EHP6 for SAP ERP 6.0 March 2012 English

PS Generic Setting (SP) (214) Building Block Configuration Guide

SAP AG Dietmar-Hopp-Allee 16 69190 Walldorf Germany

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

Copyright © 2012 SAP AG. All rights reserved. SAP, R/3, SAP NetWeaver, Duet, PartnerEdge, ByDesign, SAP BusinessObjects Explorer, StreamWork, SAP HANA, and other SAP products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of SAP AG in Germany and other countries. Business Objects and the Business Objects logo, BusinessObjects, Crystal Reports, Crystal Decisions, Web Intelligence, Xcelsius, and other Business Objects products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of Business Objects Software Ltd. Business Objects is an SAP company. Sybase and Adaptive Server, iAnywhere, Sybase 365, SQL Anywhere, and other Sybase products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of Sybase Inc. Sybase is an SAP company. Crossgate, m@gic EDDY, B2B 360°, and B2B 360° Services are registered trademarks of Crossgate AG in Germany and other countries. Crossgate is an SAP company. All other product and service names mentioned are the trademarks of their respective companies. Data contained in this document serves informational purposes only. National product specifications may vary. These materials are subject to change without notice. These materials are provided by SAP AG and its affiliated companies ("SAP Group") for informational purposes only, without representation or warranty of any kind, and SAP Group shall not be liable for errors or omissions with respect to the materials. The only warranties for SAP Group products and services are those that are set forth in the express warranty statements accompanying such products and services, if any. Nothing herein should be construed as constituting an additional warranty.

© SAP AG

Page 2 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

Icons Icon

Meaning Caution Example Note Recommendation Syntax External Process Business Process Alternative/Decision Choice

Typographic Conventions Type Style

Description

Example text

Words or characters that appear on the screen. These include field names, screen titles, pushbuttons as well as menu names, paths and options. Cross-references to other documentation.

Example text

Emphasized words or phrases in body text, titles of graphics and tables.

EXAMPLE TEXT

Names of elements in the system. These include report names, program names, Transaction codes, table names, and individual key words of a programming language, when surrounded by body text, for example, SELECT and INCLUDE.

Example text

Screen output. This includes file and directory names and their paths, messages, source code, names of variables and parameters as well as names of installation, upgrade and database tools.

EXAMPLE TEXT

Keys on the keyboard, for example, function keys (such as F2) or the ENTER key.

Example text

Exact user entry. These are words or characters that you enter in the system exactly as they appear in the documentation.



Variable user entry. Pointed brackets indicate that you replace these words and characters with appropriate entries.

© SAP AG

Page 3 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

Contents 1

Purpose............................................................................................................................. 5

2

Preparation........................................................................................................................ 5 2.1

3

Prerequisites............................................................................................................ 5

Configuration..................................................................................................................... 5 3.1

Defining Basic Settings for Projects WBS-Structure................................................5

3.1.1

Maintaining Project Types for WBS Elements.................................................5

3.1.2

Creating User-Defined Fields for WBS Elements............................................6

3.1.3

Specifying Graphics Profile for WBS Date Planning.......................................7

3.1.4

Defining Database Selection Profiles..............................................................7

3.1.5

Creating/Changing Planning Profile................................................................9

3.1.6

Maintaining Budget Profile.............................................................................11

3.1.7

Defining Tolerance Limits (for Budget)..........................................................13

3.1.8

Determining Strategy for Settlement Rule (for WBS)....................................14

3.1.9

Defining Parameters for WBS Scheduling.....................................................19

3.1.10

Creating a Project Profile..............................................................................20

3.1.11

Selection Variants (Projects).........................................................................27

© SAP AG

Page 4 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

Project System Generic Setting (SP) 1

Purpose

This configuration guide provides the information you need to set up the configuration of this building block manually. If you do not want to configure manually and prefer an automated installation process using the SAP Best Practices Installation Assistant and other tools, please refer to the SAP Best Practices Quick Guide.

2

Preparation

.2.1 Prerequisites Before you start installing this building block, you must install prerequisite building blocks. For more information, see the Building Block Prerequisite Matrix (Prerequisites_Matrix_[xx]_[yy]_ [zz].xls; the placeholder [xx] depends on the SAP Best Practices version you use, for example, BL refers to the SAP Best Practices Baseline Package, [yy] depends on the language version, for example, EN for English language, and [zz] depends on the country version, for example, IN for India: Prerequisites_Matrix_BL_EN_IN.xls). This document can be found on the SAP Best Practices documentation DVD in the folder ..\ [xx]_[zz]\Documentation\; ([xx] depends on the SAP Best Practices version and [zz] depends on the country version).

3

Configuration

.3.1 Defining Basic Settings for Projects WBS-Structure 3.1.1

Maintaining Project Types for WBS Elements

Use You can use the project type as a filtering criterion in the information system. The project type does not influence the program control or the screen selection.

Procedure 1. Access the activity using one of the following navigation options: Transaction code

OPSO

IMG menu

Project System  Structures  Templates  Standard Work Breakdown Structure  Settings for Standard and Operative WBSs  Maintain Project Types for WBS Elements

2. Activities: Create project types. 3. Overview of data records Type

YB

Description

SP: Service Project

© SAP AG

Page 5 of

SAP Best Practices

3.1.2

PS Generic Setting (SP) (214): Configuration Guide

Creating User-Defined Fields for WBS Elements

Use The following user-defined fields are defined in the system: 

General text fields You can use these fields to enter your own data, for example:





Information on people responsible



Information on substitutions or proxies



Internal phone numbers

Quantity fields and their units You can also define formula parameters for quantity fields. The formula parameters are used, for example, in work center formula calculation or network costing.



Value fields and their units



Date fields: You can use these fields, for example, to enter internal start data



Checkboxes: Here you can enter information for analyses in the information system

The key words for the user-defined fields are determined by a key word ID.

The SAP system does not check the contents of user-defined fields. You can make your own enhancements (that is, customer-specific functions) to the userdefined fields. The enhancement CNEX0001 is available for you to do this in development class CN (application development PS project management).

Procedure 1. Access the activity using one of the following navigation options:

2. 3.

Transaction code

OPS1

IMG menu

Project System  Structures  Operative Structures  Work Breakdown Structure (WBS)  User Interface Settings  Create User-Defined Fields for WBS Elements

Activities: Define the user-defined fields. Overview of data records: Field key

YBSV001

Description

SP: Setting WBS/network

Text

Text 1

Text 2

Text

Text 3

Text 4

Quantity

Quantity 1

Quantity 2

Value

Value 3

Value 4

Date

Date 1

Date 2

Checkboxes

Indicator 1

Indicator 2

© SAP AG

Page 6 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

Authorization object

3.1.3

Not selected

Specifying Graphics Profile for WBS Date Planning

Use The profile defines parameters for the display and the colored indicators of WBS elements and activities in the hierarchy graphic.

Procedure 1. Access the activity using the following navigation options: Transaction code

SPRO

IMG menu

Project System  Dates  Date Planning in WBS  Specify Graphics Profile for WBS Date Planning

2. Activities: Maintain settings for scheduling 3. On the entry screen, choose New Entries and enter the following data: General Data Time schd. prof

YBSV00000001

Description

SP: Service Project

Display Display option

1

Display option

1

Act./WBS display

Activated

Indicators Color for act.s

BLACK

Color for order

BLUE

Color milestone

BROWN_1

Color for doc.s

DARKYELLOW

Color for elem.

GRAY

Color-Subnetwk.

DARKGRAY

Color for mat.

GREEN

3.1.4

Defining Database Selection Profiles

Use All data in the information system comes from or is derived from the logical project system database (PSJ). You need the profile for this database for all analyses in the project system. In the database profile, you determine: 

The project view according to which the selected data is displayed on the screen, sorted according to the profit center, for example.

© SAP AG

Page 7 of

SAP Best Practices 

PS Generic Setting (SP) (214): Configuration Guide

The maximum explosion level for the selection, that is, the maximum number of hierarchy levels displayed in reports. Make sure that you consider the wbs levels and the levels of the assigned network hierarchy below. The level of detail depends on the project view and the selection criteria.



The objects that are selected in the database.

Once you are within an analysis, you cannot select any more objects from the database. You determine the scope of selection on the relevant initial screens.

Procedure 1. Access the activity using one of the following navigation options: Transaction code

OPTX

IMG menu

Project System  Information System  Selection  Define Database Selection Profiles

2. Activities: Define Database Selection Profiles. 3. Overview of Data Records Database prof.

YBSV00000001

Description

SP: Standard selection (structure)

Last changed by Project view

000000000001

Maximum level

99

Protected

Inactive

Not changeable

Inactive

Commercial eval.

Inactive

Superior obj.s

Activated

Origin Archive data

Not selected

Version data

Not selected

Std structures

Not selected

Selection Criteria Project def.

Activated

Sales documents

Activated

Component

Activated

WBS element WBS element

Activated

Incl. hierarchy

Activated

Dynamic sels

Activated

Network/order For WBS

Activated

Others

Activated

© SAP AG

Page 8 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

Incl. Subnets

Inactive

Network

Activated

Maint. order

Activated

Prod. Order

Activated

CO order

Activated

Activity For WBS

Activated

Others

Activated

Network act.

Activated

Act./Main.order

Inactive –> Activated

Prodn ord.acts

Inactive –> Activated

Miscellaneous Rel view

Activated

Capacity

Activated

Confirmation

Activated

PRT

Activated

Milestone

Activated

PS/text/docs

Activated

Purchasing data

Activated

Planned order

Activated

Expenses

Activated

Valuated qty

Inactive  Activated

Earned value

Inactive  Activated

3.1.5

3

Creating/Changing Planning Profile

Use The budget/planning profile groups all the control parameters for planning or budgeting together. You can use the following parameters to control your planning and budgeting: 1. Time horizon - You define the following: 

Period into the past for which you can plan/budget



Period into the future for which you can plan/budget



Start year for planning/budgeting

2. Planning/budgeting for total/annual/period values 3. Which value is displayed in addition to the plan/budget when accessing the function 4. Decimal places and scaling factor as default values 5. Detail planning (CO orders and projects)

© SAP AG

Page 9 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide



Cost element group: primary costs and revenues



Planning parameters: costs and revenues



Sender cost center group



Sender activity type group



Statistical key figure group



Costing parameters

6. Projects 

Planning in all WBS elements or only in planning elements



Availability control: annual or overall budgets

Procedure 1. Access the activity using the following navigation options: Transaction code

OPSB

IMG menu

Project System  Costs  Planned Costs  Manual Cost Planning in WBS  Hierarchical Cost Planning  Create/Change Planning Profile

2. Activities: Maintain the cost planning profile 3. Overview of data records: Field name

Description

User action and values

Profile

YBSV01

Description

SP: Costs/Revenues: Years

Bottom-up planning

Inactive

Planning elements

Activated

Past

1

Future

3

Total values

Not selected

Annual values

Activated

Decimal places

0

Scaling factor

Not selected

Controlling area currency

Activated

Default Object Currency

Not Selected

From quotation

Inactive

From sales order

Activated

Prim.CElem.grp

Not selected

Revenue CE grp

Not selected

Sender CCtr group

190

© SAP AG

Comment

Service and Consulting

Page 10 of

SAP Best Practices Field name

PS Generic Setting (SP) (214): Configuration Guide Description

User action and values

Comment

Sender act.type grp

YBMF_P00_AT

Planning activity type

Stat. key fig.group

Not selected

Costing variant

PS01

Exchange rate type

P

Value date

Not selected

Remainder translat.

Inactive

Project planning

RElem.f.billing plan 4. Save your entries.

3.1.6

Maintaining Budget Profile

Use In this step, you 

Create new budget profiles



Define parameters for new budget profiles



Change existing budget profiles

To be able to budget projects, you must create a budget profile or use an existing one. The following parameters are relevant for project budgeting: 1. Time horizon Here you define: 

The number of years in the past from the start year, for which budgeting is possible



The number of years in the future from the start year, for which budgeting is possible



Budgeting start year, a relative specification referring to the current fiscal year



Budgeting for overall and/or annual values

2. Display 

Standard view as well as the budget value when you access the function



Decimal places and scaling factor as default values

3. Currency translation: Exchange rate type - Value date 4. Availability control 

Activation type and percentage of consumption for background activation



Of annual/overall budget



Of releases

In the project budget profile, the "Overall" indicator, working in conjunction with the "Releases" indicator, has the following effect: Ind. "Overall"

Ind. "Releases"

Avail. control against...

X

X

Released overall budget

© SAP AG

Page 11 of

SAP Best Practices X Activation types:

PS Generic Setting (SP) (214): Configuration Guide X -

Released annual budget Overall budget Annual budget

0 = cannot activate This activity type may cause an already active availability control to be deactivated. 1 = automatic activation when budget is assigned You must maintain at least one tolerance limit for the budget profile. 2 = background activation when percentage of consumption is exceeded You must enter a percentage of consumption in background activation. The percentage of consumption represents the relationship of committed funds to the budget as a percentage. You must maintain at least one tolerance limit for the budget profile to have the system check the posting.



If you change the availability control configuration after budgeting, you should have the system recalculate the assigned values. To do this, restart the availability control for your project.



If you are also using the Funds Management component, you can greatly improve performance by only activating availability control in Funds Management or only activating it for projects.

Activity 1. Use Details to check the standard budget profiles delivered with the system. 2. Change the detail settings for the budget profiles or create budget profiles using New entries. You can assign a budget profile to a project 

As a default value in the Project System configuration



In the project profile for a project definition (operative structures)



In the project profile for a standard project definition (basic data)



in the Project System application menu



In the control data for the project definition (operative structures menu, Work breakdown structure  Change  Project definition, Details  Organization  Plan profile).

Procedure 1. Access the activity using one of the following navigation options: Transaction code

OPS9

IMG menu

Project System  Costs  Budget  Maintain Budget Profiles

2. Activities: Maintain budget profiles 3. Overview of data records Profile

YBSV01

Description

SP: Budget: Year;Current Budgt

© SAP AG

Page 12 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

Past

1

Future

3

Start

Not selected

Total values

Inactive

Annual values

Activated

Decimal places

2

Scaling factor

Not selected

Exchange rate type

M

Value date

Not selected

Program type budget

Not selected

Activation type

1

Usage

Not selected

Overall

Inactive

Releases

Inactive

Object currency

Inactive

Controlling area currency

Activated

Default Object Currency

Inactive

3.1.7

Defining Tolerance Limits (for Budget)

Use In this step, you enter the tolerance limits for the financial availability control. The availability control can identify budget overruns in a project at an early stage and initiates various actions. You activate availability control for a certain budget profile. You can specify one or more tolerance limits for each activity group for a budget profile. Selected actions (warning, warning with mail to person responsible for project, error message) are triggered when these limits are reached.

Prerequisites Before you can activate the availability control, you must have maintained the appropriate activation type in the budget profile

Procedure 1. Access the activity using one of the following navigation options: Transaction code

SPRO

IMG menu

Project System  Costs  Budget  Define Tolerance Limits

© SAP AG

Page 13 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

2. Activities: Define the tolerance limits for each activity group for the budget profile you are using. 3. Overview of data records COAr.

1000

Profile

YBSV01

Description

SP: Budget: Year;Current Budgt

Tr.Grp

++

Act.

1

Usage

100

Abs.variance

Not selected

3.1.8

Determining Strategy for Settlement Rule (for WBS)

Use In this step, you define the strategy for automatic generation of settlement rules. You use the strategy to determine the objects to which the settings apply (Billing element - Account assignment element – Neither) and the settlement receiver, by means of the account assignment category. The following account assignment types are available: o

Settlement to profitability segment

o

Settlement to responsible cost center

o

Settlement to requesting cost center

o

Take over settlement rule from superior object

o

No settlement rule



Settlement profile



Settlement key

Procedure 1. Access the activity using one of the following navigation options: Transaction code

SPRO

IMG menu

Project System  Costs  Automatic and Periodic Allocations  Settlement  Settlement Rule for Work Breakdown Structure Element  Determine Strategy for Settlement Rule

2. Activities 

Define a strategy.



In the Settings detail screen, stipulate: 

© SAP AG

The objects to which the strategy applies

Page 14 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide



Whether the settings only apply in the event of an organizational change



Results analysis key and profile



The settlement receiver (by means of the account assignment category)



Whether multiple assignments of sales and distribution items are supported.

3. Overview of data records for strategy Y1: Entry View Strategy Strategy

Y1

Description

SP: Service Project

4. Mark up your defined strategy and double click on the Settings folder on the left- hand side. 5. Fill in the entries below, entering each block in a single line of the settings table. Setting Line #1 Billing Elem.

Inactive

AA element

Activated

No acct asst

Inactive

Org.change

Inactive

Sett.Prof.

YBSV01

AcctAssCat

1

N:1 SD-PS

Activated

RA key

YBSV01

Setting Line #2 Billing Elem.

Activated

AA element

Inactive

No acct asst

Inactive

Org.change

Inactive

Sett.Prof.

YBSV01

© SAP AG

Page 15 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

AcctAssCat

1

N:1 SD-PS

Activated

RA key

YBSV02

6. Overview of data records for strategy Y2: Entry View Strategy Strategy

Y2

Description

SP: Internal Project

7. Mark up your defined strategy and double click on the Settings folder on the left- hand side. 8. Fill in the entries below, entering each block in a single line of the settings table. Setting Line #1 Billing Elem.

Inactive

AA element

Inactive

No acct asst

Activated

Org.change

Inactive

Sett.Prof.

YBSV05

AcctAssCat N:1 SD-PS RA key Setting Line #2 Billing Elem.

Inactive

AA element

Activated

No acct asst

Inactive

Org.change

Inactive

Sett.Prof.

YBSV05

AcctAssCat

1

N:1 SD-PS RA key

© SAP AG

Page 16 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

9. Overview of data records for Strategy YF: Entry View Strategy Strategy

YF

Description

SP: Service Project Fixprice

10. Select your defined strategy and double-click the Settings folder on the left-hand side. 11. Fill in the entries below, entering each block in a single line of the settings table. Setting Line #1 Billing Elem.

Inactive

AA element

Inactive

No acct asst

Activated

Org.change

Inactive

Sett.Prof.

90

AcctAssCat N:1 SD-PS

Inactive

RA key

Setting Line #2 Billing Elem.

Inactive

AA element

Activated

No acct asst

Inactive

Org.change

Inactive

Sett.Prof.

90

AcctAssCat N:1 SD-PS

Inactive

RA key Setting Line #3 Billing Elem.

Activated

AA element

Inactive

© SAP AG

Page 17 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

No acct asst

Inactive

Org.change

Inactive

Sett.Prof.

YBSV01

AcctAssCat

1

N:1 SD-PS

Activated

RA key

YBSV01

12. Overview of data records for Strategy YR: Entry View Strategy Strategy

YR

Description

SP: Service Project RRB

13. Select your defined strategy and double-click the Settings folder on the left-hand side. 14. Fill in the entries below, entering each block in a single line of the settings table. Setting Line #1 Billing Elem.

Inactive

AA element

Inactive

No acct asst

Activated

Org.change

Inactive

Sett.Prof.

90

AcctAssCat N:1 SD-PS

Inactive

RA key

Setting Line #2 Billing Elem.

Inactive

AA element

Activated

No acct asst

Inactive

Org.change

Inactive

Sett.Prof.

90

© SAP AG

Page 18 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

AcctAssCat N:1 SD-PS

Inactive

RA key Setting Line #3 Billing Elem.

Activated

AA element

Inactive

No acct asst

Inactive

Org.change

Inactive

Sett.Prof.

YBSV01

AcctAssCat

1

N:1 SD-PS

Activated

RA key

YBSV02

15. Save your entries.

3.1.9

Defining Parameters for WBS Scheduling

Use The profile for WBS scheduling contains the parameters for scheduling. Settings provide that your projects start with backward scheduling for networks and the network header determines the date to consider for its assigned activities.

Procedure 1. Access the activity using one of the following navigation options: Transaction code

SPRO

IMG menu

Project System  Dates  Date Planning in WBS Define Parameters for WBS Scheduling

2. Activities: Maintain the following settings for scheduling: General Data WBS scheduling profile

YSP000000001

Description

SP: backwds. WBS determines

Scheduling Scheduling type

Backwards

Start in past

Not selected

Schedul. method

WBS determines dates

© SAP AG

Page 19 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

Adjust bsc date

Activated

Automatic log

Inactive

Shift Order

Inactive

Autom. schedul.

Inactive

Latest Staging

Inactive

Reduction Max. redn. level

Inactive

Reduction type

Inactive

3. Save your entries.

3.1.10

Creating a Project Profile

Use The project profile contains default values and other control parameters such as the planning method for dates and costs. The data that you enter in the project profile will be copied into a project in its project definition or in the WBS elements which can later be overwritten. Examples 

To call up the graphic, you must first have specified various graphic profiles in the project profile.



To carry out cost planning you must specify a planning profile.



To carry out financial budgeting you must specify a financial planning profile.

The values in the project profile determine the functionality of certain areas of the project system, which is why you should not change them without careful thought. Do not change the profiles and keys from related functions that are defined in the project profile, such as the costing sheet or the results analysis key. These changes could affect existing objects. You must maintain all sections for the project profile: basic data, time scheduling, costs/revenues/finances and organizational data.

Procedure 1. Access the activity using one of the following navigation options: Transaction code

OPSA

IMG menu

Project System  Structures  Operative Structures  Work Breakdown Structure (WBS)  Create Project Profile

2. Activities 

Determine the organizational and control criteria for your company.



Create the project profiles reflecting these criteria and enter the relevant data.

3. Save your entries.

© SAP AG

Page 20 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

4. Overview of data records: Proj.pro

YBS1000

Description

SP: Service Project

Control Basic data Proj.type

YB

Field key

YBSV001

Version prof.

0000001

Simulation prof

0000001

Display options

1

Level of detail

Not selected

Partner det.prc

Not selected

All acct asst elem

Activated

Only one root

Inactive

Trsfr to proj. def.

Inactive

Change Documents

Inactive

Proj. summ. MastDa

Activated

Validation Project def.

Not selected

WBS elements

Not selected

Autom. Validation

Inactive

Substitution Project def.

Not selected

WBS elements

Not selected

Autom. Validation

Inactive

Project stock No stock

Activated

Non-valuated stk

Inactive

Valuated stock

Inactive

Automatic reqmnts grouping

Inactive

Status management PD sts. Profile

Inactive

WBS sts. prof.

Inactive

Change Documents

Inactive

© SAP AG

Page 21 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

Graphic Master data prf.

PS

Vertical from level

Not selected

SearchTxtIndex1

Not selected

Graph.prfl mstr data

HIERARCHY_S

SearchTxtIndex2

Not selected

SearchTxtIndex3

Not selected

Project summarization All WBS elements

Inactive

Billing elements

Inactive

Acct asst elements

Inactive

Sales pricing Sales organization

Not selected

Distribution channel

Not selected

Division

Not selected

DIP profile

Not selected

Organization Controlling area

1000

Company code

1000

Business area

Not selected

Plant

1000

Functional area

Not selected

Profit center Project currency

EUR

Plg board/dates WBS time scheduling WBS sched. prof

YBSV00000001

Sched. scenario

Not selected

With activities

Activated

Default values Factory calend.

01

Time unit

DAY

Planning method

© SAP AG

Page 22 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

Plan.meth/basic

1

Plan.meth/fcst

1

Calc. with act.

Not selected

Network Network profil

Inactive

Network asst

Inactive

Display network hdr

Inactive

Project planning board Plan.board prf.

000000000001

Capacity Requirements Planning Tot.tab.profile

SAPPS_G001

Tot.graphic.prf

SAPPS_G002

IndCapTabOvProf

SAPPS_GE01

IndCapGrpOvProf

SAPPS_GE02

List profile

SAPPS_G000

Hierarchy Graphic Profile group

PS

Time schd. prof

YBSV00000001

Profile

HIERARCHY_T

Controlling Costs/revenues/payments Object class

PROFT

Statistical

Inactive

Integrated planning

Inactive

Planning/budgeting Planning profile

YBSV01

Budget profile

YBSV01

Period-end closing Costing sheet

Not selected

Overhead key

Not selected

Interest profile

Not selected

© SAP AG

Page 23 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

Investment profile

Not selected

Results analysis key

Not selected

Settlement profile

YBSV01

Settmt rule strat.

Y1

Graphic Budget profile group

PS

Graph. profile budget

HIERARCHY_S

Proj.pro

YBS2000

Description

SP: Internal Project

Control Basic data Proj.type

YB

Field key

YBSV001

Version prof.

0000001

Simulation prof

0000001

Display options

1

Level of detail

Not selected

Partner det.prc

Not selected

All acct asst elem

Activated

Only one root

Inactive

Trsfr to proj. def.

Inactive

Change Documents

Inactive

Proj. summ. MastDa

Activated

Validation Project def.

Not selected

WBS elements

Not selected

Autom. Validation

Inactive

Substitution Project def.

Not selected

WBS elements

Not selected

Autom. Validation

Inactive

Project stock No stock © SAP AG

Activated Page 24 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

Non-valuated stk

Inactive

Valuated stock

Inactive

Automatic reqmnts grouping

Inactive

Status management PD sts. Profile

Inactive

WBS sts. prof.

Inactive

Change Documents

Inactive

Graphic Master data prf.

PS

Vertical from level

Not selected

SearchTxtIndex1

Not selected

Graph.prfl mstr data

HIERARCHY_S

SearchTxtIndex2

Not selected

SearchTxtIndex3

Not selected

Project summarization All WBS elements

Inactive

Billing elements

Inactive

Acct asst elements

Inactive

Sales pricing Sales organization

Not selected

Distribution channel

Not selected

Division

Not selected

DIP profile

Not selected

Organization Controlling area

1000

Company code

1000

Business area

Not selected

Plant

1000

Functional area

Not selected

Profit center Project currency

EUR

Plg board/dates WBS time scheduling © SAP AG

Page 25 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

WBS sched. prof

YBSV00000001

Sched. scenario

Not selected

With activities

Activated

Default values Factory calend.

01

Time unit

DAY

Planning method Plan.meth/basic

1

Plan.meth/fcst

1

Calc. with act.

Not selected

Network Network profil

Inactive

Network asst

Inactive

Display network hdr

Inactive

Project planning board Plan.board prf.

000000000001

Capacity Requirements Planning Tot.tab.profile

SAPPS_G001

Tot.graphic.prf

SAPPS_G002

IndCapTabOvProf

SAPPS_GE01

IndCapGrpOvProf

SAPPS_GE02

List profile

SAPPS_G000

Hierarchy Graphic Profile group

PS

Time schd. prof

YBSV00000001

Profile

HIERARCHY_T

Controlling Costs/revenues/payments Object class

PROFT

Statistical

Inactive

© SAP AG

Page 26 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

Integrated planning

Inactive

Planning/budgeting Planning profile

YBSV01

Budget profile

YBSV01

Period-end closing Costing sheet

Not selected

Overhead key

Not selected

Interest profile

Not selected

Investment profile

Not selected

Results analysis key

Not selected

Settlement profile

YBSV05

Settmt rule strat.

Y2

Graphic Budget profile group

PS

Graph. profile budget

HIERARCHY_S

3.1.11

Selection Variants (Projects)

Use The selection variants for program RKPSEL00 (Selection Criteria: Project) are created. This program is used for Period End-Closing function for projects.

Procedure 1.

Access the activity using one of the following navigation options: Transaction code

CJ8V

IMG menu

Project System  Costs Automatic and Periodic Allocations  Settlement  Create Selection Variants

2.

On the ABAP Variants: Initial screen, provide the variant.

3.

Choose Values and then Create.

4.

On the Maintain Variant: Report RKPSEL00, Variant screen, make the following entries and save: Field name

Description

User action and values

Variant

YBLSV_PRJ

Database prof.

YBSV00000001

Comment

If pop up appeared

Subobject: Values Project

From

*

Dynamic selection

© SAP AG

Page 27 of

SAP Best Practices

PS Generic Setting (SP) (214): Configuration Guide

Master data definition Project Profile

YBS1000, YBS2000

Org. units WBS element Company code

1000

Subobject: Attributes Meaning Field name

YBLSV_PRJ Description

User action and values

Variant

YSLSV_PRJ

Database prof.

YBSV00000001

Comment

If pop up appeared

Subobject: Values Project

From

*

Network/order

= Single value

blank

Dynamic selection Master data definition Project Profile

YBS1000, YBS2000

Org. units WBS element Company code

1000

Subobject: Attributes Meaning

© SAP AG

YSLSV_PRJ

Page 28 of