PTT PUBLIC COMPANY LIMITED
RATCHABURI WORLD COGENERATION COMPANY LIMITED
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT
0
02/04/13
Issued for Construction
WS
JR
NP
A
13/02/13
Issued for Approval
WS
JR
NP
Rev.
Date
Description
Prepared By
Checked By
Approved By
CONTRACTOR:
CONSULTANT:
SIAM RAJATHANEE JOINT VENTURE
UNITY ENGINEERING AND CONSULTANCY SERVICES CO.,LTD.
DOCUMENT TITLE:
MECHANICAL COMPLETION PROCEDURE
DOCUMENT NO.:
PR-P-1102.21-4012-004
REVISION:
0
DOCUMENT CHANGE RECORD
Rev
Date
Prepared/ Revised By
Reviewed By
Approved By
Description
A
13/02/13
WS
JR
NP
Issued for Approval
0
02/04/13
WS
JR
NP
Issued for Construction
REVIEW STAMP E. Work may proceed. F. Work may proceed. Submit “for Construction” Documents. G. Revise and Resubmit. Work may proceed Subject to incorporation of changes indicated. H. Revise and Resubmit. Work may not proceed. I. Review not required. Work may proceed. Acceptance in any of these categories shall be in no way relieve the Contractor/Supplier of its responsibility for the due and proper performance of the Work in accordance with the Contract/Purchase Order. Name: Sign: Date:
COMMENTS
TABLE OF CONTENT ARTICLE
PAGE
1.
SCOPE.......................................................................................................................................... 4
2.
DEFINITIONS................................................................................................................................ 4
3.
ACTIVITIES................................................................................................................................... 4
4.
CHECKLISTS, FORMS, AND LOGBOOKS..................................................................................5
5.
SCHEDULE................................................................................................................................... 6
6.
VENDOR REPRESENTATIVES.................................................................................................... 6
7.
COMPLETION OF WORK............................................................................................................ 7 MECHANICAL COMPLETION
8
NOTICE OF COMPLETION
9
MECHANICAL COMPLETION CHECKLIST OUTLINE
10
MECHANICAL COMPLETION CHECK LIST
12
FORM TR-1:
PIPING LEAK AND STRENGTH PROOF TEST REPORT (Page 1/2)...............36
FORM TR-1:
PIPING LEAK AND STRENGTH PROOF TEST REPORT (Page 2/2).............37
FORM TR-2:
HYDROSTATIC TEST RECORD.......................................................................38
FORM TR-5:
MEGGER READINGS - GROUND RESISTANCE RECORD............................39
FORM TR-6:
ELECTRICAL TEST RECORD...........................................................................40
FORM TR-7:
SAFETY AND RELIEF VALVE RECORD...........................................................41
FORM TR-8:
INSTRUMENT TEST RECORD (Page 1/2).......................................................42
FORM TR-8:
INSTRUMENT TEST RECORD (Page 2/2).......................................................43
FORM ME-2:
VESSELS........................................................................................................... 44
FORM EE-5:
CIRCUIT BREAKERS........................................................................................45
FORM EE-8: LIGHTING PANELS, INSULATION RESISTANCE, REMOTE TERMINAL DISPLAY (RTD) ........................................................................................................................... 46 FORM EE-9:
ALARM CIRCUIT OPERATION TEST...............................................................47
FORM IE-1:
CONTROLLERS................................................................................................48
FORM IE-2:
DIRECT CONNECTED RECORDERS AND RECORDER CONTROLLERS.....49
FORM IE-3:
ELECTRONIC CONTROLLERS, RECORDERS AND INDICATORS................50
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
1.
SCOPE This Specification describes and clarifies the requirements for mechanical completion and provides a format for the Contractor to carry out these activities. It is intended to expand and supplement, but not to supersede the general terms and conditions of the Contract concerning Completion, and Acceptance.
2.
DEFINITIONS For the purposes of this specification, the following definitions shall apply: Owner
means
Ratchaburi World Cogeneration Company Limited.
Advisor
means
PTT Public Company Limited.
Project
means
Gas Pipeline and Gas Metering and Regulating Station Project.
Consultant
means
Unity Engineering and Consultancy Services Co., Ltd.
Contractor
means
Siam Rajathanee Joint Venture
Vendor
means
The party which supplies materials, equipment, technical Documents/drawings and services to perform the duties specified by Contractor.
3.
ASME
means
The American Society of Mechanical Engineers.
ANSI
means
American National Standards Institute
ACTIVITIES 3.1
Mechanical Completion Means fabrication, construction, physical installation, testing, inspection, and system verification is complete, such that the Facilities are ready for introduction of product. Activities associated with the term pre-commissioning are included in mechanical completion activities and will not be described separately. Mechanical Completion shall also mean that all requirements have been met to begin Commissioning activities, including submittal of commissioning plans and documentation. In general, Mechanical Completion shall include the activities listed below. More detailed activities are included in the attached checklists. •
All civil work shall be complete, including fencing, final grading, and surface preparation
•
Piping systems shall be checked against designs, cleaned, tested for pressure ratings and tightness, dried, inerted, and restored to tight condition in readiness for operation
•
All equipment shall be installed, assembled, inspected, calibrated, adjusted, coldaligned, tested, lubricated, and cleaned as necessary to be ready for operation
•
Elements such as strainers, temporary strainers, and filters shall be installed, cleaned or replaced so that a clean element is in place for commissioning
•
All electrical systems shall be installed, energized, and tested for continuity, insulation resistance, ground fault, and mechanical operation
•
All instrumentation shall be installed, loop checked, set to proper set-points, and calibrated
•
Instrumentation loop checks to the SCADA master shall be completed
•
All modifications and upgrades to the SCADA system shall be completed
•
Probes, coupons, samplers, and other consumables shall be installed
•
Utility and safety systems shall be commissioned and demonstrated to be operational
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
3.2
•
All painting, coating, and insulation work shall be completed
•
All changes and modifications shall be incorporated
•
All functional tests of individual systems shall be performed.
•
All work shall be verified to be in accordance with the proper Specifications, Drawings (Owner and Vendor), codes, and standards
•
Deficiencies identified during Mechanical Completion activities shall be remedied prior to the commencement of Commissioning
•
Mechanical Completion documentation shall be completed and signed
Partial Activities and Exceptions With the approval of Owner, Contractor may subdivide the overall facilities into units and perform mechanical completion activities on these units separately. The units so selected shall be logical, well defined, and beneficial to project scheduling. No special consideration shall ensue as a result of the division of the Facilities into units and Contractual conditions and guarantees for Mechanical Completion of the overall Facilities shall remain in force regardless of the state of activities on the individual units. Contractor may give notice of mechanical completion of a unit with a detailed list of exceptions for items, which are incomplete, defective, or otherwise not in accordance with the Contract. This list shall include all outstanding mechanical completion items and shall show a schedule for completing each exception.
4.
CHECKLISTS, FORMS, AND LOGBOOKS 4.1
General Mechanical Completion checklists and forms will be used for all significant items to be erected, installed, and/or modified under the Contract. Contractor shall prepare these checklists and forms following the general format of the attached samples (mechanical completion only - Contractor to generate forms and checklists for commissioning), modified as necessary for individual equipment and systems. Contractor shall submit these forms for Owner approval at least thirty days prior to initiating the inspection, test, and verification activities covered by the checklists and forms. Contractor shall prepare and use logbooks for all activities carried out during Commissioning. At a minimum, Contractor shall maintain a general logbook noting for each shift the personnel onsite, events, activities, process conditions and changes, and results of any tests or inspections. Contractor shall also maintain records of system status (such as valve position and equipment hand-off-auto position) and temporary conditions (such as jumpers installed/removed and valves out of service). To allow accurate reconstruction of events in the case of an upset condition, Contractor shall have available onsite a camera and shall record instrument readings, control panel readings, and other relevant information.
4.2
Procedure The checklists and forms prepared by the Contractor and as approved by Owner shall be used as sign-off sheets for the permanent record of inspections, tests, and mechanical completion activities. These shall be signed by Contractor, Owner’s representative, and any Subcontractors or Vendors as applicable. No system or unit shall be considered mechanically complete if any items included in the checklists or forms are not fully signed. Checklists, forms, reports, or other special documentation required by Vendors or Owner shall be completed and considered a part of mechanical completion in the same manner as above. Copies of these documents shall be reproduced by the Contractor in as many copies as required and shall become part of the permanent project records.
4.3
Introduction of Natural Gas Contractor shall recognize that the introduction of natural gas to any portion of the Work is a hazardous activity requiring the full knowledge and approval of all parties involved, including
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
Contractor’s staff, Owner and Owner’s representatives, and the owners of the existing facilities. In addition, the following criteria shall be met for introduction of natural gas: •
The unit shall be mechanically complete, with any exceptions approved by Owner as described above
•
All utility and safety systems, such as firewater, vent and flare, closed drains, instrument air, and electrical, shall be completed and operational
•
The work area around the unit is safe, secure, and clean of all debris, unnecessary equipment, and excess materials
•
A work permit system for hot work, cold work, vessel entry, etc shall be in force
•
Detailed emergency and evacuation procedures shall be approved by Owner for such events as fire, loss of power, loss of instrument air, overpressure, and excessive condensate buildup
•
Procedures for shutdown and standby shall be approved by Owner
In the case of a threat to the safety of personnel or equipment during commissioning, Owner may require Contractor to halt activities, place the Facilities in a safe condition, and remedy the cause of the threat if within the power of the Contractor. If product has been introduced, such work may include depressurization and/or purging to render the Facilities safe. 5.
SCHEDULE As required by the Contract, Contractor shall prepare complete schedules for mechanical completion activities. Schedules for such units shall allow the contractually defined dates to be met.
6.
VENDOR REPRESENTATIVES 6.1
Mechanical Completion Contractor shall schedule vendor representatives to be onsite to aid in mechanical completion activities as necessary. At least 60 days prior to Mechanical Completion, Contractor shall submit for Owner’s review a list of vendor representatives to be brought to the site and a schedule showing their planned arrival and departure dates. Owner may request additions to this list. Notwithstanding the planned departures shown on this schedule, each vendor representative shall remain onsite until his equipment is fully commissioned.
6.2
Training As required to meet the Contractor’s requirements for training, the scheduling for vendor representatives shall also include ample time to provide specialized training to Owner on the vendor’s equipment. The vendor’s representative shall bring sufficient training materials, aids, and documentation as needed to complete the training requirements.
7.
COMPLETION OF WORK Completion of the Work and the sequence of Notice and Acceptance shall be as defined in the Contract. Contractor shall remain fully responsible for the Facilities and all expenses incurred between the Start of Regular Operations and Owner’s issuance of the Certificate of Acceptance. The following conditions for completion shall be met, at a minimum: •
Facilities shall be mechanically and structurally complete, inspected, tested, and operable at full design pressure
•
Facilities shall be in a tight and clean condition, and otherwise prepared as described in the Contract
•
All checklists and documentation shall be complete and signed
•
Contractor shall have issued the Notice of Start of Regular Operations to Owner.
•
All required manuals, accounting records; quality control reports and documents, as-built data, and other documents shall have been prepared and delivered in accordance with the Contract
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
•
All deficiencies identified by Owner shall have been remedied
•
Any disturbed land and facilities shall have been appropriately restored and all required landscaping shall be completed
•
All Contractually required training shall have been completed
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
MECHANICAL COMPLETION TO:
DATE : UNITS : ____________ SUBJECT: Mechanical Completion and Acceptance
ATTN:
REF NO:
Gentlemen: In accordance with the Contract, the following item(s) is (are) ready for commissioning: ITEMS
EXCEPTIONS
Please sign and return two copies in acknowledgement of your acceptance. Very truly yours,
CONTRACTOR
CERTIFICATE OF ACCEPTANCE (Mechanical Completion) Owner BY DATE
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
NOTICE OF COMPLETION TO:
DATE :
UNITS : ___ SUBJECT: Completion of Construction and Acceptance ATTN:
REF NO:
Gentlemen: Work has been completed on the item(s), unit(s), facility(ies), or plant(s) listed below. This Work is in accordance with all plans, specifications, and official instructions from Owner and articles of the Contract. ITEMS
EXCEPTIONS
Please sign and return two copies in acknowledgement of your acceptance. Very truly yours,
CONTRACTOR
CERTIFICATE OF ACCEPTANCE
Owner BY DATE
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
MECHANICAL COMPLETION CHECKLIST OUTLINE I.
PIPING Check list against Piping and Instrumentation Diagrams (P&IDs) Check list against Piping Arrangement and Isometric Drawings
II.
III.
ELECTRICAL A.
Area Classification
B.
Service Conditions
C.
Circuit Breakers, Switchgear and Motor Control Center
D.
Main Power Supply
E.
Auxiliary Power Supplies
F.
Wire and Cable
G.
Conduit Systems
H.
Electronic Instrument Loops
I.
Ground System
J.
Transformer or Generator Neutral Resistance Ground
K.
Lighting
L.
Control Stations
M.
Cathodic Protection
INSTRUMENTATION A.
General Check List
B.
Inspection and Calibration of Instruments 1.
Manufacturer's Check Lists
2.
Differential Pressure Type Flow Meters
3.
Orifice Plates
4.
Differential Level Transmitters
5.
Level Switches
6.
Flow Switches
7.
Pressure Switches
8.
Temperature Switches
9.
Miscellaneous Switches
10.
Gage Glasses
11.
Pressure Gages
12.
Pressure Instruments
13.
Temperature Instruments
14.
Control Valves
15.
Safety and Relief Valves
16.
Regulators
17.
Instrument Piping and Tubing
18.
Analytical Instruments and Specialties
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
IV.
19.
Receiver Instruments and Control Panel
20.
Annunciators
21.
Annubars
22.
Detection and Safety Devices
23.
Interface to SCADA
EQUIPMENT Vessels, Tanks and Drums
V.
FLUSHING AND CLEANING
VI.
OTHER FACILITIES A.
Safety and Fire Protection
B.
Concrete Placement and Testing
C.
Roads, Fences and Gates
D.
Soil Compaction
E.
Waste Disposal
F.
Documentation
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
MECHANICAL COMPLETION CHECK LIST This Mechanical Completion Check List is intended to assist Contractor to develop the documentation required to prepare the work for Commissioning. Items not explicitly listed but reflected in specifications or on drawings shall from part of the scope of this activity. Contractor shall be responsible to ensure that all components and systems shown on the various contract documents are properly verified after incorporation into the work to the ultimate satisfaction of the Owner.
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM 111111112.2
PERFORMED: CONTR.
WITNESSED: PTT OTHER
PIPING
Prior to hydrostatic test of station piping, it is necessary to check the station for complete conformance with the final piping and instrumentation diagrams. The final inspection must include the Owner operations representatives. It may be a combined operations, contractor and engineering effort. This check will help to reveal any errors and prevent retest of the piping in case omissions and errors are found and corrections have to be made. A thorough check must be made of all piping supports, spring hanger settings and spring support settings, anchors and welded attachments. If any welded attachments are found to be incorrect and must be changed, or if some have been omitted and have to be added, this should be done prior to hydrostatic testing if possible. If this is not possible, the welding performed after pressure test must be thoroughly supervised and carefully inspected after completion. 3. All piping systems must be checked for proper venting and draining. Check for proper slope where required.
_______
________
________
4. Is there any configuration not previously observed or corrected likely to result in hydraulic shock (water hammer), slug flow or vapor binding?
________
________
________
5. Check accessibility of all operating valves.
________
________
________
6. Check all valves for correct body material, trim and packing.
________
________
________
7. Check pipe valves and fittings for specification material, correct size, type, pipe schedule, flange rating, and metallurgy.
________
________
________
8. Check all bolted joints for proper studding, bolt length and gasket material.
________
________
________
9. Check for expansion and vibration. Check for adequate, proper and safe supports, undue stresses and alignment.
________
________
________
10. Operate all hand valves. Check for chain wheels where required, platforms and ladders. Grease all stems and hand wheels.
________
________
________
11. Check all check valves for proper flow direction.
________
________
________
12. If internal lining or sleeves are specified, are they in place? Any wear plates left out?
________
________
________
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR.
WITNESSED: PTT OTHER
13. Has stress relief been performed where required? If cold springing specified, has this been checked?
________
________
________
14. Check connections and branch piping for proper reinforcement.
________
________
________
15. Check to see that unusual or excessive piping loads and temperature strains have not been imposed on pump flanges.
________
________
________
16. Check all lubricated valves for proper lubrication as recommended by the manufacturer for the service in which the valve is to function. Verify standardization with depot personnel.
________
________
________
17. Check installation and stroke of valve operators and their lubrication and limit settings.
________
________
________
18. Check motor valve settings for proper support accessibility.
________
________
________
19. Blank off all relief valves prior to testing piping systems.
________
________
________
20. Hydraulically or hydrostatically test all pipe in accordance with applicable codes and specifications and complete Owner Form TR-1. Provide hydrostatic test record, such as form TR-2 to supplement Owner form, properly witnessed by Owner. Do not test through instruments or rotating equipment.
________
________
________
21. Perform any special tests required by the Contract specifications or drawings. Complete any required records.
________
________
________
________
________
________
________
________
________
________
________
________
22. Has blowing and/or flushing been performed? Most debris and dirt should have been routinely removed during construction. Avoid flushing dirt and debris from one section to another where it may become lodged. Do not flush into instrument take-offs. (See Flushing and Cleaning, Section V). 23. After flushing is complete and piping reassembled, check for installation of start-up strainers on pumps as specified by the drawings and specifications. Strainers must be in place before equipment has final alignment check. Check and remove any blinds used during construction and test. 24. Check to see that proper orifice plates, pressure gauges, sample valves, thermowells and other such accessories are installed as per drawings and specifications. Orifice plates should be installed after prestart flush.
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR.
WITNESSED: PTT OTHER
25. Check to see that all insulation, whether for process, noise, or personnel protection required at start-up, is installed.
________
________
________
26. Is all sentinel drilling (tell-tale holes) complete?
________
________
________
27. Special procedures are required when air or moisture must be removed or excluded. Has this work been performed?
________
________
________
28. Checks if Stamp and data reports that are required for API 5L Piping Standards are in place. Check if ASTM data reports that are required are in place.
________
________
________
29. Make the necessary tie-ins at the unit limits as required by the drawings and specifications.
________
________
________
30. Prepare operating (live) systems for safe tie-ins.
________
________
________
________
________
________
31. Install car seals or locks on valves designated as car sealed or locked valves. Check and record position of all car sealed or locked valves.
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR.
PTT
WITNESSED: OTHER
3.32 ELECTRICAL Contractor shall prepare a comprehensive Mechanical Completion form for each set of electrical connections and electrical loops to supplement: instrument data sheets, including electrical wiring and electrical connections to equipment furnished for the Work. Contractor shall follow the requirements in the Electrical Installation Specification; Vendor supplied instructions, instruction provided in this section and directions received from Owner. 33.
Area Classification Check that all equipment is suitable for the relevant area classification.
________
________
________
Service Conditions Check that all material meets the conditions specified in the plan drawings.
________
________
________
1. Equipment shall be visually inspected for damage and missing parts, and thoroughly cleaned of any dirt, debris or foreign material accumulated during construction.
________
________
________
2. All field wiring shall be checked for connection to proper terminals.
________
________
________
3. All components shall be megger tested (600-volt megger) minimum reading to be one (1) megohm, before being energized.
________
________
________
4. Make continuity checks of all circuits simulating actual operating conditions as far as possible without energizing equipment.
________
________
________
5. Verify that instruments, instrument transformers, relays, fuses and other devices are of proper type, size and rating, in accordance with relay and fuse coordination information provided.
________
________
________
6. With breaker in test position, test operation with local, remote and manual operation.
________
________
________
________
________
________
________
________
________
________
________
________
34.
C.2 Circuit Breakers, Switchgear and Motor Control Centers
7. Secure approval equipment.
of
Owner
to
energize
8. Induction type relays and other protective devices shall be set and tested per manufacturer's recommendation. 9. All seals in conduit shall be checked to determine if installed correctly and properly filled with approved sealing compound. 10. Fences and other enclosures for high voltage
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR. apparatus must be complete and locks installed on gates.
PTT
WITNESSED: OTHER
________
________
________
4. Before closing main breaker, check phase rotation and voltage.
________
________
________
5.
________
________
________
7. Check battery and charger for damage and check electrolyte for level and specified gravity. Follow manufacturer's pre-commissioning instructions.
________
________
________
8. Check emergency generator and automatic transfer equipment for automatic starting, generation and transfer with simulated loss of normal power.
________
________
________
9. Check UPS static "no-break" power system for AC and DC input voltage and check that output is "no-break" by simulating loss of AC supply and loss of battery.
________
________
________
________
________
________
________
________
________
13. All high voltage cables (above 600 volts) shall be given a high potential test according to manufacturer's instructions. This test shall be at a voltage not less than IPCEA or AEIC standard voltage test. Cable shall be tested on reel as soon as possible after delivery and again after installation (DC Volt to be applied 10 min.).
________
________
________
14. Cable runs shall be tested with a megger prior to high-potential test.
________
________
________
D.3 Main Power Supply
Energize feeders.
E. 6Auxiliary Power Supplies
F.10
Wire and Cable
11. 600-volt wiring and cable shall be inspected for mechanical defects at time of installation. Wire with damaged or non-concentric insulation shall not be used. All 600-volt wire shall be tested with a megger and shall show minimum reading as indicated in (2) to ground or between each wire and all others in a common conduit or raceway. 12. The insulation resistance will vary with conditions; the following should serve as a guide: Wire Size Insulation Resistance #12 & smaller (4mm2) 1 megohm #10 to #8 (6/10mm2) 500,000 ohms #6 to #2(16/35 mm2) 400,000 ohms #1 to #4/10 (50/95 mm2) 300,000 ohms 250 thru 750 MCM (120/300 mm2) 200,000 ohms
15. All potheads or cable terminations installed on the site shall be given the same high potential test as
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM the cable to which it is attached. 16. Complete Form EE-8 (typical) where applicable.
PERFORMED: WITNESSED: CONTR. PTT OTHER ________ ________ ________ ________
________
________
18. Underground – Check for compliance with construction drawings.
________
________
________
19. Above Ground - Check for compliance with detailed design drawings and the construction specification.
________
________
________
21. Check all terminations for proper and tight connections, check loops for continuity and accidental ground.
________
________
________
22. Inspect all terminal boxes for drains, cable seals and moisture.
________
________
________
23. Check for proper type RTD wire. Use Form EE-8 (typical) if necessary.
________
________
________
24. Check power supply and fuses at control board, control loops and field instruments. Use Form TR-6 (typical).
________
________
________
26. The ground system should be inspected for defective or incomplete connections.
________
________
________
27. Measure actual resistance to ground at the ground loop or grid with a ground resistance megger.
________
________
________
28. Check resistance to ground of all equipment and tanks that connect to individual ground rods. Each ground should test 5 ohms or less.
_______
________
________
29. Verify integrity of separate "instrument ground" needs.
________
________
________
30. Complete Form TR-5 (typical).
________
________
________
32. For resistance grounding: Check grounding transformer, resistor, current transformer, and relay for size and rating.
________
________
________
33. Set relay in accordance with relay coordination settings.
________
________
________
G.17
Conduit Systems
H. 20Electronic Instrument Loops
I.25 Ground System
J.31 Transformer or Generator Neutral Ground
K.34 Lighting
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR.
PTT
WITNESSED: OTHER
35. All light fixtures and convenience outlets shall be checked for proper voltage and operation.
________
________
________
36. Floodlights shall be checked at night and directed to obtain correct lighting design illumination levels.
________
________
________
37. Verify all illumination levels.
________
________
________
________
________
________
41. Check continuity of system.
________
________
________
42. Turn on and adjust current as appropriate before piping is placed in service.
________
________
________
43. Balance CP circuits after piping is put in service with pipeline CP.
________
________
________
L.38 Control Stations 39. Check out manual control stations. M.40 Cathodic Protection
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR.
WITNESSED: PTT OTHER
4.3544 INSTRUMENTATION Contractor shall prepare a comprehensive Mechanical Completion form to supplement each instrument data sheet furnished for the Work Contractor shall follow the requirements in the applicable Specifications, Vendor supplied instructions, instructions provided in this section and directions received from Owner. 36. General Check List 45. Check to see that specification materials have been used in the installation of instrument distribution piping, connecting tubing, and fittings.
________
________
________
46. Check all instrument loops for proper installation in accordance with the latest approved drawings.
________
________
________
47. Check to see that all parts are accessible.
________
________
________
48. Check to see that control lines are not in contact with hot lines or equipment.
________
________
________
49. Check to see that instrument air dryers and filters are working properly.
________
________
________
50. Check to see that all parts, including instrument piping and tubing, are properly supported and protected from possible damage due to operating or maintenance activities in the area.
________
________
________
51. Check to see that the power to valves and gas to instruments supplied with air by lateral lines or tubing is ready to be filled with air.
________
________
________
52. Warning hydrotest.
________
________
________
53. All piping and tubing is to be cleaned by disconnecting at both ends and blowing out. All instrument air distribution piping shall require a pneumatic test with air. Tubing shall be tested for leaks with an air bubbler in accordance with ISA standards.
________
________
________
54. After lines are cleaned and tested, they should be immediately capped or connected to the instrument to prevent any contamination or water from entering. The loop drawings should be used to record this test and cleaning. Complete Form TR-8 (typical).
________
Isolate
instruments
during
________
55. Check to see that lighting is adequate for
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
________
ITEM operations and maintenance. Check at night. 37.56
PERFORMED: WITNESSED: CONTR. PTT OTHER ________ ________ ________
Inspection and Calibration of Instruments
57. Manufacturer's Check List 2. Calibrate instrument and control system in accordance with manufacturer's information and instrument data sheets.
________
________
________
3. All instrument elements should be checked against design data for correctness of location, connection, labeling, and range of measurement.
________
________
________
4. Check to see that all measuring elements, control valves, or other instruments removed for the flushing and cleaning operation are replaced and connected.
________
________
________
5. Operate all hand valves instrument air supply valves.
________
________
________
6. Check to see that all electrical circuits are tested. Grounding for safety and shielding is to be checked.
________
________
________
7. Control valves should be tested for proper response to their control devices and for proper action on signal failure.
________
________
________
8. Alarm devices and automatic safety switches are tested. Shutdown systems are to be checked. Set all switches in accordance with instrument data sheets.
________
________
________
9. Maintain a log of instrument calibrations.
________
________
________
10. The calibration of transmitters, controllers, etc., shall be checked to comply and meet manufacturer's guaranteed accuracy’s.
________
________
________
11. Each control valve shall be checked by local pressure reduction to comply with and meet manufacturer's guaranteed accuracy’s.
________
________
________
12. Set all controllers with preliminary modes per Vendor's documentation.
________
________
________
13.Complete Form IE-1 (typical) as required.
________
________
________
including
14. All thermocouples and RTDs are to be checked in a single operation from the thermocouple to the indicator at the panel board. After disconnecting the wires from the element, the calibration of PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR. the indicator is to be checked at three points or more by the use of a potentiometer.
WITNESSED: PTT OTHER
________
________
________
________
________
________
a. Bench calibrate against a standard water column manometer at three points (zero, line 5 and line 9).
________
________
________
b. Complete manufacturer's check list.
________
________
________
a. Check nameplate data.
________
________
________
b. Check for an upstream sharp edge.
________
________
________
Measure and record bore with inside micrometer to ensure compliance with specifications.
________
________
________
Check material.
________
________
________
17. Bench calibrate against a standard water column manometer at three points
________
________
________
18. Use a precision output meter or gage to monitor output
________
________
________
19. Fill seal legs.
________
________
________
20. Complete manufacturer's check list.
________
________
________
________
________
________
22. Check and set differential pressure types using standard water column manometer.
________
________
________
23. Mechanically check only - through-flow types.
________
________
________
15. Install seal fluids where Properly seal instruments.
required.
2. Differential Pressure Type Flowmeter
3. Orifice Plates
c.
d.
4.16 Differential Transmitter
Pressure
Type
Level
5.21 Level Switches Check mechanical movement against output on float or displace types. No calibration required.] 6. Flow Switches
7.24
Pressure Switches
25. Check using a hydraulic or dead-weight
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR.
WITNESSED: PTT OTHER
test and set to the required alarm and/or trip point.
________
________
________
26. Set receiver types to the required trip point using a precision pressure gage.
________
________
________
________
________
________
________
________
________
________
________
________
31. Install as received.
________
________
________
32. Clean and check illuminators and check protectors and other accessories.
________
________
________
33. Do not replace any broken glasses without proper instruction and torque wrenches. Clean broken glass from piping.
________
________
________
11.34 Pressure Gages 35. Gages are subject to construction damage and should not be installed until immediately prior to commissioning.
________
________
________
36. Do not calibrate direct connected, bourbon-tube type gages, but where required zero instrument prior to installation.
________
________
________
37. Receiver-type pressure gages shall be three-point calibrated using a precision pressure gage and precision air regulator.
________
________
________
38. Draft gages, diaphragm type shall be three-point calibrated using a water column manometer.
________
________
________
39. Glass tube manometers and draft gages shall be filled with the proper fluid and properly zeroed.
________
________
________
8.27
Temperature Switches
28. Bench check using temperature bath.
a
controlled
29. Set to required alarm and/or trip point. 9.30
Miscellaneous Switches - Solenoid valves, electrical relays, timers, pushbuttons, etc. shall be checked for proper operation.
10. Gage Glasses
12.40
Pressure Instruments
41. Pressure and pressure differential transmitters and transducers shall be three-point bench calibrated using a
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR. hydraulic or dead weight tester prior to installation. A precision output meter or gage shall be used to monitor the output.
WITNESSED: PTT OTHER
________
________
________
________
________
________
44. Gages are subject to construction damage and should not be installed until immediately prior to commissioning.
________
________
________
45. Prior to installation, filled system instruments shall be three-point bench calibrated using a controlled temperature bath.
________
________
________
46. Thermocouple transducers shall be calibrated using a portable precision potentiometer in place in the racks.
________
________
________
47. The multi-point temperature indicator calibration shall be checked using a portable precision potentiometer.
________
________
________
48. Temperature recorder calibration shall be checked using a portable precision potentiometer.
________
________
________
49. Complete Form IE-2 (typical) and manufacturer's check list as needed.
________
________
________
50. Bi-metallic dial thermometers shall not be calibrated but the dial or the pointer reset shall be set to the known ambient temperature before installing.
________
________
________
51. Thermocouples shall be checked for type, polarity, double reversals, shielding, and proper point identification.
________
________
________
53. All diaphragm and piston-operated control valves shall be pneumatically stroked using a pressure regulator and pressure gage against the spring range shown on the nameplate. Mechanical seating and travel shall be checked against the nameplate. It is desirable that this check be made in the shop prior to installation.
________
________
________
54. Valve positioners shall be calibrated on the control valve in accordance with the instrument specifications. Split range positioners shall not have bypasses and shall be carefully checked.
________
________
________
42. Complete manufacturer's check list. 13.43
14.52
Temperature Instruments
Control Valves
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR.
WITNESSED: PTT OTHER
55. Prior to installation, electropneumatic valve transducers shall be bench calibrated with a portable or bench power supply and meter and output gage. If transducers are received mounted on valves, calibration should be done in place.
________
________
________
56. Control valve accessories, such as handwheels, booster relays, etc., shall be operationally checked.
________
________
________
57. All control valves shall be carefully checked by nameplate data and specifications and lubricated as required.
________
________
________
58. Butterfly valves shall be carefully checked to see that the vane moves freely into the upstream and downstream piping. Throttling butterfly valves shall be set for maximum travel in accordance with the vendor's data.
________
________
________
60. Check all safety valves for proper nameplate setting as per the valve and instrument specifications.
________
________
________
61. Test all relief and safety valves for proper relieving pressure and possible leakage before installation. This test shall be performed by a qualified person. Qualified person is one who as attended a school of instruction or received training pertinent to the equipment involved.
________
________
________
62. Where seals are found broken on relief valves, the relief valve is to be retested and resealed in accordance with plant safety practice.
________
________
________
63. Where block valves are permitted under the relief valve, they shall be full line size and locked in the open position.
________
________
________
64. Where rupture discs are used to isolate the safety valve from process fluid, their pressure rating is to be checked.
________
________
________
65. Conduct all operating tests required by code, law and insurance.
________
________
________
15.59
Safety and Relief Valves
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: WITNESSED: CONTR. PTT OTHER ________ ________ ________
66. Complete Form TR-7. 16.67
Regulators
68. Install self-contained pressure and temperature regulators as received.
________
________
________
69. Check inlet and nameplate data.
________
________
________
71. Check against specifications.
________
________
________
72. Verify correct installation.
________
________
________
74. Calibrate analyzers and sampling systems, using product samples where furnished.
________
________
________
75. Check recording, peak-picking, alarm interrupt circuitry. (Manufacturer to calibrate after installation.)
________
________
________
76. Package instrument systems shall be carefully checked and calibrated to vendor's specifications.
________
________
________
78. Check all instrument nameplates, both front and rear, and all panelboard nameplates for tag number, service, location, and proper spelling.
________
________
________
79. Install and check all charts and scales for range in accordance with specification.
________
________
________
80. Calibrate all principal front-of-panel, rearof-panel, and rack mounted instruments in accordance with manufacturer's instructions.
________
________
________
81. Panel instrument calibration test instruments shall be precision devices and shall be the standard for loop matching.
________
________
________
82. Check loop matching, such as zeroing transmitter to receiver.
________
________
________
83. Pressure test all signal air lines to ensure leak tightness.
________
________
________
84. Check all wiring for continuity.
________
________
________
17.70
18.73
19.77
outlet
ports
and
Instrument Piping and Tubing
Analytical Instruments and Specialties
Receiver Instruments and Control Panels
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR. 85. Perform megger tests for proper grounding and no shorts. Use Form TR-5 (typical).
WITNESSED: PTT OTHER
________
________
________
87. Check nameplates for engraving, spelling, and proper location.
________
________
________
88. Check operation and point continuity by mechanically actuating all trouble contacts for low-high-deviation alarm operation, auxiliary contact operation and sequence. Use Form EE-9.
________
________
________
________
________
________
________
________
________
20.86
Annunciators
21.89 Check operation and calibration of all annubars 22. Check all detection and safety devices. Are they property calibrated? Do they initiate the proper alarms and shutdowns upon activation? 23. Interface to SCADA a.
b.
Check transfer of digital inputs from field to SCADA display screen.
__________
_________
________
Check 0, 25, 50, 75, and 100% rising and falling levels for each analog input to SCADA display screen.
___________
_________
________
__________
_________
________
__________
_________
________
__________
__________
_______
c. Check frequency inputs at 10 Hz and maximum frequency to SCADA display screen. d. Check control outputs from SCADA command to end device in field. e.
Check analog setpoints from SCADA output to end device. Verify that feedback of setpoint is correctly shown on SCADA display with controller in local and remote.
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR.
WITNESSED: PTT OTHER
5.3858 EQUIPMENT Contractor shall prepare a comprehensive Mechanical Completion form for each unit shown in the Equipment List as furnished for the Work. Contractor shall pre-plan and notify Owner in advance when manufacturer's representatives or service engineers are to be present at the job site to implement the Mechanical Completion program. Contractor shall follow the requirements in the applicable Specifications, Vendor supplied instruction, instructions provided in this section, and directions received from Owner. Vessels, Tanks and Drums Contractor shall verify under this section: Completeness of gas dehydrators, dryers, filters, flame arrestors and silencers. 1.
__________
________
________
__________
_________
________
___________
_________
________
__________
_________
________
__________
__________
________
__________
__________
_______
Internal Inspection Before the final bolting of cover plates on manways, the interiors of the vessels must be inspected for cleanliness, completeness, and proper installation of internal components. Metallurgy of internals and interior cladding must be checked. Measurements and locations of internals must be verified as to drawings and specifications. This check shall be a joint inspection with Owner. A more detailed check list is given below. a.
Are all nozzles. Pipes. And internals installed at proper location with correct orientation and clearances as shown on the drawings and called for in the vessel specification ? b. Are all internals fabricated of proper materials as per the vessel specifications? Are cladding. lining. And wear plates installed as specified and of proper metallurgy ? c. Check tightness of all bolting, fitting, and positioning of vessel internals. d.
Are all thermowells in correct position and of correct alloy and length? Are level control or indicator floats of proper size and free to move, with stilling wells were specified?
2.
External Inspection a. b.
Are all specified nozzles and other connections installed at proper location? Are all valve connections for sampling or
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR.
WITNESSED: PTT OTHER
__________
__________
_______
__________
__________
_______
Are all ladders and platforms installed? Are there any safety hazards such as piping, valves, conduits too close to ladder rails?
__________
________
________
If vessel requires pressure test separately connected piping, has this been done? Complete From TR-2 (typical).
__________
__________
________
__________
__________
________
___________
__________
_______
5.3858 EQUIPMENT Contractor shall prepare a comprehensive Mechanical Completion form for each unit shown in the Equipment List as furnished for the Work. Contractor shall pre-plan and notify Owner in advance when manufacturer's representatives or service engineers are to be present at the job site to implement the Mechanical Completion program. pressure installed and at correct locations? c. Are all thermowells installed? d. rungs and e. form f.
Are all required pressure relief valves installed? Do nameplate pressure settings agree with specifications? If the assignment includes testing, has this been done? g. Is all lifting gear, such as davits, etc., in place? (As per drawings) i.
Are adequate vents and drains provided? Plugs or valves installed? Make check for plastic shipping plugs that must be removed and replaced with specification steel plugs for vessel rating and service.
_________
__________
________
Are plugs removed from “tell-tale” holes in reinforcing pads? Pipe vent outside using ¼” open end pipe.
_________
___________
________
Is electrical grounding system complete?
_________
___________
________
_________
_________
________
m. Special procedures are required when air or moisture must be removed or excluded. this work been done?
_________
_________
________
n. Check adequacy of lighting. This should be done at night with cooperation of Owner.
_________
_________
________
_________
_________
________
j. insulation k.
o. Is painting complete?
Has
3.
required
before
start-up
is
Complete typical Form ME-2.
ITEM
PERFORMED: CONTR.
6.3959 FLUSHING AND CLEANING 40. All piping and vessels should be thoroughly cleaned of loose scale and internal debris that
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
WITNESSED: PTT OTHER
ITEM 5.3858 EQUIPMENT Contractor shall prepare a comprehensive Mechanical Completion form for each unit shown in the Equipment List as furnished for the Work. Contractor shall pre-plan and notify Owner in advance when manufacturer's representatives or service engineers are to be present at the job site to implement the Mechanical Completion program. accumulates during construction. Flush or blow lines to remove the bulk of this loose material. A large part of this flushing can be accomplished by removing water from lines and equipment after hydrotesting or during the run-in of pumps. During test and flushing operations all lines and systems must be checked for proper drainage and venting. Most of the process and auxiliary lines may be flushed through established circuits from vessels, which are filled with water for that purpose. A single filling of a vessel may not provide adequate water for flushing all lines for which it is a reservoir, in which case a continuous or intermittent flow of water into the vessel should be maintained. Water may be admitted to most vessels via temporary connection to a nozzle on the bottom outlet line. If washing of the vessel itself is a primary object, introduce water into the top of the vessel by hose connection or by other means. Overhead lines may be flushed by overflowing the related vessel. When washing lines from a vessel always be certain that the vessel is adequately vented to prevent a vacuum condition. Verified?
PERFORMED: CONTR.
________
WITNESSED: PTT OTHER
________
41. In any system to the greatest extent possible, flush downward or horizontally, and out at low points. The low point discharge openings will usually be temporary openings made by disconnecting flanges or fittings; normal drains may be used for flush outlets provided they are equal to line size or nearly so. For best results, there should be no restriction at the outlet or any other point in a line undergoing cleaning; where it is necessary to throttle the flushing flow, do so at the supply end. The higher the velocity of flushing, the more thoroughly a line will be cleaned. With a limited supply of flushing medium, do not flush through too many circuits or openings simultaneously. Flush through all vents, drains and other side connections. Flush by-passes alternately with their main channels. Try to avoid flushing line debris into equipment where it may become lodged or trapped. This is particularly important when washing towers containing perforated trays. So far as it can be done conveniently and economically, divert the initial flow ahead of, or around such equipment until lines upstream are clean, and then flush into or through the item
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
________
ITEM
PERFORMED: CONTR.
WITNESSED: PTT OTHER
5.3858 EQUIPMENT Contractor shall prepare a comprehensive Mechanical Completion form for each unit shown in the Equipment List as furnished for the Work. Contractor shall pre-plan and notify Owner in advance when manufacturer's representatives or service engineers are to be present at the job site to implement the Mechanical Completion program. concerned. Verified?
________
________
________
42. When flushing of the lines is finished, drain water from the system as completely as possible. Provide ample top venting of all lines and vessels during the draining operation and drains must be provided in all low spots of the system to ensure removal of all flushing water or media. Blow lines with air to effect further water removal. Done?
________
________
________
43. At the conclusion of flushing any system, check carefully to see that normal alignments are restored, temporary connections broken, temporary breaks reconnected, check valve flappers and/or cover plates replaced, orifices installed, etc. Start-up strainers are to be installed for pump and alignment of equipment checked after piping has been bolted in place. Completed and checked?
________
________
________
44. Special instructions shall be issued outlining cleaning procedures for units or sections where moisture cannot be tolerated due to process considerations. Done?
________
________
________
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR.
WITNESSED: PTT OTHER
7.45 OTHER FACILITIES Contractor shall prepare a comprehensive Mechanical Completion form for each facility installed as shown on drawings. Contractor shall follow the requirements in the applicable Specifications, Vendor supplied instructions, instructions provided in this section and directions received from Owner. 46. Safety and Fire Protection 60. Are all systems operable? All components tested "end-to-end," verified and working?
________
________
________
61. Ladders and platforms are installed for safe operation and access.
________
________
________
62. Any safety hazards? Identify and describe.
________
________
________
________
________
________
65. Verify that minimum strength has been achieved for all pours.
________
________
________
66. Has all concrete work been inspected for cracks? Make necessary repairs.
________
________
________
68. Verify all new road surfaces suffered no damage and all damages have been repaired. The repairs have been accepted?
________
________
________
69. Verify all new and/or relocated gates operate properly.
________
________
________
70. Verify all fencing materials suffered no damage and all damages have been repaired to Owner satisfaction.
________
________
________
71. Verify all new road culverts and headwalls suffered no damage and all damages have been repaired to PTT satisfaction.
________
________
________
72. Have security fences, gates, and guard houses been completed?
________
________
________
73. Has construction equipment such as cranes, welding machines, etc., no long being used, been removed from operation areas?
________
________
________
47.63
Concrete Placement and Testing
64. Were all concrete tests completed? laboratory and field reports on file?
C.67
D.74
Are
Roads, Fences and Gates
Soil Compaction
75. Has
test
been
conducted,
results
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
ITEM
PERFORMED: CONTR.
WITNESSED: PTT OTHER
documented and degree of compaction accepted?
________
________
________
76. If treatments to accelerate process were used, describe and verify acceptance.
________
________
________
78. Have required governmental approvals been obtained?
________
________
________
79. Do all underground drains flow freely? Have seals been established where required?
________
________
________
80. Are outfall lines, ditches, etc., ready for use?
________
________
________
82. Complete all work shown on drawings and verify all check lists are complete.
________
________
________
2. Have required identifying signs been installed?
________
________
________
E.77
F.81
Waste Disposal
Documentation
markers
and
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
MECHANICAL COMPLETION FORMS The sample forms on the following pages may be used for recording field inspection results and tests. The list is not necessarily complete and the specific requirements for each facility or system must be a matter of agreement between Contractor and Owner. FORM NO. Test and Record Forms: TR-1, p. 1
Piping Strength Test Pressure Report (Page 1/2)
TR-1, p. 2
Piping Strength Test Pressure Report (Page 2/2)
TR-2
Hydrostatic Test Record
TR-5
Megger Readings - Ground Resistance Record
TR-6
Electrical Test Record
TR-7
Safety and Relief Valve Record
TR-8, p. 1
Instrument Test Record (Page 1/2)
TR-8, p. 2
Instrument Test Record (Page 2/2) Mechanical Equipment Check List
ME-2
Vessels Electrical Equipment Check List
EE-5
Circuit Breakers
EE-8
Lighting Panels, Insulation Resistance, and Remote Terminal Display (RTD)
EE-9
Alarm Circuit Operation Test Instrument Check List
IE-1
Controllers
IE-2
Direct Connected Recorders and Recorder Controllers
IE-3
Electronic Controllers, Recorders & Indicators
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
FORM TR-1:
PIPING LEAK AND STRENGTH PROOF TEST REPORT (Page 1/2)
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT FORM TR-1 DEPARTMENT CONDUCTING TEST
LEAK AND STRENGTH PROOF TEST REPORT (Page 1 of 2) REPORT DATE
REASON FOR TEST: NEW CONSTRUCTION EXISTING FACILITY 1.
STOCK PIPE
LOCATION:
Compressor Station (Name.________________)
Metering Station (Name.________________)
Pipeline Milepost Station
Gas Piping
“A” “B” to to
Oil/Water/Other Piping DRAWING REFERENCES: 2. PIPE DATA AND TEST PRESSURE REQUIREMENTS a. Size
b. Wall
c. Spec
d. Material
e. Min. Test Pressure
f. Min. Test Time
g. Footage Tested
Columns a. through f. need to be completed and approved prior to test. 3. TEST MEDIUM INFORMATION Water Natural Gas Nitrogen Other:_________________________ If water is to be used, the following must be completed: Source____________________________ Sample Analysis____________________________ Agency How to be Consulted_________________________ Disposed__________________________________ ENGINEERING APPROVAL BY:
DATE:
4. TEST INSTRUMENTS AND EQUIPMENT: Type
Make
Range
Pressure Recorder Temperature Recorder Dead Weight Tester Others:
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
Serial No.
Date Last Calibrated
FORM TR-1:
PIPING LEAK AND STRENGTH PROOF TEST REPORT (Page 2/2)
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT FORM TR-1
LEAK AND STRENGTH PROOF TEST REPORT Page 2 of 2
5. PROFILE DATA: ELEVATION
PRESSURING POINT
LOCATION OF DEAD WEIGHT TESTER
Survey Station Elevation 6. FIELD TEST PRESSURE DATA: Date of Test 1. Clock Time
2. Press. Point (psig)
Time Test Began 3. Min. Press. @ Max. Elev. (psig)
4. Max. Press. @ Min. Elev. (psig)
5. Amb. Temp. (ºC)
6. Test Mediu m Temp. (ºC)
Date & Time Test Ended
Weather:
1. Clock Time
4. Max. Press. @ Min. Elev. (psig)
2. Press. Point (psig)
3. Min. Press. @ Max. Elev. (psig)
5. Amb. Temp. (ºC)
6. Test Medium Temp. (ºC)
Enter in column 2, the pressure reading from the dead weight tester. Columns 3 and 4 data may be calculated if accurate elevation information is available. For compressor station piping, furnish a field sketch if test layout differs from reference drawings. Temperature and pressure recorder charts and gage calibration charts are to be attached to the original of this report together with the water analysis if such a test was necessary. For mainline piping, furnish field profile sketch recording the pipeline length tested and the elevations and pressure as at high and low elevations. Existing bench marks & survey monuments shall be referenced in the test section. TEST PERFORMED BY: Signature of Representatives OWNER/CONSULTANT Contractor (Firm) ______________________ Subcontractor (Firm)____________________
By: _______________________________________ By: _______________________________________ By: _______________________________________
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
FORM TR-2:
HYDROSTATIC TEST RECORD
GAS PIPELINE AND GAS METERING HYDROSTATIC TEST RECORD AND REGULATING STATION PROJECT FORM TR-2 TEST SECTION NO. ______________________________ (1) PIPING SERVICE SYSTEM____________________________ DATE OF TEST ________________________ METHOD OF TEST _____________TEST MEDIUM SOURCE ________________ COMPOSITION_________ AMBIENT TEMPERATURE __________________________ TEST MEDIUM TEMPERATURE ___________________ DESIGN PRESSURE ______________________________ TEST PRESSURE _________________________ (2) Line Numbers
Origin
Destination
TEST INSTRUMENTATION AND TEST RECORDS CALIBRATION READINGS THROUGH TEST PERIOD DATE
TEST INSTRUMENT DESCRIPTION AND RANGE
TIME 1
DESCRIBE:
PRESS. 2 3
FILL PUMP PRESSURE PUMP MAXIMUM PRESSURE DEADWEIGHT TESTER TEST HEADERS AND BLINDS
EQUIPMENT INCLUDED IN TEST TAG NO. DESCRIPTION REMARKS
NOTES:
Drawing No.
(1) (2)
1
TEMP. 2 3
1
ISO No.
REMARKS
LEAKS 2 3
GPM MAX GPM GPM AT MAX
EQUIPMENT EXCLUDED - SHOP TESTED TAG NO. DESCRIPTION REMARKS
Prepare documentation for each Test Section - include schematics, layout and periodic notes during test period. Use data from Project issued sheets
SUMMITTED: SUBCONTRACTOR
DATE
ACCEPTED: CONTRACTOR
DATE
OWNER /CONSULTANT LOCATION DATE
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
FORM TR-5:
MEGGER READINGS - GROUND RESISTANCE RECORD
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT FORM TR-5 GROUND SYSTEM TEST LOCATION
SYSTEM NUMBER
RESIST. (OHMS)
AMB. TEMP. ºC
SUMMITTED
MEGGER READINGS GROUND RESISTANCE RECORD WEATHER
DATE
OWNER/CONSULTANT SUBCONTRACTOR LOCATION
DATE
DATE ACCEPTED DATE
CONTRACTOR
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
TESTER'S INITIALS
EQUIPMENT
FORM TR-6:
ELECTRICAL TEST RECORD
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT FORM TR-6 SYSTEM METHOD OF TEST DESIGN VOLTAGE CIRCUIT NUMBERS
ITEM NO.
ELECTRICAL TEST RECORD
DATE OF TEST TEST VOLTAGE VOLTAGE
ORIGIN
DESTINATION
EQUIPMENT INCLUDED IN TEST DESCRIPTION ITEM NO.
SUMMITTED
OWNER /CONSULTANT SUBCONTRACTOR
DATE
LOCATION DATE
ACCEPTED CONTRACTOR DATE
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
RUN IN
DRAWING NO.
DESCRIPTION
FORM TR-7:
SAFETY AND RELIEF VALVE RECORD
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT FORM TR-7
SAFETY & RELIEF VALVE RECORD
SAFETY VALVES ITEM NUMBER
EQUIPMENT
SIZE
PRESSURE
SETTING TESTED
RELIEF VALVES
SYSTEM TEST
REMARKS:
SUMMITTED
OWNER /CONSULTANT SUBCONTRACTOR
DATE
LOCATION DATE
ACCEPTED CONTRACTOR DATE
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
DATE TESTED
INSTALLED OK
FORM TR-8:
INSTRUMENT TEST RECORD (Page 1/2)
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT FORM TR-8
INSTRUMENT BANK TEST AND CALIBRATION RECORD Sheet 1 of 2
TYPICAL FORM: TITLE FROM INSTRUMENT INPUT/OUTPUT LIST TAG NO.
NAME
(T) (1)
(C) (2)
INSTALLED LOCATION OK? (3)
VERIFY (4)
M
I
E
W
REMARKS AND OTHER R
S
NOTES: (1) Show date of bank test completed and accepted. Describe below test method used. (2) Verify calibration of instrument and describe procedure followed. Include separately approved calibration certificate. (3) Indicate compliance with drawings. (4) M = mounting with all brackets and identifiers finished I = installation complete ready for use E = piping ends connected after piping test and cleaning W = electrical wiring tested, passed and connections finished R = recorders with printing media verified (inks, pens, paper, etc.); verify with data collected during precommissioning S = remote receipt of data
SUMMITTED
OWNER /CONSULTANT SUBCONTRACTOR
DATE
LOCATION DATE
ACCEPTED CONTRACTOR DATE
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
FORM TR-8:
INSTRUMENT TEST RECORD (Page 2/2)
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT FORM TR-8
INSTRUMENT BANK TEST AND CALIBRATION RECORD Sheet 2 of 2
TYPICAL FORM: TITLE FROM INSTRUMENT INPUT/OUTPUT LIST TAG NO.
NAME
(T) (1)
(C) (2)
INSTALLED LOCATION OK? (3)
VERIFY (4)
M
I
E
W
REMARKS AND OTHER R
S
NOTES: (1) Show date of bank test completed and accepted. Describe below test method used. (2) Verify calibration of instrument and describe procedure followed. Include separately approved calibration certificate. (3) Indicate compliance with drawings. (4) M = mounting with all brackets and identifiers finished I = installation complete ready for use E = piping ends connected after piping test and cleaning W = electrical wiring tested, passed and connections finished R = recorders with printing media verified (inks, pens, paper, etc.); verify with data collected during pre-commissioning S = remote receipt of data
SUMMITTED
OWNER /CONSULTANT SUBCONTRACTOR
DATE
LOCATION DATE
ACCEPTED CONTRACTOR DATE
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
FORM ME-2:
VESSELS
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT FORM ME-2
FIELD INSTALLATION CHECK LIST
VESSELS EQUIPMENT NO. FABRICATOR TYPE MATERIAL THICKNESS
SERVICE P.O. NUMBER CODE DATE RECEIVED
ITEM TO CHECK CONDITION WHEN RECEIVED?
REMARKS/OK
ERECTION ALIGNMENT, ELEVATION & PLUMB GROUNDING STRAP INSTALLED? INTERNALS INSULATION & FIREPROOFING GROUTED CLEANED TESTED LADDERS, PLATFORMS, DAVITS CLOSED REMARKS:
SUMMITTED
OWNER /CONSULTANT SUBCONTRACTOR
DATE
LOCATION DATE
ACCEPTED CONTRACTOR DATE
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
DATE TESTED
FORM EE-5:
CIRCUIT BREAKERS
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT FORM EE-5
FIELD INSTALLATION CHECK LIST
CIRCUIT BREAKERS EQUIPMENT NO. MANUFACTURER
SERVICE INSTALLED BY
ITEM TO CHECK CONTACT PARTS CLEAN?
REMARKS/OK
VISUALLY CLEAN? (NOT CORRODED) NO MOISTURE PRESENT? ENCLOSURE HAS BREATHER & DRAIN? COVERS ON TIGHT? SEALS FILLED? INSTANTANEOUS TRIP SETTING:
PHASE A PHASE B PHASE C
REMARKS:
SUBMITTED
OWNER /CONSULTANT SUBCONTRACTOR
DATE
LOCATION DATE
ACCEPTED CONTRACTOR DATE
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
DATE TESTED
FORM EE-8:
LIGHTING PANELS, INSULATION RESISTANCE, REMOTE TERMINAL DISPLAY (RTD)
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT FORM EE-8 TYPICAL FORM FOR:
CIRCUIT NUMBER
WIRE NUMBE R
ELECTRICAL TEST RECORD
LIGHTING PANELS INSULATION RESISTANCE REMOTE TERMINAL DISPLAY (RTD) WIRE SIZE
FROM
TO
MEGGER READING (MEG OHM) @ 1
2
DATE
AMB. TEMP. ºC
WEATHER
3
NOTE: @ MEGGER READINGS TO BE WITH WIRES COMPLETELY INSTALLED, CONDUIT FITTINGS CLOSED, SEALS FILLED, AND WITH THE CIRCUIT BREAKER OPEN INSTALLED BY _________________________________________ DATE____________ SUBMITTED
OWNER /CONSULTANT SUBCONTRACTOR
DATE
LOCATION DATE
ACCEPTED CONTRACTOR DATE
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
FORM EE-9:
ALARM CIRCUIT OPERATION TEST
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT FORM EE-9
FIELD INSTALLATION CHECK LIST
ALARM CIRCUIT OPERATION TEST ALARM UNIT NUMBER
EQUIPMENT LOCATION
TESTER'S INITIALS
DATE
REMARKS
NOTE: EACH DEVICE SHOULD BE ACTUATED BY ACTUAL PRESSURE, TEMPERATURE, LEVEL, SPEED, FLOW, ETC. ALL ITEMS MUST BE SIGNED AS BEING IN SATISFACTORY CONDITION BEFORE OPERATION IS PERMITTED.
SUBMITTED
OWNER /CONSULTANT SUBCONTRACTOR
DATE
LOCATION DATE
ACCEPTED CONTRACTOR DATE
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
FORM IE-1:
CONTROLLERS
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT FORM IE-1
INSTRUMENT CHECK LIST
CONTROLLERS INSTRUMENT NO.
SERVICE
MANUFACTURER
SERIAL NO.
ITEM TO CHECK 1. Blow air supply line at filter. Adjust air supply to specified pressure. 2. Align or synchronize controller so that when both process and set point are together near mid-range, the output air pressure does not drift. Observe for at least 2 minutes. The proportional bank adjustment should be able to be moved through its full range (2 to 300%) without change in output pressure. 3. Check the tubing from output to valve or pneumatic set unit of another instrument. There should be no restriction or leaks. Check stack for leaks - tighten bolts if necessary. (Bubble test should be used on all pneumatic controller systems.) 4. Controller is connected to proper valve and to proper connections. 5. Check manual control position. Put instrument on manual, adjust output to about 9 psig, move set point above and below process pen. No change in output air pressure should result. 6. Check that controller output air action is correct for valve or instrument to which it is connected. Control action is set "as process measurement increases" output air. (INCREASES for direct action and DECREASES for reverse action.) 7. Affix calibration sticker. REMARKS:
SUBMITTED
OWNER /CONSULTANT SUBCONTRACTOR
DATE
LOCATION
ACCEPTED
DATE CONTRACTOR
DATE
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
DATE CHECKED
FORM IE-2:
DIRECT CONNECTED RECORDERS AND RECORDER CONTROLLERS
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT FORM IE-2
INSTRUMENT CHECK LIST
DIRECT CONNECTED RECORDERS AND RECORDER CONTROLLERS INSTRUMENT NO.
SERVICE
MANUFACTURER
SERIAL NO.
ITEM TO CHECK 1. Remove all paper tags, strings, shipping stops, and install chart. 2. Check pen linkages for proper connection and freedom of movement. 3. Check calibration of recording pens at three points: 0, 50%, 100% of span; if not within 0.5% of span, recalibrate and report results on attached sheet. 4. If instrument is a controller, synchronize and align controller. Blow air supply line and adjust regulator to 20 psig before connecting controller to air supply. 5. Check output air tubing for leaks and connection to proper valve. Check that control action is correct. 6. Fill pens with ink and see the ink flows freely. 7. Check that chart drive operates. 8. Check nameplates for correct identification. 9. Affix calibration sticker. Shut off chart drive. Leave instrument clean and neat, ready for operation. REMARKS:
SUBMITTED
OWNER /CONSULTANT SUBCONTRACTOR
DATE
LOCATION
ACCEPTED
DATE CONTRACTOR
DATE
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)
DATE CHECKED
FORM IE-3:
ELECTRONIC CONTROLLERS, RECORDERS AND INDICATORS
GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT FORM IE-3
INSTRUMENT CHECK LIST
ELECTRONIC CONTROLLERS, RECORDERS AND INDICATORS INSTRUMENT NO.
SERVICE
MANUFACTURER
SERIAL NO.
ITEM TO CHECK 1. Check continuity of wiring, location and value of dropping resistors, and verify service manual feature (if provided) is disengaged. 2. Turn on power supply and check voltage level and polarity. 3. Check and adjust input span and zero. 4. Set output signal limits. (High = 100%; Low = 0%) 5. Place controller in Automatic Mode and check alignment. 6. Transfer controller to the Manual Mode and check both up and down scale ramp rates. 7. Verify output signal action is correct for receiver. "Output is to _______________ with input signal increase." 8. Check correct chart and scale ranges. 9. Install recorder ink capsules 10. Affix calibration sticker. REMARKS:
SUBMITTED
OWNER /CONSULTANT SUBCONTRACTOR
DATE
LOCATION
ACCEPTED
DATE CONTRACTOR
DATE
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)