32-SAMSS-004 DATED JAN 15-2012

Share Embed Donate


Short Description

hjhbn...

Description

Materials System Specification 32-SAMSS-004

15 January 2012

Manufacture of Pressure Vessels Document Responsibility: Vessels Standards Committee

Saudi Aramco DeskTop Standards Table of Contents 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Scope............................................................ 2 Conflicts and Deviations................................ 3 References.................................................... 3 Definitions...................................................... 6 Responsibilities............................................. 8 Proposals...................................................... 8 Mechanical Design........................................ 8 Nozzles and Manways................................ 16 Internals....................................................... 19 Vessel Support............................................ 20 Clips and Attachments................................ 23 Materials...................................................... 24 Fabrication................................................... 30 Nondestructive Examination........................ 37 Postweld Heat Treatment............................ 42 Examination, Inspection, Pressure Tests and Repairs................ 43 Nameplates and Stampings........................ 47 Coatings and Painting................................. 48 Shipping Requirements............................... 48 Drawings, Calculations and Data................ 52

Table 1 – Nondestructive Examination Requirements…………………..………. 54

Previous Issue: 13 December 2011 Next Planned Update: 23 February 2016 Revised paragraphs are indicated in the right margin Primary contact: Naffaa, Mahmoud Youniss on 966-3-8809614 Copyright©Saudi Aramco 2012. All rights reserved.

Page 1 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

1

32-SAMSS-004 Manufacture of Pressure Vessels

Scope 1.1

This specification covers the minimum mandatory requirements for the manufacture of pressure vessels (referred to hereinafter also as vessels). The requirements are in addition to and supplement the requirements of the ASME Boiler and Pressure Vessel Codes.

1.2

Vessels under the scope of this specification are purchased on a stand-alone basis or as an integral part of a skid-mounted packaged equipment unit. Note:

1.3

This is applicable irrespective of the party responsible for placing the relevant purchase order (Saudi Aramco facility, LSTK contractor, sub-contractor, etc.).

This specification does not cover the following: 1)

“UM” stamped pressure vessels per ASME SEC VIII D1.

2)

In-service pressure vessels.

3)

Devices used as an integral part of piping systems, made of what are recognized as piping components (piping, fittings, etc.) and serve purposes such as straining, filtering, mixing, separating, distributing, metering and controlling flow.

4)

Pressure vessels used as part of heating, ventilation and air conditioning (HVAC) systems.

5)

Compressed gas cylinders.

1.4

Pressure vessels under scope of this specification, having partial or complete cladding, shall also conform to 32-SAMSS-031 in addition to the requirements of this specification.

1.5

Low alloy steels for vessels intended for services within the scope of API RP 934-A, API RP 934-C or API RP 934-E, shall meet all requirements of the respective document of the aforementioned documents and this specification.

1.6

1 Cr- ½ Mo and 1 ¼ Cr- ½ Mo steels used for vessels not in hydrogen service with design temperature below 440°C, shall meet all requirements of API RP 934-C and this specification.

1.7

Where a requirement of a licensor’s or a relevant industry standard/specification is more stringent than that of this specification, the most stringent requirement will govern.

1.8

A vessel that is an integral part of a skid-mounted packaged equipment unit shall be designed and manufactured by a manufacturer of such unit per the relevant SAP database. Page 2 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

2

3

32-SAMSS-004 Manufacture of Pressure Vessels

Conflicts and Deviations 2.1

Any conflicts between this Specification and other applicable Saudi Aramco Materials System Specifications (SAMSSs), Standard Drawings (SASDs), or industry standards, codes, and forms shall be in writing by the Company or Buyer Representative through the Manager, Consulting Services Department of Saudi Aramco, Dhahran.

2.2

Direct all requests to deviate from this specification in writing to the Company or Buyer Representative, who shall follow internal company procedure SAEP-302 and forward such requests to the Manager, Consulting Services Department of Saudi Aramco, Dhahran.

References Materials or equipment supplied to this specification shall comply with the latest edition of the references listed below, unless otherwise noted. 3.1

Saudi Aramco References Saudi Aramco Engineering Procedures SAEP-302

Instructions for Obtaining a Waiver of a Mandatory Saudi Aramco Engineering Requirement

SAEP-347

Supplying Material from Stockists

Saudi Aramco Materials System Specifications 01-SAMSS-016

Qualification of Storage Tanks and Pressured Equipment for Resistance to Hydrogen-Induced Cracking

32-SAMSS-020

Manufacture of Trays and Packing

32-SAMSS-031

Manufacture of Clad Vessels and Heat Exchangers

32-SAMSS-036

Manufacture of Small Pressure Vessels

Saudi Aramco Engineering Standards SAES-A-007

Hydrostatic Testing Fluids and Lay-Up Procedures

SAES-A-112

Meteorological and Seismic Design Data

SAES-A-206

Positive Materials Identification

SAES-H-100

Coating Materials and Application

SAES-L-133

Corrosion Protection Requirements for Pipelines, Piping and Process Equipment Page 3 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

SAES-M-001

Structural Design Criteria for Non-Building Structures

SAES-N-001

Industrial Insulation

SAES-W-010

Welding Requirements for Pressure Vessels

Saudi Aramco Standard Drawing AA-036322

Anchor Bolt Details

Saudi Aramco Inspection Requirements Form 175-321900

Manufacture of Pressure Vessels

Saudi Aramco Forms and Data Sheets

3.2

NMR-7919-1

Nonmaterial Requirements for Pressure Vessels

9527-ENG

Pressure Vessel Data Sheet (herein referred to as data sheet)

Industry Codes and Standards American Institute of Steel Construction AISC M011

Manual of Steel Construction

American Petroleum Institute API RP 520

Part I - Sizing, Selection, and Installation of Pressure Relieving Devices in Refineries

API RP 582

Recommended Practice and Supplementary Welding Guidelines for the Chemical, Oil, and Gas Industries

API RP 934-A

Materials and Fabrication of 2 ¼Cr-1Mo, 2 ¼Cr1Mo-¼V, 3Cr-1Mo, and 3Cr-1Mo- ¼V Steel Heavy Wall Pressure Vessels for Hightemperature, High-pressure Hydrogen Service

API RP 934-C

Materials and Fabrication of 1 ¼ Cr-½ Mo Steel Heavy Wall Pressure Vessels for High-pressure Hydrogen Service Operating at or Below 825°F (440°C)

API RP 934-E

Materials and Fabrication of 1 ¼ Cr-½ Mo Steel Pressure Vessels for Service above 825°F (440°C)

Page 4 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

American Society of Civil Engineers ASCE 7

Minimum Design Loads for Buildings and Other Structures

American Society of Mechanical Engineers (Boiler and Pressure Vessel Codes) ASME SA-20

Specification for General Requirements for Steel Plates for pressure Vessels

ASME SA-388

Ultrasonic Examination of Heavy Steel Forgings

ASME SA-578

Specification for Straight-Beam Ultrasonic Examination of Rolled Steel Plates for Special Applications

ASME SEC V

Nondestructive Examination

ASME SEC VIII D1

Rules for Construction of Pressure Vessels

ASME SEC VIII D2

Rules for Construction of Pressure Vessels, Alternative Rules

ASME B16.5

Pipe Flanges and Flanged Fittings NPS ½ through NPS 24

ASME B16.25

Butt-welding Ends

ASME B16.47

Large Diameter Steel Flanges NPS 26 through NPS 60

ASME PCC-1

Guidelines for Pressure Boundary Bolted Flange Joint Assembly

American Society for Testing and Materials ASTM A380

Practice of Cleaning, Discleaning and Passivation of Stainless Steel Part Equipment and System

ASTM E381

Standard Method of Macrotech Testing Steel Bars, Billets, Blooms, and Forgings American Society for Nondestructive Testing

American Society for Non-destructive Testing ASNT CP-189

Standard for Qualification and Certification of Nondestructive Testing Personnel

International Standards Organization ISO 15156

Petroleum and Natural Gas Industries - Materials for Use in H2S Containing Environments in Oil and Gas Production Page 5 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

National Association of Corrosion Engineers NACE RP0472

Methods of Control to Prevent In-Service Cracking of Carbon Steel Welds in P-1 Materials in Corrosive Petrochemical Refining Environments

NACE RP0590

Recommended Practice for Prevention, Detection and Correction of Deaerator Cracking

NACE TM0208

Laboratory Test to Evaluate the Vapor-Inhibiting Ability of Volatile Corrosion Inhibitor Materials for Temporary Protection of Ferrous Metal Surfaces

Process Industry Practices VEFV1100

Vessel/S&T Heat Exchanger Standard Details

Welding Research Council

4

WRC 107

Welding Research Council Bulletin

WRC 297

Welding Research Council Bulletin

Definitions AARH: Average arithmetic roughness height, which is a measure of surface texture. Cyclic Service: Services that require fatigue analysis according to screening criteria per 5.5.2 of ASME SEC VIII D2. This applies to Division 1 and Division 2 of ASME SEC VIII. Design Engineer: The Engineering Company responsible for specifying on the data sheet the mechanical design requirements for pressure vessels. Design Thickness: Sum of thickness required to withstand all primary loads and an allowance for corrosion. High - Alloy Steels: Steels with a total alloying content more than 5%. Hot Forming: Forming operations carried out at an elevated temperature such that recrystallization occurs simultaneously with deformation. Hydrogen Induced Cracking (HIC) Environment: Process streams that introduce HIC according to SAES-L-133. Hydrogen Service: Process streams containing relatively pure hydrogen and process streams containing hydrogen as a component with an absolute partial pressure of 350 kPa (50 psi) and higher. Page 6 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

Lethal Services: Process streams containing a concentration of hydrogen sulfide in excess of 20% volume per total volume of vessel shall be considered as lethal service. Other services as determined by the project design may also be designated as lethal services. Low - Alloy Steels: Steels with a total alloying content of less than 5% but more than specified for carbon steels. MDMT: Minimum design metal temperature determined by the Design Engineer and specified in the data sheet. Nominal Thickness: Thickness selected as commercially available, and supplied to the Manufacturer. For plate material, the nominal thickness is the measured thickness of the plate at the joint or location under consideration after forming. Pressure Vessel and Vessel: As defined in the ASME Boiler and Pressure Vessel Codes. Saudi Aramco Buyer: The person or company authorized by Saudi Aramco to procure pressure vessels to the requirements of this specification. Saudi Aramco Engineer: The chairman of the Vessels Standards Committee. Saudi Aramco Inspector: The person or company authorized by the Saudi Aramco Inspection Department to inspect pressure vessels to the requirements of this specification. Skid-mounted packaged equipment unit: Self-contained units for process and utility applications (e.g., air dryers, portable air compressors, filtering unit, nitrogen generation, dehydration, etc.) fabricated and skid-mounted in one section. Such unit consists of equipment (pressure vessels, compressors, pumps, storage tank, etc.), interconnecting piping, electrical and/ or instrument components, and support structures. Sulfide Stress Cracking (SSC) Environment: Process streams that introduce SSC according to SAES-L-133. Thick Wall: Nominal thickness of a pressure-retaining vessel’s component (shell, head, nozzle, etc.) greater than 50 mm. Unfired Steam Drums: As defined in ASME SEC VIII D1, paragraph U-1 (g) (2). Utility Services: Water, air and nitrogen services. Vessel Manufacturer: The Company responsible for the manufacture of new pressure vessels in accordance with this specification. Page 7 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

5

32-SAMSS-004 Manufacture of Pressure Vessels

Responsibilities The Vessel Manufacturer is responsible for the manufacture of pressure vessels, which includes complete mechanical design, Code and structural calculations, supply of all materials, fabrication, nondestructive examination, inspection, testing, surface preparation, and preparation for shipment in accordance with the completed data sheet and the requirements of this specification.

6

7

Proposals 6.1

The Vessel Manufacturer's proposal shall be based on details for individual vessels and the requirements of this specification.

6.2

The Vessel Manufacturer may offer an alternative design, but must quote on the base inquiry documents.

6.3

The proposal shall include a detailed description of any exception to the requirements of this specification.

Mechanical Design 7.1

General 7.1.1

All pressure vessels shall be designed in accordance with the rules of the Boiler and Pressure Vessel Codes, ASME SEC VIII D1 or ASME SEC VIII D2 (herein referred to as the Codes), and the requirements of this specification.

7.1.2

The ASME SEC VIII D1 or ASME SEC VIII D2, to which a vessel is to be manufactured, shall be in accordance with the data sheet.

7.1.3

Should the Vessel Manufacturer have any part of a stress analysis executed by a third party, the Vessel Manufacturer shall advise the Saudi Aramco Engineer.

7.1.4

No proof testing shall be permitted unless specifically approved by the Saudi Aramco Engineer.

7.1.5

No credit shall be given to thickness of integrally-bonded or weld metal overlay cladding in calculating material thickness, required to sustain all primary loads.

7.1.6

Application of ASME Code Cases to the manufacturing of pressure vessels requires approval of the Saudi Aramco Engineer.

Page 8 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

7.2

32-SAMSS-004 Manufacture of Pressure Vessels

7.1.7

Unfired steam drums shall be manufactured and stamped in accordance with the requirements of this specification.

7.1.8

All welded joints of category A, B, C and D shall be complete fusion full penetration welds, except for joint welds of slip-on flanges specified per paragraph 8.1.3(d) of this specification.

Design Pressure The value of design pressure(s) shall be in accordance with the data sheet. Commentary Note: Design pressure is the maximum difference in pressure between the inside and the outside of a vessel, or between the chambers of a combination unit. The term internal design pressure is used when the internal pressure is greater than the external pressure. However, the term external design pressure is used when the internal pressure is less than the external pressure.

7.3

7.4

7.2.1

Unless otherwise specified on the data sheet the design pressure will be assumed to be at the top of the vessel in the operating position.

7.2.2

Design pressure(s) acting at the bottom of vessels shall take into account pressure heads, both static and dynamic, due to the maximum liquid levels.

7.2.3

Design pressure differential for the partition(s) separating the compartment(s) of multi-compartment vessels shall be as specified on the data sheet.

7.2.4

The external design pressure and corresponding temperature shall be as specified on the data sheet.

7.2.5

Requirements for the design of packing bed supports for vessels that contains packing shall be as specified on the data sheet.

Maximum Allowable Working Pressure 7.3.1

The Vessel Manufacturer shall calculate the maximum allowable working pressure (MAWP) acting on the top of a vessel, in the hot and corroded condition in accordance with the applicable Code.

7.3.2

The MAWP of a vessel shall not be limited by flange ratings.

Design Temperature 7.4.1

The value of design temperature(s) shall be as specified on the data sheet. Page 9 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

7.4.2

7.5

32-SAMSS-004 Manufacture of Pressure Vessels

Where there are differences in the design temperatures for different zones in a vessel, the extremities of these zones will be shown on the data sheet.

Minimum Design Metal Temperature (MDMT) The value(s) of the minimum design metal temperature (MDMT) shall be as specified on the data sheet.

7.6

7.7

7.8

7.9

Service and Description 7.6.1

The service of a vessel; hydrocarbon, hydrogen, caustic, amine, wet sour, steam or utility and whether the service is cyclic and/or lethal shall be as specified on the data sheet.

7.6.2

The process description of a vessel (for examples: Amine Regenerator, Air Receiver) shall be specified on the data sheet.

Joint Efficiency 7.7.1

The joint efficiency shall be as specified on the data sheet.

7.7.2

A joint efficiency of 85% or higher shall be specified for the design of all pressure containing components of ASME SEC VIII D1 pressure vessels.

Corrosion Resistance 7.8.1

Corrosion allowance shall be as specified on the data sheet.

7.8.2

The corrosion allowances required for tray assemblies, except for attachments welded to pressure boundary components and intended to support internals, e.g., tray support rings, brackets, etc., shall be in accordance with the requirements of 32-SAMSS-020.

7.8.3

Cladding shall be applied according to the boundaries as specified on the data sheet.

Nominal Thickness Nominal thickness of shells and heads shall not be less than the following: a)

Carbon steels, 6 mm.

b)

Low chrome alloy steels, 5 mm.

Page 10 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

7.10

32-SAMSS-004 Manufacture of Pressure Vessels

Head Types 7.10.1

Refer to the data Sheet for the type of head.

7.10.2

The type of heads to be used shall be ASME 2:1-ellipsoidal or ASME hemispherical.

7.10.3

ASME flanged flat heads and ASME torispherical heads can be used only for air and water services up to a design pressure of 690 kPa (100 psi).

7.10.4

One piece construction (made from one-piece or welded multi-piece blanks) shall be used for heads with nominal thickness greater than 50 mm and vessels in cyclic, hydrogen or lethal services. Other types of head construction shall require prior approval of Saudi Aramco Engineer as defined in this specification. Note:

Following shall be submitted to support review of the proposed multisegment construction head: a)

Layout of head.

b)

Nondestructive examination.

c)

Forming procedure and,

d)

Heat treatment procedure, as applicable.

7.10.5

Heads in vessels with design thickness greater than 50 mm shall be hemispherical unless 2:1 ellipsoidal heads are deemed more economical.

7.10.6

Minimum inside radius of knuckles for conical transition sections or torispherical heads shall be as follows:

7.10.7

a)

Not be less than 15% of the outside diameter of the adjoining cylindrical section with conical section of thickness more than 50 mm.

b)

Not be less than 10% of the outside diameter of the adjoining cylindrical section with conical section of transition sections or torispherical heads with thickness more than 19 mm or less than 50 mm.

c)

Not be less than 6% of the outside diameter of the adjoining cylindrical section with conical section of transition sections or torispherical heads with thickness 19 mm and less.

Reinforcing for conical transition sections in vessels with design thickness greater than 50 mm shall be provided by increased plate Page 11 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

thickness. Use of reinforcing rings is prohibited. 7.10.8

7.10.9

7.11

Shell-to-internal head joint shall be only any of the following details: a)

Forged junction ring according to ASME SEC VIII D2, Table 4.2.5 - Detail 7.

b)

Weld build-up construction connecting shell to internal head. This is not applicable to vessels in cyclic service.

Joint details in paragraph 7.10.8 shall provide a smooth transition, minimizing peak stress concentration effects. The inner radius of the weld build-up and forged detail shall be minimum 1 inch. Backing strips used in fabricating the junction shall be removed after completion of welding. All welds shall be ground smooth flush contour of the joined parts.

Loads 7.11.1

7.11.2

Wind and Earthquake Loads a)

The Vessel Manufacturer shall calculate the static effects of loads due to wind and the effects due to earthquake loads acting on the vessel in the operating position accordance with the requirements of this specification.

b)

Wind and seismic loads shall be calculated for the vessel in its erected position in accordance with ASCE 7, using Occupancy Category IV and based on design data corresponding to the site location per SAES-A-112.

c)

Wind pressures shall be assumed to act on the projected surface area of the pressure vessel and shall include due allowances for platforms, ladders, piping, insulation, and equipment supported from the pressure vessel as specified on the data sheet.

d)

Seismic loads shall include due allowances for platforms, ladders, piping, insulation, and equipment supported from the pressure vessel as specified on the data sheet.

e)

The maximum allowable deflection in the corroded condition at the top tangent line of a vessel shall not exceed 150 mm / 30 m of height.

Wind-induced Vibration 1)

Vertical vessels shall be checked for wind-induced vibration by Page 12 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

the Vessel Manufacturer for the following cases: a)

H > 30 m with H/D ratio > 15

b)

W/HD² < 400 Where: H is the height of the vessel in meters, including the supports. D is the diameter of vessel in meters. (For multi-diameter vessels the diameter shall equal the weighted diameter of the top third). W is the weight of the vessel in kilograms in both the erected empty and operating conditions.

7.11.3

2)

The use of vortex breakers or guying devices in order to maintain stresses, due to wind-induced vibration within allowable limits, is prohibited.

3)

The fatigue life of those vessels susceptible to wind induced vibration shall be a minimum of one million cycles. The fatigue curves in ASME SEC VIII D2 shall be used for the materials at the specified design temperature.

Dead Weights of a Vessel Design of vessels shall consider the following dead loads:

7.11.4

a)

Weight of vessel including internals, supports (e.g., skirts, lugs, saddles and legs), and appurtenances (e.g., platforms, ladders, etc.).

b)

Weight of vessel contents under operating and testing conditions.

c)

Weight of refractory linings, insulation.

d)

Weight of attached equipment such as motors machinery, valves, other vessels, and piping.

Piping, Equipment and External Loads a)

The Vessel Manufacturer shall ensure that local stresses imposed on a vessel due to piping (other than the dead load), equipment, lifting, supports and other external loads do not exceed the allowable limits in accordance with the applicable Code.

Page 13 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

b) 7.11.5

32-SAMSS-004 Manufacture of Pressure Vessels

Refer to the data sheet for piping and equipment loads imposed on a vessel.

Dynamic Loads Dynamic loads caused by the action of vibratory equipment (e.g., agitators), liquid sloshing, sub-liquid surface jets, etc.

7.11.6

Thermal Loads Thermal Loads are loads caused by thermal transients and restraining thermal expansion/ interaction of the vessel and/ or its support(s).

7.12

7.13

Load Combinations 7.12.1

All components of a vessel, including its support(s), shall be designed to withstand stresses resulting from load combinations in accordance with, but not be limited to, those shown in Table 4.1.2 of ASME SEC VIII D2.

7.12.2

Anchor bolts shall be designed for load combinations, based on the allowable stress design method (Service Loads) in accordance with SAES-M-001.

7.12.3

All pressure vessel components whether shop or field fabricated shall be designed to withstand a full hydrostatic test in the erected position.

7.12.4

Combined stresses due to full hydrostatic test and the greater of wind and earthquake loads shall be within the allowable limits per ASME SEC VIII D2, paragraph 4.1.6.2, based on the lowest Specified Minimum Yield Strength (SMYS) of the materials of construction at test temperature. However, wind and earthquake design loads can be reduced to 50% of its values.

7.12.5

Loads (moments or forces) acting on a vessel due to external piping that will affect the overall integrity of the vessel shall be added to moments and forces due to other external primary loads (weight, wind or earthquake loads). Addition of piping loads shall be based on performing stress analysis.

Stress Analysis 7.13.1

Where applicable, the requirements for thermal stress and fatigue stress analyses shall be as specified in the data sheet. Analysis methods and stress combination limits presented in Division 2, Section 5, shall be used for vessels under scope of Division 1 and Division 2. However, Page 14 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

allowable stresses shall be taken from the respective tables of ASME SEC II for each division for the corresponding material and temperature. 7.13.2

The Design Engineer is responsible for specifying the heat transfer coefficients to be used for all thermal stress analysis.

7.13.3

Thermal Analysis 1)

A thermal stress analysis is required for a vessel, if a thermal gradient (calculated under steady state operating conditions and, if applicable, transient operating conditions) across any vessel section exceeds 65°C (150°F), in a distance equal to the square root of R times T, where: - R is the radius of the vessel component under consideration and, - T is the thickness of the component under consideration - R and T have the same units.

2)

As a minimum, the scope of the stress analysis shall include the following junctures, as applicable: - Head-to-shell - Support-to-vessel - Nozzle-to-shell, considering external piping loads - Tray supports to vessel wall

7.13.4

3)

Thermal analysis shall be based on gradients under steady state design conditions and also, if applicable, transient design conditions.

4)

Thermal gradients may be reduced to within allowable limits with the provision of: a)

Thermal sleeves in pressure-retaining components

b)

Hot-box design at the skirt-to-vessel junction in skirtsupported vessels with design temperatures greater than 260°C (500°F).

Fatigue Analysis 1)

Scope of the required stress analysis shall be as specified in the data sheet, in accordance with the rules of Division 2, by the Design Engineer. Page 15 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

2)

32-SAMSS-004 Manufacture of Pressure Vessels

As a minimum, the scope of the stress analysis shall include the following junctures, as applicable: - Head-to-shell - Support-to-vessel - Nozzle-to-shell, considering external piping loads - Tray supports to vessel wall

7.13.5

3)

Analysis shall be based on the calculated number of cycles for a minimum 20 year service life, as determined in accordance with the rules of Division 2, paragraph 5.5.2.

4)

The number of cycles shall include the number of start-ups, shutdowns, emergency shut-downs, and upset conditions.

Local Stress Analysis Stress analysis due to piping, equipment, lifting, supports and other external loads shall be completed in accordance with the procedures as detailed in WRC 107, WRC 297 or a finite element analysis.

8

Nozzles and Manways 8.1

General 8.1.1

The quantities, sizes, ratings, (ASME pressure classes), facings, elevations, and orientations of nozzles and manways shall be as specified on the data sheet.

8.1.2

Unless otherwise specified on the data sheet, the minimum projections for nozzles and manway necks, as measured from the outside surface of the shell or head to the face of a flange, shall meet the following requirements: a)

6 inches for NPS 6 nozzles and smaller.

b)

8 inches for NPS 8 nozzles and larger and manways necks.

c)

For insulated vessels, projection shall be sufficient to allow bolting of studs without interference with the insulation.

d)

For vessel drain connections and other connections, where a process stream is likely to be stagnant, the projection shall not exceed three times the connection nominal diameter.

Page 16 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

8.1.3

32-SAMSS-004 Manufacture of Pressure Vessels

Permissible types of flanges for nozzles and manways are according to the following: a)

Forged steel long welding neck flange.

b)

Forged steel welding neck flange. Such type of flange is welded to seamless pipe, rolled plate with 100% radiography or an integrally reinforced contour shaped forged nozzle or manway. The bore of flange shall match the bore of nozzle and manway, as applicable.

c)

Studded nozzles and proprietary designs may be offered as alternatives provided their design is in accordance with the applicable Code and approved by the Saudi Aramco Engineer.

d)

Slip-on type flange with seamless pipe nozzle necks or rolled plate with 100% radiography is permissible for vessels, which are integral parts of skid-mounted packaged equipment units, in only non-cyclic air and water services with design temperature and design pressure not exceeding 121C (250F) and 1.7 MPA (245 psi), respectively. Slip-on flange shall be welded on the front or face and at the back of the hub.

8.1.4

A body flange shall be constructed of a single-piece forging.

8.1.5

Nozzles less than 2-inch NPS are not permissible.

8.1.6

Only flanged nozzles shall be used.

8.1.7

Vessels in services other than air and water shall be provided with a minimum 2-inch NPS flanged steam-out connection.

8.1.8

The ends of butt-welded connections shall be in accordance with ASME B16.25.

8.1.9

The Vessel Manufacturer shall design nozzles that are required for the supporting of mechanical mixers and shall include the additional loads and dimensional tolerances as specified on the data sheet.

8.1.10

Minimum four gusset plates for the reinforcement of nozzles supporting mixers shall be provided.

8.1.11

Minimum inside corner radius of integrally reinforced contour nozzles and manways shall be 13 mm.

8.1.12

Design of flanged connections with stud bolts of diameter 1½ inch and above shall be such as to provide clearance to permit use of a stud and Page 17 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

bolt-tensioning device. 8.2

8.3

Reinforcement of Openings 8.2.1

Reinforcement of vessel openings shall be in accordance with the applicable Code and this specification.

8.2.2

The thickness of reinforcing pads shall not exceed the shell or head thickness of a vessel.

8.2.3

Use of internal reinforcing elements is not permitted.

Flange Ratings, (ASME Pressure Classes) and Facings 8.3.1

The ASME pressure classes and facings shall be as specified on the data sheet.

8.3.2

Bolted joints specified with non-ASME flanges shall be designed to meet all anticipated loading conditions of the vessel.

8.3.3

Pressure ratings for standard flanges shall be in accordance with the following:

8.3.4

8.3.5 8.4

a)

ASME B16.5 for flanges NPS 24 and smaller.

b)

ASME B16.47, Series A for flanges larger than NPS 24.

Gasket seating surfaces shall comply with the following: a)

For spiral wound gaskets, 125 to 250 AARH, in all services, except hydrogen.

b)

For spiral wound gaskets in hydrogen service, 125 to 150 AARH.

c)

The side-walls of rings joint flanges in all services, 63 AARH.

d)

For Nonmetallic gaskets, 250 to 500 AARH.

Machined surfaces other than gasket contact faces shall not exceed 500 AARH.

Manways 8.4.1

The number, nominal inside diameter and locations of manways shall be as specified in the data sheet.

8.4.2

All manways shall be circular. The manway covers shall be hinged or provided with handling davits as specified on the data sheet, according to PIP VEFV1100. Page 18 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

8.5

32-SAMSS-004 Manufacture of Pressure Vessels

Attachment Details for Nozzles, Manways and their Connections 8.5.1

All nozzles and manway necks shall be attached by welding completely through the total thickness of the vessel shell, head or nozzle wall, including any reinforcement. Backing rings used in attaching nozzles and manways to vessels shall be removed after welding.

8.5.2

Permissible types of nozzles, manways and their connections shall be according to the table below.

Design Conditions / Services Group

Attachment

Figure Reference from Indicated ASME Code Section VIII Division 1 Vessels Division 2 Vessels

Group I a. Pressure-retaining vessel’s component (shell, head, nozzle or manway) with design thickness greater than 50 mm b. Unfired steam boilers with design pressure exceeding 50 psi



All nozzle sizes and manway necks

c. Lethal, hydrogen and cyclic services  d. Openings larger than 900 mm (Note 1)

Connections attached to nozzles and manways

Figure UW-16.1, details: (f-1), (f-2), (f-3) or (f-4)

Table 4.2.13, details: (1), (2), (3), (4), (5) or (6)

Figure UW-16.1, details: (a), (a-1), (b), (c), (d), (e), (f-1), (f-2), (f-3), (f-4) or (g).

- Table 4.2.10, details: (1), (2), (3), (4), (6), (7) or (9)

e. Design temperature greater than 400°C (Note 1) f. Low alloy steel vessels with design thickness greater than 25 mm (Note 1) g. Vessels that will undergo PWHT (Note 1) NPS 4 and smaller nozzles

Group II Design conditions and service other than those in Group I of this table

Nozzles larger than NPS 4 and manway necks Connections attached to nozzles and manways

Note 1:

- Table 4.2.11, detail (2) - Table 4.2.13, details: (1), (2), (3), (4), (5) or (6)

Alternatively, detail per Figure UW-16.1(g) may be used for Division 1 vessels provided that design conditions/ services per a, b and/or c of group I are not applicable.

8.5.3

9

Figure UW-16.1, details: (c), (d), (e), (f-1), (f-2), (f-3), (f-4) or (g)

Integrally reinforced contour shaped attachments made partially or completely of weld build up are prohibited.

Internals 9.1

All fixed and removable internals, including trays, packing, distributors, screens, etc. shall be specified on the data sheet.

9.2

Tray rings and tray supports that are welded to vessels shall be designed by the tray manufacturer and supplied and installed by the Vessel Manufacturer in accordance with the requirements of 32-SAMSS-020.

Page 19 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

10

32-SAMSS-004 Manufacture of Pressure Vessels

9.3

The Vessel Manufacture shall design, supply and install all other internals, except for trays, as specified on the data sheet.

9.4

All removable internals are to be designed so that they may be passed through tray and vessel manways.

9.5

Internal ladder rungs shall be provided by the Vessel Manufacturer according to PIP document VEFV1100.

Vessel Support 10.1

10.2

General 10.1.1

Refer to the data sheet for the type of support.

10.1.2

Supports shall be designed to prevent excessive localized stresses due to deformations produced by the internal pressure, primary loads and, if applicable, thermal gradients in the vessel and support system.

10.1.3

Each vessel shall be designed as a self-supporting unit in accordance with the requirements of the applicable Code and AISC.

10.1.4

All supports shall be continuously welded to the vessel.

10.1.5

The material of anchor bolts shall be in accordance with this specification.

10.1.6

Base plates shall be designed by the Vessel Manufacturer for all loading conditions in accordance with this specification.

10.1.7

The allowable concrete bearing stress to be used for the design of base plates shall be 5170 kPa.

Supports for Vertical Vessels 10.2.1

The data sheet shall specify the type, location and overall dimensions required for the design of supports for vertical vessels.

10.2.2

The Vessel Manufacturer shall design all supports required, including skirts, legs, lugs, base plates, number of anchor bolts in accordance with the data sheet.

10.2.3

Skirts shall have a minimum thickness of 6 mm.

10.2.4

The mean corroded diameter of the shell and the mean diameter of the skirt shall coincide [rounded off to the nearest 3 mm], and shall be Page 20 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

symmetrical about the vessel centerline. Exceeding this offset limit shall require prior approval of the Saudi Aramco Engineer, as defined in this specification, supported by stress analysis. 10.2.5

Hot-box design when specified for skirt-supported vessels with design temperatures greater than 205°C (400°F) shall be in accordance with PIP VEFV1100 and dimensions that meet the intent of reducing the thermal gradient at the skirt-to-vessel junction.

10.2.6

One minimum 500 mm diameter skirt access opening shall be provided for vessels with diameters equal to and larger than 1200 mm. For vessels with diameters less than 1200 mm, skirt access opening diameter shall be minimum one half of the vessel diameter. Skirt access opening diameters smaller than the above specified shall require prior approval of the Saudi Aramco Engineer. It is the vessel manufacturer's responsibility to determine the need for reinforcing the opening, according to the applicable Code.

10.2.7

Piping passing through skirt openings shall be adequately supported to prevent damage during shipment.

10.2.8

The Vessel Manufacturer shall provide skirt bracing to prevent buckling during shipping and lifting in the field.

10.2.9

Skirt-to-vessel juncture details for vessels with design thickness greater than 50 mm and vessels in cyclic, hydrogen or lethal services shall be only any of the following details: a)

Forged junction ring: according to ASME SEC VIII D2, Figure 4.2.4(e).

b)

Weld build-up construction (connecting skirt to head): according to ASME SEC VIII D2, Figure 4.2.4(b). (Exception: This is not applicable to vessels in cyclic service.)

c)

Weld build-up construction (connecting skirt to shell): according to ASME SEC VIII D2, Figure 4.2.4(f). (Exception: This is not applicable to vessels in cyclic service.)

d)

Forged skirt-to-shell junction ring: similar to ASME SEC VIII, D2, Table 4.2.5 - Detail 7.

10.2.10 Joint details in paragraph 10.2.9 shall provide a smooth transition, minimizing peak stress concentration effects. The inner radius of the weld build-up and forged detail shall be minimum 1 inch. Backing strips used in fabricating the junction shall be removed after

Page 21 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

completion of welding. All welds shall be ground smooth flush contour of the joined parts. 10.2.11 Skirt-to-vessel juncture in vessels other those specified in paragraph 10.2.9 shall be according to ASME SEC VIII D2, Figure 4.2.4, detail (a), (b) or (c) and shall meet the following weld spacing requirements:

10.3

10.4

1.

Adjacent edges of the head-to-shell and skirt-to-head welds shall not be closer than the head thickness or 1 inch, whichever is greater.

2.

Adjacent edges of the skirt-to-shell weld and any category B weld joint shall not be closer than the shell thickness or 1 inch, whichever is greater.

Supports for Horizontal Vessels 10.3.1

Two saddles with anchor bolts shall be used to support horizontal pressure vessels. The vessel shall be fixed at one saddle support and free to slide at the other saddle. Saddle base plates shall be in full direct contact with the foundation.

10.3.2

The data sheet shall specify locations of the fixed and sliding saddles and dimension from vessel centerline to underside of saddle base plate.

10.3.3

The shell shall be analyzed in accordance with the “LP Zick” method. Saddle supports and the vessel shell shall be analyzed for operating and hydrotest loads including any piping, wind or other external loads.

10.3.4

Minimum of 10 mm thick reinforcing pad is required at the junction of the saddle and the vessel with all corners rounded to a minimum radius of 50 mm.

10.3.5

The anchor bolt holes on the sliding-end saddle shall be slotted to facilitate thermal expansion/ contraction along the longitudinal axis of the vessel.

Anchor Bolts 10.4.1

The Vessel Manufacturer shall determine the size and number of anchor bolts required.

10.4.2

Anchor bolts shall straddle vessel centerlines on the north-south, eastwest axes.

10.4.3

Anchor bolts shall not be less than 19 mm minimum nominal diameter.

Page 22 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

10.4.4

11

32-SAMSS-004 Manufacture of Pressure Vessels

Design of anchor bolts shall be based on the following allowable stresses: a)

104 MPa (tension).

b)

69 MPa (shear).

10.4.5

Vessels supported on skirts, lugs or legs shall be provided with an even number of anchor bolts with a minimum of four anchor bolts.

10.4.6

Vessels supported on saddles shall be provided with an even number of anchor bolts with a minimum of two anchor bolts per saddle.

Clips and Attachments 11.1

General The Vessel Manufacturer shall supply and install all clips and attachments as specified on the data sheet.

11.2

11.3

11.4

Insulation Supports 11.2.1

Support for insulation system shall be according to the data sheet.

11.2.2

The Vessel Manufacturer shall supply and install supports required for insulation.

11.2.3

The bottom heads of vertical vessels that are externally insulated shall be provided with 12 mm blank nuts. Blank nuts shall be welded on edge and located on 300 mm square centers.

Refractory Supporting System 11.3.1

Anchoring system of refractory lining shall be according to the data sheet.

11.3.2

The Vessel Manufacturer shall supply and install anchoring system required for refractory.

Fireproofing Supports 11.4.1

Support for fireproofing system shall be according to the data sheet.

11.4.2

The Vessel Manufacturer shall supply and install supports required for fireproofing materials.

11.4.3

Vertical vessels, which are not externally insulated, shall be provided with a 5 mm thick steel weather cap on the skirt to provide a flashing Page 23 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

for fireproofing. 11.5

Grounding Lugs All pressure vessels shall be provided with a grounding lug connection welded to the vessel support in accordance with PIP VEFV1100.

11.6

11.7

Equipment Davit 11.6.1

A davit for the lifting of equipment shall be supplied when specified on the data sheet.

11.6.2

The davit shall be in accordance with PIP VEFV1100.

Reinforcing Pads Reinforcing pads for all internal and external welded attachments shall be sized to meet requirements of paragraph 7.11.4 of this specification. Pads shall be a minimum of 10 mm (3/8") thick, but shall not exceed the shell thickness; with all of their corners rounded to a minimum radius of 50 mm. Distance from any edge of the attachment to the closest edge of the reinforcing pad shall not be less than 50 mm.

12

Materials 12.1

General 12.1.1

All carbon, low alloy and high alloy steels required for pressure and non-pressure components shall be as specified on the data sheet.

12.1.2

Prior approval by the Saudi Aramco Engineer is required for use of alternative materials of construction for carbon and low alloy steels pressure vessels. Alternative materials must comply with all the requirements of the applicable Code and this specification.

12.1.3

Material specifications and tests procedures for base metal and weldments materials for 1 Cr- ½ Mo, 1 ¼ Cr- ½ Mo, 2 ¼ Cr-1 Mo, 2 ¼ Cr-1 Mo- ¼ V, 3 Cr-1 Mo and 3 Cr-1 Mo- ¼ V shall be submitted to Saudi Aramco Engineer for review and approval prior to ordering the materials from the mill.

12.1.4

All materials must be clearly identified and provided with legible original or certified true copies of Mill Test Certificates. Lack of adequate identification and certification shall be cause for rejection.

Page 24 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

12.1.5

1 Cr- ½ Mo and 1 ¼ Cr- ½ Mo steels with thickness exceeding 100 mm can be used for components (shell, head, integrally reinforced nozzles, flanges, etc.) of vessels within scope of API RP 934-C, API RP 934-E and paragraph 1.6 of this specification, provided that fracture toughness requirements of the respective document of the aforementioned documents and this specification can be met.

12.1.6

Use of high alloy steels, including austenitic stainless steels, shall be on a case-by-case basis, with prior approval of the Saudi Aramco Engineer as defined in this specification. Material selection shall be based on the design temperature, minimum design metal temperature and intended service.

12.1.7

All materials, except carbon steels, shall be alloy-verified by the Vessel Manufacturer in accordance with SAES-A-206.

12.1.8

The use of C-½ Mo steels in hydrogen services is prohibited.

12.1.9

Material of construction (pressure-retaining and attachments used for supporting or lifting the vessel) shall be tested, as applicable, to verify that their mechanical properties will be retained considering all of the following thermal treatments that could affect the material: a)

All heat treatment cycles that will be required for the fabrication of the vessel, including as applicable: normalizing, normalizing and tempering, quenching and tempering, intermediate stress relief (ISR), and final postweld heat treatment (PWHT),

b)

Two PWHT cycles to account for future repairs and/or alterations.

12.1.10 As an alternative to material qualification requirements per paragraph 12.1.9 of this specification for carbon steel nozzles and standard flanges according to ASME B16.5 and B16.47 that do not require impact testing, materials of construction shall have minimum 70 MPa (10 ksi) over their specified minimum yield strength and ultimate tensile strength values. 12.1.11 Forgings shall meet a material cleanliness C2/R2/S2 rating, as described in ASTM E381. 12.1.12 Specimens for material testing shall be taken per the following: a)

Plates Specimens shall be taken from each plate transverse to the rolling direction in accordance with SA-20 at the standard test locations Page 25 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

and at a depth of ½T (T = maximum heat-treated thickness) location. If required, ½T specimens should be used for hot tensile and step cooling tests. b)

Plate-like forgings (forged rings, tubesheets, blind flanges, etc.) Specimens shall be taken from each heat transverse to the major working direction in accordance with the material specification, and at a depth of ½T of a prolongation or of a representative separate test block.

c)

Standard flanges according to ASME B16.5 and B16.47. 1. For flanges with T equal to or less than 50 mm, specimens shall be removed in accordance with the material specification. 2. For flanges with T greater than 50 mm, specimens shall be removed in accordance with the material specification from a production forging or a representative separate test block that are machined to essentially the finished product configuration prior to heat treatment. The center axis of the specimen shall be at a depth of ½T and the mid-length of the test specimen shall be at a depth at least equal to T from any second heattreated surface.

d)

Other forgings that are contour shaped or machined to essentially the finished product configuration prior to heat treatment, test specimens shall be removed in accordance with the material specification of a production forging or a representative separate test block. The center axis of the specimen shall be at a depth of ½T and the mid-length of the test specimen shall be at a depth at least equal to T from any second heat-treated surface.

e)

Pipe Specimens shall be taken from each heat and lot of pipe, transverse to the major working direction in accordance with used material specification except that test specimens should be taken from a depth of ½T.

f)

A separate test block, if used, should be made from the same heat and should receive substantially the same reduction and type of hot working as the production forgings that it represents. It should be of the same nominal thickness as the production forgings and shall be machined to essentially the finished product configuration prior to heat treatment. The separate test forgings

Page 26 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

should be heat-treated in the same furnace charge and under the same conditions as the production forgings. 12.1.13 Layered constructions are prohibited for all vessels. 12.1.14 Materials for pressure vessels for de-aeration service shall be in accordance with NACE RP0590. 12.1.15 Materials for vessels exposed to SSC environments shall be in accordance with the following: a)

Forged flanges and forged fittings are restricted to: SA-350 LF1 or LF2 or SA-266 Grade 4.

b)

Flanges above 24-inch diameter shall be SA-266 Grade 4.

c)

Studs are restricted to: SA-193 B7M or SA-320 L7M.

d)

Nuts are restricted to: SA-194 Grade 2HM.

e)

It shall satisfy the requirements of ISO 15156 and NACE RP0472.

12.1.16 Low alloy steels shall not be mixed. For example, a vessel requiring 1 Cr-½ Mo materials shall have all components manufactured from 1 Cr-½ Mo. 12.1.17 Low alloy steels shall be specified in the normalized and tempered heat-treated or quenched and tempered conditions. Material of construction shall be tested, as applicable, to verify that their mechanical properties will be retained considering thermal treatments specified in paragraph 12.1.9 of this specification. 12.1.18 Material for nameplate mounting brackets shall be of the same type and material grade as the shell material. 12.1.19 SA-36 and SA-285 materials may be used only for pressure retaining components of vessels in water and air services with plate thickness not exceeding 19 mm. 12.1.20 Materials of supports shall be as follows: 1)

Legs and lugs: same material as vessel wall base material. Supports of vessels described in paragraph 12.1.19 of this specification may be of the same ASME material P No. as that of the vessel wall base material.

2)

Skirts: same material as the vessel wall base material for a minimum distance of 300 mm measured below the vessel-to-skirt Page 27 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

connection line, unless thermal calculations require additional length. Remaining section of skirt shall be of the same material or same ASME material P No. 3)

Saddles: same material as the vessel wall base material.

12.1.21 External attachments, other than those in paragraph 12.1.20 of this specification, and internal attachments welded to the vessel shall be of the same material as the vessel wall base material. With prior approval of Saudi Aramco Engineer as defined in this specification, Stainless Steel (SS) internal attachments can be welded to carbon steel pressureretaining parts of vessels in non-sour services. 12.1.22 Internal attachments to clad vessels shall be of the same material as that of the cladding. SS 321 and SS 347 can be used interchangeably. 12.1.23 Material of construction for anchor bolts shall be ASTM A193 / A193M, ASTM F1554 Grade 36 or ASTM F1554 Grade 105 with the corresponding material of construction for nuts according to SASD AA-036322. 12.1.24 One temper embrittlement test block shall be installed in hydrotreating or hydrocracking reactors made of 2 ¼ Cr-1Mo, 2 ¼ Cr-1Mo- ¼ V, 3Cr-1Mo or 3Cr-1Mo- ¼ V. Test block shall be made from prolongation of a shell ring or a shell plate used for constructing the reactor shell. Test block shall be 300 mm long, 300 mm wide, and have thickness same as the shell. Test block shall be weld overlaid from 5 sides with the same welding procedures used to fabricate the reactors. After weld overlay, test block shall be exposed to the minimum post weld heat treatment cycle before attaching to a bottom structure of the reactor. Fabricator shall provide the test block attachment drawing for Saudi Aramco approval. 12.1.25 One manual UT test block and one TOFD UT test block shall be provided by the fabricator of hydrotreating or hydrocracking reactors made of 2 ¼ Cr-1Mo, 2 ¼ Cr-1Mo- ¼ V, 3Cr-1Mo or 3Cr-1Mo- ¼ V with shell thickness greater than 150 mm. Test blocks shall be made from prolongation of a shell ring or a shell plate used for constructing the reactor. Test blocks shall be prepared in such a way that they can be used to meet all fabricator’s UT calibration procedures and that inspection according to API RP 934A, Appendix A can be performed on site in a later date, if deemed necessary.

Page 28 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

12.2

32-SAMSS-004 Manufacture of Pressure Vessels

HIC Resistant Materials Hydrogen Induced Cracking (HIC) resistant steel shall be qualified in accordance with 01-SAMSS-016. HIC resistant steel shall be procured from Saudi Aramco approved manufacturers within a list available by the Saudi Aramco buyer, as defined in this specification.

12.3

Gasket Materials Types and material specifications of gaskets shall be as specified on the data sheet.

12.4

Impact Testing 12.4.1

The Vessel Manufacturer is responsible of determining the required Charpy impact energy value(s) based on the test temperature specified on the data sheet and the purchased vessel’s component thickness.

12.4.2

Impact test temperature for a component of a vessel shall be as specified on the data sheet.

12.4.3

Minimum acceptable Charpy impact energy values for all materials of construction (base and weld metals) shall not be less than the highest of the following applicable values: 1)

40/32 Joules for carbon steels thicker than 50 mm

2)

As specified by ASME SEC VIII D2, but not less than 34/27 Joules

3)

As specified by the licensor’s specification, but not less than 34/27 Joules

4)

55/47 Joules for 1 Cr- ½ Mo, 1 ¼ Cr- ½ Mo, 2 ¼ Cr- 1 Mo, 2 ¼ Cr- 1 Mo- ¼ V, 3 Cr- 1 Mo and 3 Cr- 1 Mo- ¼ V steels.

Commentary Notes:

12.4.4

a)

The first number of required energy values is the minimum average energy of three specimens and the second number is the minimum for one specimen of the impact test results. The second number shall not be less than 80% of the average value.

b)

Minimum acceptable Charpy impact energy values are applicable to Div. 1 and Div.2 vessels.

For Div. 1 vessels the impact testing exemptions of UG-20 (f), UCS-66 (b) (1) and (3), UCS-68(c), UG-84 (b) (2) and by reference to Table UG-84.4 are not permitted. For Div. 2 vessels the exemptions of Page 29 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

3.11.2.3, 3.11.2.4, 3.11.2.5, 3.11.2.6, 3.11.2.8, 3.11.2.10, 3.11.3.1 and 3.11.4 are not permitted.

13

12.4.5

Impact testing is required, with no exception, for pressure vessels made of low alloy steels.

12.4.6

Impact testing of materials and welding procedures are required when test temperature is lower than -28°C.

12.5

All forgings shall be forged as close as practicable to finished shape and size to develop metal flow in a direction most favorable for resisting the stresses encountered in service.

12.6

All flanges, fittings and piping for use as integral parts of pressure vessels shall be purchased from Saudi Aramco approved manufacturers, either directly or through approved stockists. Procurement of these items from stockists shall be in accordance with SAEP-347.

Fabrication 13.1

Fabrication Tolerances 13.1.1

Fabrication tolerances shall be in accordance with the more stringent of the applicable Code and PIP document VEFV1100, with the following exceptions to tolerances on page 1 of drawing VEFV1102: Tolerance 1:

Height from base line to face of top nozzle shall be the smaller of 4 mm per 3000 mm of height or 19 mm.

Tolerance 2:

Flange face of nozzle with agitator shall be aligned within ±¼ degree of indicated plan in any direction.

Tolerance 7:

Unless more stringent tolerances are specified by the process licensor, alignment of flange face of nozzle without an agitator shall be within ±½ degree of specified plan, but not to exceed 5 mm across the diameter.

Tolerance 12: Bottom of vessel support to base line 0 mm, -6 mm. Tolerance 13: For supports located above baseline, tolerances shall be 0 mm, + 6 mm. Tolerance 14: Maximum difference in peak deviations from straight, applied to the shell at any location along the circumference clear of openings, shall be: 3 mm in any Page 30 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

3000 mm of length, 12 mm in any 15000 mm of length, and shall not exceed 19 mm over the overall length of shell. In addition, distortion caused by welding of longitudinal or circumferential joints shall not exceed 6 mm maximum depth in a 900 mm length of shell centered on the weld. Tolerance 20: Deviation from average I.D. (as determined by strapping) from nominal I.D. shall be as follows: a)

±3 mm for I.D. ≤ 1200 mm

b)

±6 mm for I.D. > 1200 mm

Out-of- roundness tolerances shall be according to applicable ASME SEC VIII. Tolerance 26: Supports out of level shall be within ±3 mm. Deviation from flatness of support base plate is not acceptable, i.e., support base plates shall be in full direct contact with the foundation. Tolerance 28: Delete. Tolerance 31: Distance between centerlines of support bolt holes shall be within ±6 mm and maximum diagonal measurements shall be within ±6 mm.

13.2

13.1.2

Use of fitness-for-service assessment methodology to qualify the design of components that do not satisfy the fabrication tolerances according to this specification is prohibited.

13.1.3

Dished heads shall achieve at least the minimum required thickness in all areas after forming.

Forming and Assembly 13.2.1

Tapered transitions shall be made only on the external surface of the vessel, according to the rules of the applicable Code, in the following conditions: a)

There will be an interference with the removal of a vessel's internals.

b)

Vessels that have strict requirements regarding smooth internal profiles for flow or cyclic loading conditions or internal volume constraints. Page 31 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

13.2.2

The beveled edges of weld preparations for carbon steel plates with thickness 25 mm and thicker and all ferrous alloy plates shall be magnetic particle examined for linear discontinuities. Defects shall not exceed limits as per ASME SA-20.

13.2.3

Plate edge laminations revealed by magnetic particle examination shall be completely removed and repaired.

13.2.4

Each shell section shall be completely welded longitudinally and corrected for out of roundness and peaking of the weld seam prior to welding to adjoining shell or head.

13.2.5

All re-rolling or forming of the shell sections is to be completed prior to radiography.

13.2.6

Welds Encroachment 13.2.6.1

It is the responsibility of the manufacturer to ensure that the outer edge of welds attaching manways, nozzles (with and without reinforced pads) and other structural attachments (with and without reinforced pads), except those in paragraph 10.2.11, to pressure-retaining components shall not be closer than 1 inch from the adjacent edge of any other weld. It is the responsibility of the manufacturer to ensure that requirements of paragraph 7.11.4 of this specification are met in the vicinity of the welds. Commentary Note: Weld spacing requirements for skirt-to-vessel junctures shall be according to paragraph 10.2.11 of this specification.

13.2.7

13.2.6.2

Where the optimized fabrication layout and/ or process design requirements do not absolutely allow meeting the spacing requirement in paragraph 13.2.6.1 of this specification, NDE per paragraph 14.6 shall be performed.

13.2.6.3

It is prohibited to cover butt welds in wall of vessels that will undergo PWHT by structural attachments (with or without reinforcing pads).

Telltale Holes in Reinforcing Pads 13.2.7.1

¼ - inch telltale vent holes drilled and tapped for ⅛ -inch NPT shall be provided in reinforcing pads for welded attachments, including nozzles and manways, per the following: Page 32 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

13.2.7.2

32-SAMSS-004 Manufacture of Pressure Vessels

1)

One hole in single piece reinforcing pad.

2)

Where a pad is split, each segment shall have at least one hole.

Telltale holes shall be located at the lowest position accessible for inspection with center of the hole 25 mm from edge of the pad. This is applicable to each segment of a split reinforcing pad. Commentary Note: In case of reinforcing pads for attachments, other than nozzles and manways, center of telltale hole shall be 25 mm from the closest edge of the pad.

13.2.7.3

Telltale holes in reinforcing pads for external welded attachments shall be plugged with grease or other materials adequate for the operating temperature but not capable of retaining pressure, to prevent moisture ingress between the pad and the vessel pressure-retaining component. Telltale holes in internal attachment pads shall be seal welded.

13.2.8

Segments of split reinforcing pad shall be welded together without using a backing strip.

13.2.9

All internal and external attachments, including clips, welded directly to pressure-retaining parts, shall be fully seal welded, except for blank square nuts used for external insulation where tack welding is allowed.

13.2.10 No tack welding is permitted between heads and skirts on the inside of skirts. 13.2.11 Vessels with large diameter and/ or overall length which fabrication cannot be completely done in shop shall be designed to minimize the amount of field welding, radiography and heat treatment. Where adjacent sections are of such a size that shop fabrication and field assembly is required, the sections shall be match marked to ensure proper field fit up. 13.2.12 Forming 13.2.12.1

General a)

Cold forming is performed at temperatures within the range of above 20°C (68°F) and below 120°C (248°F).

Page 33 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

13.2.12.2

13.2.12.3

32-SAMSS-004 Manufacture of Pressure Vessels

b)

Hot forming is any forming performed above the austenite phase start temperature of 740°C (1364°F).

c)

All tempering heat treatments must be at least 25°C (45°F) above the nominal PWHT temperature as given in the applicable ASME code for the respective material.

Hot Forming 1)

All quenched and tempered materials must be completely heat-treated after hot forming to achieve the original material properties.

2)

All hot forming procedures require approval of the Saudi Aramco Engineer as defined in this specification prior to commencement of any of forming activities. Hot forming procedure shall describe all heat treatment operations and tests to be performed. The tests shall include, but not limited to, all of the mechanical tests required by the original material specification.

3)

Normalized materials that are hot formed need to be heat treated unless the below rules are followed: a)

Normalized materials that are hot formed in the range of 750°C (1382°F) to 950°C (1742°F) and still air-cooled.

b)

Normalized materials that are hot formed in a multi-step sequence must be cooled to below 200°C (392°F) prior to the last step. The material will then be re-heated within the range of 750°C (1382°F) to 950°C (1742°F) for forming in the last step.

c)

Normalized and tempered materials that are formed in accordance with either 13.2.14.2(3)(a) or 13.2.14.2(3)(b) of this specification need only receive a tempering heat treatment. The tempering temperature must not exceed the temperature stated in the steel manufacturers Material Test Certificate.

Cold Forming a)

Heat treatment requirements for Carbon Steels (P-1) and Low Alloy Steels (P-3, 4, 5, 9A and 9B) that Page 34 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

undergo cold forming (by pressing or cold spinning) shall be as follows: Fiber Elongation Strain εf (%)

Material

Heat Treatment Requirement None

Less than or equal to 5 Greater than 5 and equal to or less than 10

Carbon Steels P-1

Greater than 10

(Exception: PWHT per the applicable Code shall be performed for cold spun heads) PWHT per the applicable Code Normalizing, Normalizing and tempering or quenching and tempering, as required to maintain original material properties. None

Less than or equal to 3 Low Alloy Steels P-3, P-4, P-5, P-9A & P9B

Greater than 3 and equal to or less than 10 Greater than 10

(Exception: PWHT per the applicable Code shall be performed for cold spun heads) PWHT per the applicable Code Normalizing, normalizing and tempering or quenching and tempering, as required to maintain original material properties.

High Alloy Materials

Table 6.2 of ASME Section VIII, Division 2

Table 6.2 of ASME Section VIII, Division 2

Non-ferrous Materials

Table 6.3 of ASME Section VIII, Division 2

Table 6.3 of ASME Section VIII, Division 2

b)

Calculation of forming fiber elongation strain εf (%) shall be according to the following:

Type of Part Being Formed For double curvature heads that are formed from one-piece or welded multi-piece blanks by any process that includes dishing or cold spinning (e.g., dished heads or cold spun heads) For heads that are assembled from formed segments (e.g., spherical dished shell plates or dished segments of ellipsoidal or torispherical heads) Cylinders and cones formed from plate

Fiber Elongation Strain εf (%) εf = 100 ln [Db/(Df -2ta)]

εf = 100 tb / Rfd εf = (50 tb / Rfc) [1-(Rfc / Ro)]

Where: ln

is the natural logarithm

Db

is the diameter of unformed blank plate or diameter of intermediate product

Df

is original outside diameter

Page 35 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

Rfd

is the smallest mean radius of curvature of formed segment (mean radius of spherical segment, mean knuckle radius of knuckle segment of multi sectional semi-ellipsoidal or torispherical heads)

Rfc

is the mean radius of curvature of finished product (mean radius of cylinder, mean radius of the smaller diameter of cone)

Ro

is the mean radius of initial product (flat plate) or the intermediate product (in case of unformed initial product equals to infinity)

ta

is the nominal thickness of the plate before forming or intermediate product

tb

is the nominal thickness of the plate before forming

Commentary Notes: i)

Cold spun heads with nominal thickness exceeding 50 mm shall be heat treated by normalizing, normalizing and tempering or quenching and tempering, as required to maintain original material properties), irrespective of the calculated fiber elongation strain.

ii)

For semi-ellipsoidal and torispherical heads formed from one-piece or welded multi-piece blanks, maximum calculated extreme fiber elongation strain among all head’s zones shall be used to determine the need of heat treatment. Separate calculation for each zone (spherical crown, knuckle area, etc.) shall be made, using the greatest measured thickness and smallest radius of curvature of the zone after forming.

iii)

Separate calculation of extreme fiber elongation shall be made for each formed segment (e.g., spherical dished shell plates or dished segments of ellipsoidal or torispherical heads). Need for heat treatment shall be determined for each segment individually using the greatest measured thickness and smallest radius of curvature after forming.

iv)

In case of different forming steps without intermediate heat treatment are employed, extreme fiber elongation is the total amount of elongation of the individual forming steps. In case of intermediate heat treatment, the deformation is that elongation achieved after the last previous heat treatment. This is applicable for all types of formed part.

v)

Filler metal used in items subjected to hot forming temperatures, or normalized, shall satisfy the weld joint design requirements after such heat treatment. This is considering that such welds will generally suffer significant strength reduction.

13.2.13 Bolt tensioning device shall be used for bolting up flanged connections with stud bolts of diameter 1-½ inch and above. Bolt up of flanges, irrespective of bolt diameter shall be according to ASME PCC-1 requirements. 13.2.14 Correction of fit-up offsets of the closing longitudinal butt joint in a rolled shell ring shall be achieved by only employing rolling machine operation until the deviations are within the specified Code tolerances.

Page 36 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

13.2.15 Alignment of pre-formed sections of multi-piece vessel head at butt joints, with fit-up deviations exceeding the Code tolerances, shall be achieved by only reforming (employing pressing machine) the head segments until the deviations are within the specified limits. 13.2.16 Alignment of completely fabricated sections at girth joints (shell ring-toshell ring and head-to-shell ring), with fit-up deviations exceeding the Code tolerances, shall be achieved by only reforming the shell (using rolling machine) or head (employing pressing machine), whichever is out-of-true, until the deviations are within the specified limits. 13.3

Welding 13.3.1

All welding shall be in accordance with the requirements of SAES-W-010.

13.3.2

Dissimilar metal welds (DMW) are not permitted in sulfide stress cracking environment as defined in this specification. Welds in clad systems are acceptable if the DMW interface with the ferritic steel is not in contact with the sour fluid.

13.3.3

Following maximum allowable carbon equivalent, based on thickness (t) shall be met for pressure vessels intended for sulfide stress cracking environment.

13.3.4

14

Thickness (mm)

Carbon Equivalent (%)

6 < t < 60

0.43

60 < t < 100

0.45

t > 100

0.48

The method of weld overlay shall be such as to produce a minimum of 3.2 mm thickness meeting the specified chemical composition of the specified weld overlay material.

Nondestructive Examination 14.1

General 14.1.1

All required Nondestructive Examination (NDE) shall be performed in accordance with inspection procedures that are in complete compliance with ASME SEC V and this specification. This written procedure shall address each inspection method and technique used including acceptance criteria. When required by the purchase order or this

Page 37 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

specification the procedure(s) shall be submitted to Saudi Aramco Inspection Department for approval.

14.2

14.1.2

All Nondestructive Examination, including Magnetic Particle and Liquid Penetrant examinations, shall be performed by personnel certified in accordance with ASNT CP-189, or equivalent National Certification Programs that has been approved by the Saudi Aramco Inspection Department. Personnel responsible for interpretation of Nondestructive Examination results shall be certified to a minimum of Level II.

14.1.3

All required NDE for final acceptance of the vessel shall be performed after the completion of all welding and repairs and prior to pressure testing. In vessels requiring PWHT, all NDE for final acceptance shall be performed after the final PWHT.

14.1.4

All pressure and non-pressure welds shall be visually inspected where accessible. All segments of longitudinal, circumferential or built-up head pressure weld seams covered or rendered inaccessible by internals, lifting lugs or other attachments shall be fully radiographed over the entire affected length plus minimum 5 cm (2 inches) either side prior to installation of the attachment.

14.1.5

Magnetic particle examination or liquid penetrant examination per the applicable Code shall be performed on the surfaces of hot formed and reheat treated parts.

Radiographic Examination 14.2.1

All radiography shall be performed with intensifying screens. Only lead or lead foil (fluoro-metallic) screens shall be permitted unless otherwise approved by the Saudi Aramco Inspection Department.

14.2.2

Tungsten inclusions in Gas Tungsten Arc welds shall be evaluated as individual rounded indications. Clustered or aligned tungsten inclusions shall be removed and repaired.

14.2.3

Radiography examination requirements for weld joints categories A, B, C and D shall be according to Table 1 of this specification and the following: a)

Butt welds connecting forged junction ring, conforming to ASME SEC VIII D2, Figure 4.2.4(e), to shell and head shall be 100% radiographed. Use of ultrasonic examination method that generates permanent records can be used as a substitute to radiography, as applicable (see relevant requirements per Note 3 of Table 1). Page 38 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

b)

14.2.4

14.3

32-SAMSS-004 Manufacture of Pressure Vessels

Butt welds in multi-piece plate blanks to be formed into heads shall be 100% radiographed after forming. Use of ultrasonic examination method that generates permanent records can be used as a substitute to radiography (see relevant requirements per Note 3 of Table 1).

100% radiography examination is required for the following weld joints: a)

Butt welds connecting skirt to forged junction ring, conforming to ASME SEC VIII D2, Figure 4.2.4(e).

b)

Butt welds connecting skirt to weld build-up construction at vessel-to-skirt junction per paragraph 10.2.9 of this specification.

c)

Butt welds connecting forged junction ring according to ASME SEC VIII D2, Table 4.2.5 - Detail 7 to shell and head.

Ultrasonic Examination 14.3.1

Ultrasonic examination requirements for weld joints categories A, B, C and D shall be according to Table 1 of this specification.

14.3.2

All plates in thick wall vessels shall be ultrasonically examined by the Vessel Manufacturer in accordance with ASTM SA578. Acceptance criteria shall be Level C of SA-578.

14.3.3

Plates with thickness more than 12.5 mm (0.5 inch) shall be ultrasonically examined by the vessel manufacturer in accordance with ASME SA-435. Any area where one or more discontinuities produce a continuous total loss of back reflection accompanied by continuous indications on the same plane (within 5 % of plate thickness) that cannot be encompassed within a 25 mm (1 inch) diameter circle is unacceptable.

14.3.4

100% Ultrasonic examination is required for the following weld joints:

14.3.5

a)

Butt-welds in vessel supports.

c)

Full-penetration welds in external attachments (supports, brackets, lugs, etc.) to pressure retaining parts.

All forgings shall be 100% ultrasonically examined by the equipment manufacturer in accordance with ASME SA388. Acceptance criteria shall be in accordance with ASME SEC VIII D2, paragraph 3.3.4.2. Indications per ASME SEC VIII D2, paragraphs 3.3.4.3 and 3.3.4.4 are not acceptable.

Page 39 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

14.4

32-SAMSS-004 Manufacture of Pressure Vessels

14.3.6

100% ultrasonic examination is required for welds attaching vessel directly to skirt and conforming to ASME SEC VIII D2, Figures 4.2.4(a), 4.2.4(b) and 4.2.4(c). Where ultrasonic examination cannot be utilized, due to only construction geometric configuration, the whole joint shall be either magnetic particle (MP) or liquid penetrant (LP) examined after each 6 mm depth of weld deposit and the finished weld surface.

14.3.7

100% conventional ultrasonic examination is required for all full penetration welds in vessel supports. Alternatively, 100% radiography examination shall be used.

14.3.8

Weld build-ups construction at vessel-to-skirt junction per paragraphs 10.2.9 and 10.2.10 of this specification shall be 100% ultrasonically examined.

Magnetic Particle Examination 14.4.1

Permanent magnetic yokes are not permitted.

14.4.2

Prods are not permitted for use on air-hardenable materials, materials that require impact testing, and on the fluid side of pressured components for vessels in wet sour service.

14.4.3

Except for non-Ferro magnetic materials, magnetic particle examination using an AC yoke is required for the following welds: a)

Pressure containing weld joints categories A, B, C and D per Table 1 of this specification.

b)

Welds in vessel support (skirt, saddle, lug, and leg)

c)

Attachment welds to the pressure vessel

d)

Areas where temporary attachments have been removed

e)

Arc strike areas

Internal welds shall be examined with Wet fluorescent MPI. External welds shall be examined with wet visible MPI or Wet fluorescent MPI (Note: if wet visible MPI is used, a white color contrast coating shall be applied prior to the examination). 14.4.4

All edges prepared for welding and all openings shall be magnetic particle examined in accordance with the applicable Code.

14.4.5

Forgings shall be examined on all surfaces, utilizing wet fluorescent magnetic particle method after final machining. All defects shall be Page 40 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

removed and repaired by welding in accordance with SAES-W-010. Exception: Except for welding edges, liquid penetrant examination is acceptable as an alternative to magnetic particle examination.

14.5

Liquid Penetrant Examination For non-Ferro magnetic materials, liquid penetrant examination shall be used for the following welds:

14.6

a)

Pressure containing welds joints categories A, B, C and D per Table 1 of this specification.

b)

Welds in vessel support (skirt, saddle, lug, and leg)

c)

Attachment welds to the pressure vessel

d)

Areas where temporary attachments have been removed

e)

Arc strike areas

Welds Encroachment Where the optimized fabrication layout and/ or process design requirements do not absolutely allow meeting the spacing requirement in paragraph 13.2.6.1 of this specification, NDE per the following table shall be performed. Case

PWHT is required ( Note 1)

1. Nozzle or manway without a reinforcing pad installed onto a butt weld in vessel wall

RT of butt weld in vessel for a length equal to three times the diameter of the opening with the center of the opening at mid-length.

2. Nozzle or manway with a reinforcing pad installed onto a butt weld in vessel wall

(See paragraph 8.5.2 of this specification)

3. Nozzle or manway, without a reinforcing pad, encroaching on a butt weld in vessel wall

RT of butt weld in vessel for a length equal to three times the diameter of the opening with the center of the opening at mid-length.

4. Reinforced nozzle or manway with the reinforcing pad encroaching on the butt weld in vessel wall

N/A

5. Reinforced nozzle or manway with penetration encroaching the butt weld and the reinforcing pad covering it

N/A

(See paragraph 8.5.2 of this specification)

N/A (See paragraph 8.5.2 of this specification)

PWHT is not required Same as when PWHT is required. RT of butt weld in vessel for a length equal to three times the diameter of the opening with the center of the opening at mid-length. The butt weld shall be ground flush prior to installation of the pad. Same as when PWHT is required. RT of butt weld in vessel for a length equal to three times the diameter of the opening with the center of the opening at mid-length. RT of butt weld in vessel for a length equal to three times the diameter of the opening with the center of the opening at mid-length. The butt weld shall be ground flush prior to installation of the pad.

Page 41 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016 Case

PWHT is required ( Note 1)

32-SAMSS-004 Manufacture of Pressure Vessels PWHT is not required

6. Structural attachment, without a reinforcing pad, encroaching on a butt weld in vessel wall

RT of butt weld in vessel for a length equal to the projection of the attachment weld plus a minimum of 50 mm on either side. Minimum length of the radiographed weld is 12 inches.

Same as when PWHT is required.

7. Reinforced structural attachment, with the reinforcing pad encroaching on a butt weld in vessel wall

RT of butt weld in vessel for a length equal to the projection of the reinforcing pad attachment weld plus a minimum of 50 mm on either side. Minimum length of the radiographed weld is 12 inches.

Same as when PWHT is required.

8. Structural attachment, without a reinforcing pad, covering a butt weld in vessel wall

9. Reinforced structural attachment, with the reinforcing pad covering a butt weld in vessel wall

N/A (See prohibition in paragraph 13.2.6.3 of this specification)

N/A (See prohibition in paragraph 13.2.6.3 of this specification)

RT of butt weld in vessel for a length equal to the projection of the reinforcing pad attachment weld plus a minimum of 50 mm on either side. Minimum length of the radiographed weld is 12 inches. RT of butt weld in vessel for a length equal to the projection of the reinforcing pad attachment weld plus a minimum of 50 mm on either side. Minimum length of the radiographed weld is 12 inches. The butt weld shall be ground flush prior to installation of the pad.

10. Structural attachment (with or without reinforcing pads) encroaching: a) Another structural attachment (with or without reinforcing pads) b) Reinforced nozzle or manway

MP or LP on the entire outermost fillet weld of each attachment on the vessel side per paragraph 14.4 or 14.5, as applicable, after completion of all welds in all attachments.

Same as when PWHT is required.

c) Nozzle or manway without a reinforcing pad Note 1:

NDE for final acceptance of the vessel shall be performed after the final PWHT per paragraph 14.1.3 of this specification.

14.7

Hardness Testing Weld hardness testing shall be in accordance with the requirements of SAES-W-010.

15

Postweld Heat Treatment 15.1

Postweld heat treatment shall be done when required by the applicable Code or when specified on the data sheet.

15.2

Code exemptions for postweld heat treatment of ferritic materials based on the use of austenitic or nickel-based electrodes are not permitted for vessels in sulfide stress cracking environments as defined in this specification.

15.3

Code exemptions for postweld heat treatment of P4 and P5 materials are not permitted for applications involving either wet sour or hydrogen services or for materials exceeding 1.25% nominal chromium content.

Page 42 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

15.4

The maximum postweld heat treating soaking temperature for quenched and tempered carbon steel materials shall not exceed the temperature at which the test pieces were heat treated, as shown on the Mill Test Reports or 650°C maximum for carbon steel and 700°C for low chrome alloy steels.

15.5

Time and temperature of post weld heat treatment for carbon steel vessel with potential environmental cracking shall be in accordance with requirements of API RP582.

15.6

Final postweld heat treatment shall follow all welding and repairs but shall be performed prior to any hydrotest or other load test.

15.7

A sign shall be painted on a postweld heat treated vessel and located such that it is clearly visible from grade reading: “Caution-Vessel Has Been Postweld Heat Treated-Do Not Weld”

15.8

16

Postweld heat treatment shall be in accordance with the requirements of SAES-W-010 and this specification.

Examination, Inspection, Pressure Tests and Repairs 16.1

Examination 16.1.1

The responsibility for examination rests with the Vessel Manufacturer in accordance with the applicable Code and the requirements of this specification.

16.1.2

Additional examination of any weld joint at any stage of the fabrication may be requested by the Saudi Aramco Inspector, including repeating examination of previously examined joints. The Saudi Aramco Inspector also has the right to request or conduct independent Nondestructive Examination of any joint. If such examination should disclose nonconformance to the requirements of the applicable Code or this specification, all repair and Nondestructive examination costs shall be done at the Vessel Manufacturer's expense.

16.1.3

All necessary safety precautions shall be taken for each examination method.

16.1.4

Surface irregularities, including weld reinforcement, inhibiting accurate interpretation of the specified method of nondestructive examination shall be ground smooth.

16.1.5

Examination of all welds shall include a band of base metal at least one inch wide on each side of the weld. Page 43 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

16.2

32-SAMSS-004 Manufacture of Pressure Vessels

Inspection 16.2.1

The Saudi Aramco Inspector shall have free access to the work at all times.

16.2.2

Saudi Aramco shall have the right to inspect the fabrication at any stage and to reject material or workmanship, which does not conform to the specified requirements.

16.2.3

Saudi Aramco reserves the right to inspect, photograph, and/or videotape all material, fabrication, coating, and workmanship and any materials, equipment, or tools used or to be used for any part of the work to be performed.

16.2.4

Saudi Aramco may reject the use of any materials, equipment, or tools that do not conform to the specification requirements, jeopardize safety of personnel, or impose hazard or damage to Saudi Aramco property.

16.2.5

All of the rights of Saudi Aramco and their designated representatives for access, documentation, inspection, and rejection shall include any work done by sub-contractors or sub-vendors.

16.2.6

The Vessel Manufacturer shall provide the Saudi Aramco Inspector all reasonable facilities to satisfy him that the work is being performed as specified.

16.2.7

The fabricator shall furnish, install, and maintain in a safe operating condition all necessary scaffolding, ladders, walkways, and lighting for a safe and thorough inspection.

16.2.8

Pressure vessels manufactured in accordance with this specification are subject to verification by the Saudi Aramco Inspector in accordance with Saudi Aramco Inspection Requirements Form 175-321900, Manufacture of Pressure Vessels.

16.2.9

Prior to final inspection and pressure testing, the inside and outside of the vessel shall be thoroughly cleaned of all slag, scale, dirt, grit, weld spatter, paint, oil, etc.

16.2.10 Inspection at the mill, shop, or fabrication yard shall not release the Vessel Manufacturer from responsibility for repairing or replacing any defective material or workmanship that may be subsequently discovered in the field.

Page 44 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

16.3

32-SAMSS-004 Manufacture of Pressure Vessels

Pressure Testing 16.3.1

After completion of all external and internal welding, nondestructive examination, repairs and heat treatment, as applicable, and prior to painting, vessels shall be pressure tested using water as the testing media in accordance with the applicable Code, SAES-A-007 and this specification.

16.3.2

Pneumatic testing in lieu of hydrostatic testing requires the approval of the Manager of the Saudi Aramco Inspection Department.

16.3.3

Hydrostatic test pressure shall be held for a minimum of one hour per 25 mm of vessel thickness and in no case less than one hour.

16.3.4

Pressure testing for acceptance of the vessel shall not be made prior to the final postweld heat treatment.

16.3.5

All welded attachments provided with telltale holes shall be pneumatically tested at minimum 70kPa (10 psi) prior to heat treatment and vessel pressure testing.

16.3.6

Telltale holes in external attachments must not be plugged during the vessel pressure test. Telltale holes in internal attachments must be seal welded prior to pressure testing of the vessel.

16.3.7

The use of shellacs, glues, lead, etc., on gaskets during testing is prohibited. No paint or primer shall be applied to a vessel prior to hydrostatic testing.

16.3.8

The Vessel Manufacturer shall furnish all test materials and facilities, including blinds, bolting, and gaskets.

16.3.9

Hydrostatic pressure testing shall be performed with gaskets and bolting identical to those required in service and as specified on the data sheet. These gaskets may be used as service gaskets if the bolted joint is not disassembled after completion of hydrostatic pressure testing.

16.3.10 The manufacturer shall supply the following: a)

Minimum two sets of spare gaskets with a blind flange for each manway and blinded nozzle in the vessel.

b)

Minimum one set of service gasket set and two sets of spare gaskets for each nozzle with companion flanges in the vessel.

c)

All bolting with minimum 10% spare bolting (3 minimum for each size) per vessel. Page 45 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

16.3.11 Test pressure measured at the top of the vessel shall be: 16.3.11.1

For Division 1 vessels per UG-99(b): PT=1.3 MAWP (S/ST)

16.3.11.2

For Division 2 vessels per 8.2.1: Greater of: i)

PT = 1.43 MAWP

ii)

PT = 1.25 MAWP (ST/ S)

Where, PT

is the minimum test pressure

S

is the allowable stress at design temperature

ST

is the allowable stress at test temperature

ST/S is the lowest ratio for the pressure boundary materials, excluding bolting materials, of which the vessel is constructed. 16.3.12 Water used for pressure testing shall be potable. For vessels manufactured from stainless steel, the water shall not contain more than 50 ppm chlorides with pH value not exceeding 7 at the time of filling the vessel. 16.3.13 Temperature of water during hydrostatic testing shall be maintained at not less than 17°C throughout the testing cycle. 16.3.14 Vertical vessels that are pressure tested in the horizontal position shall be adequately supported such that the primary stresses in any part of the vessel do not exceed 90% of the minimum specified yield strength of the vessel material. 16.3.15 Horizontal vessels shall be tested while resting on their permanent support saddles without additional supports or cribbing. 16.3.16 Vessels shall be protected from being over pressured, while being pressure tested, by use of pressure test relief valve(s) meeting the following: a)

Relief valves shall be of adequate capacity set to relieve at 10% above the test pressure, provided requirements of paragraph 7.12.3 are met. Page 46 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

b)

Sizing of relief valve(s) shall be according to API RP520, Part I.

c)

The relief valve(s) shall be tested, dated, and tagged within one week prior to the pressure test.

d)

The pressure test relief valve shall be accompanied with a calibration certificate that includes the cold differential test pressure (CDTP), test date and the spring range. The CDTP shall be within the spring range.

16.3.17 After completion of pressure testing, the vessel shall be completely drained and thoroughly dried including surfaces of internals. For vessels made completely of stainless steels and vessels internally cladded or weld-overlaid with these materials, pickling and passivation shall be applied according to ASTM A380. 16.4

17

Manufacturing Repairs 16.4.1

The Saudi Aramco Engineer must review and approve crack repair procedures, required by the applicable Code, prior to commencement of repairs. It is the responsibility of the manufacturer to ensure that repairs done by the mill of any material defects, per the applicable Code, are documented.

16.4.2

After completion of repairs required by the applicable Code the following shall be repeated: a)

Heat treatment of the repaired section if it has been heat-treated prior to the repairs.

b)

All nondestructive examinations (radiography, magnetic particle, dye-penetrant, etc.) performed on the repaired section prior to the repairs.

c)

A weld map of all repairs shall be made a part of the final vessel documentation. The weld map shall include the nondestructive examination procedure and results, the welding procedure specifications and stress relief charts.

Nameplates and Stampings 17.1

Each vessel shall be identified by a nameplate and marked with the information required by the applicable Code and the requirements of this specification.

17.2

Vessels manufactured inside and outside Saudi Arabia shall be Code stamped for all services in accordance with the applicable Code. Page 47 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

18

19

32-SAMSS-004 Manufacture of Pressure Vessels

17.3

Nameplates and nameplate mounting brackets shall be located such that they will not be covered by insulation and are easily readable from grade or a platform. Brackets shall extend from the outside of vessel to clear insulation, and with sufficient access for surface preparation, and painting. The nameplate markings as required by the applicable Code shall be stamped or engraved such that the nameplate material is permanently deformed with the symbols.

17.4

Nameplates shall be 3-mm minimum thickness and manufactured from type 304 stainless steel or Monel and continuously welded to the mounting bracket according to PIP VEFV1100.

17.5

The mounting bracket shall be continuously seal-welded and positioned such as not to allow for collection of moisture or rain.

17.6

Nameplate for internally coated vessels shall show: the Saudi Aramco Painting System Numbers, type of coating, brand name, and date of application.

Coatings and Painting 18.1

Type of coating and painting systems shall be as specified on the Vessel data Sheet.

18.2

Surfaces to be coated shall be cleaned and prepared prior to its coating in accordance with SAES-H-100.

18.3

Gasket contact surfaces shall be properly protected from blasting and shall not be coated or painted.

Shipping Requirements 19.1

General 19.1.1

Vessel shall be protected against corrosion during shipping and at fabrication yard and construction sites.

19.1.2

Prior to shipping, vessels are to be completely and thoroughly dried and cleaned from all loose scales, weld slags, dirt and debris to the satisfaction of the Saudi Aramco Inspector.

19.1.3

The Vessel Manufacturer is responsible for ensuring that the vessels and internals being shipped are adequately braced and shall provide temporary supports where appropriate to ensure adequate supporting of the vessel during shipment.

Page 48 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

19.2

32-SAMSS-004 Manufacture of Pressure Vessels

19.1.4

Vessels partially shop fabricated and/or liable to suffer distortion during transit and erection shall be suitably braced. All ends that will be open during shipment shall be covered to prevent ingress of dirt and other foreign matters. The Vessel Manufacturer shall advise the Saudi Aramco Engineer of the method of protection for review and approval.

19.1.5

Markings shall be done with water-insoluble materials that contain no harmful substances that would attack or harmfully affect the vessel at both ambient and design temperatures.

19.1.6

Marking materials shall be free of lead, sulfur, zinc, cadmium, mercury, chlorine, or any other halogens.

19.1.7

Export packaging marking and shipping shall be in accordance with the purchase order.

Internal Protection 19.2.1

Thoroughly dry the internal surface of the vessel. Remove all free water. Thoroughly purge vessel with dry air so that relative humidity inside vessel is less than 40% at the lowest ambient temperature likely to be experienced in shipping and storage.

19.2.2

The interior surfaces of vessels, including internals, shall be protected from corrosion by the use of a nontoxic liquid or powder vapor phase corrosion inhibitor (VpCI) that is compatible with the metallurgy of all components in the equipment being protected and is environmentally friendly for disposal at sea. The chemistry shall be based on amine carboxylates, amine benzoates, or amine oleates with additional components as necessary. Nitrites shall not be used. Following are specific requirements for corrosion inhibitors: 19.2.2.1 Water-soluble liquid products shall provide both vapor phase and contact inhibition. These products shall be applied at the rate of 1 liter per cubic meter of internal space or the minimum specified by the inhibitor manufacturer, whichever is greater. Liquid products are preferred as these are easily removed with the process flow on start up. 19.2.2.2

Ready to spray, oil soluble liquid vapor phase corrosion inhibitors can be used at a surface application rate of 25 to 30 square meters per liter of chemical, or the minimum application rate recommended by vendor, whichever is greater.

Page 49 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

Oil soluble inhibitors will leave an oily film on the interior of the equipment that must be acceptable to the end user. 19.2.2.3 Powders shall be free flowing crystals for ease of application and be environmentally friendly for disposal at sea if necessary. Powder products shall be applied at the rate of 0.3 kg per cubic meter of internal void space or the minimum specified by the inhibitor manufacturer, whichever is greater. Powder can be fogged into the equipment or it can be placed inside Tyvek bags and then placed inside the equipment. Tyvek bags must be removed before start-up. For gas and LNG service, excess loose powder must be removed before start-up by vacuuming or by water rinsing. 19.2.2.4

Products shall be tested per NACE TM0208-2008 and shall provide Grade 3 or Grade 4 performance. When the equipment contains a copper/copper alloy component, the VpCI shall also be tested per Section 7 of NACE TM0208-2008.

19.2.2.5 For any questions on application rates, or any situations requiring clarification or for approval of other products, forms, or chemistries of vapor phase corrosion inhibitors, obtain the prior written approval of the Supervisor, Corrosion Technology Unit, Materials Engineering and Corrosion Control Division, CSD. 19.2.2.6 Vessels must be sealed vapor tight using metallic covers, for inhibitors to be effective. 19.2.3

For vessels made completely of stainless steels and vessels internally cladded or weld-overlaid with these materials, in addition vapor phase corrosion inhibitors applied per 19.2.2, nitrogen blanketing shall be used during shipment or periods of storage at the construction site. To apply nitrogen blanketing, pressurize the vessel to 60 psig with nitrogen and bleed down slowly to 5 psig. Pressurization in this manner shall be repeated 3 times. Bleed down must be slow and controlled to minimize the loss of vapor phase inhibitor. The vessel shall be clearly marked with a warning: “Warning: asphyxiation hazard--preserved with nitrogen.”

19.2.4

For vessels that have permanent internal coatings covering some or all of the vessel internals, the Vessel Manufacturer shall contact the Supervisor, Corrosion Technology Unit, Materials Engineering and

Page 50 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

Corrosion Control Division, CSD, and obtain prior written agreement on required preservation techniques. 19.2.5

Use of non-toxic desiccants is considered acceptable as an alternative internal protection measure against corrosion for vessels ONLY when the warranty will be revoked by using non-toxic vapor phase inhibitor; provided that the following conditions are met: 19.2.5.1 The plan is pre-approved in writing by the Supervisor, Corrosion Technology Unit, Materials Engineering and Corrosion Control Division, CSD. 19.2.5.2 Silica gel application rate shall be a minimum of 3.0 kg per cubic meter of internal space. 19.2.5.3 The vessel shall be maintained 100% vapor tight using bolted metal blind flanges. 19.2.5.4 The plan includes methods and designated responsible persons to evaluate the condition of the desiccant and reapply if necessary. 19.2.5.5 Calcium chloride desiccants shall not be used. 19.2.5.6 The desiccant must be removed on site prior to operating the vessel. Commentary Note: These circumstances have arisen in the past when a vessel is shipped from a manufacturer with a catalyst in place prior to field erection.

19.2.6

19.3

Other preservation products or methods may be applied with the prior written approval of the Supervisor, Corrosion Technology Unit, Materials Engineering and Corrosion Control Division, CSD.

External Protection 19.3.1

The protection of external surfaces shall be obtained by using one of the following: a)

A hard temporary preservative appropriate for the metallurgy of the vessel and can be easily removed at site prior to surface preparation and application of the Saudi Aramco coating and painting system.

Page 51 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

20

32-SAMSS-004 Manufacture of Pressure Vessels

b)

Prepare the surface and apply the complete (primer and final coatings) Saudi Aramco surface preparation, and coating and painting system in the shop.

c)

For solid Stainless Steel vessels, which are to be shipped via ocean freight, shall be protected using a temporary protective system compatible with stainless steel and suitable outdoor exposure.

19.3.2

Telltale holes in reinforcing pads shall be protected with wooden plugs or packed with rust preventative grease.

19.3.3

Flanged connections and all other machined surfaces shall be protected by a coating suitable for the metallurgy of the vessel and can be easily removed in the field. Connections shall be fitted with steel or wood cover, 3 mm thick and neoprene gaskets.

19.3.4

Covers shall be securely attached by a minimum of four bolts equally spaced. For ocean shipment, flanged connections shall also be covered with heavy-duty plastic bags securely taped to the nozzles.

19.3.5

Flanges with permanent blind flanges or covers shall be secured with the gaskets and bolting specified for service.

Drawings, Calculations and Data 20.1

The Vessel Manufacturer shall Prepare drawings, calculations, and data in accordance with NMR-7919-1, Nonmaterial Requirements. Calculations shall include, but not limited to: a.

ASME Code Section VIII calculations.

b.

Wind and earthquake calculations, as applicable.

c.

Support calculations.

d.

Calculations associated with lifting and erecting the vessel

e.

Nozzle load analysis for local and gross effect, when required.

f.

Design of internal and external attachments.

g.

Design loads and load combinations.

20.2

Drawings and calculations that are approved by the Design Engineer shall not relieve the Vessel Manufacturer from the responsibility to comply with the Codes, and this specification.

20.3

Vessel manufacturer shall prepare drawings which indicate the ultrasonic thickness of the vessel shell section, heads and nozzles. An adequate number of Page 52 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

readings shall be taken to represent the actual thickness of the components. 20.4

All approved data sheets, drawings and forms are to be submitted to EK&RD/Drawing Management Unit (DMU) for inclusion into Corporate Drawings Management System.

23 February 2011 22 May 2011 13 December 2011 15 January 2012

Revision Summary Major revision. Editorial revision intended for clarifying some requirements of the document. Minor revision intended to reflect changes to some requirements, which have been already included in the relevant SAES-D-001. Editorial revision intended for clarifying some requirements of the document.

Page 53 of 54

Document Responsibility: Vessels Standards Committee Issue Date: 15 January 2011 Next Planned Update: 23 February 2016

32-SAMSS-004 Manufacture of Pressure Vessels

Table 1 – Nondestructive Examination Requirements Weld Joint Category

Radiography (RT)

Ultrasonic (UT)

Liquid Penetrant (LP) or Magnetic Particle (MP)

A and B

Per Design Code Criteria (Spot or 100%) (1) & (3)

See Notes (2) & (3)

100%

C

100% (3)

100% (3)

100% (6)

D

See Note (4)

See Note (4)

See Note (4)

Notes: (1) 100% RT is required for vessels under any of the following services or design conditions: 

Weld joints requiring full radiography per the applicable code.



Lethal services.



Hydrogen services.



Cyclic services.



Unfired steam boilers with design pressure exceeding 50 psi.



Thick wall.

(2) 100% conventional UT is required for only vessels under any of the services or design conditions per note 1 of this table. (3) 100% UT, employing methods that generate permanent records may be used as a substitute for the combination of 100% RT and 100% conventional UT specified for vessels under common services and design conditions per notes 1 and 2 of this table. Such UT methods must be approved by Inspection Department prior to commencement of any work. (4) Inspection for Category - D weld joint shall meet the following: a)

100% RT and 100% Conventional UT for design conditions/ services Group I per paragraph 8.5.2 of this specification. Alternatively, 100% UT employing methods that generate permanent records can be used, where such methods must be approved by the Inspection Department prior to commencement of any work.

b)

Following design details shall be used where RT is required for Category - D weld joint: i. ii.

For Division 1 vessels: Figures UW-16.1: (f-1), (f-2), (f-3) or (f-4). For Division 2 vessels: Figures 4.2.13: (1), (2), (3), (4), (5) or (6).

c)

Where RT cannot be utilized, due to only joint geometry, 100% UT shall be performed on the joint from an accessible side. If conventional UT method can not be utilized, other UT methods shall be used and must be approved by Inspection Department prior to commencement of any work.

d)

Where RT and UT cannot be utilized, due to only joint geometry, following examination shall be performed: i.

For attachments without a reinforcing pad, the whole joint shall be either 100% magnetic particle (MP) or 100% liquid penetrant (LP) examined at the root pass, after each 6 mm depth of weld deposit and the final weld surface. Where PWHT is required, final surfaces of weld joints shall be examined for acceptance after final PWHT.

ii.

For attachments with a reinforcing plate, similar examination as in (i) above shall be performed at the nozzle. 100% MT or 100% LP shall be also performed on the final surface of the fillet welds attaching the reinforcing pad to vessel and nozzle.

(5) Inspection requirements for connections attached to nozzles and manways per paragraph 8.5.2 shall be according to note 4 of this table. (6) 100% MT or 100% LP shall be applied to the root pass and final surface of lap-welded Category - C weld joint.

Page 54 of 54

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF