3538-200 Qasr Project Pre-commissioning Procedure for Qasr Rev 1
November 18, 2016 | Author: HashemAliHashem | Category: N/A
Short Description
jkj...
Description
PAGE 1 OF
146
PROJECT NO. 3538-200
3538-200-10-RT-045
KHALDA PETROLUM COMPANY PRE-COMMISSIONING PROCEDURE FOR QASR COMPRESSION PROJECT WESTERN DESERT – EGYPT
(31/80)
1 0 REV
21/05/2 014 13/04/2014 DATE
10 00 0 4000-PMT-1EG-000-Z-
FINAL ISSUE
A.S
H.M
W.E
ISSUED FOR APPROVAL REVISIONS
SM BY
RK CH'D
RK APPR
PAGE 272 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT
TABLE OF CONTENTS 1.0 INTRODUCTION…………………………….........................................................................4 2.0 DEFINITIONS………………………….............................................................................5 3.0 PRE-COMMISSIONING ORGANIZATION.....................................................................7 4.0 ACTIVITIES BOARDER………………….........................................................................8 5.0 SYSTEMIZATION…………………...................................................................................9 5.1 GENERAL…………………………………………………………………………. . .9 5.2 NUMBERING SYSTEM............................................................................................9 5.3 PRE-COMMISSIONING SYSTEMS……………………………………………….10 6.0 SYSTEMSPERIORITIES……..………………………………………………………….14 7.0 PRE-COMMISSIONING PROCEDURES.........................................................................16 7.1 GENERAL PROCEDURE……………………………….........................................16 7.2 SYSTEM PROCEDURE…………………………...................................................17 7.3 MAIN PRE-COMMISSIONING ACTIVITIES........................................................18 7.4 MAIN PRE-COMMISSIONING CHECKS..............................................................18 7.5 SEQUENTIAL COMPLETION FLOW CHART......................................................47
8.0 CONFORMITY CHECK OF THE PLANT'S EQUIPMENT.............................................49
10000-Z-000-GE1-TMP-0004
(08/13)
9.0 SYSTEM DOCUMENTS………………….......................................................................49 10.0 PROGRESS MONITORING……………........................................................................50 11.0 PUNCH LISTING………………....................................................................................50 12.0 STEPS TO ACHIEVE MECHANICAL COMPLETION AND MECHANICAL COMPLETION CERTIFICATE (MCC)………….................................................................51 13.0 HSE PROCEDURE………………..................................................................................53
EGYPT
PAGE 372 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT
14.0 SYSTEMS COMPONENT LIST………..........................................................................54 15.0 ATTACHMENTS……………………...........................................................................140
10000-Z-000-GE1-TMP-0004
(08/13)
1
ATTACHMENT 1
MARKED UP P&ID’s
ATTACHMENT 2
PRE-COMMISSIONING CHECK FORMS
ATTACHMENT 3
PUNCH LIST FORM
ATTACHMENT 4
MECHANICAL COMPLETION CERTIFICATE
ATTACHMENT 5
CALIBRATION CERTIFICATE
ATTACHMENT 6
LOOP CHECK SHEET
ATTACHMENT 7
TUBING TEST CERTIFICATE
EGYPT
PAGE 472 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
1.0 INTRODUCTION This Pre-commissioning Procedure has been prepared by ENPPI for KPC, KHALDA PETROLEUM COMPANY. All involved parties shall adhere strictly to these procedures during the pre-commissioning phase of the plant. The purpose of this document is to describe the specific requirements, principles & responsibilities for the preparation, execution, verification, and documentation of pre-commissioning activities, leading to mechanical completion of the UTILITIES AND OFFSITES PROJECT. The Completion Process will start with activities related to definition and preparation of systems and will then be followed in the later stages by activities related to verification and execution. The overall scope of pre-commissioning / System acceptance testing is to verify, test and document that the equipment and systems are designed and built to fulfill its purpose according to the specified requirements and safe to operate before turnover to operation team. With the purpose of facilitating the pre-commissioning activities and surrenders, the plant has been divided into mechanical completion systems; these systems will be included in specific packages. In this respect, all the possible constituents of the plant will be categorized under certain and specific system.
10000-Z-000-GE1-TMP-0004
(08/13)
The adequate pre-commissioning tests will be performed on every item of the plant and conveniently reported through the use of pre-commissioning forms on completion of these tests.
PAGE 572 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT
2.0 DEFINITIONS
Pre-commissioning Manager
Assigned person who will Manage the precommissioning activities With all involved parties until "Ready for Commissioning" (RFC)
Pre-commissioning coordinator
A pre-commissioning engineer from ENPPI, who will be responsible for all plant systems dossiers preparation and will coordinate punch listing activity A committee chaired by ENPPI and Operation representatives and for checking and testing the Plant systems. Construction contractor for Instrumentation, electrical, mechanical , civil works…..ETC
Commissioning Integrated Team (CIT) 1
Contractor (PETROJET) Supplier Representative
Any party who supply equipment, packages, material, main items, minor items and/or services.
Partial Mechanical Completion
The Partial Mechanical Completion is achieved when a separable portion of a plant/facility is available for commissioning as defined by its portion of the approved scope.
Final Mechanical Completion
10000-Z-000-GE1-TMP-0004
(08/13)
Discipline
Pre-Commissioning
1
Punch List
The Plant is Mechanically Completed when the facility/system/subsystem defined in the approved scope, construction documentation, drawing and specification has been installed, Tested and ready for commissioning. Part of the System indicating the specialization (Civil works, Piping, Static Equipment, Electrical, Instrumentation, Rotating Machinery, Safety). Pre-Commissioning activities are the non-operating adjustments and cold alignment checks. Pre-Commissioning activities shall be managed, supervised and performed by Commissioning Integrated Team (CIT). A master list of deficiencies/outstanding works identified during final walkthrough/inspection and check-out prepared by client and/or the integrated team comprising items which must be finalized by the contractor prior to issue of the mechanical completion certificate as well as these items should be classified as (A, B & C items) according to EPC scope of work.
EGYPT
PAGE 672 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
PRE-COMMISSIONING PROCEDURE
Ready For Commissioning
System
Hydrostatic Test
10000-Z-000-GE1-TMP-0004
(08/13)
Service Test
KPC
QASR COMPRESSION PROJECT
WESTERN DESERT
The plant or part thereof is Ready for Commissioning, when the plant or any part thereof has been erected in accordance with drawing, specifications, instruction, applicable codes, regulations and when the precommissioning activities detailed in the contract between KPC and ENPPI have been completed and duly certified by the integrated team and clear or closed the relevant punch list according to agreed methodology. “Issuance mechanical completion certificate for a system means that this system is ready for commissioning” Means a part of the plant designated from the applicable P&ID diagrams for separately performing pre-commissioning. Each System was divided into disciplines indicating the specialization (Civil works, Piping, Static Equipment, Electrical, Instrumentation, Rotating Machinery, Safety). A pressure test conducted using water or other approved liquid as the test medium. A pressure test performed to prove the integrity of pipelines or plant piping using the service fluid at the maximum attainable operating pressure.
EGYPT
1
146145
Construction Assistance Team ENPPI CONSTRUCTION MANAGER
3538-200-10-RT045 MAY 21, 2014 REV.1
PAGE 772 OF
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
3.0 PRE-COMMISSIONING ORGANIZATION
1
10000-Z-000-GE1-TMP-0004
(08/13)
KPC PLANT MANAGER
KPC OPERATION TEAM
QA/QC ENGINEER
KPC WESTERN DESERT EGYPT
PAGE 872 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
10000-Z-000-GE1-TMP-0004
(08/13)
4.0 ACTIVITIES BOARDER
KPC WESTERN DESERT EGYPT
PAGE 972 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT
WESTERN DESERT
PRE-COMMISSIONING PROCEDURE
EGYPT
5.0 SYSTEMIZATION 5.1 General To enable a staged completion of the project, the entire facilities shall be divided into operational sections based on a unit or area basis, the elected numbering system intends to cover the control and documentation needs in the most appropriate and beneficial way. The objective of a staged completion is to enable each unit or area to be completed, commissioned, and started up in a sequential order so that the start-up schedule and production targets can be met. The plant is divided into systems as per the list explained hereinafter. Each system will be clearly defined and marked up on the relevant drawings. Each system will be divided into disciplines indicating the specialization (civil works, piping, static equipment, electrical, instrumentation, rotating machinery, safety). Each system shall be checked by disciplines and tested as per the relevant pre-commissioning procedure described hereinafter by construction contractor and commissioning integrated team. After all discipline had been finished all checks / tests and signing the check forms, then clearing the punch list category "A", the system is considered mechanically completed and ready for commissioning The tracing file showing the status of each system is also attached for reference and will be followed up by the pre-commissioning Manager 5.2 Numbering System
10000-Z-000-GE1-TMP-0004
(08/13)
Plant systems tagging is represented by tagging criteria as shown below in the following example X
-
300
PRE-COMM.
SYSTEM
SYSTEM
AREA
-
(U) (P) Process (U) Utility (TI) Tie-In
-
01 PRE-COMM SYSTEM
NUMBER For P&ID’s conformity check, discipline to check last issue of P&ID’s against the precommissioning P&ID’s.
PAGE 1072 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT
5.3 PRE-COMMISSIONING SYSTEMS 5.3.1
TIE-IN SYSTEMS
SYSTEM NO. X.80.TI.001 X.80. TI.002 X.80. TI.003 X.80. TI.004 X.80. TI.005 X.80. TI.006 X.80. TI.007 X.80. TI.008 X.80. TI.009 X.80. TI.010 X.80. TI.011 X.80. TI.012 X.80. TI.013 X.80. TI.014 X.80. TI.015 X.80. TI.016 X.80. TI.017 X.80. TI.018 X.80. TI.019 X.80. TI.020
10000-Z-000-GE1-TMP-0004
(08/13)
5.3.2
DESCRIPTION EXISTING PRODUCTION SEPARATOR TIE IN SYSTEM QA-V-3002A EXISTING PRODUCTION SEPARATOR TIE IN SYSTEM QA-V-3002B EXISTING PRODUCTION SEPARATOR TIE IN SYSTEM QA-V-3002C EXISTING PRODUCTION SEPARATOR TIE IN SYSTEM QA-V-4002A EXISTING PRODUCTION SEPARATOR TIE IN SYSTEM QA-V-4002B PHASE I GAS MANIFOLD TIE IN PHASE II GAS MANIFOLD TIE IN BYPASS BLOW DOWN LINES TIE IN SYSTEM PHASE I HP FLARE KO DRUM QA-V-3002 TIE IN SYATEM PHASE I COLD VENT TIE IN SYSTEM PHASE II COLD VENT TIE IN SYSTEM METHANOL AND DISTREBUTION TIE IN SYSTEM PHASE I INSTRUMENT AIR SYSTEM PHASE II BLACK START FUEL GAS TIE IN SYSTEM PHASE I BLACK START FUEL GAS TIE IN SYSTEM PHASE II HP FLARE KO DRUM QA-V-4004 TIE IN SYSTEM NEW MPU TIE IN SYSTEM NEW DIESEL TRANSFER PUMP QA-P-8020 TIE IN TO THE EXISTING 11 KV SWG QA-L-8004 PMS TIE IN RELATED TO EXISTING 11 KV SWG QA-L-8001
PROCESS SYSTEMS
SYSTEM NO. X.80.P.001 X.80.P.002 X.80.P.003 X.80.P.004 X.80.P.005 X.80.P.006 X.80.P.007 X.80.P.008
DESCRIPTION COMPRESSOR INLET MANIFOLD COMPRESSOR SUCTION DRUM TRAIN-A (QA-V-8001A) SYSTEM COMPRESSOR TRAIN-A (QA-K-8001A) SYSTEM COMPRESSOR DISCHARE COOLER TRAIN-A (QA-E-8001A) SYSTEM COMPRESSOR DISCHARE DRUM TRAIN-A (QA-V-8002A) SYSTEM COMPRESSOR DISCHARGE MANIFOLD SYSTEM COMPRESSOR SUCTION DRUM TRAIN-B (QA-V-8001B) SYSTEM COMPRESSOR TRAIN-B (QA-K-8001B) SYSTEM
EGYPT
PAGE 1172 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
X.80.P.009 X.80.P.010 X.80.P.011 X.80.P.012 X.80.P.013 X.80.P.014 X.80.P.015 X.80.P.016 X.80.P.017 X.80.P.018 X.80.P.019 X.80.P.020 X.80.P.021 X.80.P.022
10000-Z-000-GE1-TMP-0004
(08/13)
5.3.3
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
COMPRESSOR DISCHARE COOLER TRAIN-B (QA-E-8001B) SYSTEM COMPRESSOR DISCHARE DRUM TRAIN-B (QA-V-8002B) SYSTEM COMPRESSOR SUCTION DRUM TRAIN-C (QA-V-8001C) SYSTEM COMPRESSOR TRAIN-C (QA-K-8001C) SYSTEM COMPRESSOR DISCHARE COOLER TRAIN-C (QA-E-8001C) SYSTEM COMPRESSOR DISCHARE DRUM TRAIN-C (QA-V-8002C) SYSTEM COMPRESSOR SUCTION DRUM TRAIN-D (QA-V-8001D) SYSTEM COMPRESSOR TRAIN-D (QA-K-8001D) SYSTEM COMPRESSOR DISCHARE COOLER TRAIN-D (QA-E-8001D) SYSTEM COMPRESSOR DISCHARE DRUM TRAIN-D (QA-V-8002D) SYSTEM CONDENSATE SUCTION MANIFOLD CONDENSATE SUCTION DRUMS QA-V-8005A SYSTEM AND PROCESS GAS BALAN CONDENSATE SUCTION DRUMS QA-V-8005 B SYSTEM CONDENSATE EXPOET PUMPS QA-P-8003 A/B/C SYSTEM
UTILITY SYSTEMS
X.80.U.001 X.80.U. 002 X.80.U. 003 X.80.U. 004
AIR GENERATION PACKAGE AQA-K-8002A SYSTEM AIR GENERATION PACKAGE AQA-K-8002B SYSTEM AIR GENERATION PACKAGE AQA-K-8002C SYSTEM AIR DRYER PACKAGE QA-A-8005A SYSTEM
X.80.U.005
AIR DRYER PACKAGE QA-A-8005B SYSTEM
X.80.U.006 X.80.U.007 X.80.U.008 X.80.U.009 X.80.U.010 X.80.U.011 X.80.U.012 X.80.U.013 X.80.U.014 X.80.U.015 X.80.U.016 X.80.U.017 X.80.U.018
UTILITY AIR RECEIVER QA-V-8009 SYSTEM INSTRUMENT AIR RECEIVER QA-V-8010 SYSTEM UTILITY STATION PLANT AIR DISTRIBUTION SYSTEM INSTRUMENT AIR DISTRIBUTION SYSTEM NITROGEN GENERATION PACKAGE QA-A-8003 SYSTEM NITROGEN DISTRIBUTION SYSTEM UTILITY STATION PLANT NITROGEN DISTRIBUTION SYSTEM NITROGEN RECIVER, COMPRESSOR AND LETDOWN PACKAGE HP FUEL FLASH GAS PRE-HEATER FEED H.P. FUEL GAS SYSTEM H.P FUEL GAS PRE-HEATER SYSTEM H.P FUEL GAS SUPER HEATER AND CONSUMERS H.P FUEL GAS FILTERS
PAGE 1272 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
X.80.U.019 X.80.U.020 X.80.U.021 X.80.U.022 X.80.U.023 X.80.U.024 X.80.U.025 X.80.U.026 X.80.U.027 X.80.U.028 X.80.U.029 X.80.U.030 X.80.U.031 X.80.U.032 X.80.U.033 X.80.U.034 X.80.U.035 X.80.U.036 X.80.U.037 X.80.U.038 X-80-U-039 X-80-U-040 X-80-U-041 X-80-U-042
10000-Z-000-GE1-TMP-0004
(08/13)
5.3.4
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
L.P FUEL GAS BACK-UP HEATER L.P FUEL GAS SCRUBBER H.P FLARE COLLECTION AND L.P SOURCE TO COLD VENT CLOSED DRAIN COLLECTION CLOSED DRAIN DRUM CLOSED DRAIN DRUM PUMPS CLOSED DRAIN TRANSFER PUMPS NEW EMERGYNCY DEISEL GENERATOR POTABLE WATER SYSTEM DISTRIBUTION SYSTEM POTABLE WATER SODIUM HYPOCHLORITE INJECTION PACKAGE SANITARY SEWAGE LIFTING PUMP AND COLLECTION SUMP SANITARY SEWAGE TREATMENT PACKAGE TREATED SANITARY WATER FIREWATER SODIUM HYPOCHLORITE INJECTION PACKAGE FIREWATER STORAGE TANK FIREWATER JOCKRY PUMPS FIREWATER DEISEL TANKS AND PUMPS FIREWATER NETWORK & EQUIPMENT PHASE I CLOSED DRAIN DRUM PUMP PHASE II CLOSED DRAIN DRUM PUMP HVAC System GASEOUS EXTINGUISHING SYSTEM SAFETY EQUIPMENT SYSTEM CATHODIC PROTECTION SYSTEM
ELECTERICAL SYSTEMS DESCRIPTION
SYSTEM NO.
Power Transformer
X-80-U-043
L.V SWG & Motor Control Center
X-80-U-044
Neutral Grounding Resistor
X-80-U-045
PAGE 1372 OF 146145
3538-200-10-RT045 MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
10000-Z-000-GE1-TMP-0004
5.3.5
KPC WESTERN DESERT EGYPT
Small Power Distribution Panel
X-80-U-046
LTG And Small Power System
X-80-U-047
Raceways And Supports
X-80-U-048
Grounding
X-80-U-049
Battery And Battery Charger Assemblies
X-80-U-050
Uninterruptible Power Supply ( UPS) System
X-80-U-051
Lightening System
X-80-U-052
Existing MV Switchgear and Motor Control Gear
X-80-U-053
LV Bus Bar Trunking
X-80-U-054
MV Bus Bar Trunking
X-80-U-055
Power factor Equipment
X-80-U-056
Variable speed drive
X-80-U-057
Supervisory Digital Control System (SDCS)
X-80-U-058
11 kV Switchgear
X-80-U-059
DESCRIPTION
SYSTEM NO.
ESD SYSTEM and Main Cables
X-80-U-060
(08/13)
REV.1
QASR COMPRESSION PROJECT
INSTRUMENTATION SYSTEMS
PAGE 1472 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
5.3.6
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
DCS SYSTEM and Main Cables (PCS instead of DCS)
X-80-U-061
Vibration Monitoring System (VMS)
X-80-U-062
F&G SYSTEM and Main Cables
X-80-U-063
DESCRIPTION
SYSTEM NO.
PAGE / PARTY SYSTEM
X-80-U-064
PRIVET AUTOMATIC BRANCH EXCHANGE SYSTEM (PABX)
X-80-U-065
TELECOMMUNICATION SYSTEMS
NOTES: 1. The boundary between utility systems and distribution systems (i.e. utility air, drain …etc) is limited to the last block valve on the system P&ID.
10000-Z-000-GE1-TMP-0004
(08/13)
2. Suppliers pre-commissioning check lists which in their operating manuals to be used in conjunction with ENPPI pre-commissioning check lists.
PAGE 1572 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
6.0 SYSTEMS PRIORITIES The systems shall be prioritize in the following consequences in order to facilitate smooth precommissioning and allow overlapping with commissioning activities in the plant and minimize the time required for performing the activities, generally priorities as follow: 1) Electrical Systems Priorities: 1. Grounding. 2. Lightening system. 3. HVAC system. 4. LV BUS bar trunking. 5. LV SWG & motor control center. 6. MV BUS bar trunking. 7. 11 KV switchgear. 8. Existing MV switchgear and motor control gear. 9. LTG and small power system. 10. Battery and battery charger assemblies. 11. Small power distribution panel. 12. Neutral grounding resistor. 13. Power transformer. 14. Uninterruptible power supply (UPS) system. 15. Variable speed drive. 16. Supervisory digital control system (SDCS). 17. Cathodic protection system.
10000-Z-000-GE1-TMP-0004
(08/13)
2) Instrumentation Systems Priorities: 1. ESD system and main cables. 2. DCS system and main cables (PCS instead of DCS). 3. Vibration monitoring system (VMS). 3) Utilities and Tie-Ins Systems Priorities: 1. New Instrument & utility air system 2. Existing instrument air system tie-in. 3. New Diesel system. 4. existing diesel system tie-in. 5. Fire Water System 6. F&G System 7. New HP/LP fuel gas system 8. Existing fuel gas system tie-in. 9. New HP flare and LP cold vent collection. 10. Existing HP flare and clod vent system tie-ins
PAGE 1672 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
11. Nitrogen generation and distribution system. 12. Closed drain system. 13. Existing methanol system tie-in. 14. Potable water and distribution system. 15. Sanitary sewage system. 16. Phase I&II closed drain drum pump system.
10000-Z-000-GE1-TMP-0004
(08/13)
4) Process and Tie-Ins Systems Priorities: 1. Existing production separators (Phase I/II) tie-ins 2. Phase I/II Gas manifold Tie-Ins. 3. Process gas compressor trains’ systems 4. Existing Phase I/II condensate manifold Tie-Ins. 5. New condensate systems
KPC WESTERN DESERT EGYPT
PAGE 1772 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
7.0 PRE-COMMISSIONING PROCEDURES 7.1 General Procedure The pre-commissioning task will be performed in accordance with the following steps:
1
7.1.1 Construction contractor shall notify ENPPI site Coordinator and the disciplines representatives when the system is ready for the pre-commissioning activities (Construction Completion). Commissioning Integrated Team (CIT) which is a team of multi disciplines from ENPPI and KPC operation /projects team shall perform an inspection addressed to the relevant System and the Pre-commissioning activities of the specific Discipline could be started, punch items to be issued and classified A, B or C. 7.1.2
The Pre-commissioning activities will be performed by Construction contractor/ Vendor representative and punch list is cleared by Commissioning Integrated Team (CIT).
7.1.3
During the pre-commissioning phase, checks and tests items specified in this section shall be carried out as per the attached Pre-commissioning check forms and Commissioning Integrated Team will prepare the punch list, if applicable.
7.1.4
Upon signing all pre-commissioning check forms and clearing all punch list items category "A" then “ System Mechanical Completion Certificate “ shall be issued
7.1.5
Plant “Mechanical Completion Certificate “shall be issued when all systems in the plant shall have the system Mechanical Completion Certificate.
7.2 System Procedure
10000-Z-000-GE1-TMP-0004
(08/13)
The pre-commissioning work shall be carried out for the Equipment, Packages, Piping, Instruments, Fire Detection, Electrical, etc.
1
Civil work, Steel Structure and Buildings, Will not have pre-commissioning activities and will be mechanically completed upon clearance of punch list items - created after construction contractor confirm system completion - without category A items. To have system mechanical completion the following should be considered: - Signing all related check forms. - Clearing all punch items category "A". - Complete all documents related to system file.
PAGE 1872 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT
7.3 Main Pre-Commissioning Activities The General pre-commissioning activities of the system are mentioned below. Witness Water Flushing Witness Air Blowing Lube Oil Flushing P&ID's conformity checks Punch list clearing Instruments Bench Calibration Instruments installation verification Safety valves Bench Calibration Instrument cables meggering and continuity checks Electrical cables meggering and continuity checks 1
Electrical appliances meggering (ACC motors, compressor motors, generator
motors, etc,). Instrument control loops checking Electrical systems Energization (S/S, battery charger, UPS, Emergency power
supply...etc.)
10000-Z-000-GE1-TMP-0004
(08/13)
Telecommunication cables meggering and continuity checks Fiber optics cable check Static equipment External/internal inspection & boxing up Pre/Cold-alignment for rotating equipment
EGYPT
PAGE 1972 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT
7.4 Main Pre-Commissioning Checks 7.4.1
Vessels
Verify and check the following: Conformity with project documentation. Pressure, temperature, rating. Nozzles, sizes and orientation. Internals: types, dimensions, metallurgy and installation. Instrument nozzles and types. Ladders, platforms, walkways: Location, size and accessibility. Nameplate information/data. Grounding connections. Vents, drains, relief valves provided as specified. Nozzles elevation and standout Insulation (thermal/PP) Fireproofing Anchor bolt verification
10000-Z-000-GE1-TMP-0004
(08/13)
1
Manhole bolt verification (torque or tensioning) (after internals verification). Piping connections (are all nozzles connected to the correct pipeline) Levelness of the vessels Removal of preservation/transportation materials For instrumentation nozzles, the installed instrument are correct and installed properly (orientation, tightened bolts etc).
EGYPT
PAGE 2072 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
7.4.2
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT
Piping
Verify and check the following: Conformity with P&ID’s.
3
Size. Pipe: flanges, gaskets, fittings, valves in conformity with specified piping classes High point vents and low point drains. Pipe supports and spring hangers. Flange bolting tightness: nuts and bolts are properly installed. Orifice plates in correct location and direction. Valve flow direction. Insulation kits
1
Temporary strainers (location, direction)
10000-Z-000-GE1-TMP-0004
(08/13)
Slope/levelness of the pipeline
EGYPT
PAGE 2172 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
7.4.3
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
VENDOR SKID INSTALLATION
Verify and check the following:
7.4.4
.Check against drawings, specs and data sheets
1
.Check name / data plate
2
.Check skid is undamaged
3
.Check shipped loose items
4
.Remove preservation material
5
.Foundations and holding down bolting check
6
.Check skid is leveled & dowelled (where applicable)
7
.Check skid drainage
8
.Check battery limit flanges are made up correctly & permanent gaskets fitted
9
.Check bonding / grounding
10
Check Nozzles location, size and rating, elevation et
11
Check Piping connections (are the nozzle connected)
12
Check Remove temporary materials (which were required for transport etc)
13
COMPRESSORS INSTALLATION
10000-Z-000-GE1-TMP-0004
(08/13)
Verify and check the following: Check against drawings, specs & data sheets
1
Check name / data plate
2
Skid / base leveling/ dowelling satisfactory.
3
Check vibration mountings
4
Remove preservation materials
5
Remove temporary blinds from suction & discharge nozzles (where applicable).
6
Install permanent gaskets & check stress free alignment
7
1
PAGE 2272 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
Install temporary strainers and bypasses (Where applicable).
8
Check PSV's installed and correctly tagged.
9
Check lube oil pumps piped up correctly (Where applicable).
10
Check lube oil cooler clean and free from obstruction
11
Check lube oil reservoir is clean & free of debris
12
Fill lube oil systems with flushing oil (per lubrication schedule) 13 Install temporary lube oil filters for flushing purposes
14
Check instrumentation installed. 15
7.4.5
GAS COMPRESSOR
10000-Z-000-GE1-TMP-0004
(08/13)
Verify and check the following:
Refer to supplier operating and maintenance manual which include all compressor documents and drawings.
1
Adjust leveling of the compressor skid with reference to thePAGE 2372 OF 2 concrete foundation. KPC 3538-200-10-RTQASR COMPRESSION PROJECT Check the alignment of coupling hubs on compressor and gear 045 box output shaft before and after the connection of process 3 MAY 21, 2014 WESTERN DESERT PRE-COMMISSIONING PROCEDURE piping (as per supplier recommendation).
10000-Z-000-GE1-TMP-0004
(08/13)
146145
REV.1 Precision leveling of the gas turbine and application of supplier instruction regarding anchor bolt assembly installation and grouting.
EGYPT
4
Align the parallelism of the coupling hub faces (as per supplier recommendation).
5
Check the direction of rotation of the motors for the compressor package auxiliary.
6
Perform the oil flushing and check the cleanliness of oil system (by-passing the bearing).
7
Charge the first fill of lubricating oil.
8
Check the set point of all alarm and shut down switches.
9
perform the sequence check of control system (suction discharge - anti surge valves)
1 0
Check the function of ESD push button on panel.
1 1
Check the function of low lube oil pressure switch.
1 2
Start grouting of compressor base plate using non-shrinkage epoxy grout. All concrete top surfaces must be covered with grout, even if not underneath skid.
1 3
Lube oil cooler is mounted on steel structure supplied loose to be assembled. A small vent pipe is connecting top of cooler to gas turbine reservoir (as deemed necessary by the gas turbine manufacturer). lube oil cooler fan motor assembly must be greased and free to rotate by hand
1 4
Ensure good alignment between motor and fan pulleys, unless fans are directly driven by motor.
1 5
Installation of seal air cooler with interconnecting piping and moisture drain pipe, if applicable.
1 6
Installation of combustion air filter, elements, flexible element, exhaust fans to expel sand laden air,… etc.
1 7
Installation of enclosure ventilation system.
1 8
Installation of firefighting system, CO2 cylinders cabinet, piping, inside enclosure gas detectors on compressor skid ... Etc. Interconnecting CO2 piping must be St.St. 304 or 316 as a minimum.
1 9
Installation of fuel gas filter/heater (conditioning) skid with interconnecting piping.
2 0 2
PAGE 2472 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
7.4.6 TURBINE DRIVERS Verify and check the following: Adjust leveling of the turbine skid with reference to the concrete foundation.
1
Check the alignment of coupling hubs on turbine and gear box output shaft before and after the connection of process piping (as per supplier recommendation).
2
Align the parallelism of the coupling hub faces (as per supplier recommendation).
3
Check the direction of rotation of the motors for the turbine package auxiliary.
4
Check the set point of all alarm and shut down switches
5
Perform the sequence check of control system (suction discharge - anti surge valves)
6
Check the function of ESD push button on panel.
7
Check the function of all protections of the turbine.
8
Verify vendor site documentation is complete and attached.
9
Check against drawings, specs and data sheets. 10
10000-Z-000-GE1-TMP-0004
(08/13)
Remove preservation materials (where applicable). 11 Check lube /seal oil reservoirs are clean & free from debris.
12
Fill reservoirs with flushing oil (Per vendors recommendations)
13
Install temporary flushing strainers where applicable.
14
Fill lube / seal oil systems with correct oil after flushing (per lubrication schedule)
15
Check lube / seal oil pumps correctly piped up. Check lube./ seal oil coolers free from obstruction
16 17
Check hydraulic oil pump piped up correctly (Where applicable).
18
Check hydraulic oil cooler clean & free from obstruction (If applicable).
19
Check seal oil pumps are piped up correctly (Where applicable).
20
PAGE 2572 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
Check seal oil cooler clean & free from obstruction (Where applicable)
21
Check emergency lube / seal oil pump piped up correctly (where applicable)
22
Check emergency lube oil cooler clean & free from obstruction (If applicable)
23
Check all local instruments correctly installed.
24
Check fuel lines & valves are piped up correctly.
25
Check starter gas lines & valves are piped up correctly (if applicable).
26
Check air intake filters installed correctly.
27
Check enclosure fans and vents free from obstruction.
28
check fire / gas detectors installed correctly
7.4.7
29
check turbine enclosure installed correctly
30
chemical cleaning of lube oil & F.G. piping completed
31
Operation and maintenance access satisfactory.
32
INSTRUMENT / UTLITY AIR COMPRESSOR SYSTEM
10000-Z-000-GE1-TMP-0004
(08/13)
Verify and check the following: Air compressor mechanically complete Air regulators and pressure switches checked and set for normal operation. Air dryer support screen properly installed and no holes larger than the desiccant and desiccant installed.
1 2 3
Air dryer cycle has been set, checked, and ready to operate.
4
Compressor solo motors run in – Data record and compare with design.
5
PAGE 2672 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT
10000-Z-000-GE1-TMP-0004
(08/13)
Interconnection signals between the package PLC and the ICS is properly connected
EGYPT
6
Check package items completeness against vendor items. Valves and instruments must be tagged. Check electric power connections to control panel and all motors.
7
Check mounting bolts tightening for compressor, electric motor, and other package items.
8
Remove any preservatives from interior to exterior surfaces of all items as per vendor instructions. Remove all temporary material used during shipment.
9
Check the direction of rotation of electric motor by pushing the start then in a second the stop switches. Make the same test for all auxiliary electric motor in the package. Make sure that all motors rotate freely by hand before switching them to start.
10
If this is feasible when the couplings can be disconnected. Make solo runs for four hours for all uncoupled electric motors and record line currents, vibrations, bearings temp.
11
Make complete functional testing of all instruments and control loops as per vendor instrument and control listing.
12
Check the presence of air filter element in good condition in inlet filter housing, lube oil filter element, air dryer pre-filter and after filter elements.
13
Observe proper tightening of all valves, piping, fittings, instruments and controls. Check operation of manual valves (stem greasing).
14
Blow compressor discharge air through the wet air receiver to the drain of vessel by-passing the automatic moisture separator, while outlet pipe to the dryer is isolated.
15
Isolate all sub-headers from the wet air manifold and instrument air manifold until the manifolds are blown to become super clean.
16
After cleaning all interconnecting piping to the dryer, introduce air to the dryer system, to the dry air receiver and blowing all air through its drain until ensuring its super cleanliness.
17
Start sequentially cleaning individual sub headers and branching using the same system described above for the wet air as well the dry air system.
18
Check dryer silica gel is in good operating condition as specified by manufacturer
19
Check dryer is working properly and interchanging between the two towers are working properly
20
PAGE 2772 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
Note: Wet air receiver is purged by compressor until it is proven very clean. Piping to dryer are purged prior to admitting wet air to dryers, followed by purging of dry air receiver through its drain connection prior to purging the instrument air header. Wet air header shall also be purged prior to individual purge of sub headers. The same shall be applied to dry air sub and then sub-sub headers down to all individual user tie-in connections. 7.4.8
DIESEL ENGINE
Verify and check the following: 1
.Vendor documentation attached
2
.Alignment checked for engine & generator (where applicable)
3
.Check engine mountings
4
.Check base plate bolts and dowels
5
.Check fuel piping installation
6
.Check lubrication system / filters
7
.Check fuel strainer. (Install temporary strainer if applicable)
8
Check engine cooling system
9
Check engine exhaust system
10
Check engine air intake dampers & filters
11
Check engine house ventilation (if applicable)
12
Check starting system installation
13
Check firefighting and fire alarm systems installed correctly
14
.Operation / maintenance access satisfactory
15
10000-Z-000-GE1-TMP-0004
(08/13)
.Check against drawings, specs and data sheets
7.4.9
Centrifugal Pumps
PAGE 2872 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT
Verify and check the following: Conformity with project specifications and design requirements. Type of pump Piping arrangement to permit removal or replacement of pump and driver. Piping independently supported and not tightly connected to the pump, i.e. Pump will not be pulled out of alignment when lines get hot. No vapor pockets in piping. Suction strainers easily removable for cleaning. Strainers fit well so no bypassing can occur. Discharge pressure gauge readable from discharge block valve. Suction/discharge valves easily accessible, operable, and near to pump. Accessibility of auxiliary piping and controls. NPSH requirements. Base plate grouting complete Power supply to pump motor is installed. Check that motor rotation is correct. Adequate means for venting and draining pump casing available.
10000-Z-000-GE1-TMP-0004
(08/13)
Pumps and drivers aligned correctly. Check valves of proper type and installed in correct direction. All open drains from pumps and associated piping and instrumentation routed to open drain systems. All piping connected tightly and that no induced piping strains exist on pump flanges. Cold alignment (hot if required) seals are installed First cold alignment without coupling installation. Suction and discharge pipes connected to pump nozzles with not tightened bolts. Solo motor run test for two or four hours (Check no load current, noise, bearing temperature, vibrations). Data report and compare with design. Instrumentation installed and calibrated
7.4.10 PUMPS (PROGRESSIVE CAVITY)
EGYPT
PAGE 2972 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
Verify and check the following: Check against drawings, specifications and data sheets
1
Check data plate
2
Check base plate is level & dowelled (where applicable)
3
.Check / remove all preservation materials
4
All relief valves installed
5
Check oil external coolers (where applicable)
6
Check suction & discharge valves installed correctly (where applicable)
7
.Check suction strainer (install temporary strainer if required)
8
.Check discharge non return valve installed correctly (where applicable)
9
Install lube oil filters (where applicable) 10 Charge system with lube oil (Per lubrication schedule) 11 .Stress free alignment check 12 .Check motor / pump alignment (where applicable) 13 Check venire control operation & set to zero (where applicable) 14 Check bypass / minimum flow valve return to tank (where applicable) 15 Check drain lines are unobstructed 16 .Check pulsation dampers installed (where applicable) 17
10000-Z-000-GE1-TMP-0004
(08/13)
Check instruments installed 18 Operation and maintenance access satisfactory 19
7.4.11 OVERHEAD CRANE Verify and check the following: 1
.Check all crane motions are moving easily
1
PAGE 3072 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
.Check crane is stopped effectively on its rail boundaries
2
Check crane and its steel structure are capable to handle maximum capacity by .adding weights equal to crane maximum capacity
3
meggering for electrical components
4
Check arrangement of the Packaged units and fans as per HVAC drawings.
1
Check mounting bolts and fixations of the Packaged units
2
Check the belt pulley alignment and belt proper tension of the Packaged units.
3
Check the motor direction of the Packaged units and fans.
4
Check the duct work as per HVAC drawings.
5
Check the insulation of duct work as per HVAC drawings.
6
Check the control devices of the Packaged units.
7
Check the control devices of the fans.
8
Check the MCC of HVAC equipment.
9
7.4.12 HVAC SYSTEM Verify and check the following:
Check the drainage piping as per HVAC drawings. 10
10000-Z-000-GE1-TMP-0004
(08/13)
7.4.13 PACKAGED UNITS Verify and check the following: .Verify correct installation of the packaged units
1
Motor has been greased and ensure correct direction of rotation, .belts check
2
.Check the filter and filter accessibility
3
.Ensure drain pipe and connections as per specifications
4
PAGE 3172 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
Filters check (bag and Pre-filters)
5
Check the space between packaged units as per manufacture .catalogue
6
.Check the evaporator coil and fins
7
Check the power and control cables as per manufacturing wiring .diagram
8
Check the duct insulation and cladding as per ENPPI .specifications
9
.Check the direction of the rotation of the fan 10 7.4.14 ACCUMULATORS & PULSATION DAMPERS INSTALLATION Verify and check the following: 1
.Check data plate
2
.Check accumulator is undamaged
3
.Remove preservation material
4
.Check vent line is fitted and routed to safe location
5
Check priming nozzle is clean and protective plug fitted
6
.Insulation complete (where applicable)
7
.Check maintenance access satisfactory
8
10000-Z-000-GE1-TMP-0004
(08/13)
.Check against drawings, specs and data sheets
7.4.15 ALIGNMENT Verify and check the following: Remove spacer and flexible coupling and check type
1
PAGE 3272 OF 146145
3538-200-10-RT045
KPC
QASR COMPRESSION PROJECT
MAY 21, 2014
WESTERN DESERT
PRE-COMMISSIONING PROCEDURE
REV.1
EGYPT
Check DBSE correct & record
2
Check & eliminate soft foot (max allowable 0.005mm)
3
Carry out alignment using the face and periphery method according to normal .engineering practice and specifications, record results
4
Complete nozzle stress free alignment
5
-: Check the alignment as the following
6
Face Reading A1
° 90
°0
° 270
° 180 HOLDING DOWN BOLTS AND PIPEWORK LOOSE Rim Reading B1 1 A1 B1 °0 ° 90 ° 180
°0
° 270
° 270
10000-Z-000-GE1-TMP-0004
(08/13)
° 90
NOTES: 1. Final cold alignment, coupling installation and tightening of suction and discharge flanges are ° 180 Commissioning activities. HOLDING PIPEWORK TIGHT 2. Hot alignment shall be performed during start-up phaseDOWN when BOLTS normalAND operating temperatures will 3 be achieved and if it will be required. B1
A1
°0 ° 90 180° 270°
PAGE 3372 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
7.4.16 Vent and Pressure Relief Verify and check the following: Purge gas system complete and functional. Relief valves are in place, correct and ready to operate. Functional check of ESD valves. Pressure Safety Valves (PSV) bench calibration (Pop test) and register. T.S.O. classified valves: tightness test. 7.4.17 Instrument and Utility Air Verify & check the following: 1 2
10000-Z-000-GE1-TMP-0004
(08/13)
3 4 5
Air compressor mechanically complete Air regulators and pressure switches checked and set for normal operation. Air dryer support screen properly installed and no holes larger than the desiccant and desiccant installed. Air dryer cycle has been set, checked, and ready to operate. Compressor solo motors run in – Data record and compare with design.
7.4.18 AIR COOLER Verify & check the following : Motor, fan belts, gear drives bearings and fans are properly installed, adjusted and lubricated
1
PAGE 3472 OF 146145
3538-200-10-RT045
KPC
QASR COMPRESSION PROJECT
MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
WESTERN DESERT
Tightening of blade bolts, blade tip clearance (not less than vendor/ recommendations ) Alignment of motor drive pulley, fan pulley and belt 1tension.
EGYPT
2 3
Fan bearings and motor bearings are greased.
4
Rotate fans by hand to make sure they are not obstructed.
5
Installation and operation of vibrating switches and/or transmitters. All shipping braces and/or bolting are removed and the bundles are free to move with temperature changes. All the tube fins are in proper position and clean
6
Set the fan pitch properly and check alignment/rotation of motor and shaft.
9
No louvers are used in both coolers. Measure electric motor current, Solo motor run in – Data record, and compare with design. Install belt guards.
10
7 8
11 12
7.4.19 Electrical Systems 7.4.19.1 General Before starting any Pre-commissioning activity within the plant all the electric systems must be checked out by an electrical specialist responsible for the installation. Sufficient tests shall be made on all installations and equipment to assure that proper operation can be expected when the facility is put in operation. A Commissioning responsible electrical engineer must also be present for the first start-up of all rotating equipment.
10000-Z-000-GE1-TMP-0004
(08/13)
NOTE: MCC, power and control cables belong to the System where the electric user is located. N.B: Precautions regarding the connection of power & control cable shall be considered during checking operation functions of switchgears. 7.4.19.2 CABLING SYSTEM (For More Details See Electrical Mechanical Completion and Pre-Commissioning Checks for LV Cable “EL-30A”). Using megger meter to make insulation test for all cables between each conductor to ground, all other conductors and sheath grounded. Continuity tests for cables and wires. Voltage withstanding test on sample of each size/drum cables.
PAGE 3572 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
Cable markers check according to engineering documents. Check and inspection of terminations according to engineering documents and Supplier recommendation. 2 7.4.19.3 GROUNDING (For more details see electrical mechanical completion and precommissioning checks for grounding “EL-33 A”) Check and inspect the grounding system connections. Check for continuity of the main ground system loop and continuity of the taps of equipment. Check grounding resistance. Check of ground connection to equipment tightness. Check of adequate mechanical protection of ground wire (if required). Continuity test for grounding mesh branches. Ground grid and ground loop wire sizes.
7.4.19.4 LIGHTING SYSTEM (For more details see electrical mechanical completion and pre-commissioning checks for lighting and small power system “EL-23 A”) Checking of all lighting system panels, cabling, trays, junction boxes, fittings, fixtures...etc. Testing of all lighting circuits.
10000-Z-000-GE1-TMP-0004
(08/13)
Testing functional operation of photocells. Normal lighting power shall be momentarily interrupted for checking of functional operation of emergency lights. 7.4.19.5 SWITCHGEAR & MCC CHECKS (For more details see electrical mechanical completion and pre-commissioning checks for LV switchgear and motor control center “EL-04 A”) Complete component and interconnection and cable terminations inspection according to manufacturer's final approved drawings. Inspection, testing and functional check shall be according to supplier instruction. Make all necessary adjustment to switch gear and motor control center equipment. Test and calibration of all switch gear relays (using primary and secondary injection as applicable), metering, lights, indicators,
PAGE 3672 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
space heater, and check proper coordination and setting. Check the phase sequence and polarity of all equipment Functional check of all motor starters, circuit breakers' incomers, outgoing feeders and bus ties. Perform operational tests on all motor control circuits, interlock system, indicating lights, meters and all other devices. Check circuit breakers, motor starters, relays and other equipment for loose connections (both mechanical and electrical). Verify that contacts and working parts are correctly aligned and free from dust and foreign matter. Inspect circuit breakers with adjustable trips, checking both thermal (if any) and magnetic settings for proper protection. Also check thermal overload relay settings according to vendor documents. Check and sequence test for alarms, interlocks, auto-transfer, ... etc. Functional checking of switchgear and MCC from remote locations such as Control Room. Energizing the substation for readiness of plant start-up. 7.4.19.6 ELECTRIC MOTORS ( For more details see electrical mechanical completion and pre- commissioning checks for motors “EL-22 A”) Insulation testing resistance to ground by 500 VDC meager. Check correct rotation.
10000-Z-000-GE1-TMP-0004
(08/13)
Solo motor Running test for two hours duration. Data record.
7.4.19.7 BATTERY CHARGER SYSTEM CHECKS (For more details see electrical mechanical completion and pre-commissioning checks BATTERY CHARGER SYSTEM “EL-08 A”) Check equipment earthing connections to the earthing system. Insulation test of both the main and aux. circuits, this shall be carried out between phases and phases to ground. Batteries are installed as Indicated in the design. Batteries rack to be connected to the earthing system.
PAGE 3772 OF 146145
3538-200-10-RT045 MAY 21, 2014
10000-Z-000-GE1-TMP-0004
(08/13)
REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
PAGE 3872 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
7.4.20 Instrumentation 7.4.20.1 Equipment Check Instrument equipment need to be inspected and the specification data sheets checked against the nameplate. The following points to be verified: Instrument tagging. Model number and instrument classification. Size and connections. Material of construction. Instrument range and calibration. Valve action and air/electrical failure positions Control modes on controller. Restriction orifice shall be inspected for a smooth face. The orifice diameter shall be measured with an inside micrometer compared with specification. The flow inlet side of the handle to be painted in red color for easy checks, at any time, after installation. 7.4.20.2 Instruments Calibration Calibration involves checking and adjusting instrument devices against a known precise reference to ensure performance complying with the manufacturers published specifications and accuracy. Instruments include the following: Level DP transmitters. Pressure transmitters/switches.
10000-Z-000-GE1-TMP-0004
(08/13)
Indicators. Transducers. Positioners & control valves. Level displaced transmitters / switches. After completion of this work QA/QC stickers should be fixed on the instruments, then, the check form shall be signed by all concerned parties. Pressure and temperature gauges Flow DP transmitters and vortex transmitter
PAGE 3972 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
7.4.20.3 Perform Loop Checks The purpose of this checks is to ensure that the instruments on field (transmitters, valves...) are correctly calibrated, connected and addressed to the PCS and ESD systems. The link (marshalling) between the instrument and the PCS and ESD or sub-system will be established at this phase. The test is performed on loop basis and it will be executed for each loop. 1
Pre-commissioning of instruments is done by checking the inputs/outputs of the control systems from the field up to PCS and ESD consoles and the local indications/controls. This includes the instruments on the packages. The configuration part on system/sub-system will be checked: the tag descriptions, process displays (including dynamic color change indications, trend displays, scales, alarm settings, alarm thresholds, physical units, the specific parameters if applicable: controller action, parameters values (PID), digital output (maintained or pulsed) and digital inputs (limit switches, alarms). Each instrument loop should have a separate loop file including the following contents: - Loop diagram - I/O list - Alarm and Set point values - Data sheet - Calibration certificate 7.4.20.4 Installation Check Check that all sample process piping/tubing to instruments have been installed per hookup drawings. Verify that control valves and regulators are oriented in the proper flow direction, positioners function properly.
10000-Z-000-GE1-TMP-0004
(08/13)
7.4.20.5 Hydro test Of Sample Lines 1
All sample lines and tubing connections to instruments shall be hydro tested to 1.5 times the design conditions of vessels and/or piping. 7.4.20.6 Leak Test - Pneumatic Signal Tubing Pneumatic transmission and output control lines are to be disconnected from all instruments (pressure switches, relays, controllers, and actuated devices (control valves), and blown through to remove deposits. The lines are then to be reconnected to all the instruments and pneumatically tested for leaks. All solenoid valves and pneumatic relays are to be bypassed during this cleaning blow
PAGE 4072 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
down, then reconnected and actuated for the leak test. The lines are then to be reconnected to the actuated device and subjected to the leak test. 1
Pneumatic leak test is 1.1 times the design pressure.
7.4.20.7 PSV Calibration All PSV's shall be bench tested and calibrated in accordance with the relevant API recommended codes. Compressed air shall be normally used and PSV is set according to specifications. Check properly: Name plate setting pressure and identification number. Orifice size. Bellow tightness (if any) at 0.5 ATM.
10000-Z-000-GE1-TMP-0004
(08/13)
Right gaskets are used. PSV's are installed in the correct places, directions and vertical position. Atmospheric PSV vents shall be drain hold at lowest point and well supported. Up-stream and downstream the PSV block valves if any, have been sealed open/closed as per P&ID's. No liquid can be collected and be stagnant in the discharge/line to B.D. header. Once the PSV has been checked, ensure that: - Lead sealed. - Record card filled for future reference. 7.4.20.8 Control Valves All control valves shall be calibrated. Check that: Proper gaskets are used. Valve seats are clean. Direction of flow is correct.
PAGE 4172 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
Stainless Steel tubing connections are fixed. Check proper spring action according to P&ID’s requirements (FO/ FC)
7.4.20.9 Restriction/ Orifice Plates Installation Before installation, orifice plates shall be checked by the instrument inspector for conformity with specifications. Hole size shall be reported. Orifice flanges connected with guaranteed utilities consumption and with fiscal feed inlet and product outlet shall be inspected for smoothness at the welded joints. Once orifice plates are installed check the correct place (line where installed) and correct flow direction. The flow inlet side of the handle to be painted in red color for easy checks, at any time, after installation. Meter run for orifice plates shall be checked
7.4.21 Fire And Gas System 7.4.21.1 Equipment Check Fire alarm devices need to be inspected and the specification data sheets checked against the nameplate. The following points to be verified: 1
10000-Z-000-GE1-TMP-0004
(08/13)
7.4.21.2 2 3 4
Device tagging. Model number and instrument classification. Size and connections.
Devices Calibration
Device range and calibration. Calibration involves checking and adjusting Gas devices against a known precise reference to ensure performance complying with the manufacturers published specifications and accuracy.
7.4.21.3 Perform Loop Checks
PAGE 4272 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
Loop checks are required to ensure that each fire and gas device in the plant functions in the correct sequence and with the proper action. All individual components in the system must be installed and checked. 7.4.21.4 Installation Check Check that all devices are installed according to the installation drawing of the system supplier. 7.4.22 TELECOM SYSTEM 7.4.22.1 Page / Party System 7.4.22.2 Privet Automatic Branch Exchange System (PABX) 7.4.22.3 Fiber Optic Cable 7.4.23 CATHODIC PROTECTION SYSTEM
10000-Z-000-GE1-TMP-0004
(08/13)
Check that the current values from the transformers to the protected equipment/ pipe are within the recommended limits and is stable.
PAGE 4372 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
7.4.24 Flushing Or Blowing The Plant It is important to plant, schedule to record all the preparatory operations and to co-ordinate the works so that they comply with the overall commissioning schedule. Small pieces of mill scale, weld rod stubs, weld spatter, insulation, paper, wood and other debris are sometimes unavoidably left in piping and equipment on completion of construction. A systematic program for flushing with water or blowing with air will eliminate most of the debris that might obstruct control valves and orifice plate’s restriction orifices or damage machinery. The flushing and cleaning entails whatever work is necessary to obtain a clean unit ready for process operation. Part of this work can be accomplished after hydraulic test execution and before final reinstatement of the piping. 7.4.25 Recommendations - Only fresh water which also shall be suitable for the system selected (Chlorite content max. 30 ppm 1 for Austenitic stainless and duplex steels for example and compressed air should be used. -
Dirt and debris should be flushed from the unit and not into it.
-
Water is supplied with temporary flexible hoses. Prior to flushing, make a manual cleaning to minimize obstruction.
-
The P&I Diagrams are used to prepare the flushing sequence and to follow the flushing. Finally, manual fine cleaning may be necessary.
10000-Z-000-GE1-TMP-0004
(08/13)
-
progress
of
The fire water circuit should be washed.
-
All control valves should be removed and flushed from both directions using the bypass and in-line valves, if possible. Otherwise, open and clean all control valves after flushing are completed, where will be difficult to remove them.
-
Instruments must be disconnected or isolated. Restriction orifice, thermo wells, vortex flow meter; flow sight glasses and Rota meter; etc… must be taken away, if have been installed.
-
Circulated flushing of the piping system within the plant may be carried out, where it is possible. If water circulated flushing, using process pumps, is applied for system cleaning, special care for over load trip must be taken `90 due to higher density than design condition.
-
Provisional strainers are installed and periodically cleaned. Spraying nozzles must be installed after relevant lines have been flushed to avoid clogging. If necessary, take out the flapper of check valves (previous check of the availability of spare gaskets).
PAGE 4472 OF 146145
3538-200-10-RT045 MAY 21, 2014
10000-Z-000-GE1-TMP-0004
(08/13)
REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
-
Vessels with de-misters or any other internals must be flushed from the bottom taking into consideration the water level. It’s better to install de-misters and packing after flushing / air blowing.
-
Internal man-ways have to be installed after flushing/air blowing of columns with trays.
-
Lines connected to vessels without internals can be flushed into the vessel itself. After the flushing, the vessel must also be cleaned.
-
Check that stroke movement; of any valve that was cut in during the flushing, are free and complete.
-
All blinds inserted into lines or equipment must be recorded, and drawn out after flushing. The water should be drained from every low point.
-
Use compressed air for piping blow down after flushing.
-
Special attention must be paid to certain piping systems such as lubricating oil and mechanical seal circulation systems where small orifices and openings are present. It may be necessary to dismantle the piping to clean it mechanically or by pickling. Once these systems are clean, they must be kept clean to prevent repetition of the cleaning operations.
-
For temporary flushing, use grainger sheet fabricated on site gasket. Insert proper gasket 1 final re-assembling of the unit. the
-
Final reinstatement of piping after flushing/blowing/cleaning activities shall be supervised by Commissioning Integrated Team (CIT) engineers to report the conformity with the design.
only for
PAGE 4572 OF 146145
3538-200-10-RT045
KPC
QASR COMPRESSION PROJECT
MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
WESTERN DESERT
7.4.26 Pre-commissioning Check Form List. 7.4.11.1 EQUIPMENT CHECK FORMS DESCRIPTION
10000-Z-000-GE1-TMP-0004
(08/13)
1
CHECK LIST NO.
Centrifugal Pump
ME-01A
Reciprocating Pump
ME-02A
Compressors
ME-08A
Air cooler
PR-18A
Filter
PV-01-A
Fixed roof Tank
PV-04-A
Vessel
PV-06-A
A/G piping system
PI-03-A
Pipe supports
PI-04-A
U/G Drain system
PI-06-A
FIRE WATER HYDRANT
LP-01A
HOSE HOUSE
LP-02A
FIRE WATER MONITOR
LP-03A
GASEOUS EXTINGUISHING SYSTEMS
LP-05A
FIRE AND GAS ALARM SYSTEM
LP-10A
FIRE AND GAS CABLE
LP-11A
FIRE AND GAS JUNCTION BOX
LP-12A
DETECTOR
LP-13A
CONDUIT
LP-14A
AIR HANDLING UNIT
HV-01 A
CONDENSING UNIT
HV-02 A
VENTILATION FANS
HV-05 A
PACKAGED WATER COOLED CHILLERS
HV-06 A
PUMPS FOR HVAC
HV-09 A
PIPING SYSTEM FOR HVAC
HV-10 A
EGYPT
PAGE 4672 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
10000-Z-000-GE1-TMP-0004
(08/13)
1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
EXPANSION AND COMPRESSION TANKS
HV-11 A
DAMPERS
HV-12 A
DUCTWORKS
HV-13 A
AIR OUTLETS
HV-14 A
FAN COIL UNITS PRIVET AUTOMATIC BRANCH EXCHANGE SYSTEM PUBLIC ADDRESS & GENERAL ALARM SYSTEM FIBER OPTICS CABLE
HV-16 A TE-01-A TE-02-A TE-04-A
DATA COMMUNICATION SYSTEM
TE-09-A
Control Valves & Regulator
IC-02-A
Shutdown & Blow down Valve
IC-03-A
Junction Box
IC-04-A
Pressure -Flow -Level-Temperature Transmitter
IC-05-A
Orifice Plates & Ventures
IC-06-A
Local Pressure Gauge _DP & Temp Gauge
IC-09-A
DCS Panel Cabinet Console
IC-10-A
ESD Panel Cabinet Console
IC-11-A
Analyzers
IC-18-A
Instrument Cables above Ground
IC-23-A
Switches
IC-24-A
Safety & Relief Valve
PR-08-A
Cathodic Protection
CP-01-A
KPC WESTERN DESERT EGYPT
PAGE 4772 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT
7.4.11.2 ELECTRICAL CHECK FORMS
10000-Z-000-GE1-TMP-0004
(08/13)
DESCRIPTION
CHECK LIST NO.
POWER TRANSFORMERS MV SWITCHGEAR AND MOTOR CONTROL GEAR LV SWITCHGEAR AND MOTOR CONTROL CENTER BUS BAR TRUNKING SYSTEM
EL-02 A
BATTERY & CHARGER ASSEMBLIES
EL-08 A
NEUTRAL GROUNDING RESISTOR
EL-09 A
AC UNINTERRUPTABLE POWER SUPPLY
EL-12 A
VARIABLE SPEED DRIVE POWER FACTOR IMPROVEMENT EQUIPMENT MOTORS
EL-19 A
LIGHTING AND SMALL POWER MATERIAL SUPERVISORY CONTROL AND DATA ACQUISITION SYSTEM RACEWAYS AND SUPPORTS
EL-23 A
LOW VOLTAGE CABLES
EL-30 A
GROUNDING SYSTEM
EL-33 A
MOTOR CONTROL STATIONS
EL-35 A
LIGHTNING PROTECTION SYSTEM
EL-37 A
ELECTRICAL HEATERS
PR-05A
For Pre-commissioning Check Forms refer to attachment II
EL-03 A EL-04 A EL-07 A
EL-21 A EL-22 A
EL-26 A EL-27 A
EGYPT
PAGE 4872 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
7.5 Sequential Completion Flow Chart Equipment Erection &Piping Installation
Hydro-testing and re-instatement Conformity Checks and punch list issuance Clear punch list category (A)
Pre commissioning activities
Systems Dossiers Completion
Mechanical Completion Certificate
10000-Z-000-GE1-TMP-0004
(08/13)
Commissioning Activities
Plant start up and Initial operation Stable operation and performance test
Piping Flushing and Cleaning
Clear punch list category (B)
PAGE 4972 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
8.0 CONFORMITY CHECK OF THE PLANT'S EQUIPMENT Each system of the Plant will be inspected for conformity with project documentation, specifications, technical reviews and design reviews (HAZOP, ….etc.) and a punch list is drawn up to record any deviations requiring further construction work or modification. After the completion of each activity, the relevant check lists will be filled out and signed by all parties. Plant inspection and conformity check shall cover all equipment, packages, skids, piping, valves, instruments, .etc. taking in consideration that they will be finalized and inspected by Operations All inspection shall be performed against design, specifications and drawings and any defects or deviation should be cleared prior mechanical completion or plant start-up according to its criticality
9.0 SYSTEM DOCUMENTS To enable a staged completion of the Project, the entire Facilities shall be divided into systems based on a Unit or Area basis, the elected numbering system intends to cover the control & documentation needs in the most appropriate and beneficial way. Each system shall be stand-alone during pre-commissioning and will have a mechanical completion certificate as well as a separate file System file shall include as a minimum the following:
10000-Z-000-GE1-TMP-0004
(08/13)
-
Marked up P&ID indicating system boundary (updated marked up P&ID's will be issued as required). List of all component in the system such as instruments, equipment, Related hydro-test loops included in the system Hydro-test completion certificates All pre-commissioning check forms related to the system Punch list Leak testing certificate System Mechanical completion certificate
PAGE 5072 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
10.0 PROGRESS MONITORING For progress measurement and in order to prioritize the construction activities to achieve mechanical completion of the systems; the following reports will be developed: A. Hydro-test loop status. B. Loops reinstatement status. C. Systems MC status. D. Internal Punch list status. E. Pre-commissioning check forms Generally progress will be monitored and controlled by the using of completed check forms and certificates against total number of check forms to be issued 11.0 PUNCH LISTING In order to unify criteria within the different stages of the project, a unique Punch List will be generated for each system and different priority codes will be established in order to assign the appropriate responsibilities for the modification of work. Punch list team will establish and maintains this unique Punch List which will contain all the items submitted by the parties involved in the various stages of the Project (e.g.: Contractor, project inspection, operation team, loss prevention, etc.). The General structure of the Punch List will contain the following criteria:
10000-Z-000-GE1-TMP-0004
(08/13)
System Number: System Number in which it is present. Item No: Unique number that will be generated as soon as the fault is validated and approved. Item Description: Brief explanation of the encountered fault, together with the applicable tag number (if possible). Item Entry Date: Record date of the item. Scheduled Date for Completion: Date in which the fault has to be corrected. Category: Categorization of the item (A), (B) or (C). Originator (checker): Person who originates the fault, he will be responsible for following-up and clearing the fault. Scope: discipline scope to clear the item.
The main target of this unique Punch Listing methodology is to have a complete set of information throughout the system which will assist in expediting the work to be completed in every stage. With this idea in mind, a proper classification of items has been designed in
PAGE 5172 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
order to reduce categories to a minimum and to clearly identify the stages in which faults have to be corrected without avoiding the responsibility allocation Taking these terms into account, the Priority field (to be agreed between the Approver and the Construction Manager / Pre-commissioning manager) will be categorized as follows: Category “A”: Items required to be completed before Mechanical Completion Acceptance. Category “B”: Items required to be completed during commissioning & before Start-up. Category “C”:
Items could be completed after performance test.
In addition to the former, a category indicating Construction or Pre-commissioning responsibility will be clearly established in order to facilitate the item clearance For punch list form please refer to attachment III 12.0 STEPS TO ACHIEVE MECHANICAL COMPLETION AND MECHANICAL COMPLETION CERTIFICATE (MCC) The final step within the pre-commissioning activities will correspond to the handover of the systems / units by means of achieving Mechanical Completion. Mechanical Completion shall be achieved for the “SYSTEM”, when:
10000-Z-000-GE1-TMP-0004
(08/13)
The SYSTEM, is constructed in strict compliance with all requirement of the CONTRACT, including the successful completion of all required inspection, testing, and pre-commissioning; All pre-commissioning activities are completed and related check forms are signed. The work site is in a clean and in safe condition and excess materials removed. All punch list items category "A" cleared and approved. System file (dossier) completed. All documents are available at site such as vendors operating manuals, commissioning spare parts list and commissioning and start up guide.
Mechanical Completion is deemed to be achieved even if minor outstanding works, Final Punch List Items category "B & C" are still to be completed. These works should not interfere with the safe completion of the commissioning and start-up activities, and shall be properly recorded on a Final Punch List and completed within a period mutually agreed between all concerned parties
PAGE 5272 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
Upon completion of all the above mechanical completion requirements, Construction Contractor shall issue the Mechanical Completion certificate (MCC) for each system for both ENPPI and KPC approval. Project MCC shall be issued upon completion of all the systems MECHANICAL COMPLETION CERTIFICATES.
10000-Z-000-GE1-TMP-0004
(08/13)
For MCC form, refer to attachment IV
PAGE 5372 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
13.0 HSE PROCEDURES The responsibilities and regulations regarding HSE at the construction-site are already defined in the ENPPI Project HSE Plan Construction Phase; therefore this part is not a substitution for existing agreements and regulations but an amendment, especially aimed at activities which take place during the stage of pre-commissioning. The project goal "zero Incidents" is also applicable during the pre-commissioning. The last construction activities and the pre-commissioning activities will be executed in parallel. For this reason special attention should be paid to the following items:
1
10000-Z-000-GE1-TMP-0004
(08/13)
Permit to work system shall be in place to control risks of simultaneous operations Powering the panels shall be proceeded after meggering activities have been completed successfully and an announcement to all personnel by means of toolbox meetings. Lockout and tag out procedures to be implemented only authorized personnel of ENPPI and sub-contractor are allowed to work on such installation parts and this shall be organized by means of a work permit issued by the Client and/or ENPPI. During hydraulic testing of piping systems, incidents can occur such as blowing out of gaskets. Piping systems, being hydraulically tested, shall be marked with warning signs and/or marking ribbon. When this hydraulic testing starts, all personnel shall be informed by means of toolbox meetings. Piping systems which are being used in an early stage, such as air and nitrogen, shall be marked at the location of connections/valves by means of a warning signs. Testing with gasses with a pressure higher than one (1) bar (service testing air or nitrogen) shall take place without personnel working in the near area. This is because gasses act differently under pressure than liquids when sudden leakage occurs. This means areas shall be marked, or testing shall be executed in off-hours. Testing of equipment taking place in this stage shall be announced during toolbox meetings and this equipment shall be indicated by means of a marking ribbon. Valves can be operated during the I/O testing. This may give personnel working in the near area a fright, especially in case of pneumatically activated valves. Personnel shall be warned when these activities start. When electrical equipment is powered-up, the lock and safe procedure is applicable. This is done to secure and lock work-switches and other electrical parts. HSE meeting will be held before starting the pre-commissioning activities.
During the stage of actual commissioning, construction activities shall only be executed in consultation with and after permission by ENPPI. The construction activities being in execution at that time may be painting, insulation activities and solving of non-critical punch-list items. 13.1 Risk Assessment
PAGE 5472 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
Risk assessments shall be prepared before any hazardous pre-commissioning activities are executed, to identify any hazards involved and to establish what precautions need to be taken.
10000-Z-000-GE1-TMP-0004
(08/13)
14.0 SYSTEMS COMPONENT LIST
PAGE 5572 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
X.80.TI.001
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
EXISTING PRODUCTION SEPARATOR TIE IN SYSTEM QA-V-3002A A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12359, REV.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID. INSTRUMENTS CONTROL VALVES 80-FV-012A SHUTDOWN VALVE 30-ESDV-017
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES
10000-Z-000-GE1-TMP-0004
(08/13)
X.80.TI.002
PI 03 A/04 A IC-03 A/05 A09 A IC-23 A
EXISTING PRODUCTION SEPARATOR TIE IN SYSTEM QA-V-3002B A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12360, REV.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
PAGE 5672 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
INSTRUMENTS CONTROL VALVES 80-FV-012B SHUTDOWN VALVE 80-ESDV-018
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES X.80.TI.003
PI 03 A/04 A IC-03 A/05 A09 A IC-23 A
EXISTING PRODUCTION SEPARATOR TIE IN SYSTEM QA-V-3002C A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12361, REV.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID. INSTRUMENTS CONTROL VALVES 80-FV-012C SHUTDOWN VALVE 80-ESDV-019
10000-Z-000-GE1-TMP-0004
(08/13)
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES X.80.TI.004
PI 03 A/04 A IC-03 A/05 A09 A IC-23 A
EXISTING PRODUCTION SEPARATOR TIE IN SYSTEM QA-V-4002A
PAGE 5772 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12362, REV.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID. INSTRUMENTS CONTROL VALVES 80-FV-013A SHUTDOWN VALVE 80-ESDV-020
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES X.80.TI.005
PI 03 A/04 A IC-03 A/05 A09 A IC-23 A
EXISTING PRODUCTION SEPARATOR TIE IN SYSTEM QA-V-4002B A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12363, REV.04
10000-Z-000-GE1-TMP-0004
(08/13)
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID. INSTRUMENTS CONTROL VALVES 80-FV-013B SHUTDOWN VALVE 80-ESDV-021
PAGE 5872 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES X.80.TI.006
PI 03 A/04 A IC-03 A/05 A09 A IC-23 A
PHASE I GAS MANIFOLD TIE IN
A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12355, REV.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
FLOW
INSTRUMENTS 80-FIT-012
C. CHECK FORMS
10000-Z-000-GE1-TMP-0004
(08/13)
PIPING INSTRUMENTS INSTRUMENT CABLES X.80.TI.007
PI 03 A/04 A IC-05 A /09 A /06 A IC-23 A
PHASE II GAS MANIFOLD TIE IN A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12363, Rev.04 イイ 3538-200-KKD-12353, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK
PAGE 5972 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
FLOW
INSTRUMENTS 80-FIT-013
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES X.80.TI.008
PI 03 A/04 A IC-05 A /09 A /06 A IC-23 A
BYPASS BLOW DOWN LINES TIE IN SYSTEM A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12353, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK
10000-Z-000-GE1-TMP-0004
(08/13)
Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID. INSTRUMENTS SHUTDOWN VALVE 80-ESDV-041 80-ESDV-042
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES
PI 03 A/04 A IC-03 A/05 A09 A IC-23 A
PAGE 6072 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
X.80.TI.009
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
PHASE I HP FLARE KO DRUM QA-V-3002 TIE IN SYATEM A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12356, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
Temperature
INSTRUMENTS 80-TT-041
Pressure
80-PT-041
Level
80-LIT-341 80-LIT-344A 80-LIT-344B 80-LIT-344C
Flow
80-FT-041
C. CHECK FORMS
10000-Z-000-GE1-TMP-0004
(08/13)
PIPING INSTRUMENTS INSTRUMENT CABLES X.80.TI.010
PI 03 A/04 A IC-03 A/05 A09 A IC-23 A
PHASE I COLD VENT A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12357, Rev.04
PAGE 6172 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
Temperature
INSTRUMENTS 80-TT-042
Pressure
80-PT-042
Flow
80-FT-042
Oxygen analyzer
80-AIT-003
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES Analyzers X.80.TI.011
PI 03 A/04 A IC-03 A/05 A09 A IC-23 A IC-18-A
PHASE II COLD VENT A. GENERAL
10000-Z-000-GE1-TMP-0004
(08/13)
Refer to marked P&ID イイ 3538-200-KKD-12357, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
Temperature
INSTRUMENTS 80-TT-045
PAGE 6272 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
Pressure
80-PT-045
Flow
80-FT-045
Oxygen analyzer
80-AIT-004
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES Analyzers X.80.TI.012
PI 03 A/04 A IC-03 A/05 A09 A IC-23 A IC-18-A
METHANOL DISTRIBUTION SYSTEM
10000-Z-000-GE1-TMP-0004
(08/13)
A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12358, REV.04 イイ 3538-200-KKD-12210, Rev.05 イイ 3538-200-KKD-12211, Rev.04 イイ 3538-200-KKD-12212, SH1 Rev.04 イイ 3538-200-KKD-12213, Rev.04 イイ 3538-200-KKD-12214, Rev.04 イイ 3538-200-KKD-12221, Rev.04 イイ 3538-200-KKD-12222, SH1 Rev. 04 イイ 3538-200-KKD-12223, Rev. 04 イイ 3538-200-KKD-12224, Rev. 04 イイ 3538-200-KKD-12231, Rev. 04 イイ 3538-200-KKD-12232, SH1 Rev. 04 イイ 3538-200-KKD-12233, Rev. 04 イイ 3538-200-KKD-12234, Rev. 04 イイ 3538-200-KKD-12241, Rev. 04 イイ 3538-200-KKD-12242, SH1 Rev. 04 イイ 3538-200-KKD-12243, Rev. 04 イイ 3538-200-KKD-12244, Rev. 04 イイ 3538-200-KKD-12353, Rev. 04 イイ 3538-200-KKD-12354, Rev. 04 イイ 3538-200-KKD-12368, Rev. 04
KPC WESTERN DESERT EGYPT
PAGE 6372 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
Shutdown valve
10000-Z-000-GE1-TMP-0004
(08/13)
FLOW
INSTRUMENTS 80-ESDV-027 80-FI-031 80-FI-105 80-FI-107 80-FI-101 80-FI-106 80-FI-205 80-FI-207 80-FI-201 80-FI-206 80-FI-305 80-FI-307 80-FI-301 80-FI-306 80-FI-405 80-FI-407 80-FI-401 80-FI-406 80-FI-040 80-FI-033 80-FI-032
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT
PI 03 A/04 A IC-03 A/05 A09 A IC-23 A
PAGE 6472 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
CABLES X.80.TI.013
PHASE I INSTRUMENT AIR SYSTEM TIE-IN A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12364, Rev. 04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID. C. CHECK FORMS PIPING
X.80.TI.014
PI 03 A/04 A
PHASE II BLACK START FUEL GAS TIE IN SYSTEM A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12354, Rev. 04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK
10000-Z-000-GE1-TMP-0004
(08/13)
Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
FLOW
INSTRUMENTS 80-FI-021 A/B
TEMPRETURE
80-TIT-027
PRESSURE
80-PIT-098
C. CHECK FORMS
PAGE 6572 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
PIPING INSTRUMENTS INSTRUMENT CABLES X.80.TI.015
KPC WESTERN DESERT EGYPT
PI 03 A/04 A IC-03 A/ 05 A/ 06 A IC-23 A
PHASE I BLACK START FUEL GAS TIE IN SYSTEM A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12368, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
FLOW
INSTRUMENTS 80-FI-024 A/B
TEMPRETURE
80-TIT-028
PRESSURE
80-PIT-902
C. CHECK FORMS
10000-Z-000-GE1-TMP-0004
(08/13)
PIPING INSTRUMENTS INSTRUMENT CABLES X.80.TI.016
PI 03 A/04 A IC-03 A/ 05 A/ 06 A IC-23 A
PHASE II HP FLARE KO DRUM QA-V-4004 TIE IN SYSTEM A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12369, REV.04
PAGE 6672 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
Temperature
INSTRUMENTS 80-TT-046
Pressure
80-PT-046
Level
80-LIT-032A 80-LIT-032B 80-LIT-032C
Flow
80-FT-046
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES X.80.TI.017
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A
NEW MPU TIE IN SYSTEM
10000-Z-000-GE1-TMP-0004
(08/13)
A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12371, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
PAGE 6772 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
C. CHECK FORMS PIPING X.80.TI.018
MCRS-P&P-700,709,711,712
NEW DIESEL TRANSFER PUMP QA-P-8020 A. GENERAL Refer to marked P&ID イイ 3538-200-KKD-12368, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
PRESSURE
INSTRUMENTS 80-PG-099
FLOW
80-FII-025
PUMP
EQUIPMENT QA-P-8020
C. CHECK FORMS
10000-Z-000-GE1-TMP-0004
(08/13)
PIPING INSTRUMENTS CENTRIFUGAL PUMP
X.80. TI.019 X.80. TI.020
X.80.TI.019
PI 03 A/04 A IC-03 A/ 05 A/ 09 A ME-01A
TIE IN TO THE EXISTING 11 KV SWG QA-L-8004 PMS TIE IN RELATED TO EXISTING 11 KV SWG QA-L-8001
TIE IN TO THE EXISTING 11 KV SWG QA-L-8004
PAGE 6872 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
C. CHECK FORMS LV SEITCHGEAR AND CONTROL MOTOR CONTROL CENTER X.80.TI.020
EL-04 A
PMS TIE IN RELATED TO EXISTING 11 KV SWG QA-L-8001 C. CHECK FORMS LV SEITCHGEAR AND CONTROL MOTOR CONTROL CENTER
EL-04 A
4.2 PROCESS SYSTEMS X.80.P.001
COMPRESSOR INLET MANIFOLD A. GENERAL Refer to marked P&ID’s
10000-Z-000-GE1-TMP-0004
(08/13)
イイ イイ イイ イイ イイ イイ イイ イイ イイ イイ
3538-200-KKD-12355 REV.04 3538-200-KKD-12210 Rev.05 3538-200-KKD-12211 Rev.04 3538-200-KKD-12214 Rev.04 3538-200-KKD-12221 Rev.04 3538-200-KKD-12224 Rev.04 3538-200-KKD-12231 Rev.04 3538-200-KKD-12234 Rev.04 3538-200-KKD-12241 Rev.04 3538-200-KKD-12244 Rev.04 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
TEMPERATURE
INSTRUMENTS 80-TG-030 80-TIT-031
PAGE 6972 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT
80-TI-048
C.
PRESSURE
80-PG-915 80-PIT-091 A/B 80-PDIT-906 80-PDIT-907
RESTRICTED ORFICE
80-RO-013 80-RO-018
SHUTDOWN VALVE
80-ESDV-030 A/B 80-ESDV-031 A/B
BLOWDOWN VALVE
80-BDV-0010 80-BDV-0010
CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES
X.80.P.002
PI 03 A/04 A IC-03 A/ 05 A/ 09 A/ 06 A IC-23 A
COMPRESSOR SUCTION DRUM TRAIN A (QA-V-8001A) SYSTEM
10000-Z-000-GE1-TMP-0004
(08/13)
A. GENERAL Refer to marked P&ID’s イイ イイ イイ イイ イイ イイ イイ
3538-200-KKD-12211 Rev.04 3538-200-KKD-12212, SH1 Rev.04 3538-200-KKD-12221, Rev.04 3538-200-KKD-12231, Rev.04 3538-200-KKD-12241, Rev.04 3538-200-KKD-12250, Rev.05 3538-200-KKD-12254, Rev.05
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK
EGYPT
PAGE 7072 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s. INSTRUMENTS 80-TIT-101 80-TG-105 80-TG-111
10000-Z-000-GE1-TMP-0004
(08/13)
TEMPERATURE
PRESSURE
80-PDIT-101 80-PDIT-121 80-PG-103 80-PG-106 80-PG-107 80-PG-103 80-PDIT-108 80-PIT-109 80-PIT-110
LEVEL
80-LIT-101 80-LIT-102 80-LIT-107 80-LG-103
FLOW
80-FIT-102
CONTROL VALVE
80-LV-102 80-PV-123
SHUTDOWN VALVE
80-ESDV-101 A/B 80-ESDV-103
SAFETY VALVES
80-PSV-105 A/B
PIPING INSTRUMENTS INSTRUMENT CABLES VESSEL
PI-03-A/ 04-A IC-03-A/ 05-A/ 09-A/ 02-A /06A IC-23-A PV-06-A
C. CHECK FORMS
PAGE 7172 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
X.80.P.003
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
COMPRESSOR TRAIN-A (QA-K-8001A) SYSTEM A. GENERAL Refer to marked P&ID’s イイ イイ イイ
3538-200-KKD-12212 SH1, Rev.04 3538-200-KKD-12212 SH2, Rev.02 3538-200-KKD-12213, Rev.04 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
TEMPERATURE
INSTRUMENTS 80-TIT-102 80-TIT-103 80-TIT-111 80-TG-104 80-TIT-110 80-SIT-101
VIBRATION
80-VIT-101
PRESSURE
80-PIT-111 80-PIT-112 80-PG-113 80-PG-115 80-PT-5167 TRAIN A
FLOW
80-FT-2108 TRAIN A
RESTRICTED ORFICE
80-RO-101 80-RO-103
10000-Z-000-GE1-TMP-0004
(08/13)
SPEED
PAGE 7272 OF 146145
3538-200-10-RT045 MAY 21, 2014
10000-Z-000-GE1-TMP-0004
(08/13)
REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
LEVEL
80-LG-102 80-LIT-108 80-LIT-109 80-LIT-110
SHUTDOWN VALVE
80-ESDV-109
CONTROL VALVES
80-LV-108 80-AV-5167 TRAIN A
SAFETY VALVES
80-PSV-114 A/B
FLAME ARRESTOR
80-FA-2121 TRAIN A 80-FA-5177 TRAIN A 80-FA-3270 TRAIN A
BLOWDOWN VALVE
80-BDV-101
WESTERN DESERT
EQUIPMENT COMPRESSOR QA-K-8001A TURBINE QA-GTK-8001A COALESCING FILTER F-2100 FILTER F-2106 CO2 EXTINGUISHING AS-6600 / 6601 SEAL GAS TREATMENT SKID LUBE OIL COOLER VENT SEPARATOR F-2370 C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT
PI 03 A/04 A IC-03 A/ 05 A/ 09 A/ 02 A/ 06-A IC-23 A
EGYPT
PAGE 7372 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
PRE-COMMISSIONING PROCEDURE
CABLES VESSEL FILTER ELECTRIC HEATER FLAME ARRESTOR CENTRIFUGAL TURBO COMPRESSOR
X.80.P.004
KPC
QASR COMPRESSION PROJECT
WESTERN DESERT EGYPT
PV-06-A PV-01-A PR-05-A PR-11-A ME-08-A
COMPRESSOR DISCHARE COOLER TRAIN-A (QA-E-8001A) SYSTEM A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12213, Rev.04 イイ 3538-200-KKD-12214, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
10000-Z-000-GE1-TMP-0004
(08/13)
TEMPERATURE
INSTRUMENTS 80-TG-106 A/B 80-TIT-107 80-TIT-108 A/B/C 80-TIT-113A
CONTROL VALVE
80-FV-104
SWITCH
80-VSHH-102 A/B/C/D
AIR COOLER MOTOR
EQUIPMENT QA-E-8001A 80-EM-8001 AA/AB/AC/AD
PAGE 7472 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES AIR COOLER MOTOR
X.80.P.005
PI 03 A/04 A IC-03 A/ 05 A/ 09 A/ 02 A/ IC-23 A PR-18-A EL-22-A
COMPRESSOR DISCHARE DRUM TRAIN-A (QA-V-8002A) SYSTEM A. GENERAL イイ イイ イイ イイ イイ イイ イイ イイ イイ イイ イイ イイ
Refer to marked P&ID’s 3538-200-KKD-12214, Rev.04 3538-200-KKD-12224, Rev.04 3538-200-KKD-12234, Rev.04 3538-200-KKD-12244, Rev.04 3538-200-KKD-12221, Rev.04 3538-200-KKD-12241, Rev.04 3538-200-KKD-12312, Rev.04 3538-200-KKD-12359, Rev.04 3538-200-KKD-12360, Rev.04 3538-200-KKD-12361, Rev.04 3538-200-KKD-12362, Rev.04 3538-200-KKD-12363, Rev.04
10000-Z-000-GE1-TMP-0004
(08/13)
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
TEMPERATURE PRESSURE
INSTRUMENTS 80-TG-112 80-PDG-108 80-PDIT-102
PAGE 7572 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
80-PDIT-122 80-PG-117 80-PG-119 80-PIT-064 LEVEL
80-LIT-104 A/B 80-LIT-105 80-LG-106
CONTROL VALVES
80-FV-103 80-LV-105
SHUTDOWN VALVE
80-ESDV-102 A/B 80-ESDV-104
SAFETY VALVES
80-PSV-118 A/B EQUIPMENT
DISCHARGE DRUM TRAIN A
QA-V-8002A
10000-Z-000-GE1-TMP-0004
(08/13)
C. CHECK FORMS
X.80.P.006
PIPING INSTRUMENTS
PI 03 A/04 A IC-03 A/ 05 A/ 09 A/ 02 A/
INSTRUMENT CABLES
IC-23 A
VESSEL
PV-06-A
COMPRESSOR DISCHARGE MANIFOLD SYSTEM A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12210, REV.04 イイ 3538-200-KKD-12214, REV.04 イイ 3538-200-KKD-12224, REV.04
KPC WESTERN DESERT EGYPT
PAGE 7672 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
イイ イイ イイ イイ
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
3538-200-KKD-12234, REV.04 3538-200-KKD-12244, REV.04 3538-200-KKD-12353, REV.04 3538-200-KKD-12244, REV.04 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
10000-Z-000-GE1-TMP-0004
(08/13)
TEMPERATURE
INSTRUMENTS 80-TIT-033 80-TG-032
PRESSURE
80-PIT-092 80-PDIT-908 80-PG-916
RESTRICTED ORFICE
80-RO-014 80-RO-017
SHUTDOWN VALVES
80-ESDV-032 A/B
BLOWDOWN VALVE
80-BDV-011 80-BDV-013
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES X.80.P.007
PI 03 A/04 A IC-03 A/ 05 A/ 09 A/ 02 A/ 06 A IC-23 A
COMPRESSOR SUCTION DRUM TRAIN B (QA-V-8001B) SYSTEM
PAGE 7772 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
A. GENERAL Refer to marked P&ID’s イイ イイ
3538-200-KKD-12221 Rev.04 3538-200-KKD-12222 Rev.04
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
TEMPERATURE
PRESSURE
80-PDIT-201 80-PDIT-221 80-PG-203 80-PG-206 80-PG-207 80-PG-203 80-PDIT-208 80-PIT-209 80-PIT-210
LEVEL
80-LIT-201 80-LIT-202 80-LIT-207 80-LG-203
FLOW
80-FIT-202
CONTROL VALVE
80-LV-202 A/B 80-PV-223
(08/13) 10000-Z-000-GE1-TMP-0004
INSTRUMENTS 80-TIT-201 80-TG-205 80-TG-211
PAGE 7872 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT
WESTERN DESERT
PRE-COMMISSIONING PROCEDURE
SHUTDOWN VALVE
80-ESDV-201 A/B 80-ESDV-203
SAFETY VALVES
80-PSV-205 A/B
EGYPT
C. CHECK FORMS PIPING INSTRUMENTS
B (QA-
INSTRUMENT CABLES VESSEL A. GENERAL
PI-03-A/ 04-A IC-03-A/ 05-A/ 09-A/ 02-A /06A IC-23-A PV-06-A
X.80.P.008 COMPRESSOR TRAINK-8001B) SYSTEM
Refer to marked P&ID’s イイ イイ イイ
3538-200-KKD-12222 SH1, Rev.04 3538-200-KKD-12222 SH2, Rev.02 3538-200-KKD-12223, Rev.04 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
10000-Z-000-GE1-TMP-0004
(08/13)
TEMPERATURE
PRESSURE
INSTRUMENTS 80-TIT-202 80-TIT-203 80-TIT-211 80-TIT-210 80-TG-204 80-PIT-211 80-PIT-212 80-PG-213
PAGE 7972 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
10000-Z-000-GE1-TMP-0004
(08/13)
80-PT-5167 TRAIN B FLOW
80-FT-2108 TRAIN B
RESTRECTION ORFICE
80-RO-201 80-RO-203
LEVEL
80-LG-202 80-LIT-208 80-LIT-209 80-LIT-210
SPEED
80-SIT-201
VIBRATION
80-VIT-201
SHUTDOWN VALVE
80-ESDV-209
CONTROL VALVES
80-LV-208 80-AV-5167 TRAIN B
SAFETY VALVES
80-PSV-214 A/B
BLOWDOWN VALVE
80-BDV-201
FLAME ARRESTOR
80-FA-2121 TRAIN A 80-FA-5177 TRAIN A 80-FA-3270 TRAIN A
EQUIPMENT COMPRESSOR QA-K-8001B TURBINE QA-GTK-8001B COALESCING FILTER F-2100 FILTER F-2106 CO2 EXTINGUISHING AS-6600 / 6601
KPC WESTERN DESERT EGYPT
PAGE 8072 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
SEAL GAS TREATMENT SKID LUBE OIL COOLER VENT SEPARATOR
WESTERN DESERT EGYPT
F-2370
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES VESSEL FILTER ELECTRIC HEATER FLAME ARRESTOR CENTRIFUGAL TURBO COMPRESSOR X.80.P.009
PI 03 A/04 A IC-03 A/ 05 A/ 09 A/ 02 A/ 06-A IC-23 A PV-06-A PV-01-A PR-05-A PR-11-A ME-08-A
COMPRESSOR DISCHARE COOLER TRAIN-B (QA-E-8001B) SYSTEM B. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12223, Rev.04 イイ 3538-200-KKD-12224, Rev.04 The pre-commissioning shall be performed including the following:
10000-Z-000-GE1-TMP-0004
(08/13)
B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
TEMPERATURE
CONTROL VALVE
INSTRUMENTS 80-TG-206 A/B 80-TIT-207 80-TIT-208 A/B/C 80-TIT-213A 80-FV-204
PAGE 8172 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
SWITCH
AIR COOLER MOTOR
WESTERN DESERT EGYPT
80-VSHH-202 A/B/C/D EQUIPMENTS QA-E-8001B 80-EM-8001BA/BB/BC/BD
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES AIR COOLER MOTOR
X.80.P.010
PI 03 A/04 A IC-03 A/ 05 A/ 09 A/ 02 A/ IC-23 A PR-18-A EL-22-A
COMPRESSOR DISCHARE DRUM TRAIN-B (QA-V-8002B) SYSTEM A. GENERAL イイ
Refer to marked P&ID’s 3538-200-KKD-122224, Rev.04
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK
10000-Z-000-GE1-TMP-0004
(08/13)
Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
TEMPERATURE PRESSURE
INSTRUMENTS 80-TG-212 80-PDG-208 80-PDIT-202 80-PDIT-222 80-PG-217 80-PG-219
PAGE 8272 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
LEVEL
80-LIT-204 A/B 80-LIT-205 80-LG-206
CONTROL VALVES
80-FV-203 80-LV-205
SHUTDOWN VALVE
80-ESDV-202 A/B 80-ESDV-204
SAFETY VALVES
80-PSV-218 A/B
WESTERN DESERT EGYPT
EQUIPMENT DISCHARGE DRUM TRAIN B
QA-V-8002B
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES VESSEL X.80.P.011
PI-03-A/ 04-A IC-03-A/ 05-A/ 09-A/ 02-A /06A IC-23-A PV-06-A
COMPRESSOR SUCTION DRUM TRAIN-C (QA-V-8001C) SYSTEM
10000-Z-000-GE1-TMP-0004
(08/13)
A. GENERAL Refer to marked P&ID’s イイ イイ
3538-200-KKD-12231 Rev.04 3538-200-KKD-12232 SH1,Rev.04
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
PAGE 8372 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
INSTRUMENTS 80-TIT-301 80-TG-305 80-TG-311
TEMPERATURE
80-PDIT-301 80-PDIT-321 80-PG-303 80-PG-306 80-PG-307 80-PG-303 80-PDIT-308 80-PIT-309 80-PIT-310
LEVEL
80-LIT-301 80-LIT-302 80-LIT-307 80-LG-303
FLOW
80-FIT-302
CONTROL VALVE
80-LV-302 80-PV-323
SHUTDOWN VALVE
80-ESDV-301 A/B 80-ESDV-303
SAFETY VALVES
80-PSV-305 A/B
10000-Z-000-GE1-TMP-0004
(08/13)
PRESSURE
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES VESSEL
PI-03-A/ 04-A IC-03-A/ 05-A/ 09-A/ 02-A /06A IC-23-A PV-06-A
KPC WESTERN DESERT EGYPT
PAGE 8472 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
X.80.P.012
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
COMPRESSOR TRAIN-C (QA-K-8001C) SYSTEM A. GENERAL Refer to marked P&ID’s イイ イイ イイ
3538-200-KKD-12232 SH1, Rev.04 3538-200-KKD-12232 SH2, Rev.02 3538-200-KKD-12233, Rev.04 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
10000-Z-000-GE1-TMP-0004
(08/13)
TEMPERATURE
INSTRUMENTS 80-TIT-302 80-TIT-303 80-TIT-311 80-TIT-310 80-TG-304
PRESSURE
80-PIT-311 80-PIT-312 80-PG-313 80-PT-5167
FLOW RESTRICTION ORFICE
80-FT-2108 80-RO-301 80-RO-303
LEVEL
80-LG-302 80-LIT-308 80-LIT-309 80-LIT-310
SPEED
80-SIT-301
PAGE 8572 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
VIBRATION
80-VIT-301
SHUTDOWN VALVE
80-ESDV-309
CONTROL VALVES
80-LV-308 80-AV-5167 TRAIN C
SAFETY VALVES
80-PSV-314 A/B
BLOWDOWN VALVE
80-BDV-301
FLAME ARRESTOR
80-FA-2121 TRAIN C 80-FA-5177 TRAIN C 80-FA-3270 TRAIN C
WESTERN DESERT
10000-Z-000-GE1-TMP-0004
(08/13)
EQUIPMENT COMPRESSOR QA-K-8001C TURBINE QA-GTK-8001C COALESCING FILTER F-2100 FILTER F-2106 CO2 EXTINGUISHING AS-6600 / 6601 SEAL GAS TREATMENT SKID LUBE OIL COOLER VENT SEPARATOR F-2370 C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES VESSEL FILTER ELECTRIC HEATER
PI 03 A/04 A IC-03 A/ 05 A/ 09 A/ 02 A/ 06-A IC-23 A PV-06-A PV-01-A PR-05-A
EGYPT
PAGE 8672 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
PRE-COMMISSIONING PROCEDURE
FLAME ARRESTOR CENTRIFUGAL TURBO COMPRESSOR X.80.P.013
KPC
QASR COMPRESSION PROJECT
WESTERN DESERT EGYPT
PR-11-A ME-08-A
COMPRESSOR DISCHARE COOLER TRAIN-C (QA-E-8001C) SYSTEM C. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12233, Rev.04 イイ 3538-200-KKD-12234, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
10000-Z-000-GE1-TMP-0004
(08/13)
TEMPERATURE
INSTRUMENTS 80-TG-306 A/B 80-TIT-307 80-TIT-308 A/B/C 80-TIT-313A
CONTROL VALVE
80-FV-304
SWITCH
80-VSHH-302 A/B/C/D
AIR COOLER MOTOR
EQUIPMENT QA-E-8001C QA-EM-8001 CA/CB/CC/CD
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES
PI 03 A/04 A IC-03 A/ 05 A/ 09 A/ 02 A/ IC-23 A
PAGE 8772 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
PRE-COMMISSIONING PROCEDURE
AIR COOLER MOTOR
X.80.P.014
KPC
QASR COMPRESSION PROJECT
WESTERN DESERT EGYPT
PR-18-A EL-22-A
COMPRESSOR DISCHARE DRUM TRAIN-C (QA-V-8002C) SYSTEM A. GENERAL イイ
Refer to marked P&ID’s 3538-200-KKD-122234, Rev.04
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
10000-Z-000-GE1-TMP-0004
(08/13)
TEMPERATURE
INSTRUMENTS 80-TG-312
PRESSURE
80-PDG-308 80-PDIT-302 80-PDIT-322 80-PG-317 80-PG-319
LEVEL
80-LIT-304 A/B 80-LIT-305 80-LG-306
CONTROL VALVES
80-FV-303 80-LV-305
SHUTDOWN VALVE
80-ESDV-302 A/B 80-ESDV-304
SAFETY VALVES
80-PSV-318 A/B EQUIPMENT
PAGE 8872 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
DISCHARGE DRUM TRAIN C
WESTERN DESERT EGYPT
QA-V-8002C
C. CHECK FORMS PIPING INSTRUMENTS
X.80.P.015
PI-03-A/ 04-A IC-03-A/ 05-A/ 09-A/ 02-A /06A
INSTRUMENT IC-23-A CABLES VESSEL PV-06-A COMPRESSOR SUCTION DRUM TRAIN-D (QA-V-8001D) SYSTEM A. GENERAL Refer to marked P&ID’s イイ イイ
3538-200-KKD-12241 Rev.04 3538-200-KKD-12242 SH1,Rev.04
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
10000-Z-000-GE1-TMP-0004
(08/13)
TEMPERATURE
PRESSURE
INSTRUMENTS 80-TIT-401 80-TG-405 80-TG-411 80-PDIT-401 80-PDIT-421 80-PG-403 80-PG-406 80-PG-407 80-PG-403 80-PDIT-408 80-PIT-409 80-PIT-410
PAGE 8972 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT
WESTERN DESERT
PRE-COMMISSIONING PROCEDURE
LEVEL
80-LIT-401 80-LIT-402 80-LIT-407 80-LG-403
FLOW
80-FIT-402
CONTROL VALVE
80-LV-402 A/B 80-PV-423
SHUTDOWN VALVE
80-ESDV-401 A/B 80-ESDV-403
SAFETY VALVES
80-PSV-405 A/B
EGYPT
C. CHECK FORMS PIPING INSTRUMENTS
D (QA-
INSTRUMENT CABLES VESSEL A. GENERAL
PI-03-A/ 04-A IC-03-A/ 05-A/ 09-A/ 02-A /06A IC-23-A PV-06-A
X.80.P.016 COMPRESSOR TRAINK-8001D) SYSTEM
10000-Z-000-GE1-TMP-0004
(08/13)
Refer to marked P&ID’s イイ イイ イイ
3538-200-KKD-12242 SH1, Rev.04 3538-200-KKD-12242 SH2, Rev.02 3538-200-KKD-12243, Rev.04 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
PAGE 9072 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
10000-Z-000-GE1-TMP-0004
(08/13)
TEMPERATURE
INSTRUMENTS 80-TIT-402 80-TIT-403 80-TIT-411 80-TIT-410 80-TG-404
PRESSURE
80-PIT-411 80-PIT-412 80-PG-413 80-PG-415 80-PT-5167 TRAIN D
FLOW
80-FT-2108 TRAIN D
RESTRICTED ORFICE
80-RO-401 80-RO-403
LEVEL
80-LG-402 80-LIT-408 80-LIT-409 80-LIT-410
SPEED
80-SIT-401
VIBRATION
80-VIT-401
SHUTDOWN VALVE
80-ESDV-209
CONTROL VALVES
80-LV-408 80-AV-5167
SAFETY VALVES
80-PSV-414 A/B
BLOWDOWN VALVE
80-BDV-401
KPC WESTERN DESERT EGYPT
PAGE 9172 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
EQUIPMENT COMPRESSOR QA-K-8001D TURBINE QA-GTK-8001D COALESCING FILTER F-2100 FILTER F-2106 CO2 EXTINGUISHING AS-6600 / 6601 SEAL GAS TREATMENT SKID LUBE OIL COOLER VENT SEPARATOR F-2370 C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES VESSEL FILTER ELECTRIC HEATER FLAME ARRESTOR CENTRIFUGAL TURBO COMPRESSOR X.80.P.017
PI 03 A/04 A IC-03 A/ 05 A/ 09 A/ 02 A/ 06-A IC-23 A PV-06-A PV-01-A PR-05-A PR-11-A ME-08-A
COMPRESSOR DISCHARE COOLER TRAIN-D (QA-E-8001D) SYSTEM
10000-Z-000-GE1-TMP-0004
(08/13)
D. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12243, Rev.04 イイ 3538-200-KKD-12244, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s. INSTRUMENTS
PAGE 9272 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
TEMPERATURE
80-TG-406 A/B 80-TIT-407 80-TIT-408 A/B/C 80-TIT-413A
CONTROL VALVE
80-FV-404
SWITCH
80-VSHH-402 A/B/C/D
EQUIPMENTS AIR COOLER MOTOR
QA-E-8001D QA-EM-8001 DA/DB/DC/DD
WESTERN DESERT EGYPT
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES AIR COOLER MOTOR
X.80.P.018
PI 03 A/04 A IC-03 A/ 05 A/ 09 A/ 02 A/ IC-23 A PR-18-A EL-22-A
COMPRESSOR DISCHARE DRUM TRAIN-D (QA-V-8002D) SYSTEM
10000-Z-000-GE1-TMP-0004
(08/13)
A. GENERAL イイ
Refer to marked P&ID’s 3538-200-KKD-122244, Rev.04
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
TEMPERATURE
INSTRUMENTS 80-TG-412
PAGE 9372 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
PRESSURE
80-PDG-408 80-PDIT-402 80-PDIT-422 80-PG-417 80-PG-419
LEVEL
80-LIT-404 A/B 80-LIT-405 80-LG-406
CONTROL VALVES
80-FV-403 80-LV-405
SHUTDOWN VALVE
80-ESDV-402 A/B 80-ESDV-404
SAFETY VALVES
80-PSV-418 A/B EQUIPMENT
DISCHARGE DRUM TRAIN D
QA-V-8002D
C. CHECK FORMS PIPING
10000-Z-000-GE1-TMP-0004
(08/13)
INSTRUMENTS INSTRUMENT CABLES VESSEL
X.80.P.019
PI-03-A/ 04-A IC-03-A/ 05-A/ 09-A/ 02-A /06A IC-23-A PV-06-A
CONDENSATE SUCTION MANIFOLD A. GENERAL
KPC WESTERN DESERT EGYPT
PAGE 9472 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
Refer to marked P&ID’s イイ イイ イイ イイ
KPC WESTERN DESERT EGYPT
3538-200-KKD-12215, Rev.4 3538-200-KKD-12250, Rev.5 3538-200-KKD-12254, Rev.5 3538-200-KKD-12353, Rev.4
The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
PRESSURE
SHUTDOWN VALVES
80-ESDV-034A/B 80-ESDV-035A/B
SAFETY VALVES
80-PSV-006A/B 80-PSV-013
C. CHECK FORMS
(08/13) 10000-Z-000-GE1-TMP-0004
INSTRUMENTS 80-PIT-923 80-PIT-924 80-PG-004 80-PG-927 80-PDIT-910 80-PDIT-911
PIPING INSTRUMENTS INSTRUMENT CABLES X.80.P.020
PI-03-A/ 04-A IC-03-A/ 05-A/ 09-A IC-23-A
CONDENSATE SUCTION DRUMS QA-V-8005A SYSTEM
PAGE 9572 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12210, Rev.5 イイ 3538-200-KKD-12215, Rev.4 イイ 3538-200-KKD-12250, Rev.5 イイ 3538-200-KKD-12251, Rev.5 イイ 3538-200-KKD-12254, Rev.5 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
TEMPERATURE PRESSURE
80-PIT-002 A 80-PIT-003 80-PIT-076 A/B/C 80-PG-001 A 80-PG-005 A
RESTRICTION ORIFICE
80-RO-001A
LEVEL
80-LIT-001A 80-LIT-002A/B 80-LIT-016 A 80-LIT-021 A 80-LG-003 A 80-LG-004 A
CONTROL VALVES
80-PV-001 80-PV-003 A 80-LV-016 A
(08/13) 10000-Z-000-GE1-TMP-0004
INSTRUMENTS 80-TIT-001 A
PAGE 9672 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
SHUTDOWN VALVES
BLOWDOWN VALVES
80-ESDV-001A 80-ESDV-009 A 80-ESDV-011 A 80-ESDV-026 A 80-BDV-001 A
SAFETY VALVES
80-PSV-007 A/B
KPC WESTERN DESERT EGYPT
EQUIPMENT CONDENSATE SUCTION DRUM D.
CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES VESSEL
X.80.P.021
QA-V-8005 A
PI-03-A/ 04-A IC-03-A/ 05-A/ 09-A/ 02-A /06A IC-23-A PV-06-A
CONDENSATE SUCTION DRUMS QA-V-8005B SYSTEM A. GENERAL
10000-Z-000-GE1-TMP-0004
(08/13)
Refer to marked P&ID’s イイ 3538-200-KKD-12210, Rev.5 イイ 3538-200-KKD-12215, Rev.4 イイ 3538-200-KKD-12250, Rev.5 イイ 3538-200-KKD-12251, Rev.5 イイ 3538-200-KKD-12254, Rev.5 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
INSTRUMENTS
PAGE 9772 OF 146145
3538-200-10-RT045 MAY 21, 2014
10000-Z-000-GE1-TMP-0004
(08/13)
REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
TEMPERATURE
80-TIT-001 B
PRESSURE
80-PIT-002 B 80-PG-001 B 80-PG-005 B
RESTRICTION ORFICE
80-R0-001 B
LEVEL
80-LIT-001 B 80-LIT-003 B 80-LIT-016 B 80-LIT-021 B 80-LG-003 B 80-LG-004 B
CONTROL VALVES
80-LV-016 B
SHUTDOWN VALVES
80-ESDV-001 B 80-ESDV-009 B 80-ESDV-011 B 80-ESDV-026 B
BLOWDOWN VALVES
80-BDV-001 B
SAFETY VALVES
80-PSV-008 A/B EQUIPMENT
CONDENSATE SUCTION DRUM
QA-V-8005 B
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES
PI-03-A/ 04-A IC-03-A/ 05-A/ 09-A/ 02-A /06A IC-23-A
KPC WESTERN DESERT EGYPT
PAGE 9872 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
PRE-COMMISSIONING PROCEDURE
VESSEL
X.80.P.022
KPC
QASR COMPRESSION PROJECT
WESTERN DESERT EGYPT
PV-06-A
CONDENSATE EXPOET PUMPS QA-P-8003 A/B/C SYSTEM A. GENERAL Refer to marked P&ID’s イイ イイ イイ イイ イイ
3538-200-KKD-12215, Rev.4 3538-200-KKD-12250, Rev.5 3538-200-KKD-12251, Rev.5 3538-200-KKD-12254, Rev.5 3538-200-KKD-12353, Rev.4
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
10000-Z-000-GE1-TMP-0004
(08/13)
PRESSURE
INSTRUMENTS 80-PIT-008A/B/C 80-PIT-012A/B/C 80-PIT-918A/B/C 80-PDIT-009A/B/C 80-PG-011A/B/C 80-PG-928 80-PIT-
TEMPERATURE
80-TIT-016A/B/C
FLOW
80-FIT-001A/B/C 80-FIT-019A/B/C 80-FIT-011A/B
VIBRATION
80-VT-002A/B/C 80-VT-003A/B/C
PAGE 9972 OF 146145
3538-200-10-RT045
QASR COMPRESSION PROJECT
MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
SPEED
80-SIT-002A/B/C
ON-OFF VALVES
80-XV-027A/B/C
SAFETY VALVES
80-PSV-093A/B/C 80-PSV-014
CONTROL VALVES
80-FV-001A/B/C
SHUTDOWN VALVES
80-ESDV-014 80-ESDV-036A 80-ESDV-037A EQUIPMENT CONDENSATE EXPORT QA-P-8003A/B/C PUMPS AUTOMATIC TOP UP UNIT C. CHECK FORMS
10000-Z-000-GE1-TMP-0004
(08/13)
PIPING INSTRUMENTS INSTRUMENT CABLES PUMP VMS PANEL_CABINET_ CONSOL MOTOR
PI 03 A/04 A IC-03 A/ 05 A/ 06 A IC-23 A ME-01 A IC-15 A EL-22 A
4.3 UTILITY SYSTEMS X.80.U.001
AIR GENERATION PACKAGE A QA-K-8002A SYSTEM A.
GENERAL Refer to marked P&ID’s
イイ
3538-200-KKD-12300 SH1, Rev.04
KPC WESTERN DESERT EGYPT
PAGE 10072 OF 146145
3538-200-10-RT045
QASR COMPRESSION PROJECT
MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
KPC WESTERN DESERT EGYPT
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID. EQUIPMENT AIR GENERATION PACKAGE
QA-K-8002A
For I&U Air Compressor (QA-K-8002A) package pre-commissioning procedure and drawings, please refer to supplier final data book X.80.U.002
AIR GENERATION PACKAGE B QA-K-8002B SYSTEM A.
GENERAL Refer to marked P&ID’s
イイ
3538-200-KKD-12300 SH1, Rev.04
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID. EQUIPMENT AIR GENERATION PACKAGE
QA-K-8002B
For I&U Air Compressor (QA-K-8002B) package pre-commissioning procedure and drawings, please refer to supplier final data book
10000-Z-000-GE1-TMP-0004
(08/13)
X.80.U.003
AIR GENERATION PACKAGE C QA-K-8002C SYSTEM A.
GENERAL Refer to marked P&ID’s
イイ
3538-200-KKD-12300 SH1, Rev.04
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
PAGE 10172 OF 146145
3538-200-10-RT045
QASR COMPRESSION PROJECT
MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
KPC WESTERN DESERT EGYPT
EQUIPMENT AIR GENERATION PACKAGE
QA-K-8002C
For I&U Air Compressor (QA-K-8002C) package pre-commissioning procedure and drawings, please refer to supplier final data book
X.80.U.004
AIR DRYER PACKAGE QA-A-8005A SYSTEM A. GENERAL Refer to marked P&ID’s イイ
3538-200-KKD-12300, SH1, Rev.04
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID. EQUIPMENT AIR DRYER PACKAGE 80-A-8005A For Air Dryer (80-A-8005A) package pre-commissioning procedure and drawings, please refer to supplier final data book
10000-Z-000-GE1-TMP-0004
(08/13)
X.80.U.005
AIR DRYER PACKAGE QA-A-8005B SYSTEM A. GENERAL Refer to marked P&ID’s イイ
3538-200-KKD-12300, SH1, Rev.04
E. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
PAGE 10272 OF 146145
3538-200-10-RT045
QASR COMPRESSION PROJECT
MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
KPC WESTERN DESERT EGYPT
EQUIPMENT AIR DRYER PACKAGE 80-A-8005B For Air Dryer (80-A-8005B) package pre-commissioning procedure and drawings, please refer to supplier final data book X.80.U.006
UTILITY AIR RECEIVER QA-V-8009 A. GENERAL Refer to marked P&ID’s イイ
3538-200-KKD-12300, SH1 Rev.04
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
10000-Z-000-GE1-TMP-0004
(08/13)
TEMPERATURE
INSTRUMENTS 80-TIT-025
PRESSURE
80-PG-074 80-PIT-073 80-PIT-075 A/B/C
LEVEL
80-LIT-017 80-LG-018
FLOW
80-FIT-016
Safety Valve
80-PSV-076 A/B
EQUIPMENT UTILITY AIR RECEIVER 80-V-8009 C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A
PAGE 10372 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
PRE-COMMISSIONING PROCEDURE
CABLES VESSEL X.80.U.007
KPC
QASR COMPRESSION PROJECT
WESTERN DESERT EGYPT
PV-06 A
INSTRUMENT AIR RECEIVER QA-V-8010 A. GENERAL イイ イイ
Refer to marked P&ID’s 3538-200-KKD-12300, SH1 Rev.04 3538-200-KKD-12300, SH2 Rev.04 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
10000-Z-000-GE1-TMP-0004
(08/13)
PRESSURE
INSTRUMENTS 80-PG-077 80-PG-080 80-PIT-079 A/B/C 80-PIT-081
LEVEL
80-LG-019
FLOW
80-FIT-018
Safety Valve
80-PSV-082 A/B
EQUIPMENT UTILITY AIR RECEIVER 80-V-8009 C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES VESSEL
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A PV-06 A
PAGE 10472 OF 146145
3538-200-10-RT045 MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
X.80.U.008
KPC
QASR COMPRESSION PROJECT
WESTERN DESERT EGYPT
UTILITY STATION PLANT AIR DISTRIBUTION SYSTEM A. GENERAL イイ イイ
Refer to marked P&ID’s 3267-210-KKD-12300, SH1 Rev.04 3267-210-KKD-12300, SH3 Rev.04 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
PRESSURE SHUTDOWN VALVE
INSTRUMENTS 80-PIT-069 80-ESDV-015
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES
10000-Z-000-GE1-TMP-0004
(08/13)
X.80.U.009
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A
INSTRUMENT AIR DISTRIBUTION SYSTEM A. GENERAL
Refer to marked P&ID’s イイ イイ イイ イイ イイ イイ イイ
3538-200-KKD-12300, SH2 Rev.04 3538-200-KKD-12301, SH1 Rev.04 3538-200-KKD-12301, SH2 Rev.04 3538-200-KKD-12212, SH2 Rev.04 3538-200-KKD-12222, SH2 Rev.04 3538-200-KKD-12232, SH2 Rev.04 3538-200-KKD-12242, SH2 Rev.04
PAGE 10572 OF 146145
3538-200-10-RT045 MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
イイ イイ イイ イイ イイ イイ イイ イイ
KPC
QASR COMPRESSION PROJECT
WESTERN DESERT EGYPT
3538-200-KKD-12357, Rev.04 3538-200-KKD-12213, Rev.04 3538-200-KKD-12223, Rev.04 3538-200-KKD-12233, Rev.04 3538-200-KKD-12243, Rev.04 3538-200-KKD-12251, Rev.05 3538-200-KKD-12320, Rev.02 3538-200-KKD-12364, Rev.04 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
INSTRUMENTS 80-FIT-023
FLOW SHUTDOWN VALVE
80-ESDV-016 80-ESDV-038
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES
10000-Z-000-GE1-TMP-0004
(08/13)
X.80.U.010
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A
NITROGEN GENERATION PACKAGE A. GENERAL イイ
Refer to marked P&ID’s 3538-200-KKD-12301, SH1 Rev.4 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
PAGE 10672 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
EQUIPMENT NITROGEN GENERATION PACKAGE QA-A-8003 For Nitrogen Generation (QA-A-8003) package pre-commissioning procedure and drawings, please refer to supplier final data book X.80.U.011
NITROGEN DISTRIBUTION SYSTEM A. GENERAL イイ イイ イイ イイ イイ イイ イイ イイ
Refer to marked P&ID’s 3538-200-KKD-12301, SH1 Rev.04 3538-200-KKD-12301, SH2 Rev.04 3538-200-KKD-12212, SH2 Rev.02 3538-200-KKD-12222, SH2 Rev.02 3538-200-KKD-12232, SH2 Rev.02 3538-200-KKD-12242, SH2 Rev.02 3538-200-KKD-12310, Rev.04 3538-200-KKD-12311, SH2 Rev.04 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s. INSTRUMENTS 80-TIT-010 80-TIT-013 80-TIT-014 80-TIT-026 80-TG-001
PRESSURE
80-PIT-083 80-PIT-085 A/B/C 80-PIT-086 80-PG-002
FLOW
80-FIT-017 80-FIT-030
10000-Z-000-GE1-TMP-0004
(08/13)
TEMPERATURE
PAGE 10772 OF 146145
3538-200-10-RT045
KPC
QASR COMPRESSION PROJECT
MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
SAFETY VALVE
WESTERN DESERT EGYPT
80-PSV-091 A/B EQUIPMENT QA-E-8007
ELECTRIC HEATER C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES HEATER
X.80.U.012
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A PR-17 A
UTILITY STATION PLANT NITROGEN DISTRIBUTION SYSTEM A. GENERAL Refer to marked P&ID’s イイ イイ
3538-200-KKD-12301, SH2 Rev.04 3538-200-KKD-12301, SH3 Rev.04
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
(08/13)
PRESSURE
10000-Z-000-GE1-TMP-0004
INSTRUMENTS 80-PIT-095
SHUTDOWN VALVE
80-ESDV-024
C. CHECK FORMS PIPING INSTRUMENTS
PI 03 A/04 A IC-03 A/ 05 A/ 09 A
PAGE 10872 OF 146145
3538-200-10-RT045 MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
INSTRUMENT CABLES X.80.U.013
KPC
QASR COMPRESSION PROJECT
WESTERN DESERT EGYPT
IC-23 A
NITROGEN RECIVER, COMPRESSOR AND LETDOWN PACKAGE A. GENERAL Refer to marked P&ID’s イイ
3538-200-KKD-12301, SH2 Rev.04
C. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
PRESSURE
INSTRUMENTS 80-PG-089 80-PIT-087 80-PIT-088
FLOW
80-RO-012
LEVEL
80-LG-020
SAFETY VALVE
80-PSV-090 A/B
BLOWDOWN VALVE
80-BDV-009
10000-Z-000-GE1-TMP-0004
(08/13)
EQUIPMENTS Nitrogen compressor and QA-A-8004 let down package Nitrogen receiver QA-V-8011 C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES VESSEL
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A PV-06 A
PAGE 10972 OF 146145
3538-200-10-RT045
QASR COMPRESSION PROJECT
MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
KPC WESTERN DESERT EGYPT
For compressor and letdown (QA-A-8004) package pre-commissioning procedure and drawings, please refer to supplier final data book X.80.U.014
HP FUEL FLASH GAS PRE-HEATER FEED A. GENERAL Refer to marked P&ID’s イイ
3538-200-KKD-12302, Rev.04
D. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
10000-Z-000-GE1-TMP-0004
(08/13)
TEMPERATURE
INSTRUMENTS 80-TG-006 80-TIT-007 80-TIT-008 A/B
PRESSURE
80-PDIT-028 80-PDIT-030 80-PDIT-032
FLOW
80-FIT-026 A/B 80-FIT-009 80-RO-002 EQUIPMENTS
FLASH GAS PREHEATER
QA-E-8002
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A
PAGE 11072 OF 146145
3538-200-10-RT045
QASR COMPRESSION PROJECT
MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
HEATER
KPC WESTERN DESERT EGYPT
PR-17 A
X.80.U.015
H.P. FUEL GAS SYSTEM
A. GENERAL Refer to marked P&ID’s イイ イイ イイ イイ イイ
3538-200--KKD-12302, Rev.04 3538-200--KKD-12303, SH1 Rev.04 3538-200--KKD-12305, Rev.04 3538-200--KKD-12306, Rev.04 3538-200--KKD-12307, Rev.04
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
TEMPERATURE
PRESSURE
80-PIT-039 80-PIT-044A 80-PIT-044B 80-PIT-043 80-PG-096 80-PG-042 80-PG-046 80-PDIT-919
LEVEL
80-LG-007 80-LIT-006 80-LIT-005 A/B
(08/13) 10000-Z-000-GE1-TMP-0004
INSTRUMENTS 80-TG-012 80-TG-017 80-TIT-018
PAGE 11172 OF 146145
3538-200-10-RT045
QASR COMPRESSION PROJECT
MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
FLOW
80-FIT-004 A/B
CONTROL VALVE
80-LV-006
SHUTDOWN VALVE
80-ESDV-005
SAFETY VALVES
80-PSV-097 A/B 80-PSV-045 A/B
KPC WESTERN DESERT EGYPT
EQUIPMENTS HP FUEL GAS SCRUBBER
QA-V-8006
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES VESSEL X.80.U.016
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A PV-06 A
H.P FUEL GAS PRE-HEATER SYSTEM
10000-Z-000-GE1-TMP-0004
(08/13)
A. GENERAL Refer to marked P&ID’s イイ イイ イイ イイ イイ
3538-200--KKD-12210, Rev.05 3538-200--KKD-12303, SH1 Rev.04 3538-200--KKD-12303, SH2 Rev.04 3538-200--KKD-12354, Rev.04 3538-200--KKD-12368, Rev.04
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
PAGE 11272 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
TEMPERATURE
INSTRUMENTS 80-TG-010A 80-TG-010B 80-TIT-011A 80-TIT-011B 80-TIT-012A 80-TIT-012B 80-TIT-009A 80-TIT-009B 80-PG-36A 80-PG-36B 80-PG-38A 80-PG-38B 80-PDIT-035 80-PDIT-099 80-PDIT-925
FLOW RESTRICTION FLOW
80-FIT-027 A/B 80-RO-004A 80-RO-004B
CONTROL VALVE
80-PV-043 A/B/C/D
SHUTDOWN VALVE
80-ESDV-010 A/B 80-ESDV-028 A/B 80-ESDV-004 A/B
BLOWDOWN VALVE
80-BDV-004A 80-BDV-004B
SAFETY VALVES
80-PSV-037 80-PSV-931
10000-Z-000-GE1-TMP-0004
(08/13)
PRESSURE
KPC WESTERN DESERT EGYPT
PAGE 11372 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
HAND SWITCH
WESTERN DESERT EGYPT
80-HS-009A 80-HS-009B
EQUIPMENTS HP FUEL GAS HEATERS QA-E-8003A/B
C. CHECK FORMS PIPING
PI 03 A/04 A IC-03 A/ 05 A/ 09 A / 02 A / 06 A
INSTRUMENTS INSTRUMENT CABLES HEATER X.80.U.017
IC-23 A PR-17 A
H.P FUEL GAS SUPER HEATER AND CONSUMERS A. GENERAL イイ
Refer to Layout 3538-200-KKD-0307, SH1 Rev.04 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
10000-Z-000-GE1-TMP-0004
(08/13)
TEMPERATURE
INSTRUMENTS 80-TG-021A 80-TG-021B 80-TIT-022A 80-TIT-022B 80-TIT-020B 80-TIT-034B 80-TIT-019A 80-TIT-019B
PAGE 11472 OF 146145
3538-200-10-RT045
KPC
QASR COMPRESSION PROJECT
MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
PRESSURE
80-PG-047A 80-PG-047B
SHUTDOWN VALVE
80-ESDV-007
SAFETY VALVES
80-PSV-048A 80-PSV-048B
WESTERN DESERT EGYPT
EQUIPMENTS HP FUEL GAS SUPERHEATERS
QA-E-8005A/B
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES HEATER
X.80.U.018
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A PR-17 A
H.P FUEL GAS FILTERS A. GENERAL
10000-Z-000-GE1-TMP-0004
(08/13)
Refer to Layout イイ イイ イイ イイ
3538-200-KKD-12308, SH1 REV.04 3538-200-KKD-12308, SH2 REV.04 3538-200-KKD-12354, REV.04 3538-200-KKD-12368, REV.04 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID. INSTRUMENTS
PAGE 11572 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
PRE-COMMISSIONING PROCEDURE
TEMPERATURE
80-TG-021A 80-TG-021B 80-TG-109 TRAIN A/B/C/D 80-TIT-022A 80-TIT-022B 80-TIT-020B 80-TIT-034B 80-TIT-019A 80-TIT-019B
PRESSURE
80-PG-051A 80-PG-051B 80-PG-116 TRAIN A/B/C/D 80-PDIT-049 80-PDIT-063A 80-PDIT-063B 80-PIT-052 80-PIT-067 A/B/C 80-PIT-904
RESTRICTION FLOW
80-RO-006
CONTROL VALVE
80-PV-904 80-PV-052
PRESSURE REGULATOR VALVE
WESTERN DESERT
80-PV-101 PV-201-80 PV-301-80 PV-401-80
(08/13) 10000-Z-000-GE1-TMP-0004
KPC
QASR COMPRESSION PROJECT
SHUTDOWN VALVE
80-ESDV-007
BLOWDOWN VALVE
80-BDV-006
EGYPT
PAGE 11672 OF 146145
3538-200-10-RT045
KPC
QASR COMPRESSION PROJECT
MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
SAFETY VALVES
WESTERN DESERT EGYPT
80-PSV-050A 80-PSV-050B 80-PSV-101 TRAIN A/B/C/D
EQUIPMENTS HP FUEL GAS FILTERS QA-S-8001A/B C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES FILTERS X.80.U.019
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A PV-01 A
L.P FUEL GAS BACK-UP HEATER A. GENERAL Refer to Layout イイ イイ
3538-200-KKD-12308, SH1 REV.04 3538-200-KKD-12308, SH2 REV.04
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK
10000-Z-000-GE1-TMP-0004
(08/13)
Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
TEMPERATURE
INSTRUMENTS 80-TG-038 80-TG-023 80-TIT-015 80-TIT-035 80-TIT-036 80-TIT-037
PAGE 11772 OF 146145
3538-200-10-RT045
QASR COMPRESSION PROJECT
MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
PRESSURE
80-PG-056 80-PG-621 80-PIT-053A
FLOW
80-FIT-007 80-FIT-028A/B
CONTROL VALVE
80-PV-054A 80-PV-054B
SHUTDOWN VALVE
80-ESDV-025 80-ESDV-040
SAFETY VALVES
80-PSV-914 A/B 80-PSV-055 A/B
EQUIPMENTS L.P FUEL GAS HEATER QA-E-8006
C. CHECK FORMS
10000-Z-000-GE1-TMP-0004
(08/13)
PIPING INSTRUMENTS INSTRUMENT CABLES HEATER X.80.U.020
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A PR-17 A
L.P FUEL GAS SCRUBBER A. GENERAL Refer to Layout イイ イイ イイ
3538-200-KKD-12308, SH2 REV.04 3538-200-KKD-12309, REV.04 3538-200-KKD-12355, REV.04
KPC WESTERN DESERT EGYPT
PAGE 11872 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID.
C.
FLARE L.P VENT
12309,
(08/13)
12357,
10000-Z-000-GE1-TMP-0004
12310,
12369,
TEMPERATURE
INSTRUMENTS 80-TIT-029
PIPING PRESSURE INSTRUMENTS INSTRUMENT CABLES VESSEL
80-PG-933PI 03 A/04 A A/ 05 A/ 09 A 80-PIT-053IC-03 A/B/C 80-PIT-054IC-23 A
FLOW
80-FIT-005
LEVEL
80-LG-010 80-LIT-008 A/B 80-LIT-009
80-PDIT-922 PV-06 A
CONTROL VALVE
80-LV-009
SHUTDOWN VALVE
80-ESDV-006
SAFETY VALVES
80-PSV-932 A/B EQUIPMENTS
L.P FUEL GAS SCRUBBER
CHECK FORMS
QA-V-8007
X.80.U.021 H.P COLLECTION AND SOURCE TO COLD A. GENERAL Refer to Layout イイ 3538-200-KKDREV.04 イイ 3538-200-KKDREV.04 イイ 3538-200-KKDREV.04 イイ 3538-200-KKDREV.04
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK
PAGE 11972 OF 146145
3538-200-10-RT045
KPC
QASR COMPRESSION PROJECT
MAY 21, 2014
PRE-COMMISSIONING PROCEDURE
REV.1
WESTERN DESERT EGYPT
Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID. C. CHECK FORMS PIPING
X.80.U.022
PI 03 A/04 A
CLOSED DRAIN COLLECTION A. GENERAL Refer to Layout イイ イイ
3538-200-KKD-12311, SH1 REV.04 3538-200-KKD-12311, SH2 REV.04 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID check on the total system to ensure that the installation is correct as per above mentioned P&ID. C. CHECK FORMS PIPING
10000-Z-000-GE1-TMP-0004
(08/13)
X.80.U.023
PI 03 A/04 A
CLOSED DRAIN DRUM A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12311, SH2 Rev.4 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
PAGE 12072 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
PRESSURE
KPC WESTERN DESERT EGYPT
INSTRUMENTS 80-PIT80-PIT80-PG-057
LEVEL
80-LIT-011A/B 80-LIT-012 80-LG-013
PRESSURE REGULATOR VALVE
80-PCV-094
EQUIPMENT CLOSED DRAIN DRUM QA-V-8008 C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES VESSEL X.80.U.024
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A PV-06 A
CLOSED DRAIN DRUM PUMPS
10000-Z-000-GE1-TMP-0004
(08/13)
A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12311, SH2 Rev.04 イイ 3538-200-KKD-12212, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
PAGE 12172 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
PRESSURE
KPC WESTERN DESERT EGYPT
INSTRUMENTS 80-PIT-063 80-PG-058A 80-PG-058B
EQUIPMENT CLOSED DRAIN DRUM QA-P-8006 A/B PUMP C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES PUMP X.80.U.025
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A ME-01 A
CLOSED DRAIN TRANSFER PUMPS A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12311, SH2 Rev.04 イイ 3538-200-KKD-12212, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK
10000-Z-000-GE1-TMP-0004
(08/13)
Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
PRESSURE
INSTRUMENTS 80-PDIT-065A 80-PDIT-065B 80-PIT-066A 80-PIT-066B 80-PIT-068A 80-PIT-068B
PAGE 12272 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
80-PIT-929A 80-PIT-929B 80-PG-067A 80-PG-067B FLOW
80-FIT-020A 80-FIT-020B 80-FIT-029A 80-FIT-029B 80-FIT-010
ON OFF VALVES
80-XV-031A 80-XV-031B
SHUTDOWN VALVE
80-ESDV-008
SAFETY VALVES
80-PSV-930A 80-PSV-930B
EQUIPMENT CLOSED DRAIN DRUM QA-9-8007 A/B PUMP C. CHECK FORMS
10000-Z-000-GE1-TMP-0004
(08/13)
PIPING INSTRUMENTS INSTRUMENT CABLES PUMPS X.80.U.026
PI 03 A/04 A IC-03 A/ 05 A/ 09 A IC-23 A ME-01 A
NEW EMERGYNCY DEISEL GENERATOR A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12314, Rev.03
KPC WESTERN DESERT EGYPT
PAGE 12372 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s. EQUIPMENT EMERGYNCY DEISEL QA-G-8002 GENERATOR For Emergency Diesel Generator (QA-G-8002) package pre-commissioning procedure and drawings, please refer to supplier final data book X.80.U.027
POTABLE WATER AND DISTRIBUTION SYSTEM A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12315, Rev.03 イイ 3538-200-KKD-12316, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
10000-Z-000-GE1-TMP-0004
(08/13)
PRESSURE
INSTRUMENTS 80-PS-001 80-PSLL-001 80-PSHH-001 80-PI 80-PDG-019 80-PDG-020 80-PG-012A 80-PG-012B 80-PG-012C 80-PG-012D
PAGE 12472 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
LEVEL
80-LSH-001 80-LSL-001 80-LSH-002 80-LSL-002
ANALYZER
80-AI-001
WESTERN DESERT
EQUIPMENT POTABLE WATER UNLOADING PUMPS POTABLE WATER FEED PUMPS POTABLE WATER TANKS POTABLE WATER FILTERS POTABLE WATER PRESSURE VESSEL
QA-P-8008 A/B QA-P-8009 A/B QA-T-8001 A/B QA-S-8002 A/B QA-V-8013
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES CENTRIFUGAL PUMPS TANK
10000-Z-000-GE1-TMP-0004
(08/13)
FILTER X.80.U.028
PI 03 A/04 A IC-02 A/05 A/06 A/09 A/18 A IC-23 A ME-01 A PV-04 A PV 01-A
POTABLE WATER SODIUM HYPOCHLORITE INJECTION PACKAGE A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12315, Rev.03 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK
EGYPT
PAGE 12572 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
WESTERN DESERT EGYPT
Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s. EQUIPMENT SODIUM HYPOCHLORITE INJECTION PACKAGE
QA-A-8006
For Sodium Hypochlorite Injection (QA-A-8006) package pre-commissioning procedure and drawings, please refer to supplier final data book X.80.U.029
SANITARY SEWAGE LIFTING PUMP AND COLLECTION SUMP A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12317, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
PRESSURE
INSTRUMENTS 80-PG-017 80-PG-018
10000-Z-000-GE1-TMP-0004
(08/13)
LEVEL
80-LIT-007 80-LIT-018 EQUIPMENT
SANITRAY SEWAGE LIFTING PUMP SANITRAY SEWAGE COLLECTION SUMP C. CHECK FORMS
QA-P-8010 A/B QA-P-8009 A/B
PAGE 12672 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
PIPING
WESTERN DESERT EGYPT
PI 03 A/04 A IC-02 A/05 A/06 A/09 A/18 A
INSTRUMENTS INSTRUMENT CABLES PUMP X.80.U.030
KPC
IC-23 A ME-01 A
SANITARY SEWAGE TREATMENT PACKAGE A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12317, Rev.04 イイ 3538-200-KKD-12318, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s. EQUIPMENT SANITARY SEWAGE TREATMENT PACKAGE
QA-A-8007
For sanitary sewage treatment (QA-A-8007) package pre-commissioning procedure and drawings, please refer to supplier final data book X.80.U.031
TREATED SANITARY WATER
10000-Z-000-GE1-TMP-0004
(08/13)
A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12318, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
PAGE 12772 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
KPC
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
PRESSURE
WESTERN DESERT
INSTRUMENTS 80-PG-015 80-PG-016
LEVEL
80-LIT-013 80-LIT-019 EQUIPMENT
TREATED SANITRAY WATER PUMP TREATED SANITRAY WATER SUMP SLUDGE DRYING PIT
QA-P-8011 A/B QA-S-8011 A/B QA-S-8011
C. CHECK FORMS PIPING
PI 03 A/04 A IC-02 A/05 A/06 A/09 A/18 A
INSTRUMENTS INSTRUMENT CABLES PUMP X.80.U.032
IC-23 A ME-01 A
FIREWATER SODIUM HYPOCHLORITE INJECTION PACKAGE A. GENERAL
10000-Z-000-GE1-TMP-0004
(08/13)
Refer to marked P&ID’s イイ 3538-200-KKD-12320, Rev.02 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK
EQUIPMENT SODIUM HYPOCHLORITE INJECTION PACKAGE
QA-A-8008
EGYPT
PAGE 12872 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
For Sodium Hypochlorite Injection (QA-A-8008) package pre-commissioning procedure and drawings, please refer to supplier final data book X.80.U.033
FIREWATER STORAGE TANK A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12320, Rev.02 イイ 3538-200-KKD-12321, Rev.02 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
10000-Z-000-GE1-TMP-0004
(08/13)
LEVEL
INSTRUMENTS 80-LIT-010 80-LG-030
PRESSURE
80-PG-010
CONTROL VALVE
80-LV-010
EQUIPMENT FIRE WATER STORAGE QA-T-8003 TANK C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES
PI 03 A/04 A IC-02 A/05 A/ 09 A IC-23 A
PAGE 12972 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
TANKS X.80.U.034
KPC WESTERN DESERT EGYPT
PV-04 A
FIREWATER JOCKRY PUMPS A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12320, Rev.02 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
PRESSURE
INSTRUMENTS 80-PG-016A 80-PG-016B 80-PG-017A 80-PG-017B 80-PSHL-001A 80-PSHL-001B 80-PIT-010 80-PG-012 80-PCV-095
SAFETY VALVE
80-CRV-001A 80-CRV-001B
10000-Z-000-GE1-TMP-0004
(08/13)
PRESSURE REGULATOR VALVE
EQUIPMENT FIREWATER JOCKEY PUMPS
QA-P-8012 A/B
C. CHECK FORMS PIPING
PI 03 A/04 A
PAGE 13072 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
INSTRUMENTS INSTRUMENT CABLES PUMPS X.80.U.035
KPC WESTERN DESERT EGYPT
IC-02 A/05 A/ 09 A IC-23 A ME-07 A
FIREWATER DEISEL TANKS AND PUMPS A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12320, Rev.02 イイ 3538-200-KKD-12321, Rev.02 The pre-commissioning shall be performed including the following:
B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
10000-Z-000-GE1-TMP-0004
(08/13)
PRESSURE
INSTRUMENTS 80-PG-013A 80-PG-013B 80-PG-014A 80-PG-014B 80-PG-015 80-PSL-002A 80-PSL-002B
TEMPERATURE
80-TG-039 80-TG-040
LEVEL
80-LT-100A 80-LT-100B 80-LSHL-001A 80-LSHL-001B
PAGE 13172 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
80-LG-100A 80-LG-100B FLOW
80-FG-001A 80-FG-001B 80-FG-002 80-FI-049 80-FI-050
SAFETY VALVE
80-RV-001A 80-RV-001B EQUIPMENT
FIREWATER DEISEL PUMPS DEISEL FUEL DAY TANKS
QA-P-8013 A/B QA-T-8005 A/B
C. CHECK FORMS
10000-Z-000-GE1-TMP-0004
(08/13)
X.80.U.036
PIPING INSTRUMENTS INSTRUMENT CABLES PUMPS
PI 03 A/04 A IC-02 A/05 A/ 09 A
TANKS
PV-04 A
IC-23 A ME-05 A
FIREWATER NETWORK & EQUIBMENT A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12322, Rev.01 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
PAGE 13272 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES FIRE WATER HYDRANT HOSE HOUSE WATER MONITOR X.80.U.037
PI 03 A/04 A IC-03 A/05 A09 A IC-23 A LP-01 A LP-02 A LP-03 A
PHASE I CLOSED DRAIN DRUM PUMP A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12372, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
PRESSURE
INSTRUMENTS 80-PG-097
(08/13)
EQUIPMENT CLOSED DRAIN DRUM QA-P-3016 PUMP
10000-Z-000-GE1-TMP-0004
C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES PUMPS X.80.U.038
PI 03 A/04 A IC-02 A/05 A/ 09 A IC-23 A ME-01 A
PHASE II CLOSED DRAIN DRUM PUMP
PAGE 13372 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
KPC WESTERN DESERT EGYPT
A. GENERAL Refer to marked P&ID’s イイ 3538-200-KKD-12373, Rev.04 The pre-commissioning shall be performed including the following: B. P&ID’S MECHANICAL CHECK Make complete P&ID’s check on the total system to ensure that the installation is correct as per above mentioned P&ID’s.
PRESSURE
INSTRUMENTS 80-PG-098
EQUIPMENT CLOSED DRAIN DRUM QA-P-4016 PUMP C. CHECK FORMS PIPING INSTRUMENTS INSTRUMENT CABLES PUMPS X.80.U.039
PI 03 A/04 A IC-02 A/05 A/ 09 A IC-23 A ME-01 A
HVAC SYSTEM
10000-Z-000-GE1-TMP-0004
(08/13)
A. Check Forms PIPING INSTRUMENTS INSTRUMENT CABLES AIR HANDLING UNIT CONDENSING UNIT VENTILATION FANS PACKAGED WATER COOLED CHILLERS
PI 03 A/04 A IC-02 A/05 A/06 A/09 A IC-23 A HV-01 A HV-02 A HV-05 A HV-06 A
PAGE 13472 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
PUMPS FOR HVAC PIPING SYSTEM FOR HVAC EXPANSION AND COMPRESSION TANKS DAMPERS DUCTWORKS AIR OUTLETS FAN COIL UNITS
X.80.U.040
HV-09 A HV-10 A HV-11 A HV-12 A HV-13 A HV-14 A HV-16 A
GASEOUS EXTINGUISHING SYSTEM A. Check Forms GASEOUS EXTINGUISHING SYSTEM
X.80.U.041
LP-05-A
CATHODIC PROTECTION SYSTEM A. Check Forms
CATHODIC PROTECTION
10000-Z-000-GE1-TMP-0004
(08/13)
X-80.U.042
CP-01 A
Power Transformer A. Check Forms
POWER TRANSFORMERS
X-80.U.043
EL-02 A
0.4 KV L.V SWG & Motor Control Center A. Check Forms
KPC WESTERN DESERT EGYPT
PAGE 13572 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
LV SWITCHGEAR AND MOTOR CONTROL CENTER X-80.U.044
EL-04 A
Neutral Grounding Resistor A. Check Forms
Neutral Grounding Resistor X-80.U.045
EL-09 A
Small Power Distribution Panel A. Check Forms
Small Power Distribution Panel
X-80.U.046
EL-13 A
LTG And Small Power System A. Check Forms
LIGHTING AND SMALL POWER MATERIAL X-80.U.047
EL-23 A
Raceways And Supports
10000-Z-000-GE1-TMP-0004
(08/13)
A. Check Forms
RACEWAYS AND SUPPORTS X-80.U.48
EL-27 A
Grounding A. Check Forms
Grounding X-80.U.049
Battery And Battery Charger Assemblies
EL-33 A
KPC WESTERN DESERT EGYPT
PAGE 13672 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
A. Check Forms
BATTERY & CHARGER ASSEMBLIES X-80.U.050
EL-08A
Uninterruptible Power Supply UPS System A. Check Forms
AC UNINTERRUPTABLE POWER SUPPLY X-80.U.051
EL-12A
Lightening System A. Check Forms
LIGHTNING PROTECTION SYSTEM
X-80.U.052
EL-37A
MV Switchgear and Motor Control Gear A. Check Forms
MV SWITCHGEAR AND MOTOR CONTROL GEAR X-80.U.053
EL-03A
LV Bus Bar Trunking
10000-Z-000-GE1-TMP-0004
(08/13)
A. Check Forms
BUS BAR TRUNKING SYSTEM X-80.U.054
EL-07A
MV Bus Bar Trunking A. Check Forms
BUS BAR TRUNKING SYSTEM
EL-07A
KPC WESTERN DESERT EGYPT
PAGE 13772 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
X-80.U.055
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
Power factor Equipment A. Check Forms
POWER FACTOR IMPROVEMENT EQUIPMENT X-80.U.056
EL-21A
Variable speed drive A. Check Forms
VARIABLE SPEED DRIVE
X-80.U.057
EL-19 A
Supervisory Digital Control System (SDCS) A. Check Forms SUPERVISORY CONTROL AND DATA ACQUISITION SYSTEM
X-80.U.058
11 kV High Voltage Switchgear A. Check Forms
(08/13) 10000-Z-000-GE1-TMP-0004
EL-26 A
MV SWITCHGEAR AND MOTOR CONTROL GEAR X-80.U.059
ESD SYSTEM A. Check Forms
ESD Panel_Cabinet_Console
IC-11 A
EL-03A
KPC WESTERN DESERT EGYPT
PAGE 13872 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
Junction Box Instrument Cables above Ground X-80.U.060
IC-04 A IC-23 A
DCS SYSTEM AND MAIN CABLES B. Check Forms
DCS Panel_Cabinet_Console Junction Box Instrument Cables above Ground X-80.U.061
IC-10 A IC-04 A IC-23 A
VIBRATION MONITORING SYSTEM (VMS) A. Check Forms VMS PANEL _CABINET_CONSOLE
X.80.U.062
IC-15 A
F&G SYSTEM & MAIN CABLES A. Check Forms
10000-Z-000-GE1-TMP-0004
(08/13)
FIRE AND GAS SYSTEM FIRE AND GAS CABLE FIRE AND GAS JUNCTION BOX DETECTOR CONDUIT
X.80.U.063
PAGE / PARTY SYSTEM A. Check Forms
LP-10A LP-11A LP-12A LP-13A LP-14A
KPC WESTERN DESERT EGYPT
PAGE 13972 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
PRE-COMMISSIONING PROCEDURE
PUBLIC ADDRESS& GENERAL ALARM TELECOMMUNICATION CABLES TELECOMMUNICATION CABLE TRAYS DATA COMMUNICATION SYSTEM
X.80.U.064
WESTERN DESERT
TE-02 A TE-07 A TE-08 A TE-09 A
PRIVET AUTOMATIC BRANCH EXCHANGE SYSTEM (PABX) A. Check Forms
(08/13)
PRIVET AUTOMATIC BRANCH EXCHANGE SYSTEM (PABX) TELECOMMUNICATION CABLES TELECOMMUNICATION CABLE TRAYS DATA COMMUNICATION SYSTEM
10000-Z-000-GE1-TMP-0004
KPC
QASR COMPRESSION PROJECT
15.0 ATTACHMENTS
TE-01 A TE-07 A TE-08 A TE-09 A
EGYPT
PAGE 14072 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
ATTACHMENT (1)
10000-Z-000-GE1-TMP-0004
(08/13)
Marked Up P&ID’s
KPC WESTERN DESERT EGYPT
PAGE 14172 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
ATTACHMENT (2)
10000-Z-000-GE1-TMP-0004
(08/13)
Pre-Commissioning Check Forms
KPC WESTERN DESERT EGYPT
PAGE 14272 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
ATTACHMENT (3)
10000-Z-000-GE1-TMP-0004
(08/13)
Punch List Form
KPC WESTERN DESERT EGYPT
PAGE 14372 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
ATTACHMENT (4)
10000-Z-000-GE1-TMP-0004
(08/13)
Mechanical Completion Certificate
KPC WESTERN DESERT EGYPT
PAGE 14472 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
ATTACHMENT 5
10000-Z-000-GE1-TMP-0004
(08/13)
CALIBRATION CERTIFICATE
KPC WESTERN DESERT EGYPT
PAGE 14572 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
ATTACHMENT 6
10000-Z-000-GE1-TMP-0004
(08/13)
LOOP CHECK SHEET
KPC WESTERN DESERT EGYPT
PAGE 14672 OF 146145
3538-200-10-RT045 MAY 21, 2014 REV.1
QASR COMPRESSION PROJECT PRE-COMMISSIONING PROCEDURE
ATTACHMENT 7
10000-Z-000-GE1-TMP-0004
(08/13)
TUBING TEST CERTIFICATE