20140715_Recommended List of Major MEP Materials Manufacturers and Standards
June 1, 2016 | Author: Jayakrishnan Radhakrishnan | Category: N/A
Short Description
Recommended List of Major...
Description
DUBAI PARKS LIST OF RECOMMENDED MANUFACTURERS & STANDARDS FOR MAJOR MEP EQUIPMENTS Discipline
Standards / Specification
Recommended Manufacturers
Spare Parts / Extra materials
Warranty
Maintenance / Offer for AMC
FAT / SAT
Commissioning
Training / Demonstration
MECHANICAL External Network: Potable Water Pumps Bronze/SS Impeller SS shaft Cast Iron Body WRAS approved Factory assembled BS 8558:2011 GRP water tanks ‐ above ground 40‐50 mm thick, 48 kg/m3, sandwich PUF insulated WRAS approved BS EN 13280:2001 Domestic Water Treatment DM guidelines WHO guidelines
SW
1. Grundfoss 2. KSB 3. Armstrong 4. Ebara 5. Lowara 6. Holden Brooke Pullen 7. Wilo 8. ITT Bell & Gosset 1. Sekisui 2. Bridgestone 3. Balmoral 4. Mitsubishi 1. Culligan 2. Corodex 3. Nalco 4. Metito 5. Waterbird 6. Veolia
MRSP
N/A
FAT
FASR
FASR
N/A
N/A
N/A
FASR
Contractor
SW
MRSP
Annual maintenance offer FAT (quotation only) up to 5 years
FASR
FASR
1. Ingersol Dresser 2. Patterson 3. ITT Bell & Gosett 4. Aurora 5. Peerless‐Grundfoss 6. Reddy Buffallo
SW
MRSP
N/A
FAT
FASR
FASR
1. Kennedy Valve Co. 2. Mueller 3. Tyco 4. Bristol 5. Naffco 6. Kidde
SW
N/A
N/A
N/A
Contractor
Contractor
1. Grundfoss 2. Armstrong 3. ITT Bell & Gosset 4. Holden Brooke Pullen 5. KSB 6. Ebara 7. Lowara 1. Grundfoss 2. Armstrong 3. ITT Bell & Gosset 4. Holden Brooke Pullen 5. Pneumatex 6. Lowara
SW
MRSP
N/A
FAT
FASR
FASR
SW for unit
MRSP
N/A
N/A
FASR
FASR
SW for unit
MRSP
N/A
FAT
FASR
FASR
Annual maintenance offer (quotation only) up to 5 FAT years
FASR
FASR
N/A
FASR
FASR
10 years for panels
Fire sprinkler system Pumps Bronze Impeller SS shaft Cast Iron Body NFPA 20 and UAE Fire Code FM/UL approved Fire Hydrant system Hydrants NFPA 24 and UAE Fire Code
Chilled Water System Pumps Bronze Impeller SS shaft Cast Iron Body BS EN ISO 2858:2010 Factory assembled Pressurisation units BS 7074 WRAS approved
Sewerage Lifting station pumps Cast Iron Body SS Shaft SS Impeller DM guidelines BS EN 1671:1997
1. Flygt; ITT Industries. 2. Goulds Pumps; ITT Industries. 3. ABS 4. SA Armstrong 5. Grundfoss
Compressed Air Compressor BS EN 1012‐1:2010 ASME B 19.1
SW for unit & SW+4 years for compressors MRSP
1. Atlas Copco 2. Ingersoll‐Rand; Air Solutions Group. 3. Comp air 4. Kaeser Compressors, Inc.
Building Services: Potable Water Pumps Bronze/SS Impeller SS shaft Cast Iron Body
WRAS approved BS 8558:2011
SW
1. Grundfoss 2. KSB 3. Armstrong 4. Ebara 5. Lowara 6. Holden Brooke Pullen 7. Wilo 8. ITT Bell & Gosset Page : 1 of 5
MRSP
FAT
Date: 01 May 2014
DUBAI PARKS LIST OF RECOMMENDED MANUFACTURERS & STANDARDS FOR MAJOR MEP EQUIPMENTS Discipline
Standards / Specification
GRP Insulated Panel Tanks 40‐50 mm thick, 48 kg/m3, sandwich PUF insulated WRAS approved BS EN 13280:2001 Water heaters Steel Glass lined‐Small Stainless Steel‐Central DEWA and DM Guidelines BS 3456‐102.21:1998
Recommended Manufacturers 1. Sekisui 2. Bridgestone 3. Balmoral 4. Mitsubishi 1. A.O. Smith 2. Bradford 3. Viesssmann 4. Ariston 5. Thermex 6. HRS 7. Ecotherm 8. Rycroft
Spare Parts / Extra materials
Warranty
Maintenance / Offer for AMC
FAT / SAT
Commissioning FASR
Training / Demonstration
10 years for panels
N/A
N/A
N/A
Contractor
SW+4 years
N/A
N/A
N/A Contractor FAT for FASR (for central) Central heater
Contractor FASR (for central)
MRSP
N/A
FAT SAT
FASR
FASR
SW for unit & SW+4 years for compressors
MRSP
Annual maintenance offer FAT (quotation only) up to 5 years
FASR
FASR
SW for unit & SW+4 years for compressors
MRSP
N/A
N/A
FASR
FASR
SW
MRSP
N/A
N/A
FASR
FASR
SW
MRSP
N/A
FAT
FASR
FASR
SW
MRSP + 5 actuators of each type
N/A
N/A
Contractor
Contractor
SW
MRSP + 5 actuators of each type
N/A
N/A
FASR
FASR
SW
N/A
N/A
FAT
Contractor
N/A
Chilled Water Air Handling Equipment EUROVENT/AHRI BS EN 1886:2007
Close Control Air Conditioning Units EUROVENT/AHRI
DX Split units EUROVENT/AHRI BS ISO 15042:2011
Fan Coil Units EUROVENT/AHRI BS 4856‐4:1997
Fans AMCA BS 848‐1:2007
VAVs AHRI BS EN 12589:2001
Differential Pressure Control Valves BS 7350:1990
Plate Heat Exchangers SS plates EUROVENT/AHRI BS EN 1148:1999
SW
1. Flakt Woods 2. York‐JCI 3. Trane 4. Carrier 5. McQuay 6. Euroclima 7. Klimak 8. Mekar 1. Liebert 2. Emerson 3. Stulz 4. GEA 5. Johnson Controls 6. Compu‐Aire 7. Airedale 8. Climate worx 1. York ‐JCI 2. Trane 3. Carrier 4. McQuay 5. Mitsubishi 6. LG 7. O'General 1. Flakt Woods 2. York‐JCI 3. Trane 4. Carrier 5. McQuay 6. Euroclima 7. Sinko 1. Nuaire 2. Greenheck 3. PENN Ventilator Co. 4. Elta 5. Xpelair 6. Systemair 7. Dynair 1. Flakt Woods 2. Trox 3.Waterloo 4. Barcol 5. Titus 6. KBE 7. EH Price 1. Tour Anderson 2. Danfoss 3. Belimo 4. Honeywell 5. Hattersley 6. Crane 7. Flow Con 1. Alfa Laval, Inc. 2. Sondex 3. Bell & Gossett; ITT Industries. 4. APV 5. GEA 6. HRS
Sewerage
Page : 2 of 5
Date: 01 May 2014
DUBAI PARKS LIST OF RECOMMENDED MANUFACTURERS & STANDARDS FOR MAJOR MEP EQUIPMENTS Discipline
Standards / Specification Sanitary wares
Recommended Manufacturers
Spare Parts / Extra materials
Warranty
Maintenance / Offer for AMC
FAT / SAT
Commissioning
Training / Demonstration
1. Ideal Standard 2. Kohler 3. Toto 4. Twyford 5. RAK Ceramics 6. Roca 7. Villeroy & Boch
SW
MRSP
N/A
N/A
Contractor
Contractor
11 kV cables DEWA
Will be supplied by DEWA
N/A
N/A
N/A
N/A
N/A
N/A
Ring Main Units / 11 KV switchgear DEWA
Will be supplied by DEWA
N/A
N/A
N/A
N/A
N/A
N/A
Transformers DEWA
Will be supplied by DEWA
N/A
N/A
N/A
N/A
N/A
N/A
1.Ducab 2.AEI 3.Riyadh cables 4.Saudi cables 5. Delta cables 1.Schneider 2.Siemens 3.Eaton (Cutler Hammer) 4. GE 5. ABB 1. Ducab 2.Draka 3.AEI 4. Pirelli 5 Prysmian 1.Draka 2.AEI 3. Prysmian 4.BICC 5.Pirelli 1.Furse 2.Erico 3.AN Wallis 4. Altec 5. Tenby 1.Marshall 2.Decoduct 3.MK 4. Clipsal 5. Simplex 1.Barton 2.Simplex 3.Electrix 4. Transdelta 5. Wheatland 1.Adaptflex 2.Barton 3.Kopex 4.Decoduct 5.Marshall Tuflex 1.Legrand 2. B‐Line ‐ Cooper /Eton 3.Obo betterman 4.Novablue 5.Snaketray 6. MP huskey 1.Davis 2.Swifts/Legrand 3. Obo betterman 4.B‐line ‐ cooper/Eton 5. Cablofill 1. MK 2.Legrand
SW
N/A
N/A
N/A
Contractor
Contractor
MSRP + 1 pc / every size
N/A
FAT SAT
FASR
FASR
SW
N/A
N/A
N/A
Contractor
Contractor
SW
N/A
N/A
N/A
Contractor
Contractor
SW
N/A
N/A
N/A
Contractor
Contractor
SW
N/A
N/A
N/A
N/A
N/A
SW
N/A
N/A
N/A
N/A
N/A
SW
N/A
N/A
N/A
N/A
N/A
SW
N/A
N/A
N/A
N/A
N/A
SW
N/A
N/A
N/A
N/A
N/A
SW
N/A
N/A
N/A
N/A
N/A
ELECTRICAL:
LV conductors & cables DEWA, BS 6007:2006, BS EN 50525:2011, BS 6004:2012, BS 7889:2012, BS 6346:1997
Bus bars BS EN 60439‐2:2000, IEC 60439‐2:2000 BS EN 61439‐6:2012
Fire rated cables (600V‐1000V) DCD, DEWA, BS 7846:2009, BS EN 50267 (Armoured /Non armoured)
Fire rated cables (FA/EM/VA) DCD, BS 7629‐1:2008, BS 5839‐1:2002, (Non armoured) BS 5266‐1:2011, BS 8519‐1:2010, BS EN 50267
Grounding, earthing & lightning protection DEWA, BS EN 62561:2012, BS 7430:2011 BS EN 62305‐1:2011, BS EN 50310:2010
Non Metallic conduits & Accessories BS 4607‐1:1984+A2:2010, BS 4607‐3:1971 BS EN 61386‐21:2004+A11:2010 BS 4607‐5:1982+A3:2010
Metallic conduits & Accessories BS EN 61386‐1:2008
Flexible Metallic conduits & Accessories BS 4607‐1:1984+A2:2010
Metal wire ways/mesh & accessories BS EN 61537:2007, IEC 61537:2001
Cable trays/ Ladder / trunking & accessories BS EN 61537:2007, IEC 61537:2001
Cable management system/ floor/wall trunking BS EN 60423‐24:2007, BS EN 50085‐2‐2:2008
SW+1 year
Page : 3 of 5
Date: 01 May 2014
DUBAI PARKS LIST OF RECOMMENDED MANUFACTURERS & STANDARDS FOR MAJOR MEP EQUIPMENTS Discipline
Standards / Specification
Under ground ducts and raceways BS EN 61386‐24:2010
Isolators & Disconnecting switches DEWA, BS EN 60204, BS EN 60947
Wiring Devices DEWA, BS 1363
LV switch gears DEWA, BS EN 60947, BS EN 61439:2012 BS EN 60898‐1 , BS EN 608981:2003+A13:2012 BS EN 60898‐1 , BS EN 608981:2003+A13:2012 BS EN 61008‐1:2012, BS EN 60529 : 1992 Capacitor Banks DEWA, BS EN 60831, BS EN 60871, (Power factor correction equipments) BS EN 60931,
Standby Generator BS EN 60034, NFPA 110 BS 5514, BS 7698
UPS BS EN 62040:2013
Automatic Transfer switches BS EN 62310, BS EN 60947, NFPA 110
Variable frequency motor controllers BS EN 61800‐2:1998, IEC 61800‐2:1998
Indoor & out door Light fittings DEWA, BS EN 60598‐1, BS EN 12665:2011, CIBSE BS EN 13032 Lighting control system BS EN 62386, CIBSE
Central Battery Emergency lighting BS EN 1838:2013, BS 5266‐1:2011, NFPA 101 CIBSE guide TM12, NFPA 110
Fire Alarm systems DCD, NFPA 72, NFPA 101, NFPA 92A, NFPA 101A UAE fire code, BS EN 54, BS 5839 UL/FM Approved
Security access control systems Dubai Police, Meraas Security requirements
Recommended Manufacturers 3.Obo betterman 4.Ackerman 5. Electrak 1.Hepworth 2.National plastic 3.Cosmoplast 4. Binbrook 5. Dubai Pipes 1.Eton 2.ABB 3.Elektra 4. Schneider 5. Siemens 1. MK 2. Clipsal 3. Legrand 4. Crabtree 5. Hubbel 1.Schneider 2.ABB 3.Eton/ cutler hammer 4.Siemens 6. Dorman smith 1.Schneider 2.ABB 3. Power economy gulf 4. J & P capacitors 6. Lifasa 1.Caterpillar 2. Mitsubishi 3. FG wilson 4. KHD/Duetz 5 .Cummins ONAN 1.Liebert 2. Eton 3. Schneider 4. APC 5. Chloride 1.ASCO 2. Eton 3. ABB 4. Schneider 5. Siemens 1. Danfoss 2. Allen Bradley 3. Siemens 4. Lenze AC tech 3. Schneider (varies depends upon the project requirement)
1. Lutron 2. ABB 3. Philips 2. Tridonic 3.Legrand 1. Cooper lighting / CEAG 2. ABB 3. Chloride 4. Siemens 5. Inotec 6. Thomas & Betts 1. Honeywell 2. Notifier 3. Edwards 4. Tyco 5. Simplex 6. Bosch 7. Gent 8. Cooper 1. Panasonic
Spare Parts / Extra materials
Warranty
Maintenance / Offer for AMC
FAT / SAT
Commissioning
Training / Demonstration
SW
N/A
N/A
N/A
N/A
N/A
SW
N/A
N/A
N/A
Contractor
N/A
SW
N/A
N/A
N/A
Contractor
Contractor
SW+1 year
MRSP
N/A
FAT SAT
FASR
FASR
SW+1 year
MRSP
N/A
FAT SAT
FASR
FASR
SW+1 year
MRSP
FAT Annual maintenance offer SAT (quotation only) up to 5 years
FASR
FASR
SW+1 year
MRSP
FAT Annual maintenance offer SAT (quotation only) up to 5 years
FASR
FASR
SW+1 year
MRSP
N/A
FAT SAT
FASR
FASR
SW+1 year
MRSP
N/A
N/A
FASR
FASR
SW+1 year
MRSP
N/A
N/A
Contractor
Contractor
SW+1 year
MRSP
N/A
N/A
FASR
FASR
SW+1 year
MRSP
N/A
FASR
FASR
N/A
FASR
FASR
N/A
FASR
FASR
Annual maintenance offer (quotation only) up to 5 years SW+1 year
MRSP Annual maintenance offer (quotation only) up to 5 years
SW+1 year
Page : 4 of 5
MRSP
N/A
Date: 01 May 2014
DUBAI PARKS LIST OF RECOMMENDED MANUFACTURERS & STANDARDS FOR MAJOR MEP EQUIPMENTS Discipline
Standards / Specification BS EN 50133
Video surveillance equipment Dubai Police, Meraas Security requirements BS EN 50133
Public Address system / Voice Alarm system DCD, NFPA 72, NFPA 101, NFPA 92A, NFPA 101A UAE fire code, BS 5839
Building management system BS EN 14908, BS EN 15232:2012, Dubai Green building regulation
Recommended Manufacturers 2.Honeywell 3. Johnson control 4. Siemens 5. Bosch 6. IES 1. Panasonic 2. Pelco 3. Baxall 4. Vicon 5. Axis 6. Bosch 7. Siemens 1. Aties 2. Bosch 3. Merlaud 4. Bouyer 5. Panasonic 1. Honeywell 2. Siemens 3. Johnson Controls 4. Invensys 5. Trend
Warranty
Spare Parts / Extra materials
Maintenance / Offer for AMC
FAT / SAT
Commissioning
Training / Demonstration
SW+1 year
MRSP
N/A
N/A
FASR
FASR
SW+1 year
MRSP
N/A
N/A
FASR
FASR
SW+1 year
MRSP
N/A
FASR + 3rd party
FASR
Annual maintenance offer (quotation only) up to 5 years
ICT & COMMUNICATION IT cabling Etisalat, TRA, Meraas ICT requirements BS 6701:2010, TIA/EIA‐568‐C BS EN 50173 ‐ 1 BS EN 50174 ‐ 1/2/3/4 BS EN 50346 / 30310
IP PBX Etisalat, TRA, Meraas ICT requirements
Networking Meraas ICT requirements IEEE 802.x
Servers & Desktops Meraas ICT requirements
Radio TRA, Meraas security requirements
1. Belden 2. 3M 3. AMP 4. Panduit 5. Systimax 6. Corning 7. Commscope 8. Tyco 1. Cisco 2. Avaya 3. Alcatel
20 year
MRSP
N/A
N/A
FASR
FASR
SW+1 year
MRSP
N/A
N/A
FASR
FASR
1. Cisco 2. HP 3. Dlink 4. Brocade
SW+1 year
MRSP
N/A
FASR
FASR
1. HP 2. IBM 3. Dell
SW+2 year
N/A
FASR
FASR
1. Motorola 2. Maxim
SW+1 year
N/A
FASR
FASR
Annual maintenance offer (quotation only) up to 5 years MRSP Annual maintenance offer (quotation only) upto 5 years MRSP
N/A
Legend: SW: FASR: MRSP: FAT/SAT
Standard Warranty 1 Year from Final Handing over date (Warranty shall be from the manufacturer and not from the supplier/local dealer) Engage factory authorised service representative to conduct testing & commissioning and Training to the employer representatives Manufacturer recommended spare parts for 6 months ( Contractor to provide the spare parts for 6 months and a list of Manufacturer's recommended spare parts for 6 months and 1 year) Factory aceeptance Test / Site Acceptance test ‐ Shall be witnessed by client's representatives
Page : 5 of 5
Date: 01 May 2014
View more...