping  (ABS)  and  Det  Norske  Veritas  (DNV)  recommendations  criteria  were  considered  as  the  minimum requirement. 

 

     

a) 

Intact Stability 

 

A  wind‐heeling  curve  shall  be  calculated  using  the  method  presented  in  the  ABS  criteria. 

   

 

The dynamic stability at a certain angle of heel is equal to the area under the curve of  righting lever up to that angle, multiplied by the displacement. 

   

 

The area under the righting moment curve at or before either the second intercept or  the downflooding angle, which ever is less, shall not be less than 40% in excess of the  area under the wind‐heeling moment curve to the same limiting angle. 

 

          Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 30 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

       

b) 

Damage Stability 

 

The  design  damage  stability  condition  shall  be  based  on  the  worst  condition  where  one compartment in the barge is flooded.  The additional heeling moment induced by  the  effect  of  the  flooding  shall  be considered.    The  area  under  the  righting  moment  curve at or before either the second intercept or the down flooding angle, whichever  is  less,  shall  not  be  less  than  the  area  under  the  wind‐heeling  moment  curve  to  the  same limiting angle. 

   

Stability Analysis will be provided in the separate Transportation Study Report. 

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 31 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

 

6.3 

STOWAGE ARRANGEMENT   

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 32 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL

Bow

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

Anodes

137.71 Tonne

Elevation Section

Plan

Starboard

380.07 Tonne 471.68Tonne 380.07 Tonne

4

3

Port

2

Anodes

1

Bow

CLIENT PROJECT TITLE PROJECT CODE

5 Stern

Stern

78.69 Tonne

 

  Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 33 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

  6.4                         

TOWING AND BALLAST CONDITION  The stability analysis is carried out using simulation program “MOSES”.  The study is based on a mean draft of 2.17 metres and a trim of 0.55 metres by stern.         

Draft Forward   Draft Aft    Trim by Stern    Mean Draft   

=  =  =  = 

1.90   m  2.45   m  0.55   m  2.17   m 

To achieve this tow condition, water ballast for this barge is required. 

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 34 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

Document Document Number

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 35 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

  DESIGN WEIGHT DATA 

6.5     

Design weight data will be provided in the separate Transportation Study Report. 

   

 

 

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 36 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

6.6     

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

INTACT & DAMAGE STABILITY ASSESSMENT  Barge  intact  and  damage  stability  during  tow  are  based  on  IMO,  ABS  and  DNV  recommendations.  The  stability  curves  are  derived  from  statistical  stability  cases  with  the  effects of wind heeling moment imposed on them. 

  6.6.1  INTACT STABILITY ASSESSMENT       The towing condition meets the International Maritime Organization (IMO), American Bureau  of Shipping (ABS) and Det Norske Veritas (DNV) recommendations on the intact stability with  respect to the service condition. The stability standards which are stipulated as minimal are  as follows:      1)  The area under righting lever curve up to the angle of maximum righting lever, or the  angle of down flooding, or 40 degrees, whichever is less, should not be less than 0.08  m‐rad. (4.58 m‐deg). (ABS Barge Deck Cargo / Intact Stability Guidelines for Pontoons  1992)      2)  The  critical  metacentric  height  should  not  be  less  than  0.15  metre  (0.49  feet).  (IMO  Code on Intact Stability For All Type Of Ships Resolution A‐749)      3)  The righting lever should be at least 0.20 metre (0.66 feet) at an angle of heel equal to  or  greater  than  30  degree.  (IMO  Code  on  Intact  Stability  For  All  Type  Of  Ships  Resolution A‐749)      4)  The area under the righting arm should not be less than 3.15 deg‐m (10.34 deg‐ft) up  to  an  angle  of  heel  30  degree.  (IMO  Code  on  Intact  Stability  For  All  Type  Of  Ships  Resolution A‐749)      5)  The area under the righting arm should not be less than 5.15 deg‐m (16.92 deg‐ft) up  to an angle of heel of 40 degree or the down flooding angle, whichever is less. (IMO  Code on Intact Stability For All Type Of Ships Resolution A‐749)      6)  The area under the righting arm curve between the angles of heel of 30 degree and 40  degree, or the down flooding angle, should not be less than 1.72 deg‐m (5.64 deg‐ft).  (IMO Code on Intact Stability For All Type Of Ships Resolution A‐749)      7)  The range of transverse statical stability should normally exceed 40 degree (DNV Rules  for Planning and Execution of Marine Operations)      8)  The  area  under  the  righting  lever  curve  at  or  before  the  second  intercept  or  down  flooding angle, or 40 degrees, whichever is less, is not to be less than 40% in excess of  the area under the wind heeling arm curve to the same limiting angle. (DNV Rules for  Planning and Execution of Marine Operations, IMO)  Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 37 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

6.6  INTACT & DAMAGE STABILITY ASSESSMENT    6.6.2  DAMAGE STABILITY ASSESSMENT      As  calculated,  the  towing  condition  meets  the  IMO  and  DNV  recommendations  on  the  damage  stability  in  respect  of  the  service  condition.  The  stability  standards,  which  are  stipulated as minimal, are as follows:      1)  In  the  case  of  unsymmetrical  flooding,  the  total  heel  shall  not  exceed  7  degrees,  except  that,  in  special  cases,  the  Administration  may  allow  additional  heel  due  to  unsymmetrical  moment,  but  in  no  case  shall  the  final  heel  exceed  15  degrees.  (Stability of Passenger Ships in Damaged Condition, IMO Consolidated Edition 1992)      2)  In no case shall the margin line or down flooding point be submerged in the final stage  of flooding. (DNV Rules for Planning and Execution of Marine Operations, IMO)      3)  The  area  under  the  righting  lever  curve  at  or  before  the  second  intercept  or  down  flooding angle, or 40 degrees, whichever is less, is not to be less than the area under  the  wind  heeling  arm  curve  to  the same  limiting  angle.  (DNV  Rules  for  Planning  and  Execution of Marine Operations)    Intact  &  Damage  Stability  Assessment  will  be  provided  in  a  separate  Transportation  Study  Report.    6.7  SEAFASTENING DESIGN      The sea fastening design for the linepipes has been carried out based on maximum induced  force derived from barge standard motion criteria.      1)  Due  to  the  sequence  of  different  supports  being  put  in  place,  the  following  loading  conditions are considered in the analysis.      2)  The cargoes dynamic loadings due to the barge motion and wind are assumed to be  supported by supporting grillage and seafastening tiedown braces together.      A full transportation Analysis will be in a separate report (6‐001V/1043‐01/RPT/DWG)   

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 38 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

                              SECTION 7    ANNEXES                                               

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 39 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

ANNEXE 1 ‐ TOWING ARRANGEMENT (GENERIC)   

              Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 40 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

ANNEXE 1 ‐ TOWING ARRANGEMENT (ACTUAL)    The towing arrangement onboard the “SYNERGY FALCON” is as follows:    1)  Main Towing Arrangement:    ‐ Oval pin (82mm x 125mm) Smit brackets are fitted at forward, estimated MBL 280 MT  (Sin Seng Huat (Foshan) Marine Rigging Ltd, Certificate No. 80827‐4 dated 27/08/2008).    ‐   Two 2.5 metres length x 38mm diameter chafing chain, estimated MBL 83 MT.    ‐  Two 30 metres length, 38mm diameter, certified breaking load 909.9kN (Universal Wire  Rope Company Limited, U.S. A, Certificate dated 07/2008).    ‐  Tow  rope  200  metres  length  x  80mm  diameter,  PP  Superdan  8  Strand  Rope  with  6FT  Canvas  covered  eye  splicing  at  both  ends,  certified  breaking  load  95  tonnes,  Lloyd’s  Register certificate No. BUS080825/51 dated 24/01/2008.    ‐  Minimum sized shackles 25MT S.W.L    ‐  Pick‐up  line  90  metres  length  x  32mm  rope  connected  to  the  main  towing  bridle,  and  lead back to the barge ready for picking up.    2)  Emergency Towing Arrangement:    ‐ Oval  pin  (82mm  x  125mm)  Smit  bracket  is  fitted  at  forward  centeline,  estimated  MBL  280  MT  (Sin  Seng  Huat  (Foshan)  Marine  Rigging  Ltd,  Certificate  No.  80827‐4  dated  27/08/2008).    ‐  One 2.5 metres length x 38mm diameter chafing chain, estimated MBL 83 MT.    ‐  One 30 metres length, 38mm diameter, certified breaking load 909.9kN (Universal Wire  Rope Company Limited, U.S. A, Certificate dated 07/2008).    ‐  Emergency tow rope on board the “FALCON 17” 200 metres length x 80mm diameter PP  Superdan  8  Strand  Rope  with  6FT  Canvas  covered  eye  splicing  at  both  ends,  certified  breaking  load  95  tonnes,  Lloyd’s  Register  certificate  No.  BUS080825/51  dated  24/01/2008.    ‐  Messenger line 100 metres length x 24mm diameter rope connect to small pick‐up line  to  a  floating  buoy  all  soft  lashed  on  barge’s  deck  with  buoy  confirmed  afloat  before  departure.      Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 41 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

ANNEXE 2 ‐ BOLLARD PULL CALCULATION 

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 42 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

  Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 43 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

  Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 44 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

  Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 45 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

  ANNEXE 3 ‐ CERTIFICATES OF TOWING EQUIPMENT                                                                                      Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 46 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

 

Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 47 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

  Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 48 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

 

 

      Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 49 of 50

Issue Date

16-Jun-09

CONSTRUCTION MANUAL CLIENT PROJECT TITLE PROJECT CODE

VIETSOVPETRO Nam Rong – Doi Moi Pipeline Project Construction & Installation of Offshore Pipelines PTC-LIL/P01/VSP0177/09

 

 

  Document Document Number

TOWING MANUAL PIPEHAUL BARGE NO. 1 “SYNERGY FALCON” PTC-LIL-P01-00-CT-MN-027

Revision

0

Sheet No.

Page 50 of 50

Issue Date