23376582-002-ITP-AG-Piping
Short Description
Download 23376582-002-ITP-AG-Piping...
Description
LARSEN & TOUBRO LIMITED MSQ UPGRADATION (EPCC-1) PROJECT IOCL - PANIPAT Doc. No:
PMC
INSPECTION AND TEST PLAN FOR ABOVE GROUND PIPING PROJECT OWNER PMC CONTRACTOR
LT/MSQ/ITP/PIPE/AG/002
Date: 01.11.07
: EPCC-1 –MSQ UPGRADATION : INDIAN OIL CORPORATION LTD.PANIPAT. : JACOBS ENGINEERING INDIA PRIVATE LIMITED : LARSEN & TOUBRO LIMITED
LEGEND :
NA : Not Applicable, HP : Hold Point, W : Witness Point, Rw : Review of SUBCONTRACTOR SUBCONTRACTOR / L&T's documentation, documentation, S : Surveillance Surveillance by OWNER / PMC, PMC, WC : 100% 100% Examination, Examination, Spec. Spec. : Specification, Dwg. : Drawing, Std. : Standard Standard PT : Penetarnt Testing, Testing, MT: Magnetic Magnetic Particle Testing, PWHT: Post Weld Heat Treatment, IRN: Inspection Inspection Release Note Note
SL. No.
INSPECTION WITNESSES/GRADE
FIELD INSPECTION REPORT FORMAT No.
DESCRIPTION OF ACTIVITY
L&T
JACOBS
LT/MSQ/IMIR/GEN/001 LT/MSQ/IMIR/GEN/001 Rev.01
WC
W
APPROVED VENDER FORMAT
WC
HP
ABOVE GROUND PIPING A
PRIOR TO FABRICATION
1
Incoming Material
2
Welding Filler Material Approval / Qualification
3
WPS / PQR
LT/MSQ/STR/WPS/002 LT/MSQ/STR/PQR/003
WC
HP
4
Welder Performance Qualification
LT/MSQ/STR/WPQ/004
WC
HP
5
a) NDT Procedure Qualification
NDT Report
WC
HP
SR CHART
WC
HP
ISOMETRICS
WC
S
b) PWHT Procedure Qualification 6
Joint Numbering in Isometries ( Big & Small Bore )
7
Preparation of sketches for Job in case o f off sites A / G piping and Joint Numbering
APPROVED SKETCHES
WC
S
8
Transfer of Heat Nos. & Traceability
LT/MSQ/PIPE/TRA/011
WC
W
B
FABRICATION ( SHOP & FIELD )
1
Material as per piping class ( Check w.r.t. approved colour coding procedure )
LT/MSQ/PIPE/TRA/011
WC
S
WC
S
WC
S
NA
WC
S
LT/MSQ/STR/DNF/005 LT/MSQ/STR/FNW/006 LT/MSQ/STR/DNF/005
a) Fit Up check b) Dimensional checks 2
Pre heat ( If any )
3
Check for purity of purging / shielding gas
BTC OF MANUFACTURER MANUFACTURER
WC
Rw / S
4
Purging
BTC OF MANUFACTURER MANUFACTURER
WC
S
5
Shielding rate ( If any )
BTC OF MANUFACTURER MANUFACTURER
WC
S
6
Baking of Electrodes
ELECTRODE BACKING REGISTER
WC
S
7
Interpass cleaning & temperature check
NA
WC
S
Signature : Name : Date Prepared by L&T
Checked by L&T
Approved by JACOBS
Page 1 of 3
REMARKS
LARSEN & TOUBRO LIMITED MSQ UPGRADATION (EPCC-1) PROJECT IOCL - PANIPAT Doc. No:
PMC
INSPECTION AND TEST PLAN FOR ABOVE GROUND PIPING PROJECT OWNER PMC CONTRACTOR LEGEND :
LT/MSQ/ITP/PIPE/AG/002
Date: 01.11.07
: EPCC-1 –MSQ UPGRADATION : INDIAN OIL CORPORATION LTD.PANIPAT. : JACOBS ENGINEERING INDIA PRIVATE LIMITED : LARSEN & TOUBRO LIMITED NA : Not Applicable, HP : Hold Point, W : Witness Point, Rw : Review of SUBCONTRACTOR / L&T's documentation, S : Surveillance by OWNER / PMC, WC : 100% Examination, Spec. : Specification, Dwg. : Drawing, Std. : Standard PT : Penetarnt Testing, MT: Magnetic Particle Testing, PWHT: Post Weld Heat Treatment, IRN: Inspection Release Note
SL. No.
FIELD INSPECTION REPORT FORMAT No.
DESCRIPTION OF ACTIVITY
8
Visual Check of complete welds
9
Monitoring of PWHT Cycle
10
Hardness Check
L&T
JACOBS
LT/MSQ/PIPE/VCW/012
WC
S
SR CHART
WC
S
WC
S
WC
W
WC
HP
WC
S
LT/MSQ/PIPE/RGM/013
WC
W
LT/MSQ/PIPE/RGI/014
WC
HP
---------------------------------
WC
HP
B.T.C. OF MANUFACTURER/TEST REPORT OF LAB. B.T.C. OF MANUFACTURER/TEST REPORT OF LAB. B.T.C. OF MANUFACTURER/TEST REPORT OF LAB. LT/MSQ/DPT/016 LT/MSQ/MPT/017
a) For C.S. Materials
b) For A.S. Materials Piping
C) For A.S. Material Heating Coil
INSPECTION WITNESSES/GRADE
11
DPT / MPT
12
Radiography marking ( For Random Radiography )
13
Radiography interpretation
14
Spool clearance
C
ERECTION
1
Lifting arrangement
MTC/CALIBRATION CERTIFICATE
WC
Rw
2
Test Certificate for lifting tackles
MTC/CALIBRATION CERTIFICATE
WC
S
3
Location and orientation of branches
---------------------------------
WC
S
4
Provision of instrument Tappings
---------------------------------
WC
S
5
Provision of vents and drains
---------------------------------
WC
S
6
Correctness of type of supports, anchors, guides
---------------------------------
WC
S
7
Correctness of gasket / fasteners
---------------------------------
WC
S
8
Correctness of valves ( NRV, Gate, Globe, Control Valves), Steam straps and their direction of flow
---------------------------------
WC
S
9
Provision of Cold pull
---------------------------------
WC
HP
FIELD INSPECTION REPORT FORMAT No.
DESCRIPTION OF ACTIVITY SL. No.
INSPECTION SWITNESSES/GRADE
Signature : Name : Date Prepared by L&T
Checked by L&T
Approved by JACOBS
Page 2 of 3
REMARKS
REMARKS
LARSEN & TOUBRO LIMITED MSQ UPGRADATION (EPCC-1) PROJECT IOCL - PANIPAT Doc. No:
PMC
INSPECTION AND TEST PLAN FOR ABOVE GROUND PIPING PROJECT OWNER PMC CONTRACTOR LEGEND :
NA : Not Applicable, HP : Hold Point, W : Witness Point, Rw : Review of SUBCONTRACTOR / L&T's documentation, S : Surveillance by OWNER / PMC, WC : 100% Examination, Spec. : Specification, Dwg. : Drawing, Std. : Standard PT : Penetarnt Testing, MT: Magnetic Particle Testing, PWHT: Post Weld Heat Treatment, IRN: Inspection Release Note
PROOF TESTING
1
Procedure
2
Corrections of Testing arrangements
4
Date: 01.11.07
: EPCC-1 –MSQ UPGRADATION : INDIAN OIL CORPORATION LTD.PANIPAT. : JACOBS ENGINEERING INDIA PRIVATE LIMITED : LARSEN & TOUBRO LIMITED
D
3
LT/MSQ/ITP/PIPE/AG/002
All valves to be kept open and check if testing done against closed valve position Isolation of equipments, control valves, instruments, bellows, before testing. Removal of flappers from check valves
L&T
JACOBS
LT/MSQ/P/AG/005
WC
HP
---------------------------------
WC
S
--------------------------------
WC
S
--------------------------------
WC
S
LT/MSQ/UGMC/SP/023
WC
HP
LT/MSQ/PMI/STORE/019 LT/MSQ/PMI/SITE/019A
WC
HP
MTC/CALIBRATION CERTIFICATE
WC
Rw
5
Scrutiny of test packs for Mechanical and NDT Clearance
6
Positive material Identification as per Specification after completion of installation
7
Calibration of Pressure gauges
8
Air / Water Flushing ( Preliminary )
LT/MSQ/UGMC/SP/023
WC
W
9
Pneumatic / Hydro testing ( See Annexure B)
LT/MSQ/PIPE/HYD/015
WC
HP
10
Draining of Water & Air drying
LT/MSQ/UGMC/SP/023
WC
S
11
Removal of temporary blinds / supports
---------------------------------
WC
W
12
Pickling of system, if required
---------------------------------
WC
W
---------------------------------
WC
W
---------------------------------
WC
Rw
b) Torque tightening of flange joints
---------------------------------
WC
S
15
System testing
---------------------------------
WC
W
16
Setting of spring supports
---------------------------------
WC
W
ALL STAGEWISE INSPECTION REPORT
WC
Rw
13 14
Boxing up including reinstallation of flappers of check valves a) Check on fasteners & gasket and record thereof
Inspection & Test Documents Review Test and Inspection Documents
Signature : Name : Date Prepared by L&T
Checked by L&T
Approved by JACOBS
Page 3 of 3